EL26-72-000 · 2026-06-18 · FERC
ISO-NE show cause order
Back to sections and commentaryPDF page 1
195 FERC ¶ 61,215
UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION
Before Commissioners: Laura V. Swett, Chairman;
David Rosner, Lindsay S. See,
Judy W. Chang, and David LaCerte.
ISO New England Inc.
Central Maine Power Company
The Connecticut Light and Power Company
Fitchburg Gas and Electric Light Company
Green Mountain Power Corporation
Maine Electric Power Company
The Narragansett Electric Company
New England Power Company
New Hampshire Transmission, LLC
NSTAR Electric Company
Public Service Company of New Hampshire
The United Illuminating Company
Unitil Energy Systems, Inc.
Vermont Electric Cooperative, Inc.
Vermont Electric Power Company, Inc.
Vermont Transco LLC
Versant Power
Docket No.
EL26-72-000
ORDER INSTITUTING PROCEEDING
UNDER SECTION 206 OF THE FEDERAL POWER ACT
(Issued June 18, 2026)PDF page 2
Docket No. EL26-72-000
- 2 -
Paragraph Numbers
I. Background ..................................................................................................................... 6.
A. Growth of Large and Co-Located Loads and ANOPR ............................................. 6.
B. Recent Proceedings Addressing Large and Co-Located Loads .............................. 12.
1. PJM Co-Location Proceedings ............................................................................ 13.
2. SPP High Impact Large Load and High Impact Large Load Generation
Assessment Processes .............................................................................................. 16.
3. SPP Conditional High Impact Large Load Service ............................................. 18.
II. ISO-NE’s Existing Processes ....................................................................................... 20.
A. Existing Tariff Processes ......................................................................................... 20.
B. Recent Stakeholder Proceedings in ISO-NE ........................................................... 30.
III. Discussion ................................................................................................................... 32.
A. Transmission Service to Eligible Customers on Behalf of Large Loads ................ 38.
1. Jurisdiction ........................................................................................................... 42.
2. Tariff Provisions .................................................................................................. 48.
B. Cost Shifting Risk Among Transmission Customers .............................................. 64.
1. Jurisdiction ........................................................................................................... 66.
2. Additional Cost Transparency ............................................................................. 69.
3. Cost Recovery Agreements ................................................................................. 74.
C. Co-Location Arrangements and Load with Behind the Meter Generation ............. 83.
1. Definition ............................................................................................................. 85.
2. Jurisdiction ........................................................................................................... 89.
3. Tariff Provisions .................................................................................................. 91.
D. Extending New Transmission Services to Eligible Customers Taking Service on
Behalf of Flexible Large Loads ................................................................................. 101.
E. Interconnection Customers Serving Electrically Proximate Large Load and Co-
Located Load .............................................................................................................. 104.
F. Informational Report .............................................................................................. 118.
IV. Briefing Questions .................................................................................................... 120.
PDF page 3
Docket No. EL26-72-000
- 3 -
Over the past year, the Commission has taken action in numerous dockets1 to
address issues related to (a) unprecedented increases in requests for transmission service
to serve large loads2 and (b) growing interest in the co-location of loads with generating
facilities (co-location arrangements3). Separately, the Secretary of Energy (Secretary)
released an advance notice of proposed rulemaking (ANOPR) in October 2025. The
ANOPR, issued pursuant to section 403 of the Department of Energy Organization Act,4
directed the Commission to consider taking additional actions to address the addition of
large and co-located loads to the transmission system.5 The records in these proceedings
illustrate a host of urgent challenges associated with providing the transmission service
needed to serve the ongoing influx of large loads while maintaining reliability and
affordability. In particular, stakeholders have expressed concerns that large loads are not
efficiently and appropriately integrated onto the transmission system; have identified a
1 See, e.g., PJM Interconnection, L.L.C., 190 FERC ¶ 61,115 (2025) (PJM Show
Cause Order); PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (PJM Co-
Location Order); Sw. Power Pool, Inc., 194 FERC ¶ 61,031 (2026) (SPP HILL Order);
Sw. Power Pool, Inc., 195 FERC ¶ 61,196 (2026) (SPP CHILLS Order); see also, e.g.,
Duke Energy Carolinas, LLC, 193 FERC ¶ 61,237 (2025); Commonwealth Edison Co.,
194 FERC ¶ 61,181 (2026).
2 As explained below, it appears that it would be reasonable to define a large load
as (1) a new commercial or industrial customer, (2) located at a single site behind one or
more points of interconnection, (3) that has a peak load of 50 MW or greater, (4)
interconnects to the transmission system at a voltage level of greater than 69 kV, and
(5) is not part of a co-location arrangement. See infra P 56.
3 As explained below, it appears that it would be reasonable to define co-located
load as a configuration that refers to end-use customer load that is physically connected
to the facilities of an existing or planned generating facility on the interconnection
customer’s side of the point of interconnection to the RTO/ISO’s transmission system.
In this order, we will use the term co-location arrangement when referring to both the
co-located load and the associated generating facility. See infra P 86.
4 42 U.S.C. § 7173.
5 See Interconnection of Large Loads to the Interstate Transmission System,
Advance Notice of Proposed Rulemaking, Docket No. RM26-4-000 (Oct. 23, 2025)
(ANOPR); see also Letter from Chris Wright, Sec’y, U.S. Dep’t of Energy, Docket No.
RM26-4-000 (Oct. 23, 2025). The ANOPR uses the term “hybrid facilities,” which it
explains are large loads that “share a point of interconnection with new or existing
generation facilities.” ANOPR at P 12. In this order, as explained below, we use the
term co-located load.
PDF page 4
Docket No. EL26-72-000
- 4 -
number of unique challenges that large load integration poses for the reliable operation of
that system; and have debated how best to ensure that the rates, terms, and conditions of
transmission service remain just and reasonable as more and more large loads are
onboarded onto that system.6 The records in these proceedings likewise present serious
concerns about the lack of clarity and consistency in Regional Transmission Organization
or Independent System Operator (RTO/ISO) tariffs—including with respect to the rates,
terms, and conditions of service that apply to flexible large loads, co-location
arrangements, load with behind the meter generation, and generating facilities with
electrically proximate large load7 or co-located load.
The findings in several recent Commission proceedings establish the foundations
of a just and reasonable framework for addressing these concerns and ensuring the
timely, efficient, and reliable integration of large and co-located loads onto the
transmission system. For example, Southwest Power Pool, Inc. (SPP) has recently taken
a number of innovative and proactive steps to address the challenges of integrating large
loads, co-located loads, and/or generation and electrically proximate large load onto the
transmission system while ensuring that its tariff remains just and reasonable, and PJM
Interconnection, L.L.C. (PJM) has likewise taken steps toward that goal in response to
this Commission’s directives.8 By contrast, ISO New England Inc. (ISO-NE) has not yet
6 Throughout this order we rely on comments and answers filed in response to the
ANOPR in Docket No. RM26-4-000 and all referenced comments in this order were filed
in that docket, unless otherwise noted. A full list of commenter names and abbreviations
is attached to this order as an Appendix. Additionally, we have relied on the discussions
held in the Federal and State Current Issues Collaborative in Docket No. AD24-7-000
(NARUC Collaborative). All entities who wish to participate in this docket, regardless of
participation in the ANOPR proceeding or NARUC Collaborative, should file to
intervene in Docket No. EL26-72-000.
7 As explained below, for purposes of this order, an “electrically proximate large
load” is a large load, as defined in this order, that is sufficiently electrically close to the
interconnection customer’s requested point of interconnection, such that the impact on
the transmission system of the combination of the generating facility and the load, with
the exception of the transmission facilities between the two, will be effectively the same
as if they were located at the same substation (e.g., large load that is located no more than
two substations away from the generating facility). See infra P 110.
8 PJM Show Cause Order, 190 FERC ¶ 61,115; PJM Co-Location Order,
193 FERC ¶ 61,217, order on reh’g, 195 FERC ¶ 61,209 (2026) (PJM Co-Location
Rehearing Order); SPP HILL Order, 194 FERC ¶ 61,031; SPP CHILLS Order,
195 FERC ¶ 61,196.
PDF page 5
Docket No. EL26-72-000
- 5 -
proposed tariff revisions to address the challenges associated with the integration of large
and co-located loads.
As discussed below, we find that ISO-NE’s existing Transmission, Markets and
Services Tariff (Tariff) appears to be unjust, unreasonable, or unduly discriminatory or
preferential. We thus institute a show cause proceeding pursuant to section 206 of the
Federal Power Act (FPA),9 and we direct ISO-NE and the Participating Transmission
Owners,10 within 60 days of the date of this order, to either:
(1) show cause as to why the Tariff remains just and reasonable and not unduly
discriminatory or preferential without provisions addressing:
(a) the application process, study procedures, and ongoing operational
requirements that apply to Eligible Customers11 seeking transmission
service on behalf of large loads;
9 16 U.S.C. § 824e.
10 Participating Transmission Owners refers to the entities listed in the caption of
this order. We recognize that ISO-NE’s transmission owners include entities that are not
subject to the Commission’s jurisdiction because they are not public utilities pursuant to
section 201(f) of the FPA. See 16 U.S.C. § 824(f); Sw. Power Pool, Inc., 180 FERC
¶ 61,022, at PP 44-45 (2022). Accordingly, the Commission has not included Town of
Braintree Electric Light Department; Chicopee Municipal Lighting Plant; Connecticut
Municipal Electric Energy Cooperative; Connecticut Transmission Municipal Electric
Energy Cooperative; The City of Holyoke Gas and Electric Department; Town of Hudson
Light and Power Department; Massachusetts Municipal Wholesale Electric Company;
Town of Middleborough Gas & Electric Department; New Hampshire Electric
Cooperative, Inc.; Town of Norwood Municipal Light Department; Town of Reading
Municipal Light Department; Shrewsbury Electric and Cable Operations; Town of Stowe
Electric Department; Taunton Municipal Lighting Plant; Vermont Public Power Supply
Authority; and Town of Wallingford, CT, Department of Public Utilities, Electric
Division here as Participating Transmission Owners that must respond to this order to
show cause. Nonetheless, the Commission retains the authority to review each entity’s
formula rates as a component of ISO-NE’s Tariff in an order to show cause directed
towards ISO-NE, and ISO-NE must respond to this order regarding the non-public
utilities’ ISO-NE Tariff provisions on file with the Commission. See Sw. Power Pool,
Inc., 180 FERC ¶ 61,022 at P 40.
11 ISO-NE’s Tariff defines an Eligible Customer as:
(i) Any entity that is engaged, or proposes to engage, in the
wholesale or retail electric power business is an Eligible
PDF page 6
Docket No. EL26-72-000
- 6 -
(b) additional transparency concerning the network upgrade costs to
provide transmission service to Eligible Customers on behalf of large loads,
a pro forma cost recovery agreement between ISO-NE, the relevant
transmission owner, and Eligible Customer taking transmission service on
behalf of the large load to mitigate the risk of cost shifting among
transmission customers, and a mechanism to ensure such payments are
appropriately credited toward transmission owners’ transmission revenue
requirements consistent with the Commission’s cost-of-service regulations;
(c) the rates, terms, and conditions of service that apply to co-location
arrangements;
(d) transmission services that reflect Eligible Customers taking
transmission service on behalf of co-located loads, load with behind the
meter generation, and flexible large loads that are willing and able to limit
their use of the transmission system under certain conditions;12 and
Customer under the [Tariff]. (ii) Any electric utility
(including any power marketer), Federal power marketing
agency, or any other entity generating electric energy for sale
or for resale is an Eligible Customer under the [Tariff]. . . .
(iii) Any end user taking or eligible to take unbundled
transmission service or Local Delivery Service pursuant to a
state requirement that the Transmission Owner with which
that end user is directly interconnected or the distribution
company having the service territory in which that entity is
located (if that entity is a retail customer) offer the
transmission service or Local Delivery Service, or pursuant to
a voluntary offer of such service by the Transmission Owner
with which that end user is directly interconnected, or the
distribution company having the service territory in which
that entity is located (if that entity is a retail customer) is an
Eligible Customer under the [Tariff].
ISO-NE, Transmission, Markets and Services Tariff, § I.2 (Rules of Construction;
Definitions) (177.0.0), § I.2.2 (ISO-NE Tariff).
12 As explained below, for purpose of this order, “flexible” large loads are a subset
of large loads, as used in this order, that are not co-located with generation, but are
willing and able to limit their energy withdrawals from the transmission system under
certain conditions. See infra note 221.
PDF page 7
Docket No. EL26-72-000
- 7 -
(e) the rates, terms, and conditions of service applicable to interconnection
customers serving electrically proximate large load or co-located load; or
(2) explain what changes to the Tariff would remedy the identified concerns if the
Commission were to determine that the Tariff has in fact become unjust and
unreasonable or unduly discriminatory or preferential and, therefore, proceeds to
establish a replacement Tariff.
We are also concerned with ISO-NE’s need to ensure adequate generation to serve
new large loads.13 We therefore direct ISO-NE to submit, within 30 days of the date of
issuance of this order, an informational report on how ISO-NE intends to ensure that
adequate generation will be available to serve existing and new large loads, as detailed
later in this order.
We recognize that large loads, including data centers, are actively working with
transmission owners and other relevant entities to interconnect to, and to take service
from, the transmission system. We appreciate that different large loads are currently at
different stages of that process. We also understand that large loads and Eligible
Customers taking transmission service on behalf of large loads are negotiating, entering
into, and/or have executed various agreements related to interconnecting to the
transmission system and/or the provision of transmission service. This proceeding is not
intended to disrupt existing commercial arrangements, but rather to establish prospective
reforms. Accordingly, any Tariff revisions offered by ISO-NE and/or the Participating
Transmission Owners in response to this proceeding should (a) propose a reasonable
implementation period to ensure minimal disruption to such existing commercial
arrangements, and (b) allow a reasonable amount of time to finalize ongoing agreements
that are nearing completion as of the date such Tariff provisions are filed with the
Commission. Such proposed Tariff revisions should include a reasonable effective date
that accommodates such considerations regarding these existing commercial
arrangements.
I.
Background
A.
Growth of Large and Co-Located Loads and ANOPR
As the Secretary explained in the ANOPR, electricity demand in the United States
is expected to grow at an extraordinary pace in the near term, largely due to the rapid
13 Cf. PJM Co-Location Order, 193 FERC ¶ 61,217 at PP 237-239 (highlighting
PJM’s ongoing Critical Issue Fast Path stakeholder process to consider proposals to help
integrate large load additions without causing resource inadequacy and directing an
informational report on the status of those proposals).
PDF page 8
Docket No. EL26-72-000
- 8 -
growth of large loads.14 The Secretary highlighted findings from the North American
Electric Reliability Corporation (NERC) that show that demand growth is now higher
than at any point in the past two decades, driven in part by increasing quantities of large
commercial and industrial load, most notably data centers, connecting rapidly to the
transmission system.15 The Secretary also highlighted NERC’s conclusion that the size
and speed with which data centers can be connected to the grid present unique challenges
for demand forecasting and system planning. The ANOPR proposed that, in light of the
unprecedented current and expected growth of large loads seeking to interconnect to the
transmission system, the Commission should standardize interconnection procedures and
agreements for large loads, including those that seek to share a point of interconnection
with new or existing generation facilities.16
On April 16, 2026, the Commission issued an order regarding its intent to act with
respect to the ANOPR docket.17 In that order, the Commission explained that it agreed
with the Secretary “that, ‘[i]n light of the unprecedented current and expected growth of
large loads’ such as data centers, there is an urgent need for thoughtful reforms to ensure
that large loads are ‘able to connect to the transmission system in a timely, orderly, and
non-discriminatory manner.’”18 After recognizing the Commission’s recent actions in
proceedings involving issues associated with large loads,19 the Commission concluded
14 ANOPR at 2 (citing U.S. Dep’t of Energy, Resource Adequacy Report:
Evaluating the Reliability & Security of the United States Electric Grid (July 2025),
www.energy.gov/sites/default/files/2025-
07/DOE%20Final%20EO%20Report%20%28FINAL%20JULY%207%29.pdf).
15 Id. (citing NERC, 2024 Long- Term Reliability Assessment 8 (Dec. 2024,
updated July 2025),
https://www.nerc.com/pa/RAPA/ra/Reliability%20Assessments%20DL/NERC_Long%2
0Term%20Reliability%20Assessment_2024.pdf).
16 Id. P 12. For example, the ANOPR proposed that load and hybrid facilities
should be studied together with generating facilities, observing that “siting a large load
near or at the same point of interconnection as a new generating facility could reduce the
network upgrades needed to interconnect only the load or only the generating facility.”
ANOPR at P 20.
17 Interconnection of Large Loads to the Interstate Transmission Sys., 195 FERC
¶ 61,045 (2026) (Order Regarding Intent to Act).
18 Id. P 2.
19 Id. (citing PJM Co-Location Order, 193 FERC ¶ 61,217; SPP HILL Order,
194 FERC ¶ 61,031; Commonwealth Edison Co., 194 FERC ¶ 61,181; Tri-State
Generation & Transmission Ass’n, 193 FERC ¶ 61,070; Duke Energy Carolinas, LLC,
PDF page 9
Docket No. EL26-72-000
- 9 -
that it was clear that additional “action is warranted to support further progress where it is
needed.”20
ISO-NE states that, while New England has not experienced data center proposals
to the extent seen in other regions of the country to date,21 it is aware of interest in large
load development within its footprint and is prioritizing preparation for the potential of
large load additions.22 In 2026, in acknowledgement of the potential growth of large
loads in the region, ISO-NE included a separate projection for large load nameplate
capacity for the first time in its Capacity, Energy, Loads, and Transmission (CELT) load
forecast.23 ISO-NE also recently presented on its efforts to plan for large load growth in
the region at the 2026 New England Conference of Public Utilities Commissioners.24
Eversource notes in its ANOPR comments that the rapid onset of the interconnection of
large loads around the country, especially data center and electrification projects,
represents an unprecedented sea change in the industry.25 Additionally, the Commission
has recently accepted several study agreements filed by multiple transmission owners in
ISO-NE that include terms and conditions for conducting studies concerning the viability
of interconnecting large loads.26 Further, the Southeast PIOs in their ANOPR comments
193 FERC ¶ 61,237).
20 Id. PP 3-4.
21 ISO-NE, ISO-NE’s Response to Chairman David Rosner’s September 18, 2025
Letter Seeking a Dialogue on Large Load Growth in New England 1 (Oct. 6, 2025),
https://www.iso-ne.com/static-assets/documents/100028/large-load-forecasting-isone-
response.pdf (ISO-NE Letter).
22 Id.; see also ISO-NE, Final Draft 2026 Large Load Forecast 3 (Mar. 27, 2026),
https://www.iso-ne.com/static-assets/documents/100033/fx2026_large_loads.pdf (noting
that there are a couple hundred MW of large loads in the formal study phase) (ISO-NE
Large Load Forecast Presentation).
23 See ISO-NE Large Load Forecast Presentation at 14.
24 See ISO-NE, Planning for Large Loads in New England (May 20, 2026),
https://www.iso-ne.com/static-
assets/documents/100035/iso_large_loads_necpuc_symposium_mcbride.pdf.
25 Eversource November 21 ANOPR Comments at 2.
26 See, e.g., NSTAR Elec. Co., Docket No. ER21-2696-000 (Oct. 14, 2021)
(delegated order); Pub. Serv. Co. of N.H., ER24-2522-000 (Aug. 30, 2024) (delegated
order); NSTAR Elec. Co., Docket No. ER25-1796-000 (May 27, 2025) (delegated order);
NSTAR Elec. Co., Docket No. ER25-1795-000 (May 27, 2025) (delegated order); The
PDF page 10
Docket No. EL26-72-000
- 10 -
cite to a Report from NESCOE, which states that while the New England area may have
less data center development currently than areas such as Virginia, data center issues are
likely to become more salient in New England as other markets become saturated and
power and land availability becomes an issue.27 Moreover, recent news articles note
increased interest in data center development throughout the region.28
Although some commenters in the ANOPR proceeding assert that ISO-NE’s
existing processes effectively facilitate the interconnection of large loads,29 many other
entities support additional reforms addressing large and co-located loads. ISO-NE agrees
that clear rules should be developed, in part based on its existing processes, for
integrating large loads and co-location arrangements onto the transmission system.30
Entities in ISO-NE highlight the unique planning and reliability challenges that large and
co-located loads pose for the region.31 NESCOE states that regulators should prioritize
Conn. Light & Power Co., Docket No. ER26-1158-000 (Mar. 18, 2026) (delegated
order); The Conn. Light & Power Co., Docket No. ER26-1597-000 (Apr. 21, 2026)
(delegated order).
27 Southeast PIOs November 21 ANOPR Comments at 36 (citing NESCOE, Data
Centers and the Power System: A Primer, at 4 (2024), https://nescoe.com/resource-
center/data-centers-primer/).
28 See, e.g., Jon Lamson, Data Center Interest, Opposition on the Rise in New
England, RTO Insider (Apr. 2, 2026), https://www.rtoinsider.com/129446-data-center-
interest-opposition-on-the-rise-new-england/#/; Patrick Anderson, Why RI Now Finds
Itself in the Center of the Data Center Debate, The Providence Journal (Apr. 20, 2026),
https://www.providencejournal.com/story/news/politics/state/2026/04/20/ri-debates-
building-and-regulating-data-centers-starting-in-smithfield/89594859007/; Sabrina
Shankman, An Economic Opportunity, or an Energy Crisis in Waiting? Data Centers Are
Coming to Massachusetts, Boston Globe (Jun. 6, 2025),
https://www.bostonglobe.com/2025/06/06/science/an-economic-opportunity-or-an-
energy-crisis-waiting-data-centers-are-coming-massachusetts/.
29 See New England Consumer-Owned Systems November 21 ANOPR Comments
at 22 (“To the extent that large-load development accelerates in New England, the region
already has a mature, carefully tailored set of interconnection requirements that reflect
unique reliability characteristics, transmission constraints, and long-standing market
design.”); see also Eversource November 21 ANOPR Comments at 5-6 (“In Eversource’s
experience, prospective large loads overwhelmingly prefer the retail construct.”).
30 ISO-NE November 21 ANOPR Comments at 2.
31 NESCOE November 21 ANOPR Comments at 2-3, 12; New England
Consumer-Owned Systems November 21 ANOPR Comments at 26-27 (noting that the
PDF page 11
Docket No. EL26-72-000
- 11 -
maintaining grid reliability and energy affordability.32 New England Consumer-Owned
Systems assert that the Commission should adopt safeguards to ensure that large and
co-located loads are integrated onto the transmission system without introducing
unacceptable reliability concerns.33 Additionally, National Grid states that its own
experience in New England has confirmed the need to define the rules for large load
interconnections, and supports reforms that capture the efficiencies of generation paired
with electrically proximate large load.34
Some entities are also concerned with protecting ratepayers from cost shifts
caused by large and co-located loads.35 National Grid states that innovative solutions to
integrate large loads will reduce the amount of system upgrades required, which will in
turn benefit existing ratepayers by exposing them to less risk of higher costs associated
with new upgrades.36 Other commenters argue that the Commission should provide
mechanisms for additional load flexibility.37 New England Consumer-Owned Systems
also highlight the potential for co-location arrangements to avoid certain wholesale
charges, including transmission and ancillary services charges.38
Moreover, many commenters in the ANOPR proceeding filed persuasive
comments documenting, generally, the need for clear and consistent tariff provisions to
risks of large load are particularly acute in New England because ISO-NE has significant
transmission constraints and has a system peak that is only approximately 30,000 MW,
such that the consequences of large or co-located loads improperly operating could be
severe).
32 NESCOE November 21 ANOPR Comments at 2-3.
33 New England Consumer-Owned Systems November 21 ANOPR Comments at
26-27.
34 National Grid November 21 ANOPR Comments at 2-3, 17-18.
35 Maine Public Advocate November 21 ANOPR Comments at 2; New England
Consumer-Owned Systems November 21 ANOPR Comments at 4, 19-20; State Entities
November 21 ANOPR Comments at 7-8.
36 National Grid November 21 ANOPR Comments at 2-3.
37 Maine Public Advocate November 21 ANOPR Comments at 4-5; State Entities
November 21 ANOPR Comments at 8.
38 New England Consumer-Owned Systems November 21 ANOPR Comments at
13-14.
PDF page 12
Docket No. EL26-72-000
- 12 -
ensure regulatory and process certainty, fairness and consistency, and efficiency as large
and co-located loads are added to the transmission system in increasing numbers.39
There is also broad support for rules that help to ensure that other transmission customers
are not unfairly burdened with additional costs or reliability impacts as large and co-
located loads interconnect to the transmission system.40 In addition, many ANOPR
commenters highlighted the need to efficiently integrate large loads, particularly data
centers, to support national security priorities and economic development.41
B.
Recent Proceedings Addressing Large and Co-Located Loads
Over the past year, the Commission has begun to address, both sua sponte and in
response to complaints and FPA section 20542 filings, the growing use of co-location
arrangements.43 The Commission’s orders in those proceedings have addressed the need
39 See, e.g., AI Supply Chain Alliance November 21 ANOPR Comments at 2;
Calibrant November 21 ANOPR Comments at 1-3; CEBA November 21 ANOPR
Comments at 9-11; Constellation November 21 ANOPR Comments at 6; DCC November
21 ANOPR Comments at 3-4; ECA November 21 ANOPR Comments at 7-11; EPSA
November 21 ANOPR Comments at 4-6; Infrastructure Masons December 5 ANOPR
Comments at 4-7; Microsoft November 21 ANOPR Comments at 9-10; National Grid
November 21 ANOPR Comments at 7; ODEC December 5 ANOPR Comments at 2-4;
R Street November 21 ANOPR Comments at 3; Switch December 5 ANOPR Comments
at 3; Tract November 21 ANOPR Comments at 5; Vantage November 21 ANOPR
Comments at 5-6; Vistra December 5 ANOPR Comments at 1-2.
40 See, e.g., APPA November 21 ANOPR Comments at 6; Buckeye November 21
ANOPR Comments at 17; Exelon November 21 ANOPR Comments at 10; Kansas
Commission November 21 ANOPR Comments at 12; NCSL November 21 ANOPR
Comments at 1; NRECA November 21 ANOPR Comments at 8-9; NY UIU November
21 ANOPR Comments at 3; OCC November 21 ANOPR Comments at 9; Oklo
December 5 ANOPR Comments at 3; Southeast PIOs December 5 ANOPR Comments
11-15; State Entities November 21 ANOPR Comments at 7-8; Tri-State November 21
ANOPR Comments at 8; UCS November 21 ANOPR Comments at 9-11; U.S.
Representatives November 21 ANOPR Comments at 1.
41 See, e.g., AI Supply Chain Alliance November 21 ANOPR Comments at 2;
DCC November 21 ANOPR Comments at 3; ECA November 21 ANOPR Comments at
6; Geronimo November 21 ANOPR Comments at 1-2; Google November 21 ANOPR
Comments at 2-3; Verrus December 5 ANOPR Comments at 2.
42 16 U.S.C. § 824d.
43 See PJM Show Cause Order, 190 FERC ¶ 61,115; PJM Co-Location Order,
193 FERC ¶ 61,217, order on reh’g, PJM Co-Location Rehearing Order, 195 FERC ¶
PDF page 13
Docket No. EL26-72-000
- 13 -
for clear and consistent tariff provisions regarding the rates, terms, and conditions of
service that apply to co-location arrangements and for transmission services that reflect
Eligible Customers taking transmission service on behalf of co-located loads and load
with behind the meter generation that are willing and able to limit their energy
withdrawals from the transmission system under certain conditions. Several other
Commission proceedings have addressed the challenges of integrating large loads onto
the transmission system, including the need for clear and consistent tariff provisions
regarding the provision of transmission service to Eligible Customers on behalf of large
loads and for interconnection customers serving electrically proximate large load. As
explained below, these proceedings provide examples that will help to ensure that
jurisdictional transmission service is provided in a manner that is just and reasonable and
maintains reliability as large loads are integrated onto the transmission system and co-
location arrangements become more common. It is in this context that the Commission
now considers whether ISO-NE’s Tariff remains just and reasonable without similar
provisions.
1.
PJM Co-Location Proceedings
On February 20, 2025, the Commission initiated a show cause proceeding against
PJM and the PJM transmission owners regarding the lack of tariff provisions addressing
with sufficient clarity or consistency the rates, terms, and conditions of service that apply
to co-location arrangements.44 The Commission explained when initiating that
proceeding that the absence of such provisions may leave entities unable to determine
what steps they can or must take to effectuate co-location arrangements of various
configurations and how to do so in a manner that is just and reasonable.45 On December
18, 2025, the Commission found that PJM’s tariff was indeed unjust and unreasonable
because it does not contain provisions addressing with sufficient clarity or consistency
the rates, terms, and conditions of service that apply to interconnection customers serving
co-located load and Eligible Customers taking transmission service on behalf of co-
located load.46
61,209; SPP HILL Order, 194 FERC ¶ 61,031; SPP CHILLS Order, 195 FERC ¶ 61,196.
44 See PJM Show Cause Order, 190 FERC ¶ 61,115.
45 Id. P 74. The PJM Show Cause Order defined co-located load as a
“configuration [that] refers to end-use customer load that is physically connected to the
facilities of an existing or planned Customer Facility on the Interconnection Customer’s
side of the Point of Interconnection (‘POI’) to the PJM Transmission System.” Id. P 3
n.4.
46 PJM Co-Location Order, 193 FERC ¶ 61,217.
PDF page 14
Docket No. EL26-72-000
- 14 -
Specifically, the Commission found that the PJM tariff was unjust and
unreasonable because there is a lack of sufficient clarity or consistency as to the rates,
terms, and conditions of service that apply to interconnection customers serving
co-located load.47 The Commission also found that PJM’s tariff was unjust and
unreasonable because it does not include transmission services that reflect Eligible
Customers taking transmission service on behalf of co-located loads that are willing and
able to limit their energy withdrawals from the transmission system under certain
conditions.48 Additionally, the Commission found that PJM’s behind the meter
generation rules were no longer just and reasonable.49 The Commission directed PJM to
file a compliance filing to revise its tariff: (1) to set forth specific terms and conditions
that an interconnection customer in PJM seeking to serve co-located load must follow in
order to effectuate a co-location arrangement;50 (2) to require that the Eligible Customer
taking transmission service on behalf of co-located load takes one of three transmission
services: (a) network integration transmission service (NITS) or a new interim, non-firm
transmission service while network upgrades to provide full NITS service are constructed
(interim NITS); (b) a new firm contract demand transmission service; or (c) a new non-
firm contract demand transmission service;51 (3) to revise the behind the meter generation
rules and implement a transition process for existing behind the meter generation
participants;52 and (4) to make several clarifications on how certain aspects of PJM’s
generator interconnection process apply to interconnection customers seeking to serve
co-located load.53
On June 18, 2026, concurrently with the instant order, the Commission issued an
order modifying the discussion in the PJM Co-Location Order and setting aside the order
in part; accepting in part and rejecting in part PJM’s compliance filing, and directing a
further compliance filing; and establishing as just and reasonable certain rates, terms, and
47 Id. P 176.
48 Id. P 177.
49 Id. P 179.
50 Id. PP 187-192, 225-230.
51 Id. PP 193-218. The Commission also established a paper hearing to determine
the just and reasonable rates, terms, and conditions for the new transmission services. Id.
