EL26-67-001 · 2026-07-20 · Indicated PJM Transmission Owners
The Indicated PJM Transmission Owners submit Request for Clarification, or in the Alternative, Rehearing of the 06/18/2026 Order
Back to sections and commentaryPDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
)
Docket No. EL26-67-000
REQUEST FOR CLARIFICATION, OR IN THE ALTERNATIVE, REHEARING OF
THE INDICATED PJM TRANSMISSION OWNERS
Pursuant to Section 313 of the Federal Power Act (“FPA”)1 and Rules 212 and 713 of the
Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“Commission” or
“FERC”),2 the Indicated PJM Transmission Owners (“PJM Transmission Owners”)3 respectfully
request clarification, or in the alternative, rehearing of the Commission’s order issued on June 18,
2026, in this proceeding relating to the appropriate definitions of “large load” and “electrically
proximate large load.”4
On June 18, 2026, the Commission issued show cause orders under section 206 of the FPA
to PJM Interconnection, L.L.C. (“PJM”), Midcontinent Independent System Operator, Inc.,
Southwest Power Pool, Inc., California Independent System Operator Corporation, ISO New
England Inc., and New York Independent System Operator, Inc., together with their transmission
1
16 U.S.C. § 825l(a).
2
18 C.F.R. §§ 385.212 and 385.713 (2025).
3
The Indicated PJM Transmission Owners are: American Electric Power Service Corporation on behalf of its
affiliates, Appalachian Power Company, Indiana Michigan Power Company, Kentucky Power Company, Kingsport
Power Company, Ohio Power Company, Wheeling Power Company, AEP Appalachian Transmission Company, Inc.,
AEP Indiana Michigan Transmission Company, Inc., AEP Kentucky Transmission Company, Inc., AEP Ohio
Transmission Company, Inc., and AEP West Virginia Transmission Company, Inc.; The Dayton Power and Light
Company d/b/a AES Ohio; Dominion Energy Services, Inc. on behalf of Virginia Electric and Power Company d/b/a
Dominion Energy Virginia; Duke Energy Business Services, LLC for Duke Energy Kentucky, Inc. and Duke Energy
Ohio, Inc.; Duquesne Light Company; East Kentucky Power Cooperative, Inc.; Exelon Corporation on behalf of its
affiliates Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company,
Commonwealth Edison Company of Indiana, Inc., Delmarva Power & Light Company, PECO Energy Company, and
Potomac Electric Power Company; FirstEnergy Service Company, on behalf of its affiliates American Transmission
Systems, Incorporated, Jersey Central Power & Light Company, Mid-Atlantic Interstate Transmission LLC, The
Potomac Edison Company, Monongahela Power Company, Keystone Appalachian Transmission Company, and
Trans-Allegheny Interstate Line Company (collectively, the “FirstEnergy Companies”); PPL Electric Utilities
Corporation; and Rockland Electric Company.
4
PJM Interconnection, L.L.C., et al., 195 FERC ¶ 61,211 (2026) (“PJM Show Cause Order” or “Order”).
PDF page 2
2
owners,5 directing each region to justify or reform the tariff provisions governing how large loads
connect to and receive service from the transmission system.6
The PJM Show Cause Order preliminarily found that PJM’s existing Open Access
Transmission Tariff (“PJM Tariff”) appeared to be unjust, unreasonable, or unduly discriminatory
or preferential because of a lack of sufficiently clear and consistent provisions to address service
for large loads and related configurations.7 The Commission therefore directed PJM and its
transmission owners, within 60 days, to show cause why the PJM Tariff remains just and
reasonable without provisions addressing: (1) the application process, study procedures, and
ongoing operational requirements for Eligible Customers8 seeking transmission service on behalf
of large loads; (2) additional transparency concerning Network Upgrade costs for such service,
together with the absence of a pro forma cost recovery agreement and a mechanism to ensure
related payments are properly credited to transmission owners’ revenue requirements; (3)
transmission service options tailored to flexible large loads willing and able to limit their use of
the transmission system under certain conditions; and (4) rates, terms, and conditions applicable
to interconnection customers serving “electrically proximate large load” or co-located load.9 The
5
Midcontinent Indep. Sys. Operator, Inc., et al., 195 FERC ¶ 61,212 (2026), Southwest Power Pool, et al.,
195 FERC ¶ 61,213 (2026), California Indep. Sys. Operator, Inc., et al., 195 FERC ¶ 61,214 (2026), ISO New England
Inc., et al., 195 FERC ¶ 61,215 (2026), New York Indep. Sys. Operator, Inc., et al., 195 FERC ¶ 61,216 (2026)
(collectively, the “Show Cause Orders”).
