ER27-25-000 · 2026-11-09 · MISO
MISO Answer to Comments and Protests on the Large Load Addition Resource Study
Back to sections and commentaryPDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
Midcontinent Independent
)
Docket No. ER27-25-000
System Operator, Inc.
)
MOTION FOR LEAVE TO ANSWER AND ANSWER OF
THE MIDCONTINENT INDEPENDENT SYSTEM
OPERATOR, INC. TO COMMENTS AND PROTESTS
The Midcontinent Independent System Operator, Inc. (“MISO”) submits1 this Motion for
Leave to Answer and Answer to the comments and protests filed in the above-captioned docket.
This proceeding involves a filing made under section 205 of the Federal Power Act (“FPA”)2 to
implement the proposed Large Load Addition Resource Study (“LARS”) process. In Docket No.
ER27-25-000, MISO proposed to amend its Attachment X, Generator Interconnection Procedures
(“GIP”), and Attachment FF to provide a framework for the accelerated study of the addition of
200 MW or greater loads together with new generation resources that are electrically proximate to
those loads.3
MISO seeks leave to respond to the submitted comments and protests due to the importance
of the LARS process in addressing the integration of large loads onto MISO’s Transmission
1
See Rules 212 and 213 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission
(“FERC” or “Commission”), 18 C.F.R. §§ 385.212 and 213 (2026).
2
16 U.S.C. § 824d.
3
See Midcontinent Indep. Sys. Operator, Inc., “Large Load Addition Resource Study Process,” Docket No. ER27-
25-000
(Oct.
2,
2026)
(“LARS
Filing”);
the
GIP
and
Attachment
FF
are
available
at:
https://www.misoenergy.org/legal/rules-manuals-and-agreements/tariff/.
PDF page 2
2
System.4 Also, because a number of commenters misstate the intent and background of LARS,
raise extraneous issues, seek clarifications, and/or propose changes, MISO requests permission to
respond to the intervenors’ arguments to clarify the record and assist the Commission with its
decision-making.
I.
MOTION FOR LEAVE TO FILE ANSWER
Under the Commission’s rules, answers to protests generally are not permitted.5
Nonetheless, the Commission waives this requirement where an otherwise prohibited answer
would clarify the issues under consideration, ensure completeness of the record or assist the
Commission in its decision-making.6 Consistent with this precedent, MISO asks for leave to
submit this Answer to the protests filed in the above-captioned docket7 to provide additional
information related to certain issues raised by the intervenors and assist the Commission in its
decision-making. MISO’s response is particularly warranted given how LARS fits in with MISO’s
broader large load framework. Accordingly, MISO respectfully requests that Rule 213(a)(2)8 be
waived and that the Commission accept this Answer for good cause shown.
4
MISO uses the uncapitalized term “large load” in this answer rather than the “Large Load” term proposed in
MISO’s pending Large Load Interconnection Reliability Requirements filing. This is done to avoid confusion
because that definition remains pending before the Commission and because, given the 200 MW threshold for
entry into LARS, not all “Large Loads” will be eligible to be a “LARS Associated Load.”
5
See 18 C.F.R. § 385.213(a)(2)(2026).
6
See, e.g., Midcontinent Indep. Sys. Operator, Inc., 169 FERC ¶ 61,173, at P 24 (2019) (accepting MISO’s answer
to protests that assisted in the decision-making process); Texas Eastern Transmission, LP, 122 FERC ¶ 61,205,
at P 8 (2008) (accepting answer that completed the record); California Independent System Operator Corp.,
105 FERC ¶ 61,284, at P 10 (2003) (accepting answer that clarified the issues under consideration).
7
There is no prohibition under the Commission’s rules for submitting answers to comments.
8
18 C.F.R. § 385.213(a)(2)(2026).
PDF page 3
3
II.
EXECUTIVE SUMMARY
MISO proposed LARS as part of its response to the Commission’s Show Cause Order,9
and as a standalone procedure that will immediately improve the study process for large loads
looking to connect to MISO’s system and create significant opportunities for lowering the costs of
mitigating the impacts of integrating the largest of large loads onto the MISO Transmission
System. As highlighted in many of the comments filed in this docket, the energy industry is
changing quickly, and many states are experiencing significant new load additions in the near-
term.10 LARS is one of MISO’s proposed solutions to more effectively address this problem. It
is a standalone process that enables the optimization of transmission solutions by allowing MISO
to study both the large load and the generation that will serve it at the same time, promoting process
efficiency, cost responsibility, and affordability. The tool offers a vast improvement over the status
quo leveraging available efficiencies in other MISO processes.
MISO appreciates the opportunity to respond to the protests and comments in support it
received in response to its LARS filing. In particular, MISO appreciates the opportunity to clarify
misconceptions and concerns surrounding cost impacts. LARS, in fact, provides an opportunity
to better mitigate cost impacts of new Large Load integration over the status quo for LSEs that
choose to leverage the tool. While LARS was well-received by a wide variety of stakeholders,
9
Midcontinent Independent System Operator, Inc., Order Instituting Proceeding Under Section 206 of the Federal
Power Act, 195 FERC ¶ 61,212 (2026) (“Show Cause Order” or “SCO”).
10 All LARS Comment citations in this Answer are from Midcontinent Indep. Sys. Operator, Inc., “Large Load
Addition Resource Study Process,” Docket No. ER27-25-000 (Oct. 2, 2026). See Data Center Coalition LARS
Comments at 2-3; NIPSCO LARS Comments at 2-4; MISO Transmission Owners LARS Comments at 6-9;
Entergy and Cleco LARS Comments at 10-11; Mississippi Public Service Commission and the Louisiana Public
Service Commission (the “Southern Regulators”) LARS Comments at 1-2; and Alliant Energy Corporation and
Consumers Energy LARS Comments at 15-16.
PDF page 4
4
there are certain aspects of the LARS process that warrant additional explanation given the
comments received.
