ER26-3380-000 · 2026-10-12 · PJM

Motion for Abeyance of PJM Interconnection, L.L.C. (ER26-3380-000 and EL26-108-000), holding the backstop paper hearing pending a new section 205 filing

Read topic-matched comments in ER26-3380

Topics in the text: Filing procedure · Credit and exit · Cost allocation

What the document says

PDF p. 1

PJM asks FERC to hold the paper hearing while it files a new section 205 proposal.

respectfully requests that the Commission hold the paper hearing proceedings, including any additional briefings, in this docket in abeyance pending resolution of PJM’s forthcoming filing PDF p. 1
Filed comments: Filing procedure

PDF p. 2

PJM asks FERC to hold the paper hearing while it files a new section 205 proposal.

PJM plans to submit a new FPA section 205 filing that addresses, inter alia, cost allocation issues, Transmission Owner exit responsibilities, and LSE collateral requirements as they relate to RBP by October 29, 2026. PDF p. 2
Filed comments: Cost allocation

Responses and related views

No section-specific public response is linked for this document.

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Filing procedure

Pursuant to Rule 212 of the Federal Energy Regulatory Commission’s (“Commission”) Rules of Practice and Procedure,1 PJM Interconnection, L.L.C. (“PJM”) respectfully requests that the Commission hold the paper hearing proceedings, including any additional briefings, in this docket in abeyance…
Read this passage Filed comments: Filing procedure

CERTIFICATE OF SERVICE

printed heading

CERTIFICATE OF SERVICE I hereby certify that I have on this 12th day of October served a copy of the foregoing upon all parties on the service list in these proceedings in accordance with the requirements of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010. /s/…
Read this passage