EL26-71-000 · 2026-08-03 · Western Area Power Administration
Motion to Rescind Show Cause Order as applied to Western Area Power Administration
Back to sections and commentaryPDF page 1
- 1 -
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
California Independent System Operator
Corporation
Citizen S-Line Transmission LLC
Citizens Sunrise Transmission LLC
Citizens Sycamore-Penasquitos
Transmission LLC
City of Anaheim, California
City of Azusa, California
City of Banning, California
City of Colton, California
City of Pasadena, California
City of Riverside, California
DCR Transmission, L.L.C.
DesertLink, LLC
GridLiance West LLC
Horizon West Transmission, LLC
LS Power Grid California, LLC
Morongo Transmission LLC
Pacific Gas and Electric Company
San Diego Gas & Electric Company
Southern California Edison Company
Startrans IO, L.L.C.
SunZia Transmission, LLC
Trans Bay Cable LLC
Valley Electric Association, Inc.
Viridon Path 15, LLC
Western Area Power Administration
Docket No. EL26-71-000
MOTION TO RESCIND SHOW CAUSE ORDER
ON BEHALF OF THE WESTERN AREA POWER ADMINISTRATION
Pursuant to Rule 212 of the Commission’s Rules of Practice and Procedure,1 the Western
Area Power Administration (WAPA) hereby submit this motion to rescind the show cause order
1 18 C.F.R. § 385.212 (2026).
PDF page 2
- 2 -
issued by the Commission in the above-referenced proceeding on June 18, 2026,2 as directed to
WAPA in its capacity as a Participating Transmission Owner (“TO”) in the California
Independent System Operator Corporation (“CAISO”).
I.
WAPA BACKGROUND
WAPA is a power marketing administration of the U.S. Department of Energy. WAPA
was created in 1977 by section 302(a)(1)(E) and (F) of the Department of Energy Organization
Act. WAPA’s mission is to market and deliver reliable, renewable, cost-based federal
hydroelectric power, transmission, and related services within a 15-state region of the central and
western United States. WAPA was established to assume the marketing functions of power
generated by the various dams owned and operated by the U.S. Department of Interior, Bureau of
Reclamation (Reclamation), and the U.S. Army Corp of Engineers. WAPA is engaged in,
among other things, marketing, transmitting, and arranging for delivery of power to its customers
– which include Reclamation’s project-use loads and WAPA’s other electric service customers.
WAPA markets power to preference entities who are generally nonprofits including public utility
districts, municipalities, water and irrigation districts, federal and state agencies, rural electric
cooperatives, and Native American Tribes. WAPA also owns, operates, and maintains high
voltage transmission systems to facilitate delivery of its power to its customers, and sells excess
transmission capacity.
WAPA’s Sierra Nevada Region (WAPA-SN) sells power at wholesale to preference
customers in California from multiple hydroelectric powerplants of the Central Valley Project
(CVP) and market purchases, using the CVP transmission system. The great majority of WAPA-
SN’s system operates as a sub-balancing authority area under the Balancing Authority of
2 Cal. Indep. Sys. Operator Corp., 195 FERC ¶ 61,214 (2026) (the “Show Cause Order”).
PDF page 3
- 3 -
Northern California (BANC). However, one of WAPA-SN’s transmission lines is within the
operational control of the CAISO.
WAPA-SN became a Participating TO in the CAISO and signed the Transmission
Control Agreement (“TCA”) among and between the CAISO and its Participating TOs in
December 2004. WAPA only placed under the operational control of the CAISO its rights and
interests in the Path 15 Upgrade Project, a single, approximately 83-mile, 500-kilovolt
transmission line extending from the PG&E Los Banos Substation to the PG&E Gates
Substation. A federal entity, WAPA has reserved various rights and authorities necessary to
facilitate its participation as a TO for the Path 15 Upgrade project, including use of its own Tarif
or OATT for interconnections to the Path 15 Upgrade to the extent the CAISO provisions are
inconsistent.
II.
RELEVANT BACKGROUND
On June 18, 2026, the Commission issued the Show Cause Order, thereby initiating a
proceeding under Section 206 of the Federal Power Act. The Show Cause Order found that the
CAISO’s Open Access Transmission Tariff (“CAISO Tariff”) and/or the TO Tariffs of each of
the CAISO Participating TOs appear to be unjust, unreasonable, or unduly discriminatory or
preferential to the extent that they do not include provisions establishing the rates, terms, and
conditions for the interconnection of and service to certain large and co-located loads. The Show
Cause Order therefore directed the CAISO and the CAISO Participating TOs to either explain
how their respective tariffs remain just and reasonable without specific provisions for the
interconnection of large and co-located loads or to develop such provisions.3
3 Show Cause Order at P 3.
PDF page 4
- 4 -
III.
JUSTIFICATION FOR RESCISSION
WAPA is a non-public utility that is exempt from the Commission’s jurisdiction pursuant
to Section 201(f) of the Federal Power Act.4 The Commission acknowledged that the Show
Cause Order included Participating TOs that are not subject to the Commission’s jurisdiction and
explained that it would “rescind the show cause order” against such entities at their request,
provided that the CAISO “respond[s] to this order regarding the non-public utility’s CAISO
Tariff provisions on file with the Commission.”5 Accordingly, as a non-public utility, WAPA
requests that the Commission rescind the Show Cause Order against it.
WAPA has and will continue to coordinate and cooperate with the CAISO in responding
to the Show Cause Order, to the extent that the CAISO requests assistance from WAPA and
other non-public utilities. WAPA has conferred with the CAISO in advance of the filing of this
motion. In accordance with WAPA policy and practice, if in the course of WAPA’s continued
coordination with the CAISO that it determines changes to its Tariff are needed to address the
issues in the Show Cause Order, WAPA will file proposed revisions to its Tariff with the
Commission in due course.
4 16 U.S.C. 824(f) (2024) (”No provision in this subchapter shall apply to, or be deemed to include, the United
States”), cited in Show Cause Order at P 3, n.9.
5 Show Cause Order at P 3, n.9.
PDF page 5
- 5 -
IV.
CONCLUSION
WHEREFORE, for the foregoing reasons, WAPA respectfully requests that the
Commission rescind the Show Cause Order against WAPA as a non-public utility and ask that
the Commission waive any notice and comment periods that might be applicable to this motion.
Respectfully submitted,
/s/ J.Ben Summerhays
Attorney for Western Area Power Administration
Western Area Power Administration
12155 W. Alameda Parkway
Lakewood, CO 80228-8213
(720) 962-7023
summerhays@wapa.gov
August 3, 2026
PDF page 6
CERTIFICATE OF SERVICE
I hereby certify that I have on this 3rd day of August, 2026, caused a copy of the
foregoing document to be sent to all parties on the list compiled by the Secretary of the
Commission in this proceeding, by electronic mail or such other means as may have been
specified by such party, pursuant to Commission Rule 2010.
/s/ J. Ben Summerhays
Attorney for Western Area Power Administration