LARS Responds to the Commission’s Show Cause Order
First and foremost, LARS responds to several of the concerns raised in the Commission’s
Show Cause Order.11 LARS addresses the Commission’s concern regarding the speed at which
large loads are seeking to interconnect,12 by enabling the generation associated with the most
resource intensive (i.e., the largest) large loads to be aligned and studied on a similar timeline to
that currently experienced for Expedited Project Reviews (“EPRs”) of local transmission projects
associated with large load additions. LARS also enables the potentially-significant cost saving
efficiencies that the Show Cause Order sought for electrically proximate large loads and associated
generation by allowing for a more complete picture of the localized Transmission System and the
identification of an optimized set of Network Upgrades to address the impacts of both the load and
the generation, creating opportunities for more efficient, and potentially less costly Network
Upgrades that could be identified in the separate load and generation studies that occur today.13
LARS Helps Mitigate Cost Shifting, Supports Cost Causation Principles, and Addresses
Urgent Needs Now Without Prejudicing Subsequent Large Load Reforms
Second, MISO recognizes the importance of developing a cost allocation framework that
will prevent cost shifting and align with the Commission’s cost causation principles. As MISO
explained in its transmittal letter, aspects of the broader cost allocation framework for large loads
11 Show Cause Order at P 113.
12 Show Cause Order at P 120 (expressing concern that “the relative speed and concentration at which large loads
are seeking to interconnect appears to be outpacing the addition of new generation, which in turn heightens
reliability risks and drives up costs to ratepayers.”).
13 Show Cause Order at P 106-109.
PDF page 5
5
and implementing agreements are still being developed by MISO, the Transmission Owners, and
other stakeholders but will ultimately be part of MISO’s response to the Show Cause Order to be
filed on November 16. MISO has committed to incorporating the large load reforms being
developed in response to the Show Cause Order with LARS as they become accepted by the
Commission.14 Even without these, the LARS proposal includes a Tariff mechanism for
identifying and assigning any necessary transmission Network Upgrades associated with the
generation/load pair to the Transmission Customer or the Interconnection Customer.
MISO understands the desire of some protestors to delay LARS until all of MISO’s
proposed large load reforms can be considered together. However, such a delay would frustrate
the goals of the Show Cause Order and needlessly sacrifice the benefits of critical reforms for
ratepayers and stakeholders without corresponding benefit. Acceptance by the requested effective
date is needed to give MISO and its stakeholders the time to establish internal processes and
implement LARS by the first quarter of 2027. Rejecting or delaying LARS implementation will
not slow down the pace of Large Load integration. MISO has processed more than 32,734 MW
of large load additions through its EPR process anticipates that it will be required to process
anywhere from an additional 5,000 MW to 15,000 MW in Q1 of 2027. If LARS is not available,
the result would not be that large load studies will stop until all elements of Large Load reform
have been accepted by the Commission. Rather, large loads will continue to be studied through
the EPR process, which does not allow MISO to identify optimized transmission solutions or
utilize a non-GIA generator as a mitigation option. The cost, timing, and efficiency benefits of
14 Many of these additional elements will become applicable to LARS automatically because all loads included in
LARS are “Large Loads” and thus requirements applicable to Large Loads such as the transparency dashboard,
will apply. Where reconciliation of Tariff versions is required in order to apply forthcoming reforms to LARS,
MISO has committed to make such filings promptly. See, LARS Transmittal Letter at n 66.
PDF page 6
6
LARS should not be delayed pending the approval of other reforms, especially since MISO has
committed to integrating those reforms into LARS upon their acceptance.
LARS Does Not Adversely Impact Projects in the Existing Interconnection Queue
Third, MISO has structured the LARS process to not harm projects in the existing
generation interconnection queue. LARS projects are not displacing current projects in the
Definitive Planning Phase (“DPP”) queue and claims that LARS projects will take the transmission
headroom capacity of projects in future queue cycles are speculative. LARS projects will identify
optimized transmission solutions that could ultimately create more headroom on the transmission
system with their potentially larger Network Upgrades, and any LARS projects and their
associated upgrades may be used to help alleviate constraints observed in queue cycle studies.
Moreover, maintaining LARS as a process separate from the DPP better insulates Interconnection
Customers from bearing the cost of Network Upgrades needed to accommodate generation serving
a LARS Associated Load.
LARS Is Appropriately Scoped to Address the Unique Challenges and Opportunities
Associated with the Largest Large Loads and Generation Pairs
Fourth, the LARS Application and strict eligibility requirements are designed to ensure
that only genuinely shovel-ready generation-and-load pairs participate in LARS. MISO structured
LARS to permit participation by all developers and resource types. The process requires
Transmission Customers to collaborate with other parties before submitting a LARS Application.
Rather than making Transmission Customers (commonly LSEs) gatekeepers of the LARS process,
this requirement recognizes the essential role Transmission Customers play in integrating large
loads onto the grid. Limiting loads to a minimum of 200 MW and requiring commercial
agreements will act as a natural barrier to speculative projects and will result in only truly
PDF page 7
7
committed generation and load pairs applying. Following MISO’s experience with loads
participating in its EPR process, MISO’s 200 MW threshold for large loads participating in LARS
is reasonable and will serve to ensure that LARS is only used by the largest load participants,
which enables MISO to identify optimized transmission solutions. MISO does not believe that
implementing a sunset on LARS is appropriate at this juncture but is committed to reviewing the
process on a regular basis to determine whether there continues to be sufficient demand for it.
LARS Meets the Independent Entity Variation Standard; It is An Innovative Solution
Tailored to Specific Needs and is Consistent with the Goals of Commission Orders.
Finally, MISO has met the standard for independent entity variation as serial studies of the
generation side of LARS projects are necessary to facilitate the quick addition of these projects to
the grid and LARS will not change DPP rules. LARS is limited in scope both by its strict eligibility
requirements and because only thirty generation and load pairs may be studied each year. Thus,
the LARS proposal meets the goals of Order Nos. 2003 and 2023 by expediting the development
of new generation, while protecting reliability and ensuring that rates are just and reasonable,15 as
well as by establishing strict eligibility requirements to meet readiness principles of the Orders and
ensuring only truly commercially viable projects participate.16
III.
ANSWER
Twenty-one entities filed substantive Protests or Comments in response to the LARS filing.
