Order dismissing Eolian's request for rehearing and clarification of the June 18, 2026 CAISO show-cause order
Topics in the text: Filing procedure · Connecting load and generation · Cost allocation
What the document says
Unpaginated filing
FERC dismisses the rehearing requests because a show-cause order is not a final order.
The Commission determined only that the tariffs appear to be unjust, unreasonable, and unduly discriminatory or preferential and instituted an FPA section 206 show cause proceeding to reach a final determination on this issue. Source text
Unpaginated filing
FERC will not clarify the show-cause orders while the cases sit in abeyance.
We do not intend to provide clarification or guidance with respect to the Show Cause Order while the show cause proceeding is held in abeyance. Source text
Unpaginated filing
Eolian sought permanent load-limited interconnection for front-of-meter generation in five of six proceedings.
Eolian requests clarification or, in the alternative, rehearing to provide that electrically proximate generation may access permanent load-limited generator interconnection service Source text
Responses and related views
No section-specific public response is linked for this document.
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
Show Cause Order In the Show Cause Order, the Commission found that CAISO’s existing Tariff and/or the TO Tariffs appear to be unjust, unreasonable, or unduly discriminatory or preferential because they lack certain provisions related to large loads and co-located loads and instituted a show cause…Read this passage
Discussion
printed heading · Topic match: Filing procedure
Discussion Rule 713(b) of the Commission’s Rules of Practice and Procedure permits requests for rehearing “of any final decision or other final order in a proceeding.”[fn:18] A final order imposes an obligation, denies a right, or fixes some legal relationship as a consummation of the…Read this passage
Footnotes
Word notes · Topic match: Filing procedure
Operator Corp., 195 FERC ¶ 61,214, at PP 3, 31 (2026) (Show Cause Order); order granting rescission and abeyance requests, Cal.Read this passage