PP 219-20.
52 Id. PP 221-224.
53 Id. PP 161, 231-36.
PDF page 15
Docket No. EL26-72-000
- 15 -
conditions for the new transmission services (i.e., interim NITS, firm contract demand
transmission service, and non-firm contract demand transmission service).54
2.
SPP High Impact Large Load and High Impact Large Load
Generation Assessment Processes
On January 14, 2026, the Commission accepted revisions to SPP’s tariff to add a
high impact large load (HILL) study process and High Impact Large Load Generation
Assessment (HILLGA) process.55 SPP’s tariff revisions established HILLs as a new
category of load;56 imposed enhanced study requirements to enable SPP to assess the
HILL’s reliability impacts on the transmission system;57 and created additional, ongoing
operational requirements for transmission customers serving HILLs to ensure continued
reliability of the transmission system.58 The tariff revisions also established the HILLGA
54 PJM Co-Location Rehearing Order, 195 FERC ¶ 61,209 at PP 7-9. PJM’s
compliance filing proposing revisions in response to the Commission’s directives
regarding clarification that certain aspects of PJM’s generator interconnection process
apply to interconnection customers seeking to serve co-located load was accepted in part
on April 16, 2026. PJM Interconnection, L.L.C., 195 FERC ¶ 61,030 (2026).
55 SPP HILL Order, 194 FERC ¶ 61,031 at PP 61, 64.
56 SPP defines a HILL as:
A new commercial or industrial load, or increase in
commercial or industrial load, at a single site connected
through one or more shared Points of Interconnection (POIs)
or delivery points, where such load is either (1) 10 MW or
more if connected to the Transmission System at a voltage
level less than or equal to 69 [kilovolts (kV)]; or (2) 50 MW
or more if connected to the Transmission System at a voltage
level greater than 69 kV. An Electric Storage Resource is not
considered a HILL.
SPP, Open Access Transmission Tariff, Sixth Revised Vol. No. 1, pt. I, § 1 (Definitions
H) (1.0.0).
57 SPP HILL Order, 194 FERC ¶ 61,031 at PP 13-17 (explaining that the HILL
process requires up to three additional studies beyond those required of all transmission
service requests for transmission customers requesting to add or modify a delivery point
associated with a HILL, including a HILL delivery point study, HILL supplemental load
connection study, and potential supplemental Electromagnetic Transient study).
58 Id. P 18 (explaining that market participants registering a HILL must (1) follow
PDF page 16
Docket No. EL26-72-000
- 16 -
process, a new generator interconnection service and related interconnection process to
facilitate the prompt interconnection of generating facilities that are specifically identified
for, and limited to, serving a HILL and are located no more than two substations away
from the HILL.59
The Commission stated that SPP demonstrated that the “unprecedented growth in
large loads in the SPP region presents significant and unique operational and planning
challenges.”60 The Commission found that SPP demonstrated that its proposed HILL
process was a just and reasonable approach for integrating transmission customers’ new
large loads onto SPP’s transmission system in a reliable manner.61 The Commission
found that it was reasonable to impose additional study requirements and other proposed
requirements given the unique operating characteristics of HILLs. The Commission
further found that the proposed study requirements would ensure the reliable integration
of the transmission customer’s HILLs onto SPP’s transmission system and would provide
SPP with information about their impact on SPP’s transmission system, including the
transmission system’s ability to withstand and control disturbances by the HILL at the
point of interconnection.62 In addition, the Commission found that the proposed study
deposits would discourage speculative HILL study requests.63 Finally, the Commission
all nonconforming load requirements (e.g., additional load forecast requirements); (2)
provide load data via telemetry in real time; (3) have remote capability to disconnect the
load from the transmission system made available to the transmission operator; (4) have
an up/down ramp rate not exceeding 20 MW per minute unless otherwise directed; (5)
include additional information with registration; and (6) not have withdrawals from the
transmission system without appropriate transmission service); id. P 19 (explaining that
the transmission owner, at the transmission customer’s expense, must install a phasor
measurement unit or similar equipment); id. PP 20-21 (explaining that the transmission
customer will be required to comply with ride-through requirement guidelines).
59 Id. P 27 (explaining that, under the HILLGA process, SPP proposes to study
HILLGA requests to determine whether any network upgrades are needed to
accommodate the generating facility’s injection to the local area); id. P 32 (explaining
that SPP will grant HILLGA customers a new type of interconnection service, load
limited resource interconnection service, which grants limited interconnection service
solely to serve the associated HILL).
60 Id. P 60.
61 Id. P 61.
62 Id. P 62.
63 For the HILL delivery point study, SPP required a $10,000 non-refundable
application fee and a $100,000 study deposit, with an additional $200,000 study deposit if
PDF page 17
Docket No. EL26-72-000
- 17 -
concluded that the proposed ongoing reliability requirements would allow SPP to
maintain reliable operation of its transmission system by increasing SPP’s visibility,
providing necessary data, and imposing real-time operational safeguards for HILLs.64 In
accepting HILLGA, the Commission found that “SPP’s HILLGA process reasonably
provides a flexible, expedited, and separate serial interconnection process that will
facilitate the prompt interconnection of generating facilities that are limited to serving a
HILL in the same local area.”65
3.
SPP Conditional High Impact Large Load Service
On June 5, 2026, the Commission accepted revisions to SPP’s tariff to add a new
type of non-firm transmission service, conditional high impact large load service
(CHILLS).66 CHILLS allows transmission customers serving HILLs to reliably receive
transfers of energy until sufficient designated resources and/or network upgrades are in
place to support long-term, firm transmission service.67 CHILLS is an as-available
transmission service that will transfer energy to designated points of delivery to serve the
portion of a HILL eligible to receive CHILLS, subject to curtailment and interruption.68
CHILLS has a maximum term of seven years, which is intended to incentivize
transmission customers seeking CHILLS to obtain the designated resources and/or
complete the network upgrades needed to procure long-term firm transmission service
through existing tariff processes.69
The Commission found that SPP had shown that unprecedented growth in large
loads presents significant and unique operational and planning challenges.70 The
Commission also found that SPP’s ability to add HILLs to its transmission system in a
an Electromagnetic Transient study was also required. Id. P 15. For the HILL
supplemental load connection study, SPP allows the host transmission owner to require a
$25,000 study deposit. Id. P 16.
64 Id. P 63.
65 Id. P 64.
66 SPP CHILLS Order, 195 FERC ¶ 61,196 at P 1.
67 Id. P 7.
68 Id. PP 9-10.
69 Id. P 9.
70 Id. P 84.
PDF page 18
Docket No. EL26-72-000
- 18 -
timely manner may be limited due to delays in obtaining sufficient designated resources
and completing network upgrades needed to provide long-term firm transmission service
to such load.71 The Commission concluded that CHILLS is a just and reasonable and not
unduly discriminatory or preferential approach to addressing the need to expeditiously
interconnect and provide transmission service to new HILLs, while maintaining the
reliable operation of SPP’s transmission system.72
II.
ISO-NE’s Existing Processes
A.
Existing Tariff Processes
ISO-NE’s Tariff sets forth the processes by which an Eligible Customer may
request Regional Network Service, Local Network Service, and firm or non-firm Local
Point-to-Point Service. Regional Network Service73 is transmission service over Pool
Transmission Facilities (PTF) provided by ISO-NE to Network Customers74 to serve
their loads.75 Network Customers taking Regional Network Service must also take Local
Network Service.76
In order for ISO-NE to provide Regional Network Service to any Eligible
Customer, (1) the Eligible Customer must submit an application for Regional
Transmission Service (which includes a request to recognize a new Regional Network
Load); (2) the Eligible Customer and ISO-NE complete the technical arrangements set
forth in sections II.16.3 and II.16.4 of ISO-NE’s Tariff; and (3) the Eligible Customer
must either have an executed (or a filed unexecuted) Market Participant Service
71 Id.
72 Id.
73 ISO-NE Tariff, § II.11 (Nature of Regional Network Service) (2.0.0).
74 Network Customer is a “Transmission Customer receiving [Regional Network
Service] or [Local Network Service].” Id. § I.2.2. A Transmission Customer is “any
Eligible Customer that (i) executes, on its own behalf or through its Designated Agent, an
[Market Participant Service Agreement] or [Transmission Service Agreement]” or
requests to file an unexecuted agreement. Id.
75 PTF are transmission facilities rated 69 kV or above required to allow energy
from significant power sources to move freely on the New England Transmission System
owned by Participating Transmission Owners, and operated by ISO-NE. See id. § II.49
(Definition of PTF) (2.0.0).
76 See id. § II.23 (Application of Part II.B to Transmission Customers) (0.0.0).
PDF page 19
Docket No. EL26-72-000
- 19 -
Agreement, or have an executed (or request a filed unexecuted) Service Agreement for
Regional Network Service.77
When an Eligible Customer requests Regional Network Service, ISO-NE reviews
the effect of the requested service on the reliability requirements to meet existing and
pending obligations of any affected transmission owner(s) and on the obligations of the
particular Participating Transmission Owner and determines whether evaluation as part of
a Cluster Study is needed.78 The Cluster Study is also used to process all requests for
generator interconnection service, as well as to process requests made under ISO-NE’s
Elective Transmission Upgrade Interconnection Procedures.79 An Eligible Customer
seeking transmission service on behalf of load must execute a Cluster Study Agreement
and submit it to ISO-NE, together with study and commercial readiness deposits and
technical data required of new requests for Network Resource Interconnection Service by
Schedule 22 (for requests greater than 20 MW) and Schedule 23 (for requests up to 20
MW).80 The Cluster Study consists of a short circuit analysis, a stability analysis, a
power flow analysis, such as electromagnetic transient analysis, including thermal
analysis and voltage analysis, a system protection analysis, and any other analyses that
are deemed necessary by ISO-NE in consultation with the interconnecting transmission
owner.81
If ISO-NE finds that it is likely that a Direct Assignment Facility82 will be
required, a portion of the Cluster Study evaluation shall be performed by the affected
77 Id. § II.16 (Initiating Service) (1.0.0); id. attach. B (Service Agreement for
Regional Network Service) (1.0.0).
78 Id. § II.19 (Study Procedures for Regional Network Service Requests) (3.0.0),
II.19.1, II.19.2.
79 Id. Schedule 25 (Elective Transmission Upgrade Interconnection Procedures)
(12.0.0), § 3.3.2.
80 Id. § II.19.1; see also id. Schedule 22 (Large Generator Interconnection
Procedures) (26.0.0), § 7.2.; id. Schedule 23 (Small Generator Interconnection
Procedures) (23.0.0), § 7.2.
81 Id. Schedule 22, § 7.3.
82 Direct Assignment Facilities are defined in part as “facilities or portions of
facilities that are constructed for the sole use/benefit of a particular Transmission
Customer requesting service under the [Tariff] or a Generator Owner requesting an
interconnection. Direct Assignment Facilities . . . shall be paid for by the [Transmission]
Customer.” Id. § I.1.2.
PDF page 20
Docket No. EL26-72-000
- 20 -
Participating Transmission Owner(s), subject to review by ISO-NE.83 If ISO-NE
determines that network upgrades are needed to accommodate the Eligible Customer’s
request for Regional Network Service, ISO-NE, the transmission owner, or a third party
consultant for the interconnection customer will conduct a Facilities Study.84 The costs
of the network upgrades needed to accommodate the Eligible Customer’s request for
Regional Network Service will be allocated to the Eligible Customer in the same manner
that the costs of upgrades to accommodate generating facilities are allocated pursuant to
Schedule 11 of the Tariff.85 The cost responsibility for network upgrades identified as
needed to support requests for Regional Transmission Service are allocated to the
transmission Customer as follows: (1) if the network upgrade is found to be a Cluster
Enabling Transmission Upgrade,86 the costs are allocated based on the request’s relative
distribution impact in the cluster;87 or (2) if the network upgrade is not a Cluster Enabling
Transmission Upgrade, the costs for System Network Upgrades are allocated based on
the request’s proportional impact on the need for such upgrade, and the costs for
Substation Network Upgrades shall be allocated first per capita for each Interconnection
Facility interconnecting to the substation at the same voltage level, then per capita to each
generating facility or Elective Transmission Upgrade Interconnection Customer sharing
the Interconnection Facility.88
Network Customers must follow certain operating arrangements, terms, and
conditions.89 For example, the Tariff requires that ISO-NE, the applicable Participating
83 Id. § II.19.1.
84 Id. § II.19.2.
85 Id. § II.19.4.
86 A Cluster Enabling Transmission Upgrade is new significant transmission line
infrastructure that is identified in the Cluster Enabling Transmission Upgrade Regional
Planning Study conducted in accordance with Tariff Section II, Attachment K. A Cluster
Enabling Transmission Upgrade Regional Planning Study is, in turn, carried out to enable
interconnection requests when either (1) two or more interconnection requests have been
withdrawn from a Cluster Study Process in the same electrical part of the New England
control Area, or (2) procurements are underway for resources in the same electrical part
of the New England Control Area. See id. Schedule 22, §§ 1, 4.2.1; id. Schedule 23,
§§ 1, 4.2.1; id. Schedule 25, §§ 1, 4.2.1.
87 Id. Schedule 11 (6.0.0), § 5(i).
88 Id. Schedule 11, § 5(ii)(1)(a-b).
89 Id. § II.22 (Operating Arrangements) (2.0.0).
PDF page 21
Docket No. EL26-72-000
- 21 -
Transmission Owner(s), and the Network Customer operate and maintain equipment
necessary for integrating the Network Customer within the PTF (including, but not
limited to, remote terminal units, metering, communications equipment, and relaying
equipment).90 The Network Customer also has a reporting obligation to respond
promptly and completely to ISO-NE’s and the applicable Participating Transmission
Owners’ reasonable requests for information, including, but not limited to, data necessary
for operations, maintenance, regulatory requirements, and analysis.91 Under emergency
system operations, the Network Customer’s equipment and facilities are subject to all
applicable emergency operation standards required of and by ISO-NE to operate in an
interconnected transmission network.92 The Tariff also allows ISO-NE to take whatever
actions it deems necessary during emergency operating conditions to: (i) preserve the
integrity of its transmission system; (ii) limit or prevent damage; (iii) expedite restoration
of service; or (iv) preserve public safety.
Network Customers pay a charge that covers both local transmission and the costs
of regional transmission. For local transmission costs, Network Customers pay a
monthly rate calculated by determining a cost allocation factor based on the customer’s
coincident peak for the month multiplied by the Local Network rate for the area in which
the customer takes service.93 For regional transmission charges, Network Customers are
allocated a Regional Network Service charge, which is determined by combining the
annual transmission revenue requirements for the transmission owners of regional PTF
and dividing by the average 12-month coincident peak for the region.94
Local Network Service and Local Point-To-Point Service are Local Transmission
Services, which are transmission services provided by Participating Transmission Owners
over non-PTFs to transmission customers.95 Eligible Customers may request Local
Transmission Service through the Local Service processes in Schedule 21 of the ISO-NE
90 Id. § II.22.2.
91 Id. § II.22.2(c).
92 Id. § II.22.2(i).
93 Id. § II.21 (Rates and Charges) (8.0.0), II.21.1-2.
94 Id. Schedule 9 (Regional Network Service) (5.0.0). PTFs include both existing
transmission assets that benefit the regional network as well as new regional transmission
planned to meet reliability and economic needs. Id. § II.49.
95 Id. Schedule 21 (Local Service) (15.0.0), §§ I (Local Point-to-Point Service), II
(Local Network Service). Non-PTFs are local transmission facilities owned and operated
by local transmission owners.
PDF page 22
Docket No. EL26-72-000
- 22 -
Tariff. Each Participating Transmission Owner has its own Schedule 21 provisions filed
in the ISO-NE Tariff specific to that Participating Transmission Owners’ facilities.
Studies performed to support Local Service requests are administered by the applicable
Participating Transmission Owner as the transmission service provider. The transmission
customer must agree to compensate the Participating Transmission Owner for any
necessary transmission facility additions.96 Local Network Upgrades and Direct
Assignment Facilities costs are charged to the transmission customer.97 Transmission
customers must execute a Local Service Agreement prior to initiating Local Transmission
Service.98
In addition, Market Participants and Participating Transmission Owners must
submit to ISO-NE for approval a Proposed Plan Application99 for: (i) any additions or
changes to resources or facilities under its control; and (ii) any new or materially changed
plan for action, excluding deactivations or reductions in capacity for resources, that may
have a significant adverse impact on the regional power system.100 ISO-NE then
conducts a “do no harm” reliability review to ensure the proposal does not have a
significant adverse reliability impact prior to allowing the project to proceed. In
performing electric planning and reliability studies, ISO-NE relies on the CELT Report
as the primary source of assumptions. ISO-NE’s Transmission Planning Technical Guide
indicates that specific large proposed loads, such as data centers and large green house
facilities, are not generally included in the CELT load forecast but may be included in a
study such as the Proposed Plan Application depending on “the degree of certainty that
96 Id. Schedule 21, §§ I.14, II.7.d.
97 Id. Schedule 21, §§ I.1.e, II.9.
98 Id. Schedule 21, §§ I.4.a.vi, II.3.a, attach. A (Form of Local Service
Agreement).
99 See ISO-NE, Proposed Plan Applications, https://www.iso-ne.com/system-
planning/transmission-planning/proposed-plan-applications.
100 ISO-NE Tariff, § I.3 (Obligations of MPs and Other Customers) (10.0.0),
§ I.3.9.
PDF page 23
Docket No. EL26-72-000
- 23 -
the large proposed load will come to fruition.”101 As we note above, however, a forecast
of large load capacity was included in the latest 2026-2035 CELT Report.102
ISO-NE processes large generator interconnection requests under Schedule 22 of
its Tariff (Standard Large Generator Interconnection Procedures) and small generator
interconnection requests under Schedule 23 of its Tariff (Standard Small Generator
Interconnection Procedures).103 ISO-NE processes both small and large generators in a
single, integrated Cluster Study process. First, ISO-NE conducts a Cluster Study to
evaluate the impact of the proposed interconnection on the reliability and operation of the
New England Transmission System to identify the interconnection facilities and network
upgrades that are required to reliably interconnect the generating facilities in that Cluster
Study and a non-binding good faith estimate of cost responsibility.104 Next, ISO-NE may
conduct a Cluster Restudy if one or more interconnection customers withdraw from the
cluster, the scope of which is consistent with the scope of an initial Cluster Study.105
Finally, ISO-NE may conduct an Interconnection Facilities Study for each
interconnection request to specify and provide a non-binding estimate of the cost of the
equipment, engineering, procurement, and construction work needed to implement the
conclusions of the Cluster Study report and electrically connect the interconnection
facilities to the transmission system, unless the interconnection customer(s) elects to
waive the facilities study.106
Pursuant to the Tariff, an interconnection customer may request, and ISO-NE may
provide, provisional interconnection service enabling the receipt of electric energy
capability from the generating facility at the point of interconnection on a limited and
temporary basis prior to completion of requisite interconnection facilities, network
101 See ISO-NE, Transmission Planning Technical Guide § 2.2.3 (May 23, 2025),
https://www.iso-ne.com/static-
assets/documents/100023/transmission_planning_technical_guide_rev8_3_final.pdf.
102 See supra P 8.
103 ISO-NE Tariff, Schedule 22 (26.0.0), § 7.2.; id. Schedule 23 (23.0.0), § 7.2.
104 Id. Schedule 22, § 7.3; see also id. Schedule 23, § 7.3 (Scope of Cluster Study).
105 Id. Schedule 22, § 7.5 (Cluster Study Restudies); see also id. Schedule 23, § 7.5
(Cluster Study Restudies).
106 Id. Schedule 22, §§ 8.1 (Interconnection Facilities Study Agreement), 8.2
(Scope of Interconnection Facilities Study); see also id. Schedule 23, §§ 8.1
(Interconnection Facilities Study Agreement), 8.2 (Scope of Interconnection Facilities
Study).
PDF page 24
Docket No. EL26-72-000
- 24 -
upgrades, distribution upgrades, or system protection facilities.107 In evaluating a request
for provisional interconnection service, ISO-NE and the Interconnecting Transmission
Owner shall determine, through available studies or additional studies as necessary,
whether stability, short circuit, thermal, and/or voltage issues would arise if
interconnection customer interconnects without modifications to the generating facility or
the New England Transmission System. An interconnection customer may also request,
and ISO-NE may provide, surplus interconnection service for unused capability of
interconnection service at an existing point of interconnection.108 Studies for surplus
interconnection service may consist of reactive power, short circuit/fault duty, stability
analyses, and/or other appropriate studies, and steady-state (thermal/voltage) analyses
may also be performed as necessary to ensure that all required reliability conditions are
studied.109
B.
Recent Stakeholder Proceedings in ISO-NE
ISO-NE recently indicated that it is engaging with transmission owners regarding
potential large load interconnections, and that it is communicating with states to
understand any potential policies creating incentives for data centers and to share
information on how ISO-NE would review such proposed developments.110
Additionally, ISO-NE explained that it participates in several interregional initiatives on
large loads as well as the upcoming NERC Large Load Task Force.111 ISO-NE’s
Consumer Liaison Group met on June 2, 2026 to discuss data center issues.112 Finally,
although not directly related to large and co-located loads, ISO-NE is currently engaged
with stakeholders to better address seasonal reliability challenges and to more accurately
reflect resource contributions to resource adequacy.113
107 Id. Schedule 22, app. 11, art. 5.9.2 (Provisional Interconnection Service); see
also id. Schedule 23, app. 11, art. 1.6.3 (Provisional Interconnection Service).
108 Id. Schedule 22, § 3.3 (Utilization of Surplus Service); see also id. Schedule 23
§ 3.3 (Utilization of Surplus Interconnection Service).
109 Id. Schedule 22, § 3.3.1; see also id. Schedule 23, § 3.3.1.
110 ISO-NE Letter at 1-2.
111 Id. at 3.
112 Jon Lamson, ISO-NE Consumer Liaison Group Talks Data Center Impacts,
RTO Insider (June 7, 2026), https://www.rtoinsider.com/133689-iso-ne-consumer-
liaison-group-talks-data-center-impacts/.
113 See ISO-NE, Capacity Auction Reforms Key Project, https://www.iso-
PDF page 25
Docket No. EL26-72-000
- 25 -
While we are encouraged by ISO-NE’s stakeholder efforts, and by its initial
attention to the pressing concerns associated with large and co-located loads114 and to the
Secretary’s interest in these issues,115 we are initiating this FPA section 206 proceeding
in order to ensure that ISO-NE’s ongoing processes generate reforms that are sufficiently
timely and comprehensive to address the concerns we today identify. As such, and as the
Commission explained in the April Order Regarding Intent to Act, we find that the
Commission must now take further action to ensure that ISO-NE promptly proposes
revisions to ensure that its Tariff remains just and reasonable.
III.
Discussion
Based on the discussion below, pursuant section 206 of the FPA, we direct
ISO-NE and the Participating Transmission Owners, within 60 days of the date of this
order, to either:
(1) show cause as to why the Tariff remains just and reasonable and not unduly
discriminatory or preferential without provisions addressing:
(a) the application process, study procedures, and ongoing operational
requirements that apply to Eligible Customers seeking transmission service
on behalf of large loads;
(b) additional transparency concerning the network upgrade costs to
provide transmission service to Eligible Customers on behalf of large loads,
a pro forma cost recovery agreement between ISO-NE, the relevant
transmission owner and Eligible Customer taking transmission service on
behalf of the large load to mitigate the risk of cost shifting among
transmission customers, and a mechanism to ensure such payments are
appropriately credited towards transmission owners’ transmission revenue
requirements consistent with the Commission’s cost-of-service regulations;
(c) the rates, terms, and conditions of service that apply to co-location
arrangements;
(d) transmission services that reflect Eligible Customers taking
transmission service on behalf of co-located loads, load with behind the
ne.com/committees/key-projects/capacity-auction-reforms-key-project.
114 See id. at 1.
115 See supra PP 6-7.
PDF page 26
Docket No. EL26-72-000
- 26 -
meter generation, and flexible large loads that are willing and able to limit
their use of the transmission system under certain conditions; and
(e) the rates, terms, and conditions of service applicable to interconnection
customers serving electrically proximate large load or co-located load; or
(2) explain what changes to the Tariff would remedy the identified concerns if the
Commission were to determine that the Tariff has in fact become unjust and
unreasonable or unduly discriminatory or preferential and, therefore, proceeds to
establish a replacement Tariff.
We also direct ISO-NE to submit, within 30 days of the date of issuance of this
order, an informational report on how ISO-NE intends to ensure that adequate generation
will be available to serve existing and new large loads.
Interested entities may respond within 30 days of ISO-NE’s and the Participating
Transmission Owners’ filings, addressing either or both of: (1) whether the existing
Tariff remains just and reasonable and not unduly discriminatory or preferential; and
(2) if not, what changes to the Tariff should be implemented as replacement rates.
We recognize that ISO-NE and/or the Participating Transmission Owners (to the
extent the matters addressed herein implicate aspects of the Tariff over which they have
the filing rights) may elect to address some or all of the issues discussed in this order by
proposing revisions to the Tariff pursuant to their applicable FPA section 205 filing
rights. We strongly encourage this. Although both the Secretary’s ANOPR and our own
Order Regarding Intent to Act expressly recognized (and indeed encouraged) that
possibility,116 no such filings were received from ISO-NE by the Commission prior to the
issuance of this order. Should ISO-NE and/or the Participating Transmission Owners
elect to make such filings in response to this order, those filings should state explicitly
that the proposals are being submitted under FPA section 205. Should ISO-NE and/or
the Participating Transmission Owners submit a filing under FPA section 205, they
should also explain which of the Commission’s above directives their filing addresses
and how it resolves them. Additionally, any such filing should provide a reasoned
explanation for how the proposal will avoid disrupting existing commercial arrangements
and clearly identify a reasonable effective date that accommodates such existing
commercial arrangements.
The Commission will consider requests from ISO-NE and/or the Participating
Transmission Owners to hold, for up to 90 days, all or certain aspects of this FPA section
206 proceeding in abeyance, including the deadline to respond to this order. Any such
abeyance, which will begin as of the deadline to respond to this order, would be
116 See ANOPR at P 32; Order Regarding Intent to Act, 195 FERC ¶ 61,045 at P 5.
PDF page 27
Docket No. EL26-72-000
- 27 -
considered to provide ISO-NE and the Participating Transmission Owners time while
they work through the stakeholder processes to develop FPA section 205 filings to revise
the Tariff to address the issues raised in this order. Requests for a full or partial
abeyance117 should be submitted prior to the deadline to respond to this order,
specifically within 45 days of issuance of this order, to allow time for the Commission to
act on the abeyance request. We emphasize that we will not grant such abeyances
reflexively, that any abeyance will be limited to 90 days, and that we will look with great
disfavor toward requests to extend the abeyance period. We anticipate that successful
abeyance requests, if any, will include both (1) a robust description of the content of a
potential future filing under FPA section 205 and (2) a reasoned and specific explanation
of when such a filing is expected to be made.
In cases where, as here, the Commission institutes a section 206 investigation on
its own motion, section 206(b) of the FPA requires that the Commission establish a
refund effective date that is no earlier than the date of the publication by the Commission
of notice of its intention to initiate such proceeding nor later than five months after the
publication date. In such cases, in order to give maximum protection to customers, and
consistent with our precedent, we have historically tended to establish the section 206
refund effective date at the earliest date allowed by section 206, and we do so here as
well.118 That date is the date of publication of notice of initiation of this proceeding in
the Federal Register.
A.
Transmission Service to Eligible Customers on Behalf of Large Loads
We today make a preliminary finding that ISO-NE’s Tariff appears to be unjust
and unreasonable because it lacks provisions that address, with sufficient clarity and
consistency, how ISO-NE and/or the Participating Transmission Owners will timely
study (i.e., within 60-90 days of receiving the request) the provision of transmission
service to Eligible Customers on behalf of large loads.119
117 A partial abeyance may be appropriate to the extent ISO-NE is developing FPA
section 205 filings in response to only a subset of the directives in this order. For any
remaining directives, we expect a response to this order within the 60-day deadline set
forth herein.
118 See, e.g., Idaho Power Co., 145 FERC ¶ 61,122 (2013); Canal Elec. Co.,
46 FERC ¶ 61,153, order on reh’g, 47 FERC ¶ 61,275 (1989).
119 As discussed below, our findings here also apply to the study process for
unbundled retail transmission service requests by end-use large load customers, as
allowed by state law or voluntary utility rules.
PDF page 28
Docket No. EL26-72-000
- 28 -
Throughout this order, we use the phrase “the provision of transmission service to
Eligible Customers on behalf of large loads” to encompass the provision of new,
modified, or additional jurisdictional transmission service to Eligible Customers on
behalf of large loads. We note that this phrase is not limited to instances where an
Eligible Customer submits an application to request new transmission service. It also
includes instances where an Eligible Customer requests a new or modified point of
delivery to serve a large load, where a large load seeks a new or modified delivery point
as an unbundled retail transmission service customer, or where large loads are otherwise
included in an Eligible Customer’s reported load growth and that Eligible Customer is
taking NITS.
We direct ISO-NE and the Participating Transmission Owners, to the extent the
matters addressed herein implicate aspects of the Tariff over which they have the filing
rights, to explain whether the Tariff remains just and reasonable without an application
process, study procedures, and ongoing operational requirements that address the unique
characteristics and challenges of providing transmission service to Eligible Customers on
behalf of large loads, or to propose appropriate Tariff revisions.
We acknowledge that our concerns, described below, may not be as urgent in the
ISO-NE region as in other RTOs/ISOs, but the record indicates that there have been, and
there is potential for an increase in, requests for transmission service by Eligible
Customers on behalf of large loads.120 Additionally, we note that the record indicates
that the more limited growth of large loads in the ISO-NE region may be due to the lack
of a clear and consistent process in ISO-NE’s Tariff for how ISO-NE and/or the
Participating Transmission Owners will study the provision of transmission service to
Eligible Customers on behalf of large loads.121 Given the unique challenges that
providing transmission service to Eligible Customers on behalf of large loads poses for
ensuring just and reasonable rates, as well as for potentially maintaining reliable
operation of the transmission system should the growth of large loads in the region
increase, we remain concerned that ISO-NE’s Tariff appears to be unjust and
unreasonable without provisions addressing how ISO-NE and/or the Participating
Transmission Owners will study the provision of transmission service to Eligible
Customers on behalf of large loads with sufficient clarity and consistency.
1.
Jurisdiction
At the outset, we clarify the principles relating to the Commission’s jurisdiction
over the matters relevant to the integration of large loads onto the transmission system
120 See supra P 8.
121 See National Grid November 21 ANOPR Comments at 2-3 (noting the need to
define “rules of the road” for large load interconnection).
