ER27-432-001 · 2026-11-10 · Southwest Power Pool, Inc.
Marked8543-c98d2db8-21b1-4bff-8977-95b41bb9803c.pdf
Back to sections and commentaryPDF page 1
Upper Missouri Zone
Rate Sheet for Point-To-Point Transmission Service
The currently effective rates for Point-To-Point Transmission Service in the Upper
Missouri (“UMZ”) rate zone are set forth in the “UMZ PTP Rate Att T” tab of the Revenue
Requirements and Rates File (“RRR File”) posted on the SPP website. Transmission Owners
that have Commission approved rate(s) in the UMZ rate zone are: Basin Electric Power
Cooperative (“Basin Electric”); Heartland Consumers Power District (“Heartland”); Missouri
River Energy Services (“MRES”); East River Electric Power Cooperative, Inc. (“East River”);
Corn Belt Power Cooperative (“Corn Belt”); NorthWestern Energy Public Service Corporation
(“NWPS”); Northwest Iowa Power Cooperative (“NIPCO”); Harlan Municipal Utilities
(“HMU”); Western Area Power Administration, Upper Great Plains Region (“Western-UGP”);
Central Electric Power Cooperative, Inc. (“Central Power”); Mountrail-Williams Electric
Cooperative (“Mountrail-Williams”); Mor-Gran-Sou Electric Cooperative, Inc. (“Mor-Gran-
Sou”); Roughrider Electric Cooperative, Inc. (“Roughrider”); L and O Power Cooperative
(“LOPC”); and Upper Missouri G. & T. Electric Cooperative, Inc (“UMGT”).
Balanced Portfolio Reallocation Adjustment of Point-To-Point Rates
Rates for Point-To-Point Transmission Service specified in this Attachment T shall be
adjusted to reflect any amount reallocated from the Zonal Annual Transmission Revenue
Requirement in accordance with Section IV.A of Attachment J. The rates, including any
applicable reallocation adjustment, shall be set forth in the RRR File posted on the SPP website.
Point-To-Point Transmission Service and Conditional High Impact Large Load Service
Revenue Crediting for Point-To-Point Rates
Rates for Point-To-Point Transmission Service under this Attachment T shall reflect any
adjustments for Schedules 7, and 8 revenues, 14, Scheduleand 15 revenues, Incremental Market
Efficiency Use revenues, and revenues distributed and allocated under Attachment AU,
implemented in accordance with Section 34.1(2) of this Tariff. The rates, including any
applicable adjustments for Schedules 7 and, 8, 14 revenues, andSchedule 15 revenues,
PDF page 2
Incremental Market Efficiency Use revenues, and revenues distributed and allocated under
Attachment AU, shall be set forth in the RRR File.
Firm Point-To-Point Transmission Service
The Transmission Customer shall compensate the Transmission Provider each month for
Reserved Capacity at the sum of the applicable charges based upon the rates set forth in the RRR
File, calculated pursuant to the formula rates of Basin Electric, Heartland, MRES, MRES
Members (includes Moorhead Public Service; Orange City Municipal Utilities; City of Pierre,
South Dakota; City of Sioux Center, Iowa; Watertown Municipal Utility Department; Denison
Municipal Utilities; and Vermillion Light & Power), East River, Corn Belt, NWPS, NIPCO,
HMU, Western-UGP, Central Power, Mountrail-Williams, Mor-Gran-Sou, Roughrider, LOPC,
and UMGT including any ATRR associated with facility credits provided in the UMZ rate zone,
set forth in Attachment H, Addendums 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 37,
40, 41, 42, 45, 47, 49, and 53 (list appropriate addendums, respectively) of the Tariff, and as
described below:
1.
Yearly delivery: the UMZ Monthly delivery rate multiplied by 12 months.
2.
Monthly delivery: the sum of the Basin Electric, Heartland, MRES, MRES
Members, East River, Corn Belt, NWPS, NIPCO, HMU, Western-UGP,
Central Power, Mountrail-Williams, Mor-Gran-Sou, Roughrider, LOPC,
and UMGT Annual Transmission Revenue Requirements determined
under these entities’ formula rates, including any ATRR associated with
facility credits provided in the UMZ rate zone, divided by the UMZ total
load estimate and divided by 12 months.
3.
Weekly delivery: the UMZ Yearly delivery rate divided by 52.
4.
Daily delivery: the UMZ Weekly delivery rate divided by 7.
Non-Firm Point-To-Point Transmission Service
The Transmission Customer shall compensate the Transmission Provider for Non-Firm
Point-To-Point Transmission Service up to the sum of the applicable charges based upon the
rates set forth in the RRR File, calculated pursuant to the formula rates of Basin Electric,
Heartland, MRES, MRES Members, East River, Corn Belt, NWPS, NIPCO, HMU, Western-
PDF page 3
UGP, Central Power, Mountrail-Williams, Mor-Gran-Sou, Roughrider, LOPC, and UMGT
including any ATRR associated with facility credits provided in the UMZ rate zone, and as
described below:
1.
Monthly delivery: the sum of the Basin Electric, Heartland, MRES, MRES
Members, East River, Corn Belt, NWPS, NIPCO, HMU, Western-UGP,
Central Power, Mountrail-Williams, Mor-Gran-Sou, Roughrider, LOPC,
and UMGT Annual Transmission Revenue Requirements determined
under these entities’ formula rates, including any ATRR associated with
facility credits provided in the UMZ rate zone, divided by the UMZ total
load estimate and divided by 12 months.
2.
Weekly delivery: the UMZ Monthly delivery rate multiplied by 12 and
divided by 52.
3.
Daily delivery: the UMZ Weekly delivery rate divided by 7.
4.
Hourly delivery: the UMZ Monthly delivery rate divided by 730 hours
per month.