ER26-3380-001 · 2026-10-13 · American Municipal Power
Request for Clarification and Alternative Request for Rehearing of American Municipal Power, Inc.
Back to sections and commentaryPDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
)
Docket Nos. ER26-3380-000
EL26-108-000
REQUEST FOR CLARIFICATION AND ALTERNATIVE
REQUEST FOR REHEARING OF
AMERICAN MUNICIPAL POWER, INC.
American Municipal Power, Inc. (“AMP”) hereby requests clarification of certain
aspects of the Federal Energy Regulatory Commission’s (“Commission” or “FERC”)
September 29, 2026 order in the above-captioned docket,1 which addressed the proposal
by PJM Interconnection, L.L.C. (“PJM”) to establish a Reliability Backstop Procurement
(“RBP”) for the PJM region.2 Clarification of the September 29 Order is warranted to help
ensure that any method for allocating RBP costs (whether developed in this proceeding
or proposed by PJM in a future filing) comports with the Commission’s goal of allocating
RBP costs to regions experiencing load growth driven by new large loads, consistent with
cost causation principles.
First, the Commission should clarify its suggestion in the September 29 Order that
it may be just and reasonable for PJM to “base the RBP allocation on the difference
between the actual load for 2026/2027 delivery year in each Electric Distributor zone/area
with the most recent 2028/2029 delivery year load forecast for each Electric Distributor
zone/area.”3 The Commission should make clear that it would not be just and reasonable
to implement this cost allocation method if (as is likely) it would result in RBP costs being
1 PJM Interconnection, L.L.C., 196 FERC ¶ 61,245 (2026) (“September 29 Order”).
2 PJM, Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from Large
Loads, Docket No. ER26-3380-000 (July 31, 2026) (“PJM Filing”).
3 September 29 Order at P 159.PDF page 2
2
allocated to Electric Distributor zone/areas that are not experiencing load growth
attributable to data centers or other large loads, as such an allocation would be
inconsistent with the cost causation principle.
Second, the Commission should clarify that it did not make a final determination in
the September 29 Order that PJM’s proposed cost allocation method is not just and
reasonable.4 The Commission should also clarify that parties will have the opportunity in
the paper hearing to argue that PJM’s as-filed proposal to allocate RBP cost responsibility
is just and reasonable and not unduly discriminatory or unduly preferential.5 In the
alternative, AMP requests rehearing.
I.
BACKGROUND
PJM proposed the RBP as “a one-time time procurement of new capacity to
address resource adequacy challenges in the PJM Region.”6 The mechanism was
designed to procure a targeted quantity of capacity under fixed agreements with terms up
to fifteen years beginning with the 2028/2029 Delivery Year and ending with the
2042/2043 Delivery Year.7 PJM set the Initial RBP Target at 6,831.3 MW.8
PJM proposed to allocate the Initial RBP Target “to each Electric Distributor’s
zone/area using that zone/area’s pro-rata share of the difference between the forecasted
4 See id. at PP 153-57.
5 See id. at P 158.
6 PJM Filing, Transmittal Letter at 1.
7 Id. at 8.
8 Id. at 31. This quantity (in megawatts (“MW”) of Unforced Capacity (“UCAP”)) is the amount that PJM’s
Base Residual Auction for the 2028/2029 Delivery Year cleared short of PJM’s RTO-wide reliability
requirement at the price cap of $325/MW-day. Id. at 7. PJM proposed that the Initial RBP Target could
be decremented to account for certain new offsetting capacity (Qualifying RBP Offset UCAP MW), as
well as for any qualifying Electric Distributor zone/areas that opt out of procuring capacity through the
RBP. See id. at 8-9.
