Midcontinent Independent System Operator, Inc.'s Large Load Addition Resource Study Process (transmittal letter; requested effective date December 2, 2026)
Topics in the text: Connecting load and generation · Reliability and curtailment · Cost allocation
What the document says
PDF p. 2
LARS studies a 200 MW-plus load and its paired generation together in about 120 days.
LARS will provide a path for the interconnection of both large loads and supporting generation pairs in a parallel 120-day study process. PDF p. 2
Two state commissions back the parallel study
Mississippi and Louisiana Public Service Commissions · Direct response
The commissions backed a 120-day joint study. They said studying the load and its generator together could avoid duplicating network upgrades; the limit of ten pairs per period made it manageable. They wanted a permanent process so projects could plan and finance construction.
Arkansas signs on to the Southern regulators’ case
Arkansas Public Service Commission · Direct response
Arkansas expressly agreed with the Mississippi and Louisiana commissions’ comments and asked FERC to accept MISO’s tariff changes. It did not offer its own numerical estimate of costs or queue delays.
Entergy and Cleco contrast 120 days with years in the regular queue
Entergy and Cleco · Direct response
The utilities said some ordinary MISO study cycles had taken four years or more. They supported the 120-day path and argued that its cap of ten load-generator pairs per study period would keep it workable.
Supporters say studying load and generation together removes duplicative upgrades and lowers costs.
The goal of LARS is not necessarily to find the lowest cost solution for either the load or generation but to identify the solution that best fits both PDF p. 15
Applicants must post $250,000, show site control, and sign a five-year pairing contract.
A non-refundable fee of $250,000 must accompany the LARS Application and be paid by the LARS Associated Transmission Customer. PDF p. 8
Utilities say deposits and commitments screen speculative requests
Alliant Energy and Consumers Energy · Direct response
The utilities backed the readiness requirements because a speculative project could occupy one of a limited number of study slots. They argued the joint model could identify cheaper combined upgrades.
DTE supported the pairing rules and minimum commitment as evidence of a lasting commercial relationship. It also said the tariff allowed the interconnection customer to participate even though the transmission customer submits the application.
Applicants must post $250,000, show site control, and sign a five-year pairing contract.
The agreement must be legally binding and must state a minimum term of five years PDF p. 9
Utilities say deposits and commitments screen speculative requests
Alliant Energy and Consumers Energy · Direct response
The utilities backed the readiness requirements because a speculative project could occupy one of a limited number of study slots. They argued the joint model could identify cheaper combined upgrades.
DTE supported the pairing rules and minimum commitment as evidence of a lasting commercial relationship. It also said the tariff allowed the interconnection customer to participate even though the transmission customer submits the application.
Applicants must post $250,000, show site control, and sign a five-year pairing contract.
limiting the amount of requested Interconnection Service to no more than 150% of the peak demand of the LARS Associated Load, and demonstration of 100% site control PDF p. 10
Utilities say deposits and commitments screen speculative requests
Alliant Energy and Consumers Energy · Direct response
The utilities backed the readiness requirements because a speculative project could occupy one of a limited number of study slots. They argued the joint model could identify cheaper combined upgrades.
DTE supported the pairing rules and minimum commitment as evidence of a lasting commercial relationship. It also said the tariff allowed the interconnection customer to participate even though the transmission customer submits the application.
Bloom backed the study but challenged its 200 MW entry threshold. It proposed letting transmission-connected loads of at least 50 MW participate and asked FERC not to delay the requested start date.
The load must be 200 MW or more at one point of withdrawal, unaggregated.
While MISO is allowing aggregation for LARS Generating Facilities, MISO is not allowing aggregated load to participate in LARS. PDF p. 11
Bloom proposes 50 MW without delaying the filing
Bloom Energy · Direct response
Bloom backed the study but challenged its 200 MW entry threshold. It proposed letting transmission-connected loads of at least 50 MW participate and asked FERC not to delay the requested start date.
Generation must connect in the load's Local Resource Zone, which can span several states.
Another important condition of the LARS process is the requirement that the load and generation pair be located in the same Local Resource Zone PDF p. 10
The pair must stay together 15 years; if the load leaves, the generator gets a year.
this requirement ensures that the LARS study process accurately reflects the expected impacts of the Generating Facility and LARS Associated Load on the Transmission System for a significant period of time. PDF p. 16
Upgrades for violations seen in the load study, or in both studies, go to zonal load.
Then any common violations that show up in the generation and load studies are assigned to BRP and Other project types. Only the violations but for the generator are assigned GIP project types. PDF p. 12
PDF p. 13
MISO says double-allocated headroom gets fixed later through MTEP projects, paid by zonal load.
