Attachment A- Marked Tariff 4919-3670-8807 v.1.pdf
Read topic-matched comments in ER26-3515
Topics in the text: Reliability and curtailment · Registry access · Connecting load and generation
Responses and related views
No section-specific public response is linked for this document.
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Attachment A
printed heading · Topic match: Reliability and curtailment
Attachment A Revisions to the PJM Open Access Transmission Tariff and Resource Adequacy Agreement (Marked/Redline Format)Read this passage Filed comments: Reliability and curtailment
Definitions – A - B
PDF bookmark · Topic match: Reliability and curtailment
Annual Revenue Rate: “Annual Revenue Rate” shall mean the rate employed to assess a compliance penalty charge on a Curtailment Service Provider under Tariff, Attachment DD, section 11.Read this passage Filed comments: Reliability and curtailment
Attachment H:
printed heading
Attachment H: “Attachment H” shall refer collectively to the Attachments to the PJM Tariff with the prefix “H” that set forth, among other things, the Annual Transmission Rates for Network Integration Transmission Service in the PJM Zones.Read this passage
Attachment K-Appendix, section 7.4.3.
printed heading
Avoidable Cost Rate: “Avoidable Cost Rate” shall mean a component of the Market Seller Offer Cap calculated in accordance with Tariff, Attachment DD, section 6.Read this passage
Definitions – E - F
PDF bookmark
Definitions – E - FRead this passage
Economic-based Enhancement or Expansion:
PDF bookmark
Economic-based Enhancement or Expansion:Read this passage
“Economic-based Enhancement or Expansion” shall have the same meaning provided in the Operating Agreement.
PDF bookmark
“Economic-based Enhancement or Expansion” shall have the same meaning provided in the Operating Agreement.Read this passage
Economic Load Response Participant:
PDF bookmark
Economic Load Response Participant: “Economic Load Response Participant” shall mean a Member or Special Member that qualifies under Operating Agreement, Schedule 1, section 1.5A, and the parallel provisions of Tariff,Read this passage
Attachment K-Appendix, section 1.5A, to participate in the PJM Interchange Energy Market
printed heading
Economic Load Response Regulation Only Participant: “Economic Load Response Regulation Only Participant” shall mean a Member or Special Member that qualifies under Operating Agreement, Schedule 1, section 1.5A, and the parallel provisions of Tariff, Attachment K-Appendix, section 1.5A, and is only…Read this passage
Eligible Customer:
PDF bookmark · Topic match: Reliability and curtailment
Eligible New Large Loads: “Eligible New Large Loads” shall mean a New Large Load eligible to provide Interim Resource Adequacy Service in accordance with Tariff, Attachment DD-4, section V.Read this passage Filed comments: Reliability and curtailment
Emergency Condition:
PDF bookmark · Topic match: Connecting load and generation
System restoration and black start shall be considered Emergency Conditions, provided that a Generation Interconnection Customer is not obligated by an Interconnection Service Agreement to possess black start capability.Read this passage Filed comments: Reliability and curtailment
Energy Market Opportunity Cost:
PDF bookmark
Energy Market Opportunity Cost: “Energy Market Opportunity Cost” shall mean the difference between (a) the forecasted cost to operate a specific generating unit when the unit only has an operational limitation due to limitations imposed on the unit by Applicable Laws and Regulations, and (b) the…Read this passage
Energy Resource:
PDF bookmark
Energy Resource: “Energy Resource” shall mean a Generating Facility that is not a Capacity Resource.Read this passage
Energy Settlement Area:
PDF bookmark
Energy Settlement Area: “Energy Settlement Area” shall mean the bus or distribution of busses that represents the physical location of Network Load and by which the obligations of the Network Customer to PJM are settled.Read this passage
Energy Storage Resource:
PDF bookmark
Energy Storage Resource: “Energy Storage Resource” shall mean a resource capable of receiving electric energy from the grid and storing it for later injection to the grid that participates in the PJM Energy, Capacity and/or Ancillary Services markets as a Market Participant.Read this passage
Energy Transmission Injection Rights:
PDF bookmark · Topic match: Retail and wholesale authority
Entity Providing Supply Services to Default Retail Service Provider: “Entity Providing Supply Services to Default Retail Service Provider” shall mean any entity, including but not limited to a load aggregator or power marketer, providing supply services to an electric distribution company when that…Read this passage Filed comments: Retail and wholesale authority
Environmental Laws:
PDF bookmark
Environmental Laws: “Environmental Laws” shall mean applicable Laws or Regulations relating to pollution or protection of the environment, natural resources or human health and safety.Read this passage
Equivalent Load:
PDF bookmark
Equivalent Load: “Equivalent Load” shall mean the sum of a Market Participant’s net system requirements to serve its customer load in the PJM Region, if any, plus its net bilateral transactions.Read this passage
Extended 30-minute Reserve Requirement:
PDF bookmark
Extended 30-minute Reserve Requirement:Read this passage
“Extended 30-minute Reserve Requirement” shall equal the 30-minute Reserve Requirement in a Reserve Zone or Reserve Sub-zone, plus 190 MW, plus any additional reserves scheduled under emergency conditions necessary to address operational uncertainty. The Extended 30-minute Reserve Requirement is calculated in accordance with the PJM Manuals.
PDF bookmark
“Extended 30-minute Reserve Requirement” shall equal the 30-minute Reserve Requirement in a Reserve Zone or Reserve Sub-zone, plus 190 MW, plus any additional reserves scheduled under emergency conditions necessary to address operational uncertainty.Read this passage
External Market Buyer:
PDF bookmark
External Market Buyer: “External Market Buyer” shall mean a Market Buyer making purchases of energy from the PJM Interchange Energy Market for consumption by end-users outside the PJM Region, or for load in the PJM Region that is not served by Network Transmission Service.Read this passage
External Resource:
PDF bookmark
External Resource: “External Resource” shall mean a generation resource located outside the metered boundaries of the PJM Region.Read this passage
Facilities Study:
PDF bookmark
As used in the Interconnection Service Agreement or Construction Service Agreement, Facilities Study shall mean that certain Facilities Study conducted by Transmission Provider (or at its direction) to determine the design and specification of the Customer Funded Upgrades necessary to accommodate…Read this passage
Fast-Start Resource:
PDF bookmark
Fast-Start Resource:Read this passage
“Fast-Start Resource” shall have the meaning set forth in Tariff, Attachment K-Appendix, section 2.2A
PDF bookmark
“Fast-Start Resource” shall have the meaning set forth in Tariff, Attachment K-Appendix, section 2.2ARead this passage
Federal Power Act:
PDF bookmark
Federal Power Act: “Federal Power Act” shall mean the Federal Power Act, as amended, 16 U.S.C. §§ 791a, et seq.Read this passage
FERC or Commission:
PDF bookmark
FERC or Commission: “FERC” or “Commission” shall mean the Federal Energy Regulatory Commission or any successor federal agency, commission or department exercising jurisdiction over the Tariff, Operating Agreement and Reliability Assurance Agreement.Read this passage
Final Offer:
PDF bookmark
Final Offer:Read this passage
“Final Offer” shall mean the offer on which a resource was dispatched by the Office of the Interconnection for a particular clock hour for the Operating Day.
PDF bookmark
“Final Offer” shall mean the offer on which a resource was dispatched by the Office of the Interconnection for a particular clock hour for the Operating Day.Read this passage
Financial Transmission Right:
PDF bookmark
Financial Transmission Right: “Financial Transmission Right” or “FTR” shall mean a right to receive Transmission Congestion Credits as specified in Operating Agreement, Schedule 1, section 5.2.2 and the parallel provisions of Tariff, Attachment K-Appendix, section 5.2.2.Read this passage
Financial Transmission Right Obligation:
PDF bookmark
Financial Transmission Right Obligation: “Financial Transmission Right Obligation” shall mean a right to receive Transmission Congestion Credits as specified in Operating Agreement, Schedule 1, section 5.2.2(b), and the parallel provisions of Tariff, Attachment K-Appendix, section 5.2.2(b).Read this passage
Financial Transmission Right Option:
PDF bookmark
Financial Transmission Right Option: “Financial Transmission Right Option” shall mean a right to receive Transmission Congestion Credits as specified in Operating Agreement, Schedule 1, section 5.2.2(c), and the parallel provisions of Tariff, Attachment K-Appendix, section 5.2.2(c).Read this passage
Firm Point-To-Point Transmission Service:
PDF bookmark
Firm Point-To-Point Transmission Service: “Firm Point-To-Point Transmission Service” shall mean Transmission Service under the Tariff, Part II, section 13 that is reserved and/or scheduled between specified Points of Receipt and Delivery pursuant to Tariff, Part II.Read this passage
Firm Transmission Feasibility Study:
PDF bookmark
Firm Transmission Feasibility Study:Read this passage
“Firm Transmission Feasibility Study” shall mean a study conducted by the Transmission Provider in accordance with Tariff, Part II, section 19.3 and Tariff, Part III, section 32.3.
PDF bookmark
“Firm Transmission Feasibility Study” shall mean a study conducted by the Transmission Provider in accordance with Tariff, Part II, section 19.3 and Tariff, Part III, section 32.3.Read this passage
Firm Transmission Withdrawal Rights:
PDF bookmark · Topic match: Credit and exit
FTR Credit Requirement: “FTR Credit Requirement” shall mean the amount of credit that a Participant must provide in order to support the FTR positions that it holds and/or for which it is bidding.Read this passage
Definitions – I – J - K
PDF bookmark
Definitions – I – J - KRead this passage
IDR Transfer Agreement:
PDF bookmark
IDR Transfer Agreement: “IDR Transfer Agreement” shall mean an agreement to transfer, subject to the terms of Tariff, Part VI, section 237, Incremental Deliverability Rights to a party for the purpose of eliminating or reducing the need for Local or Network Upgrades that would otherwise have been…Read this passage
Immediate-need Reliability Project:
PDF bookmark
Immediate-need Reliability Project:Read this passage
“Immediate-need Reliability Project” shall have the same meaning provided in the Operating Agreement.