Of that number, ten parties supported LARS, recognizing and confirming the need to act
expeditiously to address the dramatic growth in large load development. Many of these supporters
recognize in their comments that LARS provides a path to avoid studying large loads and
15 Order No. 2003 at 11.
16 Order No. 2023 at 454-455.
PDF page 8
8
associated generation through separate processes on different schedules and would produce a more
realistic picture of the grid, which could create opportunities for MISO to potentially optimize
Network Upgrades.17 The commenters recognized that pairing large loads with generation to
support them is one way to reduce the need for significant transmission upgrades that may be
needed if only the generation or load were interconnecting to MISO’s system.18 Eleven parties
submitted either protests or requests for clarification on certain details of the LARS proposal.
In this answer, MISO seeks to clarify certain aspects of the LARS proposal including that:
(1) it is responsive to the concerns underlying Commission’s electrically proximate arrangements
discussion described in the Show Cause Order; (2) it provides an effective vehicle to help support
resource adequacy in the face of impending Large Load additions; (3) it provides an efficient and
reasonable parallel study process that will address urgent needs now while will also working with
MISO’s forthcoming Large Load reforms; (4) it will help address affordability and identify
optimized transmission solutions; (5) it will not negatively impact projects in the existing
interconnection queue; (6) its eligibility requirements are appropriate and will limit the number of
applicants to those that are commercially ready; and (7) it is consistent with the goals of the Show
Cause Order and Commission principles established in other relevant Commission Orders.
MISO’s LARS proposal is just and reasonable and not unduly discriminatory. As such, MISO
17 Consumers Energy and Alliant LARS Comments at 2; Data Center Coalition LARS Comments at 4; DTE
LARS Comments at 2; Electricity Customer Alliance (“ECA”) LARS Comments at 1.
18 Entergy and Cleco LARS Comments at 2.
PDF page 9
9
respectfully asks that the Commission accept its proposal to enable MISO to implement this
needed study process by the first quarter of 2027.
A.
LARS is Responsive to the Commission’s Show Cause Order
The Electrically Proximate Requirement
Many of the protesters suggested that how MISO defined “electrically proximate” is not
responsive to the Commission’s Show Cause Order.19 The protesters emphasize that the
Commission defined “electrically proximate” as a “large load that is located no more than two
substations away from the generating facility.”20 The protestors argued that MISO’s proposal of
allowing the generation and load pair to be located in the same Local Resource Zone (“LRZ”) to
meet the electrically proximate requirement fails to meet the Commission’s expectations.21 But
the Commission expressly stated that it would “consider proposed revisions to this definition that
ensure it is appropriately tailored to MISO’s transmission system.”22 MISO is expanding upon the
Commission’s definition to fit its needs and resource adequacy construct. LARS does not limit
the electrical or physical distance between the load and generator within the same LRZ to provide
maximum flexibility for the generation/load pairs. MISO determined that requiring the generation
and load to be located within the same LRZ enabled flexibility while still allowing it to identify
optimized Network Upgrade solutions. In developing LARS, MISO concluded that defining a
maximum distance based on substations would impede the flexibility of large loads and
19 Clean Energy Trades LARS Comments at 18; the Community Organizations and Clean Energy Advocates (the
“Advocates”) LARS Comments at 37-38; Consumer Advocates LARS Comments at 9; OMS LARS Comments
at 8; and the Southern Minnesota Municipal Power Agency and WPPI Energy (the “Midwest TDUs”) LARS
Comments at 5-6.
20 Show Cause Order at P 112.
21 MISO clarifies that both the large load’s point of withdrawal (“POW”) and the generator’s point of
interconnection (“POI”) as well as the facilities must be located in the same LRZ.
22 Show Cause Order at P 112.
PDF page 10
10
Interconnection Customers to site their projects in a way that made the most sense for the parties.
Moreover, in the context of MISO’s Transmission System, such a limit would be arbitrary. MISO
notes that depending on a transmission line’s voltage level, two substations could still be hundreds
of miles apart and does not necessarily result in generation and load being geographically near
each other.23 On other parts of MISO’s Transmission System, several substations can be fairly
close together such that a geographically proximate Generating Facility and large load may have
very limited options for interconnection.
Under the LARS construct, there is no requirement that the Generating Facility limit its
output in real time to fluctuations in the demand of the large load.24 This is not the mechanism
LARS uses to create value and potential savings. Thus, a bus or other electrical distance limit is
not a necessary component of the LARS construct. The opportunities for lowering the Network
Upgrade costs of interconnecting and providing generation to the large load come from the LARS
process’s ability to include generation that does not yet have a Generation Interconnection
Agreement (“GIA”) in the load study and to model the proposed large load in the generation study.
LARS enables this to be done with confidence because LARS places requirements on both the
LARS Associated Transmission Customer and the Interconnection Customer that are not otherwise
required of loads and generators that greatly reduce both the opportunities for speculative
23 MISO, Transferred Transmission Facilities, available at: https://www.misoenergy.org/legal/transferred-
transmission-facilities/#t=10&p=0&s=FileName&sd=asc. See for example, ITC Midwest: Lehigh to Raun
345kV 116 miles, available at:
https://cdn.misoenergy.org/ITC%20Midwest%20Transmission%20Owner%20Transferred%20Facilities%2020
26390628.xlsx; ATC: Briggs Road to North Madison 345kV 161 miles, available at:
https://cdn.misoenergy.org/American%20Transmission%20Company%20Transferred%20Facilities%20202639
0603.xls; ALLETE MP/MHEB: Iron Range to Dorsey 500kV 357 miles (224 to the border), available at:
https://cdn.misoenergy.org/ALLETE%20MP%20SWLPC%20Transferred%20Facilities%202026390599.xlsx.
24 MISO has proposed a process to accommodate such arrangements, through its ZG Interconnection Service
process, which currently is pending before the Commission in Docket No. ER26-3552-000. LARS does not seek
to duplicate ZG Interconnection Service but instead provide a different tool for different situations.
