ER26-3515-000 · 2026-09-23 · PJM

PJM answers comments and protests about interim resource adequacy service

Back to sections and commentary

PDF page 1

UNITED STATES OF AMERICA 
BEFORE THE 
FEDERAL ENERGY REGULATORY COMMISSION 
 
) 
PJM Interconnection, L.L.C.                      ) 
Docket No. ER26-3515-000 
) 
 
MOTION FOR LEAVE TO ANSWER AND ANSWER OF  
PJM INTERCONNECTION, L.L.C. 
The Base Residual Auction for the 2027/2028 Delivery Year procured insufficient 
capacity to meet the PJM Region Reliability Requirement.1  Thus, it is unclear whether, as 
of June 1, 2027, the PJM Region will have enough capacity to meet the longstanding 
reliability metric of one event in 10 years loss of load expectation.2   
The realities of the operational emergencies caused by the influx of New Large 
Loads endemic to PJM Interconnection, L.L.C. (“PJM”) demand a region-wide response 
at the wholesale level that simultaneously respects the jurisdictions of the 13 PJM states 
and the District of Columbia (together, “PJM states”) at the retail level.  PJM’s proposed 
Interim Resource Adequacy Service (“IRAS”) and Large Load Registry provide the needed 
tools to mitigate such operational emergencies in PJM, a footprint that includes the largest 
 
1 See 2027/2028 Base Residual Auction Report, PJM Interconnection, L.L.C. (Dec. 17, 2025), 
https://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-info/2027-2028/2027-2028-bra-
report.pdf [https://perma.cc/TA3Y-95AX] (“2027/2028 BRA Report”).  Capitalized terms not otherwise 
defined herein have the meaning as defined in the August 13 Filing, PJM Open Access Transmission Tariff, 
Reliability Assurance Agreement Among the Load Serving Entities in the PJM Region (“RAA”), and 
Amended and Restated Operating Agreement of PJM (“Operating Agreement”).  In the context of revisions 
proposed in this proceeding, the Tariff will be referred to as “proposed Tariff,” and the RAA will be referred 
to as “proposed RAA.”  PJM Interconnection, L.L.C., Proposal of PJM Interconnection, L.L.C. to Establish 
Interim Resource Adequacy Service and a Large Load Registry to Address System Reliability, Docket 
No. ER26-3515-000 (Aug. 13, 2026) (“August 13 Filing”). 
2 See PJM Interconnection, L.L.C., 194 FERC ¶ 61,049, at P 20 (“PJM states that . . . the proposed [Variable 
Resource Requirement (“VRR”)] Curve meets PJM’s Reliability Requirement, which targets a 1-in-10-year 
Loss of Load Expectation [(“LOLE”)] on a long-term average basis.”), order on reh’g, 196 FERC ¶ 61,007 
(2026).  PJM is still developing the 2027 Load Forecast and has yet to conduct the Third Incremental Auction 
for the 2027/2028 Delivery Year.  Thus, it is still unknown whether the PJM Region will be short of capacity 
heading into the Delivery Year.

PDF page 2

2 
concentration of data centers in the world sharing the grid with over 67 million people.  
IRAS provides the tools to address essential reliability and resource adequacy issues in 
PJM while simultaneously permitting large loads to interconnect to the system, providing 
a broad framework under which states can exercise their own regulatory authority and 
protecting existing customers from capacity price increases resulting from the effects of 
New Large Loads, consistent with the Statement of Principles Regarding PJM issued on 
January 16, 2026, by the National Energy Dominance Council (“NEDC”) and the 13 
governors of the PJM states,3 and the Ratepayer Protection Pledge, to which many 
intervenors in this proceeding are signatories.4   
 
 
 
3 Statement of Principles Regarding PJM, National Energy Dominance Council, 1 (Jan. 16, 2026), 
https://www.energy.gov/documents/statement-principles-regarding-pjm 
[https://perma.cc/35HJ-W56E] 
(“NEDC/PJM Governors’ Principles”).  The 13 state signatories are the governors of Delaware, Illinois, 
Indiana, Kentucky, Maryland, Michigan, New Jersey, North Carolina, Ohio, Pennsylvania, Tennessee, 
Virginia, and West Virginia.  Except for in reference to the “NEDC/PJM Governors’ Principles,” reference 
herein to the PJM states shall include the 13 state signatories and the District of Columbia. 
4 Ratepayer Protection Pledge, The White House (Mar. 4, 2026), https://www.whitehouse.gov/releases/ 
2026/03/ratepayer-protection-pledge/ [https://perma.cc/N8PH-K82T] (“Ratepayer Protection Pledge”).  The 
Ratepayer Protection Pledge requires, inter alia, that New Large Loads “will voluntarily negotiate new, 
separate rate structures with their utilities and relevant State governments wherever they build data centers,” 
commit to “build, bring, or buy the new generation resources and electricity needed to satisfy their new 
energy demands,” and “add more capacity that serves the broader public by increasing supply” in order to 
protect “Americans from higher prices” and commit to “[c]ontribut[e] to [e]lectric and [c]ommunity 
[r]esilience” by “coordinat[ing] with grid operators to contribute to a more reliable grid.”  IRAS reflects such 
coordination at a just and reasonable rate.  See also President Trump’s Ratepayer Protection Pledge Secures 
American 
AI 
Dominance, 
Protects 
Consumers, 
The 
White 
House 
(July 
23, 
2026), 
https://www.whitehouse.gov/releases/2026/07/president-trumps-ratepayer-protection-pledge-secures-
american-ai-dominance-protects-consumers/ [https://perma.cc/9VDB-B4EH] (“Ratepayer Protection Pledge 
Announcement”); Data centers pay their way. Ratepayers pay theirs., The White House, 
https://www.whitehouse.gov/ratepayer-protection-pledge/ [https://perma.cc/TC2X-AN5T] (last visited on 
Sep. 21, 2026) (“July 2026 Ratepayer Protection Pledge Update”) (identifying over 300 organizations that 
include over 250 utilities, cooperatives, and transmission cooperatives to municipal utilities and state 
associations, 44 data center developers, 7 Artificial Intelligence companies, and 23 governors that joined the 
Ratepayer Protection Pledge).