PDF page 3
3
Load Adjustments for the 2026/2027 Delivery Year and the 2028/2029 Delivery Year.”9
Thus, the Initial RBP Target of 6,831.3 MW would be allocated to those Electric Distributor
zone/areas that provided PJM projections of large load growth between 2026 and 2028.10
Although there would be several more steps in determining ultimate liability for RBP
Charges under PJM’s proposal, zone/areas that did not receive any allocation at this first
step would be effectively excluded from responsibility for RBP Charges. PJM asserted
that this allocation framework would be consistent with cost causation principles and the
Ratepayer Protection Pledge.11
In the September 29 Order, the Commission preliminarily found that aspects of
PJM’s RBP proposal – including cost allocation – may be unjust, unreasonable, unduly
discriminatory or preferential.12 The Commission established paper hearing procedures
to address three aspects of the PJM Filing – cost allocation, Transmission Owner exit
rules, and collateral requirements for Load Serving Entities (“LSEs”).13 The paper hearing,
the Commission explained, “should address the Commission’s potential modifications
9 PJM Filing, Attach. A, proposed Tariff, Attachment DD, section 18.3(a).
10 See, e.g., id., Attach. C, Croop Aff. at ¶¶ 41-43; Transmittal Letter at 96-97.
11 See id., Transmittal Letter at 100-108. PJM effectively confirmed that neither AMP, nor any AMP
member, would be allocated any of the costs of procuring the Initial RBP Target (i.e., RBP Charges)
under PJM’s as-filed proposal, as all AMP members were within zone/areas that would not receive any
allocation of the Initial RBP Target. See AMP, Comments, Docket No. ER26-3380-000, at 2 (Aug. 21,
2026) (“AMP Comments”).
12 See September 29 Order at P 23. FERC also concluded that the existing PJM Open Access
Transmission Tariff (“Tariff”) “may be unjust and unreasonable because the existing reliability backstop
provisions appear to be insufficient to prevent the grave resource adequacy concerns that led PJM to
file the instant proposal in the first place.” Id. at P 29.
13 See id. at PP 23-24. The Commission also established a new proceeding in Docket No. EL26-108-000
pursuant to section 206 of the Federal Power Act (“FPA”) “in anticipation of the Commission directing
significant modifications to certain aspects of PJM’s RBP proposal following the paper hearing.” Id. at P
27.
PDF page 4
4
with respect to the portions of PJM’s existing RBP proposal” that FERC found may be
unjust and unreasonable.14
While establishing a paper hearing, the Commission “strongly encourage[d] PJM
to address the issues discussed in this order by submitting an alternative proposal
pursuant to its FPA section 205 filing rights without delay.”15 The Commission observed
that such a filing could “obviate the need for the paper hearing procedures,”16 and the
Commission indicated that it would likely hold the paper hearing in abeyance if PJM files
a new FPA section 205 filing within thirty days of the September 29 Order.17
II.
REQUEST FOR CLARIFICATION
A.
The Commission should clarify that it would not be just and
reasonable to implement its potential modification to PJM’s proposed
RBP cost allocation if that approach would result in the allocation of
RBP costs to zone/areas that are not experiencing load growth
attributable to large loads.
In finding that PJM’s proposed RBP cost allocation may be unjust and
unreasonable, the Commission’s principal concern was that PJM’s reliance on Load
Adjustments could “potentially leav[e] out some new large loads,”18 because Load
Adjustments “account[] for net load growth associated with any size or type of load, while
excluding any new large loads that PJM knew of and accounted for when calculating the
initial load forecast.”19 Excluding new large loads from the Load Adjustments used to
14 Id. at P 23.
15 Id. at P 28; see also id. at PP 3, 158, 160.
16 Id. at P 3.
17 Id. at P 24.
18 Id. at P 155. The Commission also found that “PJM’s proposed opt-out for qualifying cooperatives and
municipal utilities may be unjust, unreasonable, and unduly discriminatory.” Id. at P 152.