PDF page 29
Docket No. EL26-72-000
- 29 -
and the impacts of large loads on the transmission system. We recognize that rates,
terms, and conditions associated with the addition of and service to large loads implicate
both federal and state interests. We also recognize that resolution of issues related to
large load additions will require the involvement of both federal and state actors,
including the Commission, state public utility commissions, and other state and local
entities. We are encouraged by efforts made at the state level to address issues related to
large load additions that fall within state jurisdiction.122
As discussed below, however, certain aspects of the process for integrating large
loads onto the transmission system fall squarely within the Commission’s exclusive
jurisdiction. Specifically, we find that it is within the Commission’s exclusive authority
to ensure that transmission provider and/or transmission owner tariffs include sufficiently
clear and consistent provisions governing how transmission service to Eligible Customers
on behalf of large loads interconnecting to the transmission system will be studied,
including whether new or upgraded transmission facilities are necessary to provide the
requested transmission service. The Commission has jurisdiction over the study process
for transmission service to both Eligible Customers on behalf of large loads and
unbundled retail transmission service to end-use large load customers where, pursuant to
state law or a public utility’s voluntary offer of such service, the large load is an Eligible
Customer under the transmission provider and/or transmission owner tariffs.123
The Commission is a creature of statute and has jurisdiction over only those
matters that Congress has given it the authority to regulate.124 That authority includes
jurisdiction over the wholesale sale and transmission of electricity in interstate
commerce, including all facilities used for such sale and transmission.125 As relevant
here, the Commission must ensure that the rates, charges, and classifications for such
transmission of electricity—as well as the practices directly affecting such transmission
of electricity—are just and reasonable and not unduly discriminatory or preferential.126
122 See generally NARUC April 14 ANOPR Comments (highlighting action taken
by state public utility commissions related to large loads).
123 Under the pro forma OATT, Eligible Customers include end-use customers
seeking unbundled retail transmission service, pursuant to state law or public utility’s
voluntary offer of such service. Pro forma OATT, § 1.12 (Definitions – Eligible
Customer); see also ISO-NE Tariff, § I.2 (Rules of Construction; Definitions) (177.0.0),
§ I.2.2.
124 Atl. City Elec. Co. v. FERC, 295 F.3d 1, 8 (D.C. Cir. 2002).
125 16 U.S.C. § 824(b)(1).
126 Id. §§ 824d, 824e; see FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 278
(2016) (EPSA) (approving “a common-sense construction of the FPA’s language,
PDF page 30
Docket No. EL26-72-000
- 30 -
The Supreme Court has held that the Commission’s authority over interstate transmission
is not limited to wholesale transmission service and that the Commission has authority
over unbundled retail transmission service.127 As part of its transmission authority, the
Commission has exercised jurisdiction over the terms of certain interconnections to the
transmission system as an element of transmission service,128 including the
interconnection of wholesale load to the transmission system.129
As applied to large load additions to the transmission system, these principles
mean that the Commission has exclusive jurisdiction over the rates, terms, and conditions
of interstate transmission service to Eligible Customers on behalf of large loads
connecting to the transmission system, and the practices directly affecting the provision
of such interstate transmission of electricity. An essential component of providing such
transmission service is the process by which the transmission provider and/or
transmission owner evaluates (1) whether it can provide the requested transmission
service and (2) the impact that providing such transmission service will have on the
jurisdictional transmission system, including determining whether any new or upgraded
transmission facilities are needed to provide transmission service while maintaining
reliable operation of the transmission system. This transmission service study process
determines what network upgrades are needed to provide transmission service to Eligible
Customers on behalf of large loads, the costs of which are included in transmission rates.
As such, this study process directly affects Commission-jurisdictional transmission
rates.130 The Commission has exclusive authority to ensure that the process to study the
limiting FERC’s ‘affecting’ jurisdiction to rules or practices that ‘directly affect the
wholesale rate’” (cleaned up)).
127 New York v. FERC, 535 U.S. 1, 17, 19-20 (2002) (upholding the Commission’s
exercise of jurisdiction over unbundled retail transmission service).
128 Tenn. Power Co., 90 FERC ¶ 61,238, at 61,761 (2000) (Tennessee Power),
order denying reh’g, 91 FERC ¶ 61,271 (2000); Standardization of Generator
Interconnection Agreements & Procs., Order No. 2003, 104 FERC ¶ 61,103, at P 9
(2003); see also Laguna Irrigation Dist., 91 FERC ¶ 61,340, at 62,152 (2000).
129 Pac. Gas & Elec. Co., 109 FERC ¶ 61,392, at P 37 (2004); Pac. Gas & Elec.
Co., 115 FERC ¶ 61,193, at PP 36-38 (2006).
130 Cf. Transmission Plan. & Cost Allocation by Transmission Owning &
Operating Pub. Utils., Order No. 1000, 136 FERC ¶ 61,051, at P 112 (2011) (“It is
through the transmission planning process that public utility transmission providers
determine which transmission facilities will more efficiently or cost-effectively meet the
needs of the region, the development of which directly impacts the rates, terms and
conditions of jurisdictional service.”).
PDF page 31
Docket No. EL26-72-000
- 31 -
provision of transmission service to Eligible Customers is just and reasonable and not
unduly discriminatory or preferential. We therefore find that we have authority to ensure
that tariffs include provisions that clearly and consistently address the study process for
the provision of transmission service to Eligible Customers on behalf of large loads,
including the unique impacts that providing transmission service to Eligible Customers
on behalf of large loads may have on the transmission system.
At the same time, we continue to recognize that the FPA expressly reserves to
states the authority over any other sale of electric energy, including retail sales and
wholesale sales not in interstate commerce (such as wholesale sales within the Electric
Reliability Council of Texas region), as well as facilities used for the generation and
distribution of electricity.131 As such, we recognize that states will continue to regulate:
(1) the specific terms of retail sales to large load;132 (2) which entities may make retail
sales within their borders, including which entities are legally permitted to provide
electricity to retail large load customers;133 and (3) any siting decisions and construction
associated with the large load project.134 Nothing in this order is intended to intrude upon
state authority over retail service to large loads.
In sum, we today exercise our authority to ensure that the process by which
jurisdictional transmission providers and/or transmission owners will study the provision
of jurisdictional transmission service to Eligible Customers on behalf of large loads
interconnecting to the transmission system, including where, as allowed by state law or a
public utility’s voluntary offer of such service, an end-use large load seeks unbundled
retail transmission service, is just and reasonable and not unduly discriminatory or
preferential. Pursuant to that authority, we find that ISO-NE’s Tariff appears to be unjust
and unreasonable or unduly discriminatory or preferential because it lacks sufficiently
clear and consistent provisions regarding the study process related to the provision of
transmission service to Eligible Customers on behalf of large loads. We need not
131 16 U.S.C. § 824(b)(1); see Dayton Power & Light Co. v. FERC, 126 F.4th
1107, 1129 (6th Cir. 2025).
132 See EPSA, 577 U.S. at 279-80 (recognizing state authority over retail electricity
sales); New York v. FERC, 535 U.S. at 28 (same).
133 PJM Show Cause Order, 190 FERC ¶ 61,115 at PP 68-69.
134 See, e.g., Citizens Action Coal. of Ind., Inc. v. FERC, 125 F.4th 229, 238 (D.C.
Cir. 2025) (citing 16 U.S.C. § 824(b)(1)) (recognizing state authority over generation
resource mix, including through their siting authority); Order No. 1000, 136 FERC
¶ 61,051 at P 107 (acknowledging state authority over siting, permitting, and construction
of transmission facilities).
PDF page 32
Docket No. EL26-72-000
- 32 -
comprehensively address the Commission’s jurisdiction over other aspects of the addition
of large loads to the transmission system at this time.
2.
Tariff Provisions
In the following section, we begin by considering ISO-NE’s Tariff as it relates to
how ISO-NE and/or the Participating Transmission Owners will study the provision of
transmission service to Eligible Customers on behalf of large loads and explain our
concerns that the lack of sufficiently clear and consistent provisions regarding the study
process for the provision of transmission service to Eligible Customers on behalf of large
loads is unjust and unreasonable or unduly discriminatory or preferential. We then
consider whether the Tariff is unjust and unreasonable without certain elements. First,
we consider whether the Tariff lacks sufficiently clear and consistent Tariff provisions
establishing an appropriate definition of large load, as a separate category of load.
Second, we consider whether the Tariff lacks sufficiently clear and consistent Tariff
provisions establishing an application process and requirements for Eligible Customers
requesting transmission service on behalf of large loads and a study process that
considers the unique operational challenges of providing transmission service to Eligible
Customers on behalf of large loads. Third, we consider whether the Tariff lacks
sufficiently clear and consistent Tariff provisions establishing ongoing operational
requirements necessary to ensure that ISO-NE can reliably provide transmission service
given the unique operational impacts on the transmission system of providing
transmission service to Eligible Customers on behalf of large loads. Finally, we consider
whether the Tariff requires such ongoing operational requirements for Eligible Customers
taking transmission service on behalf of large loads to be memorialized in service
agreements.
We preliminarily find that ISO-NE’s Tariff appears to be unjust and unreasonable
or unduly discriminatory or preferential because it does not contain provisions addressing
with sufficient clarity and consistency how ISO-NE and/or the Participating Transmission
Owners will study the provision of transmission service to Eligible Customers on behalf
of large loads. We recognize that ISO-NE and/or the Participating Transmission Owners
may have existing load integration processes, including studies that are performed in
evaluating the provision of transmission service to Eligible Customers on behalf of large
loads.135 However, we are concerned that those processes and any required studies with
regard to the provision of transmission service are not described in the Tariff with the
degree of clarity and specificity necessary to ensure that the transmission provider can
mitigate operational risks of providing transmission service to Eligible Customers on
behalf of large loads, given their impact on the transmission system, avoid disputes
regarding how studies are conducted, deter speculative or duplicative requests for
135 See supra PP 21, 26.
PDF page 33
Docket No. EL26-72-000
- 33 -
transmission service by Eligible Customers on behalf of large loads, and help avoid
excessive and unnecessary network upgrades. Moreover, we are concerned that the
existing Tariff does not contain other elements akin to those described below, which we
preliminarily find may be necessary to ensure that the rates, terms, and conditions of
jurisdictional transmission service are just and reasonable.
At the outset, we recognize that the Participating Transmission Owners may be
primarily responsible for conducting the studies that (1) evaluate whether a large load
may be interconnected to the transmission system and served by the Eligible Customer,
and (2) determine whether network upgrades are necessary to provide transmission
service. This may be particularly true where an Eligible Customer seeks local
transmission service on behalf of a large load and where that service takes place over
non-PTFs. We appreciate that this role may stem from how ISO-NE and the
Participating Transmission Owners allocated rights and responsibilities in the governing
documents establishing ISO-NE. We do not seek to alter that allocation of rights and
responsibilities.
We are nonetheless concerned that ISO-NE’s Tariff lacks a study process that
addresses the unique operational and reliability challenges that providing transmission
service to Eligible Customers on behalf of large loads presents to the transmission
system. Large loads can be more energy intensive and geographically concentrated than
traditional load, and exhibit different load profiles and operational characteristics.136
While the ISO-NE region has seen a smaller growth in large loads than other regions,
large loads are looking to interconnect in the region.137 ISO-NE itself has recognized that
large loads can be highly uncertain in terms of attrition rates, relative construction time,
and electric demand characteristics.138 New England Consumer-Owned Systems note
that the addition—or sudden loss—of large loads’ demand can reshape regional power
flows, trigger major transmission and voltage support needs, and impose substantial costs
on existing customers if not properly regulated.139 As a result, providing transmission
service to Eligible Customers on behalf of large loads may be more complex and could
136 See, e.g., SPP HILL Order, 194 FERC ¶ 61,031 at PP 7-8; NERC,
Characteristics and Risks of Emerging Large Loads (July 2025),
https://www.nerc.com/globalassets/who-we-are/standing-committees/rstc/whitepaper-
characteristics-and-risks-of-emerging-large-loads.pdf (NERC Characteristics and Risks
of Large Loads).
137 See supra P 8.
138 ISO-NE Letter at 2.
139 New England Consumer-Owned Systems November 21 ANOPR Comments at
2.
PDF page 34
Docket No. EL26-72-000
- 34 -
raise greater reliability concerns for the transmission system, relative to a situation where
Eligible Customers seek transmission service on behalf of traditional load.
We acknowledge that ISO-NE’s Tariff currently outlines study procedures for the
provision of Regional Network Service to Eligible Customers.140 However, the study
procedures in Tariff Section II.19 refer to the LGIP and SGIP in Schedules 22 and 23,
which explicitly pertain to interconnection customers.141 In addition, Eligible Customers
seeking Local Transmission Service go through study processes that may be less clear or
vary depending on which Participating Transmission Owner is providing the Local
Transmission Service. Without a clear and consistent process to study the provision of
transmission service to Eligible Customers on behalf of large loads, ISO-NE and/or the
Participating Transmission Owners may not fully capture the transmission system
impacts of providing such transmission service, which could result in significant
operational risks for the transmission system. Furthermore, we are concerned that,
without sufficiently clear and consistent Tariff provisions, ISO-NE will not have the
ongoing visibility and operational control necessary to provide reliable transmission
service.
We are also concerned that the absence of sufficiently clear and consistent tariff
provisions for how ISO-NE and/or the Participating Transmission Owners will study the
provision of transmission service to Eligible Customers on behalf of large loads will lead
to disputes over a variety of issues—e.g., study timelines and delays,142 how the
transmission service needed on behalf of the large load is studied,143 what types of
network upgrades are considered, and how required network upgrades to provide the
requested transmission service are determined.144 Such disputes may arise from the lack
140 See supra PP 21-22.
141 ISO-NE Tariff, § II.19.2.
142 See, e.g., CEBA November 21 ANOPR Comments at 12-13; Eolian November
21 ANOPR Comments at 14-16; Institute for Progress November 21 ANOPR Comments
at 7-8; Microsoft November 21 ANOPR Comments at 9; ODEC December 5 ANOPR
Comments at 4.
143 Commenters raised concern that large loads are not studied with consideration
of their known operating characteristics, including their willingness to be flexible or
curtailable. See, e.g., ClearPath November 21 ANOPR Comments at 5-6; Constellation
November 21 ANOPR Comments at 23-24; Critical Loop November 21 ANOPR
Comments at 3; GridCare December 5 ANOPR Comments at 1-2; L. Lynne Kiesling
November 21 ANOPR Comments at 10.
144 Specifically, commenters raised concern that transmission providers/owners
may only consider traditional transmission infrastructure or that there is a lack of
PDF page 35
Docket No. EL26-72-000
- 35 -
of transparency in how studies are performed and how decisions will be made.145 We are
thus concerned that the lack of clear and consistent provisions in ISO-NE’s Tariff related
to the study process for the provision of transmission service to Eligible Customers on
behalf of large loads appears to be unjust and unreasonable or unduly discriminatory or
preferential.
Lastly, we are concerned that ISO-NE’s existing Tariff fails to deter speculative or
duplicative requests for transmission service by Eligible Customers on behalf of large
loads. ISO-NE itself has a methodology for derating data centers in its load forecasts due
to their more speculative nature.146 Many ANOPR comments assert that clear and
consistent provisions establishing study timelines and costs, readiness requirements,
and/or penalties will deter speculative or duplicative requests related to large load
additions.147 Commenters explain that speculative requests may bog down and delay the
consideration of alternative transmission solutions. See, e.g., ACORE November 21
ANOPR Comments at 3-4, 6-7; American Terawatt November 21 ANOPR Comments at
4-5; Calibrant November 21 ANOPR Comments at 1-2, 3; CEBA November 21 ANOPR
Comments at 9-10; Chamber of Commerce November 21 ANOPR Comments at 3; CTC
Global Corporation November 21 ANOPR Comments at 1-3; DCC November 21
ANOPR Comments at 10-11; GridCARE December 5 ANOPR Comments at 4; Industrial
Customers November 21 ANOPR Comments at 27-28; Infrastructure Masons December
5 ANOPR Comments at 18; Iron Mountain Data Centers, LLC November 21 ANOPR
Comments at 3-4; Land Trust Alliance November 21 ANOPR Comments at 5-6; PIOs
November 21 ANOPR Comments at 22; Southeast PIOs November 21 ANOPR
Comments at 44-45; WATT and Advancing Modern Powerlines November 21 ANOPR
Comments at 5-8.
145 See, e.g., CEBA November 21 ANOPR Comments at 12; ECA December 5
ANOPR Comments at 1-2; Eolian November 21 ANOPR Comments at 17-18; EPSA
November 21 ANOPR Comments at 6; Infrastructure Masons December 5 ANOPR
Comments at 4, 6-7; Southeast PIOs November 21 ANOPR Comments at 39-40; Switch
December 5 ANOPR Comments at 3; Tract November 21 ANOPR Comments at 5;
Vantage November 21 ANOPR Comments at 5-6; Verrus November 21 ANOPR
Comments at 6, 12; Vistra December 5 ANOPR Comments at 27.
146 See, e.g., ISO-NE Large Load Forecast Presentation at 8.
147 See, e.g., ACORE November 21 ANOPR Comments at 6; AEU November 21
ANOPR Comments at 17-18; Amazon November 21 ANOPR Comments at 6; Crusoe
December 5 ANOPR Comments at 5-6; EDF Power November 21 ANOPR Comments at
12-13; EEI November 21 ANOPR Comments at 20; Fervo November 21 ANOPR
Comments at 3; GridCare December 5 ANOPR Comments at 5; Invenergy November 21
ANOPR Comments at 6; Microsoft November 21 ANOPR Comments at 9; Ohio FEA
PDF page 36
Docket No. EL26-72-000
- 36 -
study process, wasting time and resources for transmission providers;148 result in
inaccurate study results or delays for other Eligible Customers seeking transmission
service on behalf of load;149 create a substantial risk of cost shifts if the large load
additions do not materialize as planned;150 and distort load forecasts.151 Clear and
consistent study procedures that include readiness requirements (i.e., meaningful
milestones and/or financial commitments) can help ensure that Eligible Customers’
requests for transmission service on behalf of large loads are more viable and more likely
to materialize as planned, given that they must meet specific milestones and/or pay costs
to proceed.
More specifically, we preliminarily find that ISO-NE’s Tariff appears to be unjust
and unreasonable because it lacks sufficiently clear and consistent Tariff provisions that
address certain aspects of the process to provide transmission service to Eligible
Customers on behalf of large loads, including:
November 21 ANOPR Comments at 4.
148 See, e.g., ATC November 21 ANOPR Comments at 12; Eolian November 21
ANOPR Comments at 17-18; GridCare December 5 ANOPR Comments at 5; Illinois AG
November 21 ANOPR Comments at 9-10; Institute for Progress November 21 ANOPR
Comments at 9; Ohio FEA November 21 ANOPR Comments at 4; Vistra November 21
ANOPR Comments at 23.
149 See, e.g., Amazon November 21 ANOPR Comments at 6; CEBA November 21
ANOPR Comments at 8; ClearPath November 21 ANOPR Comments at 4; Geronimo
November 21 ANOPR Comments at 12; TAPS November 21 ANOPR Comments at
14-15.
150 See, e.g., Buckeye November 21 ANOPR Comments at 1-2; Exelon November
21 ANOPR Comments at 3; Kansas Commission November 21 ANOPR Comments at
12; NRECA November 21 ANOPR Comments at 9; OCC November 21 ANOPR
Comments at 9; Southeast PIOs November 21 ANOPR Comments at 20; State Entities
November 21 ANOPR Comments at 7-8; TAPS November 21 ANOPR Comments at 15,
22-24; Tri-State November 21 ANOPR Comments at 6, 8; Vistra November 21 ANOPR
Comments at 23.
151 See, e.g., CEBA November 21 ANOPR Comments at 8; EEI November 21
ANOPR Comments at 20; ELCON November 21 ANOPR Comments at 7; Invenergy
November 21 ANOPR Comments at 6; GridCare December 5 ANOPR Comments at 5;
OCC November 21 ANOPR Comments at 9; PIOs November 21 ANOPR Comments at
5; Southeast PIOs November 21 ANOPR Comments at 41; Talen November 21 ANOPR
Comments at 9.
PDF page 37
Docket No. EL26-72-000
- 37 -
(1) a definition of large load sufficient to capture loads that present the unique
challenges described herein;
(2) the application process for requesting transmission service to Eligible
Customers on behalf of large loads and the study procedures, including readiness
requirements, for studying the provision of transmission service to Eligible
Customers on behalf of large loads;
(3) ongoing operational requirements for transmission customers152 serving large
loads necessary to ensure reliable operation of the transmission system; and
(4) pro forma provisions in transmission service agreements to memorialize these
terms.
First, we preliminarily find that ISO-NE’s Tariff appears to be unjust and
unreasonable because it lacks a definition of large load, as a new category of load.
Integrating large loads poses specific challenges to transmission system operation given
their size, operational behavior, and unique potential to impact the transmission
system.153 An appropriate definition, including a load size and interconnection voltage
threshold, should be based on the characteristics of ISO-NE’s transmission system. That
said, based on the record in the ANOPR proceeding,154 it appears that it would be
152 We note that such ongoing operational requirements should apply to
transmission customers, rather than Eligible Customers, as these requirements apply after
the Eligible Customer has an executed (or a filed unexecuted) service agreement for
transmission service and have become transmission customers under the Tariff.
153 See generally NERC, 2024 Long- Term Reliability Assessment 38 (Dec. 2024,
updated July 2025), https://www.nerc.com/pa/RAPA/ra/Reliability%20
Assessments%20DL/NERC_Long%20Term%20Reliability%20Assessment_2024.pdf).
154 See, e.g., Constellation November 21 ANOPR Comments at 13 (supporting a
voltage threshold); DTE November 21 ANOPR Comments at 3, 17-19 (recommending a
threshold of an amount between 50 MW to 100 MW); Eolian November 21 ANOPR
Comments at 8-9 (recommending a voltage threshold greater than or equal to an amount
between 60 kV to 100 kV); Illinois AG November 21 ANOPR Comments at 7
(supporting a 20 MW or 50 MW threshold and consideration of other factors, such as
voltage level); ITC November 21 ANOPR Comments at 3 (recommending a threshold of
between 50 MW to 100 MW); National Grid November 21 ANOPR Comments at 11-12
(asserting appropriate thresholds of 50 or 80 MW depending on the region); Nebraska
Board November 21 ANOPR Comments at 4 (proposing a 50 MW threshold); New
Mexico Commission November 21 ANOPR Comments at 5 (proposing a 50 MW
threshold).
PDF page 38
Docket No. EL26-72-000
- 38 -
reasonable to define a large load as a new, commercial or industrial customer, located at a
single site behind one or more points of interconnection, and that has a peak load of 50
MW or greater, interconnects to the transmission system at a voltage level of greater than
69 kV, and is not part of a co-location arrangement. In its response to this order, ISO-NE
should explain whether the Tariff remains just and reasonable without such a definition,
or propose Tariff revisions establishing its own definition of large load.
Second, we preliminarily find that ISO-NE’s Tariff appears to be unjust and
unreasonable because it lacks sufficiently clear and consistent Tariff provisions
establishing the application process and study procedures that will be used when ISO-NE
and/or the Participating Transmission Owners evaluate the provision of transmission
service to Eligible Customers on behalf of large loads. For example, we are concerned
with the lack of clarity as to what aspects of the study and provision of Regional Network
Service apply only to interconnection customers subject to the LGIP or SGIP as opposed
to all Eligible Customers seeking Regional Network Service, as well as with the clarity
and consistency of the Local Transmission Service study procedures in various
Participating Transmission Owners’ Schedule 21 procedures. ISO-NE’s should explain
whether the Tariff remains just and reasonable, for example, without: (1) an application
process that accepts Eligible Customers’ applications for transmission service on behalf
of large loads on a rolling basis; (2) a non-refundable application fee and sufficient
readiness requirements that escalate at distinct phases of the study process to deter
duplicative or speculative requests for transmission service (e.g., meaningful milestones
and/or financial commitments); and (3) information and data requirements that Eligible
Customers must submit to ISO-NE and/or the Participating Transmission Owners
regarding the characteristics of the large load on behalf of which the Eligible Customer is
taking transmission service, including disclosure to ISO-NE of any substantially similar
pending transmission service requests on behalf of the same large load customer.155
ISO-NE may also elect to propose Tariff revisions establishing such an application
process, fee, and requirements.
Further, ISO-NE’s Tariff appears to lack sufficiently clear and consistent
provisions establishing a study process for evaluating the provision of transmission
service to Eligible Customers on behalf of large loads that considers the unique
characteristics and impacts of large loads on the transmission system. For example, we
are concerned that ISO-NE’s Tariff may not clearly and consistently require ISO-NE or
the Participating Transmission Owners to conduct studies that evaluate the transmission
system’s ability to withstand risks observed from analyzed large load behavior created by
the large load at the point of interconnection, or any other necessary supplemental studies
155 The Electric Reliability Council of Texas (ERCOT) has proposed a similar
disclosure requirement in its Batch Zero process for large load interconnections. ERCOT
Planning Guide, § 9.7.1(1)(b) (proposed Mar. 4, 2026).
PDF page 39
Docket No. EL26-72-000
- 39 -
to evaluate the impact of providing transmission service to Eligible Customers on behalf
of large loads.156 Additionally, we preliminarily find that ISO-NE’s Tariff appears unjust
and unreasonable because it lacks appropriate provisions recognizing within the
transmission service request study process the unique operational characteristics of large
loads that are willing and able to limit their energy withdrawals under certain conditions,
which may thereby lessen or potentially avoid the need for certain network upgrades.
While flexible large loads can reduce the demand on the transmission system, and
therefore potentially reduce the need for additional transmission capacity, additional
informational and study requirements may be necessary to account for the dynamic
nature of these types of loads while maintaining reliability.157 Additionally, we note that
accurate models using Electromagnetic Transient studies may help to ensure that
transmission service needed on behalf of large loads can be provided without
compromising reliability.158
Additionally, we preliminarily find that ISO-NE’s Tariff appears to be unjust and
unreasonable because it lacks clear and consistent provisions requiring the evaluation of
alternative transmission technologies159 as potential solutions to accommodate an
156 See generally NERC, Industry Recommendation: Large Load Interconnection,
Study, Commissioning, and Operations (Sep. 2025),
https://www.nerc.com/globalassets/programs/bpsa/alerts/2025/nerc-alert-level-2--large-
loads.pdf (finding that unique operational characteristics of large loads necessitate
enhancements to studies).
157 See, e.g., AEMA November 21 ANOPR Comments at 6; Thermal Battery
Alliance November 21 ANOPR Comments at 7; Verrus November 21 ANOPR
Comments at 10.
158 See, e.g., NERC, Draft Reliability Guideline: Risk Mitigation for Emerging
Large Loads 6-7 (May 2026), https://www.nerc.com/globalassets/who-we-are/standing-
committees/rstc/reliabilityguideline_riskmitigationforemerginglargeloads.pdf; NERC,
Assessment of Gaps in Existing Practices, Requirements, and Reliability Standards for
Emerging Large Loads 31 (Mar. 2026), https://www.nerc.com/globalassets/our-
work/guidelines/reliability/white-paper---assessment-of-gaps.pdf; see also SPP HILL
Order, 194 FERC ¶ 61,031 at P 62. We acknowledge that Electromagnetic Transient
study processes are already within the scope of the Cluster Study process through which
Regional Network Service requests are processed. See supra P 22. However, we note
that it is unclear if such Electromagnetic Transient study processes are carried out under
Local Transmission Service studies processes.
159 For purposes of this order, alternative transmission technologies include static
synchronous compensators, static VAR compensators, advanced power flow control
devices, transmission switching, synchronous condensers, voltage source converters,
PDF page 40
Docket No. EL26-72-000
- 40 -
Eligible Customer’s request for transmission service on behalf of a large load.
Alternative transmission technologies can add more capacity on existing transmission
lines quickly, often within one to three years.160 Unlike with traditional load growth,161
large load customers often have development timelines requiring interconnection to the
transmission system faster than traditional network upgrades can be built, necessitating a
sufficient evaluation of alternative transmission technologies that can more quickly
accommodate transmission service requests from Eligible Customers on behalf of large
loads.162 The Commission has previously recognized that alternative transmission
advanced conductors, tower lifting, and dynamic line ratings. We note that the
Commission has also referred to these types of technologies as Grid Enhancing
Technologies (GETs).
160 WATT and Advancing Modern Powerlines November 21 ANOPR Comments
at 5-6.
161 See, e.g., SPP HILL Order, 194 FERC ¶ 61,031 at P 7 (explaining that the
HILL proposal was needed in part due to large load customers frequently requesting
transmission service within months rather than years of their intended commercial
operation, straining legacy regulatory frameworks and planning processes originally
designed for slow, incremental, and predictable load growth); see also Commission Staff,
2025 State of the Market Report 8 (Mar. 2026) (“[D]ata centers have characteristics
unlike more traditional loads [including] size, strong desire for faster interconnection, and
potential flexibility.”).
162 Exec. Off. of the President, Winning the Race: America’s AI Action Plan 1-2,
15 (July 2025), https://www.whitehouse.gov/wp-content/uploads/2025/07/Americas-AI-
Action-Plan.pdf (explaining that accelerated deployment of AI data centers is a critical
matter of national security and international economic competitiveness, and
recommending federal policy action to optimize the existing grid through advanced grid
technologies); WATT and Advancing Modern Powerlines November 21 ANOPR
Comments at 5-8 (“[Alternative transmission technologies’] deployment timelines are
more aligned with the interconnection needs of new large loads, which may only take 1-2
years to construct.”); Industrial Customers November 21 ANOPR Comments at 28
(“Achieving speed-to-power in the near-term, while also protecting customers, will
require the use of GETs, advanced reconductoring, and unlocking all available system
capacity.”); Energy Systems Integration Group, Historical and Modern Large Loads:
Characteristics, Context, and Industry Action to Meet Grid and Customer Needs 4 (Mar.
2026), https://www.esig.energy/wp-content/uploads/2026/03/ESIG-Historical-vs-
Modern-Large-Loads-white-paper-2026.pdf (describing the timing mismatch between
how long it takes to build a new data center and how long it takes to plan, permit, and
build transmission).
PDF page 41
Docket No. EL26-72-000
- 41 -
technologies have the potential to mitigate or defer the need for traditional network
upgrades and often can be deployed both more quickly and at lower cost than traditional
network upgrades, and therefore failing to consider whether alternative transmission
technologies can meet transmission needs more efficiently or cost-effectively than
traditional network upgrades has the potential to render Commission-jurisdictional rates
unjust and unreasonable.163 Further, to the extent network upgrades costs to
accommodate an Eligible Customer’s request for transmission service on behalf of a large
load are rolled into a transmission owner’s transmission revenue requirement,
transmission customers other than the Eligible Customer may bear a portion of those
network upgrades costs, highlighting the need for clear and consistent provisions
requiring the evaluation of least-cost options like alternative transmission technologies to
mitigate the rate impact on all transmission customers.