PDF page 3

3 
The IRAS proposal is a response to the following basic realities:  
• A region-wide response must guide and provide a framework for the 
PJM states’ various disparate approaches;   
• To maintain reliability and resource adequacy, PJM, as well as the 
states, must have key information about the location and 
characteristics of New Large Loads entering the region; and  
• Load Serving Entities (“LSEs”) serving New Large Loads, or the New 
Large Loads, must arrange for new capacity to meet their resource 
adequacy needs.  Absent such new capacity, New Large Loads must 
be flexible and, pursuant to PJM’s operational needs, reduce their 
energy demands when called upon during system emergencies.   
PJM stands behind the IRAS proposal as a just and reasonable and not unduly 
discriminatory or preferential response.  Protests calling for IRAS to be simply rejected 
outright ignore or fail to recognize the realities of the myriad risks that doing nothing 
presents.  Moreover, entities that seek rejection of the IRAS proposal on jurisdictional 
grounds conveniently overlook the fact that integrating large loads in a manner that 
(1) ensures reliability; (2) allows for these loads to interconnect to the system; and 
(3) protects existing ratepayers, is a responsibility shared between the states and PJM.  The 
Pennsylvania Governor’s office and other state intervenors acknowledge as much,5 while 
some opponents of the IRAS proposal would point to the division of authority between 
PJM and the states as grounds for eliminating the IRAS proposal altogether.6   
 
 5 PA Governor Answer at 2 (“First, protestors are wrong that PJM has veered beyond its jurisdiction.  PJM 
is squarely in its lane to operate the bulk power system in order to maintain system reliability . . . .”); see also 
NJ BPU Comments and Limited Protest at 3 (expressing that the “IRAS plan strikes an appropriate balance 
between state and federal jurisdictional divisions”); PIOs Limited Protest at 20 (The IRAS framework’s 
“design elements ensure that the IRAS Framework respects jurisdictional roles and is a just and reasonable 
approach to maintaining resource adequacy and protecting other customers.”). 
6 See, e.g., DCC Protest at 8-14; Google Protest at 8-11; IMM Protest at 3; Dominion Protest at 4.

PDF page 4

4 
The time to act is now.7  Indeed, the comments and protests in this proceeding show 
general conceptual support for IRAS from a wide range of interests—including states and 
their public utility and consumer advocacy groups,8 transmission owners,9 capacity 
 
7 Pursuant to Rules 212 and 213 of the Federal Energy Regulatory Commission (“Commission” or “FERC”) 
Rules of Practice and Procedure, 18 C.F.R. §§ 385.212, 385.213, PJM submits this Motion for Leave to 
Answer and Answer to comments and protests filed in response to PJM’s August 13 Filing.  Although 
Commission Rule 213(a)(2) does not generally permit answers to protests, the Commission permits answers 
for good cause shown, such as when an answer contributes to a more accurate and complete record or 
provides useful information that assists the Commission’s deliberative process.  PJM respectfully moves for 
leave to file this answer, as it will aid the Commission’s decision-making process by providing responses to 
the various comments and protests filed in response to PJM’s filings in this docket.  PJM therefore asks that 
the Commission accept this answer.  See, e.g., PJM Interconnection, L.L.C., 182 FERC ¶ 61,073, at P 13 
(2023) (“We accept the answers . . . because they have provided information that assisted us in our decision-
making process.”). 
8 OPSI Comments and Request for Clarification or to Sever at 1 (“OPSI is supportive of both identifying 
[New Large Loads] that have not brought capacity to meet their needs in an  [New Large Load] registry and 
the need to send a wholesale curtailment signal, equivalent to the  [New Large Load] quantity that does not 
have associated capacity, prior to entering into pre-emergency procedures.”); Ohio FEA Comments at 9 
(“PJM’s IRAS is a timely effort to confront reliability concerns caused by significant data center load growth 
in the region.  The proposed BYONC construct, the Large Load Registry, and the curtailment prioritization 
of certain loads when necessary to ensure reliability during emergency conditions will all require massive 
new coordination effort by PJM, states, EDUs, and LSEs.”); NJ BPU Comments and Limited Protest at 3 
(“The Board thinks PJM’s Proposal presents thoughtful consideration of the various stakeholder proposals 
and perspectives and thinks its final IRAS plan strikes an appropriate balance between state and federal 
jurisdictional divisions in the [FPA].  While there are certain elements of the Proposal that the Board does 
not support, these elements are not consequential to the foundational principles or procedures of IRAS and 
could be modified, or severed and rejected, without undermining the overall package reforms.  In some 
instances, the Board is simply asking for additional clarification from PJM.”); PA Governor Answer at 2 
(“IRAS is a critical measure to protect the region’s reliability and its ratepayers, consistent with the 
[NEDC/PJM Governors’ Principles] and the Ratepayers Protection Pledge.”), 5 (“PJM’s proposal of IRAS 
is necessary and appropriate in response to the severe challenges facing the region.”),  & 6 (“Governor 
Shapiro therefore urges the Commission to approve IRAS without delay, as timely implementation is critical 
to have IRAS in effect in time to avoid disruption of service for existing customers and to ensure its rate 
protective effects are in place before the next Base Residual Auction in December.”). 
9 Dominion Comments at 3 (“Dominion Energy Virginia generally supports the proposed framework for 
IRAS.  However, PJM’s approach for implementation as presented in the transmittal letter and the Tariff 
amendments raises concerns that it will not accommodate all business models and state regulatory 
frameworks within the PJM Region.”).

PDF page 5

5 
providers,10 large loads,11 LSEs,12 public interest organizations,13 and others.14  Although 
most who support IRAS also advocate for tweaks or other changes to the proposed 
framework, this should not be interpreted as dissatisfaction with IRAS as a whole.  Rather, 
requests for tweaks or elimination of certain elements reflect the fact that PJM has not 
 