19 Id. at P 155; see also id. at P 154 (agreeing “with concerns in the record that relying on Load Adjustments
to measure load growth may be inconsistent or not reasonably capture forecasted load growth or actual
PDF page 5
5
allocate the Initial RBP Target, the Commission reasoned, “could lead to the costs
imposed on certain entities not being at least roughly commensurate with the benefits
they will receive from the procurement.”20 In other words, the Commission was not
persuaded that the load growth data upon which PJM proposed to rely would accurately
identify, and allocate costs to, zone/areas with the new large loads that drove the region’s
current capacity shortfall, as required by the cost causation principle.21
In response to this perceived deficiency in PJM’s proposal, the Commission
remarked that it may be just and reasonable for PJM to “base the RBP allocation on the
difference between the actual load for 2026/2027 delivery year in each Electric Distributor
zone/area with the most recent 2028/2029 delivery year load forecast for each Electric
Distributor zone/area.”22 This approach, the Commission suggested, “may be consistent
with the cost causation principle because it would appropriately assign RBP costs to the
Electric Distributor zone/areas with the reported new load that is driving the need for the
procurement.”23 The Commission indicated that parties should address this potential
modification to PJM’s cost allocation proposal in the paper hearing procedures.24
The cost causation principle dictates that “all Commission-jurisdictional rates and
charges must reflect to some degree the costs actually caused by the customer who must
large load growth.”). As explained, infra, in section III.B.1, the Commission appears to have
misunderstood how PJM calculated the Load Adjustment data on which PJM relied to set the Initial RBP
Target.
20 Id. at P 155.
21 See, e.g., id., Comm’r See, concurring, at P 3 (observing that “PJM missed the mark on an important
element of its proposal: it did not adequately ensure that the procurement’s costs will be allocated to the
customers who drive its need.”).
22 Id. at P 159.
23 Id.
24 Id. at PP 158, 160.
PDF page 6
6
pay for them, and costs must be allocated in a manner that is at least roughly
commensurate with benefits.”25 Adherence to this principle in allocating RBP costs, as
the Commission properly recognized, requires that RBP costs are borne by the
zone/areas experiencing growth in large loads.26 The United States Department of Energy
(“DOE”) underscored this point in its recent Statement of Position, “emphasiz[ing] the
need to protect ratepayers from the costs associated with rising demand caused by other
large load customers.”27
To help ensure that the method for allocating RBP costs (whether developed
through the paper hearing or proposed by PJM in an FPA section 205 filing) comports
with the Commission’s goal of allocating RBP costs to zone/areas experiencing load
growth driven by new large loads, the Commission should clarify that it would not be just
and reasonable to apply the Commission’s potential modification to PJM’s cost allocation
method if it would result in RBP costs being allocated to Electric Distributor zone/areas
that are not experiencing load growth attributable to data centers or other large loads, as
such an allocation would be inconsistent with the cost causation principle.
The requested clarification would avoid any potential misinterpretation of the
Commission’s statement that its potential modification to the PJM proposal “would
appropriately assign RBP costs to the Electric Distributor zone/areas with the reported
new load that is driving the need for the procurement.”28 Specifically, clarification would
25 Id. at P 150 (citation modified).
26 Id. at PP 154-55; see also id., Comm’r Rosner, concurring, at P 2 (opining that the Commission’s
guidance “will enable PJM to assign costs to those responsible (i.e. to the zones with data center growth)
for the resource adequacy shortfall, consistent with cost causation principles”).
27 DOE, Notice of Intervention and Statement of Position of the United States Department of Energy,
Docket Nos. ER26-3380-000, et al., at 6 (Oct. 7, 2026).
28 September 29 Order at P 159.
PDF page 7
7
indicate that the Commission’s reference to “new load that is driving the need for the
procurement” means new data center and other large load.
