EL26-67-000 · 2026-07-09 · Individual No Affiliation
Motion to Intervene and Comments of Evan Pierce re the large-load interconnection tariff provisions
Back to sections and commentaryPDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
)
Docket No. EL26-67-000
I. MOTION TO INTERVENE
New Era Energy & Digital Inc. is a data center developer pursuing data center and energy
development in the PJM service area. New Era Energy & Digital Inc. is concerned with
maintaining transmission reliability and affordability while advancing economic development
associated with data centers.
II. COMPLIANCE WITH RULE 203
The exact name of the movant is New Era Energy & Digital Inc. New Era Energy & Digital’s
principal place of business is located at 200 N. Loraine Street, Suite 1324, Midland, TX 79701.
Service of pleadings, documents, and communications in this proceeding should be made on the
following: Evan A. Pierce, Chief Development Officer – evan@newerainfra.ai
III. INTRODUCTION AND RELEVANT BACKGROUND
A. The Commission Opened This Section 206 Proceeding in Response to Rapid
Large-Load Growth and the Need for Tariff-Specific Reforms in PJM.
This proceeding arises from the Commission’s ongoing consideration of the transmission,
reliability, affordability, and cost-allocation issues associated with the rapid growth of large
loads, namely data centers. On October 23, 2025, the Secretary of Energy issued an advance
notice of proposed rulemaking requesting that the Commission consider additional action to
address the addition of large and co-located loads to the interstate transmission system.1 The
Commission subsequently agreed that large-load growth created an urgent need for reforms to
ensure timely, orderly, and non-discriminatory interconnection, concluded that further action was
warranted, and announced its intent to act by the end of June 2026.2
On June 18, 2026, the Commission instituted this proceeding under section 206 of the Federal
Power Act—a process for examining and potentially fixing unjust or unreasonable tariff rules.3
The Commission preliminarily found that PJM’s Open Access Transmission Tariff—the
1 Ensuring the Timely and Orderly Interconnection of Large Loads, Advance Notice of Proposed Rulemaking,
Docket No. RM26-4-000 (October 2025).
2 Interconnection of Large Loads to the Interstate Transmission Sys., 195 FERC ¶ 61,045, at PP 2–4 (April 2026).
3 PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 (June 2026) (“Order Instituting Proceeding Under Section 206
of the Federal Power Act”).
PDF page 2
rulebook governing access to PJM’s transmission system—appears to be unjust, unreasonable, or
unduly discriminatory or preferential (the Federal Power Act standard for unlawful tariff terms)
because it lacks sufficiently clear and consistent provisions addressing the integration of large
loads onto the PJM transmission system.4 The Commission therefore directed PJM and the PJM
Transmission Owners to “show cause” why the Tariff remains just and reasonable without such
provisions, or to explain what Tariff changes would remedy the Commission’s concerns if the
Commission proceeds to establish a replacement Tariff.5
The Commission’s order identifies four categories of tariff issues relevant here: (1) the
application process, study procedures, and ongoing operational requirements for Eligible
Customers (entities that may request transmission service under PJM’s tariff) seeking
transmission service on behalf of large loads; (2) transparency and cost-recovery measures for
Network Upgrade costs (the costs of transmission-system improvements needed to accommodate
the service) associated with such service; (3) transmission services for flexible large loads that
are willing and able to limit their use of the transmission system under certain conditions; and (4)
the rates, terms, and conditions applicable to interconnection customers serving co-located load
or electrically proximate load (meaning large demand located at or near a generation facility).6
The Commission also directed PJM to file a report explaining how PJM will ensure that adequate
generation will be available to serve existing and new large loads.7
B. The Commission Identified PJM-Specific Concerns Regarding Large Loads, Co-
Located Generation, Flexible Demand, and Resource Adequacy.
The Commission’s concerns are substantial in PJM. The order notes that PJM’s load forecast
predicts peak load growth of 32 GW from 2024 to 2030, with 30 GW of that growth projected to
come from data centers.8 The order also identifies comments raising concerns that large-load
additions in PJM are contributing to resource-adequacy, reliability, affordability, and
interconnection-delay challenges.9 In addition, the Commission summarized concerns that
infrastructure costs driven by data center load could be shifted to other transmission customers,
including through Network Upgrade costs and transmission costs borne in corresponding PJM
zones or, where applicable, the broader PJM region.10
The Commission also emphasized the need for clearer tariff rules governing flexible large loads.