ISO-NE should explain whether the Tariff remains just and reasonable without
provisions that (1) require the evaluation of alternative transmission technologies in
transmission service request studies, using models that are capable of evaluating the
transmission system to accurately account for advanced transmission technologies, in all
instances, without the need for a request from the Eligible Customer seeking transmission
service on behalf of a large load; and (2) if traditional network upgrades are selected
instead of alternative transmission technologies, inclusion in the study report to the
Eligible Customer seeking transmission service on behalf of a large load of a sufficiently
clear demonstration of why alternative transmission technologies are not feasible (i.e.,
would not resolve reliability violations identified or meet the relevant planning criteria)
or would not result in lower costs or a faster timeline for accommodating the transmission
service request; or propose Tariff revisions establishing such provisions. This
transparency and informational requirement is warranted for the regulatory scheme we
are establishing for transmission service requests by Eligible Customers on behalf of
large loads given demand from and the expedited development timelines for large load
customers. We underscore that we are not mandating the use of alternative transmission
technologies. To the extent stakeholders believe that specific characteristics of providing
transmission service to Eligible Customers on behalf of large loads warrant requirements
beyond those contemplated here, we seek further briefing.
163 Improvements to Generator Interconnection Procs. & Agreements, Order No.
2023, 184 FERC ¶ 61,054 at P 1583, order on reh’g, 185 FERC ¶ 61,063 (2023), order
on reh’g, Order No. 2023-A, 186 FERC ¶ 61,199, errata notice, 188 FERC ¶ 61,134
(2024); see also Bldg. for the Future Through Elec. Reg’l Transmission Plan. & Cost
Allocation, Order No. 1920, 187 FERC ¶ 61,068 at P 1201, order on reh’g, Order No.
1920-A, 189 FERC ¶ 61,126 (2024), order on reh’g, Order No. 1920-B, 191 FERC
¶ 61,026 (2025).
PDF page 42
Docket No. EL26-72-000
- 42 -
Finally, based on the record, it appears reasonable that such study processes,
culminating in a report to the Eligible Customer with the results of the studies, including
any Direct Assignment Facilities and network upgrades necessary to accommodate the
transmission service request as well as a non-binding good-faith estimate of the cost and
the time to construct such facilities, should take no more than 60-90 days calendar days to
complete.164 To the extent ISO-NE or the Participating Transmission Owners already
have such procedures and conduct such studies, but those processes are not included in
the Tariff, ISO-NE and the Participating Transmission Owners should explain their
existing processes and consider whether amendments are necessary to the Tariff to
memorialize those processes and also address the concerns expressed herein. Otherwise,
ISO-NE should explain whether the Tariff remains just and reasonable without: (1)
sufficiently clear and consistent provisions to evaluate the impact of providing the
requested transmission service to Eligible Customers on behalf of large loads, including
identifying the Direct Assignment Facilities and network upgrades necessary to provide
such service reliably; (2) provisions to appropriately recognize within the transmission
service study process the unique operational characteristics of large loads; (3) a study
deadline of no more than 60-90 calendar days; or propose Tariff revisions establishing
them
Third, we preliminarily find that ISO-NE’s Tariff appears to be unjust and
unreasonable because it lacks provisions addressing ongoing operational requirements for
transmission customers taking transmission service on behalf of large loads. We are
concerned that without such requirements the rates, terms, and conditions of transmission
service may be unjust and unreasonable. The unique nature of these large loads creates
challenges for operation of the transmission system and necessitates greater visibility and
operational control when providing transmission service to transmission customers on
behalf of large loads, without which the reliability of the transmission system could be at
risk.165 For example, we are concerned that ISO-NE’s Tariff does not require
transmission customers to provide ISO-NE hourly forecasts, telemetry data, and other
164 Several commenters support a 60-day timeline. See, e.g., Constellation
November 21 ANOPR Comments at 26; Critical Loop December 5 ANOPR Comments
at 8; EDF Power November 21 ANOPR Comments at 16; Tract November 21 ANOPR
Comments at 9. Other commenters note that SPP’s HILL process has a 90-day timeline,
or otherwise support a 90-day timeline. See, e.g., AEMA November 21 ANOPR
Comments at 3; Eolian December 5 ANOPR Comments at 27; Industrial Customers
November 21 ANOPR Comments at 20; PJM November 21 ANOPR Comments at 7;
SPP November 21 ANOPR Comments at 16-17.
165 E.g., ATC November 21 ANOPR Comments at 14; CAISO November 21
ANOPR Comments at 10 (citing NERC Characteristics and Risks of Large Loads); Herb
Schrayshuen November 21 ANOPR Comments at 2-5.
PDF page 43
Docket No. EL26-72-000
- 43 -
data to ensure sufficient visibility or specify requirements for maintaining communication
channels between ISO-NE and the transmission customer on behalf of the large load.
Additionally, we are concerned that the Tariff does not require transmission owners to
install, and transmission customers to pay for, equipment to enable ISO-NE to monitor
large loads for impacts of, for example, fast-ramping load that may impact the
transmission system too quickly to be captured by conventional data acquisition systems
(e.g., the need for phasor measurement units or similar equipment). We are also
concerned that the Tariff does not require the transmission customer to enable ISO-NE to
remotely disconnect large loads when necessary to maintain reliability of the
transmission system, with the costs of such equipment directly assigned to the
transmission customer, as well as the terms and conditions under which ISO-NE may
remotely disconnect the large load (e.g., emergency conditions, so that transmission
equipment is not harmed). Further, we are concerned that the Tariff does not specify
ramp rate or ride-through requirements with which the transmission customer taking
transmission service on behalf of the large load must comply. Lastly, we are concerned
that the Tariff does not specify requirements for necessary control technologies and/or
protection systems that may be necessary to limit a transmission customer’s withdrawals
from the transmission system as appropriate.166 ISO-NE should explain whether the
Tariff remains just and reasonable without these or other ongoing operational
requirements as part of the rates, terms, and conditions of transmission service or propose
Tariff revisions establishing necessary ongoing operational requirements.
Fourth, we preliminarily find that ISO-NE’s Tariff appears to be unjust and
unreasonable because it lacks pro forma provisions in a transmission service agreement
between ISO-NE and the transmission customer taking transmission service on behalf of
a large load to memorialize the above terms (e.g., equipment requirements, data
requirements, remote disconnect capability).167 We are concerned that, without such
pro forma provisions in a transmission service agreement between ISO-NE and the
transmission customer, ISO-NE may be unable to enforce ongoing operational
requirements for transmission customers taking transmission service on behalf of large
166 Specifically, as discussed below, the Commission has found that such
necessary control technologies and/or protection schemes may be appropriate where
Eligible Customers are taking one of the new transmission services. See infra PP 99,
103.
167 We recognize that an Eligible Customer must be party to a Market Participant
Service Agreement or Service Agreement for Regional Network Service prior to
initiating Regional Network Service, and must be party to a Local Service Agreement
prior to initiating Local Transmission Service. However, we find that these agreements
do not contain provisions that memorialize the terms described above. See supra PP 21,
26.
PDF page 44
Docket No. EL26-72-000
- 44 -
loads. ISO-NE should explain whether the Tariff remains just and reasonable without
such pro forma provisions in a transmission service agreement, or propose revisions to
include pro forma provisions memorializing the ongoing operational requirements in a
transmission service agreement between ISO-NE and the transmission customer.
B.
Cost Shifting Risk Among Transmission Customers
We next preliminarily find that ISO-NE’s Tariff appears to be unjust and
unreasonable because it lacks adequate mechanisms to mitigate the risk of cost shifting
among transmission customers, which may result in unjust and unreasonable rates for
transmission service. In particular, we are concerned about the apparent lack of (1)
transparency regarding the assignment of network upgrades, and their associated costs,
that are needed to provide transmission service to Eligible Customers on behalf of large
loads; and (2) a pro forma cost recovery agreement between ISO-NE, the relevant
transmission owner, and the Eligible Customer taking transmission service on behalf of
large loads that help ensure that Eligible Customers bear the risk and are ultimately
responsible for costs incurred to provide transmission service, including the cost of
network upgrades.
We direct ISO-NE and the Participating Transmission Owners, to the extent the
matters addressed herein implicate aspects of the Tariff over which they have the filing
rights, to explain whether the Tariff remains just and reasonable without (1) robust,
accurate, and systematic provision of data on ISO-NE’s website in a single location, and
in an easily accessible format that is searchable and allows users to filter the data,
regarding the cost for network upgrades needed to provide transmission service to
Eligible Customers on behalf of large loads; and (2) a pro forma cost recovery agreement
between ISO-NE, the relevant transmission owner, and the Eligible Customer taking
transmission service on behalf of a large load, or to propose Tariff revisions to provide
additional transparency and establish such a pro forma cost recovery agreement. We
encourage state regulators responsible for setting retail rates to provide input to ISO-NE
regarding their transparency needs.
1.
Jurisdiction
The Commission has a duty to address the risk of cost shifting among transmission
customers that may result in unjust and unreasonable transmission rates. As explained
above, the Commission is obligated to ensure that the rates charged for jurisdictional
transmission service—as well as any practice directly affecting such rates—are just and
reasonable and not unduly discriminatory or preferential. With respect to the addition of
large loads to the transmission system, the Commission has exclusive authority to ensure
that transmission rates are just and reasonable. The costs of those upgrades to the
transmission system (i.e., network upgrades) necessary to provide transmission service to
Eligible Customers on behalf of large loads are inputs to jurisdictional transmission rates,
PDF page 45
Docket No. EL26-72-000
- 45 -
and thus directly affect the Commission-jurisdictional rates paid by transmission
customers. To fulfill its responsibility to ensure that transmission rates are just and
reasonable, the Commission must act to address the risk of cost shifting among
transmission customers due to (1) the process transmission providers and/or transmission
owners use to evaluate the facilities needed, and the associated costs, for the provision of
transmission service to Eligible Customers on behalf of large loads and (2) speculative
transmission service requests by Eligible Customers on behalf of large loads that could
result in unjust and unreasonable transmission rates.
In response to the ANOPR, many commenters raise concerns about the impact that
large load additions can have on retail ratepayers, particularly the concern that other retail
ratepayers may be forced to subsidize network upgrades needed to add large loads to the
transmission system.168 While we appreciate and are similarly concerned about this
issue, the Commission is limited to addressing jurisdictional transmission rates and as
such, we do so herein. As the Commission has explained, states determine how
Commission-approved rates are collected among the relevant retail consumers along with
the rates for state-jurisdictional matters.169 Specifically, states have authority over how
the wholesale costs of providing electricity, including transmission of such electricity, to
those retail customers are recovered through retail rates.170 We are encouraged by efforts
taken by states to reform retail tariffs to address the potential for retail cost shifting as
large loads come online,171 as well as voluntary efforts by transmission owners to protect
retail ratepayers through cost recovery agreements with large loads.172 We are also
encouraged by the execution of the President’s Ratepayer Protection Pledge, through
168 See, e.g., National Grid November 21 ANOPR Comments at 16-17; New
England Consumer-Owned Systems November 21 ANOPR Comments at 4, 19-21; New
England Public Systems November 21 ANOPR Comments at 9-10.
169 PJM Show Cause Order, 190 FERC ¶ 61,115 at P 167.
170 Id. P 68.
171 See, e.g., EEI March 12 ANOPR Comments at Attach. 1, 9-13; NARUC
April 13 ANOPR Comments at 2-6 (noting examples of states acting to address large
load interconnection).
172 See, e.g., Commonwealth Edison Co. 194 FERC ¶ 61,106 (2026);
Commonwealth Edison Co., 194 FERC ¶ 61,109 (2026); Commonwealth Edison Co.,
194 FERC ¶ 61,110 (2026); Commonwealth Edison Co., 194 FERC ¶ 61,113 (2026);
PECO Energy Co., 193 FERC ¶ 61,148 (2025); Dayton Power & Light Co., 192 FERC
¶ 61,103 (2025); Dayton Power & Light Co., 189 FERC ¶ 61,220 (2024).
PDF page 46
Docket No. EL26-72-000
- 46 -
which data center developers have committed to shield retail ratepayers from increased
electricity prices.173
We expect that the additional cost transparency measures proposed in the
following section will give state public utility commissions and other state regulators the
information necessary to allow them to understand which transmission costs are caused
by which transmission customers, so that they can sub-allocate these costs to the
appropriate retail customers. Indeed, the Commission’s objective in this proceeding is to
respect the cooperative federalism approach established under the FPA. Specifically, one
of the benefits of providing transparency on the costs of network upgrades necessary to
provide transmission service to Eligible Customers on behalf of large loads is so that state
regulators can use that information to protect residential and small commercial customers
by incorporating those costs into the retail rates as they see fit given their authority to set
rates for different classes of retail customers. We encourage state public utility
commissions, state regulators, and state consumer advocates to submit comments
explaining whether this information is sufficient and granular enough or to submit
comments explaining precisely which additional information on transmission cost
allocation may be needed to inform proper state-jurisdictional cost allocation.
2.
Additional Cost Transparency
We preliminarily find that ISO-NE’s Tariff appears to be unjust and unreasonable
or unduly discriminatory or preferential because it does not contain provisions requiring
the provision of data on ISO-NE’s website in a single location, and in an easily accessible
format that is searchable and allows users to filter the data, on transmission service
requested by Eligible Customers on behalf of large loads, for network upgrades evaluated
in the local transmission planning process that are needed to provide transmission service
to Eligible Customers on behalf of those large loads, and the costs for those network
upgrades. We preliminarily find that cost transparency measures are needed to provide
stakeholders with sufficient information and visibility regarding the network upgrades,
and their associated costs, needed to provide transmission service to Eligible Customers
on behalf of large loads.
We recognize that there may have been limited large load growth in the ISO-NE
region so far; however, the record indicates the potential for large load growth in the
region and transmission owners are studying the need for network upgrades that will be
needed to provide transmission service to Eligible Customers on behalf of large loads.174
ISO-NE also included a forecast for large loads embedded in its 2026 CELT load
173 Proclamation No. 11014, 91 Fed. Reg. 11439 (Mar. 4, 2026).
174 See supra P 8.
PDF page 47
Docket No. EL26-72-000
- 47 -
forecast.175 ISO-NE’s Tariff does not appear to require that information identifying the
network upgrades needed to provide transmission service to Eligible Customers on behalf
of large loads and the costs of those network upgrades determined through local
transmission planning processes be readily available on ISO-NE’s website in a single
location, and in an easily accessible format that is searchable and allows users to filter the
data. The speed and scale with which Eligible Customers are seeking transmission
service on behalf of large loads makes it difficult for interested parties, including
transmission customers and state regulators, to accurately assess which transmission costs
are driven by requests for transmission service by Eligible Customers to serve large
loads. We are concerned that the potentially speculative nature of requests for
transmission service by Eligible Customers on behalf of large loads,176 the speed and
scale with which large loads might seek to be added to the transmission system, the
potential need for significant network upgrades to provide transmission service to
Eligible Customers on behalf of large loads, and the lack of centralized information on
the associated transmission costs in ISO-NE hamper the ability of the Commission and
stakeholders (including transmission customers and state regulators177) to understand and
accurately assess the relationship between the addition of large loads to the transmission
system and wholesale transmission costs.
We are concerned that without sufficient transparency regarding the network
upgrades, and their associated costs, needed to provide transmission service to Eligible
Customers on behalf of large loads, stakeholders may lack information and visibility
regarding the costs driven by large load additions. We preliminarily find that, for
network upgrades evaluated in the local transmission planning process178 that are needed
175 See ISO-NE Large Load Forecast Presentation at 14.
176 See supra P 54.
177 See Transcript, NARUC Collaborative, Docket No. AD24-7-000, at 16-17
(Feb. 11, 2026) (Chair Bagot, Virginia) (asserting that additional transparency at the RTO
level would help the states get the information they need to “identify . . . that bucket of
costs” related to large load-driven transmission costs), 19 (Commissioner Chattopadhyay,
New Hampshire) (noting the need for “all parties to be able to see things transparently”
with respect to wholesale transmission costs), 35-37 (Chair Martz, Iowa) (raising concern
that currently RTOs/ISOs do not have to clearly explain when a “bucket of costs is
specifically for this large load” and noting that “if we, at the state level, can’t see the
driver [of transmission costs], we can’t assign the cost to the causer[,] [a]nd so we need
that clarity”), 69-70 (Chair Myers, Arizona) (“[B]eing able to allocate the large load costs
to the correct bucket when it gets to the states is kind of a top priority.”).
178 Our concern with transparency regarding network upgrades needed to provide
transmission service to Eligible Customers on behalf of large loads, as well as the costs of
PDF page 48
Docket No. EL26-72-000
- 48 -
to provide transmission service to Eligible Customers on behalf of large loads, ISO-NE
must provide clear, timely, and detailed information regarding the extent to which
requests for transmission service by Eligible Customers on behalf of large loads
necessitate network upgrades to accommodate the transmission service to Eligible
Customers on behalf of large loads, as well as the costs of those network upgrades.
We note that centralized information regarding network upgrades needed to
accommodate requests for transmission service by Eligible Customers on behalf of large
loads would also help inform stakeholders at the state and local level to address
affordability and other challenges posed by the integration of large loads. Indeed,
commenters state that the opaque nature of requests for transmission service by Eligible
Customers on behalf of large loads, and the associated network upgrades required to
provide that transmission service, prevent wholesale and retail customers, states, and
other stakeholders from understanding such costs.179
Accordingly, we preliminarily find that ISO-NE’s Tariff appears to be unjust and
unreasonable because it does not require the provision of data on ISO-NE’s website in a
single location, and in an easily accessible format that is searchable and allows users to
filter the data, that identifies the network upgrades that are needed to accommodate
such upgrades, is limited to network upgrades planned through the local transmission
planning process. While we acknowledge that in Order No. 890, the Commission
adopted requirements for RTOs/ISOs, as well as for transmission owners to the extent
that they perform transmission planning within an RTO/ISO, to have open and
transparent transmission planning processes, there are additional requirements that apply
to regional transmission planning processes (that do not apply to local transmission
facilities) and thus is relevant to the distinction here. Specifically, under Order No. 1000,
public utility transmission providers, including RTOs/ISOs, must evaluate as part of their
regional transmission planning process whether there are transmission facilities that more
efficiently or cost-effectively meet the transmission planning region’s identified
transmission needs. See Order No. 1000, 136 FERC ¶ 61,051 at P 11.
179 See OCC November 21 ANOPR Comments at 3 (“Consumers, state advocates
and state regulatory commissions have a right to know which entities are seeking large-
load interconnections, the nature of the requested service, and how related costs could
flow through to transmission and distribution rates.”); U.S. House of Representatives
Committee on Energy and Commerce Ranking Members November 21 ANOPR
Comments at 2 (urging the Commission to “require sufficient transparency from grid
operators so it can determine which specific large load facilities are responsible for grid
upgrade needs”); CPUC November 21 ANOPR Comments at 16-17 (asserting that the
public posting of large load cost responsibility determinations would improve
transparency, to the benefit of businesses and ratepayers).
PDF page 49
Docket No. EL26-72-000
- 49 -
requests for transmission service by Eligible Customers on behalf of large loads, and the
costs of those network upgrades. ISO-NE should explain whether the Tariff remains just
and reasonable without provisions that would require ISO-NE and the Participating
Transmission Owners to publicly post and regularly update data that details: (1) the
aggregate amounts of proposed large load additions in ISO-NE’s footprint, including the
aggregate amounts in each transmission pricing zone; (2) the planned network upgrades
needed to provide transmission service to Eligible Customers on behalf of large loads,
identified by type of equipment and network upgrades (e.g., new substation,
reconductoring, a new high-voltage transmission line) for each transmission service
request; and (3) cost estimates for those network upgrades; or propose such Tariff
revisions. ISO-NE and the Participating Transmission Owners should also consider what
other data related to transmission costs resulting from the provision of transmission
service to Eligible Customers on behalf of large loads would be useful to include on
ISO-NE’s website. To the extent there are concerns about data confidentiality, ISO-NE
and the Participating Transmission Owners should consider whether there are ways to
mitigate those concerns while still providing the necessary transparency.
3.
Cost Recovery Agreements
We next preliminarily find that ISO-NE’s Tariff appears to be unjust and
unreasonable because it lacks adequate mechanisms to mitigate the risk of cost shifting
among transmission customers, which may result in unjust and unreasonable rates for
transmission service. In particular, we are concerned about the apparent lack of a pro
forma cost recovery agreement between ISO-NE, the relevant transmission owner, and
the Eligible Customer taking transmission service on behalf of large loads that help
ensure that Eligible Customers bear the risk and are ultimately responsible for costs
incurred to provide transmission service, including the cost of network upgrades.
Several commenters discuss the risk of cost shifting among transmission
customers that could result from transmission service requests by Eligible Customers on
behalf of large loads.180 Commenters also argue that retail-level large load tariffs do not
protect wholesale transmission customers from cost shifting.181 Specifically, commenters
180 See, e.g., Buckeye November 21 ANOPR Comments at 8-13; APPA November
21 ANOPR Comments at 6 (“Wholesale transmission customers in particular could be
left shouldering massive costs if new large loads do not ultimately attain or maintain the
level of electricity demand that is being forecasted.”); NRECA November 21 ANOPR
Comments at 21 (noting the risk that other transmission customers could bear stranded
upgrade costs caused by large loads that they cannot absorb); TAPS November 21
ANOPR Comments at 22-24; California DWR November 21 ANOPR Comments at 8.
181 TAPS November 21 ANOPR Comments at 26 (“[A] number of state
commissions are moving forward with retail large load tariffs, which provide for varying
PDF page 50
Docket No. EL26-72-000
- 50 -
in the record contend that, while a retail-level large load tariff protects the load serving
entity taking wholesale transmission service and its retail customers, it fails “to provide
any mechanism to protect other wholesale transmission customers” from stranded
transmission costs.182 The Kansas Commission states that while its Large Load Power
Services rate plan that requires large loads to make minimum payments toward
transmission costs protects retail ratepayers from large-load driven transmission costs, it
cannot protect against cost shifting associated with regional transmission buildout where
“the large loads that formed the basis for the [regional] transmission plans do not
materialize, leaving only existing customers to pay for generational expansions of the
transmission grid.”183 TAPS contends, moreover, that it is not sufficient for the
Commission to rely on transmission owners to voluntarily file cost recovery agreements
to protect transmission customers from cost shifting for network upgrades.184 New
England Consumer-Owned Systems also assert that where costs arise solely from the
addition of new loads, shifting those costs to existing ratepayers would effectively require
ratepayers to subsidize new entrants.185
We are likewise concerned that there may be speculative transmission service
requests by Eligible Customers on behalf of large loads that could result in cost shifting
among transmission customers, which may lead to unjust and unreasonable increases in
jurisdictional transmission rates. When a transmission owner constructs network
upgrades to accommodate an Eligible Customer’s request for transmission service on
behalf of a large load, those transmission costs will be included in the transmission
owner’s transmission revenue requirement. If, however, the Eligible Customer takes less
transmission service than anticipated because the large load operates at a lower demand
than anticipated or fails to materialize at all, other transmission customers may see an
increase in transmission rates. In such a situation, those other transmission customers
protections, but may not require the revenues and minimum demand levels to be included
in wholesale transmission rates.”); Buckeye November 21 ANOPR Comments at 14-16;
Kansas Commission November 21 ANOPR Comments at 15-16.
182 Buckeye November 21 ANOPR Comments at 14-15; see TAPS November 21
ANOPR Comments at 26-27 & nn.50-51.
183 Kansas Commission November 21 ANOPR Comments at 11-12.
184 TAPS November 21 ANOPR Comments at 25-26 (noting that AES Ohio
“committed to reflecting the payments it received from the data center in its Commission-
jurisdictional transmission revenue requirement so that other customers are protected,” in
a Construction Service Agreement with Amazon).
185 New England Consumer-Owned Systems November 21 ANOPR Comments at
4, 19-20.
PDF page 51
Docket No. EL26-72-000
- 51 -
may have to pay for potentially unnecessary network upgrades that they neither caused
the need for nor benefit commensurately from. In other words, this introduces the risk
that costs may be unfairly shifted to other transmission customers, which may result in
those costs then being passed through to residential customers, among others.
ISO-NE’s Tariff does not require cost recovery agreements between ISO-NE, the
relevant transmission owner, and the Eligible Customer taking transmission service on
behalf of a large load. Such agreements would help ensure that the Eligible Customer
makes a minimum contribution to the transmission owner’s transmission revenue
requirement commensurate with the costs incurred to provide the requested transmission
service, including the costs of any needed network upgrades. Absent such cost recovery
agreements, we are concerned that there is no mechanism to help ensure that Eligible
Customers taking transmission service on behalf of large loads (as opposed to other
transmission customers) bear the risk of, and are ultimately responsible for, the costs
incurred to provide them with the requested transmission service, including the costs of
any needed network upgrades.
Accordingly, we preliminarily find that, in order to prevent unjust and
unreasonable cost shifting among transmission customers, it appears necessary for
ISO-NE, the relevant transmission owner, and the Eligible Customer taking transmission
service on behalf of a large load to enter into a cost recovery agreement that requires the
Eligible Customer to make a minimum contribution toward the transmission owner’s
transmission revenue requirement, if the Eligible Customer ultimately takes less
transmission service than anticipated because the large load does not materialize as
planned or is not developed at all. We preliminarily find that such cost recovery
agreements are necessary to help ensure that the Eligible Customer is responsible for
timely paying the costs of large load-driven transmission (i.e., the costs incurred to
provide them with the requested transmission service, including the costs of any needed
network upgrades), rather than having those costs paid by other transmission customers
that neither caused the need for nor benefit commensurately from those network
upgrades.186 Our preliminary finding is not intended to alter or call into question existing
regional cost allocation methods for network upgrades, but instead is focused on helping
to prevent cost shifting among transmission customers.
We note that several transmission owners and large load customers have filed cost
recovery agreements (Transmission Security Agreements or Construction Service
Agreements) with the Commission that guarantee minimum contributions from a large
load customer (rather than from the Eligible Customer taking transmission service on
behalf of the large load customer) to the transmission owner’s transmission revenue
186 See, e.g., Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1368
(D.C. Cir. 2004); Ill. Com. Comm’n v. FERC, 576 F.3d 470, 476 (7th Cir. 2009).
PDF page 52
Docket No. EL26-72-000
- 52 -
requirement.187 Although we decline to preliminarily find that cost recovery agreements
between the transmission owner and the large load customer (rather than the Eligible
Customer) are necessary to ensure just and reasonable transmission rates, we continue to
find that such agreements directly affect Commission-jurisdictional transmission rates.
Therefore, to the extent a transmission owner and a large load customer enter into a cost
recovery agreement (whether voluntarily or pursuant to state law) through which the
large load customer guarantees contributions to the transmission owner’s Commission-
jurisdictional transmission revenue requirement, we find that such an agreement should
be filed with the Commission.188 To reduce duplicative credit requirements and
transaction costs, we direct further briefing on whether it would be appropriate for such
an agreement to substitute for the requirement on the Eligible Customer to enter into a
cost recovery agreement with the transmission owner, if the agreement with the large
load customer provided comparable or greater protection against cost shifting among
transmission customers than an agreement between the transmission owner and the
Eligible Customer would.
In addition to our preliminary finding that ISO-NE’s Tariff is unjust and
unreasonable because it lacks a pro forma cost recovery agreement of this type, we also
preliminarily find that the minimum contribution required pursuant to such an agreement
should be based on the level of jurisdictional transmission service (in MW) requested by
the Eligible Customer on behalf of the large load. That figure is in turn tied to how
ISO-NE and/or Participating Transmission Owners will study the requested transmission
service and determine any necessary network upgrades that must be developed to provide
the requested transmission service. We note, however, that there may be other just and
reasonable methods for determining this minimum contribution, including methods that
account for potential timing differences between when costs are incurred to develop
needed Network Upgrades and the pace at which the large load ramps toward energizing
at its full level of requested service. We further preliminarily find that the cost recovery
agreement should include a credit support (or other financial security) requirement
sufficient to secure the obligations of the Eligible Customer taking transmission service
on behalf of a large load to pay the amounts owed pursuant to the cost recovery
agreement. We find that a cost recovery agreement with a specified minimum financial
contribution and financial security sufficient to secure such contribution is necessary to
mitigate cost shifting if the Eligible Customer ultimately takes less transmission service
than anticipated because the large load does not materialize as planned or is not
187 See supra note 172.
188 We emphasize that this finding is in no way intended to preempt or interfere
with the ability of states to implement ratepayer protection measures designed to mitigate
cost shifting among retail customers, such as through state-jurisdictional large load
tariffs.
PDF page 53
Docket No. EL26-72-000
- 53 -
developed at all. We preliminarily find that an Eligible Customer may include a credit
support or other financial security posted by a large load as part of a retail agreement to
avoid creating duplicative credit support requirements. ISO-NE should explain why such
a pro forma cost recovery agreement is not necessary to ensure just and reasonable rates,
or propose such a pro forma cost recovery agreement. To the extent that stakeholders
believe that other mechanisms could address our cost shifting concerns, we seek further
briefing as discussed below.189
Lastly, we expect that any payments made by an Eligible Customer to a
transmission owner pursuant to such a cost recovery agreement (or by a large load to a
transmission owner pursuant to other voluntary agreement) will be appropriately credited
toward transmission owners’ transmission revenue requirements consistent with the
Commission’s cost-of-service regulations.190 We preliminarily find that it appears
reasonable for filers of formula rates to provide a separate workpaper in the annual
informational filing describing how any payments made pursuant to a cost recovery
agreement are reflected in the transmission owner’s transmission formula rate.
Although the Commission’s concerns surrounding cost shifting described above
may not present the same as in other RTOs/ISOs, we remain concerned that cost shifting
may occur. We acknowledge that the requests for Regional Network Service by Eligible
Customers on behalf of large loads may be studied in a Cluster Study. We note that the
Cluster Study may result in network upgrades or new facilities that the Eligible Customer
requesting Regional Network Service on behalf of the large load is obligated to pay for,
including applicable study costs consistent with Commission policy and Schedules 11
and 12.191 However, we note that these cost allocation provisions in Schedules 11 and 12
may not be sufficiently clear as they do not specifically contemplate network upgrades or
facilities identified for the provision of Regional Network Service. We also remain
concerned that cost shifting may occur through the recovery of the Participating
Transmission Owners’ transmission revenue requirements for transmission projects
planned through the Local Transmission Planning Process due to speculative requests to
accommodate transmission service to serve large loads, i.e., where large loads do not
materialize or where the MW quantity of such large loads is lower than proposed, or
because of the study process used to evaluate the facilities needed, and the associated
costs, to accommodate the provision of transmission service to Eligible Customers on
behalf of large loads.
189 See infra P 122.
190 See 18 C.F.R. pt. 101 (2025).
191 ISO-NE Tariff, § II.21.1.
PDF page 54
Docket No. EL26-72-000
- 54 -
C.
Co-Location Arrangements and Load with Behind the Meter
Generation
The Commission recently addressed in the PJM region the need for sufficiently
clear and consistent tariff provisions addressing the rates, terms, and conditions that apply
to co-location arrangements and for transmission services that reflect an Eligible
Customer taking transmission service on behalf of Eligible Load192 that is willing and
able to limit its energy withdrawals from the transmission system under certain
conditions.193 As discussed below, ISO-NE’s Tariff appears to be unjust and
unreasonable because it lacks such provisions.