PDF bookmark
“Immediate-need Reliability Project” shall have the same meaning provided in the Operating Agreement.Read this passage
Inadvertent Interchange:
PDF bookmark
Inadvertent Interchange: “Inadvertent Interchange” shall mean the difference between net actual energy flow and net scheduled energy flow into or out of the individual Control Areas operated by PJM.Read this passage
Incidental Expenses:
PDF bookmark
Incidental Expenses: “Incidental Expenses” shall mean those expenses incidental to the performance of construction pursuant to an Interconnection Construction Service Agreement, including, but not limited to, the expense of temporary construction power, telecommunications charges, Interconnected…Read this passage
Incremental Auction Revenue Rights:
PDF bookmark
Incremental Auction Revenue Rights: “Incremental Auction Revenue Rights” shall mean the additional Auction Revenue Rights, not previously feasible, created by the addition of Incremental Rights-Eligible Required Transmission Enhancements, Merchant Transmission Facilities, or of one or more…Read this passage
Incremental Available Transfer Capability Revenue Rights:
PDF bookmark
Incremental Available Transfer Capability Revenue Rights: “Incremental Available Transfer Capability Revenue Rights” shall mean the rights to revenues that are derived from incremental Available Transfer Capability created by the addition of Merchant Transmission Facilities or of one of more…Read this passage
Incremental Deliverability Rights (IDRs):
PDF bookmark
Incremental Deliverability Rights (IDRs): “Incremental Deliverability Rights” or “IDRs” shall mean the rights to the incremental ability, resulting from the addition of Merchant Transmission Facilities, to inject energy and capacity at a point on the Transmission System, such that the injection…Read this passage
Incremental Energy Offer:
PDF bookmark
Incremental Energy Offer: “Incremental Energy Offer” shall mean the cost in dollars per MWh of providing an additional MWh from a synchronized unit.Read this passage
Incremental Multi-Driver Project:
PDF bookmark
Incremental Multi-Driver Project:Read this passage
“Incremental Multi-Driver Project” shall have the same meaning provided in the Operating Agreement.
PDF bookmark
“Incremental Multi-Driver Project” shall have the same meaning provided in the Operating Agreement.Read this passage
Incremental Rights-Eligible Required Transmission Enhancements:
PDF bookmark
Incremental Rights-Eligible Required Transmission Enhancements: “Incremental Rights-Eligible Required Transmission Enhancements” shall mean Regional Facilities and Necessary Lower Voltage Facilities or Lower Voltage Facilities (as defined in Tariff, Schedule 12) and meet one of the following…Read this passage
Increment Offer:
PDF bookmark
Increment Offer: “Increment Offer” shall mean a type of Virtual Transaction that is an offer to sell energy at a specified location in the Day-ahead Energy Market.Read this passage
Initial Operation:
PDF bookmark · Topic match: Connecting load and generation
Initial Operation: “Initial Operation” shall mean the commencement of operation of the Customer Facility and Customer Interconnection Facilities after satisfaction of the conditions of Tariff, Attachment O- Appendix 2, section 1.4 (an Interconnection Service Agreement).Read this passage
“Integer Relaxation” shall mean the process by which the commitment status variable for an Eligible Fast-Start Resource is allowed to vary between zero and one, inclusive of zero and one, as further described in Tariff, Attachment K-Appendix, section 2.2.
PDF bookmark
“Integer Relaxation” shall mean the process by which the commitment status variable for an Eligible Fast-Start Resource is allowed to vary between zero and one, inclusive of zero and one, as further described in Tariff, Attachment K-Appendix, section 2.2.Read this passage
Interconnected Entity:
PDF bookmark
Interconnected Entity: “Interconnected Entity” shall mean either the Interconnection Customer or the Interconnected Transmission Owner; Interconnected Entities shall mean both of them.Read this passage
Interconnected Transmission Owner:
PDF bookmark
Interconnected Transmission Owner: “Interconnected Transmission Owner” shall mean the Transmission Owner to whose transmission facilities or distribution facilities Customer Interconnection Facilities are, or as the case may be, a Customer Facility is, being directly connected.Read this passage
Interconnection Construction Service Agreement:
PDF bookmark
Interconnection Construction Service Agreement: “Interconnection Construction Service Agreement” shall mean the agreement entered into by an Interconnection Customer, Interconnected Transmission Owner and the Transmission Provider pursuant to Tariff, Part VI, Subpart B and in the form set forth in…Read this passage
Interconnection Customer:
PDF bookmark
Interconnection Customer: “Interconnection Customer” shall mean a Generation Interconnection Customer and/or a Transmission Interconnection Customer.Read this passage
Interconnection Facilities:
PDF bookmark
Interconnection Facilities: “Interconnection Facilities” shall mean the Transmission Owner Interconnection Facilities and the Customer Interconnection Facilities.Read this passage
Interconnection Feasibility Study:
PDF bookmark
Interconnection Feasibility Study: “Interconnection Feasibility Study” shall mean either a Generation Interconnection Feasibility Study or Transmission Interconnection Feasibility Study.Read this passage
Interconnection Party:
PDF bookmark
Interconnection Party: “Interconnection Party” shall mean a Transmission Provider, Interconnection Customer, or the Interconnected Transmission Owner.Read this passage
Interconnection Request:
PDF bookmark
Interconnection Request: “Interconnection Request” shall mean a Generation Interconnection Request, a Transmission Interconnection Request and/or an IDR Transfer Agreement.Read this passage
Interconnection Service:
PDF bookmark · Topic match: Connecting load and generation
Interconnection Service: “Interconnection Service” shall mean the physical and electrical interconnection of the Customer Facility with the Transmission System pursuant to the terms of Tariff, Part IV and Tariff, Part VI and the Interconnection Service Agreement entered into pursuant thereto by…Read this passage
Interconnection Service Agreement:
PDF bookmark · Topic match: Connecting load and generation
Interconnection Service Agreement: “Interconnection Service Agreement” shall mean an agreement among the Transmission Provider, an Interconnection Customer and an Interconnected Transmission Owner regarding interconnection under Tariff, Part IV and Tariff, Part VI.Read this passage
Interconnection Studies:
PDF bookmark
Interconnection Studies: “Interconnection Studies” shall mean the Interconnection Feasibility Study, the System Impact Study, and the Facilities Study described in Tariff, Part IV and Tariff, Part VI.Read this passage
Interface Pricing Point:
PDF bookmark · Topic match: Reliability and curtailment
Interim Resource Adequacy Service: “Interim Resource Adequacy Service” shall mean a load reduction service through which New Large Loads reduce load as directed by the applicable Electric Distributor in response to an Interim Resource Adequacy Service Action requested by the Office of the…Read this passage Filed comments: Reliability and curtailment
Internal Market Buyer:
PDF bookmark
Internal Market Buyer: “Internal Market Buyer” shall mean a Market Buyer making purchases of energy from the PJM Interchange Energy Market for ultimate consumption by end-users inside the PJM Region that are served by Network Transmission Service.Read this passage
Interruption:
PDF bookmark
Interruption: “Interruption” shall mean a reduction in non-firm transmission service due to economic reasons pursuant to Tariff, Part II, section 14.7.Read this passage
Definitions – L – M – N
PDF bookmark
Definitions – L – M – N Large Load: “Large Load” shall have the meaning provided in the Reliability Assurance Agreement.Read this passage
List of Approved Contractors:
PDF bookmark
List of Approved Contractors: “List of Approved Contractors” shall mean a list developed by each Transmission Owner and published in a PJM Manual of (a) contractors that the Transmission Owner considers to be qualified to install or construct new facilities and/or upgrades or modifications to…Read this passage
Load Interest:
PDF bookmark
Load Interest:Read this passage
“Load Interest” shall mean, for the purposes of the minimum offer price rule, responsibility for serving load within the PJM Region, whether by the Capacity Market Seller, an affiliate of the Capacity Market Seller, or by an entity with which the Capacity Market Seller is in contractual privity with respect to the subject Generation Capacity Resource.
PDF bookmark
“Load Interest” shall mean, for the purposes of the minimum offer price rule, responsibility for serving load within the PJM Region, whether by the Capacity Market Seller, an affiliate of the Capacity Market Seller, or by an entity with which the Capacity Market Seller is in contractual privity…Read this passage
Load Management:
PDF bookmark
Load Management: “Load Management” shall mean a Demand Resource (“DR”) as defined in the Reliability Assurance Agreement.Read this passage
Load Ratio Share:
PDF bookmark
Load Ratio Share: “Load Ratio Share” shall mean the ratio of a Transmission Customer’s Network Load to the Transmission Provider’s total load.Read this passage
Load Reduction Event:
PDF bookmark
Load Reduction Event: “Load Reduction Event” shall mean a reduction in demand by a Member or Special Member for the purpose of participating in the PJM Interchange Energy Market.Read this passage
“Load Serving Charging Energy” shall mean energy that is purchased from the PJM Interchange Energy Market and stored in an Energy Storage Resource or Open-Loop Hybrid Resource for later resale to end-use load.
PDF bookmark
“Load Serving Charging Energy” shall mean energy that is purchased from the PJM Interchange Energy Market and stored in an Energy Storage Resource or Open-Loop Hybrid Resource for later resale to end-use load.Read this passage
Load Shedding:
PDF bookmark
Load Shedding: “Load Shedding” shall mean the systematic reduction of system demand by temporarily decreasing load in response to transmission system or area capacity shortages, system instability, or voltage control considerations under Tariff, Part II or Part III.Read this passage
Local Upgrades:
PDF bookmark
Local Upgrades: “Local Upgrades” shall mean modifications or additions of facilities to abate any local thermal loading, voltage, short circuit, stability or similar engineering problem caused by the interconnection and delivery of generation to the Transmission System.Read this passage
“Long-lead Project” shall have the same meaning provided in the Operating Agreement.
PDF bookmark
“Long-lead Project” shall have the same meaning provided in the Operating Agreement.Read this passage
Long-Term Firm Point-To-Point Transmission Service:
PDF bookmark
Long-Term Firm Point-To-Point Transmission Service: “Long-Term Firm Point-To-Point Transmission Service” shall mean firm Point-To-Point Transmission Service under Tariff, Part II with a term of one year or more.Read this passage
Loss Price:
PDF bookmark
Loss Price: “Loss Price” shall mean the loss component of the Locational Marginal Price, which is the effect on transmission loss costs (whether positive or negative) associated with increasing the output of a generation resource or decreasing the consumption by a Demand Resource based on the…Read this passage
Attachment K-Appendix, section 2.
printed heading
M2M Flowgate: “M2M Flowgate” shall have the meaning provided in the Joint Operating Agreement between the Midcontinent Independent Transmission System Operator, Inc. and PJM Interconnection, L.L.C.Read this passage
Market Monitoring Unit Advisory Committee or MMU Advisory Committee:
PDF bookmark
Market Monitoring Unit Advisory Committee or MMU Advisory Committee: “Market Monitoring Unit Advisory Committee” or “MMU Advisory Committee” shall mean the committee established under Tariff, Attachment M, section III.H.Read this passage
Market Operations Center:
PDF bookmark
Market Operations Center: “Market Operations Center” shall mean the equipment, facilities and personnel used by or on behalf of a Market Participant to communicate and coordinate with the Office of the Interconnection in connection with transactions in the PJM Interchange Energy Market or the…Read this passage
Market Participant Energy Injection:
PDF bookmark
Market Participant Energy Injection: “Market Participant Energy Injection” shall mean transactions in the Day-ahead Energy Market and Real-time Energy Market, including but not limited to Day-ahead generation schedules, real- time generation output, Increment Offers, internal bilateral transactions…Read this passage
Market Participant Energy Withdrawal:
PDF bookmark
Market Participant Energy Withdrawal:Read this passage
“Market Participant Energy Withdrawal” shall mean transactions in the Day-ahead Energy Market and Real-time Energy Market, including but not limited to Demand Bids, Decrement Bids, real-time load (net of Behind The Meter Generation expected to be operating, but not to be less than zero), internal bilateral transactions and Export Transactions, as further described in the PJM Manuals.
