ER27-25-000 · 2026-10-23 · Alliant and Consumers Energy
Comments of Alliant Energy Corporate Services, Inc. and Consumers Energy Company in Support of MISO's Proposed Tariff Revisions
Back to sections and commentaryPDF page 1
1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
Midcontinent Independent System Operator, Inc. ) Docket No. ER27-25
COMMENTS OF ALLIANT ENERGY CORPORATE SERVICES, INC. AND
CONSUMERS ENERGY COMPANY IN SUPPORT OF MISO’S PROPOSED TARIFF
REVISIONS
Pursuant to Rule 212 of the Federal Energy Regulatory Commission’s (“FERC” or
“Commission”) Rules of Practice and Procedure,1 18 C.F.R. § 385.212, Alliant Energy Corporate
Services, Inc (“AECS”) and Consumers Energy Company (“Consumers Energy”)2 respectfully
submit these comments in support of the Midcontinent Independent System Operator, Inc.’s
(“MISO”) Large Load Addition Resource Study (LARS) Proposal (“Proposal”) in the above-
captioned docket. AECS and its affiliates, 3 and Consumers Energy, as load-serving entities
(“LSEs”) support the need for an interconnection process that facilitates the timely study of
generation paired with an associated large load(s) to arrive at optimized transmission solutions.
Large loads increasingly seek service on accelerated timelines, creating a need for study processes
capable of evaluating load, generation, and associated transmission requirements on a more
coordinated basis. The LARS Proposal offers a practical approach to meeting load growth while
helping to maintain resource adequacy and supporting a cost-effective mix of generating resources.
1 18 C.F.R. § 385.212 (2025).
2 Consumers Energy is a Load Serving Entity (LSE) and active participant in the MISO generation interconnection
queue process. Consumers Energy is a public utility serving over 1.9 million residential, commercial, and industrial
electric customers in the Michigan Joint Zone of the MISO footprint.
3 AECS affiliates include Wisconsin Power & Light Company and Interstate Power & Light Company (collectively,
the “Alliant Energy Operating Companies”). The Alliant Energy Operating Companies are LSEs and active
participants in the MISO generation interconnection queue process. The companies have and continue to support
MISO improvements to interconnection processes and believe that while queue process enhancements are needed
and helpful, the benefits will take years to realize given the current status of queue cycles.
PDF page 2
2
AECS and Consumers Energy respectfully request that the Commission accept the LARS
Proposal.
Support for LARS as a Just and Reasonable Study Pathway
LARS offers an opportunity to plan transmission around the combined needs of new large
loads and paired generation, rather than evaluating each through separate processes. This
integrated approach will enable MISO to identify optimized transmission solutions, eliminate
duplicative or unnecessarily expensive upgrades, and help deliver lower-cost outcomes for
customers. The LARS Proposal provides a path to avoid studying qualifying large loads and
associated generation through separate processes using different assumptions and on different
schedules that may produce different transmission solutions. MISO has proposed using consistent
assumptions and rigorous methodologies to study the load and generation in parallel, with the
objective of completing the process within approximately 120 days. 4 This approach has the
potential to provide greater certainty regarding generation interconnection requirements,
transmission service, and the network upgrades necessary to support reliable service. MISO’s
filing further explains that LARS responds directly to the Commission’s Show Cause Order by
allowing MISO to account for the operational dynamics of serving electrically proximate large
loads.5 These benefits support acceptance of LARS as just and reasonable.
The Commission should support reforms that allow credible, commercially mature large
load projects to move forward efficiently while maintaining appropriate reliability protections.
MISO’s broader framework for integrating large loads onto its system appropriately recognizes
that acceleration must be coupled with operational capabilities such as telemetry, coordination,
curtailment capability, ride-through, stability controls, resilience, and security.
4 LARS Proposal at 11-12, 18.
5 Id. at 3.
PDF page 3
3
An expedited process should be available to projects demonstrating a high degree of
commercial and development certainty. MISO has emphasized that LARS is intended for specific
load-generation pairings with contractual arrangements and shovel-ready conditions, rather than
as an alternative fast-track interconnection queue for generators serving general system load.6
Strong readiness requirements are therefore an appropriate safeguard against speculative projects
consuming scarce study resources or affecting transmission solutions for projects that are prepared
to proceed.
AECS and Consumers Energy therefore support LARS as a practical response to the
planning challenges presented by new large-load development. Its value extends beyond a shorter
study schedule: evaluating load and generation together creates an opportunity to optimize
transmission investments and achieve lower-cost solutions for customers. By combining that
opportunity with reliable study practices and clear participation safeguards, LARS provides a
disciplined framework suited to the needs of the MISO footprint.
Continued Stakeholder Collaboration on Implementation
AECS and Consumers Energy expect MISO will continue working with stakeholders to
refine LARS implementation details, including providing greater certainty regarding the
conditions under which projects may retain interconnection rights over time. Large load
development is evolving rapidly, and the industry is still gaining experience with the operating
characteristics, development timelines, and transmission implications of these facilities.
Accordingly, AECS and Consumers Energy support implementation of LARS with sufficient
transparency and stakeholder engagement to allow MISO to refine the framework as practical
experience identifies opportunities for improvement. Continued stakeholder engagement will be
6 Id. at 11, 25, and 28.
PDF page 4
4
important to realizing the benefits of LARS while maintaining reliable service and the integrity of
the interconnection process.
For these reasons, AECS and Consumers Energy respectfully request that the Commission
find MISO’s LARS Proposal is a just and reasonable approach to coordinating the study of large
loads and paired generation, optimizing transmission solutions, and facilitating timely, reliable
service at lower costs for customers, and accept the LARS Proposal.
Respectfully submitted,
/s/ Mitchel Myhre
Mitchel Myhre
Director of Grid Planning and RTO Relations
Alliant Energy Corporate Services, Inc.
4902 N. Biltmore Lane
Madison, WI 54718
Tel.: (608) 458-6273
Email: MitchellMyhre@alliantenergy.com
/s/ Rachael Moore
Rachael H. Moore
Principal Attorney
Consumers Energy Company
One Energy Plaza
Jackson, MI 49201
Phone: (517) 788-1147
Email: rachael.moore@cmsenergy.comPDF page 5
5
CERTIFICATE OF SERVICE
I hereby certify I have this day served the foregoing document upon each person designated
on the official service list compiled by the Secretary in these proceedings.
Dated at Cedar Rapids, Iowa, this 23 day of October 2026.
/s/ Dezirae Fisher
Dezirae Fisher
Senior Paralegal
Alliant Energy Corporate Services, Inc.
200 1st St SE
Cedar Rapids, IA 52401
Tel: (319) 786-4113
Email: deziraefisher@alliantenergy.com