ER26-3650-000 · 2026-09-18 · Mississippi Public Service CommissionArkansas Public Service Commission
Protest of Mississippi Public Service Commission et al. re Midcontinent Independent System Operator, Inc.'s 08/28/2026 filing
Back to sections and commentaryPDF page 1
1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
Midcontinent Independent System Operator,
Inc.
)
)
Docket No. ER26-3650-000
PROTEST OF THE SOUTHERN REGULATORS
The Mississippi Public Service Commission and the Arkansas Public Service Commission
(together, the Southern Regulators) protest MISO’s1 August 28, 2026 filing to establish
interconnection reliability requirements for large loads.2 Southern Regulators support Entergy’s3
Limited Protest4 and request for relief and offer the following additional comments.5
First, the Filing provides only a general overview of interconnection requirements
applicable to large loads. It lacks the specific detail needed to actually interconnect to the grid.
Absent that detail, developers and the transmission owners are unable to design, purchase and
install the correct equipment to operate large loads (e.g., refineries, data centers). A general
description is not enough. And, in the absence of those requirements, developers and transmission
owners run the risk and expense of installing equipment, consistent with good utility practices,
only to then replace that equipment at great expense after MISO later publishes the actual
requirements. MISO’s approach is analogous to building a house based on a picture instead of
technical drawings.
Second, when it finally develops the requirements, MISO unreasonably proposes to place
them in Business Practice Manuals (BPMs). MISO can easily change BPMs with minimal or no
1 Midcontinent Independent System Operator, Inc. (MISO).
2 Midcontinent Independent System Operator, Inc., Interconnection Reliability Requirements for Large Loads,
Docket No. ER26-3650-000 (filed Aug. 28, 2026) (Filing).
3 Entergy includes Entergy Services, LLC. and its operating companies: Entergy Arkansas, LLC, Entergy Louisiana,
LLC, Entergy Mississippi, LLC, Entergy New Orleans, LLC, and Entergy Texas, Inc.
4 Limited Protest of Entergy Services, LLC, Docket No. ER26-3650-000 (filed Sept. 18, 2026) (Entergy Protest).
5 Southern Regulators file these comments pursuant to Rules 212 and 214 of the Federal Energy Regulatory
Commission’s (FERC or Commission) Rules of Practice and Procedure. 18 C.F.R. §§ 385.212 and 385.214 (2026).PDF page 2
2
input from market participants. Any recommendation market participants do provide regarding a
BPM is treated as a suggestion that MISO may ignore. Developers and transmission owners have
no recourse to challenge a BPM other than by filing a complaint at FERC. These requirements
will impose significant costs on developers and transmission owners; changing the requirements
will further increase those costs. As Entergy explained, the Rule of Reason mandates that these
requirements be placed in the Tariff where they are subject to FERC’s oversight to ensure they are
just and reasonable.6
Finally, the remedy Entergy seeks – that MISO make a compliance filing that clearly
identifies these requirements and places them in the tariff – is fully within FERC’s authority.
Conclusion
Consistent with Entergy’s Limited Protest, the Southern Regulators ask that FERC
condition acceptance of MISO’s Filing by requiring MISO to file the specific interconnection
requirements in the Tariff, not in the BPMs.
Barton Norfleet
Special Counsel; Federal Energy Affairs
Mississippi Public Service Commission
501 N. West Street, Suite 201-A
P.O. Box 1174
Jackson, MS 39215-1174
Phone: (601) 961-5821
barton.norfleet@psc.ms.gov
Respectfully submitted,
/s/ William D. Booth
William D. Booth
Orrie A. Walsvik
Michael Best & Friedrich LLP
1000 Maine Avenue, S.W.
Suite 400
Washington, D.C. 20024
Phone: (202) 747-9560
wdbooth@michaelbest.com
orrie.walsvik@michaelbest.com
Attorneys for the Mississippi Public
Service Commission
6 Entergy Protest at 3-17.
PDF page 3
3
/s/ Bridgette Frazier
Bridgette Frazier
Luke Kinder
Commission Counsel
Arkansas Public Service Commission
1000 Center Street
P.O. Box 400
Little Rock, AR 72201-4314
Telephone: (501) 682-5816
(501) 682-5766
bridgette.frazier@arkansas.gov
luke.kinder@arkansas.gov
Attorneys for the Arkansas Public Service
Commission
Dated September 18, 2026
PDF page 4
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon the parties designated
on the official service list for the above-captioned docket in accordance with the requirements of
Rule 2010 of the Commission’s Rules of Practice and Procedure.
Dated at Madison, Wisconsin on this 18th day of September, 2026.
Respectfully submitted,
/s/ Orrie Walsvik
Orrie Walsvik
Michael Best & Friedrich LLP
1 S. Pinckney Street
Suite 700
Madison, WI 53703
Phone: (608) 257-3055
Orrie.walsvik@michaelbest.com