The order recognizes that certain large loads may be willing and able to limit their withdrawals
from the transmission system under specified conditions, and preliminarily finds that PJM’s
4 Id. PP 3, 35.
5 Id. PP 3, 35, Ordering Para. (B).
6 Id. PP 3, 35.
7 Id. PP 3, 102–104, Ordering Para. (C).
8 Id. P 8.
9 Id. P 9.
10 Id. PP 9–10.
PDF page 3
Tariff appears unjust and unreasonable because it lacks transmission services reflecting those
operational characteristics.11 Similarly, the Commission preliminarily found that PJM’s Tariff
appears to lack generator interconnection study procedures and services that allow
interconnection customers serving electrically proximate large load or large co-located load to
obtain interconnection service reflecting the operational dynamics of serving such load. 12
Finally, the Commission identified a related supply-side concern. PJM has undertaken several
initiatives to address resource adequacy and large-load growth (whether enough generation will
be available to meet demand reliably), including the Reliability Resource Initiative, Expedited
Interconnection Track, voluntary “Bring Your Own New Generation” approach, and the connect-
and-manage framework.13 The Commission nevertheless expressed concern that these efforts
may be insufficient, particularly in light of generator retirements and tightening supply
conditions, and directed PJM to file a detailed informational report addressing how adequate
generation will be available to serve existing and new large loads.14
The below comments address two issues that fall within the scope of the Commission’s order
and should be addressed in PJM’s forthcoming filings: first, the use of “Maximum Net
Withdrawal” as a tariff-based mechanism for evaluating large loads paired with dependable
nearby generation; and second, fast-track treatment for safe supply additions, including uprates
(output increases at existing power plants) and reactivation or reconnection of retired or
mothballed capacity (existing power plants or units that are shut down or inactive), as part of
PJM’s response to the Commission’s resource-adequacy directive.
IV. LIMITED COMMENTS
New Era Energy & Digital submits these limited comments to identify two issues that PJM
should address in its forthcoming filings in this proceeding. These comments are directed to the
specific issues raised in the Commission’s June 18, 2026 order: the treatment of generation
serving electrically proximate or large co-located load, and PJM’s required report on the
availability of adequate generation to serve existing and new large loads.15
A. PJM Should Address Maximum Net Withdrawal as Part of Any Framework for
Generation Serving Electrically Proximate or Large Co-Located Load.
The Commission preliminarily found that PJM’s Tariff appears to be unjust and unreasonable
because it lacks generator interconnection study procedures and services allowing an
11 Id. PP 85–87.
12 Id. PP 88–101; id. P 95.
13 Id. PP 31–34; id. P 103.
14 Id. PP 102–104.
15 PJM Interconnection, L.L.C., 195 FERC ¶ 61,211, at PP 3, 35, 88–104 (2026) (“Order Instituting Proceeding
Under Section 206 of the Federal Power Act”).
PDF page 4
interconnection customer to seek generator interconnection service that reflects the operational
dynamics of serving electrically proximate large load or large co-located load.16 The
Commission also identified potential generator-side approaches under which a generating
facility’s output could be limited to match the associated load, existing Energy Resource
Interconnection Service or Network Resource Interconnection Service (ERIS and NRIS; two
types of generator interconnection service under PJM’s rules) could be used with controls to
prevent net injection (power exported onto the transmission system) above the existing
interconnection agreement, or a new generator interconnection service could ensure no injection
to the transmission system. 17
PJM’s response should address the corresponding load-side issue as well. Where a large load is
paired with dependable nearby generation and accepts binding operational limits on its reliance
on the transmission system, PJM should evaluate the project based on the facility’s enforceable
maximum net withdrawal from the transmission system, rather than assuming the facility will
impose its full gross demand (the facility’s total electricity need before accounting for nearby
generation) on the grid at all times.
For purposes of these comments, “Maximum Net Withdrawal” means the enforceable upper
limit, measured in megawatts at the applicable point of interconnection or delivery point, that the
combined load/generation configuration may withdraw from the transmission system. A
Maximum Net Withdrawal framework would not replace reliability analysis. Rather, it would
provide the correct study assumption where the project’s physical configuration, controls, and
service obligations make the net-withdrawal limit operationally enforceable.
Such an approach fits the Commission’s reasoning in this order. The Commission explained that
where a generating facility’s output is matched to the demand of electrically proximate large load
or large co-located load, or where the generating facility’s output is limited to ensure no new
injection, the transmission-system impacts may be limited and may reduce the need for Network
Upgrades.18 That same principle supports studying the associated load based on an enforceable
cap on net withdrawals where the load and generation are operated as a controlled configuration.