In the event that overallocation does occur, any constraints that are identified as needing mitigation in the MTEP process will be formalized in a future MTEP project. PDF p. 13
Who gets first claim on spare grid capacity?
American Clean Power Association and Southern Renewable Energy Association · Direct response
The trade associations said studying accelerated projects without other generators already waiting could leave later studies with fewer feasible connections and higher costs. They objected to a permanent parallel route without a cap on total capacity.
Solar Energy Industries Association and Advanced Energy United · Direct response
The protesters asked FERC to reject the proposal or clarify that an applicant meeting all published requirements could not lose access at the transmission customer’s discretion.
State organization asks for protection of existing queue positions
Organization of MISO States, quoted by Utility Dive · Direct response
OMS warned that a rapid route must not turn into a general substitute for the queue. It asked for safeguards before qualifying pairs could claim transmission capacity ahead of projects already waiting.
MISO says double-allocated headroom gets fixed later through MTEP projects, paid by zonal load.
The cost of the MTEP project will be allocated based on existing Tariff rules, which is likely to be the load within the transmission pricing zone where the transmission upgrade is required. PDF p. 13
Who gets first claim on spare grid capacity?
American Clean Power Association and Southern Renewable Energy Association · Direct response
The trade associations said studying accelerated projects without other generators already waiting could leave later studies with fewer feasible connections and higher costs. They objected to a permanent parallel route without a cap on total capacity.
Solar Energy Industries Association and Advanced Energy United · Direct response
The protesters asked FERC to reject the proposal or clarify that an applicant meeting all published requirements could not lose access at the transmission customer’s discretion.
State organization asks for protection of existing queue positions
Organization of MISO States, quoted by Utility Dive · Direct response
OMS warned that a rapid route must not turn into a general substitute for the queue. It asked for safeguards before qualifying pairs could claim transmission capacity ahead of projects already waiting.
MISO will file its cost-shifting agreement by November 16, 2026; LARS need not wait.
all of which will be submitted to the Commission in a FPA section 205 filing by November 16, 2026. PDF p. 14
Consumer offices question the treatment of existing load
Iowa Office of Consumer Advocate, Illinois and Michigan attorneys general, Minnesota Department of Commerce and co-protesters · Direct response
The joint protesters asked how the study would prevent costs shifting to other customers. They warned that related MISO proposals could exempt about 30 GW of existing load from some reliability requirements; 30 GW was not the size of the proposed LARS study queue.
MISO will file its cost-shifting agreement by November 16, 2026; LARS need not wait.
LARS can be implemented based on the Tariff revisions filed herein and need not await these future filings. PDF p. 14
Consumer offices question the treatment of existing load
Iowa Office of Consumer Advocate, Illinois and Michigan attorneys general, Minnesota Department of Commerce and co-protesters · Direct response
The joint protesters asked how the study would prevent costs shifting to other customers. They warned that related MISO proposals could exempt about 30 GW of existing load from some reliability requirements; 30 GW was not the size of the proposed LARS study queue.
MISO says only the transmission customer can buy transmission service, so it must file.
Because only the Transmission Customer can procure Transmission Service under established Tariff processes, LARS requires the LARS Associated Transmission Customer to be the party that initiates the LARS Application PDF p. 6
Google backs co-study but wants safeguards for independent bids
Google · Direct response
Google supported studying loads and generators together but questioned the separate assumptions used in the ordinary queue. It wanted cost protections and a way for independent generators to participate without discrimination by the serving utility.
MISO says only the transmission customer can buy transmission service, so it must file.
This does not supersede the role of the LARS Associated Transmission Customer to determine whether to submit a LARS Application PDF p. 9
Google backs co-study but wants safeguards for independent bids
Google · Direct response
Google supported studying loads and generators together but questioned the separate assumptions used in the ordinary queue. It wanted cost protections and a way for independent generators to participate without discrimination by the serving utility.
A parallel queue can promise the same grid capacity twice
Clean Energy Advocates · Direct response
The advocates warned that two study tracks using different assumptions could count the same unused transmission capacity twice. They challenged assigning upgrade costs to existing customers based on agreements whose terms FERC had not seen.