We direct ISO-NE and the Participating Transmission Owners, to the extent the
matters addressed herein implicate aspects of the Tariff over which they have the filing
rights, to explain whether the Tariff remains just and reasonable without provisions
addressing the rates, terms and conditions that apply to interconnection customers serving
co-located load and for Eligible Customers taking transmission service on behalf of
Eligible Load, or propose Tariff revisions establishing the rates, terms, and conditions
that apply to co-location arrangements.
1.
Definition
The PJM Co-Location Order adopted the following definition of co-located load:
a “configuration [that] refers to end-use customer load that is physically connected to the
facilities of an existing or planned Customer Facility on the Interconnection Customer’s
side of the Point of Interconnection to the PJM Transmission System.”194 The PJM
Co-Location Order used the term co-location arrangement when referring to both the co-
located load and the associated generator.195
For purposes of this order, it appears that it would be reasonable to define co-
located load as a configuration that refers to end-use customer load that is physically
connected to the facilities of an existing or planned generating facility on the generator
interconnection customer’s side of the point of interconnection to the RTO/ISO’s
192 As discussed below, for purposes of this order, we will use the term Eligible
Load to refer to co-located load and/or load with behind the meter generation. See infra
P 88.
193 PJM Co-Location Order, 193 FERC ¶ 61,217 at P 2; PJM Co-Location
Rehearing Order, 195 FERC ¶ 61,209 at PP 91-102.
194 PJM Co-Location Order, 193 FERC ¶ 61,217 at P 164 (alterations in original).
195 Id. P 3.
PDF page 55
Docket No. EL26-72-000
- 55 -
transmission system. In this order, we will also use the term co-location arrangement
when referring to both the co-located load and the associated generating facility.
ISO-NE’s Tariff does not define the term “Behind the Meter Generation.” For
purposes of this order, it appears reasonable based upon the record to refer to Behind the
Meter Generation (BTMG) similarly to how that term is used in the PJM Co-Location
Order, as a generating facility that delivers energy to load without using the transmission
system or any distribution facilities.196
For purposes of this order, we will use the term Eligible Load to refer to co-
located load and/or load with BTMG.197
2.
Jurisdiction
As explained in the PJM Co-Location Order, the Commission has exclusive
jurisdiction to oversee the interconnection of generating facilities to the interstate
transmission system, including where generators serve co-located load.198 The
Commission retains exclusive authority to regulate the procedures and agreements that
apply to the interconnection of a generator that will make wholesale sales, both where the
generator interconnects directly to the interstate transmission system and where a
generator interconnects to dual-use distribution facilities.199 Further, the Commission has
exclusive jurisdiction over the provision of transmission service to an Eligible Customer
on behalf of Eligible Load, provided that transmission of electricity is in interstate
commerce.200 As the Commission found in the PJM Co-Location Order, we continue to
acknowledge that the application of these principles depends on the specific facts and
circumstances presented in particular situations.201
196 See PJM Co-Location Order, 193 FERC ¶ 61,217 at P 7 n.19 (citing PJM,
Intra-PJM Tariffs, OATT, § I.1 (Definitions - A-B) (21.0.0)).
197 PJM Co-Location Rehearing Order, 195 FERC ¶ 61,209 at P 91.
198 PJM Co-Location Order, 193 FERC ¶ 61,217 at P 171 (citing 16 U.S.C.
§§ 824d, 824e; EPSA, 577 U.S. at 278).
199 Id. P 172 (citing Nat’l Ass’n of Regul. Util. Comm’rs v. FERC, 475 F.3d 1277,
1282 (D.C. Cir. 2007)).
200 Id. P 173.
201 Id. P 174.
PDF page 56
Docket No. EL26-72-000
- 56 -
Additionally, we reiterate that certain other aspects of co-location arrangements
fall squarely within the jurisdiction of the states. As we explained in the PJM Co-
Location Order, states retain exclusive authority over the specific terms of retail sales and
retail rate design, including retail cost allocation to the co-located load; which entities are
legally permitted to provide electricity to retail customers in co-location arrangements;
and which generating facilities are sited and allowed to serve co-located load.202
3.
Tariff Provisions
We preliminarily find that ISO-NE’s Tariff appears to be unjust and unreasonable
or unduly discriminatory or preferential because it does not contain provisions addressing
with sufficient clarity and consistency the rates, terms, and conditions of service that
apply to interconnection customers serving co-located load. We also preliminarily find
that ISO-NE’s Tariff appears to be unjust and unreasonable or unduly discriminatory or
preferential because it does not contain provisions addressing with sufficient clarity and
consistency transmission services that reflect that an Eligible Customer taking
transmission service on behalf of Eligible Load is willing and able to limit its energy
withdrawals from the transmission system under certain conditions.
The absence of such provisions may leave entities unable to determine what steps
they can or must take to effectuate co-location arrangements of various configurations.
One step includes determining how interconnection customers serving co-located load
may use generator interconnection processes in ISO-NE’s Tariff to facilitate their co-
location arrangements. A further step includes requiring interconnection customers
serving co-located load to specify the Eligible Customer taking transmission service on
behalf of the co-located load under the Tariff for purposes of assessing charges, including
the appropriate charges for wholesale services that should apply to such Eligible
Customers. Without such a common and consistent understanding of entities’
responsibilities relevant to co-location arrangements, many of which may significantly
affect rates and are realistically susceptible of specification,203 we are concerned that
these arrangements may be developed in a manner that is itself unjust and unreasonable
or that may result in unjust and unreasonable rates for other customers.
Moreover, as discussed further below, we are especially concerned that the
absence of Tariff provisions addressing transmission and ancillary service rates for
Eligible Customers taking transmission service on behalf of Eligible Load creates the
potential that Eligible Customers, on behalf of Eligible Load, may not be required to pay
for wholesale transmission services that they receive, as required by the cost causation
202 Id. PP 167-169.
203 Hecate Energy Greene Cnty. 3 LLC v. FERC, 72 F.4th 1307, 1312 (D.C. Cir.
2023).
PDF page 57
Docket No. EL26-72-000
- 57 -
principle. That principle provides that all Commission-jurisdictional rates and charges
must “reflect to some degree the costs actually caused by the customer who must pay for
them,”204 and that costs must be allocated in a manner that is at least roughly
commensurate with the benefits that entity receives.205
We preliminarily find that ISO-NE’s Tariff appears to be unjust and unreasonable
because it lacks sufficient clarity and consistency as to the rates, terms, and conditions of
service that apply to interconnection customers serving co-located load, including the
scope of the analyses ISO-NE performs as part of its existing study process to evaluate
the impacts of co-location arrangements, which may need to account for any potential
dynamic impacts of co-located load and any potential impacts of requests to modify an
existing generating facility’s interconnection service level to serve co-located load on
transmission system reliability. Additionally, in the PJM Co-Location Order, the
Commission found that it was necessary to clarify that interconnection customers seeking
to use new generating facilities to serve co-located load may (1) request interconnection
service at a level below the generating facility’s maximum facility output; (2) use
existing procedures to accelerate interconnection requests that satisfy certain tariff
criteria; and (3) request provisional interconnection service and surplus interconnection
service.206 As such, interconnection customers seeking to use their generating facilities
to serve co-located load have no means of knowing the appropriate mechanism for setting
forth the terms and conditions of co-location arrangements. We are concerned that the
details of such a process—including the existing rules and studies applicable to such
generator interconnection arrangements—are not sufficiently detailed in the Tariff to
ensure clarity for how interconnection customers may seek to serve co-located load.
Moreover, without an Eligible Customer designated to take transmission service on
behalf of a co-located load, there is no mechanism for ISO-NE to address situations in
which a co-located load withdraws energy from the transmission system.
Therefore, we preliminarily find that ISO-NE’s Tariff appears to be unjust and
unreasonable because it does not contain provisions addressing with sufficient clarity and
consistency the rates, terms, and conditions of service that apply to interconnection
customers serving co-located load. ISO-NE should explain whether the Tariff remains
just and reasonable without such provisions, or propose Tariff revisions.
204 Midwest ISO Transmission Owners v. FERC, 373 F.3d at 1368.
205 See, e.g., Ill. Com. Comm’n v. FERC, 576 F.3d at 476.
206 PJM Co-Location Order, 193 FERC ¶ 61,217 at PP 231-235. PJM’s
compliance filing proposing revisions in response to these directives was accepted in part
on April 16, 2026. PJM Interconnection, L.L.C., 195 FERC ¶ 61,030.
PDF page 58
Docket No. EL26-72-000
- 58 -
We have similar concerns regarding ISO-NE’s existing rate designs for
transmission and ancillary services that are used by Eligible Customers taking
transmission service on behalf of Eligible Load. The Commission has previously found
that co-located loads that are synchronized with the transmission system use and benefit
from at least some ancillary services and may be reasonably charged for such benefits. 207
Specifically, the Commission has found that, regardless of whether a co-located load
withdraws energy from the transmission system, co-located load relies on and benefits
from regulation service and black start service, and concluded that Eligible Customers
taking one of the new transmission services (discussed below) on behalf of co-located
load must pay for these ancillary services on a gross demand basis.208 In the PJM
Co-Location Rehearing Order, the Commission applied these findings to Eligible
Customers taking transmission service on behalf of load with BTMG.209 However, ISO-
NE’s Tariff does not appear to include a mechanism by which an Eligible Customer, on
behalf of Eligible Load, would be charged for ancillary services commensurate with its
usage of such services, particularly if such customer did not withdraw energy from the
transmission system. We note that New England Consumer-Owned Systems asserts that
co-location arrangements could allow large loads to bypass transmission, energy,
capacity, and ancillary service charges while shifting those costs to regional transmission
customers.210
Therefore, we preliminarily find that ISO-NE’s Tariff appears to be unjust and
unreasonable because it does not address whether and how Eligible Customers taking one
of the new transmission services on behalf of Eligible Loads will be charged for their use
of regulation and black start services, which introduces the risk that Eligible Load may
benefit from regulation and black start services without contributing to cost recovery for
such services. As noted in the PJM Co-Location Order, this introduces the risk that costs
may be allocated entirely to other transmission customers and passed through to
residential customers, among others.211 ISO-NE should explain whether the Tariff
remains just and reasonable without requiring Eligible Customers taking one of the new
transmission services on behalf of Eligible Loads to pay for regulation and black start
services on a gross demand basis, or propose Tariff revisions that require them to do so.
207 PJM Co-Location Order, 193 FERC ¶ 61,217 at P 183.
208 Id. PP 184-185.
209 See PJM Co-Location Rehearing Order, 195 FERC ¶ 61,209 at P 400.
210 New England Consumer-Owned Systems November 21 ANOPR Comments at
3, 13-16.
211 See PJM Co-Location Order, 193 FERC ¶ 61,217 at P 159.
PDF page 59
Docket No. EL26-72-000
- 59 -
The Commission also found in the PJM Co-Location Order that Eligible
Customers taking transmission service on behalf of co-located loads are willing and able
to limit their energy withdrawals from the transmission system under certain conditions.
As such, the Commission found that Eligible Customers taking transmission service on
behalf of co-located loads should be allowed to choose a transmission service that aligns
with their use of the transmission system and therefore aligns the charges for service with
the benefits received.212 On rehearing, the Commission found that it is just and
reasonable for these services to be available to Eligible Customers taking transmission
service on behalf of loads with BTMG.213 We are concerned that ISO-NE’s Tariff lacks
transmission services that would reflect the ability of Eligible Customers on behalf of
Eligible Loads to take transmission services that align with their use of the transmission
system, which may result in inefficient and costly transmission buildout and costs paid by
transmission customers.214
Therefore, we also preliminarily find that ISO-NE’s Tariff appears to be unjust
and unreasonable because it does not include transmission services that reflect Eligible
Customers taking transmission service on behalf of Eligible Load that are willing and
able to limit their use of the transmission system under certain conditions. ISO-NE
should explain whether the Tariff remains just and reasonable without the transmission
services described by the Commission in the PJM Co-Location Order, with regional
variation as appropriate, being available to Eligible Customers taking transmission
service on behalf of Eligible Load, or propose appropriate Tariff revisions. Specifically,
ISO-NE should explain whether the Tariff remains just and reasonable without (1) an
interim non-firm network transmission service while network upgrades are being
constructed (i.e., interim NITS) and (2) permanent firm and non-firm contract demand
transmission services (transmission service up to a specified MW quantity, i.e., the
contract level, on a firm or non-firm basis). We note that the Commission has found it
just and reasonable that, in order for an Eligible Customer to take interim NITS, firm
contract demand transmission service, and non-firm contract demand transmission
service, an Eligible Customer must have necessary control technologies and/or protection
212 Id. P 199.
213 PJM Co-Location Rehearing Order, 195 FERC ¶ 61,209 at PP 101-103.
214 See, e.g., PSEG November 21 ANOPR Comments at 20 (“The Commission’s
long-standing policy is to encourage reduced use of the transmission system, which
would in turn reduce upgrades to the transmission system, to the benefit of all
transmission customers. For instance, if a co-located load’s use of the transmission
system is limited (or to a lesser degree) than other traditional in front of the meter loads,
it should be responsible for costs based on its limited use.”).
PDF page 60
Docket No. EL26-72-000
- 60 -
systems, which may include a special protection scheme, to limit its energy withdrawals
to its approved level.215
Finally, we preliminary find that ISO-NE’s Tariff is unjust and unreasonable
because it allows load with BTMG to net its BTMG against its load for purposes of
calculating Regional Network Service charges. In the PJM Co-Location Order, the
Commission found that PJM’s BTMG rules, which allowed load serving entities that
provide service to loads with qualifying BTMG to reduce their costs by netting output
from BTMG in the calculation of their peak demand for the purpose of determining NITS
charges, were unjust and unreasonable.216 The Commission concluded that PJM’s
BTMG rules were no longer consistent with cost causation principles because large loads
configured in a BTMG arrangement with significant generation will raise cost shifting
concerns compared to loads pursuing smaller amounts of netting.217 The Commission
also found that such rules could lead to reliability and resource adequacy risks because
PJM is obligated to serve transmission customers using BTMG, but does not consider
such customers in transmission and resource adequacy planning.218 The Commission
directed PJM to revise its retail BTMG rules, including establishing a MW threshold for
the amount of load at a particular electrical location that network customers may net by
using BTMG.219 We are similarly concerned that ISO-NE’s Tariff allows Network
Customers that provide service to loads with BTMG to reduce their Regional Network
Service charges because the definition of Monthly Regional Network Load, which is used
to calculate the Regional Network Service charge, excludes load offset by the portion of
the output of a Generator Asset that serves load located behind the same retail customer
meter as the Generator Asset.220 ISO-NE should explain whether the Tariff remains just
and reasonable even though it allows netting of BTMG from load for purposes of
determining Regional Network Service charges for loads configured in a BTMG
arrangement or propose Tariff revisions. Recognizing potential impacts on existing
customers, we note that ISO-NE may explain whether current BTMG rules for customers
that fall below a new MW materiality threshold for the amount of load at a particular
215 PJM Co-Location Rehearing Order, 195 FERC ¶ 61,209 at P 480.
216 PJM Co-Location Order, 193 FERC ¶ 61,217 at PP 7, 186.
217 Id. P 186.
218 Id.
219 Id. P 221.
220 ISO-NE Tariff, § II.21.2; see also ISO New Eng. Inc., 178 FERC ¶ 61,086
(2022).
PDF page 61
Docket No. EL26-72-000
- 61 -
electrical location that Network Customers may net using BTMG remain just and
reasonable.
D.
Extending New Transmission Services to Eligible Customers Taking
Service on Behalf of Flexible Large Loads
In response to the ANOPR, a number of commenters argue that certain large loads
are able to limit their withdrawals from the transmission system under certain conditions.
Namely, commenters observe that flexible large loads221 can quickly and verifiably adjust
their consumption in response to system conditions or price signals.222 Commenters in
the ANOPR also observe that, where load studies and system planning consider the
flexible nature of large loads, flexible large loads can potentially defer or reduce the need
for network upgrades, among other potential benefits.223 In recognition of this flexibility,
many commenters support new transmission services that reflect the operational
capabilities of flexible large loads, including interim NITS while network upgrades are
constructed, and non-firm transmission service.224
221 For purposes of this order, “flexible” large loads are a subset of large loads, as
used in this order, that are not co-located with generation, but are willing and able to limit
their energy withdrawals from the transmission system under certain conditions.
222 See, e.g., AEMA November 21 ANOPR Comments at 1-2; Land Trust Alliance
November 21 ANOPR Comments at 10; California DWR November 21 ANOPR
Comments at 5; CEBA November 21 ANOPR Comments at 14-15; ClearPath November
21 ANOPR Comments at 2-4; Digital Energy Council November 21 ANOPR Comments
at 1; EDF Power November 21 ANOPR Comments at 4; Emerald November 21 ANOPR
Comments at 2; Verrus November 21 ANOPR Comments at 4.
223 See, e.g., AEMA November 21 ANOPR Comments at 5; ELCON November
21 ANOPR Comments at 9; Emerald November 21 ANOPR Comments at 6-7; Institute
for Progress November 21 ANOPR Comments at 11; Land Trust Alliance November 21
ANOPR Comments at 10; LS Power November 21 ANOPR Comments at 5; Microsoft
November 21 ANOPR Comments at 10-11; National Grid November 21 ANOPR
Comments at 19-20; OMS November 21 ANOPR Comments at 13-14; Southeast PIOs
November 21 ANOPR Comments at 50.
224 See, e.g., Constellation November 21 ANOPR Comments at 24-25; Calibrant
November 21 ANOPR Comments at 2-4; Critical Loop November 21 ANOPR
Comments at 2; Digital Power Network November 21 ANOPR Comments at 3; PIOs
November 21 ANOPR Comments at 27-28; Splight November 21 ANOPR Comments at
3-4.
PDF page 62
Docket No. EL26-72-000
- 62 -
We preliminarily find that ISO-NE’s Tariff appears to be unjust and unreasonable
because it does not include transmission services that reflect Eligible Customers taking
transmission service on behalf of flexible large loads that are willing and able to limit
their use of the transmission system under certain conditions. The transmission services
available to Eligible Customers, including on behalf of flexible large loads, in ISO-NE
are Regional Network Service, Local Network Service, and firm and non-firm Local
Point-to-Point Transmission Service.225 While these remain just and reasonable options
for an Eligible Customer to take on behalf of a flexible large load, based on the record
before us, we preliminarily find that new transmission services should be available to
reflect the operational reality that large loads may use the transmission system to
differing extents and certain large loads are willing and able to limit their use of the
transmission system under certain conditions.226 As explained above, the Commission
found that Eligible Customers taking transmission service on behalf of Eligible Load
should be allowed to choose a transmission service that aligns with their use of the
transmission system and therefore aligns the charges for service with the benefits
received.227 As the record suggests, Eligible Customers taking transmission service on
behalf of flexible large load also may be willing and able to limit their use of the
transmission system under certain conditions. As recognized in the ANOPR record, load
flexibility can avoid inefficient and costly transmission system build-out.228 In addition,
transmission services that reflect that flexible large loads are willing and able to limit
their withdrawals from the transmission system under certain conditions could help
225 See supra P 20 (describing existing transmission services in ISO-NE).
226 See supra P 101.
227 PJM Co-Location Order, 193 FERC ¶ 61,217 at P 199; PJM Co-Location
Rehearing Order, 195 FERC ¶ 61,209 at P 103.
228 See supra P 101; see also PJM Co-Location Order, 193 FERC ¶ 61,217 at
PP 160, 177, 199 (finding that new transmission service options reflect a co-located
load’s ability to limit withdrawals from the transmission system and potentially avoid
costly and inefficient transmission system buildout that may not be necessary).
PDF page 63
Docket No. EL26-72-000
- 63 -
timely interconnect flexible large loads.229 Entities in the ISO-NE footprint acknowledge
the importance of facilitating load flexibility.230
Therefore, we are concerned that ISO-NE’s Tariff does not include transmission
services that reflect the use of the transmission system by Eligible Customers on behalf of
flexible large load, on both an interim and permanent basis. ISO-NE should explain
whether the Tariff remains just and reasonable without the transmission services
described by the Commission in the PJM Co-Location Order, with regional variation as
appropriate, being available to Eligible Customers taking transmission service on behalf
of flexible large loads, or propose appropriate Tariff revisions. Specifically, ISO-NE
should explain whether the Tariff remains just and reasonable without (1) an interim
non-firm network transmission service while network upgrades are being constructed
(i.e., interim NITS) and (2) permanent firm and non-firm contract demand transmission
services (transmission service up to a specified MW quantity, i.e., the contract level, on a
firm or non-firm basis). Finally, we note that the Commission has found it just and
reasonable that, in order for an Eligible Customer to take interim NITS, firm contract
demand transmission service, and non-firm contract demand transmission service, an
Eligible Customer must have necessary control technologies and/or protection systems,
which may include a special protection scheme, to limit its energy withdrawals to its
approved level.231
E.
Interconnection Customers Serving Electrically Proximate Large Load
and Co-Located Load
In response to the ANOPR, a number of commenters agree that the ability to study
new load and new generation together, when physically or electrically proximate,
presents system benefits and can help address the challenges posed by large load
additions.232 Commenters argue that studies that consider large load and generation
229 See supra P 101; see also PJM Co-Location Order, 193 FERC ¶ 61,217 at
PP 201 (finding that the interim, non-firm transmission service will facilitate the “timely”
provision of transmission service and that “[t]his willingness to curtail would potentially
allow them to obtain service more quickly”), 205 (recognizing that parties argue that co-
located loads may be able to receive transmission service faster with use of a new, limited
transmission service product than they would if they selected NITS, to the extent that
providing NITS would require network upgrades that the limited transmission service
would not).
230 See, e.g., Maine Public Advocate November 21 ANOPR Comments at 4-5;
State Entities November 21 ANOPR Comments at 8.
231 PJM Co-Location Rehearing Order, 195 FERC ¶ 61,209 at P 480.
232 See e.g., DCC November 21 ANOPR Comments at 5-6; DTE November 21
PDF page 64
Docket No. EL26-72-000
- 64 -
together present a more complete picture of the grid and can enable the identification of
more accurate, efficient, and cost-effective transmission solutions by minimizing system
impacts.233 As a result, this can speed up the interconnection process for both large loads
and generation, and shorten energization timelines,234 which commenters contend
reduces uncertainty for both parties235 and “is necessary to match the pace of AI
innovation in the United States.”236 CEBA also highlights that cost and timeline factors
drive developers to submit multiple requests for price and timing discovery, which
inflates queue volumes, distorts demand and supply forecasts, and causes significant
delays when projects withdraw late after finding costs or energization timelines
uneconomic.237 Other benefits to a joint study identified by commenters include
improving load forecasting and siting decisions238 and reducing the need for critical
supply chain components.239
Commenters contend that current generator interconnection study processes may
not adequately capture generation and load, including by failing to model known
electrically proximate large load in base case assumptions, which may result in inaccurate
ANOPR Comments at 11; Google November 21 ANOPR Comments at 7; International
Energy Credit Association November 21 ANOPR Comments at 10; Terraflux November
21 ANOPR Comments at 1.
233 AEU November 21 ANOPR Comments at 13; ClearPath November 21
ANOPR Comments at 4; DCC November 21 ANOPR Comments at 5; DTE November
21 ANOPR Comments at 8-11; ENGIE November 21 ANOPR Comments at 6; Entergy
November 21 ANOPR Comments at 5; Geronimo November 21 ANOPR Comments at
17-18; Information Technology Industry Council November 21 ANOPR Comments at 2.
234 DCC November 21 ANOPR Comments at 5; DTE November 21 ANOPR
Comments at 8-11; Information Technology Industry Council November 21 ANOPR
Comments at 2; Microsoft November 21 ANOPR Comments at 8-9; Verrus December 5
ANOPR Comments at 9.
235 ClearPath November 21 ANOPR Comments at 4; CEBA November 21
ANOPR Comments at 8.
236 Microsoft November 21 ANOPR Comments at 8-9.
237 CEBA November 21 ANOPR Comments at 8.
238 ELCON November 21 ANOPR Comments at 5; Maryland Commission
November 21 ANOPR Comments at 6-7.
239 AEU November 21 ANOPR Comments at 13.
PDF page 65
Docket No. EL26-72-000
- 65 -
studies and inefficient system build-out.240 For example, Eolian states that in its
experience developing a project in PJM, the failure of the generator interconnection study
process to reflect reasonably expected load conditions on the grid models triggered overly
costly network upgrades and caused the cancellation of generation project that could have
reliably served adjacent load growth.241
Commenters in the ANOPR proceeding argue that the current state of the
generator interconnection queue is not meeting the expeditious time frame needed to
match the pace of large load additions and ensure the safe and reliable interconnection of
these loads.242 For example, Oracle states that one of the most significant and
widespread delays it encounters when siting data centers in the U.S. is access to sufficient
energy.243 Similarly, Helion contends that more than half of U.S. developers now
identify interconnection delays as the single biggest barrier to adding new generation
capacity.244 Commenters contend that if large load interconnection proceeds more
quickly than new generation can come online, the result could be price increases for
consumers.245
A number of commenters support expedited interconnection studies for new
generation paired with load.246 Some commenters argue that one solution to generator
240 Base Power November 21 ANOPR Comments at 7; Eolian November 21
ANOPR Comments at 18-19; Eolian May 19 ANOPR Comments at 2; Longroad
November 21 ANOPR Comments at 8.
241 Eolian May 19 ANOPR Comments at 10.
242 See, e.g., AEP December 5 ANOPR Comments at 1; DCC November 21
ANOPR Comments at 8; esVolta November 21 ANOPR Comments at 11-12; Oracle
May 1 ANOPR Comments at 4.
243 Oracle November 21 ANOPR Comments at 1.
244 Helion November 21 ANOPR Comments at 1 (citing Third Way, Picking Up
the PACE: A Comprehensive Analysis of Available Pathways to Accelerating Clean
Energy (PACE) (Nov. 2025)).
245 AEP December 5 ANOPR Comments at 1-2; OPSI November 21 ANOPR
Comments at 6-7, 11.
246 See, e.g., DTE November 21 ANOPR Comments at 8; ENGIE November 21
ANOPR Comments at 4; International Energy Credit Association November 21 ANOPR
Comments at 8; Meta November 21 ANOPR Comments at 5-6; Ohio FEA November 21
ANOPR Comments at 5.
PDF page 66
Docket No. EL26-72-000
- 66 -
interconnection delays may be the creation of time-limited or conditional interconnection
service for generators serving large loads, which could require less time for initial
generator interconnection studies and improve speed to power.247 For example, several
commenters express support for SPP’s HILLGA proposal as a model and urge the
Commission to establish nationwide rules similar to that approach.248 Other commenters
suggest reforms to expedite studies for new generation paired with large loads at existing
points of interconnection that have already been studied, arguing it is unjust and
unreasonable not to fully utilize existing infrastructure and proven reliability paths while
new load waits for service.249
1.
Jurisdiction
The Commission’s statutory authority includes jurisdiction over the wholesale sale
and transmission of electricity in interstate commerce, including the facilities used for
such sale and transmission.250 The Commission also has exclusive jurisdiction to
regulate the procedures and agreements applicable to generating facilities seeking to
interconnect to a Commission-jurisdictional distribution facility or transmission
facility.251 In the PJM Co-Location Order, the Commission observed that a generator’s
interconnection to the interstate transmission system “does not fall outside of the
Commission’s jurisdiction merely because there is [c]o-[l]ocated [l]oad behind the
247 AEP December 5 ANOPR Comments at 12; AEU November 21 ANOPR
Comments at 13; Google December 5 ANOPR Comments at 15; see also Duke
November 21 ANOPR Comments at 21-22.
248 AEP December 5 ANOPR Comments at 4; Crusoe December 5 ANOPR
Comments at 7; Enchanted Rock November 21 ANOPR Comments at 4; Google
November 21 ANOPR Comments at 7; GridStor November 21 ANOPR Comments at 5;
Verrus November 21 ANOPR Comments at 9.
249 Constellation June 5 ANOPR Comments at 8-9.
250 16 U.S.C. § 824(b)(1).
251 Id.; Nat’l Ass’n of Regul. Util. Comm’rs v. FERC, 475 F.3d at 1280-82
(affirming Order No. 2003 and observing that “interconnections appear to be
relationships between parties with respect to electricity flowing over facilities. . . . By
establishing standard agreements [the Commission] has exercised its jurisdiction over
the terms of those relationships.”); see Pac. Gas & Elec. Co., 115 FERC ¶ 61,193 at P 36
(“[I]interconnection is part and parcel of transmission of electric energy in interstate
commerce, and thus interconnection service is part and parcel of jurisdictional
transmission service.”).
PDF page 67
Docket No. EL26-72-000
- 67 -
generator’s point of interconnection.”252 By the same token, the Commission retains
jurisdiction over a generator’s interconnection even where the generator plans to serve an
electrically proximate large load.
We recognize that states have exclusive authority over resource planning and the
generation mix within their boundaries.253 Nothing about our preliminary finding here,
however, intrudes or is intended to intrude on that exclusive authority. Rather, we
preliminarily find that it is necessary and appropriate to exercise our exclusive
jurisdiction over generator interconnection to ensure the availability of generator
interconnection processes specifically tailored to the unique operational characteristics of
generating facilities dedicated to serving electrically proximate large loads and co-located
loads, as defined below. The Commission has exercised this jurisdiction previously in
requiring generator interconnection services that allow certain generating facilities to
interconnect more quickly through the use of provisional interconnection service and
surplus interconnection service,254 and has approved interconnection processes that allow
certain generating facilities to interconnect more quickly by replacing a retiring existing
generating facility.255
2.
Definitions
For purposes of this order, it appears to be reasonable to use the term “electrically
proximate large load” to mean a large load, as defined in this order,256 that is sufficiently
electrically close to the interconnection customer’s requested point of interconnection,
such that the impact on the transmission system of the combination of the generating
facility and the load, with the exception of the transmission facilities between the two,
will be effectively the same as if they were located at the same substation (e.g., large load
that is located no more than two substations away from the generating facility). We will
252 PJM Co-Location Order, 193 FERC ¶ 61,217 at P 171.
253 See, e.g., Citizens Action Coal. of Ind., Inc. v. FERC, 125 F.4th at 238 (citing
16 U.S.C. § 824(b)(1)).
254 Reform of Generator Interconnection Procs. & Agreements, Order No. 845,
163 FERC ¶ 61,043, at PP 438, 467 (2018), order on reh’g & clarification, Order No.
845-A, 166 FERC ¶ 61,137, order on reh’g & clarification, Order No. 845-B, 168
FERC ¶ 61,092 (2019); Order No. 2023, 184 FERC ¶ 61,054 at P 1436; PJM
Interconnection, L.L.C., 190 FERC ¶ 61,083 (2025).
255 See, e.g., PJM Interconnection, L.L.C., 194 FERC ¶ 61,079 (2026);
Midcontinent Indep. Sys. Operator Inc., 167 FERC ¶ 61,146 (2019).