6
The Commission’s June 18, 2026, show cause orders follow the Secretary of Energy’s letter, pursuant to
section 403 of the Department of Energy Organization Act, directing FERC to initiate a rulemaking proceeding and
to consider its advanced notice of proposed rulemaking (“ANOPR”) to accelerate large load interconnections. See
Letter and ANOPR of Chris Wright, Sec’y, U.S. Dep’t of Energy (Oct. 23, 2025). The Commission subsequently
invited comments on the proposed ANOPR. See Notice Inviting Comments, Docket No. RM26-4-000 (issued Oct.
27, 2025).
7
PJM Show Cause Order at PP 3, 35.
8
All capitalized terms that are not otherwise defined herein shall have the meaning set forth in the PJM Tariff.
9
PJM Show Cause Order at PP 3, 35.
PDF page 3
3
Commission directed PJM either to justify the absence of such provisions or to propose Tariff
revisions addressing those concerns.10
The PJM Transmission Owners share the underlying goals driving the Commission’s
issuance of the Show Cause Orders: namely, to enable new large load customers to efficiently
interconnect to the transmission system while simultaneously ensuring reliability and protecting
existing customers. To that end, the PJM Transmission Owners respectfully seek clarification, or
in the alternative, rehearing of two preliminary findings in the PJM Show Cause Order:
1. The Commission should clarify that adopting the definition of “large load” proposed
in the Show Cause Order, including the 50 MW threshold criteria, does not prevent
PJM and the PJM Transmission Owners from proposing and supporting additional
service-specific criteria for large load customers relating to the types of services
contemplated in the Show Cause Order. If the Commission declines to make this
clarification, it should grant rehearing, as a one-size-fits-all approach for all customers
that meet the definition of “large load” is likely to be over-inclusive and unduly
discriminatory, and undermine the Commission’s speed-to-power goals for large load
customers, particularly large computational loads that are crucial to serving AI
processes.
2. The Commission should clarify that PJM and the PJM Transmission Owners will be
permitted to propose and support a definition of “large load” and “electrically
proximate large load” that are not based on the location of facilities relative to the Point
of Interconnection,11 e.g., by proposing a definition that relies on the Point of Change
of Ownership. If the Commission declines to adopt this clarification, it should grant
rehearing. As PJM and the PJM Transmission Owners have explained in the PJM co-
located load proceeding, there are significant problems with adopting such definitions
based on facilities on the customer-side of the Point of Interconnection, including
potentially encouraging gaming activities that will undermine the efficient and reliable
interconnection of large loads.
10
PJM Show Cause Order at PP 3, 35.
11
Id. at P 94 & n.7.
PDF page 4
4
I.
REQUESTS FOR CLARIFICATION AND REHEARING
A.
Statement of Issues and Specification of Errors
To the extent that the Commission declines to grant clarification as set forth below, the
PJM Transmission Owners submit the following Statement of Issues and Specification of Errors
pursuant to Rule 713(c)(1) and 713(c)(2) of the Commission’s Rules of Practice and Procedure:12
To the extent that the definition of “large load” proposed in the PJM Show Cause Order
is intended to restrict PJM and the PJM Transmission Owners from proposing and
supporting additional service-specific criteria for large load customers, the PJM Show
Cause Order is arbitrary and capricious, does not reflect reasoned decision-making, and
is unsupported by substantial evidence in violation of the Administrative Procedure Act
because the Commission did not develop a sufficient record to support such a
restriction, and such a restriction would be unjust, unreasonable, and unduly
discriminatory. Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto Ins. Co., 463 U.S.
29, 43 (1983) (an agency “must examine the relevant data and articulate a satisfactory
explanation for its action including a ‘rational connection between the facts found and
the choice made’”) (citation omitted) (“State Farm”); Consol. Edison Co. of N.Y. v.
FERC, 45 F.4th 265 (D.C. Cir. 2022); Consol. Edison Co. of N.Y. v. FERC, 347 F.3d
964, 972 (D.C. Cir. 2003); PJM Interconnection, L.L.C., 161 FERC ¶ 61,252 (2017);
Fla. Gas Transmission Co. v. FERC, 604 F.3d 636, 639 (D.C. Cir. 2010) (quoting Pac.
Gas & Elec. Co. v. FERC, 373 F.3d 1315, 1319 (D.C. Cir. 2004)) (“Fla. Gas”); PJM
Interconnection, L.L.C., 119 FERC ¶ 61,318 (2007); Midwest Indep. Transmission Sys.
Operator, Inc., 117 FERC ¶ 61,113 (2006) (“Midwest ISO”).