10 Voltus Comments at 4 (“Voltus approves the IRAS proposal as a whole and supports PJM’s reintroduction 
of the RTO-wide CAM/IRAS incentive framework.”); NRG Comments and Limited Protest at 1-2 (“In 
general, [NRG Companies (“NRG”)] supports PJM’s efforts to provide certainty and clarity to market 
participants and New Large Loads that do not bring new supply into the PJM market.  NRG also supports 
PJM’s efforts to articulate rules pertaining to the curtailment of New Large Loads that do not bring new 
supply where such customers are curtailed before existing pre-emergency and emergency customers.”); SEIA 
Comments at 8 (“The IRAS proposal is another necessary response to PJM’s growing resource adequacy 
issues.”). 
11 ACORE Comments at 1 (“ACORE . . . supports the requirement for a new large load to contract for new 
capacity under BYONC to avoid being subject to potential curtailments under IRAS.  Such a requirement 
will strongly incent longer-term (at least 10 year) contracting with BYONC capacity by the large loads 
availing themselves of the IRAS BYONC provision.”); Sunrun Comments at 2-3 (“Sunrun respectfully 
requests that the Commission accept PJM’s filing subject to a discrete clarification or compliance filing 
confirming that verified PSA values reduce IRAS obligations, with appropriate measurement, verification, 
performance scoring, reconciliation, and no-double-counting safeguards, or, in the alternative, reject the 
filing without prejudice.”). 
12 AMP Limited Protest at 3 (“During [the IRAS CIFP] process, AMP endorsed – and continues to endorse 
– many of the core features of PJM’s IRAS proposal, including the Large Load Registry, offsetting IRAS 
obligations with BYONC, preserving retail regulatory authority over the determination of the end use loads 
ultimately subject to IRAS, and the exclusion of unhedged New Large Loads from the Variable Resource 
Requirement Curve.  In general, the PJM [IRAS] Filing proposes a reasonable framework to ‘connect and 
manage’ new large loads in the PJM region.”). 
13 PIOs Limited Protest at 1 (“[T]he IRAS Filing is an essential mechanism to protect customers in PJM from 
skyrocketing costs and degrading reliability caused by the forecasted rapid influx of large loads. PIOs believe 
the IRAS Filing could, if modified as described below, permanently resolve emerging resource adequacy 
shortfalls while respecting jurisdictional boundaries.”).  The Public Interest Organizations (“PIOs”) consist 
of Sierra Club, Natural Resources Defense Council, Environmental Law and Policy Center, Appalachian 
Voices, and the Center for Progressive Reform.  See also Appalachian Voices Comments at 1 (“PJM’s IRAS 
Proposal is an ambitious, yet narrowly tailored solution to address the primary issue facing the region: the 
outsized and unprecedent [sic] development of large loads and the unsustainable bill impacts they have 
created for residential ratepayers. . . . By applying only to Load Serving Entities serving New Large Loads, 
whose size and operational attributes create unique concerns for the bulk transmission system and resource 
adequacy, PJM’s IRAS Proposal does not unduly discriminate.  Nor does it inappropriately cross 
jurisdictional lines, but will instead complement efforts already underway to address large load integration 
in Virginia.”). 
14 Persistence Analytics Comments at 4 (“PAG supports PJM’s effort to establish a Large Load Registry and 
an interim framework that better aligns large-load integration with resource adequacy and ratepayer 
protection.  The proposal correctly recognizes that reliable implementation depends on more than collecting 
a headline [megawatt (“MW”)] value.”); Hans Royal Comments at 1 (“I support approval of the Interim 
Resource Adequacy Service (IRAS), the Large Load Registry, and the Bring Your Own New Capacity 
(BYONC) provisions.  The July 27 Board framework followed a substantial stakeholder process and places 
the reliability obligation where it belongs: on new load that enters without bringing new supply, not on 
customers already served by the system.”).

PDF page 6

6 
proposed IRAS as an inseverable “package,” but instead—in the interest of administrative 
efficiency and acknowledging the urgency with which PJM must act15—affirmatively 
stated that each element is modifiable and severable so long as consistent with PJM’s 
overarching objectives.16  Although PJM is amenable to a certain degree of severability of 
the component parts of IRAS so as to provide the Commission with a degree of flexibility, 
this does not mean, however, that PJM is waiving its Federal Power Act (“FPA”) 
section 205 rights, 16 U.S.C. § 824d, to a timely response from the Commission with 
respect to this proposal, consistent with section 205 of the FPA.  Moreover, the question 
before the Commission, as in all section 205 proceedings, is not whether the proposal is 
the sole means of achieving its stated ends but whether it is a just and reasonable proposal, 
among the many that could be offered in protests, to address the critical reliability issue 
that PJM has detailed in the August 13 Filing.17   
Given PJM’s declaration that it is not proposing a package to be accepted or 
rejected as a whole, elements of the August 13 Filing can stand on their own and should be 
timely approved as just and reasonable.  Most significantly, PJM highlights the importance 
of timely Commission approval of the following discrete elements:  the Large Load 
Registry,18 the definition of Large Load,19 and the general obligation in proposed RAA, 
 
15 August 13 Filing, Transmittal Letter at 9. 
16 August 13 Filing, Transmittal Letter at 9-11, 121-125. 
17 See, e.g., Cities of Bethany, 727 F.2d 1131 (D.C. Cir. 1984) (“FERC has interpreted its authority to review 
rates under [the FPA] as limited to an inquiry into whether the rates proposed by a utility are reasonable—
and not to extend to determining whether a proposed rate schedule is more or less reasonable than alternative 
rate designs.” (citing In re Pub. Serv. Co. of Ind., Inc., 1976 F.P.C. LEXIS 1334 (Mar. 10, 11976)); Midwest 
Indep. Transmission Sys. Operator, Inc., 127 FERC ¶ 61,109, at P 20 (2009) (“It is well established that there 
can be more than one just and reasonable rate . . . .” (citing Am. Elec. Power Serv. Corp. v. Midwest Indep. 
Transmission Sys. Operator, Inc., 122 FERC ¶ 61,083, at P 88, order on reh’g, 125 FERC ¶ 61,342 (2008))).   
18 Proposed Tariff, Attachment DD-4, section VII. 
19 Proposed RAA, Article 1, Definitions – Large Load (“‘Large Load’ shall mean end-use customer(s) load 
that has a cumulative peak load of 50 [MW] or greater at a single electrical site behind one or more points of

PDF page 7

7 
section 7.8 that LSEs bring new capacity in an amount that equals or exceeds its New Large 
Loads’ peak load.20  Each of these elements are foundational to PJM’s ability to put in 
place an effective response to the rapidly increasing large load demand in a manner that 
does not harm overall region-wide reliability.  
The PJM Region and other regions have already experienced some of the 
challenging operational issues emblematic of the high volume of new large loads the PJM 
Region is facing today.21  Without IRAS, the reliability concerns may soon become even 
more acute.  Therefore, to ensure PJM has the tools to manage the region-wide reliability 
issues presented by the influx of large loads, the key operational tools noted above must be 
in place by June 1, 2027.   
At bottom, IRAS is a just and reasonable means of managing the influx of New 
Large Loads into the PJM Region while maintaining resource adequacy, reliability, and 
affordability in a manner that respects the divide between state and federal authorities, 
provides a framework that accommodates and in fact welcomes further state action, and 
 
interconnection, where for configurations involving multiple affiliated load facilities or multiple points of 
interconnection with affiliated load facilities behind them, all affiliated load facilities within a one-mile radius 
will be considered a single electrical site as further described in the PJM Manuals.”).  
20 The revisions to the RAA clarify an LSE’s obligation to bring new capacity in an amount that equals or 
exceeds its New Large Loads’ peak load or be subject to load reduction requests during Emergencies prior 
to Pre-Emergency Load Management Response (“Pre-Emergency Load Management”).  Proposed RAA, 
section 7.8. 
21 Recently, for example, “a July 22 event saw nearly 4,000 MW of data center load trip offline unexpectedly 
in Virginia.  It was the largest such event in PJM history.”  PJM interconnection, L.L.C., PJM, Dominion 
Review Large Load Transfer Event, PJM Inside Lines (Aug. 11, 2026), https://insidelines.pjm.com/pjm-
dominion-review-large-load-transfer-event/ [https://perma.cc/55S2-LEWB].   Also, in recent months, PJM 
has repeatedly requested FPA 202(c) orders from the Department of Energy to obtain permission to dispatch 
backup generation, often those of data centers, in excess of environmental restrictions to manage emergency 
conditions due to hot weather conditions and the threats that extended heat poses to the reliability of the 
interstate bulk power system.  As PJM informed the Department of Energy, on July 2, 2026, during the 
evening peak, “PJM was close to having to trigger the backup generator emergency action, if certain system 
contingencies were to have arisen.”  Request for Extension of Existing Emergency Order No. 202-26-33 
Issued Pursuant to Federal Power Act, Section 202(c), PJM Interconnection, L.L.C. (July 3, 2026), 
https://www.energy.gov/documents/pjms-202c-extension-application-202-26-33a [https://perma.cc/RS4E-
F8EK].