PDF page 11
11
submissions and the potential for cost shifts due to the load or generation not being built.25 With
both the load and Generating Facility accounted for in the same study process, their impacts at
peak operation (i.e. maximum injection of the Generating Facility and full amount of Transmission
Service requested for the large load) can be accounted for in the modeling stage, thereby avoiding
the potential for requiring Network Upgrades in one study that are more expensive or different
from what would be identified if both were studied in isolation. This delivers the value of
optimized Network Upgrades but using a different, innovative approach, one which is tailored to
the needs of the MISO region and the other MISO processes.
While some protestors complain that a Local Resource Zone is too large to address the
Commission’s “electrically proximate” discussion, none have provided evidence to suggest that
MISO’s LRZ-based requirements will not allow for a more optimized set of Network Upgrades
than is possible to identify under current processes. Nor do protestors recognize that that, while
adjacent large loads and Generating Facilities may produce the most significant Network Upgrade
optimization, limiting LARS on that basis would—in aggregate leave the efficiency and cost
savings LARS promises by making it unusable in the many situations where it could still produce
a more optimized set of Network Upgrades. In this respect, MISO also notes that LARS is limited
to large loads and Generating Facilities that seek at least 200 MW of Transmission Service and
200 MW of Interconnection Service respectively. Given this scale, the potential efficiency and
cost savings for Network Upgrade optimization may easily span an LRZ.
25 It is highly unlikely that a Transmission Customer and Interconnection Customer would choose to enter LARS if
they did not have a high degree of commitment to each other’s projects being built. And if one does not
materialize, new service or a new study reflecting the impact of only the facility proposed to remain is required
for the Generating Facility or Large load to maintain their service, thus avoiding cost shift risks.
PDF page 12
12
Moreover, while LARS sets the outer boundaries at the borders of a Local Resource Zone,
it nonetheless creates a strong incentive for the LARS Associated Generating Facilities and LARS
Associated Load to site as close together as is practical in order to maximize potential Network
Upgrade cost savings of a common set of Network Upgrades. MISO’s LRZ approach thus can be
considered an “electrically proximate plus” construct because it provides benefits both to those
large load and Generating Facility pairs that can site next to each other while also providing
benefits to those further apart. It should not be objectionable that LARS provides efficiency
benefits in more situations than the smaller subset contemplated by the Show Cause Order.
Finally, allowing Generating Facilities participating in LARS to interconnect at multiple
POIs furthers the “electrically proximate plus” benefits of LARS. This provides Interconnection
Customers with the necessary flexibility to serve extremely large loads and in way that MISO can
optimize any necessary transmission solutions. As Ms. Drake explained in her testimony,
“[u]ltimately, limiting the generation and LARS Associated Load to locations within the same
LRZ ensures deliverability of the generation to the LARS Associated Load because it avoids
potential capacity import / capacity export limitations for the individual LRZ and also avoids price
separation between the paired generation and LARS Associated Load.”26 MISO therefore
correctly determined that the LRZ was the appropriate limitation on electrically proximate
generation and load pairs as adequately fitting within its current construct and providing maximum
flexibility for participants.
26 Drake LARS Testimony at 40-41.
PDF page 13
13
LARS Heeds the Call for Speed to Power and Supports Resource
Adequacy
The immensity and rate of large load additions across the United States is requiring unique
proposals. While MISO had already considered creating a process to study load with generation
at the same time, the Commission’s Show Cause Order underscored the need to establish the study
process sooner rather than later. LARS advances that objective within the MISO region by
providing a process through which significant new large loads and generation intended to support
that load can be studied on an accelerated and coordinated basis. LARS is another complementary
tool that harmonizes with MISO’s large load framework including its recently proposed ZGIA
process for co-located load. Each of the proposed processes seek to address different challenges
posed by large load growth and LARS provides a pathway for paired load and generation to be
studied and commence service together.
The Commission recognized in its Show Cause Order that “the relative speed and
concentration at which large loads are seeking to interconnect appears to be outpacing the addition
of new generation, which in turn heightens reliability risks and drives up costs to ratepayers” and
stated it was “concerned that MISO and load serving entities are unable to plan adequate generation
to serve all load at the pace such load seeks to connect.”27 MISO developed LARS in the context
of this dramatic large load growth and is proposing the LARS process to help address that growth.
The strict entry requirements for LARS both support its intended benefits and underscore that
LARS is not, and should not be, a replacement for the DPP.28 Rather, it is intended to be a narrowly
scoped but powerful process. LARS speeds up the interconnection process for a select number
and kind of project where the large load has formally partnered with generation for a period of 15
27 Show Cause Order at P 120.
28 See id. at 12.
PDF page 14
14
years. LARS will provide a path for the interconnection of both large loads and supporting
generation pairs in a parallel 120-day study process. This will enable MISO to optimize
transmission solutions for these pairs when studying their impacts at the same time.
B. Large Load Cost Allocation Framework
Several protesters oppose LARS because it fails to address the cost-shifting concerns and
lacks transparency on costs.29 First, LARS does not create any new cost shift opportunities, but
LARS does mitigate risks that already exist. Further, as explained in the transmittal letter, MISO
continues to work with stakeholders to develop pro forma cost recovery agreements as part of its
Large Load Project Review (“LLPR”) process, which will be proposed as part of MISO’s response
to the Commission’s Show Cause Order. MISO also will address transparency for Large Load-
driven Network Upgrade costs. This work is important and MISO has committed to integrating
LARS with its other large load reforms as they are accepted by the Commission and become
available for use. However, MISO disagrees that the LARS is incomplete or should not be
accepted unless and until LLPR and its related reforms have been accepted by the Commission.
LARS significantly improves upon current processes available to study large loads. With
respect to cost responsibility, accountability, and cost shifting, the LARS filing includes Tariff
language stating:
Once MTEP approval occurs for the LARS Associated Load, the LARS Associated
Transmission Customer remains responsible for the identified BRPs and Other
assigned projects even if such LARS Associated Load does not commence service
or commences service for less than the total amount of the LARS Associated
Load….30
29 Anna Farrar LARS Comments at 3; the Advocates LARS Comments at 13; Consumer Advocates LARS
Comments at 6; OMS LARS Comments at 5; and Google LAR Comments at 3.
