EL26-69-000 · 2026-08-14 · FERC

Letter order granting the NYISO, New York Transmission Owners and Non-Incumbent Transmission Owners abeyance motions

Topics in the text: Filing procedure · Cost allocation · Connecting load and generation

What the document says

Unpaginated filing

Five of six cases go into 90-day abeyance; responses are due November 16.

Therefore, responses to the Show Cause Order will be due on November 16, 2026, and answers to responses will be due on December 16, 2026. Source text

Unpaginated filing

A timely section 205 filing suspends that respondent's duty to answer the show-cause order.

then the obligation of the respondent(s) who have made such an FPA section 205 filing to file a response to the Show Cause Order will be suspended Source text

Unpaginated filing

FERC granted abeyance because each movant described its coming filing and named a filing date.

NYISO, NYTOs, and Non-Incumbent TOs have provided a robust description of the filings they anticipate making, provided a date by which they intend to make such filings Source text

Unpaginated filing

FERC invites each respondent to say which tariff revisions justify ending the show-cause case.

we encourage NYISO and/or Transmission Owners to explain, with specificity, which of their proposed Tariff revisions they believe resolve all or some of the Commission’s preliminary findings in the Show Cause Order Source text

Responses and related views

No section-specific public response is linked for this document.

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Filing procedure

In this order, we grant the Abeyance Motions filed by NYISO, NYTOs, and Non-Incumbent TOs and hold this proceeding in abeyance for 90 days.
Read this passage

Footnotes

Word notes · Topic match: Filing procedure

PP 38, 40. [fn:5] 18 C.F.R. § 385.212 (2025). [fn:6] NYTOs include: Central Hudson Gas & Electric Corporation; Consolidated Edison Company of New York, Inc.; New York State Electric & Gas Corporation; Niagara Mohawk Power Corp.; Orange and Rockland Utilities, Inc.; and Rochester Gas and Electric…
Read this passage