PDF page 8

8 
avoids disrupting existing commercial arrangements.  As discussed below, none of the 
protests or comments submitted in this matter22 undermine the fact that the proposals set 
forth in PJM’s August 13 Filing are just and reasonable and not unduly discriminatory or 
preferential revisions.23  Given the importance of having tools to manage the reliability 
issues presented by the new large loads that have not yet brought new capacity by June 1, 
2027, PJM respectfully requests that, to the extent the Commission rejects any element of 
this filing, the Commission either direct prescriptive changes to be implemented on 
compliance or provide guidance to aid PJM and stakeholders to develop a just and 
reasonable approach.  The issues outlined herein are simply too important, and the timing 
too critical, for PJM and its stakeholders to have to guess in such a case as to what the 
Commission would find acceptable.   
For the reasons set forth below and in PJM’s August 13 Filing, the proposed Tariff 
and RAA changes should be accepted, and made effective, no later than October 12, 2026, 
as requested.  A timely Commission order will allow PJM to proceed with the removal of 
Eligible New Large Loads from the VRR Curve used in the Base Residual Auction 
associated with the 2029/2030 Delivery Year scheduled to commence this December. 
I. 
ANSWER 
A. 
There Is Overwhelming Support for PJM’s Proposed Large Load 
Registry. 
The proposed Large Load Registry received overwhelming support from PJM 
stakeholders and commenters in this proceeding.  In particular, stakeholders supported the 
 
22 See Appendix A, Protests, Comments, Requests for Clarification, and Answers Filed to Date attached 
hereto.  
23 While PJM’s answer does not address every argument raised by intervenors, silence on any argument 
should not be deemed as acceptance of the arguments raised.

PDF page 9

9 
fact that it is needed to ensure appropriate cost allocation, and that it would provide the 
transparency necessary to identify large loads.24  The Large Load Registry is designed to 
provide PJM with critical information affecting operations, transmission planning, and 
markets.  For example, and as recognized by the Commission, PJM must have visibility 
into where Large Loads will be located so as to be prepared for operational issues 
distinctive to Large Loads that may arise, including protecting the transmission system 
from large loads unexpectedly dropping off or coming on to the grid.25  There have been 
severe incidents of large loads tripping offline in PJM, which could have led to significant 
outages had PJM not been able to respond in time.26  Such information will also be 
invaluable for states and other planning entities.  The Commission should accept the Large 
Load Registry as just and reasonable, based on the obvious value it provides in supporting 
the transparent development of large loads independent of whether it is part of IRAS as a 
whole. 
Notably, none of the comments received regarding the Large Load Registry 
outright oppose it.  Rather, as discussed below, many commenters state that they support 
the Large Load Registry and offer comments that do not undermine the concept as a whole, 
but rather seek to modify limited aspects of it.27 
 
24 August 13 Filing, Transmittal Letter at 30-31; see e.g., id. at 30 (“[I]n response to a poll of stakeholders 
posted on July 16, 2026, 82% of the 66 stakeholder respondents agreed that a Large Load registration 
requirement is necessary to ‘ensur[e] that costs of new capacity required to serve new large load should be 
allocated to data centers.’”). 
25 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at P 212 n.444 (2025) (“December 2025 Show Cause 
Order”) (citing PJM Interconnection, L.L.C., Answer of PJM Interconnection, L.L.C., Docket 
Nos. EL25-49-000, et al., at 44 (Mar. 24, 2025)). 
26 See James Downing, Data Centers’ Reliability Impacts Examined at FERC Meeting, RTO Insider (Apr. 17, 
2025), 
https://www.rtoinsider.com/103130-ferc-gets-update-data-center-reliability/ 
[https://perma.cc/DU3R-PR9B] (discussing 1,500 MW drop from Louden County data center tripping 
offline). 
27 East Kentucky Power Cooperative (“EKPC”) complains that PJM “overstated” the support it received from 
stakeholders because, as PJM understands the concern, the support for a registry was somehow contingent

PDF page 10

10 
Several parties, for example, assert that states and state consumer advocates should 
have broader, less-restricted access to the Large Load Registry.  The Pennsylvania Public 
Utility Commission (“PA PUC”) and the Organization of PJM States, Inc. (“OPSI”), for 
example, each ask the Commission to ensure that states have information sufficient to 
determine how curtailment should be implemented and how costs should be calculated and 
allocated.28  As discussed in the transmittal letter, PJM proposed to follow its existing rules 
for disseminating confidential information—as set forth in the Operating Agreement, and 
accordingly, the information contained in the Large Load Registry will be available to 
Authorized Commissions, among others, subject to confidentiality requirements.29  
“Authorized Commission,” in turn, is currently defined to include state public utility 
commissions, as well as organizations thereof.30 It is therefore entitled to have the same 
access as others permitted to do so under PJM’s proposal.  The Public Utilities Commission 
of Ohio’s Office of the Federal Energy Advocate (“Ohio FEA”), in fact, supports the Large 
Load Registry, recognizes that states will have access to it, and asserts that there should be 
 
upon the IRAS obligations being borne by LSEs, whereas now the Electric Distributor must “interpret the 
registry and or seek guidance from a [Relevant Electric Retail Regulatory Authority (“RERRA”)] to 
determine which loads it must curtail.”  See EKPC Limited Protest at 5-6 & n.22.  While it is unclear what 
the exact concern is, the obligation to provide information to PJM for the Large Load Registry is borne by 
the LSE, not the Electric Distributor directly, although PJM would welcome information provided by an 
Electric Distributor.  See proposed RAA, Schedule 11, section B.1(b) (“The Parties [i.e., LSEs] acknowledge 
that information related to the development and maintenance of the Large Load Registry may be obtained by 
the Office of the Interconnection from Electric Distributors in accordance with the provisions of the 
Operating Agreement and the Tariff.”).  Regardless, PJM disputes EKPC’s characterization as there was 
indeed broad support for a registry as evidenced in the August 13 Filing. 
28 PA PUC Comments at 7; OPSI Comments and Request for Clarification or to Sever at 7. 
29 August 13 Filing, Transmittal Letter at 28 (citing proposed RAA, Schedule 11, section B.1(d) 
(“Information maintained in the Large Load registry may be available to Authorized Commissions, 
Transmission Owners, Electric Distributors, LSEs, the Market Monitoring Unit, and FERC subject to 
appropriate data protection safeguards required by Operating Agreement, section 18.17.”)). 
30 See PJM Operating Agreement, section 1, Definitions A-B (“‘Authorized Commission’ shall mean (i) a 
State public utility commission that regulates the distribution or supply of electricity to retail customers and 
is legally charged with monitoring the operation of wholesale or retail markets serving retail suppliers or 
customers within its State or (ii) an association or organization comprised exclusively of State public utility 
commissions described in the immediately preceding clause (i).”).