PDF bookmark
“Market Participant Energy Withdrawal” shall mean transactions in the Day-ahead Energy Market and Real-time Energy Market, including but not limited to Demand Bids, Decrement Bids, real-time load (net of Behind The Meter Generation expected to be operating, but not to be less than zero), internal…Read this passage
Material Modification:
PDF bookmark · Topic match: Connecting load and generation
Material Modification: “Material Modification” shall mean any modification to an Interconnection Request that has a material adverse effect on the cost or timing of Interconnection Studies related to, or any Network Upgrades or Local Upgrades needed to accommodate, any Interconnection Request with…Read this passage
Maximum Emergency:
PDF bookmark
Maximum Emergency: “Maximum Emergency” shall mean the designation of all or part of the output of a generating unit for which the designated output levels may require extraordinary procedures and therefore are available to the Office of the Interconnection only when the Office of the…Read this passage
Maximum Facility Output:
PDF bookmark · Topic match: Connecting load and generation
Maximum Facility Output: “Maximum Facility Output” shall mean the maximum (not nominal) net electrical power output in megawatts, specified in the Interconnection Service Agreement, after supply of any parasitic or host facility loads, that a Generation Interconnection Customer’s Customer Facility…Read this passage
Maximum Generation Emergency:
PDF bookmark
Maximum Generation Emergency: “Maximum Generation Emergency” shall mean an Emergency declared by the Office of the Interconnection to address either a generation or transmission emergency in which the Office of the Interconnection anticipates requesting one or more Generation Capacity Resources, or…Read this passage
Maximum Generation Emergency Alert:
PDF bookmark
Maximum Generation Emergency Alert:Read this passage
“Maximum Generation Emergency Alert” shall mean an alert issued by the Office of the Interconnection to notify PJM Members, Transmission Owners, resource owners and operators, customers, and regulators that a Maximum Generation Emergency may be declared, for any Operating Day in either, as applicable, the Day-ahead Energy Market or the Real-time Energy Market, for all or any part of such Operating Day.
PDF bookmark
“Maximum Generation Emergency Alert” shall mean an alert issued by the Office of the Interconnection to notify PJM Members, Transmission Owners, resource owners and operators, customers, and regulators that a Maximum Generation Emergency may be declared, for any Operating Day in either, as…Read this passage
Maximum Run Time:
PDF bookmark
Maximum Run Time:Read this passage
“Maximum Run Time” shall mean the maximum number of hours a generating unit can run over the course of an Operating Day, as measured by PJM’s State Estimator.
PDF bookmark
“Maximum Run Time” shall mean the maximum number of hours a generating unit can run over the course of an Operating Day, as measured by PJM’s State Estimator.Read this passage
“Maximum State of Charge” shall mean the maximum State of Charge that should not be exceeded, measured in units of megawatt-hours.
PDF bookmark
“Maximum State of Charge” shall mean the maximum State of Charge that should not be exceeded, measured in units of megawatt-hours.Read this passage
Maximum Weekly Starts:
PDF bookmark
Maximum Weekly Starts:Read this passage
“Maximum Weekly Starts” shall mean the maximum number of times that a generating unit can be started in one week, defined as the 168 hour period starting Monday 0001 hour, under normal operating conditions.
PDF bookmark
“Maximum Weekly Starts” shall mean the maximum number of times that a generating unit can be started in one week, defined as the 168 hour period starting Monday 0001 hour, under normal operating conditions.Read this passage
Merchant A.C. Transmission Facilities:
PDF bookmark
Transmission Facility” shall mean Merchant Transmission Facilities that are alternating current (A.C.) transmission facilities, other than those that are Controllable A.C.Read this passage
Merchant D.C. Transmission Facilities:
PDF bookmark
Transmission Facilities” shall mean direct current (D.C.) transmission facilities that are interconnected with the Transmission System pursuant to Tariff, Part IV and Part VI.Read this passage
Merchant Network Upgrades:
PDF bookmark
Merchant Network Upgrades: “Merchant Network Upgrades” shall mean additions to, or modifications or replacements of, physical facilities of the Interconnected Transmission Owner that, on the date of the pertinent Transmission Interconnection Customer’s Upgrade Request, are part of the Transmission…Read this passage
Merchant Transmission Facilities:
PDF bookmark
Merchant Transmission Facilities: “Merchant Transmission Facilities” shall mean A.C. or D.C. transmission facilities that are interconnected with or added to the Transmission System pursuant to Tariff, Part IV and Part VI and that are so identified in Tariff, Attachment T, provided, however, that…Read this passage
Merchant Transmission Provider:
PDF bookmark
Merchant Transmission Provider: “Merchant Transmission Provider” shall mean an Interconnection Customer that (1) owns, controls, or controls the rights to use the transmission capability of, Merchant D.C.Read this passage
Metering Equipment:
PDF bookmark · Topic match: Connecting load and generation
Metering Equipment: “Metering Equipment” shall mean all metering equipment installed at the metering points designated in the appropriate appendix to an Interconnection Service Agreement.Read this passage
Minimum Generation Emergency:
PDF bookmark · Topic match: Credit and exit
Minimum Participation Requirements: “Minimum Participation Requirements” shall mean a set of minimum training, risk management, communication and capital or collateral requirements required for Participants in the PJM Markets, as set forth herein and in the Form of Annual Certification set forth as…Read this passage
“Multi-Driver Project” shall have the same meaning provided in the Operating Agreement.
PDF bookmark
“Multi-Driver Project” shall have the same meaning provided in the Operating Agreement.Read this passage
Native Load Customers:
PDF bookmark
Native Load Customers: “Native Load Customers” shall mean the wholesale and retail power customers of a Transmission Owner on whose behalf the Transmission Owner, by statute, franchise, regulatory requirement, or contract, has undertaken an obligation to construct and operate the Transmission…Read this passage
Near-Term Transmission Service:
PDF bookmark
Near-Term Transmission Service: “Near-Term Transmission Service” shall mean Transmission Service which ends not more than 10 days after the Transmission Service request date.Read this passage
NERC:
PDF bookmark
NERC: “NERC” shall mean the North American Electric Reliability Corporation or any successor thereto.Read this passage
NERC Interchange Distribution Calculator:
PDF bookmark
NERC Interchange Distribution Calculator: “NERC Interchange Distribution Calculator” shall mean the NERC mechanism that is in effect and being used to calculate the distribution of energy, over specific transmission interfaces, from energy transactions.Read this passage
“Net Benefits Test” shall mean a calculation to determine whether the benefits of a reduction in price resulting from the dispatch of Economic Load Response exceeds the cost to other loads resulting from the billing unit effects of the load reduction, as specified in Operating Agreement, Schedule 1, section 3.3A.4 and the parallel provisions of Tariff, Attachment K-Appendix, section 3.3A.4.
PDF bookmark
“Net Benefits Test” shall mean a calculation to determine whether the benefits of a reduction in price resulting from the dispatch of Economic Load Response exceeds the cost to other loads resulting from the billing unit effects of the load reduction, as specified in Operating Agreement, Schedule…Read this passage
Network Customer:
PDF bookmark
Network Customer: “Network Customer” shall mean an entity receiving transmission service pursuant to the terms of the Transmission Provider’s Network Integration Transmission Service under Tariff, Part III.Read this passage
Network Integration Transmission Service:
PDF bookmark
Network Integration Transmission Service: “Network Integration Transmission Service” shall mean the transmission service provided under Tariff, Part III.Read this passage
Network Load:
PDF bookmark
Network Load: “Network Load” shall mean the load that a Network Customer designates for Network Integration Transmission Service under Tariff, Part III.Read this passage
Network Operating Agreement:
PDF bookmark
Network Operating Agreement: “Network Operating Agreement” shall mean an executed agreement that contains the terms and conditions under which the Network Customer shall operate its facilities and the technical and operational matters associated with the implementation of Network Integration…Read this passage
Network Operating Committee:
PDF bookmark
Network Operating Committee: “Network Operating Committee” shall mean a group made up of representatives from the Network Customer(s) and the Transmission Provider established to coordinate operating criteria and other technical considerations required for implementation of Network Integration…Read this passage
Network Resource:
PDF bookmark
Network Resource: “Network Resource” shall mean any designated generating resource owned, purchased, or leased by a Network Customer under the Network Integration Transmission Service Tariff.Read this passage
Network Service User:
PDF bookmark
Network Service User: “Network Service User” shall mean an entity using Network Transmission Service.Read this passage
Network Transmission Service:
PDF bookmark
Network Transmission Service: “Network Transmission Service” shall mean transmission service provided pursuant to the rates, terms and conditions set forth in Tariff, Part III, or transmission service comparable to such service that is provided to a Load Serving Entity that is also a Transmission…Read this passage
Network Upgrades:
PDF bookmark
Network Upgrades: “Network Upgrades” shall mean modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System.Read this passage
New Large Load:
PDF bookmark
New Large Load:Read this passage
“New Large Load” shall mean end-use customer load that is either (a) a Large Load that goes into service after June 1, 2027, or (b) incremental load in-service after June 1, 2027, that increases the existing end-use customer load at a single electrical site that, prior to such incremental load, did not previously meet the definition of Large Load. However, to the extent three consecutive Delivery Years meet the requirements of Tariff, Attachment DD-4, section IV(b)(iii), then New Large Load shall mean end-use customer load that is either (a) a Large Load that goes into service after June 1 of the first Delivery Year for which the requirements of Tariff, Attachment DD-4, section IV(b)(iii) are not met or (b) incremental load in-service after June 1 of the first Delivery Year for which the requirements of Tariff, Attachment DD-4, section IV(b)(iii) are not met that increases the existing end-use customer load at a single electrical site that, prior to such incremental load, did not previously meet the definition of Large Load.
