EL26-68-000 · 2026-08-07 · Missouri Public Service Commission
Comments of the Public Service Commission of the State of Missouri in support of Southwest Power Pool, Inc.'s et al. request for abeyance filed 08/03/2026
Back to sections and commentaryPDF page 1
1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
)
Southwest Power Pool, Inc.
)
Docket No. EL26-68-000
)
COMMENTS OF THE PUBLIC SERVICE COMMISSION OF THE STATE OF
MISSOURI IN SUPPORT OF THE JOINT MOVANTS’ REQUEST FOR ABEYANCE
Pursuant to Rule 20081 and the Notice Establishing Answer Period issued in this docket
on August 4, 2026, by the Federal Energy Regulatory Commission (Commission or FERC), the
Public Service Commission of the State of Missouri (Missouri PSC) hereby submits these
comments in support of the request for abeyance filed by the Southwest Power Pool, Inc. (SPP)
and various transmission owners (collectively, Joint Movants) on August 3, 2026.
I. Summary of Comments
The Commission should grant the Joint Movants’ request for a 95-day abeyance in order
to accommodate SPP’s stakeholder process. Although the Commission said it will disfavor a
request for an abeyance exceeding 90 days, SPP’s Board of Directors meeting is scheduled for
November 17, 2026—one day outside the 90-day window. The Joint Movants’ requested 95-day
abeyance will allow SPP to complete its stakeholder and approval process for its compliance
filing in this docket, including input from state regulators. The requested abeyance will allow
SPP’s stakeholder community adequate time to address important issues highlighted by the
Commission and represents only a de minimus extension beyond the Commission’s 90-day
timeline. Therefore, the Joint Movants demonstrated good cause for the requested abeyance and
it should be granted.
1 18 C.F.R. § 385.2008.
PDF page 2
2
II. Service and Communication
All pleadings, correspondence and other communications related to this proceeding
should be directed to:
Rodney Massman
John D. Borgmeyer
General Counsel
Asst. General Counsel-Regulation
Public Service Commission of the Public Service Commission of the
State of Missouri
State of Missouri
P.O. Box 360
P.O. Box 360
Jefferson City, MO 65102
Jefferson City, MO 65102
(573) 751-7510
(573) 751-7504
rodney.massman@psc.mo.gov
john.borgmeyer@psc.mo.gov
III. Background
The Missouri PSC is a “state commission” as defined in Section 1.101(k) of the
Commission’s Rules of General Applicability.2 Missouri law authorizes the Missouri PSC to
regulate rates, charges and terms of service for the sale and distribution of electricity by public
utilities to consumers in the state.3 The Missouri PSC is an active member of the SPP Regional
State Committee (RSC).
The Commission issued its Order Instituting Proceeding Under Section 206 of the
Federal Power Act (Show Cause Order) in this docket on June 18, 2026.4 The Commission
made a preliminary finding that SPP’s existing tariff appears to be unjust, unreasonable, or
unduly discriminatory or preferential in that it lacks certain provisions.5 The Commission
recognized and applauded the steps SPP and its stakeholders have already taken to address the
addition of large and co-located loads to the transmission system.6 The Commission also noted,
2 18 C.F.R. 1.101(k).
3 Section 386.250 Revised Statutes of Missouri (RSMo)(2016).
4 195 FERC ¶ 61,213 (June 18, 2026).
5 Show Cause Order at P. 3.
6 Id. at P. 2.PDF page 3
3
however, that SPP had not yet proposed tariff revisions to address all the challenges associated
with integrating these loads into its system.
In the Show Cause Order, the Commission said it will consider requests from SPP and/or
its transmission owners to hold this proceeding in abeyance for up to 90 days.7 The Commission
said it will not grant such abeyances reflexively, and it “will look with great disfavor” upon
requests for abeyance beyond the 90-day period.8 Successful requests must include a robust
description of a future compliance filing and a reasoned and specific explanation of when the
compliance filing will be made.9
On August 3, 2026, the Joint Movants filed a request for abeyance.10 The Joint Movants
asked to hold the proceedings in abeyance for 95 days, up to and including November 20, 2026.