PDF page 11

11 
no concerns with confidentiality standards as state commissions access this information.31  
To the extent that information submitted to the Large Load Registry is designated as 
confidential, the Authorized Commission may be required to adhere to the process 
necessary to access this information pursuant to Operating Agreement, section 18.17.4, 
which is a pre-existing section.32  This proposal does not recommend any new restrictions, 
nor are any necessary, as this matter was resolved by the Commission some years ago when 
it approved the sharing of information with Authorized Commissions.33   
JCA and the Office of the Ohio Consumers’ Counsel (“OCC”) both argue that state 
consumer advocates are wrongfully excluded from the list of entities that have access to 
the Large Load Registry.34  The Large Load Registry is expected to collect information 
which may be confidential, commercially sensitive, or may implicate infrastructure 
security concerns.  PJM must therefore only permit access to this registry to as small a 
universe of entities as possible, while still making sure it is available to those who require 
access to implement their responsibilities, as well as operational and planning needs.35  
 
31 Ohio FEA Comments at 5-6. 
32 Operating Agreement, section 18.17.4 (setting forth conditions under which PJM will disclose confidential 
information to an Authorized Commission). 
33 See PJM Interconnection, L.L.C., 107 FERC ¶ 61,322 (2004).  Joint Consumer Advocates (“JCA”) 
similarly argue more broadly that the proposed confidentiality provisions, which point to existing Operating 
Agreement, section 18.17.4, may prove too onerous, thereby preventing states from accessing Large Load 
Registry information in a timely manner.  JCA Protest and Comments at 35-37.  However, they also concede 
that “changes to the Tariff process for handling confidential information is beyond the scope of this 
proceeding.”  JCA Protest and Comments at 37.  Further, while OPSI and PA PUC express concerns 
regarding access to the Large Load Registry, they support it and did not express any specific concerns 
regarding PJM’s current process for managing access to confidential information. 
34 JCA Protest and Comments at 33-35; OCC Protest at 9, 20-23.  OCC further argues that it is unduly 
discriminatory to exclude state consumer advocates from the list.  OCC Protest at 23.  There is no undue 
discrimination here because, among other things, state consumer advocates are not similarly situated to any 
of the other entities who require access to the Large Load Registry to meet their legal obligations to regulate 
retail or wholesale rates.  See N.Y. Indep. Sys. Operator, Inc., 162 FERC ¶ 61,124, at P 10 (2018) (“To say 
that entities are similarly situated does not mean that there are no differences between them; rather, it means 
that there are no differences that are material to the inquiry at hand.”). 
35 This is consistent with the Commission’s findings when it accepted PJM’s definition of “Authorized 
Commission.”  In response to comments that confidential information should also be provided to consumer

PDF page 12

12 
Nevertheless, PJM reiterates its commitment to publicly post aggregated data regarding, 
among other things, areas in PJM with the greatest concentrations of large loads.36  This 
level of detail is appropriate for public use, including by state consumer advocate offices, 
in aiding transparency into the growth of large loads in the PJM footprint.   
JCA asserts that PJM’s proposed Tariff language should affirmatively state that 
PJM will validate the information provided for the Large Load Registry.37  PJM fully 
intends to review the information, and when read in context, proposed RAA, Schedule 11, 
section B.1(c) conveys that PJM will coordinate with the “applicable Transmission Owner 
and Electric Distributor as needed.”38  
Old Dominion Electric Cooperative (“ODEC”) asks PJM to clarify which entity is 
obligated to provide information to PJM for the Large Load Registry.39  Assuming the 
obligated entity is the LSE, ODEC next asserts that there is certain information identified 
in proposed RAA, Schedule 11, section B.1(a) that LSEs may not have available to them, 
 
advocates’ offices and joint action agencies, the Commission rejected these concerns, stating that “[t]he 
original purpose of establishing these provisions was to provide access to confidential information to state 
commissions who have the regulatory and legal authority to monitor retail electric markets within the state.  
The change proposed by these commenters would open up the possibility of many other state agencies being 
able to receive confidential information, which is not the purpose of the Commission's directive to PJM.”  
PJM Interconnection, L.L.C., 107 FERC ¶ 61,322, at P 22. 
36 See August 13 Filing, Transmittal Letter at 42-43, 48; see also id. at 42-43 (“[T]o aid transparency to the 
public, PJM will post aggregated data from the Large Load Registry, which will be aggregated by Electric 
Distributor zone/area, where possible and in a manner consistent with existing confidentiality protections.  
Aggregating the data by zone/area supports transparency by putting stakeholders on notice of the zones/areas 
that have been assigned IRAS in a given Delivery Year, that may be potentially required to reduce load under 
certain emergency conditions pursuant to IRAS, while maintaining the confidentiality of the data.”). 
37 See JCA Comments and Protest at 31-33 (citing proposed RAA, Schedule 11, section B.1(c) (“The Office 
of the Interconnection may review information and coordinate with the applicable Transmission Owner and 
Electric Distributor as needed, regarding the validity of the information provided . . . .”) (emphasis added)). 
38 JCA Protest and Comments at 31-33 (citing proposed RAA, Schedule 11, section B.1(c) (“The Office of 
the Interconnection may review information and coordinate with the applicable Transmission Owner and 
Electric Distributor as needed, regarding the validity of the information provided . . . .” (emphasis added)). 
39 ODEC Comments at 3-4.