Clarification is also appropriate to resolve the incongruity between, on the one
hand, the Commission’s aim of ensuring that RBP costs are allocated to zone/areas with
large load growth driving resource adequacy deficiencies, and, on the other hand, the
likelihood that its proposed cost allocation method would allocate RBP costs to
zone/areas without new large loads. Contrary to the Commission’s goals in suggesting
its revised cost allocation approach, implementing its potential modification to RBP cost
allocation would likely violate cost causation principles, as it could result in the allocation
of RBP costs to zone/areas that have not experienced load growth attributable to data
centers or other large loads. The Commission’s proposed modification apparently calls
for PJM to allocate RBP costs to each Electric Distributor zone/area based on its load
ratio share of forecasted load growth between the 2026/2027 and 2028/2029 delivery
years. Such a load ratio share approach to allocating costs would not comport with cost
causation. As the Commission recognized, “[t]he RBP is a one-time procurement of
capacity resources to address a shortfall attributable to load growth in certain Electric
Distributor zone/areas.”29 Simply assigning RBP costs based on each zone/area’s share
of the difference between the actual load for the 2026/2027 delivery year and the load
forecast for 2028/2029 would not ensure that costs are appropriately allocated to those
“certain Electric Distributor zone/areas”30 driving the capacity shortfall. The Commission’s
29 Id. at P 156 (emphasis added).
30 Id.
PDF page 8
8
modified approach is instead likely also to capture zone/areas where load growth is
attributable to ordinary, organic load growth, not new large loads.
B.
The Commission should clarify that it has not made a final decision
regarding the justness and reasonableness of PJM’s proposed cost
allocation method.
AMP generally supported the RBP cost allocation method proposed in the PJM
Filing, observing that it would appropriately allocate the Initial RBP Target to zone/areas
with large load growth documented in forecast Load Adjustments.31 As noted above,
however, the Commission concluded “that PJM’s proposed RBP cost allocation method
may be unjust and unreasonable,”32 finding that, “based on the current record, PJM has
not adequately demonstrated that its proposal is just and reasonable and consistent with
the cost causation principle.”33
The September 29 Order, however, is ambiguous as to whether the Commission
intended to make a final decision as to the justness and reasonableness of PJM’s as-filed
cost allocation method that would be subject to a request for rehearing. While certain
statements in the September 29 Order indicate that the Commission made no final
determination on the merits of PJM’s proposal,34 other statements in the Order suggest
31 See AMP Comments at 2.
32 September 29 Order at P 153.
33 Id.
34 See, e.g., id. at P 23 (“[o]ur preliminary analysis indicates that . . . aspects of PJM’s proposal have not
been shown to be just and reasonable and may be unjust, unreasonable, unduly discriminatory or
preferential, or otherwise unlawful.”); id. (“PJM’s filing raises issues of material fact that cannot be
resolved based on the record before us and that are more appropriately addressed in the paper hearing
procedures established below.”); id at P 153 (“PJM’s proposed RBP cost allocation method may be
unjust and unreasonable”).
PDF page 9
9
that the Commission conclusively found that PJM’s proposed cost allocation method is
not just and reasonable.35
The Commission should clarify that it has not made a final decision regarding the
justness and reasonableness of PJM’s as-filed RBP cost allocation approach, and that
the September 29 Order is not a final order as to that issue. Granting the requested
clarification would be consistent with the general proposition that, when the Commission
makes preliminary findings on an issue and establishes further procedures, it has not
made a final determination that is subject to rehearing requests.36
The Commission should also clarify that parties may address PJM’s as-filed cost
allocation proposal in the paper hearing procedures. Those procedures would provide an
appropriate forum for parties to clarify aspects of PJM’s proposal that are subject to
misinterpretation, and address other details related to the merits of PJM’s as-filed cost
allocation method. The hearing process would allow the Commission to make a final
determination on the proposal’s justness and reasonableness based on a more complete
record.37 The opportunity to further evaluate PJM’s original proposal could be particularly
valuable given the concerns discussed above regarding the Commission’s proposed
modification to PJM’s cost allocation approach.
35 See, e.g., id. at P 156 (“PJM has not demonstrated that reliance on the Load Adjustment process is just
and reasonable.”); id. at P 158 (“we now conclude that additional record evidence is needed to determine
whether PJM’s proposed RBP cost allocation method could be just and reasonable if modified.”); id.,
Comm’r See, concurring, at P 3 (“PJM missed the mark on an important element of its proposal: it did
not adequately ensure that the procurement’s costs will be allocated to the customers who drive its
need.”).