The additional five days is necessary to accommodate SPP’s full stakeholder process,
culminating in a Board of Directors meeting scheduled for November 17, 2026.
IV. Comments of the Missouri PSC
The Joint Movants have demonstrated good cause for the requested 95-day abeyance.
Commission Rule 2008 provides that “the time by which any person is required… to act under
any… order may be extended by the decisional authority for good cause, upon a motion made
before the expiration of the period prescribed… .” On April 14, 2025, for example, the
Commission granted SPP a 12-month extension of time to submit filings in compliance with the
Commission’s Order No. 1920 to accommodate its comprehensive stakeholder process.11
Similar good cause exists to grant the much more limited 95-day abeyance requested here.
7 Id. at P. 33.
8 Id.
9 Id.
10 Docket No. EL26-68, Joint Movants’ Amended Motion To Hold Section 206 Proceeding in Abeyance, Accession
No. 20260803-5265 (August 3, 2026) (Joint Motion).
11 Docket RM21-17, Notice of Extension of Time, Accession No. 20250414-3017 (April 14, 2025).
PDF page 4
4
The issues identified by the Commission involve numerous interrelated aspects of SPP’s
tariff. Developing revisions that meet the Commission’s requirements will need careful technical
analysis and input from the various members and stakeholder groups affected by these changes.
The requested 95-day abeyance will allow the stakeholders to refine the proposals and present
them to the SPP Board for full consideration while maintaining the Commission’s expedited
timeline.
Issues related to transparency and the avoidance of cost shifting12 are particularly
important to the Missouri PSC and other state regulators who bear the responsibility of setting
retail rates that include FERC-jurisdictional transmission costs. The Missouri PSC is an active
participant in the RSC13 and the Cost Control and Allocation Review and Evaluation (CARE)
Team, both of which will play a role in analyzing and refining SPP’s compliance tariff revisions.
The CARE Team in particular will evaluate potential responses to the Commission’s concerns
regarding multiple potential approaches to cost mitigation and cost shifting.14 The requested
abeyance will allow the CARE Team time to complete this important work and present its
recommendations to the Board.
Along with these important benefits, the requested 95-day extension represents only a
minor extension of the Commission’s preferred 90-day extension timeline. As the Commission
noted in its Show Cause Order, SPP and its stakeholders have been national leaders in
developing new approaches to integrating large loads into the transmission system. Allowing
SPP and its stakeholders additional time to fully evaluate and approve the remaining work will
12 Show Cause Order at P. 3.
13 The RSC holds primary responsibility for cost allocation and the approach to resource adequacy across the entire
region. SPP Bylaws Section 7.2.
14 Joint Motion at pgs. 12-13.
PDF page 5
5
ultimately save administrative resources, promote durable solutions, and will not unduly delay
this proceeding.
V. Conclusion
The Missouri PSC respectfully submits these comments in support of the Joint Movants’
request for a 95-day abeyance of this Section 206 proceeding.
Respectfully submitted,
/s/ John D. Borgmeyer
John D. Borgmeyer
Asst. General Counsel-Regulation
Public Service Commission of the
State of Missouri
P.O. Box 360
Jefferson City, MO 65102-0360
573-751-7504 (telephone)
573-522-4016 (facsimile)
John.borgmeyer@psc.mo.gov
Certificate of Service
Pursuant to Rule 2010 of the Commission's Rules of Practice and Procedure, I hereby
certify that I have this day served a copy of the foregoing document on all persons designated on
the official service list compiled by the Secretary of the Commission in this proceeding by
electronic service dated on this 7th day of August, 2026.
/s/ John D. Borgmeyer
Jefferson City, Missouri