PDF bookmark
“New Large Load” shall mean end-use customer load that is either (a) a Large Load that goes into service after June 1, 2027, or (b) incremental load in-service after June 1, 2027, that increases the existing end-use customer load at a single electrical site that, prior to such incremental load, did…Read this passage
New PJM Zone(s):
PDF bookmark
New PJM Zone(s): “New PJM Zone(s)” shall mean the Zone included in the Tariff, along with applicable Schedules and Attachments, for Commonwealth Edison Company, The Dayton Power and Light Company and the AEP East Operating Companies (Appalachian Power Company, Columbus Southern Power Company,…Read this passage
New Service Customers:
PDF bookmark
New Service Customers: “New Service Customers” shall mean all customers that submit an Interconnection Request, a Completed Application, or an Upgrade Request that is pending in the New Services Queue.Read this passage
New Service Request:
PDF bookmark
New Service Request: “New Service Request” shall mean an Interconnection Request, a Completed Application, or an Upgrade Request.Read this passage
New Services Queue:
PDF bookmark
New Services Queue: “New Services Queue” shall mean all Interconnection Requests, Completed Applications, and Upgrade Requests that are received within each six-month period ending on March 31 and September 30 of each year shall collectively comprise a New Services Queue.Read this passage
No-load Cost:
PDF bookmark
No-load Cost: “No-load Cost” shall mean the hourly cost required to theoretically operate a synchronized unit at zero MW.Read this passage
Nominal Rated Capability:
PDF bookmark · Topic match: Reliability and curtailment
Non-Curtailment Charge: “Non-Curtailment Charge” shall mean the charge applicable to Demand Resources and Price Responsive Demand as defined in Tariff, Attachment DD, section 10B(b).Read this passage Filed comments: Reliability and curtailment
Non-Firm Point-To-Point Transmission Service:
PDF bookmark · Topic match: Reliability and curtailment
Non-Firm Point-To-Point Transmission Service: “Non-Firm Point-To-Point Transmission Service” shall mean Point-To-Point Transmission Service under the Tariff that is reserved and scheduled on an as-available basis and is subject to Curtailment or Interruption as set forth in Tariff, Part II, section…Read this passage Filed comments: Reliability and curtailment
Non-Firm Sale:
PDF bookmark
Non-Firm Sale: “Non-Firm Sale” shall mean an energy sale for which receipt or delivery may be interrupted for any reason or no reason, without liability on the part of either the buyer or seller.Read this passage
Non-Firm Transmission Withdrawal Rights:
PDF bookmark
Non-Firm Transmission Withdrawal Rights: “No-Firm Transmission Withdrawal Rights” shall mean the rights to schedule energy withdrawals from a specified point on the Transmission System.Read this passage
Non-Retail Behind The Meter Generation:
PDF bookmark
Non-Retail Behind The Meter Generation: “Non-Retail Behind The Meter Generation” shall mean Behind the Meter Generation that is used by municipal electric systems, electric cooperatives, or electric distribution companies to serve load.Read this passage
Non-Synchronized Reserve:
PDF bookmark
Non-Synchronized Reserve:Read this passage
“Non-Synchronized Reserve” shall mean the reserve capability of non-emergency generation resources that can be converted fully into energy within ten minutes of a request from the Office of the Interconnection dispatcher, and is provided by equipment that is not electrically synchronized to the Transmission System.
PDF bookmark
“Non-Synchronized Reserve” shall mean the reserve capability of non-emergency generation resources that can be converted fully into energy within ten minutes of a request from the Office of the Interconnection dispatcher, and is provided by equipment that is not electrically synchronized to the…Read this passage
Non-Synchronized Reserve Event:
PDF bookmark
Non-Synchronized Reserve Event:Read this passage
“Non-Synchronized Reserve Event” shall mean a request from the Office of the Interconnection to generation resources able and assigned to provide Non-Synchronized Reserve in one or more specified Reserve Zones or Reserve Sub-zones, within ten minutes to increase the energy output by the amount of assigned Non-Synchronized Reserve capability.
PDF bookmark
“Non-Synchronized Reserve Event” shall mean a request from the Office of the Interconnection to generation resources able and assigned to provide Non-Synchronized Reserve in one or more specified Reserve Zones or Reserve Sub-zones, within ten minutes to increase the energy output by the amount of…Read this passage
“Non-Variable Loads” shall have the meaning specified in Operating Agreement, Schedule 1, section 1.5A.6, and the parallel provisions of Tariff, Attachment K-Appendix, section 1.5A.6.
PDF bookmark
“Non-Variable Loads” shall have the meaning specified in Operating Agreement, Schedule 1, section 1.5A.6, and the parallel provisions of Tariff, Attachment K-Appendix, section 1.5A.6.Read this passage
Non-Zone Network Load:
PDF bookmark
Non-Zone Network Load: “Non-Zone Network Load shall mean Network Load that is located outside of the PJM Region.Read this passage
Normal Maximum Generation:
PDF bookmark
Normal Maximum Generation: “Normal Maximum Generation” shall mean the highest output level of a generating resource under normal operating conditions.Read this passage
Normal Minimum Generation:
PDF bookmark
Normal Minimum Generation: “Normal Minimum Generation” shall mean the lowest output level of a generating resource under normal operating conditions.Read this passage
Definitions – T – U - V
PDF bookmark
Definitions – T – U - V Tangible Net Worth: “Tangible Net Worth” shall mean total assets less goodwill and other intangible assets, minus total liabilities.Read this passage
Target Allocation:
PDF bookmark
Target Allocation: “Target Allocation” shall mean the allocation of Transmission Congestion Credits as set forth in Operating Agreement, Schedule 1, section 5.2.3, and the parallel provisions of Tariff,Read this passage
Attachment K-Appendix, section 5.2.3, or the allocation of Auction Revenue Rights Credits as
printed heading
Attachment K-Appendix, section 5.2.3, or the allocation of Auction Revenue Rights Credits as set forth in Operating Agreement, Schedule 1, section 7.4.3, and the parallel provisions of Tariff,Read this passage
Attachment K-Appendix, section 7.4.3.
printed heading
Third Incremental Auction: “Third Incremental Auction” shall mean an Incremental Auction conducted three months before the Delivery Year to which it relates.Read this passage
Third-Party Sale:
PDF bookmark
Third-Party Sale: “Third-Party Sale” shall mean any sale for resale in interstate commerce to a Power Purchaser that is not designated as part of Network Load under the Network Integration Transmission Service but not including a sale of energy through the PJM Interchange Energy Market established…Read this passage
Transmission Congestion Charge:
PDF bookmark
Transmission Congestion Charge: “Transmission Congestion Charge” shall mean a charge attributable to the increased cost of energy delivered at a given load bus when the transmission system serving that load bus is operating under constrained conditions, or as necessary to provide energy for…Read this passage
Transmission Congestion Credit:
PDF bookmark
Transmission Congestion Credit: “Transmission Congestion Credit” shall mean the allocated share of total Transmission Congestion Charges credited to each FTR Holder, calculated and allocated as specified in Operating Agreement, Schedule 1, section 5.2, and the parallel provisions of Tariff,…Read this passage
Transmission Customer:
PDF bookmark
Transmission Customer: “Transmission Customer” shall mean any Eligible Customer (or its Designated Agent) that (i) executes a Service Agreement, or (ii) requests in writing that the Transmission Provider file with the Commission a proposed unexecuted Service Agreement, to receive transmission…Read this passage
Transmission Facilities:
PDF bookmark
Transmission Facilities: “Transmission Facilities” shall have the meaning set forth in the Operating Agreement.Read this passage
Transmission Forced Outage:
PDF bookmark
Transmission Forced Outage: “Transmission Forced Outage” shall mean an immediate removal from service of a transmission facility by reason of an Emergency or threatened Emergency, unanticipated failure, or other cause beyond the control of the owner or operator of the transmission facility, as…Read this passage
Transmission Injection Rights:
PDF bookmark
Transmission Injection Rights: “Transmission Injection Rights” shall mean Capacity Transmission Injection Rights and Energy Transmission Injection Rights.Read this passage
Transmission Interconnection Customer:
PDF bookmark
Transmission Interconnection Customer: “Transmission Interconnection Customer” shall mean an entity that submits an Interconnection Request to interconnect or add Merchant Transmission Facilities to the Transmission System or to increase the capacity of Merchant Transmission Facilities…Read this passage
Transmission Interconnection Facilities Study:
PDF bookmark
Transmission Interconnection Facilities Study: “Transmission Interconnection Facilities Study” shall mean a Facilities Study related to a Transmission Interconnection Request.Read this passage
Transmission Interconnection Feasibility Study:
PDF bookmark
Transmission Interconnection Feasibility Study: “Transmission Interconnection Feasibility Study” shall mean a study conducted by the Transmission Provider in accordance with Tariff, Part IV, section 36.2.Read this passage
Transmission Interconnection Request:
PDF bookmark
Transmission Interconnection Request: “Transmission Interconnection Request” shall mean a request by a Transmission Interconnection Customer pursuant to Tariff, Part IV to interconnect or add Merchant Transmission Facilities to the Transmission System or to increase the capacity of existing…Read this passage
Transmission Loading Relief:
PDF bookmark
Transmission Loading Relief: “Transmission Loading Relief” shall mean NERC’s procedures for preventing operating security limit violations, as implemented by PJM as the security coordinator responsible for maintaining transmission security for the PJM Region.Read this passage
Transmission Loss Charge:
PDF bookmark
Transmission Loss Charge: “Transmission Loss Charge” shall mean the charges to each Market Participant, Network Customer, or Transmission Customer for the cost of energy lost in the transmission of electricity from a generation resource to load as specified in Operating Agreement, Schedule 1,…Read this passage
Transmission Owner:
PDF bookmark
Transmission Owner: “Transmission Owner” shall mean a Member that owns or leases with rights equivalent to ownership Transmission Facilities and is a signatory to the PJM Transmission Owners Agreement.Read this passage
Transmission Owner Attachment Facilities:
PDF bookmark
Transmission Owner Attachment Facilities: “Transmission Owner Attachment Facilities” shall mean that portion of the Transmission Owner Interconnection Facilities comprised of all Attachment Facilities on the Interconnected Transmission Owner’s side of the Point of Interconnection.Read this passage
Transmission Owner Interconnection Facilities:
PDF bookmark · Topic match: Connecting load and generation
Transmission Owner Interconnection Facilities: “Transmission Owner Interconnection Facilities” shall mean all Interconnection Facilities that are not Customer Interconnection Facilities and that, after the transfer under Tariff, Attachment P, Appendix 2, section 5.5 to the Interconnected…Read this passage
Transmission Owner Upgrade:
PDF bookmark
Transmission Owner Upgrade:Read this passage
“Transmission Owner Upgrade” shall have the same meaning provided in the Operating Agreement.