PDF page 13

13 
and that failure to provide that information may subject them to enforcement action.40  
First, PJM clarifies that it is indeed the LSE serving a Large Load that is obligated to 
provide PJM with the information for the Large Load Registry.41  Second, PJM agrees there 
may be instances where an LSE may not have all of the information required for the Large 
Load Registry readily available.  That is why the proposed RAA language contemplates 
that Electric Distributors may provide the information for the Large Load Registry on 
behalf of their relevant LSEs, and that PJM will have the ability to reach out to Electric 
Distributors and large loads as necessary to supplement information provided by LSEs.42     
The PJM Industrial Customer Coalition (“PJMICC”) and the Industrial Energy 
Consumers of America (“IECA”) both argue that the Large Load Registry should not 
include existing Large Loads, that they must be clearly exempted from all IRAS obligations 
if they are included, and that any data submitted must be protected.43  PJM discussed this 
issue in great detail in its transmittal letter for its IRAS proposal.44  There, PJM explained 
that, in fact, including existing Large Loads in the Large Load Registry will help ensure 
that PJM is able to clearly identify which Large Loads, i.e., New Large Loads, are subject 
to IRAS requirements.  In particular, the in-service date is a critical piece of information, 
 
40 ODEC Comments at 4-6. 
41 See proposed RAA, Schedule 11, section B.1(a) states that “[e]ach Party shall submit, or cause to be 
submitted, to the Office of the Interconnection the following information, as may be further described in the 
PJM Manuals, related to each Large Load served by the Party,” and a Party to the RAA is an LSE, as stated 
in the Preamble to the RAA (“WHEREAS, each Party to this Agreement is a Load Serving Entity within the 
PJM Region”) and the RAA itself is titled “Reliability Assurance Agreement Among Load Serving Entities 
In The PJM Region” (emphasis added).  The RAA includes a definition of “Party” that is broader than just 
LSEs and PJM will continue to evaluate this.   
42 See proposed RAA, Schedule 11, section B.1(b) (“The Parties [i.e., LSEs] acknowledge that information 
related to the development and maintenance of the Large Load Registry may be obtained by the Office of the 
Interconnection from Electric Distributors in accordance with the provisions of the Operating Agreement and 
the Tariff.”). 
43 PJMICC Comments at 4, 5-8; IECA Comments at 1-2. 
44 August 13 Filing, Transmittal Letter at 38-40.

PDF page 14

14 
because IRAS only applies to New Large Load which, pursuant to the proposed definition, 
go into service after June 1, 2027 (including incremental load).45  Regardless, the 
information to be gathered through the Large Load Registry has benefit and usefulness 
outside of the IRAS context.  Indeed, as PJM explained in the August 13 Filing, PJM must 
have visibility into the full spectrum of all Large Loads in its footprint in order to properly 
manage its system and ensure reliability.46  Further, the security and confidentiality 
safeguards are sufficiently robust, and indeed are consistent with existing confidentiality 
requirements currently contained in the Operating Agreement, as discussed above.47   
B. 
PJM’s Proposed Definition of Large Load Is Consistent with Commission 
Guidance and Is Just and Reasonable. 
PJM’s proposed definition of Large Load, as discussed extensively in its proposal, 
is just and reasonable and aligned with Commission guidance as set forth in the Show 
Cause proceeding, which in turn was based on the record in the Department of Energy’s 
Advance Notice of Proposed Rulemaking (“DOE ANOPR”) proceeding.48 
Despite this alignment with the Commission’s guidance, several parties argue that 
the 50 MW threshold is unsupported or should be changed.49  The Independent Market 
Monitor (“IMM”) adds that the 50 MW threshold will exclude data centers with peak loads 
 
45 August 13 Filing, Transmittal Letter at 38-39 (citing proposed definition of New Large Load). 
46 See August 13 Filing, Transmittal Letter at 41-42. 
47 Operating Agreement, section 18.17.  FirstEnergy Service Company (“FirstEnergy”) asserts that the list of 
information to be provided to PJM by LSEs should not be finalized until the pro forma transmission service 
agreement contemplated in the broader Show Cause proceeding is finalized.  FirstEnergy Limited Protest and 
Comments at 11-12 (citing PJM Interconnection, L.L.C., 196 FERC ¶ 61,129 (2026)).  PJM is unclear about 
the connection between the two issues as framed by FirstEnergy, since any transmissions service agreement 
does not appear to have any bearing on the information that will be contained in the proposed Large Load 
Registry.  To the extent that any connection arises, PJM can address any need to revisit the list of information 
at that time. 
48 August 13 Filing, Transmittal Letter at 31-32. 
49 See PJMICC Comments at 4; IECA Comments at 2; Talen Protest at 9-10.

PDF page 15

15 
less than that amount.50  PJMICC and IECA further argue that the “baseline” MW level for 
existing Large Loads should be established, such that only the net 50 MW above that 
baseline would trigger IRAS requirements.51  As mentioned, PJM discussed the support for 
the 50 MW threshold, specifically finding that 50 MW was entirely in keeping with what 
was contemplated by the Commission, as discussed in the DOE ANOPR proceeding.52  No 
information presented by any of these parties renders PJM’s proposed threshold unjust and 
unreasonable.  Further, PJM disagrees that there should be any “baseline” established 
above which only the net MW would be considered for IRAS purposes.  Since PJM has 
proposed that 50 MW is the appropriate threshold necessary for purposes of tracking Large 
Loads and ensuring that PJM has visibility into them in order to ensure reliability, it would 
be entirely contradictory to simply ignore any MW that may have existed at a Large Load 
before an additional 50 MW were added.  Given the reliability and operational purposes of 
the Large Load Registry, PJM must have visibility into all Large Loads for registry 
purposes to ensure reliability and facilitate proper planning for the region, and existing 
Large Loads should be treated no differently. 
 
50 IMM Comments at 29-31. 
51 PJMICC Comments at 10-11; IECA Comments at 2. 
52 See PJM Interconnection, L.L.C., 195 FERC ¶ 61,211, at P 58 (2026) (“June 2026 Order to Show Cause”) 
(citing Interconnection of Large Loads to the Interstate Transmission System, Motion to Intervene and 
Comments of DTE Electric Company,  Docket No. RM26-4-000, at 3, 17-19 (Nov. 21, 2025) (recommending 
a threshold of an amount between 50 MW to 100 MW); Interconnection of Large Loads to the Interstate 
Transmission System, Comments of the People of the State of Illinois by the Office of the Illinois Attorney 
General, Docket No. RM26-4-000, at 7 (Nov. 21, 2025) (supporting a 20 MW or 50 MW threshold and 
consideration of other factors, such as voltage level); Interconnection of Large Loads to the Interstate 
Transmission System, Comments of ITC, Docket No. RM26-4-000, at 3 (Nov. 21, 2025) (recommending a 
threshold of between 50 MW to 100 MW); Interconnection of Large Loads to the Interstate Transmission 
System, Comments of the Nebraska Power Board in Response to the Invitation to Submit Comments in the 
Advance Notice of Proposed Rulemaking, Docket No. RM26-4-000, at 4 (Nov. 21, 2025) (proposing a 
50 MW threshold); Interconnection of Large Loads to the Interstate Transmission System, Initial Comments 
of the New Mexico Public Regulation Commission, Docket No. RM26-4-000, at 5 (Nov. 21, 2025) 
(proposing a 50 MW threshold)).

