PJM informational filing on the September 30, 2026 Members Committee vote on governance term sheets
Topics in the text: Registry access
What the document says
PDF p. 1
The Members term sheet won the two-thirds sector-weighted Members Committee vote.
The Members term sheet, sponsored by a group of PJM Members, received the requisite sector-weighted two-thirds majority vote of the PJM Members Committee PDF p. 1
PDF p. 1
Neither PJM's own term sheet nor the Consumer Advocates' reached even a majority.
Neither PJM’s nor the Consumer Advocates’ term sheet received the requisite two-thirds or even a majority vote. PDF p. 1
PDF p. 1
PJM says the states and governors do not find the approved term sheet satisfactory.
the Organization of PJM States, Inc., the PJM Governors’ Collaborative and other state representatives do not view the approved term sheet as satisfactory. PDF p. 1
Responses and related views
States object to members controlling access to FERC
OPSI and PJM Governors’ Collaborative governance negotiating team · Related public statement
Before the vote, the states’ negotiating team opposed the members’ term sheet. The team said the proposed supermajority requirement would let private members decide whether a state proposal received equal consideration at FERC. It preferred a direct route for states to be heard.
LaCerte points to gridlock in PJM’s stakeholder process
Commissioner David LaCerte · Related public statement
At WIRES on July 9, LaCerte said PJM’s stakeholder process too often protected individual business interests and prevented agreement. He was discussing governance months before the members voted, not evaluating their final term sheet.
Rosner links investment signals to state confidence
Commissioner David Rosner · Related public statement
At the July hearing Rosner told Senator McCormick that market rules can send investment signals, but those signals lose force if states do not trust how prices are set. He wanted states involved in regional planning.
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Registry access
The Members term sheet, sponsored by a group of PJM Members, received the requisite sector-weighted two-thirds majority vote of the PJM Members Committee, and advanced over a PJM term sheet and over a Consumer Advocates term sheet.