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
This is done to avoid confusion because that definition remains pending before the Commission and because, given the 200 MW threshold for entry into LARS, not all “Large Loads” will be eligible to be a “LARS Associated Load.” The Honorable Debbie-Anne Reese October 2, 2026 Page 2 MISO requests that…
printed heading · Topic match: Connecting load and generation
In addition, the Commission requested a detailed informational report on any proposals under consideration to address the issue of resource adequacy to serve new large loads, strongly encouraging new proposals to the extent necessary to address these concerns.10 The LARS process responds to this…
printed heading · Topic match: Connecting load and generation
The Honorable Debbie-Anne Reese October 2, 2026 Page 7 for the LARS Associated Load and has the responsibility to construct Network Upgrades (subject to applicable Tariff rules that are not changed by this filing).27 The fourth key participant is the entity that owns or controls the LARS Associated…
printed heading · Topic match: Connecting load and generation
A non-refundable fee of $250,000 must accompany the LARS Application and be paid by the LARS Associated Transmission Customer.32 Notably, MISO is establishing a “pre-submission coordination process” that LARS applicants must participate in prior to submitting a LARS Application.33 This coordination…
printed heading · Topic match: Connecting load and generation
Drake explained, “LARS studies will not include Interconnection Requests currently in the generator interconnection queue that do not have an executed GIA.”56 MISO has designed the LARS study this way to reduce the number of speculative projects in the modeling process.
printed heading · Topic match: Connecting load and generation
Drake explains, the LARS process enables MISO to optimize solutions for the transmission grid to reduce costs overall while also maintaining reliability.69 The LARS Application must identify a Commercial Operation Date for the Generating Facility and a Load In-Service Date for the LARS Associated…
A. LARS COMPLEMENTS OTHER COMPONENTS OF MISO’S LARGE LOAD
printed heading · Topic match: Connecting load and generation
Stakeholders have raised questions regarding how LARS generation will interact with generation already progressing through the ordinary Generator Interconnection Queue and the protections necessary to avoid adversely affecting existing Interconnection Customers.85 The transmission capacity headroom…
B. ADDRESSING FERC’S SHOW CAUSE ORDER: ELECTRICALLY PROXIMATE
printed heading · Topic match: Connecting load and generation
Drake explained in her testimony, “[u]ltimately, limiting the generation and LARS Associated Load to locations within the same LRZ ensures deliverability of the generation to the LARS Associated Load because it avoids potential capacity import / capacity export limitations for the individual LRZ…
PDF bookmark · Topic match: Connecting load and generation
DESCRIPTION OF PROPOSED TARIFF REVISIONS To implement the LARS process proposed herein, MISO is requesting approval of new Tariff provisions, as well as revisions to several existing provisions.94
A. Attachment X (Generator Interconnection Procedures).
printed heading · Topic match: Connecting load and generation
The proposed revisions are as follows: No changes shall be made to the LARS Application after submission and prior to the execution or the unexecuted filing of the LLGIA and MTEP approval for the LARS Associated Load except that a LARS Application that is deferred to the next available LARS Study…
Attachment X – Appendix 1 (Interconnection Request for a Generating
printed heading · Topic match: Connecting load and generation
These revisions include adding new options for interconnection requests and interconnection service to accommodate LARS, confirm that the amount of Interconnection Service cannot exceed 150% of the total amount of its LARS Associated Load, to describe the requirements for LARS Associated Load and…
Attachment X – Appendix 6 (Generator Interconnection Agreement)
printed heading · Topic match: Connecting load and generation
The proposed revisions are as follows: This LLGIA shall be terminated by Transmission Provider after giving Interconnection Customer ninety (90) Calendar Days advance written notice if: (1) the LARS Associated Load or a portion of the LARS Associated Load fails to achieve a Service Commencement…
E. Attachment FF (Transmission Expansion Planning Protocol)
printed heading · Topic match: Connecting load and generation
Both the Transmission Owner supporting the LARS Application and requesting to join LARS shall submit the required Large Load information to the MTEP Portal and an Interconnection Customer supporting the LARS Application and requesting to join LARS shall submit their Interconnection Request with the…
PDF bookmark · Topic match: Connecting load and generation
MISO also clarified several of the requirements of the LARS process including addressing the concerns on representation of the LARS generator/load pair within the parallel study processes.117 The stakeholder process also addressed the relationship between the load and generation, project-readiness…
PDF bookmark · Topic match: Connecting load and generation
Acceptance of LARS by the requested effective date is necessary to allow LARS to begin on this timeframe because the proposed rules require pre-submission coordination and for MISO to develop software to support the LARS Application prior to opening the first LARS Study Period.
COMMUNICATIONS MISO respectfully requests waiver of Rule 203(b)(3) of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.203(b)(3) (2026), to the extent necessary to permit the designation of more than two persons for service on behalf of MISO in this proceeding and requests all…
NOTICE AND SERVICE MISO has served a copy of this filing electronically upon all parties listed on the Commission’s eService list, and upon all Tariff customers, MISO Members, Member representatives of Transmission Owners and non-Transmission Owners, as well as all state commissions within the MISO…
CONCLUSION For all of the foregoing reasons, MISO respectfully requests that the Commission accept this filing and grant waiver of any Commission regulations the Commission deems applicable, but not specifically addressed above in order for the Commission to accept it as proposed.