PDF page 16

16 
EKPC, Ohio Energy Leadership Council (“Ohio ELC”), and FirstEnergy contend 
that PJM should differentiate between data center Large Loads/computational Large Loads 
and other types of Large Loads, such as manufacturing or industrial loads.53  PJM 
implemented the approach the Commission set forth in the June 2026 Show Cause Order, 
and as described in the August 13 Filing, adjusted the definition consistent with regional 
practices.54  These entities have shown no basis for deviating from the Commission’s 
approach of treating data center or computational, manufacturing, industrial, or other types 
of Large Load the same.55   
C. 
There Is Widespread Support to Establish a Policy that New Large Loads 
Must Bring New Capacity. 
Based on the filings in this proceeding, there is widespread support for the notion 
that all LSEs in PJM serving New Large Loads via Network Integration Transmission 
Service (“NITS”) must bring new capacity to satisfy the resource adequacy needs of such 
New Large Load.56  Adoption of this policy was a key element of the August 13 Filing.57  
Specifically, PJM proposed to include as the first sentence of proposed RAA, section 7.8: 
 
53 EKPC Limited Protest at 25-27; Ohio ELC Comments and Limited Protests at 3-8; FirstEnergy Limited 
Protest and Comments at 10-11. 
54 See August 13 Filing, Transmittal Letter at 31-36. 
55 PJMICC and IECA both assert that PJM should clarify that its measurement of “peak load” aligns with 
retail behind-the-meter generation rules approved by the Commission. PJMICC Comments at 14; IECA 
Comments at 3.  This issue is outside the scope of this proceeding, and in any event, would be ultimately 
decided in conjunction with state retail authorities. 
56 Buckeye Limited Comments at 2; OPSI Comments and Request for Clarification or to Sever at 6. 
57 See August 13 Filing, Transmittal Letter at 3-4, 21-22.

PDF page 17

17 
Effective June 1, 2027, each LSE that desires to provide Network 
Transmission Service to support New Large Loads must designate 
one or more Generation Capacity Resources or Capacity Storage 
Resources that had not cleared an RPM Auction as Network 
Resource(s) in a cumulative amount that equals or exceeds the 
LSE’s New Large Load’s peak load (in MW) as reported in the 
Large Load Registry pursuant to RAA, Schedule 11 or such New 
Large Load may be subject to load reduction requests during 
Emergencies prior to Pre-Emergency Load Management Response. 
PJM proposed to include this policy in the RAA, i.e., the “Reliability Assurance 
Agreement Among Load Serving Entities in the PJM Region.”  As its title makes clear, the 
RAA establishes the policy and methods for addressing resource adequacy.  All LSEs in 
PJM must sign the RAA and are bound by its terms and conditions.  By including this 
sentence in RAA, Article 7, PJM intends to establish the policy that New Large Loads must 
bring new capacity or PJM may request that they reduce their energy consumption to 
alleviate emergency conditions.58   
As PJM explained,59 this policy is consistent with the Ratepayer Protection Pledge 
introduced in March 202660 and recently expanded in July 2026,61 which assures that New 
 
58 To be clear, this is designed as a condition of New Large Loads interconnecting and taking Network 
Transmission Service.  To the extent the New Large Load takes one of the alternative transmission services 
being addressed through other proceedings, this policy would not immediately apply.  In fact, as Mr. 
Christopher Pilong explained, this policy inherently would not apply to New Large Loads being served via 
non-firm transmission services, as they would have been curtailed prior to this stage of addressing emergency 
conditions.  See August 13 Filing, Affidavit of Christopher Pilong on Behalf of PJM Interconnection, L.L.C. 
(Attachment C) ¶ 12 (“Pilong Aff.”). 
59 See August 13 Filing, Transmittal Letter at 4-5. 
60 Ratepayer Protection Pledge.  
61 See Ratepayer Protection Pledge Announcement; July 2026 Ratepayer Protection Pledge Update 
(identifying over 300 organizations that include over 250 utilities, cooperatives, and transmission 
cooperatives to municipal utilities and state associations, 44 data center developers, 7 Artificial Intelligence 
companies,  and 23 governors that joined the Ratepayer Protection Pledge.  The 38 data center developers 
include: Aligned Data Centers, LLC; Amazon.com, Inc.; Applied Digital Corporation; Beale Infrastructure 
Group, LLC; Bitdeer Technologies Group; CleanSpark LLC; Cloud HQ LLC; Cologix, Inc.; Compass 
Datacenters, LLC; Core Scientific, Inc.; CoreWeave, Inc.; Corscale, LLC; Crusoe Technologies LLC; 
CyrusOne, Inc.; DataBank Holdings, Ltd.; Digital Realty Trust, Inc.; Diode Ventures, LLC, a Black & Veatch 
company; EdgeConnex Inc.; EdgeCore Digital Infrastructure (d/b/a EdgeCore Internet Real Estate, LLC); 
Equinix, Inc.; Google LLC (“Google”) (d/b/a Alphabet Inc.); Iron Mountain Incorporated; Meta Platforms, 
Inc.; Keel Infrastructure Corp.; Lambda; Microsoft Corporation; Nebius Group N.V.; NTT Global Data

PDF page 18

18 
Large Loads will, at a minimum, “build, bring, or buy the new generation resources and 
electricity needed to satisfy their new energy demands, paying the full cost of those 
resources whether by building, or buying from, new or otherwise additive power plants” 
because it “advances self-sufficiency and protects Americans from higher prices.”62  
Indeed, this policy furthers the federal policy stated in the Ratepayer Protection Pledge by 
requiring action consistent with the pledge, and incentivizes New Large Loads to invest in 
new Capacity Resources to meet their needs and—importantly—protect native loads from 
the cost increases driven by New Large Loads.  Commission rejection of this statement of 
policy in the RAA would effectively bring into question, if not displace, the commitments 
that large loads and LSEs have already made by signing the Ratepayer Protection Pledge.  
D. 
IRAS Divides Authority over Responses to an Interim Resource Adequacy 
Event in a Manner Consistent with Commission Jurisdiction. 
The IRAS framework is deliberately designed with the relevant Commission 
precedent on how “issues” related to large load additions “require the involvement of both 
federal and state actors”63 in mind.  Ultimately, “[s]tripped of embellishment, the facts are 
straightforward,” as the Pennsylvania Governor’s Office explains:  
[U]nder IRAS, PJM can only direct “a MW quantity of load 
reduction to the relevant Electric Distributer zone(s)/area(s)”—it 
neither targets nor directs specific retail customers to be subject to 
curtailment, nor compels or restricts the authority of the retail 
authority to prioritize among the retail customers that must be 
 
Centers (d/b/a NTT DATA, Inc.); OpenAI, L.L.C.; Oracle Corporation; Oppidan Connect Data Centers (d/b/a 
Oppidan Investment Company); Prologis, Inc.; Quality Technology Services, LLC; Rowan Digital 
Infrastructure Pty. Ltd.; Skybox Datacenters, LLC; Skylar Opportunities LLC; STACK Infrastructure, Inc.; 
Starwood Digital Ventures (d/b/a Starwood Capital Operations, LLC); Stream Data Centers, L.P.; Switch, 
Inc.; T5Data Centers, LLC; TA Realty LLC; Vantage Data Centers Management Company, LLC; and x.AI 
LLC). 
62 Ratepayer Protection Pledge. 
63 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115, at P 66, order directing compliance, December 2025 
Show Cause Order, 193 FERC ¶ 61,217.