36 See, e.g., PJM Interconnection, L.L.C., 196 FERC ¶ 61,214, at P 19 (2026); DCR Transmission, L.L.C.,
195 FERC ¶ 61,181, at P 19 (2026).
37 See September 29 Order at P 153 (concluding “based on the current record” that PJM did not adequately
demonstrate that its cost allocation proposal is just and reasonable).
PDF page 10
10
III.
ALTERNATIVE REQUEST FOR REHEARING
If the Commission denies the clarification requested in section II.B above, AMP
seeks rehearing of the September 29 Order pursuant to FPA section 31338 and
Commission Rule 713.39 The Commission should grant rehearing of its determination that
PJM’s proposed RBP cost allocation method – particularly its reliance on Load
Adjustments – is not just and reasonable. The Commission’s rejection of PJM’s proposal
was arbitrary and capricious, as it was based on an apparent misunderstanding of PJM’s
approach.
A.
Statement of Issues
In accordance with Rule 713(c)(2),40 AMP provides the following enumerated
statement of issues, including citations to representative Commission and court
precedent on which it relies:
1.
The Commission’s conclusion that PJM’s proposed RBP cost allocation
method was not just and reasonable was arbitrary and capricious.41
2.
The Commission’s conclusion that PJM’s proposed RBP cost allocation
method was not just and reasonable was arbitrary and capricious, as it was based upon
an apparent misunderstanding of the record evidence.42
38 16 U.S.C. § 825l.
39 18 C.F.R. § 385.713.
40 18 C.F.R. § 385.713(c)(2).
41 5 U.S.C. § 706(2); Motor Vehicle Mfrs. Ass’n of the United States, Inc. v. State Farm Mut. Auto. Ins. Co.,
463 U.S. 29, 43 (1983); New England Power Generators Ass’n v. FERC, 881 F.3d 202 (D.C. Cir. 2018);
KeySpan-Ravenswood, LLC v. FERC, 348 F.3d 1053 (D.C. Cir. 2003).
42 5 U.S.C. § 706(2); Motor Vehicle Mfrs. Ass’n., 463 U.S. at 43.
PDF page 11
11
B.
Request for Rehearing
1.
The Commission’s rejection of PJM’s RBP cost allocation
method was based on an apparent misunderstanding of that
method.
As discussed above, the Commission’s principal rationale for rejecting PJM’s
proposed cost allocation method was that PJM’s reliance “on Load Adjustments to
measure load growth may be inconsistent or not reasonably capture forecasted load
growth or actual large load growth.”43 While the Commission reasonably determined that
the cost causation principle requires RBP costs to be allocated based on “large load
growth,” the Commission erred in concluding that PJM’s as-filed proposal would not
accomplish this aim. The Commission’s conclusion appears to have been based, in
significant part, on a misunderstanding of the PJM methodology. As a consequence, the
Commission’s decision is not the product of reasoned decision making.44
The Commission expressed concern that, based on PJM’s discussion of its load
forecasting process in a prior proceeding, “it appears some large loads may never have
been accounted for as Load Adjustments because PJM accounted for them when
calculating the initial load forecast.”45 This observation misapprehends the PJM Load
Adjustment methodology used in allocating the Initial RBP Target. PJM’s proposed RBP
cost allocation method was based on the Load Adjustments in Table B9b in the 2026 PJM
43 September 29 Order at P 154.
44 Motor Vehicle Mfrs. Ass’n., 463 U.S. at 43 (an agency decision is arbitrary and capricious where the
agency offers “an explanation for its decision that runs counter to the evidence before the agency”).
45 September 29 Order at P 155 (citing PJM Interconnection, L.L.C., 188 FERC ¶ 61,200, at P 21 (2024));
see also id. (“the delta accounts for net load growth associated with any size or type of load, while
excluding any new large loads that PJM knew of and accounted for when calculating the initial load
forecast.”).