30 See Tariff Sheets included with LARS Filing at Attachment FF, proposed section I.D.1.b.ii.g.
PDF page 15
15
This language clearly associates the non-GIP local Transmission Facilities needed to accommodate
Transmission Service for a large load undergoing the LARS study process with the LARS
Associated Transmission Customer and assigns the cost of these facilities to the LARS Associated
Transmission Customer even if the large load is ultimately not built. MISO and the MISO
Transmission Owners will include in their Large Load filing(s) due on November 16, 2026, the
pro forma cost recovery agreements that provide an enforcement mechanism for the obligations
of Transmission Customers seeking Transmission Service to serve Large Loads. MISO also has
committed to integrate the Large Load reforms into the LARS process through an appropriate
filing once those reforms are accepted, and MISO is willing to accept a compliance directive
requiring such a filing should the Commission deem this necessary. However, MISO cannot
predict how long it will take for these further reforms to be accepted by the Commission and
become effective. What MISO can predict is that large loads will continue to move forward and
require expedited study of Network Upgrades to interconnect them. Delaying or denying LARS
will not address the concerns raised by protests. Rather, it will simply mean that MISO will be
required to use current processes, such as EPR, to study these large loads.
LARS significantly improves upon current study processes, addresses numerous concerns
expressed in the Show Cause Order, and can be applied to the next group of large load integrations
even if other reforms are not yet accepted. MISO does not claim that LARS is a panacea or that it
will obviate the need for forthcoming additional reforms such as pro forma agreements and
transparency mechanisms. But the fact that all reforms may not be available when LARS
PDF page 16
16
commences would be a poor reason to deny the MISO footprint the clear benefits that LARS can
provide for processing large loads and their associated generation integrations in the near term.
LARS is not creating a new cost-allocation problem. MISO has historically applied
distribution factor (“DFAX”) thresholds for cost assignment of GIPs. In situations where a
generator has an impact but is below the DFAX threshold, the cumulative impact of all
Interconnection Requests may create a transmission need that must be resolved in MTEP or a
future DPP cycle. LARS is no different.
The EPR process was historically facilitated by MISO to study projects out of the regular
MTEP cycle when there was an urgent system need that would be jeopardized unless an expedited
system impact study was conducted.31 EPRs allow for the incremental addition of transmission
and load to the electric grid. The recent and dramatic acceleration of these EPR submittals drives
the need for more generation to meet that increased spot load growth. An example of this is
demonstrated in the figure below, which shows that individual EPR requests continue to increase
in load size and transmission investment.32
31 MISO, MTEP25 Report 36 at 6(2025), https://cdn.misoenergy.org/MTEP25%20Report731648.pdf (“MISO
MTEP 25 Report”) (“MISO has worked with stakeholders to refine the Expedited Project Review (EPR) process
to advance urgent transmission projects outside the standard MTEP cycle — with the increased use of this process
being a good indication of how quickly system needs are emerging.”).
32 MISO, EPR Statistic Update, Expedited Project Review Technical Studies Task Force (EPR-TSTF), Slide 9,
Nov. 3, 2026, available at: https://cdn.misoenergy.org/20261103%20EPR-
TSTF%20Item%2003%20MISO%20EPR%20Statistics UPDATED792865.pdf? t id=5OVCdhOREsRw7Ezo
Ar-xAA%3d%3d& t uuid=Toha-
s9SSzWtdq2zatRW5g&_t_q=EPR&_t_tags=language%3aen%2csiteid%3a11c11b3a-39b8-4096-a233-
c7daca09d9bf%2candquerymatch&_t_hit.id=Optics_Models_Find_RemoteHostedContentItem/792865&_t_hit.
pos=4.
PDF page 17
17
This EPR data supports MISO’s assertion that load growth is increasing dramatically in the MISO
footprint and will likely continue to do so in 2027 and beyond. Moreover, based on internal
analysis, with this increase in EPR submittals, MISO has also seen an increase in the average
Network Upgrade cost in 2026.33 As the load margins grow tighter, larger investments are needed
to mitigate constraints as MISO is relying on more generation transfers to cover the load.
LARS is one component of MISO’s answer to this problem. And it is needed urgently. By
enabling large loads (≥200 MW) to pair with generation, MISO can study the pair in the LARS
process and potentially identify optimized transmission solutions. The EPR process only studies
load and cannot incorporate a generator as a potential mitigation solution unless it has a GIA,
which can delay getting the load interconnected as it is waiting for generation to be studied and
completed. LARS improves upon this status quo, provides speed to power for the largest of large
33 Fifty-six Load Requests were approved as part of MTEP26 with an average cost of $145,000,000 per project. For
large loads greater than 200 MW, the average cost was $201,000,000.
PDF page 18
18
loads, and significantly decreases the opportunities for cost shifting even while other reforms
remain pending.
LARS is a solid building block in MISO’s large load framework and can be implemented
independently from the forthcoming LLPR filing. The LARS process does not create new
opportunities for cost shifting and, even without the LLPR process, imposes more accountability
on the Transmission Customer than MISO’s current processes do. Finally, there is nothing in the
LARS proposal that would prevent a state regulator from allocating costs of a BRP or Other project
more granularly to a specific retail customer.34
C. LARS Will Not Harm the Existing Queue
MISO understands that many stakeholders are concerned that LARS projects will take
available transmission capacity or headroom from other projects currently in the DPP queue.35
The argument is that since LARS and DPP interconnection customers are vying for the same
capacity, adding LARS projects to the transmission system before DPP projects will necessarily
reduce the transmission headroom available for DPP projects.36 The assertion is that because
LARS projects will be studied first, they will have priority on MTEP upgrades that could have
otherwise been utilized to mitigate constraints for a previously queued DPP project that is subject
to a longer study process.37
34 Nor does LARS intrude on the authority of RERRAs to establish rules and policies for their Load Serving Entities.
35 See Advanced Energy United and Solar Energy Industries Association (“SEIA”) at 10; the American Clean Power
Association and the Southern Renewable Energy Association (“Clean Energy Trades”) at 15; Ms. Farrar at 2; the
Advocates at 19; and the Consumer Advocates at 11.