The PJM Show Cause Order is arbitrary and capricious, does not reflect reasoned
decision-making, and is unsupported by substantial evidence in violation of the
Administrative Procedure Act because the Commission did not develop a sufficient
record to support defining “large load” or “electrically proximate large load” by
reference to the interconnection customer’s point of interconnection. State Farm, 463
U.S. at 43 (an agency “must examine the relevant data and articulate a satisfactory
explanation for its action including a ‘rational connection between the facts found and
the choice made’”) (citation omitted); Consol. Edison Co. of N.Y. v. FERC, 45 F.4th
265; Consol. Edison Co. of N.Y. v. FERC, 347 F.3d at 972; PJM Interconnection,
L.L.C., 161 FERC ¶ 61,252; Fla. Gas, 604 F.3d at 639 (quoting Pac. Gas & Elec. Co.
v. FERC, 373 F.3d at 1319); PJM Interconnection, L.L.C., 119 FERC ¶ 61,318;
Midwest ISO, 117 FERC ¶ 61,113.
12
18 C.F.R. § 385.713(c)(1), (c)(2).
PDF page 5
5
B.
Arguments
1.
The Commission Should Clarify That the Proposed Definition of
“Large Load” in the Show Cause Order Does not Limit PJM and the
PJM Transmission Owners From Proposing Additional Service-
Specific Criteria for the Services Contemplated in the Order.
In the PJM Show Cause Order, the Commission preliminarily found that the PJM Tariff
appears unjust and unreasonable because it lacks certain provisions governing the process to
provide transmission service to Eligible Customers on behalf of large loads, including a definition
of large load, as a new category of load. The Commission further stated that, based on the ANOPR
record, it would be reasonable to define a large load as a new commercial or industrial customer
at a single site, behind one or more points of interconnection, with a peak load of 50 MW or greater,
interconnected at a voltage above 69 kV, and not part of a co-location arrangement. The
Commission therefore directed PJM either to show cause why the PJM Tariff remains just and
reasonable without such a definition or to propose tariff revisions establishing its own definition
of large load.
The Commission should clarify that this definition, including the 50 MW threshold, does
not limit PJM or the PJM Transmission Owners from proposing additional criteria or reasonable
distinctions between large load customers for purposes of designing and implementing the
products addressed in the Order. It may not be appropriate to offer identical services to all large
load customers. For instance, considerations such as seasonality versus peak load measurements
and functional distinctions between types of customers (e.g., hyperscale computational loads
versus “traditional” manufacturing and commercial customers) may merit distinctions in how
different products are designed, offered and priced. The Commission therefore should clarify that
the proposed large load definition does not prejudge the appropriate criteria for every other purpose
under the PJM Tariff.
PDF page 6
6
If the Commission declines to adopt this clarification, the Commission should grant
rehearing. The PJM Show Cause Order fails to justify a conclusion that the proposed large load
definition requires that every customer meeting the definition of large load must be offered the
same services under the same rates, terms and conditions.13 To the contrary, requiring a one-size-
fits all approach for all large load customers with respect to each new service is likely to undermine
the goals of the Show Cause Order, particularly the desire for speed-to-power. As the PJM
Transmission Owners explained in their comments on the ANOPR, an overly inclusive definition
of “large load” risks repeating the same flaws that occurred with inflated generation
interconnection queues.14 It is therefore of critical importance that PJM and the PJM Transmission
Owners have sufficient flexibility to design and implement services with appropriate criteria that
account for meaningful differences between large load customers. Limiting this flexibility would
be arbitrary, capricious, and would not reflect reasoned decision-making.
2.
The Commission Should Clarify That “Large Load” and “Electrically
Proximate Large Load” Need not be Defined Based on the Point of
Interconnection.
As noted above, the Commission indicated in the PJM Show Cause Order that it would be
reasonable to define a large load as a new commercial or industrial customer at a single site, behind
one or more points of interconnection.15 Similarly, in discussing potential rules and procedures
relating to “electrically proximate large load,” the Commission found that it would be reasonable
to define “electrically proximate large load” as a large load that is sufficiently electrically close to
the interconnection customer’s requested point of interconnection such that, with the exception of
the transmission facilities between the two, the impact on the transmission system of the
13
PJM Show Cause Order at P 58.
14
Indicated PJM Transmission Owners Comments, Docket No. RM26-4-000, at 4-9 (filed Nov. 21, 2025).
15
PJM Show Cause Order at n.2.
