PJM Transmission Owners' partial compliance filing implementing the Interim NITS rate
Topics in the text: Cost allocation
What the document says
PDF p. 2
The PJM TOs file the Interim NITS rate, effective July 1, 2028 to match PJM.
attached to this filing are new and revised tariff records for the PJM Tariff necessary to implement the rate for Interim NITS PDF p. 2
PDF p. 2
The PJM TOs file the Interim NITS rate, effective July 1, 2028 to match PJM.
The PJM Transmission Owners request that the revisions submitted with this partial compliance filing become effective on July 1, 2028. PDF p. 2
PDF p. 1
The TOs flag the Interim NITS rate may be terminated because FERC's directives are challenged.
the Commission’s directives being complied with herein are under challenge before the Commission and through petitions for review, such that the tendered tariff sheet revisions herein may be subject to a subsequent termination filing PDF p. 1
Responses and related views
No section-specific public response is linked for this document.
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
Suite 500 East 1301 K Street NW Washington, D.C. 20005-3317 August 17, 2026 Honorable Debbie-Anne A.Read this passage
I. DESCRIPTION OF COMPLIANCE FILING
printed heading · Topic match: Cost allocation
On August 14, 2026, the Commission granted these extension requests.Read this passage
II. Effective Date
PDF bookmark
EFFECTIVE DATE The PJM Transmission Owners request that the revisions submitted with this partial compliance filing become effective on July 1, 2028.Read this passage
III. Additional Information
PDF bookmark
III.Read this passage
A. Communications
PDF bookmark
Communications Communications regarding this filing should be addressed to the following individuals, whose names should be entered on the official service list maintained by the Secretary for this proceeding. 5 PJM Extension Motion at 1-2. 3 Pulin Shah Vice President of Transmission Development…Read this passage
B. List of Documents Submitted with Filing
PDF bookmark
List of Documents Submitted with Filing In addition to this transmittal letter, this filing includes the following attachments: • Attachment A: Clean Tariff Records for the PJM Tariff • Attachment B: Redlined Tariff Records for the PJM TariffRead this passage
C. Service
PDF bookmark
Service PJM has served a copy of this filing on all PJM Members and on all state utility regulatory commissions in the PJM Region by posting this filing electronically.Read this passage
IV. Conclusion
PDF bookmark
IV.Read this passage
CONCLUSION
printed heading
CONCLUSION For the reasons stated herein, the PJM Transmission Owners respectfully request that the Commission accept this partial compliance filing without hearing, modification or condition.Read this passage