36 See Clean Energy Trades at 20 (“LARS projects would gain priority access to transmission capacity and avoid
Network Upgrades they would otherwise trigger, shifting costs to DPP customers and other transmission
customers.”).
37 See id.
PDF page 19
19
MISO has taken numerous steps to protect current DPP queue projects from losing
available transmission capacity. First, each LARS study cycle model will be built based on the
existing MTEP model, which would not remove any available headroom from active DPP queue
projects using previous MTEP models.38 All approved projects which have gone through the
MTEP, EPR, ERAS, or DPP processes are included in the base LARS model. All load studies
follow the same concepts outlined in MTEP but in a more expedited manner. Second, MISO
already has several processes in place to address these kinds of situations. MISO’s Business
Practice Manual 015 for generation interconnection states that in order to mitigate a constraint,
MISO will check the MTEP appendices and discuss the issue with the impacted transmission
owners to determine if there already exists a planned project that will alleviate the constraint.39
The base case for each DPP cycle is not updated once the study process starts except for generation
changes due to withdrawals or generator retirements. This will ensure that the transmission
capacity that is available for DPP projects is not being taken away by LARS projects approved
outside of the DPP cycle.40
Several commenters also implied that LARS projects will result in higher network upgrade
costs for DPP projects, but there is no evidentiary support for this assertion and the proposed LARS
tariff redlines require LARS participants to pay all Network Upgrade costs associated with their
proposed project even if they end up withdrawing it. Moreover, any LARS projects and their
38 See Drake LARS Testimony at 32-33.
39 BPM
15,
Section
6.1.1.1.
MISO’s
Business
Practices
Manuals
can
be
found
at:
https://www.misoenergy.org/legal/rules-manuals-and-agreements/business-practice-manuals/.
40 To the extent that protestors’ argument is that hypothetical future Interconnection Customers may see diminished
Transmission headroom as a result of MISO adopting the LARS process, such an argument would be entirely
speculative. LARS Applicants will pay for the Network Upgrades their projects require and, like other customers,
may create headroom or use it.
PDF page 20
20
associated Network Upgrades approved as part of the LARS process can be used to mitigate
constraints in DPP cycles, which may also benefit DPP projects.41
D. LARS Application and Eligibility Requirements
i. LARS is Not Preferential to LSEs.
A common complaint among protestors was that LARS enables Load Serving Entities
(“LSEs”) to gatekeep who can participate in the process.42 MISO disagrees with this assessment
for several reasons. First, under MISO’s current processes, only Transmission Owners may submit
EPR requests – Interconnection Customers have never been allowed to submit these kinds of
requests to MISO. LARS does not change this dynamic. LARS is a load-driven process, and an
Interconnection Customer cannot require a Transmission Customer to scope their Transmission
Service request around a generator they have not chosen to pair with. Thus, it is logical to require
the Transmission Customer to act as the applicant. To the extent that an Interconnection Customer
has developed an agreement to work together with a Transmission Customer, the requirement that
the Transmission Customer initiate the application provides no barrier to participation. If no such
agreement exists, then the pairing of load and generation in a coordinated study process would be
premature and speculative. LARS does not prevent Independent Power Producers (“IPPs”) from
competing to supply energy to large loads under applicable state and or utility-led RFP processes.
However, for an accelerated study process to have the level of certainty needed to function, the
pairing must be established prior to submitting a LARS Application. LARS takes generation and
Transmission Customer pairings as it finds them. It is not intended as an avenue for exploring
41 See Clean Energy Trades LARS Comments at 20; the Advocates LARS Comments at 18-19; and OMS LARS
Comments at 4.
42 See Clean Energy Trades at 6; the Advocates at 12; Geronimo Power at 5-6; and Google at 9.
PDF page 21
21
commercial relationships that do not yet exist, and this is not required for the proposal to be just,
reasonable, and nondiscretionary.
Second, while LARS is not intended to change well-established roles and responsibilities
for who can submit projects needed to facilitate new load into MTEP, MISO has carefully
developed LARS so as to not impede commercial relationships between Interconnection
Customers and Transmission Customers. Specifically, LARS allows arrangements involving
Interconnection Customers that are separate entities from the Transmission Customer and provides
that the Interconnection Customer—and not the LARS Transmission Customer—will receive the
LLGIA awarding Interconnection Service to LARS Associated Generating Facility and make
decisions regarding the generator interconnection portion of the LARS Study. In other words,
LARS simply recognizes the entities currently allowed to seek transmission service from MISO,
and then adds a participation framework to ensure that any Interconnection Customers that pair
with the Transmission Customer can participate in LARS and receive an LLGIA.
Several commenters also pointed to SPP’s HILLGA process as a model that MISO should
emulate with LARS.43 HILLGA is a generator-driven process, while LARS is emphasizing the
paired generation and load. The LARS Application requires both sides of the pair to participate
and provide information for the application. LARS also has stricter site control requirements such
that the Transmission Owner must agree on the POI at the time of application submission. MISO
structured LARS so that it would only encourage truly shovel-ready, commercial projects where
the relevant parties had already reached agreement before applying. MISO does not believe the
LARS process will work for all projects – it was not designed to – but it will work for generation
43 See Advanced Energy United and SEIA LARS Comments at 9; Clean Energy Trades LARS Comments at 17;
and Geronimo Power LARS Comments at 10.
PDF page 22
22
and load pairs that have reached an agreement before applying to participate in LARS. This kind
of certainty and information will enable MISO to complete these parallel studies on an expedited
basis and will assist MISO with identifying any optimized transmission solutions.
The LARS proposal in no way limits who can bring a proposed generation project to a
Transmission Customer seeking Transmission Service on behalf of a Large Load that. All of this
occurs prior to LARS. If an IPP has a generation project that is better, more cost effective, or
otherwise preferable to alternatives, nothing in the LARS process stops the IPP from bringing this
project forward for consideration and entering into a pairing arrangement with a LARS
Transmission Customer. To the extent an IPP believes it is disadvantaged in such competition,
that is not a result of any feature of the LARS proposal.