PDF page 12
12
Load Forecast,46 and those adjustments incorporate large loads that might otherwise be
captured in the initial load forecast, thus avoiding the concern identified by the
Commission.
As the Commission notes, PJM stated in Docket No. ER24-2447 that, to avoid
double counting of forecast load, PJM will not generally make a Load Adjustment if, based
on its review process, it concludes that a potential Load Adjustment is already captured
in the underlying load forecast model.47 The actual process is more complex. Relevant
here, PJM’s review of Load Adjustments includes a sensitivity analysis, reflected in Table
B9 of the PJM Load Forecast,48 that seeks to identify the extent to which a proposed Load
Adjustment includes large load already embedded in PJM’s initial econometric forecast.49
Table B9 presents the results of this sensitivity analysis, quantifying the Load Adjustment
amounts included in the final forecast that are over and above what is already embedded
in PJM’s initial forecast.50 Reliance on Load Adjustment quantities in Table B9 to allocate
RBP costs would indeed present a concern of undercounting new large loads.
PJM, however, did not rely on the Load Adjustments shown in Table B9 to allocate
RBP costs, it proposed to use the Load Adjustments in Table B9b of the Load Forecast.
46 PJM Filing, Attach. C, Croop Aff. at ¶ 43 (citing 2026 PJM Load Forecast Report Data Tables, PJM
Interconnection,
L.L.C.,
Tab
Table
B9b
(Feb.
2026),
https://www.pjm.com/-
/media/DotCom/planning/res-adeq/load-forecast/2026-load-report-tables.xlsx [https://perma.cc/SST2-
EGUZ]; 2026 PJM Load Forecast Report, PJM Interconnection, L.L.C., 5-6 (Jan. 14, 2026),
https://www.pjm.com/-/media/DotCom/library/reports-notices/load-forecast/2026-load-report.pdf
[https://perma.cc/J24E-7CV7] (describing Table B9b results)).
47 See September 29 Order at P 155; see also PJM Interconnection, L.L.C., 188 FERC ¶ 61,200 at P 21.
48 See footnote 46, supra.
49 See, e.g., PJM, 2026 PJM Long-Term Load Forecast, Load Analysis Subcommittee presentation, at p.
28
(Jan.
23,
2026),
https://www.pjm.com/-/media/DotCom/committees-
groups/subcommittees/las/2026/20260123/20260123-item-03---pjm-2026-long-term-load-forecast---
presentation.pdf.
50 See id.
PDF page 13
13
The Load Adjustments reflected in Table B9b, which was developed after PJM’s filing in
Docket ER24-2447, are intended to include new large loads that might otherwise have
been reflected in the underlying econometric forecast. PJM has described51 the basic
methodology for Table B9b Load Adjustments to be as follows: First, PJM identifies zones
with existing data center loads. Second, PJM removes monthly data center load from the
commercial Energy Information Administration data underlying the load forecast. Third,
PJM removes hourly data center load from historical loads used in PJM’s model
estimation. Finally, total accepted load is added to the load forecast. Thus, PJM removes
large loads from the underlying forecast data and adds large loads back into the forecast
through the Load Adjustments.52 Table B9b is intended to capture the difference between
the final forecast and what the final forecast would be without any large load, not just
without Load Adjustment requests above the embedded value.
The difference between the B9 and B9b analyses can be seen in a comparison of
the respective results, with Table B9b generally reflecting larger Load Adjustments, as
would be expected given the nature of that analysis:
51 PJM, 2026 PJM Long-Term Load Forecast, Load Analysis Subcommittee presentation, at p. 28,
https://www.pjm.com/-/media/DotCom/committees-
groups/subcommittees/las/2026/20260123/20260123-item-03---pjm-2026-long-term-load-forecast---
presentation.pdf.
52 For zones without existing data center loads, total accepted large load gets added into the forecast. See
id.
