Tab D - Redline ZGIA to pro forma GIA.pdf
Read topic-matched comments in ER26-3552
Topics in the text: Connecting load and generation · Registry access · Reliability and curtailment
Responses and related views
No section-specific public response is linked for this document.
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
Surplus Interconnection Service shall mean any Interconnection Service that is derived from the unneeded portion of Interconnection Service established in a GIA or in agreement with, or under the tariff of, a Transmission Owner prior to integration into MISO, such that if Surplus Interconnection…Read this passage Filed comments: Connecting load and generation
A. Constructing MISO Transmission Owner
printed heading
Constructing MISO Transmission Owner 1. ______________ 2. ______________ 3. ______________ 4. ______________Read this passage
B. SPP:
printed heading
Selected Option pursuant to Article 5.1: Interconnection Customer selects the [_____________] Option as described in Article 5.1.[ ], 5.1.[ ] and 5.1.[ ] shall not apply to this GIAZGIA. 2.Read this passage
A. Interconnection Customer Milestones
printed heading · Topic match: Connecting load and generation
Enter into amendment of this GIAZGIA, if required, for Interconnection Requests that did not elect optional negotiation period adjustment for Interconnection Facilities Study pursuant to GIAZGIA Section 11.3.1.Read this passage Filed comments: Connecting load and generation
B. Transmission Owner Milestones
printed heading
Transmission Owner to enter Network Upgrade information into Transmission Provider’s MTEP database and model on demand. 10 Business Days after Effective Date.Read this passage
C. Affected System Owner Milestones
printed heading
Transmission Owner shall provide the following “as-built” drawings, information and documents regarding the Transmission Owner’s Interconnection Facilities pursuant to Article 5.11 of this GIAZGIA. 2.Read this passage
A. General
printed heading
General The IBR plant shall adhere to IEEE 2800-2022 Clause 4 requirements, except for subclauses 4.1 (introduction), 4.5 (operational measurement and communication capability), 4.6 (control capability requirements), 4.8 (isolation devices), 4.9 (inadvertent energization of TS), 4.11…Read this passage
B. Response to Abnormal Conditions
printed heading
Response to Abnormal Conditions The IBR plant shall adhere to IEEE 2800-2022 Clause 7 requirements, except for subclauses 7.2.1 (voltage protection) and 7.3.1 (mandatory frequency tripping).Read this passage
C. Reactive Power
printed heading
Reactive Power The IBR plant shall adhere to IEEE 2800-2022 Clause 5 requirements.Read this passage
D. Primary Frequency Response
printed heading
Primary Frequency Response The IBR plant shall adhere to IEEE 2800-2022 Clause 6 requirements, except for Subclause 6.2 (fast frequency response).Read this passage
E. Supervisory Control and Data Acquisition (SCADA) Capability
printed heading · Topic match: Reliability and curtailment
Transmission Provider and Interconnection Customer shall determine what SCADA information is essential for the proposed IBR plant, taking into account the size of the plant and its characteristics, location, and importance in maintaining generation resource adequacy and transmission system…Read this passage Filed comments: Reliability and curtailment
F. Disturbance Monitoring and Reporting Requirements
printed heading
Disturbance Monitoring and Reporting Requirements IBR plants with generating capacities of more than 20 MW must monitor and record data for all frequency ride-through events, transient low-voltage disturbances that initiated reactive current injection, reactive current injection or momentary…Read this passage
G. Applicability
printed heading · Topic match: Connecting load and generation
MISO Attachment X: Appendix 619 FERC Electric Tariff GeneratorZG Interconnection Agreement (GIAZGIA) ATTACHMENTS 11031.0.0 Appendix I to GIAZGIA Requirements Applicable to Surplus Interconnection Service Where this GIAZGIA provides for Surplus Interconnection Service, Interconnection Customer…Read this passage Filed comments: Connecting load and generation