While several commenters also urged the Commission to sunset the LARS process after a
certain period of time, MISO does not support an arbitrary end date for LARS and believes that
allowing more time will help IPPs participate in the process.44 MISO’s internal forecast indicates
that large loads will continue to grow in coming years. MISO’s own recent experience with its
EPR process demonstrates the dramatic increase in large load development. MISO does not want
to propose an arbitrary end date on a beneficial study process that will help MISO identify
optimized transmission solutions. Moreover, IPPs and other market participants will have more
time to collaborate with Transmission Customers and LSEs when proposing potential
generation/load pairs. MISO is not opposed to regularly reviewing LARS usage patterns to
consider whether changes are needed but does not believe that a specific sunset date is appropriate.
44 Clean Energy Trades LARS Comments at 17; and OMS LARS Comments at 10.
PDF page 23
23
Finally, the structural design of LARS will systematically limit the number of projects that can be
studied in it given the size and certainty requirements.
To facilitate this transparency, MISO commits to publicly post, at the beginning of each
LARS cycle, information on each LARS generation/load pair’s POI and POW, the MW values for
large load and the generator, the project’s LRZ location, and the number of LARS Applications
received. This is an importance piece of MISO’s commitment to transparency as part of the
integration of large loads onto the Transmission System. Since LARS is proposed for such a
unique and small group of projects, there is no need to place an arbitrary sunset on the study
process.45
ii. The 200 MW Large Load Size Threshold is Necessary for Optimization
Over the past several years, MISO has gained experience with large loads through its EPR
process. Through this experience, MISO has seen loads that are greater than 200 MW having a
more significant impact on the Transmission System than smaller projects. MISO developed
LARS for a select group of large loads that will have a sizeable impact on the system and that have
formally paired with generation. MISO’s design of LARS utilizes a more holistic study process
for only the largest loads to try to optimize the best solution for the system. MISO plans to keep
the current EPR process available for smaller load sizes of less than 50 MW or existing loads that
are adding less than 25 MW and that still require faster processing than the traditional MTEP
process. Moreover, in its November 16 filing, MISO will be proposing its LLPR process to study
Large Loads greater than 50 MW that are not paired with a generator. LARS is a study process
for large loads that are at least 200 MW and that have formally paired with a generator. MISO has
45 MISO has always intended to provide this information as part of its broader commitment to transparency and
expressly commits to making such public posting. While MISO does not believe that a compliance directive
requiring MISO to reflect this commitment in the Tariff is needed, MISO would not object to such a directive if
the Commission believes it is necessary.
PDF page 24
24
developed these different study processes for diverse load sizes to increase the efficiency of the
studies and identify the best mitigation solutions.
The parallel study process supplied by LARS is especially important for these very large
load sizes. Optimized transmission solutions are the most impactful with very large loads. For
example, if there is an extremely large data center being served by multiple generating facilities
then it is likely that the associated Network Upgrades will be much larger, and the best opportunity
for minimizing the cost of these Network Upgrades is studying the load and generation together.
LARS is not aiming to replace other study processes at MISO but rather to ensure that the best
study process for realizing cost efficiencies is utilized for the largest of loads. This is another
reason why it is key that the Commission approve the LARS process expeditiously. In the context
of the forecasted large load growth that MISO is facing in the near-term, it is critical that LARS is
approved as soon as possible.
iii.
The 15-Year Pairing Commitment is Necessary for Certainty
The 15-year minimum pairing of the generation and load pairs in LARS is a necessary
aspect of ensuring certainty for MISO and ensuring that LARS is not used as a queue-jumping
process by Interconnection Customers. MISO seeks to prevent either the generator or the load
from using LARS to connect quickly and then operate without their partner. Requiring a 15-year
minimum commitment is a key part of ensuring that pairing is a formal, long-term commitment.
MISO envisions that LARS pairs will perform concurrently even though MISO is not requiring a
generating facility’s output to be matched to the demand of the electrically proximate large load.
This is another requirement that will reduce speculative generation or load proposals that are not
ready to connect to MISO’s transmission system. Requiring this commitment to remain in place
for a 15-year period is a balanced approach that ensures the pairings remain in place for a long
PDF page 25
25
enough period of time and that discourages overuse of the process without foreclosing changes in
the remote future that would create challenges to attracting project investment/financing.
Thus, arguments that LARS is flawed because it requires more commitment and
commercial certainty than most projects entering the queue can provide entirely miss the point of
what LARS is—and is not—intended to do. The agreement requirement is flexible enough for
projects with commercial certainty to participate in LARS, regardless of the type of entity that is
developing them. And the agreement requirement should not be made more flexible to allow in
projects that do not meet the high hurdle that LARS is designed to maintain. LARS is not a broad
queue replacement proposal and does not detract from the ability of ordinary generation or load
projects to enter the DPP queue or EPR process (or to be submitted in the LLPR process) on the
same basis as they have before LARS was proposed. MISO is simply requiring that the LARS
generator and the LARS Associated Load remain committed for a significant amount of time to
ensure certainty and as a way to avoid the circumvention of the DPP process.
E. MISO Has Met the Standard for an Independent Entity Variation
i. LARS accomplishes the purposes of Order Nos. 2003 and 2023
MISO is requesting an independent entity variation for LARS, which is a unique process
that will involve a much smaller number of proposed projects that will be studied each year when
compared to the traditional DPP queue. Consistent with Order Nos. 2003 and 2023, MISO may
seek variations from the pro forma Large Generator Interconnection Procedures (“LGIP”) and
Large Generator Interconnection Agreement (“LGIA”) if those variations “are just, reasonable,
PDF page 26
26
not unduly discriminatory or preferential, and accomplish the purpose of” the terms proposed in
Order Nos. 2003 and Order 2023.46
Because LARS is a standalone process, it should be viewed as one large independent entity
variation with a defined rule set rather than individual independent entity variations for the
numerous differences between the cluster-based process outlined in Order 2023-2023-A and
LARS serial-based study approach for the generation side of the pair.47 LARS will not be plagued
with the same type of restudies that justified the Commission’s adoption of the cluster study
approach for the DPP process because a much smaller number of eligible projects will be studied
annually. Since the number of projects that qualify for LARS will be significantly smaller than
those that can participate in the DPP queue study, MISO can effectively study the proposed LARS
projects on a serial basis and, as explained earlier, does not result in priority access for scarce
available transmission capacity. MISO agrees that in most instances cluster studies are the most
efficient route for an interconnection queue, but due to the unique characteristics of the LARS
process, a serial-based study approach is more appropriate and will facilitate addressing more
optimized transmission solutions in the MISO footprint.