PJM should therefore address whether any tariff provisions proposed in response to this order
should include: (1) a binding net-withdrawal cap in the relevant service agreement or other tariff-
governed arrangement; (2) real-time metering and telemetry (measurement and communications
data visible to grid operators) for load, generation, and net withdrawals; (3) operational controls
or protection systems sufficient to maintain withdrawals within the approved limit; (4) operator
visibility (PJM’s ability to see and manage the facility’s grid impacts in real time) sufficient to
16 Id. P 95.
17 Id. PP 95, 98, 100.
18 Id. PP 95–96.
PDF page 5
preserve reliability; and (5) tariff consequences if the facility exceeds its approved Maximum
Net Withdrawal.
PJM should also explain what transmission service the Eligible Customer must take for a large
load operated subject to an enforceable Maximum Net Withdrawal. The Commission expressly
encouraged PJM to consider what type of transmission service an Eligible Customer will need to
take on behalf of electrically proximate large load or large co-located load, noting that generator
interconnection service does not itself convey transmission service.19 A Maximum Net
Withdrawal framework would help answer that question by tying the associated transmission
service to the project’s enforceable use of the transmission system, rather than to an assumption
that the full gross load must always be served from the grid.
B. PJM’s Resource-Adequacy Report Should Address Fast-Track Treatment for Safe
Supply Additions.
The Commission separately directed PJM to file an informational report explaining how PJM
intends to ensure that adequate generation will be available to serve existing and new large
loads.20 The Commission recognized PJM’s existing efforts, including the Reliability Resource
Initiative, Expedited Interconnection Track, voluntary “Bring Your Own New Generation”
approach, connect-and-manage framework, and reliability backstop procurement, but stated that
those efforts may still fall short in light of generator retirements and tightening supply
conditions.21
PJM’s report should address not only how large loads can be served more quickly, but also how
additional supply can be brought online more quickly where the system impacts are bounded and
can be studied safely. Large-load growth presents a supply problem as well as a load-service
problem. A complete response should therefore address whether PJM’s existing tariff and study
processes allow expedited treatment for limited, low-risk generation additions that can increase
available supply without requiring a full multi-year queue process.
In particular, PJM should address whether its Tariff provides an adequate pathway for expedited
treatment of uprates at existing generating facilities. Such treatment should be limited to
modifications that rely on existing interconnection facilities, do not involve a change in
generation technology or fuel type, can be evaluated independently through existing system
models or a limited-scope study (a narrower review focused on the incremental grid impacts),
and do not materially affect the cost or timing of lower-queued projects (those that entered the
interconnection queue later) or already-interconnected projects. Where those conditions are met,
19 Id. P 101.
20 Order, 195 FERC ¶ 61,211 at PP 102–104, Ordering Para. (c).
21 Id. P 103.
PDF page 6
the incremental nature of the uprate may warrant a narrower and faster study process while
preserving all applicable reliability requirements.
PJM should also address whether its Tariff provides an adequate pathway for expedited
reconnection or reactivation of retired or mothballed capacity. Such treatment should be
available only where the relevant interconnection facilities remain available or can be safely
restored, required permits and operating authorizations remain available or can be obtained, and
any reliability impacts can be evaluated through a limited-scope review. The purpose would not
be to bypass reliability review, but to avoid subjecting bounded reactivations of existing capacity
to procedures designed for wholly new speculative projects.
The Commission has already recognized, in this order and related precedent, that certain forms
of generator interconnection service may allow resources to interconnect more quickly where
their impacts are limited or where they use existing interconnection capability. PJM’s required
resource-adequacy report should therefore identify whether existing PJM processes are adequate
to accelerate safe uprates and reconnections, and if not, what tariff changes or stakeholder
processes would be needed to create such a pathway.
C. Reservation of Rights
Because the Commission has directed PJM to file a 30-day informational report and a 60-day
show-cause response, and has allowed interested entities to respond after those filings, New Era
Energy & Digital submits these comments on a limited basis and reserves the right to submit
further comments after PJM and the Transmission Owners make their directed filings.22
V. CONCLUSION
For the foregoing reasons, New Era Energy & Digital respectfully requests that the Commission
grant its motion to intervene and consider these limited comments in evaluating PJM’s
forthcoming filings in this proceeding.
22 Order, 195 FERC ¶ 61,211, Ordering Paras. (B), (C), (E).