PDF page 7
7
combination of the generating facility and load will be effectively the same as if they were located
at the same substation.16
The Commission should clarify that in any Section 205 filing or other response to the PJM
Show Cause Order, PJM and/or the PJM Transmission Owners are not limited to defining “large
load” or “electrically proximate large load” based on reference to the point of interconnection, and
that they will have sufficient flexibility to propose other points of reference, such as the Point of
Change of Ownership. Given the significant detail that the Show Cause Order leaves to PJM and
the PJM Transmission Owners to develop as to what constitutes electrical proximity and other
aspects of the Show Cause Order’s proposal, it is crucial that PJM and the PJM Transmission
Owners have maximum flexibility to ensure speed-to-power, reliability, and customer protection
goals are met. Indeed, the Commission has already been presented, in the related co-located load
proceeding, with evidence that the point of interconnection frequently is an imprecise boundary
insofar as it may unreasonably conflate customer-owned facilities with those owned by other
entities, including Transmission Owner-owned facilities.17 In that proceeding, PJM and the PJM
Transmission Owners provided evidence that the definition of “Co-Located Load” should be based
on the Point of Change in Ownership,18 rather than the Point of Interconnection because it reflects
the legal and operational boundary between customer-owned facilities and transmission owner
facilities and avoids sweeping in transmission owner interconnection facilities into the definition
16
Id. at P 94.
17
See PJM 30-Day Compliance Filing, Docket No. ER26-1088-000, at 3 & n.14 (filed Jan. 20, 2026) (“30-Day
Compliance Filing”); see also PJM Transmission Owners Request for Rehearing or Clarification, Docket No. ER26-
1088-000, at 4-8 (filed May 18, 2026); PJM Interconnection, L.L.C., 195 FERC ¶ 61,030, at PP 27-28 (2026).
18
PJM defined “Point of Change in Ownership” in Tariff, Part VIII, Subpart A, section 400, Definitions P, is
the point at which “the Project Developer’s Interconnection Facilities connect to the Transmission Owner’s
Interconnection Facilities.” See 30-Day Compliance Filing at n.14.
PDF page 8
8
of large load.19 The Commission has, to date, rejected PJM’s proposal to define Co-Located Load
based on the Point of Change of Ownership because PJM did not seek rehearing or clarification of
the Commission’s order in the separate co-located load proceeding in which it adopted that
definition.20 That rejection is inapt here because the services that the Commission is proposing in
the Show Cause Order involve different customers (i.e., Co-Located Load customers versus other
types of large load customers), and thus, PJM and the PJM Transmission Owners cannot be limited
in responding to Show Cause Order based on the Co-Located Load dockets.
Furthermore, the PJM Transmission Owners are not asking the Commission to decide at
this time in this proceeding whether the point of interconnection or some other criteria should be
used to define “large loads” or “electrically proximate large loads.” Nevertheless, the Commission
should clarify that the PJM Show Cause Order does not require reference to the point of
interconnection, and that PJM and the PJM Transmission Owners may, in a Section 205 filing or
other response to the Order, propose other criteria, subject of course to showing they are just and
reasonable. If the Commission declines to grant this clarification, it should grant rehearing on this
issue. The PJM Show Cause Order does not explain why the point of interconnection is the
appropriate criterion for PJM, as opposed to other metrics such as ownership, delivery
configuration, voltage, or operational effect on the transmission system. Any determination that a
large load customer or electrically proximate large load customer must be defined based only on
reference to the point of interconnection is therefore not based on reasoned decision-making and
is not supported by substantial evidence.
19
See 30-Day Compliance Filing at 3 & n.14; see also PJM 60-Day Compliance Filing, Docket No. ER26-
1479-000, at 32 (filed Feb. 23, 2026).
20
See PJM Interconnection, L.L.C., 195 FERC ¶ 61,030, at P 27.
PDF page 9
9
II.
CONCLUSION
For the foregoing reasons, the PJM Transmission Owners respectfully request that the
Commission grant rehearing of the PJM Show Cause Order for the reasons set forth herein, or,
alternatively, clarify the Order as set forth in Section I.
Respectfully submitted,
/s/ Michael Kunselman
Michael Kunselman
Richard P. Sparling
Nicholas J. Cicale
Jonathan A. Namazi
Davis Wright Tremaine LLP
1301 K Street NW
Suite 500 East
Washington, DC 20005
Counsel for the FirstEnergy
Companies
On behalf of the Indicated PJM
Transmission Owners
Dated: July 20, 2026
PDF page 10
CERTIFICATE OF SERVICE
Under Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. §
385.2010 (2025), I hereby certify that I have this day served the foregoing document upon each
person designated on the official service list compiled by the Secretary in this proceeding.
Dated at Washington, D.C., this 20th day of July 2026.
/s/ Deiman Flores
Deiman Flores
Davis Wright Tremaine LLP
1301 K Street NW
Suite 500 East
Washington, DC 20005