EL26-69-000 · 2026-08-03 · New York Independent System Operator, Inc.

NYISO requests more time to answer the June 18 show cause order

Topics in the text: Filing procedure · Connecting load and generation · Reliability and curtailment

Responses and related views

No section-specific public response is linked for this document.

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Filing procedure

The NYISO respectfully requests that the Commission hold this proceeding in abeyance for the maximum period permitted by the Show Cause Order, i.e., for 90 days, until November 16, 2026.
Read this passage

I. Background

printed heading

I.
Read this passage

Background

printed heading · Topic match: Filing procedure

Background The Commission has determined that there are “a host of urgent challenges associated with providing the transmission service needed to serve the ongoing influx of large loads while 5 The Show Cause Order states that it will “consider [abeyance] requests from NYISO and/or the Transmission…
Read this passage

II. The NYISO Should Be Granted a 90-Day Abeyance to Pursue a Section 205 Filing

printed heading · Topic match: Filing procedure

The NYISO Should Be Granted a 90-Day Abeyance to Pursue a Section 205 Filing Through Its Shared Governance Process to Address the Show Cause Order in a Manner Tailored to the NYISO Region The NYISO recognizes that the concerns raised in the Show Cause Order are critically important and must be of…
Read this passage

III. The NYISO’s Plans for Developing and Submitting its Section 205 Proposal

printed heading · Topic match: Filing procedure

It is apparent that stakeholders endorse an abeyance and are prepared to work collaboratively and quickly to help refine the NYISO’s proposal.
Read this passage

IV. Request for Expedited Action by August 13 and for Shortened Comment Period

printed heading · Topic match: Filing procedure

Request for Expedited Action by August 13 and for Shortened Comment Period The NYISO respectfully requests that the Commission act on this motion by August 13, 2026.
Read this passage

V. Conclusion

printed heading

V.
Read this passage

Conclusion

printed heading · Topic match: Filing procedure

Conclusion For the foregoing reasons, the NYISO respectfully requests that the Commission issue an order by August 13, 2026, holding this proceeding in abeyance for 90 days until November 16, 2026.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Rensselaer, NY this 3rd day of August 2026. /s/ Alexander Morse Alexander Morse New York Independent System Operator, Inc. 10 Krey Blvd.