256 See supra P 56.
PDF page 68
Docket No. EL26-72-000
- 68 -
consider proposed revisions to this definition that ensure it is appropriately tailored to
ISO-NE’s transmission system.
3.
Tariff Provisions
We preliminarily find that ISO-NE’s Tariff appears to be unjust and unreasonable
because it does not contain provisions allowing an interconnection customer to seek the
generator interconnection service(s) that reflects the operational dynamics of serving
either: (1) an electrically proximate large load; or (2) a co-located load, as defined in this
order,257 that has a high peak load (i.e., large co-located loads that are 50 MW or
greater).258 Specifically, we preliminarily find that ISO-NE’s Tariff appears to be unjust
and unreasonable because it lacks a generator interconnection study process and/or
generator interconnection service to reflect an interconnection customer’s commitment in
an interconnection agreement to limit the generating facility’s output to minimize the
impact on the transmission system while serving an electrically proximate large load or
large co-located load. We are concerned that ISO-NE’s Tariff lacks, for example,
generator interconnection study procedures and generator interconnection services that
reflect (a) an interconnection customer’s commitment in an interconnection agreement to
limit a generating facility’s output to match the hourly forecast of an electrically
proximate large load or large co-located load; and/or (b) a generating facility with
necessary control technologies and/or protection systems, which may include a special
protection scheme,259 that ensure that the injection does not exceed the limit in the
existing or new interconnection agreement. Where a generating facility’s output is
matched to the demand of the electrically proximate large load or large co-located load or
if the generating facility’s output is limited to ensure no new injection, the impacts to the
transmission system of interconnecting the generating facility to serve that electrically
proximate large load or large co-located load may be limited,260 thereby potentially
reducing the need for network upgrades, which can accelerate the generator
257 See supra P 86.
258 We note that generator interconnection service in and of itself does not convey
transmission service.
259 PJM Co-Location Rehearing Order, 195 FERC ¶ 61,209 at P 480.
260 In other words, because the generating facility and load are located so closely
on the transmission system, if the generating facility’s output matches the load’s demand,
then the transmission provider would need to study only the local impacts because the
impact on the transmission system of the combination of the generating facility and the
load, with the exception of the transmission facilities between the two, will be effectively
the same as if they were located at the same substation.
PDF page 69
Docket No. EL26-72-000
- 69 -
interconnection process.261 In the absence of Tariff provisions accounting for these
operational dynamics when an interconnection customer’s generating facility is serving
electrically proximate large loads or large co-located loads, new shovel-ready generating
facilities may face unnecessary delays in reaching commercial operation under current
generator interconnection processes and will be unable to serve the immediate demand of
new large loads or large co-located loads.262
As commenters in the ANOPR proceeding have recognized, the status quo may
result in inefficient and unnecessary development of infrastructure, which leads to
unnecessarily higher network upgrade costs that may result in unjust and unreasonable
rates.263 The Commission has already determined in the PJM Co-Location Order that
without the new transmission services that reflect the operational dynamics of co-location
arrangements, there could be unnecessary, costly, and inefficient network upgrades,
increasing network upgrades costs.264 The same result may occur in the absence of new
261 See, e.g., AEU November 21 ANOPR Comments at 13 (“To the extent that a
new large load and new generation or storage resource are geographically and electrically
proximate, studying them together would reduce network upgrades, lower costs, and
reduce the need for critical supply chain components.”); DTE November 21 ANOPR
Comments at 10 (integrating the study of load and its supporting generation “reduces the
need for network upgrades, optimizes the use of existing infrastructure, and accelerates
the timeline for bringing both load and generation online”); Eolian November 21 ANOPR
Comments at 18 (“It is obvious from basic engineering principles that generation located
near load requires less transmission infrastructure to serve that load than generation
located distant from load.”); GridStor November 21 ANOPR Comments at 5 (“Siting a
large load near or at the same point of interconnection as a new generating facility could
reduce the network upgrades needed to interconnect only the load or only the generating
facility.”).
262 See AEP December 5 ANOPR Comments at 1; Base Power November 21
ANOPR Comments at 7; CEBA November 21 ANOPR Comments at 8; DCC November
21 ANOPR Comments at 6 (asserting that a clear framework to study large loads paired
with generation would resolve development bottlenecks); Eolian November 21 ANOPR
Comments at 18-19; Eolian May 19 ANOPR Comments at 2; Google November 21
ANOPR Comments at 7 (calling for nationwide rules enabling proximate load-generation
interconnection to “accelerate the pace at which new generation comes online”);
Longroad November 21 ANOPR Comments at 8.
263 See, e.g., AEU November 21 ANOPR Comments at 13, AEP December 5
ANOPR Comments at 1-2; Longroad November 21 ANOPR Comments at 8; OPSI
November 21 ANOPR Comments at 11.
264 PJM Co-Location Order, 193 FERC ¶ 61,217 at P 177 (“[F]or Eligible
PDF page 70
Docket No. EL26-72-000
- 70 -
generator interconnection study procedures and generator interconnection services
tailored to a new generating facility coming online for the express purpose of serving an
electrically proximate large load or large co-located load.265
SPP recognized this problem and submitted an FPA section 205 filing to
implement a new, interim, generator interconnection service and related generator
interconnection process, HILLGA, to facilitate the prompt interconnection of generating
facilities that are specifically identified for and limited to serving a HILL, which the
Commission accepted.266 The Commission found that HILLGA “reasonably provides a
flexible, expedited, and separate serial interconnection process that will facilitate the
prompt interconnection of generating facilities that are limited to serving a HILL in the
same local area.”267 We do not expect or propose that ISO-NE adopt an identical process
to SPP’s HILLGA process, nor do we preliminarily find that the absence of Tariff
provisions specifically mirroring SPP’s Tariff renders ISO-NE’s Tariff unjust and
unreasonable. Nevertheless, we remain concerned that the Tariff may be unjust and
unreasonable without any uniquely tailored interconnection study process and/or
generator interconnection service to recognize the reduced transmission system impacts
that may result from the interconnection of a generating facility where the
interconnection customer has committed, in an interconnection agreement, to limit the
generating facility’s output to match the hourly forecast of an electrically proximate large
load or large co-located load.268 To the extent that the interconnection customer’s
Customers taking service on behalf of Co-Located Loads that do not reserve
transmission . . . requiring such Eligible Customers to take NITS on behalf of these
Co-Located Loads may in some circumstances result in costly and inefficient
transmission system buildout that may not be necessary if such Eligible Customers are
willing and able to take a transmission service that requires fewer Network Upgrades to
provide, and therefore may result in lower Network Upgrade costs, than would NITS.”).
265 See AEP December 5 ANOPR Comments at 1-2 (stating that current processes
produce insufficient/inefficient infrastructure and “potentially unsustainable price
increases”); Eolian May 19 ANOPR Comments at 2, 10 (contending that a lack of
coordinated study leads to unjust and unreasonable outcomes).
266 SPP HILL Order, 194 FERC ¶ 61,031.
267 Id. P 64.
268 While, as discussed above, we view such a process that permits generation to
serve electrically proximate loads no more than two substations away from the generators
to be reasonable, we understand the unique features of ISO-NE’s transmission system
may warrant consideration of a more limited definition of electrically proximate. See
Duke November 21 ANOPR Comments at 21-22; DTE November 21 ANOPR
PDF page 71
Docket No. EL26-72-000
- 71 -
generating facility is serving an electrically proximate large load, we believe that the
generator interconnection service should be of an interim nature until the interconnection
customer obtains Energy Resource Interconnection Service (ERIS) or Network Resource
Interconnection Service (NRIS). To the extent that the interconnection customer’s
generating facility is serving a large co-located load, it may be reasonable for the
generator interconnection service to be permanent because there will be no injections
onto the transmission system and therefore it does not present operational or planning
risks for reliability.
Another potentially reasonable approach could be to develop a generator
interconnection study process that would allow the use of existing ERIS or NRIS of an
existing generator to connect a new generating facility and a new large load behind the
same point of interconnection of the existing generator with necessary control
technologies and/or protection systems, which may include a special protection scheme,
that ensure that the net injection does not exceed the amount in the existing generator
interconnection agreement.269 Such an approach could expedite the interconnection
study process for a generator planning to serve an electrically proximate (in this case at
the same point of interconnection) large load.270 An additional potentially reasonable
approach could be a new load-limited generator interconnection service that allows a new
generating facility and new large co-located load seeking to interconnect behind the same
new point of interconnection, with necessary control technologies and/or protection
systems, which may include a special protection scheme, to ensure that there is no
injection to the transmission system.271 It may be reasonable for such a load-limited
generator interconnection service to be or not to be of an interim nature. We invite
ISO-NE and/or Participating Transmission Owners, in responding to this order or in an
FPA section 205 filing, to submit original proposals designed to address the concerns
expressed herein and tailored to their unique circumstances.
Comments at 8-11 (asserting that studying large loads with electrically proximate
generation streamlines interconnection and reduces upgrades); AEU November 21
ANOPR Comments at 13-15.
269 See Constellation June 5 ANOPR Comments at 1-2, 10-13.
270 See id. at 5 (explaining that when new generation load pairings “are sited at an
existing generator’s Point of Interconnection and fall within the same study parameters
reflected by that existing generator’s interconnection, they benefit from studies and
upgrades already completed for that existing generator and can come on more rapidly
without jeopardizing reliability”).
271 See MISO November 21 ANOPR Comments at 13; see also MISO TOs April 3
ANOPR Comments at 13-14.
PDF page 72
Docket No. EL26-72-000
- 72 -
We are concerned that the absence of generator interconnection study procedures
and generator interconnection services facilitating the interconnection of a new
generating facility that is being brought onto the transmission system in order to serve an
electrically proximate large load or large co-located load will result in ISO-NE’s current
generator interconnection process failing to keep pace with the new large loads seeking to
be integrated onto ISO-NE’s transmission system.272 We preliminarily find that this
outcome may be unjust and unreasonable because reliance on ISO-NE’s current generator
interconnection processes for generating facilities serving electrically proximate large
loads or large co-located loads could result in unnecessary interconnection delays,
unnecessary network upgrades, and an otherwise inefficient expansion of the
transmission system, imposing unnecessary delays and costs on transmission customers.
ISO-NE should explain whether the Tariff remains just and reasonable without, for
example, provisions that establish: (1) a new generator interconnection study process and
new interim generator interconnection service that reflect an interconnection customer’s
commitment, in a generator interconnection agreement, to limit a generating facility’s
output to match the hourly forecast of an electrically proximate large load or large
co-located load; or (2) a generator interconnection study process that allows the use of the
existing ERIS or NRIS of an existing generator to connect a new generating facility and a
new large load behind the same point of interconnection of the existing generator with
necessary control technologies and/or protection systems, which may include a special
protection scheme, that ensures that the net injection does not exceed the amount in the
existing generator interconnection agreement; or (3) a new generator interconnection
service that allows a new generating facility and new large co-located load seeking to
interconnect behind the same new point of interconnection with necessary control
technologies and/or protection systems, which may include a special protection scheme,
to ensure that there is no injection to the transmission system. We note that, with respect
to numbers (2) or (3), these approaches could be either interim or permanent. These
approaches may not be mutually exclusive.
Given that generator interconnection service in and of itself does not convey
transmission service, we encourage ISO-NE to consider, in responding to these concerns,
what type of transmission service an Eligible Customer will need to take on behalf of the
272 See Helion November 21 ANOPR Comments at 1 (noting interconnection
delays are the biggest barrier to adding new generation); Oracle November 21 ANOPR
Comments at 1 (noting significant delays in access to sufficient energy for data centers);
OPSI November 21 ANOPR Comments at 11 (explaining that expedited study
encourages loads to bring their own generation); Enchanted Rock November 21 ANOPR
Comments at 4; Microsoft November 21 ANOPR Comments at 8-9.
PDF page 73
Docket No. EL26-72-000
- 73 -
electrically proximate large load or large co-located load.273 We note that, in the PJM
Co-Location Order, the Commission found that the Eligible Customer must take
transmission service on behalf of co-located load that will not withdraw energy from the
transmission system, even if it is 0 MW.274
F.
Informational Report
The rapid addition and proliferation of large loads without commensurate
additions of supply or demand-side resources presents resource adequacy concerns. As
discussed above and highlighted in the ANOPR, the growth of demand, and the speed of
such growth, is driven in large part by the interconnection of large loads. While not
expressly contemplated in the ANOPR, commenters highlight the strain rapid demand
growth is putting on resource adequacy in many regions.275 Indeed, the relative speed
and concentration at which large loads are seeking to interconnect appears to be
outpacing the addition of new generation, which in turn heightens reliability risks and
drives up costs to ratepayers.276 We are concerned that ISO-NE and load serving entities
are unable to plan adequate generation to serve all load at the pace such load seeks to
connect.
We recognize that ISO-NE is currently engaged with stakeholders to improve
resource adequacy through the Capacity Auction Reforms Seasonal/Accreditation Key
Project, which seeks to better address seasonal reliability challenges and to more
accurately reflect resource contributions to resource adequacy.277 Additionally, ISO-NE
is engaging with transmission owners regarding potential large load interconnections, and
is communicating with states to understand any potential policies creating incentives for
273 See SPP HILL Order, 194 FERC ¶ 61,031 at P 34.
274 PJM Co-Location Order, 193 FERC ¶ 61,217 at P 206.
275 See, e.g., Entergy November 21 ANOPR Comments at 29-30; Eolian
November 21 ANOPR Comments at 16-17; Industrial Customers November 21 ANOPR
Comments at 24-26; R Street November 21 ANOPR Comments at 1; South Dakota
Commission November 13 ANOPR Comments at 5; Talen December 5 ANOPR
Comments at 7.
276 See, e.g., Eolian November 21 ANOPR Comments at 16-17; David Gardiner &
Associates November 21 ANOPR Comments at 1-2; Joint Consumer Advocates
December 5 ANOPR Comments at 2; PSEG November 21 ANOPR Comments at 8;
Southern California Edison December 5 ANOPR Comments at 3.
277 See ISO-NE, Capacity Auction Reforms Key Project, https://www.iso-
ne.com/committees/key-projects/capacity-auction-reforms-key-project.
PDF page 74
Docket No. EL26-72-000
- 74 -
data centers and to share information on how ISO-NE would review such proposed
developments.278 Accordingly, we direct ISO-NE to submit in Docket No. EL26-72-000,
within 30 days of the date of issuance of this order, a detailed informational report on any
proposals under consideration in its stakeholder process to address the issue of resource
adequacy to serve new large loads. We also strongly encourage new proposals to the
extent necessary to address these concerns. The informational report must include a
detailed schedule of key milestones, such as stakeholder or ISO-NE Board votes, that
includes the estimated date on which ISO-NE expects to file any such proposals with the
Commission. Additionally, as part of this informational report, we direct ISO-NE to
identify any ongoing stakeholder processes that aim to increase the pace of adding
generating capacity in the ISO-NE region. The informational report must include a
detailed schedule of such initiatives, including timing of the stakeholder process and
dates of any anticipated filings with the Commission.
IV.
Briefing Questions
We note that large loads, including data centers, are actively working with
transmission owners and other relevant entities to interconnect to, and to take
interconnection and/or transmission service from, the transmission system and may be at
varying stages of that process. We appreciate that different large loads are currently at
different stages of that process. We also understand that large loads and Eligible
Customers taking transmission service on behalf of large loads are negotiating, entering
into, and/or have executed various agreements related to interconnecting to the
transmission system and/or the provision of transmission service. We direct further
briefing regarding how ISO-NE and the Participating Transmission Owners, in
responding to the order to show cause, should protect existing commercial arrangements
including: (1) what would be a reasonable implementation period to ensure minimal
disruption to such existing commercial arrangements, and (2) how to allow a reasonable
amount of time to finalize ongoing agreements that are nearing completion as of the date
such Tariff provisions are filed with the Commission.
Today’s order proposes, as part of a potential replacement rate, to establish new
transmission services that recognize flexible large loads’ ability and willingness to limit
their use of the transmission system under certain conditions. As we assess this proposal,
we also consider how these new transmission services might affect other parts of
ISO-NE’s Tariff and/or processes. Specifically, what, if any, potential impacts on
regional and local transmission planning would arise from the introduction of the new
transmission services discussed herein? For example, when planning for load growth,
how would transmission providers and planners account for flexible large loads’ potential
278 ISO-NE Letter at 1-2.
PDF page 75
Docket No. EL26-72-000
- 75 -
preference to take the new transmission services, including potential uncertainties around
the type, location, and quantity of such expected loads?
Today’s order preliminarily finds that ISO-NE’s Tariff appears to be unjust and
unreasonable without the inclusion of cost shifting protections. We find that there may
be a variety of possible approaches to protect customers from significant cost shifts
associated with network upgrades triggered by large loads. To that end, we direct
respondents to include information regarding potential structures for agreements between
the transmission owner/provider and an Eligible Customer to prevent unjust and
unreasonable cost shifts among transmission customers related to network upgrades costs
required for large loads. Further, please include information on what an appropriate
minimum level of cost recovery and financial security from an Eligible Customer would
be under any such agreements.
Today’s order preliminarily finds that ISO-NE’s Tariff appears to be unjust and
unreasonable because it lacks clear and consistent provisions requiring the evaluation of
alternative transmission technologies. The order directs ISO-NE to explain whether the
Tariff remains just and reasonable without provisions that (1) require the evaluation of
alternative transmission technologies in transmission service request studies, using
models that are capable of evaluating the transmission system to accurately account for
advanced transmission technologies, in all instances, without the need for a request from
the Eligible Customer seeking transmission service on behalf of large load; and (2) if
traditional network upgrades are selected instead of alternative transmission technologies,
inclusion in the study report to the Eligible Customer seeking transmission service on
behalf of large load of a sufficiently clear demonstration of why alternative transmission
technologies are not feasible (i.e., would not resolve reliability violations identified or
meet the relevant planning criteria) or would not result in lower costs or a faster timeline
for accommodating the transmission service request. As noted above, to the extent
stakeholders believe that specific characteristics of providing transmission service to
Eligible Customers on behalf of large loads warrant requirements beyond those
contemplated here, we seek further briefing.
Today’s order preliminarily finds that ISO-NE Tariff appears to be unjust and
unreasonable because it does not contain provisions allowing an interconnection
customer serving electrically proximate large load or large co-located load to seek
generator interconnection service(s) that reflects the operational dynamics of serving such
loads. Any filings or tariff changes submitted in response to this order should address the
following questions:
a. To what extent would ISO-NE allow an interconnection customer’s
generating facility serving electrically proximate large load or large co-
located load to participate in ISO-NE’s energy and ancillary services
PDF page 76
Docket No. EL26-72-000
- 76 -
market, and if ISO-NE were to allow them to participate, what restrictions
or mitigation would ISO-NE apply?
b. To the extent that ISO-NE plans for the electrically proximate large load or
large co-located load associated with an interconnection customer’s
generating facility for resource adequacy purposes, would ISO-NE account
for the generating facilities serving electrically proximate large load or
large co-located load in the resource adequacy construct? If applicable,
would ISO-NE allow the generating facilities serving electrically proximate
large load or large co-located load to participate in ISO-NE’s capacity
market? If so, would ISO-NE accredit these generating facilities using the
same method as other ISO-NE generating facilities?
The Commission orders:
(A)
Pursuant to the authority contained in and subject to the jurisdiction
conferred upon the Federal Energy Regulatory Commission by section 402(a) of the
Department of Energy Organization Act and by the FPA, particularly section 206 thereof,
and pursuant to the Commission’s Rules of Practice and Procedure and the regulations
under the FPA (18 C.F.R. Chapter I), the Commission hereby institutes a proceeding in
Docket No. EL26-72-000 as discussed in the body of this order.
(B)
ISO-NE and the Participating Transmission Owners are hereby directed,
within 60 days of the date of the order, either: (1) to show cause as to why the Tariff
remains just and reasonable and not unduly discriminatory or preferential; or (2) to
explain what changes to the Tariff they believe would remedy the identified concerns if
the Commission were to determine that the Tariff has in fact become unjust and
unreasonable or unduly discriminatory or preferential and, therefore, proceeds to
establish a replacement Tariff.
(C)
ISO-NE is directed to submit an informational report within 30 days of the
date of issuance of this order, as discussed in the body of this order.
(D)
Any interested person desiring to be heard in Docket No. EL26-72-000
must file a notice of intervention or motion to intervene, as appropriate, with the Federal
Energy Regulatory Commission, 888 First Street, NE, Washington, DC 20426, in
accordance with Rule 214 of the Commission’s Rules of Practice and Procedure,
18 C.F.R. § 385.214 (2025), within 21 days of the date of issuance of this order. The
Commission encourages electronic submission of interventions in lieu of paper using the
“eFiling” link at http://www.ferc.gov. Persons unable to file electronically may file by
U.S. mail addressed to Federal Energy Regulatory Commission, Secretary of the
Commission, 888 First Street, N.E., Washington, DC 20426, or by hand (including
PDF page 77
Docket No. EL26-72-000
- 77 -
courier) delivery to Federal Energy Regulatory Commission, 12225 Wilkins Avenue,
Rockville, MD 20852.
(E)
Interested entities may respond within 30 days of ISO-NE’s and the
Participating Transmission Owners’ filing, addressing either or both of: (1) whether the
Tariff remains just and reasonable and not unduly discriminatory or preferential; and (2)
if not, what changes to the Tariff should be implemented as a replacement rate.
(F)
The Secretary shall promptly publish in the Federal Register a notice of the
Commission’s initiation of the proceeding under section 206 of the FPA in Docket No.
EL26-72-000.
(G)
The refund effective date in Docket No. EL26-72-000 pursuant to section
206 of the FPA shall be the date of publication in the Federal Register of the notice
discussed in Ordering Paragraph (F) above.
By the Commission. Chairman Swett is concurring with a separate statement attached.
Commissioner Rosner is concurring with a separate statement
attached.
Commissioner See is concurring with a separate statement attached.
Commissioner Chang is concurring with a separate statement
attached.
Commissioner LaCerte is concurring with a separate statement
attached.
( S E A L )
Debbie-Anne A. Reese,
Secretary.
PDF page 78
Docket No. EL26-72-000
- 78 -
Appendix - Commenters in Docket No. RM26-4-000
Advanced Energy Management Alliance (AEMA)
Advanced Energy United (AEU)
Advancing Modern Powerlines Coalition (together with Working for Advanced
Transmission Technologies Coalition, WATT and Advancing Modern Powerlines)
Advocates for Consumer Regulated Electricity
AES Corporation
AI Supply Chain Alliance
Alexandre Figueras, on behalf of Monza Tech
Alliance for Tribal Clean Energy
Alliant Energy Corporate Services, Inc.
Amazon Energy LLC (Amazon)
America’s Power
American Chemistry Council
American Clean Power Association
American Conservation Coalition
American Council on Renewable Energy (ACORE)
American Electric Power Service Corporation279
American Public Gas Association
American Public Power Association (APPA)
American Terawatt, Inc. (American Terawatt)
American Transmission Company LLC (ATC)280
Americans for a Clean Energy Grid
Antora Energy, Inc.
Arevia Power
Arizona Public Service Company
Arkansas Public Service Commission
Attorney General of the State of Oklahoma
279 American Electric Power Service Corporation submitted comments on behalf
of its affiliates Appalachian Power Company, Indiana Michigan Power Company,
Kentucky Power Company, Kingsport Power Company, Ohio Power Company,
Wheeling Power Company, Public Service Company of Oklahoma, Southwestern
Electric Power Company, AEP Appalachian Transmission Company, Inc., AEP Indiana
Michigan Transmission Company, Inc., AEP Kentucky Transmission Company, Inc.,
AEP Ohio Transmission Company, Inc., AEP West Virginia Transmission Company,
Inc., AEP Oklahoma Transmission Company, Inc., and AEP Southwestern Transmission
Company, Inc.
280 ATC submitted comments on behalf of itself and its corporate manager ATC
Management Inc.
PDF page 79
Docket No. EL26-72-000
- 79 -
Base Power Company, Inc. (Base Power)
Bloom Energy Corporation
Buckeye Power, Inc. (Buckeye)
Calibrant Energy Holdings, LLC (Calibrant)
California Department of Water Resources State Water Project (California DWR)
California Independent System Operator Corporation
California Public Utilities Commission (CPUC)
Center for Biological Diversity
Chevron U.S.A., Inc.
Clean Energy Buyers Association (CEBA)
ClearPath, Inc. (ClearPath)
Confederated Tribes and Bands of the Yakama Nation
Constellation Energy Generation, LLC (Constellation)
Consumer Energy Alliance
Consumers Energy Company
Critical Loop, Inc. (Critical Loop)
Crusoe Energy Systems, Inc. (Crusoe)
CTC Global Corporation
Data Center Coalition (DCC)
David Gardiner & Associates
Delaware Division of the Public Advocate (together with Pennsylvania Office of
Consumer Advocate, Joint Consumer Advocates)281
Digital Energy Council
Digital Power Network
Distributed Capacity Parties282
Dr. Elisa Nelson
DTE Electric Company (DTE)
Duke Energy Corporation (Duke)
EDF Power Solutions, Inc. (EDF Power)
Edison Electric Institute (EEI)
Electricity Consumers Resource Council (ELCON)
Electricity Customers Alliance (ECA)
Electric Power Supply Association (EPSA)
Emerald AI (Emerald)
Enchanted Rock, LLC
Energy Trading Institute
281 The Illinois Attorney General joined the Joint Consumer Advocates in filing
reply comments.
282 Distributed Capacity Parties include: Clovereleaf Infrastructure; Spark
Community Investment d/b/a Sparkfund; and Voltus, Inc.
PDF page 80
Docket No. EL26-72-000
- 80 -
ENGIE North America, Inc. (ENGIE)
Entergy Services, LLC (Entergy)283
Environmental Law & Policy Center
Eolian L.P. (Eolian)
Equinix, Inc.
esVolta, LP
ETX Upstream, LLC
Eversource Energy (Eversource)284
Exelon Corporation (Exelon)285
Fervo Energy Company (Fervo)
FirstEnergy Service Company286
Front Door Technologies LLC
Fluence
FuelCell Energy, Inc.
Georgia Public Service Commission
Geronimo Power, LLC (Geronimo)
Google LLC (Google)
Governors Josh Shapiro and Glenn Youngkin
GridCARE
GridStor LLC (GridStor)
Harvard Electricity Law Initiative
Helion Energy (Helion)
Herbert Schrayschuen
283 Entergy submitted comments on behalf of the Entergy Operating Companies,
which include Entergy Arkansas, LLC, Entergy Louisiana, LLC, Entergy Mississippi,
LLC, Entergy New Orleans, LLC, and Entergy Texas, Inc.
284 Eversource submitted comments on behalf of its affiliates The Connecticut
Light and Power Company, NSTAR Electric Company, and Public Service Company of
New Hampshire, and through its agent Eversource Energy Service Company.
285 Exelon submitted comments on behalf of itself and its affiliates Atlantic City
Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison
Company, Commonwealth Edison Company of Indiana, Inc., Delmarva Power and Light
Company, PECO Energy Company, and Potomac Electric Power Company.
286 FirstEnergy Service Company submitted comments on behalf of itself and its
affiliates American Transmission Systems, Inc., Jersey Central Power & Light Company,
Mid-Atlantic Interstate Transmission LLC, Keystone Appalachian Transmission
Company, The Potomac Edison Company, Monongahela Power Company, and Trans-
Allegheny Interstate Line Company.
PDF page 81
Docket No. EL26-72-000
- 81 -
Heron Power Electronics Company
Indiana Energy Association
Indicated PJM Transmission Owners287
Industrial Customer Organizations (Industrial Customers)288
Information Technology Industry Council
Infrastructure Masons, Inc. (Infrastructure Masons)
Institute for Progress
International Energy Credit Association
Invenergy289
Iron Mountain Data Centers, LLC
ISO New England, Inc. (ISO-NE)
287 Indicated PJM Transmission Owners include: AEP on behalf of Appalachian
Power Company, Indiana Michigan Power Company, Kentucky Power Company,
Kingsport Power Company, Ohio Power Company, Wheeling Power Company, AEP
Appalachian Transmission Company, Inc., AEP Indiana Michigan Transmission
Company, Inc., AEP Kentucky Transmission Company, Inc., AEP Ohio Transmission
Company, Inc., and AEP West Virginia Transmission Company, Inc.; AMP
Transmission, LLC; City of Cleveland, Department of Public Utilities, Division of
Cleveland Public Power; City of Hamilton, OH; Dominion Energy Services, Inc. on
behalf of Virginia Electric and Power Company d/b/a Dominion Energy Virginia; Duke
Energy Corporation on behalf of its affiliates Duke Energy Ohio, Inc., Duke Energy
Kentucky, Inc., and Duke Energy Business Services LLC; Duquesne Light Company;
East Kentucky Power Cooperative; Exelon Corporation, on behalf of Atlantic City
Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison
Company, Commonwealth Edison Company of Indiana, Inc., Delmarva Power & Light
Company, PECO Energy Company, and Potomac Electric Power Company; FirstEnergy
Service Company, as agent for its affiliates American Transmission Systems,
Incorporated, Jersey Central Power & Light Company, Mid-Atlantic Interstate
Transmission LLC, Keystone Appalachian Transmission Company, The Potomac Edison
Company, Monongahela Power Company and Trans-Allegheny Interstate Line
Company; Old Dominion Electric Cooperative; PPL Electric Utilities Corporation;
Rockland Electric Company; Southern Maryland Electric Cooperative, Inc.; UGI Utilities
Inc; and Wabash Valley Power Association, Inc.
288 Industrial Customers include: the Industrial Energy Consumers of America,
the American Forest & Paper Association, the PJM Industrial Customer Coalition, and
the Coalition of MISO Transmission Customers
289 Invenergy includes: Invenergy Wind Development North America LLC,
Invenergy Solar Development North America LLC, and Invenergy Thermal Development
Holdings LLC.
PDF page 82
Docket No. EL26-72-000
- 82 -
ITC Holdings Corp. (ITC)
Jason Miller, on behalf of VEIR Inc.
Kansas Corporation Commission (Kansas Commission)
L. Lynne Kiesling
L.M. Marlowe
Land Trust Alliance
Large Public Power Council
Lauren Hopkins
LEAN Energy US
Load Flexibility Parties290
Long Island Power Authority
Longroad Energy Holdings, LLC (Longroad)
Louisiana Public Service Commission
LS Power Development, LLC (LS Power)
Maine Office of the Public Advocate (Maine Public Advocate)
Maryland Energy Administration
Maryland Public Service Commission
Maven Solutions
MCC Economics and Finance
Meta Platforms, Inc.
Michigan Attorney General Dana Nessel
Microsoft, Inc. (Microsoft)
Midcontinent Independent System Operator, Inc.
MISO Transmission Owners (MISO TOs)291
290 Load Flexibility Parties include: Enerwise Global Technologies, LLC d/b/a
CPower, Enel North America, Inc., and Voltus, Inc.