PDF page 14
14
2026 Load Forecast – Table B9
2026 Load Forecast – Table B9b
PDF page 15
15
Because the Load Adjustments in Table B9b are intended to count new large load
quantities, including those that might have otherwise been embedded in the initial PJM
load forecast data, use of Table B9b addresses the Commission’s principal concern with
PJM’s use of Load Adjustments in the cost allocation methodology. Accordingly, the
Commission erred in finding that PJM’s approach was not just and reasonable based on
that concern.
2.
The objections raised by the NJBPU did not warrant rejection of
PJM’s cost allocation methodology.
In rejecting PJM’s cost allocation methodology, the Commission also pointed to an
answer filed by the New Jersey Board of Public Utilities (“NJPBU”).53 Although generally
supporting reliance on Load Adjustments to allocate RBP costs, the NJBPU Answer
raised concerns about utilities’ potential use of inconsistent criteria in submitting the Load
Adjustment requests that formed the basis for PJM’s proposed cost allocation.54 While a
specific MW threshold for Load Adjustments might have been preferable (and has now
been adopted55), the absence of such a bright line does not undermine a conclusion that
the Load Adjustments submitted by utilities in connection with the 2026 Load Forecast
reasonably captured the large loads driving the region’s current capacity shortfall.
Moreover, once the proposed Load Adjustments were submitted, PJM engaged in a
robust independent analysis to ensure that the proposals were evaluated based on
consistent standards, regardless of the criteria used by the respective utilities that
53 September 29 Order at P 155 (citing NJBPU, Motion for Leave to Answer and Answer, at 3-6 (Sept. 24,
2026) (“NJBPU Answer”)). As noted, the NJBPU filed its answer just five days before the date by which
PJM asked the Commission to act on its Filing).
54 See NJBPU Answer at 3-6.
55 See id. at 4 n.13 (noting that PJM Manual 19 has been updated to specify a 50 MW threshold for future
Load Adjustments).
PDF page 16
16
submitted the Load Adjustments.56 Accordingly, the NJBPU’s concerns did not warrant
rejection of PJM’s cost allocation approach.
Because the Commission’s rationales for rejecting PJM’s proposed RBP cost
allocation method were based on a mistaken or incomplete understanding of PJM’s
approach, the Commission should grant rehearing of its rejection of PJM’s approach.
IV.
CONCLUSION
WHEREFORE, for the foregoing reasons, American Municipal Power, Inc.
requests the Commission to clarify its September 29 Order as explained herein. In the
alternative, AMP requests rehearing of the Commission’s rejection of PJM’s RBP cost
allocation methodology.
Respectfully submitted,
/s/ John McCaffrey
John McCaffrey
Stinson LLP
1775 Pennsylvania Avenue NW
Suite 800
Washington, DC 20006
(202) 728-3026
john.mccaffrey@stinson.com
Dated: October 13, 2026
/s/ Gerit F. Hull
Lisa G. McAlister
Senior Vice President & General Counsel
Gerit F. Hull
Deputy General Counsel for Regulatory Affairs
American Municipal Power, Inc.
1111 Schrock Road, Suite 100
Columbus, OH 43229
(614) 540-1111
lmcalister@amppartners.org
ghull@amppartners.org
56 See, e.g., PJM, Load Adjustment Requests Summary for 2026 Load Forecast - Preliminary, Load
Analysis
Subcommittee
presentation
(Nov.
24,
2025),
https://www.pjm.com/-
/media/DotCom/committees-groups/subcommittees/las/2025/20251124/20251124-item-03---large-
load-adjustment-requests-summary.pdf.
PDF page 17
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each
person designated on the official service list compiled by the Secretary in this proceeding.
Dated at Washington, D.C., this 13th day of October, 2026.
/s/ John McCaffrey
John McCaffrey
Stinson LLP
1775 Pennsylvania Avenue NW
Suite 800
Washington, DC 20006
(202) 728-3026
john.mccaffrey@stinson.com