PDF bookmark
“Transmission Owner Upgrade” shall have the same meaning provided in the Operating Agreement.Read this passage
Transmission Planned Outage:
PDF bookmark
Transmission Planned Outage: “Transmission Planned Outage” shall mean any transmission outage scheduled in advance for a pre-determined duration and which meets the notification requirements for such outages specified in Operating Agreement, Schedule 1, and the parallel provisions of Tariff,…Read this passage
Transmission Provider:
PDF bookmark
Transmission Provider: The “Transmission Provider” shall be the Office of the Interconnection for all purposes, provided that the Transmission Owners will have the responsibility for the following specified activities: (a) The Office of the Interconnection shall direct the operation and coordinate…Read this passage
Transmission Provider’s Monthly Transmission System Peak:
PDF bookmark
Transmission Provider’s Monthly Transmission System Peak: “Transmission Provider’s Monthly Transmission System Peak” shall mean the maximum firm usage of the Transmission Provider’s Transmission System in a calendar month.Read this passage
Transmission Service:
PDF bookmark
Transmission Service: “Transmission Service” shall mean Point-To-Point Transmission Service provided under Tariff, Part II on a firm and non-firm basis.Read this passage
Transmission Service Request:
PDF bookmark
Transmission Service Request: “Transmission Service Request” shall mean a request for Firm Point-To-Point Transmission Service or a request for Network Integration Transmission Service.Read this passage
Transmission System:
PDF bookmark
Transmission System: “Transmission System” shall mean the facilities controlled or operated by the Transmission Provider within the PJM Region that are used to provide transmission service under Tariff, Part II and Part III.Read this passage
Transmission Withdrawal Rights:
PDF bookmark · Topic match: Credit and exit
Unsecured Credit: “Unsecured Credit” shall mean any credit granted by PJMSettlement to a Participant that is not secured by Collateral.Read this passage
Upgrade Construction Service Agreement:
PDF bookmark
Upgrade Construction Service Agreement: “Upgrade Construction Service Agreement” shall mean that agreement entered into by an Eligible Customer, Upgrade Customer or Interconnection Customer proposing Merchant Network Upgrades, a Transmission Owner, and the Transmission Provider, pursuant to Tariff,…Read this passage
Upgrade Customer:
PDF bookmark
Upgrade Customer: “Upgrade Customer” shall mean a customer that submits an Upgrade Request pursuant to Operating Agreement, Schedule 1, section 7.8, and the parallel provisions of Tariff, Attachment K-Appendix, section 7.8.Read this passage
Upgrade Feasibility Study:
PDF bookmark
Upgrade Feasibility Study:Read this passage
“Upgrade Feasibility Study” shall mean a study conducted by the Transmission Provider in accordance with Tariff, Part IV, section 36.3.
PDF bookmark
“Upgrade Feasibility Study” shall mean a study conducted by the Transmission Provider in accordance with Tariff, Part IV, section 36.3.Read this passage
Upgrade-Related Rights:
PDF bookmark
Upgrade-Related Rights: “Upgrade-Related Rights” shall mean Incremental Auction Revenue Rights, Incremental Available Transfer Capability Revenue Rights, Incremental Deliverability Rights, and Incremental Capacity Transfer Rights.Read this passage
Upgrade Request:
PDF bookmark
Upgrade Request: “Upgrade Request” shall mean a request submitted in the form prescribed in Tariff, Attachment EE, for evaluation by the Transmission Provider of the feasibility and estimated costs of (a) a Merchant Network Upgrade or (b) the Customer-Funded Upgrades that would be needed to provide…Read this passage
Virtual Transaction:
PDF bookmark
Virtual Transaction:Read this passage
“Virtual Transaction” shall mean a Decrement Bid, Increment Offer and/or Up-to Congestion Transaction.
PDF bookmark · Topic match: Reliability and curtailment
“Virtual Transaction” shall mean a Decrement Bid, Increment Offer and/or Up-to Congestion Transaction.Read this passage Filed comments: Reliability and curtailment
I. INTRODUCTION
printed heading
I.Read this passage
INTRODUCTION
printed heading · Topic match: Reliability and curtailment
As more fully set forth in this Attachment and the PJM Manuals, and in conjunction with the Reliability Assurance Agreement: (a) Interim Resource Adequacy Service is a load reduction service, effective starting with the 2027/2028 Delivery Year, through which Eligible New Large Loads may be…Read this passage Filed comments: Reliability and curtailment
II. RESPONSBILITIES OF THE OFFICE OF THE INTERCONNECTION
printed heading · Topic match: Reliability and curtailment
RESPONSBILITIES OF THE OFFICE OF THE INTERCONNECTION The Office of the Interconnection shall: (a) maintain the Large Load Registry, pursuant to Reliability Assurance Agreement, Schedule 11; (b) identify Eligible New Large Loads; (c) determine the megawatt quantity of New Large Loads eligible to…Read this passage Filed comments: Reliability and curtailment
III. RESPONSBILITIES OF ELECTRIC DISTRIBUTORS
printed heading · Topic match: Registry access
RESPONSBILITIES OF ELECTRIC DISTRIBUTORS Electric Distributors shall: (a) execute the Office of the Interconnection’s directives to implement Interim Resource Adequacy Service Actions among the Eligible New Large Loads in the Electric Distributor’s zone/area, which is an area within a Zone for…Read this passage Filed comments: Registry access
IV. DETERMINATION OF MAXIMUM INTERIM RESOURCE ADEQUACY
printed heading · Topic match: Reliability and curtailment
DETERMINATION OF MAXIMUM INTERIM RESOURCE ADEQUACY SERVICE EACH ELIGIBLE NEW LARGE LOAD MAY PROVIDE IN A DELIVERY YEAR (a) All Eligible New Large Loads shall be available to be requested to provide Interim Resource Adequacy Service by the Office of the Interconnection. (b) The amount of Interim…Read this passage Filed comments: Reliability and curtailment
V. DETERMINATION OF NEW LARGE LOADS ELIGIBILITY TO PROVIDE
printed heading · Topic match: Registry access
DETERMINATION OF NEW LARGE LOADS ELIGIBILITY TO PROVIDE INTERIM RESOURCE ADEQUACY SERVICE (a) All New Large Loads shall be Eligible New Large Loads to the extent that the sum of a New Large Load’s Eligible New Large Load Amount is less than the New Large Load’s registered peak load (in MW), as…Read this passage Filed comments: Registry access
VI. BRING YOUR OWN NEW CAPACITY CRITERIA
printed heading · Topic match: Connecting load and generation
To the extent three consecutive Delivery Years meet the requirements of Tariff, Attachment DD-4, section IV(b)(iii), then megawatts of Unforced Capacity may qualify as BYONC to the extent the underlying resource meets the criteria in subsection (b) below and such megawatts (1) have not cleared in…Read this passage
VII. BRING YOUR OWN NEW CAPACITY ARRANGEMENTS WITH NEW LARGE
printed heading · Topic match: Registry access
By April 15, the Office of the Interconnection shall update the Large Load Registry to reflect any verified arrangements between New Large Loads and BYONC. (c) For an arrangement between a New Large Load and BYONC to be effective for the 2029/2030 Delivery Year, for any BYONC arrangement to be…Read this passage Filed comments: Registry access
VIII. BRING
printed heading
BRING YOUR OWN NEW CAPACITY PARTICIPATION IN THE RELIABILITY PRICING MODEL (a) All BYONC in an arrangement with a New Large Load must meet the requirements in Tariff, Attachment DD, section 5.5A and become Capacity Resources eligible to participate in RPM Auctions. (b) All BYONC in an arrangement…Read this passage
IX. ALLOCATION OF RBP UCAP MW
printed heading · Topic match: Cost allocation
ALLOCATION OF RBP UCAP MW (a) Each Electric Distributor zone/area allocated RBP Charges pursuant to Tariff, Attachment DD, section 18.3(a) shall be allocated RBP UCAP MW on a pro-rata basis using the Electric Distributor zone/area’s assigned share of the total Final RBP Target MW across all…Read this passage Filed comments: Cost allocation
X. COMPENSATION FOR PROVIDING INTERIM RESOURCE ADEQUACY
printed heading · Topic match: Reliability and curtailment
COMPENSATION FOR PROVIDING INTERIM RESOURCE ADEQUACY SERVICE (a) The rate for the provision of Interim Resource Adequacy Service shall be 50% of the Non-Performance Charge Rate specified in Tariff, Attachment DD, section 10A(e), unless any Eligible New Large Load elects to (i) accept in its retail…Read this passage Filed comments: Reliability and curtailment
ARTICLE 1 – DEFINITIONS
PDF bookmark
ARTICLE 1 – DEFINITIONS Unless the context otherwise specifies or requires, capitalized terms used herein shall have the respective meanings assigned herein or in the Schedules hereto, or in the PJM Tariff or PJM Operating Agreement if not otherwise defined in this Agreement, for all purposes of…Read this passage
Agreement:
PDF bookmark
Agreement: Accredited UCAP:Read this passage
“Accredited UCAP” shall mean the quantity of Unforced Capacity, as denominated in Effective UCAP, that an ELCC Resource is capable of providing in a given Delivery Year.
PDF bookmark
“Accredited UCAP” shall mean the quantity of Unforced Capacity, as denominated in Effective UCAP, that an ELCC Resource is capable of providing in a given Delivery Year.Read this passage
Accredited UCAP Factor:
PDF bookmark
Accredited UCAP Factor:Read this passage
“Accredited UCAP Factor” shall mean, through the 2024/2025 Delivery Year, one minus EFORd, and for 2025/2026 Delivery Year and subsequent Delivery Years, the ratio of the Capacity Resource’s Accredited UCAP to the Capacity Resource’s installed capacity.
PDF bookmark
“Accredited UCAP Factor” shall mean, through the 2024/2025 Delivery Year, one minus EFORd, and for 2025/2026 Delivery Year and subsequent Delivery Years, the ratio of the Capacity Resource’s Accredited UCAP to the Capacity Resource’s installed capacity.Read this passage
Behind The Meter Generation:
PDF bookmark
Behind The Meter Generation: “Behind The Meter Generation” shall refer to a generating unit that delivers energy to load without using the Transmission System or any distribution facilities (unless the entity that owns or leases the distribution facilities consented to such use of the distribution…Read this passage
Black Start Capability:
PDF bookmark
Black Start Capability: “Black Start Capability” shall mean the ability of a generating unit or station to go from a shutdown condition to an operating condition and start delivering power without assistance from the power system.Read this passage
Capacity Emergency Transfer Objective (CETO):
PDF bookmark
Capacity Emergency Transfer Objective (CETO): “Capacity Emergency Transfer Objective” or “CETO” shall mean, through the 2024/2025 Delivery Year, the amount of electric energy that a given area must be able to import in order to remain within a loss of load expectation of one event in 25 years when…Read this passage
Capacity Emergency Transfer Limit (CETL):
PDF bookmark
Capacity Emergency Transfer Limit (CETL): Capacity Emergency Transfer Limit” or “CETL” shall mean the capability of the transmission system to support deliveries of electric energy to a given area experiencing a localized capacity emergency as determined in accordance with the PJM Manuals.Read this passage
“Capacity Performance Resource” shall have the same meaning as in Tariff, Attachment DD.