291 MISO TOs include: Ameren Services Company, as agent for Union Electric
Company d/b/a Ameren Missouri, Ameren Illinois Company d/b/a Ameren Illinois and
Ameren Transmission Company of Illinois; American Transmission Company LLC; Big
Rivers Electric Corporation; Central Minnesota Municipal Power Agency; Citizens
Electric Corporation; City Water, Light & Power (Springfield, IL); Cleco Power LLC;
Cooperative Energy; Dairyland Power Cooperative; Duke Energy Business Services,
LLC for Duke Energy Indiana, LLC; East Texas Electric Cooperative; Entergy Arkansas,
LLC; Entergy Louisiana, LLC; Entergy Mississippi, LLC; Entergy New Orleans, LLC;
Entergy Texas, Inc.; Great River Energy; GridLiance Heartland LLC; Hoosier Energy
Rural Electric Cooperative, Inc.; Indiana Municipal Power Agency; Indianapolis Power
& Light Company d/b/a AES Indiana; Lafayette Utilities System; MidAmerican Energy
Company; Minnesota Power (and its subsidiary Superior Water, L&P); Montana-Dakota
Utilities Co.; Northern Indiana Public Service Company LLC; Northern States Power
Company, a Minnesota corporation, and Northern States Power Company, a Wisconsin
corporation, subsidiaries of Xcel Energy Inc.; Northwestern Wisconsin Electric
PDF page 83
Docket No. EL26-72-000
- 83 -
Mississippi Public Service Commission
Missouri Public Service Commission
Monitoring Analytics, LLC, acting in its capacity as the Independent Market Monitor for
PJM
Nathan Peterson
National Association of Regulatory Utility Commissioners (NARUC)
National Association of State Utility Consumer Advocates
National Conference of State Legislatures (NCSL)
National Congress of American Indians
National Grid PLC (National Grid)292
National Rural Electric Cooperative Association (NRECA)
Nebraska Power Review Board (Nebraska Board)
New England States Committee on Electricity
New England Conference of Public Utility Commissioners (NESCOE)
New England Consumer-Owned Systems293 (together with Energy New England, LLC,
New England Consumer-Owned Systems)
New England Public Systems294
Company; Otter Tail Power Company; Prairie Power, Inc.; Republic Transmission, LLC;
Southern Illinois Power Cooperative; Southern Indiana Gas & Electric Company (d/b/a
CenterPoint Energy Indiana South); Southern Minnesota Municipal Power Agency;
Wabash Valley Power Association, Inc.; and Wolverine Power Supply Cooperative, Inc
292 National Grid submitted comments behalf of its affiliates Niagara Mohawk
Power Corporation; New England Power Company; New England Electric Transmission
Corporation; New England Hydro-Transmission Corporation; New England Hydro-
Transmission Electric Company, Inc.; and Massachusetts Electric Company.
293 New England Consumer-Owned Systems include: Belmont Municipal Light
Department, Block Island Utility District, Braintree Electric Light Department, Concord
Municipal Light Plant, Danvers Electric Division, Georgetown Municipal Light
Department, Groveland Electric Light Department, Hingham Municipal Lighting Plant,
Hudson Light & Power Department, Littleton Electric Light & Water Department,
Merrimac Municipal Light Department, Middleborough Gas & Electric Department,
Middleton Electric Light Department, North Attleborough Electric Department, Norwood
Municipal Light Department, Clear River Electric & Water District, Rowley Municipal
Lighting Plant, Stowe Electric Department, Taunton Municipal Lighting Plant, Town of
Wallingford, Connecticut Department of Public Utilities Electric Division, Westfield Gas
and Electric Light Department, and Mid-Coast Regional Redevelopment Authority.
294 New England Public Systems include: Connecticut Municipal Electric
Cooperative, Massachusetts Municipal Wholesale Electric Company, and Vermont
PDF page 84
Docket No. EL26-72-000
- 84 -
New Mexico Public Regulation Commission (New Mexico Commission)
New York Independent System Operator, Inc.
New York State Department of State Utility Intervention Unit (NY UIU)
New York Public Service Commission
New York State Reliability Council
New York Transmission Owners295
North American Electric Reliability Corporation
North Carolina Utilities Commission
North Carolina Utilities Commission Public Staff
North Dakota Public Service Commission
Northeastern Rural Electric Membership Corporation
NRG Energy, Inc.
Office of the Illinois Attorney General (Illinois AG)
Office of the Ohio Consumers’ Counsel (OCC)
Oklahoma Corporation Commission
Oklo Inc. (Oklo)
Old Dominion Electric Cooperative (ODEC)
Oncor Electric Delivery Company LLC
ON Energy Storage, Inc.
OpenAI Inc.
Oracle America, Inc. (Oracle)
Organization of MISO States, Inc. (OMS)
Organization of PJM States, Inc. (OPSI)
Paces AI Inc.
Pacific Gas & Electric Company
Paige Lambermont, on behalf of Competitive Enterprise Institute
Paul Statchen
Pennsylvania Office of Consumer Advocate
Pennsylvania Public Utility Commission
Pew Charitable Trusts Energy Modernization Project
PJM Interconnection, LLC
Power for Tomorrow
PPL Corporation296
Public Power Supply Authority.
295 New York Transmission Owners include: Central Hudson Gas & Electric
Corporation, Consolidated Edison Company of New York, Inc., New York Power
Authority, New York State Electric & Gas Corporation, Niagara Mohawk Power Corp.
(d/b/a National Grid), Orange and Rockland Utilities, Inc., Long Island Power Authority,
and Rochester Gas and Electric Corporation.
296 PPL Corporation submitted comments on behalf of the PPL Companies, which
PDF page 85
Docket No. EL26-72-000
- 85 -
Prime Mover Institute
PSEG Companies (PSEG)297
Public Citizen, Inc.
Public Interest Organizations (PIOs)298
Public Utilities Commission of Ohio’s Office of the Federal Energy Advocate (Ohio
FEA)
R Street Institute (R Street)
Rewiring America
MCC Economics Ltd.
RWE Clean Energy, LLC
Sarah McKinley
Shell Energy North America (US), L.P.
Sierra Club
SMA Solar Technology AG
Solar Energy Industries Association
South Carolina Office of Regulatory Staff
South Dakota Public Utilities Commission (South Dakota Commission)
Southeast Public Interest Organizations (Southeast PIOs)299
Southern California Edison Company (Southern California Edison)
Southern Companies300
Southern Maryland Electric Cooperative, Inc.
Southwest Power Pool, Inc.
include PPL Electric Utilities Corporation, Louisville Gas & Electric Company and
Kentucky Utilities, and The Narragansett Electric Company d/b/a Rhode Island Energy.
297 PSEG Companies include: Public Service and Gas Company, PSEG Power
LLC, and PSEG Energy Resources & Trade LLC, which are each wholly-owned, direct
or indirect subsidiaries of Public Service Enterprise Group Incorporated.
298 PIOs include: Clean Air Task Force, Inc., Coalition for Affordable Utility
Services and Energy Efficiency in Pennsylvania, Earthjustice, Environmental Defense
Fund, Montana Environmental Information Center, Natural Resources Defense Council,
Sustainable FERC Project, Sierra Club, and Southern Environmental Law Center.
299 Southeast PIOs include: Southern Environmental Law Center, Appalachian
Voices, North Carolina Sustainable Energy Association, South Carolina Coastal
Conservation League, and Southern Alliance for Clean Energy.
300 Southern Companies include: Georgia Power Company, Alabama Power
Company, and Mississippi Power Company.
PDF page 86
Docket No. EL26-72-000
- 86 -
Southwest Power Pool Transmission Owner Group301
Splight Inc. (Splight)
State Entities302
Steel Manufacturers Association
Switch, Ltd. (Switch)
Talen Energy Corporation (Talen)
Terraflux LLC (Terraflux)
Tesla, Inc.
Texas Blockchain Council
Thermal Battery Alliance
Tract Holding Company I, LLC (Tract)
Transmission Access Policy Study Group (TAPS)
Tri-State Generation and Transmission Association, Inc. (Tri-State)
Travis Fisher, on behalf of Cato Institute
U.S. Chamber of Commerce (Chamber of Commerce)
U.S. Energy Storage Coalition
U.S. House of Representatives Committee on Energy and Commerce Ranking
Members303
U.S. Representatives304
U.S. Senate Committee on Energy and Natural Resources
U.S. Senators305
301 Southwest Power Pool Transmission Owner Group includes: American
Electric Power Service Corporation, Evergy Kansas Central, Inc., Evergy Metro, Inc.,
Evergy Missouri West, Inc., Oklahoma Gas and Electric Company, and Xcel Energy
Services Inc., on behalf of Southwestern Public Service Company.
302 State Entities include: Massachusetts Attorney General’s Office, the Arizona
Attorney General’s Office, the Colorado Attorney General’s Office, the Connecticut
Office of Consumer Counsel, the Maryland Office of People’s Counsel, the Minnesota
Attorney General’s Office, the Office of the Nevada Attorney General, Bureau of
Consumer Protection, the New Hampshire Office of the Consumer Advocate, the Oregon
Attorney General, and the Rhode Island Division of Public Utilities and Carriers.
303 Submitted by Frank Pallone, Jr. (Ranking Member) and Kathy Castor (Ranking
Member, Subcommittee on Energy).
304 The U.S. Representatives that submitted comments include: Suhas
Subramanyam, John W. Mannion, Mike Quigley, and Donald S. Beyer Jr.
305 The U.S. Senators that submitted comments include: Edward J. Markey, Chris
Van Hollen, Elizabeth Warren, Peter Welch, Raphael Warnock, Richard Blumenthal, and
PDF page 87
Docket No. EL26-72-000
- 87 -
U.S. Senator Jon Ossoff
Union of Concerned Scientists (UCS)
Vantage Data Centers (Vantage)
Verrus
Virginia State Corporation Commission
Vistra Corp. (Vistra)
Washington Utilities and Transportation Commission
WIRES
Wisconsin Electric Company
Wisconsin Public Service Corporation
Adam B. Schiff.
PDF page 88
UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION
ISO New England Inc.
Central Maine Power Company
The Connecticut Light and Power Company
Fitchburg Gas and Electric Light Company
Green Mountain Power Corporation
Maine Electric Power Company
The Narragansett Electric Company
New England Power Company
New Hampshire Transmission, LLC
NSTAR Electric Company
Public Service Company of New Hampshire
The United Illuminating Company
Unitil Energy Systems, Inc.
Vermont Electric Cooperative, Inc.
Vermont Electric Power Company, Inc.
Vermont Transco LLC
Versant Power
Docket No. EL26-72-000
(Issued June 18, 2026)
SWETT, Chairman, concurring:
Today, we take historic action to push our country’s electric markets and economy
into the future—a future of fair cost allocation, unprecedented transparency for the
American ratepayer, respect for states’ rights, efficient markets and speed to power. Last
October, Secretary Wright articulated the monumental, generational and “urgent”
challenge FERC must solve for our country when he directed us to develop “reforms to
ensure the timely and orderly interconnection of large loads to the transmission system.”1
I strongly agree. And now, through this suite of six orders, we deliver.
Simply put, the show cause orders the Commission issues today to each of the six
electric markets subject to its jurisdiction find that the status quo across much of the
country is not good enough.2 Nowhere close. The record prompted by the Secretary’s
1 Advance notice of proposed rulemaking (ANOPR) Interconnection of Large
Loads to the Interstate Transmission System, Advance Notice of Proposed Rulemaking
(Oct. 23, 2025) (ANOPR); see Letter from Chris Wright, Sec’y, U.S. Dep’t of Energy
(Oct. 23, 2025) (Secretary’s Letter).
2 Cal. Indep. Sys. Operator Corp., 195 FERC ¶ 61,214 (2026) (CAISO); ISO New
PDF page 89
Docket No. EL26-72-000
- 2 -
ANOPR leaves no doubt that most of the markets (and their existing rules) are inherently
slow and prohibitive of the dexterity necessary to adapt to and power societal evolution—
whether brought about by technological innovation or sustaining the great industrial
economy that anchors America.
I wholeheartedly, fully concur with these orders, which we carefully crafted to
execute upon the problems the Secretary identified in a manner that is quick, efficient,
and legally durable. I write separately to highlight certain considerations underlying the
Commission’s procedural approach to delivering on the ANOPR and to today’s orders.
Based on my analysis of the extensive record and numerous ongoing substantive
stakeholder interactions, I have determined that the most productive way to “build upon
the[] principles”3 in the ANOPR and “work expeditiously”4 towards a solution is to issue
individualized orders to show cause to each market.5 That is so for two main reasons.
First, the record the Commission collected in response to the challenges identified
in the ANOPR and subsequent resulting developments indicate that an approach that
honors the ANOPR principles but accounts for widening regional variation may now be
more efficient than a one-size-fits-all rule.6 The world has changed a great deal since last
Eng. Inc., 195 FERC ¶ 61,215 (2026) (ISO-NE); Midcontinent Indep. Sys. Operator, Inc.,
195 FERC ¶ 61,212 (2026) (MISO); N.Y. Indep. Sys. Operator, Inc., 195 FERC ¶ 61,216
(2026) (NYISO); PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 (2026) (PJM); Sw.
Power Pool, Inc., 195 FERC ¶ 61,213 (2026) (SPP) (collectively, Orders to Show
Cause).
3 Secretary’s Letter at 2.
4 Id.
5 See SEC v. Chenery Corp., 332 U.S. 194, 202-03 (1947) (“[A]n administrative
agency must be equipped to act either by general rule or individual order. To insist upon
one form of action to the exclusion of the other is to exalt form over necessity. . . . [T]he
choice made between proceeding by general rule or by individual, ad hoc litigation is one
that lies primarily in the informed discretion of the administrative agency.”); Wis. Gas
Co. v. FERC, 770 F.2d 1144, 1166 (D.C. Cir. 1985) (“It is a well-settled principle of
administrative law that the decision whether to proceed by rulemaking or adjudication
lies within the broad discretion of the agency.”).
6 “[T]he Commission may rely on ‘generic’ or ‘general’ findings of a systemic
problem to support imposition of an industry-wide solution.” Interstate Nat. Gas Ass’n
of Am. v. FERC, 285 F.3d 18, 37 (D.C. Cir. 2002) (internal citations omitted). However,
the Commission “has long allowed different regional transmission organizations to
follow different rules, in recognition of regional variations including potential differences
PDF page 90
Docket No. EL26-72-000
- 3 -
October. The ANOPR itself, including the articulated principles, appears to have shifted
the playing field and prompted great progress across several electric markets. This
change (and the Commission’s alignment with the Secretary) is well illustrated by a
number of landmark orders approving several market new constructs that we issued since
October, which together operationalize the Secretary’s principles and laid groundwork
for meaningful reform and today’s actions.7 While working to develop those orders, the
Commission has simultaneously devoted significant attention to evaluating the various
procedural paths through which we might comprehensively deliver.
Individual show cause proceedings will allow the Commission to ensure that
solutions to the problems the Secretary identified are tailored to the specific, varied
circumstances and market constructs of each region. Indeed, a careful review of today’s
six orders reveals the many ways in which those orders are customized for each market’s
unique circumstances and progress (or lack thereof) towards serving large load. To name
just a few examples, the orders recognize ongoing stakeholder processes in various
regions and are adapted to existing tariff provisions concerning large and co-located
loads; account for regional variances in allocating rights and responsibilities among
RTOs/ISOs and the transmission owners; leave room for each market to tailor operational
requirements for large loads that are particular to their region; and otherwise account for
incumbent regional differences on topics such as cost allocation and cost transparency,
study processes, and network upgrade procedures.
Proceeding via show cause proceedings will also allow the markets (and their
respective transmission owners) to explain, in the first instance, how to address the
Commission’s concerns. These entities have the deepest understanding of their
respective regions and are best positioned to implement solutions we identified, in the
most expeditious manner. The Commission will promptly evaluate their responses to
today’s orders, and, with input from stakeholders, swiftly establish appropriate reforms.
Second, proceeding via individual show cause orders will allow the Commission
to act more quickly than through traditional rulemaking. Notice-and-comment
rulemaking may not capitalize upon individual market progress prompted since October
and would be unduly time-consuming,8 as it also inevitably would require the additional
steps of accommodating the regional variations of the approach we take today.
Rulemaking efforts can be particularly inefficient when, as here, they risk incubating
in ‘geographic size and location.’” Cent. Hudson Gas & Elec. Corp. v. FERC, 138 F.4th
531, 539 (D.C. Cir. 2025) (internal citations omitted).
7 See id. P 2 & nn.6-11.
8 See, e.g., Comments of Talen Energy Corporation, Docket No. RM26-4, at 5-6
(filed Nov. 21, 2025).
PDF page 91
Docket No. EL26-72-000
- 4 -
uncertainty after progress has begun, and diverting scarce stakeholder resources away
from other endeavors, such as the development of market-specific reforms submitted to
the Commission under section 205 of the Federal Power Act (FPA). (To be clear, we
very much encourage 205 submissions encapsulating the principles we articulate in the
206s, and with all due deliberate haste.)
Furthermore, rulemaking requires a lengthy series of steps before the proposed
reforms would actually take effect—e.g., a NOPR, then a final rule, then potential orders
on rehearing, and then a “compliance” process in which affected parties make filings (or,
more likely, multiple rounds of filings) explaining how they intend to implement the rule.
By their nature, these procedures take time. For example, the compliance process for the
Commission’s Order No. 20239 (which matured out of an ANOPR issued in July 2021
and a NOPR issued in June 2022) still is not fully complete as of June 2026. The
compliance process for Order No. 222210 (NOPR issued in November 2016) could be
considered completed in May 2026; however, even with that timing, not all of the
RTOs/ISOs have yet fully implemented their Commission-accepted market rules. I
provide these examples not to suggest that the completion of a rulemaking process on the
interconnection of large loads would take this long,11 but rather to make clear the scope
of the years-long delays in implementation that might be expected if the Commission
elected to proceed via a NOPR. By contrast, we expect that individual show cause
proceedings for each of the RTO/ISOs will enable the Commission to spearhead lasting
reform much more expeditiously.
The six markets together cover nearly two-thirds of load subject to Commission-
jurisdictional rates, and therefore focusing initially on those regions is a prudent first step.
But I am under no illusion that the challenges discussed in today’s orders are somehow
9 Improvements to Generator Interconnection Procs. & Agreements, Order No.
2023, 184 FERC ¶ 61,054, order on reh’g, 185 FERC ¶ 61,063 (2023), order on reh’g,
Order No. 2023-A, 186 FERC ¶ 61,199, errata notice, 188 FERC ¶ 61,134 (2024).
10 Participation of Distributed Energy Res. Aggregations in Mkts. Operated by
Reg’l Transmission Orgs. & Indep. Sys. Operators, Order No. 2222, 172 FERC ¶ 61,247
(2020), order on reh’g, Order No. 2222-A, 174 FERC ¶ 61,197, order on reh’g, Order
No. 2222-B, 175 FERC ¶ 61,227 (2021).
11 I do not mean to suggest that the public utilities subject to compliance under
these rulemakings—or the Commission itself—have been derelict. The time-consuming
nature of the compliance process is a natural consequence of complex, nuanced efforts
toward tariff reform. As Chairman, I will continue to evaluate Commission directives to
ensure that obligations on regulated entities are not unduly burdensome and to make
certain that Commission action during the compliance process is as timely as possible.
PDF page 92
Docket No. EL26-72-000
- 5 -
unique to the RTO/ISO regions. Our actions today do not foreclose the possibility of a
future rulemaking, and nor do they prevent us from acting on filings made under sections
205 and 206 of the FPA. I encourage transmission providers and other stakeholders
outside RTO/ISO regions to make individual filings to address the issues we discuss
today.
FERC is no longer the sleepy, responsive agency of the past—our country cannot
afford for it to be. This is a time for the best thinkers we have to collaborate on solving
our biggest problems, and thus it is my great honor to deliver a solution that honors the
Secretary’s goals. For these reasons, I respectfully concur.
________________________
Laura V. Swett
Chairman
PDF page 93
UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION
ISO New England Inc.
Central Maine Power Company
The Connecticut Light and Power Company
Fitchburg Gas and Electric Light Company
Green Mountain Power Corporation
Maine Electric Power Company
The Narragansett Electric Company
New England Power Company
New Hampshire Transmission, LLC
NSTAR Electric Company
Public Service Company of New Hampshire
The United Illuminating Company
Unitil Energy Systems, Inc.
Vermont Electric Cooperative, Inc.
Vermont Electric Power Company, Inc.
Vermont Transco LLC
Versant Power
Docket No. EL26-72-000
(Issued June 18, 2026)
ROSNER, Commissioner, concurring:
The electric industry is in the midst of changes not seen in a generation.
Compared to more traditional load growth, the large loads seeking to connect to the grid
today are larger, sometimes by orders of magnitude, and more concentrated. They also
exhibit different operational characteristics, such as the ability to quickly change their
energy consumption, sometimes in seconds. Often, these large loads seek to connect to
the grid as quickly as possible. And because of these dynamics, large loads are rapidly
driving the need for new transmission infrastructure and energy supply. This creates new
challenges that, if unaddressed, could jeopardize the reliability and affordability of the
grid on which we all depend.
Today, we are taking an important step toward addressing these challenges. We
are opening a dialogue with each of the six RTO/ISOs on a series of reforms that are
tailored to address the unique reliability and affordability challenges posed by large load
growth and the infrastructure buildout needed to serve dramatically growing demand.
Informed by the record developed in response to the Secretary of Energy’s October 2025
PDF page 94
Docket No. EL26-72-000
- 2 -
ANOPR,1 and by innovative proposals that stakeholders have filed with the Commission
under FPA section 205, today’s orders are aimed at ensuring that the grid remains reliable
and affordable for all customers, especially residential customers. It is also crucial that
we unlock the immense economic opportunity that once-in-a-generation growth
represents. While each order’s specific focus varies according to the progress that each
RTO/ISO has made, our actions today fit broadly into four key pillars that, taken
together, provide a foundation for durable reform. Today, we are: (1) Protecting
Consumers, (2) Safeguarding Reliability, (3) Enhancing Transparency, and (4) Fostering
Innovation (see Figure 1). I write separately to explain how.
*****
Protecting Consumers: Today’s orders include key protections that promote
affordability. First, today’s orders require “Cost Recovery Agreements”, which are
designed to ensure that large loads pay their fair share of the costs incurred to serve them,
regardless of whether the large load comes online as planned. Thus, if new infrastructure
is built to accommodate a data center, and that data center doesn’t show up, residential
customers are not left on the hook to pay the costs. Cost Recovery Agreements prevent
those costs from being shifted to residential customers. Depending on how they are
structured, Cost Recovery Agreements can also address the potentially uneven pacing of
new infrastructure costs, where grid upgrade costs may hit customer bills before the large
load is fully online and energized. Data centers have committed to paying their own
way.2 Today, with “Cost Recovery Agreements,” we are taking steps to ensure that those
commitments are honored. I note, however, that the door remains open to other creative,
regionally-specific ideas to protect consumers. If there are other ways to accomplish that
goal, I welcome those proposals.
Another win for consumers is requiring RTO/ISOs to consider grid enhancing
technologies (GETs), including dynamic line ratings, when adding new large loads to the
grid. GETs are technologies that squeeze more juice out of the existing grid, reducing the
need for expensive upgrades and speeding up the time connect. Ensuring that RTO/ISOs
consider GETs in the planning process—and if GETs are not used, explain why—not
only helps new large loads get connected more quickly, but is also a commonsense step
towards saving all consumers money. Put differently, today’s orders will help us
understand if we are leaving efficiencies on the table, an outcome we cannot afford.
1 U.S. Dep’t of Energy, Secretary of Energy Chris Wright, Direction that the
Commission Initiate Rulemaking Procedures and Proposal Regarding the Interconnection
of Large Loads Pursuant to the Secretary’s Authority Under Section 403 of the
Department of Energy Organization Act (Oct. 23, 2025).
2 See Proclamation No. 11014, 91 Fed. Reg. 11439 (Mar. 4, 2026).
PDF page 95
Docket No. EL26-72-000
- 3 -
Safeguarding Reliability: Today’s orders safeguard reliability. They help ensure
that RTO/ISOs use study procedures and operational requirements that reflect large
loads’ unique characteristics and the reliability impacts of connecting them to the grid.
Those novel characteristics and reliability impacts are well-documented, and it is not
clear if existing study procedures or operational requirements account for them. Clear,
comprehensive, and specifically tailored study procedures and operational requirements
are needed, such as enhanced data reporting and telemetry to increase visibility into how
these loads interact with the grid, and today’s orders represent progress towards this goal.
Finally, although not part of today’s orders, I want to highlight NERC’s ongoing
efforts to establish registration criteria for large computational loads and to develop
reliability standards.3 NERC’s goal is to finish the first phase of this critical work this
year. It is essential that NERC meet this deadline. I encourage all stakeholders to
participate in NERC’s process.
Enhancing Transparency: Today’s orders provide regulators—the Commission
and, critically, our state partners—and customers with data on how connecting large
loads to the grid affects bills. Today’s orders embody a commonsense approach: if a
Network Upgrade is built to connect a large load to the grid, consumers should know who
that upgrade was built for and what it cost.
Transparency is important because “who pays?” has been and continues to be a
fraught and contentious question for large load interconnection. Stakeholders, including
state regulators and the ratepayers that they represent, must know the costs, for whom
they are being incurred, and how they are being allocated, to know that everyone is
paying their fair share. Today’s orders ensure that this information is public, accessible,
and clear. State regulators in more than half of the country have enacted large load
tariffs.4 Our action today helps them as they continue their critically important work.
The Commission’s action today also addresses speculative load interconnection
requests, which clog up load interconnection queues, divert resources, and distort
forecasts. Under current rules, data centers can (and are incentivized to) “shop around”
their prospective projects with different utilities to identify the fastest and cheapest
location to connect. This wastes time and resources studying projects that are not real.
Worse yet, it can inflate expected load growth by modeling projects that do not
3 NERC, Large Loads Action Plan Q1 2026 Update (Apr. 2026),
https://www.nerc.com/globalassets/initiatives/large-loads-action-plan/llap-quarterly-
update-q1-2026.pdf.
4 See, e.g., National Association of Regulatory Utility Commissioners
Supplemental Comments at 2-6; Edison Electric Institute Supplemental Comments at
App. 9-13.
PDF page 96
Docket No. EL26-72-000
- 4 -
materialize, leading to double counting, inaccurate market signals, and unnecessarily high
prices for consumers. Today, we target speculative projects by establishing escalating
readiness requirements for distinct phases of the study process to deter duplicative or
speculative requests for transmission service. I strongly encourage RTO/ISOs to pursue
other improvements to load forecasts, such as using objective screening criteria like
physical site control, to ensure that the data used to plan the grid is as accurate as
possible.5
Fostering Innovation: As I have said, to meet the moment, “a business-as-usual
approach . . . will not suffice.”6 Building new infrastructure is difficult and costly, which
delays efforts to connect large loads to the grid quickly, reliably, and cost effectively.
This is doubly true when generation and load are planned and studied separately.
Today’s orders push beyond this status quo.
First, today’s orders promote flexible transmission services—that is, non-firm
service to a co-located load that is willing and able to limit withdrawals from the grid—in
every RTO/ISO (see Figure 2). As we explained when we first created these
transmission services in PJM for co-located loads, customers willing to embrace
flexibility can reduce the need for Network Upgrades and generating capacity to serve a
co-located load, which speeds up connecting to the grid and reduces costs for the co-
located load as well as other retail customers.
Second, today’s orders recognize that extending these same transmission services
to large loads that are not co-located but that may also be willing to limit their
withdrawals from the grid can unlock even more efficiency. Just as for co-located loads,
legalizing flexible transmission service options for more large load customers can speed
interconnection, avoid constructing unnecessary transmission upgrades, reduce strain on
the grid, and make power bills cheaper for everyone.
Finally, today’s orders embrace yet another innovation. Load and generation need
not be co-located to reduce the number of Network Upgrades; in other words, literal co-
location is not the only way to facilitate faster, more efficient, and more cost-effective
connections to the grid. Rather, where a large load and an associated generator are
electrically proximate (i.e., close together) and studied together, the reliability impacts on
the grid may be more limited than if the load and generator are studied separately. Just
like with co-location, more limited impacts on the grid mean, all else equal, fewer
5 See Comm’r David Rosner, Letter to the RTOs/ISOs on Large Load Forecasting
(Sept. 18, 2025), https://www.ferc.gov/news-events/news/chairman-rosners-letter-
rtosisos-large-load-forecasting.
6 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2026), (Rosner, Comm’r,
concurring) at P 3.
PDF page 97
Docket No. EL26-72-000
- 5 -
Network Upgrades, which makes connecting to the grid faster, more efficient, and
cheaper for both the large load and the associated generator. That last point is key. To
add new supply to the grid, we must create incentives for “Bring Your Own New
Generation.” Today’s orders make BYONG faster and more efficient.
SPP has been a leader in showing how to push beyond the status quo. With its
innovative HILLGA proposal, approved by the Commission in January,7 SPP leveraged
the opportunity for speed and efficiency by studying load and generation together, and by
creating a limited, expedited interconnection service to connect faster. By matching the
generator’s output to the electrically proximate large load’s demand, the impacts to the
grid are less than they otherwise would be, minimizing the need for time-consuming and
costly Network Upgrades needed to connect. HILLGA is one solution that works for
SPP, but today’s orders direct other regions to follow SPP’s lead in ways that work for
them. Today’s orders add a key tool by ensuring that all RTO/ISOs can study load and
generation together.
*****
The Commission’s action today is an important step forward, but the Commission
cannot accomplish this work alone. States are essential partners in this work. The
Commission’s actions here respect the long-standing jurisdictional line between federal
and state authority provided by Congress and repeatedly affirmed by the Supreme Court.
States retain exclusive jurisdiction to allocate the costs of FERC-jurisdictional
transmission charges among their retail ratepayers, including co-located loads. States
also hold the keys to energy infrastructure permits, so we rely on their decisions to ensure
that needed transmission and generation get built. At a time when some large loads are
retail customers that can consume as much energy as a small city, it is imperative that we
work within our respective jurisdictions, but that we collaborate. I look forward to
continued collaboration.
Today’s orders begin an important dialogue with RTO/ISOs. As a potential next
step, today’s orders invite RTO/ISOs to respond by submitting proposals under FPA
section 205. I cannot encourage this enough. I also encourage public utilities outside of
RTO/ISOs across the country to do the same. The electric industry is rapidly evolving
with regions experiencing and addressing these challenges in different ways. Many of
the examples on which the actions in today’s orders are based on stakeholders thinking
creatively to develop solutions, and I welcome other new, innovative, and regionally
tailored proposals that build on the four key pillars set forth today: (1) Protecting
Consumers, (2) Safeguarding Reliability, (3) Enhancing Transparency, and (4) Fostering
Innovation. Only by working together can we rise to the occasion and meet this once-in-
7 See Sw. Power Pool, Inc., 194 FERC ¶ 61,031 (2026).
PDF page 98
Docket No. EL26-72-000
- 6 -
a-generation moment to deliver the reliable and affordable energy on which we all
depend. It will not be easy, but I remain optimistic and look forward to the path ahead.
For these reasons, I respectfully concur.
