EL26-72-001 · 2026-09-21 · FERC

Order dismissing Eolian's request for rehearing and clarification of the June 18, 2026 ISO-NE show-cause order

Topics in the text: Filing procedure · Connecting load and generation · Cost allocation

What the document says

Unpaginated filing

FERC dismisses the rehearing requests because a show-cause order is not a final order.

We therefore dismiss the request for rehearing, which concerns a Commission action that is not final and that will be succeeded by further Commission action. Source text

Unpaginated filing

FERC will not clarify the show-cause orders while the cases sit in abeyance.

We do not intend to provide clarification or guidance with respect to the Show Cause Order while the show cause proceeding is held in abeyance. Source text

Unpaginated filing

Eolian sought permanent load-limited interconnection for front-of-meter generation in five of six proceedings.

Eolian requests clarification or, in the alternative, rehearing to provide that electrically proximate generation may access permanent load-limited generator interconnection service Source text

Responses and related views

No section-specific public response is linked for this document.

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Filing procedure

Show Cause Order In the Show Cause Order, the Commission found that ISO-NE’s existing Tariff appears to be unjust, unreasonable, or unduly discriminatory or preferential because it lacks certain provisions related to large loads and co-located loads and instituted a show cause proceeding pursuant…
Read this passage

Discussion

printed heading · Topic match: Filing procedure

Discussion Rule 713(b) of the Commission’s Rules of Practice and Procedure permits requests for rehearing “of any final decision or other final order in a proceeding.”[fn:18] A final order imposes an obligation, denies a right, or fixes some legal relationship as a consummation of the…
Read this passage

Footnotes

Word notes · Topic match: Filing procedure

Inc., 196 FERC ¶ 61,132, at PP 7-8 (2026) (Abeyance Order). [fn:12] Id.
Read this passage