Thus, the Commission should find that MISO’s LARS process accomplishes the purposes
of Order Nos. 2003 and 2023 despite not implementing a cluster process for the study of the
generators.48 A serial study process for the generating facilities participating in LARS is justified
because it will be completed on an extremely small number of projects per year and cluster studies
exist to manage interdependence among large numbers of unrelated requests, and that problem
does not arise in LARS with such a small number being studied in a geographically dispersed
46 Order No. 2003, 104 FERC ¶ 61,103 at PP 825-826; Order No. 2023, 184 FERC ¶ 61,054 at P 1764.
47 See Order No. 2023, 184 FERC ¶ 61,054 at P 1764.
48 See Order No. 2003, 104 FERC ¶ 61,103 at PP 825-826; Order No. 2023, 184 FERC ¶ 61,054 at P 1764.
PDF page 27
27
manner across different LRZs. LARS advances Order No. 2003’s goal of expediting new
generation while protecting reliability.49
LARS also meets Order No. 2023’s goal of insulating the DPP queue and ensuring that
only truly commercially ready projects apply.50 Notably, the LARS process requires an increased
non-refundable payment (“D1”) of $250,000 that will be applied toward the costs related to
processing the LARS request. The D1 payment and study deposits are used for study costs and
other costs associated with processing the LARS request, which includes MISO internal staffing
hours and contractor staffing hours. The strict eligibility requirements, including agreeing to
formally pair for a minimum of fifteen years, also serves as a deterrent to speculative projects and
enables the expedited study of unique generation/load pairs. Ultimately, LARS will help ensure
interconnection to the transmission system in a reliable, efficient, transparent, and timely manner.
F. Miscellaneous Clarifications and Requests.
MISO first seeks to clarify the allowable Interconnection Service amount requested under
the LARS Interconnection Request and whether the LARS Associated Load’s expected peak
demand means the load’s demand at the time it first takes service or the expected demand once
any planned phase build outs are completed.51 MISO wants to clarify that it means that the
identified peak demand amount identified in the LARS Application (i.e., amount of Transmission
Service requested), regardless of whether the load comes into service in phases. The applicants
submitting a LARS Application must identify the LARS Associated Load’s expected peak
49 See Order No. 2003, FERC Stats. & Regs. ¶ 31,146 at PP 822-827; Order No. 2003-A, FERC Stats. & Regs. ¶
31,160 at P 759.
50 See Improvements to Generator Interconnection Procs. & Agreements, Order No. 2023, 184 FERC ¶ 61,054,
order on reh’g, 185 FERC ¶ 61,063 (2023), order on reh’g, Order No. 2023-A, 186 FERC ¶ 61,199, errata notice,
188 FERC ¶ 61,134 (2024).
51 Base Electron Power LARS Comments at 3.
PDF page 28
28
Demand once it is fully in service, even if it is developed and built in phases. But this does not
mean generation can be sized to account for potential future load size increases not reflected in a
Transmission Service/LARS application.
Second, MISO recognizes that Invenergy requested that “[t]he Commission should direct
MISO to revise its proposed Tariff to clarify that MHVDC transmission lines and associated
interconnected generation should be eligible to participate in LARS.”52 Invenergy argues that both
MHVDC transmission lines and the generating facilities connected to those lines are equally
capable of serving large load customers.53 MISO appreciates this unique and creative proposal but
does not believe that LARS is the appropriate construct for MHVDC transmission line
participation.
First, the interconnection of MHVDC facilities is governed by its own process in Attachment
GGG, which is separate from the GIP process and is much more study intensive.54 Second,
MHVDC Injection Rights may only be granted through the same study process as Interconnection
Requests via Attachment X. If Invenergy is looking to have Injection Rights approved through
the LARS process instead of the DPP process, that idea should be proposed in a new proceeding
as it would require significant changes to Attachment GGG and Attachment X. As it currently
stands, MHVDC projects can obtain firm Injection Rights (External NRIS) via the DPP process
and pursue an off-taker for the generation facilitated by the MHVDC project outside of existing
MISO processes. Third, MISO notes that the MHVDC interconnection process and the LARS
process have nearly incompatible timelines as the connection procedures for MHVDC lines can
52 Invenergy LARS Comments at 4.
53 Id.
54 See MISO, Attachment GGG, Merchant HVDC Transmission Connection Procedures (MHCP), available at:
https://docs.misoenergy.org/miso12-legalcontent/Attachment_GGG_-
_Merchant_HVDC_Transmission_Connection_Procedures_%28MHCP%29.pdf.
PDF page 29
29
take considerably longer than 120 days. LARS is a process for the parallel study of generation
and load pairs. That said, MISO does not, in concept, oppose considering the addition of MHVDC
participation within the LARS construct through a future filing. However, this is outside the scope
of the current LARS proposal and would need to be proposed as an issue and then considered
through MISO’s stakeholder process.
IV.
CONCLUSION
WHEREFORE, MISO respectfully requests that the Commission: (1) accept this Answer;
and (2) accept the LARS Filing as discussed herein.
Respectfully submitted,
/s/ Christopher Supino
Christopher D. Supino
Managing Senior Corporate Counsel
720 City Center Dr
Carmel, IN 46032
Telephone: (317) 249-5400
Email: csupino@misoenergy.org
Attorneys for the Midcontinent Independent System
Operator, Inc.
Dated:
November 9, 2026
PDF page 30
30
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person
designated on the official service list compiled by the Secretary in this proceeding.
Dated at Carmel, Indiana this 9th day of November, 2026.
/s/ Dawn Kaminski
Dawn Kaminski
Midcontinent Independent
System Operator, Inc.
720 City Center Drive
Carmel, Indiana 46032
Telephone: (317) 249-5400