________________________
David Rosner
Commissioner
PDF page 101
UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION
ISO New England Inc.
Central Maine Power Company
The Connecticut Light and Power Company
Fitchburg Gas and Electric Light Company
Green Mountain Power Corporation
Maine Electric Power Company
The Narragansett Electric Company
New England Power Company
New Hampshire Transmission, LLC
NSTAR Electric Company
Public Service Company of New Hampshire
The United Illuminating Company
Unitil Energy Systems, Inc.
Vermont Electric Cooperative, Inc.
Vermont Electric Power Company, Inc.
Vermont Transco LLC
Versant Power
Docket No. EL26-72-000
(Issued June 18, 2026)
SEE, Commissioner, concurring:
Growing electricity demand underscores America’s economic strength and the
opportunities that come with it. And with new opportunities come new challenges. The
pace and scale of emerging large loads create new circumstances that require us to adapt
in how we build and manage the grid. Large and flexible loads can materially change
system operations, for instance, as well as near-term planning needs, upgrade
requirements, and how we allocate costs. Most existing systems were not designed to
accommodate those changes—especially not at the pace needed to support AI growth and
advanced manufacturing that are central to America’s economic competitiveness. As a
result, uncertainty over the operative rules and delays in interconnecting large loads can
undermine reliability and investment and add unacceptable and avoidable costs.
Today, the Commission takes strong action within our jurisdictional sweep to
address these and other challenges that large load growth poses to the interstate
transmission system. Today’s orders support both just and reasonable rates and speed to
(reliable) power. I’m deeply grateful for the many commenters who shared their insight
and ideas in this action. They let us build a record that highlights the need for clearer
processes, better information, and faster analysis while our country moves new large load
PDF page 102
Docket No. EL26-72-000
- 2 -
additions online. As we press forward in these dockets, I will be looking to continue
building on the momentum already underway across the country to craft more practical,
region-specific solutions that support timely action while protecting consumers. Our
continued ability to deliver reliable and affordable electricity requires nothing less.
Today’s orders speak for themselves. I write separately to briefly highlight two
principles baked throughout them and that I believe must remain central as the
Commission evaluates further steps.
First, these issues extend beyond the Commission. Creating efficient, predictable
large load interconnection processes is a joint and overlapping task for us, other federal
agencies, the States, and the RTOs/ISOs and utilities. My animating principle here is that
we must use FERC’s statutory authority to bring clarity to the parts of this national issue
we own, and to complement and aid others as they tackle theirs. The very procedure the
Commission deploys today reflects that goal: Recognizing the value in region-specific
approaches, we are directing individual action in each of the RTO/ISO regions and
encouraging—strongly—proposals under section 205 of the Federal Power Act from
transmission providers or other entities that are molded to their unique system needs.
Most critically, exercising our authority fully without hamstringing our regulatory
and industry partners means respecting the States. States make many of the key decisions
that affect how we manage large loads. States bring indispensable expertise over local
conditions, siting needs, retail structures, and the resource decisions within their borders.
And they have been hard at work pursuing the retail implications and other State-specific
concerns that large load interconnection presents.1 All this effort flows from the States’
statutorily preserved role in regulating the power system. Today’s order understands that
limit—our power “extend[s] only to those matters which are not subject to regulation by
the States.”2 It also embraces the value in a statutory lens that views large load issues as
an area of shared federal-State responsibility. As we require clear study and operational
parameters for large load interconnection, we should remember that the nation’s energy
landscape is not monolithic. State and regional diversity is a strength, and today’s orders
know that the best solutions reflect differing system characteristics. Our action today is
designed to support further State efforts in this urgent and fast-moving space, not
override them.
Second, affordability must be at the forefront as we protect consumers from
unnecessary costs in a time of rising demand. True, the Commission lacks authority over
all the factors that drive electricity costs at the retail level. Today’s orders recognize that.
1 See EEI Supplemental Comments at Appendix 9 – 13 (listing pending and
approved State large load tariffs).
2 16 U.S.C. § 824(a).
PDF page 103
Docket No. EL26-72-000
- 3 -
In response, the orders strive to aid the States in their front-line affordability duties by
getting into their hands all relevant information about Commission-jurisdictional costs.
As these matters move forward, I am particularly interested in continued feedback from
the States on what information they most need to assess cost implications as new loads
come online. Are the cost transparency measures we identify today sufficient, or are
additional or more granular data needed for States to appropriately suballocate
transmission costs among retail customers? Tools like alternative cost allocation
structures, greater clarity in transmission service agreements, accounting for States’
large-load-specific tariffs, and direct assignment in appropriate cases may help States
ensure that retail consumers do not bear costs incommensurate with the benefits they
receive.
Moving to areas where the Commission has a more direct role in ensuring cost
responsibility, we need to pull all the levers we have to keep rates fair and transparent.
Today we reaffirm our responsibility to assign jurisdictional costs to the customers who
drive or benefit from grid upgrades, not shift them onto families and small businesses.
For instance, today’s orders seek to reduce large-load driven network upgrade costs
through alternative transmission technologies, or ATTs (also commonly called Grid
Enhancing Technologies). In determining how best to meet the needs of this historic
large load growth, technologies that can improve system capability faster than traditional
upgrades and at lower costs deserve a hard look. ATTs may not be the best tool in every
circumstance, but where they are they can support timely interconnections and avoid
potentially tens or hundreds of millions of dollars in unnecessary network upgrade costs
that would otherwise flow into transmission customers’ bills.
So our approach today supports continuing the Commission’s policy to roll most
network upgrade costs—including those in the large load space—into the embedded-cost
rate most transmission customers pay. But it includes an asterisk that this policy works
for ratepayers only so long as we remain committed to pursuing technological
innovations that keep those costs at a responsible and accountable level. Today’s order
thus calls for transmission providers to sufficiently evaluate ATTs to assess if and how
they can meet large loads’ interconnection needs. The answer may be yes or no in a
given case. But if the transmission provider opts for traditional network upgrades, they
must demonstrate why ATTs are not feasible or would not result in lower costs or a faster
timeline for the large load interconnection customer. In short, the goal is to respect
transmission providers’ engineering judgments while protecting against upgrade costs
when ATTs could solve transmission needs faster and with a lower bill.
I am also sensitive to novel questions about cost shifting that interconnecting large
load may present. Today’s findings on cost recovery agreements between transmission
owners and Eligible Customers are an important step in mitigating the risks of stranded
assets if large loads prove speculative. We are also reducing unnecessary redundancy by
allowing an Eligible Customer to meet its financial security requirements by relying on
PDF page 104
Docket No. EL26-72-000
- 4 -
credit support or other financial security a large load customer may have posted under a
retail agreement. As we gain more experience studying transmission service requests on
behalf of large loads, it may become appropriate to further streamline financial security
arrangements. Perhaps, for instance, cost -recovery agreements between a transmission
owner and a large load customer itself could satisfy an Eligible Customer’s financial
security requirements. As we move forward, I’ll be looking to ensure cost-recovery
agreements contain fair and transparent measures to ensure the right costs get on the right
bills. (Relatedly, the discussion about the full nature of transmission-related charges in
our concurrent PJM Order on Rehearing, Clarification, Compliance, and Paper Hearing 3
may prove relevant here: Real-world experience with new transmission services for co-
located load may clarify if future action becomes needed to address potential cost shifts
as Eligible Customers take new transmission services on behalf of large loads.4)
More generally, as we gain more experience as an industry and a country in
getting large loads connected to the grid, I welcome bold proposals to keep affordability
central. Large load growth presents a real opportunity to build a stronger, more capable,
and more reliable electric system that can benefit all ratepayers. Meeting that opportunity
at the pace we need and at an acceptable cost requires innovative thinking and fast action.
I commend the States in their continued work in these areas. I urge the RTOs and ISOs
to continue their good work as they respond quickly to today’s orders. I also remain
committed to moving forward within the Commission’s statutory zone with clarity and
decisiveness. I am proud to support the Commission’s important steps today. And we all
have more work ahead.
For these reasons, I respectfully concur.
______________________________
Lindsay S. See
Commissioner
3 PJM Interconnection, L.L.C., 195 FERC ¶ 61,209 (2026).
4 See id. P 456.
PDF page 105
UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION
ISO New England Inc.
Central Maine Power Company
The Connecticut Light and Power Company
Fitchburg Gas and Electric Light Company
Green Mountain Power Corporation
Maine Electric Power Company
The Narragansett Electric Company
New England Power Company
New Hampshire Transmission, LLC
NSTAR Electric Company
Public Service Company of New Hampshire
The United Illuminating Company
Unitil Energy Systems, Inc.
Vermont Electric Cooperative, Inc.
Vermont Electric Power Company, Inc.
Vermont Transco LLC
Versant Power
Docket No. EL26-72-000
(Issued June 18, 2026)
CHANG, Commissioner, concurring:
In a series of orders today, the Commission initiates separate proceedings under
Federal Power Act (FPA) section 206 to explore the impact of the increasing growth of
large loads in Regional Transmission Organization (RTO) and Independent System
Operator (ISO) regions. The preliminary findings in these orders, and the associated
proposed reforms to RTO/ISO and transmission owner tariffs, could significantly change
how loads procure, use, and pay for transmission service, with ramifications for
RTO/ISO operations, planning, and markets. I write separately to emphasize the
importance of building actionable records in these proceedings, particularly with respect
to our consideration of customer protection, transmission service, and alternative
transmission technology reforms.
I.
Overview of Today’s Orders
In each of today’s orders to show cause, the Commission identifies a series of
issues raised by the ongoing growth of large loads, directs briefing on whether existing
tariffs remain just and reasonable in light of those developments, and describes possible
solutions to those issues if the Commission ultimately concludes that the relevant tariffs
PDF page 106
Docket No. EL26-72-000
- 2 -
are unjust and unreasonable. Each order is directed to a specific RTO/ISO and relevant
transmission owners that play a role in interconnecting large loads to the Commission-
jurisdictional transmission system. The Commission does not pursue the broad assertion
of jurisdictional authority contemplated in the Advanced Notice of Proposed
Rulemaking, which I hope assuages concerns raised by our state colleagues that the
Commission ought not encroach upon matters properly left to their jurisdiction.1
Broadly summarized, each order seeks regional input on a specific list of issues:
(1) the clarity and consistency of existing rules governing how each RTO/ISO and its
relevant transmission owners analyze the impact of providing transmission service to
Eligible Customers on behalf of large loads; (2) whether each RTO/ISO tariff requires
reforms to mitigate the risk of cost shifting among wholesale transmission customers; (3)
whether each RTO/ISO tariff (other than PJM) requires additional clarity regarding the
provisions addressing co-located generation and load arrangements; (4) the potential
extension of new firm and non-firm transmission services to co-located load, load with
behind the meter generation, and other flexible loads; and (5) the need for reforms,
modeled on Southwest Power Pool, Inc.’s High Impact Large Load Generation
Assessment concept, to facilitate a process through which a generator may temporarily
serve a co-located or electrically proximate load until interconnection and transmission
service is available. The Commission also invites each region to submit FPA section 205
filings that can address each issue identified in the orders, thereby resolving the
Commission’s concerns.
II.
The Commission Needs Good Records to Ensure Reasoned Decision-Making
I first want to emphasize that the Commission needs active participation from
interested stakeholders to develop thorough records in each region. The Commission
cannot make reasoned decisions about whether reforms might be needed without an
accurate understanding of the existing processes, which differ by region. Because the
Commission is acting via FPA section 206 rather than generically through a rulemaking,
the issues addressed by these orders will be subject to ex parte restrictions across the
RTOs/ISO regions, including with our state colleagues whose regulation can and will
directly affect the individual transmission owners that need to comply with the orders
issued today. This will limit the Commission’s ability to engage in informal fact-finding
1 I will do my part to ensure that the Commission continues to be a collaborative
partner to our state counterparts, other federal agencies, and the industry as we seek to
address this wide-ranging challenge. Accordingly, I welcome feedback from our state
colleagues and others if they believe the Commission’s preliminary findings raise
jurisdictional concerns.
PDF page 107
Docket No. EL26-72-000
- 3 -
and discussions with regional stakeholders, and thus, it is even more essential that the
record in each region fully reflects the views of all interested parties.
Second, I highlight three issues below that will be especially important to the
success of this effort, and I hope that interested parties will take particular care in helping
the Commission address those issues. Importantly, I recognize that the record established
in each RTO/ISO region will (and should) differ, which will allow the Commission to
ensure any required changes to an RTO/ISO’s tariff are appropriately tailored to that
region’s needs.
III.
The Commission Needs to Pursue Meaningful Customer Protection
The FPA is fundamentally a customer protection statute,2 and the Commission has
an obligation to ensure that the rates that wholesale and transmission customers pay are
just and reasonable. Rapid large load growth has strained planning and resource
procurement processes around the country, as transmission owners, load serving entities,
and generators accelerate the building of new infrastructure needed to serve these new
loads. As we develop the new infrastructure, many have raised concerns about whether
these costs are being fairly assigned to new and existing customers, whose benefits must
be commensurate with the costs they pay. While individual states have been exploring or
using various approaches to protect retail customers against unjustified cost shifts, the
Commission to date has not initiated any proactive exploration of how to protect
wholesale customers against unjustified cost shifts. I am laser-focused on this issue
because we should not create unjustified costs for consumers in our efforts to connect and
serve large loads.
In today’s orders, the Commission launches an inquiry into whether existing
RTO/ISO tariffs include adequate mechanisms to mitigate the risk of undue cost shifting
among transmission customers. To address this risk, the Commission preliminarily
identifies a two-part solution: (1) that each RTO/ISO post public information about the
amount of new large loads seeking to connect to the RTO’s/ISO’s transmission system,
any Network Upgrades identified in the local transmission planning process to serve
those loads, and the costs of those Network Upgrades; and (2) that each RTO/ISO adopt a
pro forma cost recovery agreement to help ensure that Eligible Customers serving large
loads bear the risk and are ultimately responsible for costs incurred to provide
transmission service. I strongly support this effort to provide additional transparency
regarding jurisdictional transmission service requests and the costs associated with
providing transmission service to the requesting parties, as the Commission cannot
2 See, e.g., Mun. Light Bds. Of Reading and Wakefield v. FPC, 450 F.2d 1341,
1348 (D.C. Cir. 1971) (stating that the FPA’s “primary aim is the protection of
consumers from excessive rates and charges”).
PDF page 108
Docket No. EL26-72-000
- 4 -
effectively execute its statutory responsibilities without sufficient understanding of the
costs that feed into jurisdictional rates.
Exploring how agreements between transmission owners and Eligible Customers
can protect wholesale customers against cost shifts is important. However, as I have
previously explained, bilateral agreements that simply provide transmission revenue
contributions untethered from any assessment of the actual cost of providing transmission
service induced by individual large loads may be insufficient to adequately protect other
customers against unjustified cost shifts.3 It is therefore important that the resulting
regulatory and rate design are not limited to a pre-defined solution set, and that parties
provide the Commission with comprehensive records outlining various and innovative
approaches to protect customers. I am encouraged by the continued development of the
ANOPR record on this subject,4 innovative solutions being developed at the state level,5
and a growing body of thoughtful analyses and proposed approaches to provide customer
protection for costs driven by large load growth.6 Without prejudging any particular
proposed solution, the Commission needs a robust record in each docket and each region
to ensure we establish the right cost shift protections for wholesale customers, including
but not limited to the commitments outlined in the Ratepayer Protection Pledge.7
3 E.g., PECO Energy Co., 193 FERC ¶ 61,148 (2025) (Comm’r
Chang, concurring); Commonwealth Edison Co., 194 FERC ¶ 61,109 (2026) (Comm’r
Chang, concurring).
4 E.g., Interconnection of Large Loads to the Interstate Trans. Sys., Supplemental
Comments of FirstEnergy Svc. Co., Docket No. RM26-4-000 (filed June 5, 2026); id.,
Comment of the Harvard Electricity Law Initiative, Docket No. RM26-4-000 (Apr. 15,
2026); id., Supplemental Comments of WIRES, Docket No. RM26-4-000 (Mar. 30,
2026).
5 E.g., Utility Dive, Microsoft seeks Nevada tariff to shield ratepayers from data
center costs (June 8, 2026), available at https://www.utilitydive.com/news/microsoft-
seeks-nevada-tariff-to-shield-ratepayers-from-data-center-costs/822250/.
6 E.g., Travis Kavulla, How Will Data Centers Pay for Power?, American Affairs
(may 2026), available at https://americanaffairsjournal.org/2026/05/how-will-data-
centers-pay-for-power/ ; Electricity Customer Alliance, A Customer-Centric Agenda for
the Federal Energy Reg. Comm’n (Jan. 2026), available at https://lnkd.in/em-apfuQ;
Grid Strategies, Federal Transmission Pricing Vol. 2, Options for Ensuring Affordability
in an Era of High Load Growth (June 2026), available at
https://gridstrategiesllc.com/project/federal-transmission-pricing.
7 Proclamation No. 11014, 91 Fed. Reg. 11439 (Mar. 4, 2026).
PDF page 109
Docket No. EL26-72-000
- 5 -
I support initiating our own review of customer protection approaches, rather than
simply relying on voluntary commitments that may fall short of optimal protection,
because the Commission has the opportunity and obligation to get this issue right. I
therefore encourage interested parties to assist the Commission in that effort by clearly
and comprehensively explaining the benefits and tradeoffs of alternative customer
protection approaches. How power infrastructure costs will be assigned across Eligible
Customers that serve large loads and other customers is at the core of the efforts we
initiate today.
IV.
The Commission Needs to Understand the Implications of Extending New
Transmission Services to Additional Loads and Regions
The orders also preliminarily find that the Commission should extend the
transmission services developed in the PJM co-location proceeding – Interim NITS, Firm
Contract Demand, and Non-Firm Contract Demand – to new types of load and new
regions. These new transmission services represent a fundamental paradigm shift from
the traditional network service and point-to-point transmission service models established
in Order No. 888 that have been used across the country for the last three decades. While
these services have the potential to facilitate more efficient use and build out of the
transmission system, they also contemplate running the system “tighter” than we have
done in the past, potentially with more loads on the system served by co-located or
behind-the-meter generation, and potentially more use of batteries, load control systems,
and backup resources to manage demand during system peaks or other stressed
conditions. While it is important to identify innovative solutions that can adapt to the
needs of the system, the Commission and grid operators must also be careful not to
implement changes that create unforeseen reliability risks. Ultimately, we must find the
proper balance (and I would argue we are exploring a new balance) between costs of
investments versus reliability.
The Commission’s experience in the PJM co-location proceeding highlights the
complexities and challenges of introducing these new transmission services, which have
significant ramifications for system operations, transmission planning, grid reliability,
market dispatch, resource adequacy, and cost allocation. As the Commission considers
whether to expand these transmission services to new types of load and new regions, I
encourage commenters to address what impacts the introduction of new firm and non-
firm transmission products would have in their regions, as well as any relevant
characteristics that might distinguish their regions from the Commission’s findings in the
PJM co-location docket. Ultimately, this topic will have direct long-term impacts on how
future transmission systems will be planned and configured, how efficiently future power
markets will operate, and how customers will respond to prices and system needs.
Therefore, I am specifically interested in understanding how extending the new
transmission services might affect individual suppliers or customers, as well as how
existing systems or processes might be affected by these new services. I am open to
PDF page 110
Docket No. EL26-72-000
- 6 -
understanding how these services might be helpful to a region or that they may create
problems not yet anticipated.
V.
The Orders Recognize the Importance of Evaluating Advanced Transmission
Technologies
Lastly, today we preliminarily find that each RTO/ISO’s tariff is unjust and
unreasonable because the tariff lacks clear and consistent provisions requiring the
evaluation of alternative transmission technologies as potential solutions to accommodate
an Eligible Customer’s request for transmission service on behalf of a large load.
Specifically, it is important for RTO/ISOs and transmission owners to evaluate whether
alternative transmission technologies are feasible in reducing the cost of transmission
system upgrades or allow for a faster timeline for accommodating the transmission
service request. As many transmission owners have explored various alternative
technologies in pilot projects,8 it is time to roll out all available technologies to reduce
risks and costs for customers, as well as help the industry continue to develop new
technologies that can increase the robustness of our transmission system while protecting
customers from higher costs.
8 See, e.g., Increasing Mkt. and Planning Efficiency Through Improved Software,
Effective Congestion Mitigation with Transmission Topology Optimization at Alliant
Energy and ATC, Docket No. AD10-12-016, available at
https://www.ferc.gov/media/effective-congestion-mitigation-transmission-topology-
optimization-alliant-energy-and-atc (Alliant and ATC were able to save customers
approximately $24 million over a 12-month period through the use of topology
optimization); Pablo Ruiz and Derek Brown, “Reliable and Efficient Congestion
Mitigation Using Transmission Reconfigurations,” NewGrid and Evergy presentation
(Oct. 2022)¸ available at https://www.spp.org/Documents/67968/SAG%20Meeting%20
Materials%2020221007.zip (identifying reconfigurations, had they been implemented,
which could eliminate 98% of overloads and reduce congestion costs by 85% for
congestion patterns associated with 10 significant constraints on Evergy’s system);
Pacific Gas & Electric Press Release, PG&E and Smart Wires Enhance Grid Reliability,
Capacity for Data Centers in San Jose (May 28, 2025), available at
https://investor.pgecorp.com/news-events/press-releases/press-release-details/2025/PGE-
and-Smart-Wires-Enhance-Grid-Reliability-Capacity-for-Data-Centers-in-San-
Jose/default.aspx (describing PG&E’s deployment of advanced power flow control
devices were able to mitigate thermal overloads by up to 34%, enabling an additional 100
MW of firm power delivery over existing lines at a congested substation).
PDF page 111
Docket No. EL26-72-000
- 7 -
VI.
Conclusion
Today’s orders address some of the most consequential issues currently in the
industry and before the Commission. I hope that these proceedings provide vehicles
through which the Commission can provide much-needed clarity and direction, and it is
imperative that we build strong and comprehensive records on each issue in each region
to inform our decision-making. I therefore encourage all interested parties to fully
engage and help the Commission navigate these complex, multi-faceted challenges. Our
success will ultimately be measured by our shared ability to deliver reliable and
affordable power to all customers, to ensure new loads can interconnect in a timely
fashion while paying their fair share of system costs, and to protect existing customers
against adverse reliability or economic impacts.
For these reasons, I respectfully concur.
________________________
Judy W. Chang
Commissioner
PDF page 112
UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION
ISO New England Inc.
Central Maine Power Company
The Connecticut Light and Power Company
Fitchburg Gas and Electric Light Company
Green Mountain Power Corporation
Maine Electric Power Company
The Narragansett Electric Company
New England Power Company
New Hampshire Transmission, LLC
NSTAR Electric Company
Public Service Company of New Hampshire
The United Illuminating Company
Unitil Energy Systems, Inc.
Vermont Electric Cooperative, Inc.
Vermont Electric Power Company, Inc.
Vermont Transco LLC
Versant Power
Docket No. EL26-72-000
(Issued June 18, 2026)
LACERTE, Commissioner, concurring:
I support today’s fleet of show cause orders. We are at an inflection point in the
history of American energy infrastructure. The extraordinary and rapid growth of large
loads in RTOs and ISOs is faster than the current system can handle. This order charts a
course for addressing the potential gaps and shortcomings in ISO-NE’s Tariff that need to
be resolved to appropriately respond to this growth, as informed by careful review of the
thousands of pages of comments received in response to the advance notice of proposed
rulemaking (ANOPR).1 I write separately to underscore my expectation for RTOs and
ISOs, including ISO-NE, to timely submit their robust, thoughtful, and region-specific
proposals to address the concerns that we have preliminarily identified in their respective
tariffs and agreements. By harnessing your region-specific expertise and creativity to
bring tailored solutions to the table, together we can efficiently, reliably, and affordably
1 Interconnection of Large Loads to the Interstate Transmission System, Advance
Notice of Proposed Rulemaking, Docket No. RM26-4-000, (Oct. 23, 2025) (ANOPR);
see also Letter from Chris Wright, Sec’y, U.S. Dep’t of Energy (Oct. 23, 2025)
(Secretary’s Letter).
PDF page 113
Docket No. EL26-72-000
- 2 -
integrate large load, co-located load and generation and/or storage, as well as electrically
proximate large load onto the transmission system. I also support the use of alternative
transmission technologies to unlock every megawatt of existing capacity from our current
transmission system. We have the technology. We should use it now to enable faster
interconnection of large loads, lower costs to customers, and help prevent cost shifting.
To that end, and in light of our action in today’s orders, I also ask the state public
utility commissions—whether they have already approved large load retail tariffs, are in
the process of crafting large load retail tariffs, or have yet to embark on this essential
tariff design process—to take a hard look and ensure their large load retail tariff
provisions insulate ratepayers from the negative impacts of data center growth.
Additionally, I expect ISO-NE to design proposals in response to this show cause order
that dovetail with the efforts on the retail side to implement the Ratepayer Protection
Pledge, protect customers, and ensure that large loads cover the costs they incur to
integrate with the grid.
The stakes here could not be higher and every gambler knows that the secret to
surviving is knowing what to throw away and knowing what to keep.2 Today’s orders do
exactly that—adopting thoughtful proposals that position our nation for success, driving
meaningful change, and rejecting the gridlock, half-measures, and failure to plan that
have gone on for far too long. The data center odyssey that we embarked upon first with
PJM, then SPP, we now aggressively extend to all the RTO/ISO regions.3 Enabling the
swift and efficient interconnection of large loads to the transmission system while
maintaining affordability, reliability, commitment to open access, competitive principles
and cooperative federalism, will only be achieved through consistent, coordinated action
and persistence. But without that first step,4 there is no direction, no forward momentum,
no journey, and no way to arrive at our future destination. In the show cause orders we
issue today, the Commission takes a series of long strides towards our ultimate large load
interconnection destination: we make preliminary findings that the RTO/ISO tariffs,
including ISO-NE, may be unjust and unreasonable and/or unduly discriminatory or
2 Kenny Rogers, The Gambler (United Artists Records 1978).
3 Interconnection of Large Loads to the Interstate Transmission System, 195
FERC ¶ 61,045 at P 2 (2026) (Order Regarding Intent to Act) (citing PJM Co-Location
Order, 193 FERC ¶ 61,217; SPP HILL Order, 194 FERC ¶ 61,031; Commonwealth
Edison Co., 194 FERC ¶ 61,181 (2026); Tri-State Generation and Transmission Ass’n,
193 FERC ¶ 61,070 (2025); Duke Energy Carolinas, LLC, 193 FERC ¶ 61,237 (2025)).
4 Admittedly, we are further down the road in some regions as compared with
others.
PDF page 114
Docket No. EL26-72-000
- 3 -
preferential because they lack features necessary to timely, reliably, and safely
interconnect and serve new large loads in a way that produces just and reasonable rates.
I commend each commentor for their robust and ongoing responses to the
concerns that Secretary Wright and the Commission raised in the ANOPR proceeding.
The comments helped us identify the common issues, common solutions, and individual
differences among the RTOs/ISOs. We heard a plea for broad flexibility and regionally
tailored solutions. And we will strive to work towards those solutions, not through top-
down, one-size-fits-all mandates, but through consideration of region-specific proposals.
And we endeavor to support an appeal for federal policies that build upon rather than
disrupt current and planned developments, reflecting state and local processes and
stakeholder efforts. Through these individually tailored and region-specific show cause
orders, we are delivering to ensure that our transmission system can accommodate new
large loads in a timely, safe, and reliable manner. And, importantly, in a manner that
ensures benefits and protection for all customers. Affordability remains a top concern as
we proceed forward.
The collective voices in the ANOPR comments have shaped our decision to issue
six separate individually tailored and region-specific show cause orders, rather than a
proposed final rule at this time. But the success of the next phase of this journey rests
with you, ISO-NE, and your stakeholders. We are directing you to expeditiously bring
forward for our consideration your novel, region-specific solution(s). Time is of the
essence. By inviting you to proceed under FPA section 205, we are giving you
significant perks: the benefits of first wielder of the pen and the relatively capacious
standard under FPA section 205 that allows us to accept a potentially broad range of
proposals provided they are shown to be just and reasonable and not unduly
discriminatory or preferential.5 We are even giving you flexibility to propose the
implementation date for your innovative proposals. But such freedom comes with great
and concomitant responsibility.
This is not a time to be cavalier and dodge the urgent need to meet the moment.
While this is a long journey, even so, we must continue to move at breakneck pace to win
5 See, e.g., NRG Power Mktg, LLC v. FERC, 862 FERC 108, 105 (D.C. Cir. 2017)
(FERC may not employ a rate design that follows “a completely different strategy” than,
or is “methodologically distinct” from, a proposed rate) (internal quotations omitted);
Oxy USA, Inc. v. FERC, 64 F.3d 679, 692 (D.C. Cir. 1995) (stating that a proposal under
FPA section 205 “need not be the only reasonable methodology, or even the most
accurate”); City of Winnfield v. FERC, 744 F.2d 871, at 874-875 (D.C. Cir. 1984)
(comparing the respective authorities of the Commission and public utilities under
sections 205 and 206).
PDF page 115
Docket No. EL26-72-000
- 4 -
the AI race. So let me be direct. If you choose not to submit timely, reasonable, non-
discriminatory or preferential, comprehensive, and substantiated proposal(s), as directed
and as required under our applicable statutes, your deficient response will not go
unnoticed. I am prepared to play jurisdictional hardball, if needed.6 This Commission
has appropriately exercised considerable restraint in asserting the full scope of our
jurisdiction in these orders. However, the Commission has very broad jurisdiction over
transmission that we will not hesitate to utilize as necessary to ensure that we meet our
objectives in all show cause proceedings, including this ISO-NE proceeding we initiate
here. If we find your Tariff is in fact unjust and unreasonable and unduly discriminatory
or preferential, any failure on your end to provide a sufficient FPA filing or filings to
address the large-load-related concerns that we have identified will result in the
Commission dictating the solutions for you. I say this not as a threat, but as a statement
of duty. While you may not like our remedies—I have often said that the federal
government generally does not come up with the best solutions—this is an outcome we
are prepared to pursue given the gravity of the moment and our statutory obligation.
Notwithstanding our readiness to step in, it greatly benefits everyone for you to come up
with an approach tailored to your region.
I will end my concurrence where I began: We have heard your concerns, and, let
me underscore, now is the time for you to heed ours. This is an extraordinarily
consequential proceeding. The stakes for reliability, for affordability, and for the
American ratepayer could not be higher. We owe it to the public to get this right. I look
forward to reviewing and acting as expeditiously as possible on your responses to this
show cause order, which I expect will include an FPA section 205 proposal or proposals.
For these reasons, I respectfully concur.
______________________________
David LaCerte
Commissioner
6 16 U.S.C. § 824(b); New York v. FERC, 535 U.S. 17 (2002) (“There is no
language in the statute limiting FERC’s transmission jurisdiction to the wholesale
market[.]”)) (emphasis in original); id. at 20 (stating that “the FPA authorizes FERC's
jurisdiction over interstate transmissions, without regard to whether the transmissions are
sold to a reseller or directly to a consumer[.]”).