PDF bookmark
“Capacity Performance Resource” shall have the same meaning as in Tariff, Attachment DD.Read this passage
Capacity Resources:
PDF bookmark
Capacity Resource Provider: “Capacity Resource Provider” shall mean a Member that (1) owns, or has the contractual authority to control the output of, a Generation Capacity Resource, that has not transferred such authority to another entity; (2) or a DER Aggregator that has a contractual…Read this passage
Capacity Transfer Right:
PDF bookmark
Capacity Transfer Right: “Capacity Transfer Right” shall have the meaning specified in Tariff, Attachment DD.Read this passage
Consolidated Transmission Owners Agreement, PJM Transmission Owners Agreement or Transmission Owners Agreement:
PDF bookmark
Consolidated Transmission Owners Agreement, PJM Transmission Owners Agreement or Transmission Owners Agreement: “Consolidated Transmission Owners Agreement,” “PJM Transmission Owners Agreement” or “Transmission Owners Agreement” shall mean that certain Consolidated Transmission Owners Agreement,…Read this passage
Control Area:
PDF bookmark
Control Area: “Control Area” shall mean an electric power system or combination of electric power systems bounded by interconnection metering and telemetry to which a common generation control scheme is applied in order to: (a) match the power output of the generators within the electric power…Read this passage
Daily Unforced Capacity Obligation:
PDF bookmark
Daily Unforced Capacity Obligation: “Daily Unforced Capacity Obligation” shall mean the capacity obligation of a Load Serving Entity during the Delivery Year, determined in accordance with the Reliability Assurance Agreement, Schedule 8 or, as to an FRR Entity, in the Reliability Assurance…Read this passage
Delivery Year:
PDF bookmark
Delivery Year: “Delivery Year” shall mean a Planning Period for which a Capacity Resource is committed pursuant to the auction procedures specified in Tariff, Attachment DD or pursuant to an FRR Capacity Plan under RAA, Schedule 8.1.Read this passage
Demand Resource (DR):
PDF bookmark
Demand Resource (DR): “Demand Resource” or “DR” shall mean a Limited Demand Resource, Extended Summer Demand Resource, Annual Demand Resource, Base Capacity Demand Resource or Summer- Period Demand Resource with a demonstrated capability to provide a reduction in demand or otherwise control load in…Read this passage
Demand Resource Factor or DR Factor:
PDF bookmark
Demand Resource Factor or DR Factor: “Demand Resource Factor” or “DR Factor” shall mean, for Delivery Years through May 31, 2018, that factor approved from time to time by the PJM Board used to determine the unforced capacity value of a Demand Resource in accordance with Reliability Assurance…Read this passage
Demand Resource Sell Offer Plan:
PDF bookmark
Demand Resource Sell Offer Plan: “Demand Resource Sell Offer Plan” shall mean the plan required by Reliability Assurance Agreement, Schedule 6 and Reliability Assurance Agreement, Schedule 8.1 in support of an intended offer of Demand Resources in an RPM Auction, or an intended inclusion of Demand…Read this passage
Electric Cooperative:
PDF bookmark
Electric Cooperative: “Electric Cooperative” shall mean an entity owned in cooperative form by its customers that is engaged in the generation, transmission, and/or distribution of electric energy.Read this passage
Electric Distributor:
PDF bookmark
Electric Distributor: “Electric Distributor” shall mean a Member that 1) owns or leases with rights equivalent to ownership of electric distribution facilities that are used to provide electric distribution service to electric load within the PJM Region; or 2) is a generation and transmission…Read this passage
Emergency:
PDF bookmark
Emergency: “Emergency” shall mean (i) an abnormal system condition requiring manual or automatic action to maintain system frequency, or to prevent loss of firm load, equipment damage, or tripping of system elements that could adversely affect the reliability of an electric system or the safety of…Read this passage
End-Use Customer:
PDF bookmark · Topic match: Retail and wholesale authority
End-Use Customer: “End-Use Customer” shall mean a Member that is a retail end-user of electricity within the PJM Region.Read this passage Filed comments: Retail and wholesale authority
Energy Efficiency Resource:
PDF bookmark
Energy Efficiency Resource: “Energy Efficiency Resource” shall mean a project, including installation of more efficient devices or equipment or implementation of more efficient processes or systems, meeting the requirements of RAA, Schedule 6 and exceeding then-current building codes, appliance…Read this passage
“Exigent Water Storage” shall mean water stored in the pondage or reservoir of a hydropower resource which is not typically available during normal operating conditions (as those conditions are described in the relevant FERC hydropower license), but which can be drawn upon during emergency conditions (as described in the FERC hydropower license), including in order to avoid a load shed. In an effective load carrying capability analysis, exigent storage capability from an upstream hydro facility can be considered relative to a downstream hydro facility by assessing cascading storage and flows.
PDF bookmark · Topic match: Reliability and curtailment
“Exigent Water Storage” shall mean water stored in the pondage or reservoir of a hydropower resource which is not typically available during normal operating conditions (as those conditions are described in the relevant FERC hydropower license), but which can be drawn upon during emergency…Read this passage Filed comments: Reliability and curtailment
Existing Demand Resource:
PDF bookmark · Topic match: Connecting load and generation
A Generation Capacity Resource shall be deemed to be in service if interconnection service has ever commenced (for resources located in the PJM Region), or if it is physically and electrically interconnected to an external Control Area and is in full commercial operation (for resources not located…Read this passage
Facilities Study Agreement:
PDF bookmark
Facilities Study Agreement: “Facilities Study Agreement” shall have the same meaning as in Tariff, Part VI, section 206.Read this passage
FERC or Commission:
PDF bookmark
FERC or Commission: “FERC” or “Commission” shall mean the Federal Energy Regulatory Commission or any successor federal agency, commission or department exercising jurisdiction over the Tariff, Operating Agreement and Reliability Assurance Agreement.Read this passage
Firm Point-To-Point Transmission Service:
PDF bookmark
Firm Point-To-Point Transmission Service: “Firm Point-To-Point Transmission Service” shall have the meaning specified in the Tariff.Read this passage
Firm Service Level:
PDF bookmark
Firm Service Level:Read this passage
“Firm Service Level” or “FSL” of Price Responsive Demand shall mean the level, determined at a PRD Substation level, to which Price Responsive Demand shall be reduced during the Delivery Year when the Locational Marginal Price exceeds the price associated with such Price Responsive Demand identified by the PRD Provider in its PRD Plan. “Firm Service Level” or “FSL” of Demand Resource shall mean the pre-determined level to which an end-use customer’s load shall be reduced, upon notification from the Curtailment Service Provider’s market operations center or its agent.
PDF bookmark · Topic match: Reliability and curtailment
“Firm Service Level” or “FSL” of Demand Resource shall mean the pre-determined level to which an end-use customer’s load shall be reduced, upon notification from the Curtailment Service Provider’s market operations center or its agent.Read this passage Filed comments: Reliability and curtailment
Firm Transmission Service:
PDF bookmark
Firm Transmission Service: “Firm Transmission Service” shall mean transmission service that is intended to be available at all times to the maximum extent practicable, subject to an Emergency, an unanticipated failure of a facility, or other event beyond the control of the owner or operator of the…Read this passage
Fixed Resource Requirement Alternative or FRR Alternative:
PDF bookmark
Fixed Resource Requirement Alternative or FRR Alternative: “Fixed Resource Requirement Alternative” or “FRR Alternative” shall mean an alternative method for a Party to satisfy its obligation to provide Unforced Capacity hereunder, as set forth in the Reliability Assurance Agreement, Schedule 8.1.Read this passage
Forecast Pool Requirement:
PDF bookmark
Forecast Pool Requirement: “Forecast Pool Requirement” or “FPR” shall mean the amount equal to one plus the unforced reserve margin (stated as a decimal number) for the PJM Region required pursuant to this Reliability Assurance Agreement, as approved by the PJM Board pursuant to Reliability…Read this passage
FRR Capacity Plan or FRR Plan:
PDF bookmark
FRR Capacity Plan or FRR Plan: “FRR Capacity Plan” or “FRR Plan” shall mean a long-term plan for the commitment of Capacity Resources and Price Responsive Demand to satisfy the capacity obligations of a Party that has elected the FRR Alternative, as more fully set forth in the Reliability Assurance…Read this passage
FRR Entity:
PDF bookmark
FRR Entity: “FRR Entity” shall mean, for the duration of such election, a Party that has elected the FRR Alternative hereunder.Read this passage
FRR Service Area:
PDF bookmark
In the event that the service obligations of an Electric Cooperative or Public Power Entity are not defined by geographic boundaries but by physical connections to a defined set of customers, the FRR Service Area in such circumstances shall be defined as all customers physically connected to…Read this passage
Full Requirements Service:
PDF bookmark
Full Requirements Service: “Full Requirements Service” shall mean wholesale service to supply all of the power needs of a Load Serving Entity to serve end-users within the PJM Region that are not satisfied by its own generating facilities.Read this passage
Generation Capacity Resource:
PDF bookmark
Generation Capacity Resource: “Generation Capacity Resource” shall mean a Generating Facility, or the contractual right to capacity from a specified Generating Facility, that meets the requirements of RAA, Schedule 9 and RAA, Schedule 10, and, for Generating Facilities that are committed to an FRR…Read this passage
Generation Owner:
PDF bookmark
Generation Owner: “Generation Owner” shall mean a Member that owns or leases with rights equivalent to ownership, or otherwise controls and operates one or more operating generation resources located in the PJM Region.Read this passage
Generator Forced Outage:
PDF bookmark
Generator Forced Outage: “Generator Forced Outage” shall mean an immediate reduction in output or capacity or removal from service, in whole or in part, of a generating unit by reason of an Emergency or threatened Emergency, unanticipated failure, or other cause beyond the control of the owner or…Read this passage
Generator Maintenance Outage:
PDF bookmark
Generator Maintenance Outage: “Generator Maintenance Outage” shall mean the scheduled removal from service, in whole or in part, of a generating unit in order to perform repairs on specific components of the facility, if removal of the facility qualifies as a maintenance outage pursuant to the PJM…Read this passage
Generator Planned Outage:
PDF bookmark
Generator Planned Outage: “Generator Planned Outage” shall mean the scheduled removal from service, in whole or in part, of a generating unit for inspection, maintenance or repair with the approval of the Office of the Interconnection in accordance with the PJM Manuals.Read this passage
Good Utility Practice:
PDF bookmark
Good Utility Practice: “Good Utility Practice” shall mean any of the practices, methods and acts engaged in or approved by a significant portion of the electric utility industry during the relevant time period, or any of the practices, methods and acts which, in the exercise of reasonable judgment…Read this passage
Incremental Auction:
PDF bookmark
Incremental Auction: “Incremental Auction” shall mean any of several auctions conducted for a Delivery Year after the Base Residual Auction for such Delivery Year and before the first day of such Delivery Year, including the First Incremental Auction, Second Incremental Auction, Third Incremental…Read this passage
IOU:
PDF bookmark
IOU: “IOU” shall mean an investor-owned utility with substantial business interest in owning and/or operating electric facilities in any two or more of the following three asset categories: generation, transmission, distribution.Read this passage
Load Serving Entity or LSE:
PDF bookmark
Load Serving Entity or LSE: “Load Serving Entity” or “LSE” shall mean any entity (or the duly designated agent of such an entity), including a load aggregator or power marketer, (i) serving end-users within the PJM Region, and (ii) that has been granted the authority or has an obligation pursuant…Read this passage
Locational Reliability Charge:
PDF bookmark
Locational Reliability Charge: “Locational Reliability Charge” shall mean the charge determined pursuant to RAA, Article 7, section 2.Read this passage
Markets and Reliability Committee:
PDF bookmark
Markets and Reliability Committee: “Markets and Reliability Committee” shall mean the committee established pursuant to the Operating Agreement as a Standing Committee of the Members Committee.Read this passage
Maximum Emergency Service Level:
PDF bookmark
Maximum Emergency Service Level:Read this passage
“Maximum Emergency Service Level” or “MESL” of Price Responsive Demand for the 2017/2018 through the 2021/2022 Delivery Years shall mean the level, determined at a PRD Substation level, to which Price Responsive Demand shall be reduced during the Delivery Year when a Maximum Generation Emergency is declared and the Locational Marginal Price exceeds the price associated with such Price Responsive Demand identified by the PRD Provider in its PRD Plan.
PDF bookmark
“Maximum Emergency Service Level” or “MESL” of Price Responsive Demand for the 2017/2018 through the 2021/2022 Delivery Years shall mean the level, determined at a PRD Substation level, to which Price Responsive Demand shall be reduced during the Delivery Year when a Maximum Generation Emergency is…Read this passage
Member:
PDF bookmark
Member: “Member” shall have the meaning provided in the Operating Agreement.Read this passage
Members Committee:
PDF bookmark
Members Committee: “Members Committee” shall mean the committee specified in Operating Agreement, section 8 composed of the representatives of all the Members.Read this passage
NERC:
PDF bookmark
NERC: “NERC” shall mean the North American Electric Reliability Corporation or any successor thereto.Read this passage
Network Transmission Service:
PDF bookmark
Network Transmission Service: “Network Transmission Service” shall mean transmission service provided pursuant to the rates, terms and conditions set forth in Tariff, Part III or transmission service comparable to such service that is provided to a Load Serving Entity that is also a Transmission…Read this passage
Nominal PRD Value:
PDF bookmark
Nominal PRD Value: “Nominal PRD Value” shall mean, as to any PRD Provider, an adjustment, determined in accordance with Reliability Assurance Agreement, Schedule 6.1, to the peak-load forecast used to determine the quantity of capacity sought through an RPM Auction, reflecting the aggregate effect…Read this passage
Nominated Demand Resource Value:
PDF bookmark
Nominated Demand Resource Value: “Nominated Demand Resource Value” shall have the meaning specified in Tariff, Attachment DD.Read this passage
Non-Retail Behind the Meter Generation:
PDF bookmark
Non-Retail Behind the Meter Generation: “Non-Retail Behind the Meter Generation” shall mean Behind the Meter Generation that is used by municipal electric systems, electric cooperatives, and electric distribution companies to serve load.Read this passage
Obligation Peak Load:
PDF bookmark
Obligation Peak Load: “Obligation Peak Load” shall have the meaning specified in Reliability Assurance Agreement, Schedule 8.Read this passage
Office of the Interconnection:
PDF bookmark
Office of the Interconnection: “Office of the Interconnection” shall mean the employees and agents of PJM Interconnection, L.L.C., subject to the supervision and oversight of the PJM Board, acting pursuant to the Operating Agreement.Read this passage
Operating Agreement of the PJM Interconnection, L.L.C., Operating Agreement or PJM Operating Agreement:
PDF bookmark
Operating Agreement of the PJM Interconnection, L.L.C., Operating Agreement or PJM Operating Agreement: “Operating Agreement of the PJM Interconnection, L.L.C.,” “Operating Agreement” or “PJM Operating Agreement” shall mean that agreement, dated as of April 1, 1997 and as amended and restated as of…Read this passage
Operating Reserve:
PDF bookmark
Operating Reserve: “Operating Reserve” shall mean the amount of generating capacity scheduled to be available for a specified period of an Operating Day to ensure the reliable operation of the PJM Region, as specified in the PJM Manuals.Read this passage
Other Supplier:
PDF bookmark
Other Supplier: “Other Supplier” shall mean a Member that: (i) is engaged in buying, selling or transmitting electric energy, capacity, ancillary services, Financial Transmission Rights or other services available under PJM’s governing documents in or through the Interconnection or has a good faith…Read this passage
Partial Requirements Service:
PDF bookmark
Partial Requirements Service: “Partial Requirements Service” shall mean wholesale service to supply a specified portion, but not all, of the power needs of a Load Serving Entity to serve end-users within the PJM Region that are not satisfied by its own generating facilities.Read this passage
Party:
PDF bookmark
Party: “Party” shall mean an entity bound by the terms of the Operating Agreement.Read this passage
Percentage Internal Resources Required:
PDF bookmark
Percentage Internal Resources Required: “Percentage Internal Resources Required” shall mean, for purposes of an FRR Capacity Plan, the percentage of the LDA Reliability Requirement for an LDA that must be satisfied with Capacity Resources located in such LDA.Read this passage
PJM:
PDF bookmark
PJM: “PJM” shall mean PJM Interconnection, L.L.C., including the Office of the Interconnection as referenced in the PJM Operating Agreement.Read this passage
PJM Board:
PDF bookmark
PJM Board: “PJM Board” shall mean the Board of Managers of the LLC, acting pursuant to the Operating Agreement, except when such term is being used in Tariff, Attachment M, in which case PJM Board shall mean the Board of Managers of PJM or its designated representative, exclusive of any members of…Read this passage
PJM Manuals:
PDF bookmark
PJM Manuals: “PJM Manuals” shall mean the instructions, rules, procedures and guidelines established by the Office of the Interconnection for the operation, planning and accounting requirements of the PJM Region.Read this passage
PJM Region:
PDF bookmark
PJM Region: “PJM Region” shall have the same meaning as provided in the Operating Agreement.Read this passage
PJM Region Installed Reserve Margin:
PDF bookmark
PJM Region Installed Reserve Margin: “PJM Region Installed Reserve Margin” shall mean the percent installed reserve margin for the PJM Region required pursuant to Reliability Assurance Agreement, Schedule 4.1, as approved by the PJM Board.Read this passage
PJM Tariff, Tariff, O.A.T.T., OATT or PJM Open Access Transmission Tariff:
PDF bookmark
PJM Tariff, Tariff, O.A.T.T., OATT or PJM Open Access Transmission Tariff: “PJM Tariff,” “Tariff,” “O.A.T.T., “OATT” or “PJM Open Access Transmission Tariff” shall mean that certain PJM Open Access Transmission Tariff, including any schedules, appendices, or exhibits attached thereto, on file with…Read this passage
Planned Demand Resource:
PDF bookmark
Planned Demand Resource: “Planned Demand Resource” shall mean any Demand Resource that does not currently have the capability to provide a reduction in demand or to otherwise control load, but that is scheduled to be capable of providing such reduction or control on or before the start of the…Read this passage
A “Planned DER Capacity Aggregation Resource” shall mean any DER Capacity Aggregation Resource that does not currently have the capability to provide generation or reduction in demand, but that is scheduled to be capable of providing such generation or reduction in demand on or before the start of the Delivery Year for which such resource is to be committed, as determined in accordance with the requirements of Reliability Assurance Agreement, Schedule 6.2. As set forth in Reliability Assurance Agreement, Schedule 6.2 and Reliability Assurance Agreement, Schedule 8.1, a DER Aggregator submitting a DER Capacity Aggregation Resource Sell Offer Plan shall identify in such plan all DER Capacity Aggregation Resources in excess of those that qualify as Existing DER Capacity Aggregation Resources. A Planned DER Capacity Aggregation Resource must comply with all provisions of the DER Aggregator Participation Model described in Tariff, Attachment K-Appendix, section 1.4B and Operating Agreement, Schedule 1, section 1.4B, prior to the applicable Delivery Year.
PDF bookmark
A “Planned DER Capacity Aggregation Resource” shall mean any DER Capacity Aggregation Resource that does not currently have the capability to provide generation or reduction in demand, but that is scheduled to be capable of providing such generation or reduction in demand on or before the start of…Read this passage
Planned External Generation Capacity Resource:
PDF bookmark
Any such resource shall cease to be considered a Planned External Generation Capacity Resource as of the earlier of (i) the date that interconnection service commences as to such resource; or (ii) the resource has cleared an RPM Auction, in which case it shall become an Existing Generation Capacity…Read this passage
Planned Generation Capacity Resource:
PDF bookmark · Topic match: Connecting load and generation
For purposes of the must-offer requirement and mitigation of offers for any RPM Auction for a Delivery Year, a Generation Capacity Resource shall cease to be considered a Planned Generation Capacity Resource as of the earlier of (i) the date that Interconnection Service commences as to such…Read this passage
Planning Period:
PDF bookmark
Planning Period: “Planning Period” shall mean the 12 months beginning June 1 and extending through May 31 of the following year, or such other period approved by the Members Committee.Read this passage
PRD Curve:
PDF bookmark
PRD Curve:Read this passage
“PRD Curve” shall mean a price-consumption curve at a PRD Substation level, if available, and otherwise at a Zonal (or sub-Zonal LDA, if applicable) level, that details the base consumption level of Price Responsive Demand and the decreasing consumption levels at increasing prices.
PDF bookmark
“PRD Curve” shall mean a price-consumption curve at a PRD Substation level, if available, and otherwise at a Zonal (or sub-Zonal LDA, if applicable) level, that details the base consumption level of Price Responsive Demand and the decreasing consumption levels at increasing prices.Read this passage
PRD Provider:
PDF bookmark
PRD Provider: “PRD Provider” shall mean a PJM Member that has entered contractual arrangements with end- use customers that satisfy the eligibility criteria for and provides Price Responsive Demand.Read this passage
“PRD Provider’s Zonal Expected Peak Load Value of PRD” shall mean the expected contribution to Delivery Year peak load of a PRD Provider’s Price Responsive Demand, were such demand not to be reduced in response to price, based on the contribution of the end-use customers comprising such Price Responsive Demand to the most recent prior Delivery Year’s peak demand, escalated to the Delivery Year in question, as determined in a manner consistent with the Office of the Interconnection’s load forecasts used for purposes of the RPM Auctions.
PDF bookmark
“PRD Provider’s Zonal Expected Peak Load Value of PRD” shall mean the expected contribution to Delivery Year peak load of a PRD Provider’s Price Responsive Demand, were such demand not to be reduced in response to price, based on the contribution of the end-use customers comprising such Price…Read this passage
PRD Reservation Price:
PDF bookmark
PRD Reservation Price:Read this passage
“PRD Reservation Price” shall mean an RPM Auction clearing price identified in a PRD Plan for Price Responsive Demand load below which the PRD Provider desires not to commit the identified load as Price Responsive Demand.
PDF bookmark
“PRD Reservation Price” shall mean an RPM Auction clearing price identified in a PRD Plan for Price Responsive Demand load below which the PRD Provider desires not to commit the identified load as Price Responsive Demand.Read this passage
PRD Substation:
PDF bookmark
PRD Substation:Read this passage
“PRD Substation” shall mean an electrical substation that is located in the same Zone or in the same sub-Zonal LDA as the end-use customers identified in a PRD Plan or PRD registration and that, in terms of the electrical topography of the Transmission Facilities comprising the PJM Region, is as close as practicable to such loads.
PDF bookmark
“PRD Substation” shall mean an electrical substation that is located in the same Zone or in the same sub-Zonal LDA as the end-use customers identified in a PRD Plan or PRD registration and that, in terms of the electrical topography of the Transmission Facilities comprising the PJM Region, is as…Read this passage
Price Responsive Demand:
PDF bookmark
Price Responsive Demand:Read this passage
“Price Responsive Demand” or “PRD” shall mean end-use customer load registered by a PRD Provider pursuant to Reliability Assurance Agreement, Schedule 6.1 that have, as set forth in more detail in the PJM Manuals, the metering capability to record electricity consumption at an interval of one hour or less, Supervisory Control capable of curtailing such load (consistent with applicable RERRA requirements) at each PRD Substation identified in the relevant PRD Plan or PRD registration in response to a Performance Assessment Interval that triggers a PRD performance assessment or a Non-PAI Event, and a retail rate structure, or equivalent contractual arrangement, capable of changing retail rates as frequently as an hourly basis, that is linked to or based upon changes in real-time Locational Marginal Prices at a PRD Substation level and that results in a predictable automated response to varying wholesale electricity prices.
PDF bookmark · Topic match: Retail and wholesale authority
“Price Responsive Demand” or “PRD” shall mean end-use customer load registered by a PRD Provider pursuant to Reliability Assurance Agreement, Schedule 6.1 that have, as set forth in more detail in the PJM Manuals, the metering capability to record electricity consumption at an interval of one hour…Read this passage Filed comments: Retail and wholesale authority
Price Responsive Demand Credit:
PDF bookmark
Price Responsive Demand Credit:Read this passage
“Price Responsive Demand Credit” shall mean a credit, based on committed Price Responsive Demand, as determined under Reliability Assurance Agreement, Schedule 6.1.
PDF bookmark
“Price Responsive Demand Credit” shall mean a credit, based on committed Price Responsive Demand, as determined under Reliability Assurance Agreement, Schedule 6.1.Read this passage
Public Power Entity:
PDF bookmark
Public Power Entity: “Public Power Entity” shall mean any agency, authority, or instrumentality of a state or of a political subdivision of a state, or any corporation wholly owned by any one or more of the foregoing, that is engaged in the generation, transmission, and/or distribution of electric…Read this passage
Qualifying Transmission Upgrades:
PDF bookmark
Qualifying Transmission Upgrades: “Qualifying Transmission Upgrades” shall have the meaning specified in Tariff, Attachment DD.Read this passage
Relevant Electric Retail Regulatory Authority:
PDF bookmark
Relevant Electric Retail Regulatory Authority:Read this passage
“Relevant Electric Retail Regulatory Authority” or “RERRA” shall have the meaning specified in the PJM Operating Agreement.
PDF bookmark
“Relevant Electric Retail Regulatory Authority” or “RERRA” shall have the meaning specified in the PJM Operating Agreement.Read this passage
Reliability Principles and Standards:
PDF bookmark
Reliability Principles and Standards: “Reliability Principles and Standards” shall mean the principles and standards established by the Office of the Interconnection that define, among other things, an acceptable probabilistic of loss of load criteria due to inadequate generation or transmission…Read this passage
Required Approvals:
PDF bookmark
Required Approvals: “Required Approvals” shall mean all of the approvals required for the Operating Agreement to be modified or to be terminated, in whole or in part, including the acceptance for filing by FERC and every other regulatory authority with jurisdiction over all or any part of the…Read this passage
Self-Supply:
PDF bookmark
Self-Supply: “Self-Supply” shall have the meaning provided in Tariff, Attachment DD.Read this passage
State Consumer Advocate:
PDF bookmark · Topic match: Registry access
State Consumer Advocate: “State Consumer Advocate” shall mean a legislatively created office from any State, all or any part of the territory of which is within the PJM Region, and the District of Columbia established, inter alia, for the purpose of representing the interests of energy consumers…Read this passage Filed comments: Registry access
State Regulatory Structural Change:
PDF bookmark
State Regulatory Structural Change: “State Regulatory Structural Change” shall mean as to any Party, a state law, rule, or order that, after September 30, 2006, initiates a program that allows retail electric consumers served by such Party to choose from among alternative suppliers on a competitive…Read this passage
Steam Class:
PDF bookmark
Steam Class:Read this passage
“Steam Class” shall mean an ELCC Class consisting of Unlimited Resources of the steam technology type and the primary fuel is not coal or nuclear.
PDF bookmark
“Steam Class” shall mean an ELCC Class consisting of Unlimited Resources of the steam technology type and the primary fuel is not coal or nuclear.Read this passage
Supervisory Control:
PDF bookmark · Topic match: Reliability and curtailment
Except to the extent automation is not required by the provisions of the Operating Agreement, the curtailment shall be automated, meaning that load shall be reduced automatically in response to control signals sent by the PRD Provider or its designated agent directly to the control equipment where…Read this passage Filed comments: Reliability and curtailment
Threshold Quantity:
PDF bookmark
Threshold Quantity: “Threshold Quantity” shall mean, as to any FRR Entity for any Delivery Year, the sum of (a) the Unforced Capacity equivalent (determined using the Pool-Wide Average EFORD through the 2024/2025 Delivery Year, or pool-wide average Accredited UCAP Factor effective with the…Read this passage
Transmission Owner:
PDF bookmark
Transmission Owner: “Transmission Owner” shall mean a Member that owns or leases with rights equivalent to ownership Transmission Facilities and is a signatory to the PJM Transmission Owners Agreement.Read this passage
Unforced Capacity:
PDF bookmark
Unforced Capacity: “Unforced Capacity” shall mean installed capacity rated at summer conditions that is not on average experiencing a forced outage or forced derating, calculated for each Capacity Resource on the 12-month period from October to September without regard to the ownership of or the…Read this passage
Winter Peak Load (or WPL):
PDF bookmark
Winter Peak Load (or WPL):Read this passage
“Winter Peak Load” or “WPL” shall mean the average of the Demand Resource customer’s specific peak hourly load between hours ending 7:00 EPT through 21:00 EPT on the PJM defined 5 coincident peak days from December through February two Delivery Years prior the Delivery Year for which the registration is submitted. Notwithstanding, if the average use between hours ending 7:00 EPT through 21:00 EPT on a winter 5 coincident peak day is below 35% of the average hours ending 7:00 EPT through 21:00 EPT over all five of such peak days, then up to two such days and corresponding peak demand values may be excluded from the calculation. Upon approval by the Office of the Interconnection, a Curtailment Service Provider may provide alternative data to calculate Winter Peak Load, as outlined in the PJM Manuals, when there is insufficient hourly load data for the two Delivery Years prior to the relevant Delivery Year or if more than two days meet the exclusion criteria described above.
PDF bookmark · Topic match: Reliability and curtailment
“Winter Peak Load” or “WPL” shall mean the average of the Demand Resource customer’s specific peak hourly load between hours ending 7:00 EPT through 21:00 EPT on the PJM defined 5 coincident peak days from December through February two Delivery Years prior the Delivery Year for which the…Read this passage Filed comments: Reliability and curtailment
Zonal Capacity Price:
PDF bookmark
Zonal Capacity Price: “Zonal Capacity Price” shall mean the clearing price required in each Zone to meet the demand for Unforced Capacity and satisfy Locational Deliverability Requirements for the LDA or LDAs associated with such Zone.Read this passage
Zone or Zonal:
PDF bookmark
Zone or Zonal: “Zone” or “Zonal” shall refer to an area within the PJM Region, as set forth in Tariff, Attachment J and RAA, Schedule 15, or as such areas may be (i) combined as a result of mergers or acquisitions or (ii) added as a result of the expansion of the boundaries of the PJM Region.Read this passage
Zonal Winter Weather Adjustment Factor (ZWWAF):
PDF bookmark
Zonal Winter Weather Adjustment Factor (ZWWAF):Read this passage
“Zonal Winter Weather Adjustment Factor” or “ZWWAF” shall mean the PJM zonal winter weather normalized coincident peak divided by PJM zonal average of 5 coincident peak loads in December through February.
PDF bookmark · Topic match: Reliability and curtailment
“Zonal Winter Weather Adjustment Factor” or “ZWWAF” shall mean the PJM zonal winter weather normalized coincident peak divided by PJM zonal average of 5 coincident peak loads in December through February. 7.8 Requirement to Designate Network Resources to Serve Capacity Needs for New Large Loads and…Read this passage Filed comments: Reliability and curtailment
D. FRR Capacity Plans
PDF bookmark
Each FRR Entity shall submit its initial FRR Capacity Plan as required by subsection C.1 of this Schedule, and shall annually extend and update such plan by no later than one month prior to the Base Residual Auction for each succeeding Delivery Year in such plan.Read this passage
SCHEDULE 11 DATA SUBMITTALS
PDF bookmark
SCHEDULE 11 DATA SUBMITTALSRead this passage
A. To perform the studies required to determine the Forecast Pool Requirement and Daily
printed heading · Topic match: Registry access
The Office of the Interconnection also may consult with the Large Load. (d) Based on the information provided, or caused to be provided, by each Party, as well as other information provided by, for example, Electric Distributors, the Office of the Interconnection shall maintain a registry of all…Read this passage Filed comments: Registry access