PDF page 19

19 
curtailed in order to meet the required MW quantity of bulk load 
reduction and safeguard the reliability of the grid.64 
Likewise, the PIOs comment that IRAS “relies on a clear division of labor between PJM, 
Electric Distributors, LSEs, state authorities, and end-use customers.  PJM proposes new 
rules that directly affect wholesale market prices and grid reliability.  Even if those federal 
rules affect retail customer behavior, they are legally sound.”65  The New Jersey Board of 
Public Utilities (“NJ BPU”) similarly states that IRAS “strikes an appropriate balance 
between state and federal jurisdictional divisions in the Federal Power Act” and that it 
“falls squarely within PJM’s authority in maintaining resource adequacy at the wholesale 
level.”66  
1. 
IRAS is targeted expressly at improving PJM’s wholesale market by 
supporting resource adequacy and the reliability of the PJM Region.  
Some protestors allege that the IRAS framework exceeds the Commission’s 
jurisdictional boundary between wholesale and retail capacity markets, “because it targets 
particular retail customers[,]” i.e., large loads.67  Protestors’ claims are supported by neither 
fact nor law.  Indeed, a clear-eyed review of what it actually means to “target” retail 
customers makes this abundantly clear.   
As the Supreme Court of the United States has held, to the extent a rule may affect 
both federally regulated wholesale rates and non-federally regulated retail rates, it is 
important to consider “the target at which” the rule aims.68  Whether such a rule “targets” 
 
64 PA Governor Answer at 10 (citation omitted).  
65 PIOs Limited Protest at 18. 
66 NJ BPU Comments and Limited Protest at 3-4. 
67 Google Protest at 8, 10; Vistra Protest at 2. 
68 ONEOK, Inc. v. Learjet, Inc., 575 U.S. 373, 385 (2015) (“Accordingly, where (as here) a state law can be 
applied to nonjurisdictional as well as jurisdictional sales, we must proceed cautiously, finding pre-emption

PDF page 20

20 
retail or wholesale customers turns on the justification for the rule, not on whether or the 
extent to which the rule affects or even compels action of retail or wholesale customers.69   
In EPSA, the Supreme Court concluded that the Commission’s regulation of 
demand response targets wholesale sales,70 because the Commission’s “justifications for 
regulating demand response are all about, and only about, improving the wholesale 
market.”71  The details here are important.  In EPSA, the Court found that the Commission’s 
justifications for the Rules are focused on the impacts of demand response participation on 
wholesale rates—namely:  
• “help[ing to]create a ‘well-functioning competitive wholesale electric energy 
market’ with ‘reduce[d] wholesale power prices;’”  
• “‘enhanc[ing] reliability;’”  
• “‘help[ing to] improve the functioning and competitiveness of [wholesale 
energy] markets’ by replacing high-priced, inefficient generation;” and  
• “exerting ‘downward pressure’ on ‘generator bidding strategies’ and 
‘support[ing] system reliability.’”72   
Thus, the Court held:  “The retail market figures no more in the Rule’s goals than in the 
mechanism through which the Rule operates.”73  In other words, because the justifications 
provided by the Commission were “about, and only about, improving the wholesale 
market,” the Court concluded that the proposed demand response rules targeted wholesale 
rates, and thus fell within the Commission’s jurisdictional authority. 
 
only where detailed examination convinces us that a matter falls within the pre-empted field as defined by 
our precedents.”). 
69 FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 264 (2016) (“EPSA”). 
70 EPSA, 577 U.S. at 282 (citing ONEOK, 575 U.S. at 385). 
71 EPSA, 577 U.S. at 282. 
72 EPSA, 577 U.S. at 282-83 (some alterations in original). 
73 EPSA, 577 U.S. at 283.

PDF page 21

21 
Likewise, the justifications that PJM has provided for IRAS demonstrate that the 
target or aim of IRAS is targeted to PJM’s wholesale market and enhancing the reliable 
operation of the bulk electric power system.  Specifically, the reasons for IRAS that PJM 
has enumerated are as follows: 
• “support[ing] system reliability in the PJM Region,” where “the unprecedented 
addition of large loads, most notably data centers, have given rise to resource 
adequacy shortfalls—and associated real-time operational issues that IRAS is 
intended to address;”74   
• providing a new tool in “situations where PJM determines that the available 
economic real-time supply may be insufficient to maintain reserves to meet 
applicable Reserve Requirements and/or Interconnection Reliability Operating 
Limits (“IROL”) within prescribed limits and prevent cascading outages;”75 and 
• providing “tools to address situations where regional resource adequacy 
shortfalls would jeopardize reliability.”76 
Indeed, the Commission has long held that “maintaining adequate resources within PJM 
has a significant and direct effect on jurisdictional rates and services, and therefore falls 
within the Commission’s jurisdiction. . . . If insufficient resources are made available, 
system reliability throughout the PJM grid may be compromised.  In addition, where 
resource demand exceeds the supply, the price for capacity may increase.  These are direct 
effects on Commission-jurisdictional rates.”77  IRAS addresses system reliability and 
resource 
adequacy 
of 
the 
PJM 
Region, 
which 
have 
direct 
effects 
on 
Commission-jurisdictional rates.  PPL Electric Company (“PPL”) puts it this way: 
[T]he intended objective of IRAS is clear and unequivocal—”to 
maintain system reliability for the purpose of supporting the 
 
74 August 13 Filing, Transmittal Letter at 6. 
75 August 13 Filing, Transmittal Letter at 2. 
76 August 13 Filing, Transmittal Letter at 3. 
77 PJM Interconnection, L.L.C., 119 FERC ¶ 61,318, at P 48 (2007), aff’d sub nom., Pub. Serv. Elec. & Gas 
Co. v. FERC, 324 F.App’x 1 (D.C. Cir. 2009); id. PP 46-47 & nn.68-70 (The “other cases” to which the order 
refers are Cal. Indep. Sys. Operator Corp., 116 FERC ¶ 61,274, at PP 1113-1114 (2006); Cal. Indep. Sys. 
Operator Corp., 115 FERC ¶ 61,172, at P 36 (2006); Gainesville Utils. Dep’t v. Fla. Power Corp., 402 U.S.

PDF page 22

22 
integration of New Large Loads to the PJM Region that are not in 
arrangements with new capacity additions to the PJM Region.”  In 
other words, IRAS serves a fundamentally PJM-specific regional 
and FERC-centric purpose, and is not intended to fulfill any smaller 
state or local jurisdictional legal function under FPA section 201.78   
“PJM’s proposal is,” as the PA Governor Answer states, “manifestly aimed at provision of 
a wholesale product or service, and at ensuring reliable operation of the bulk power system; 
each is clearly within its jurisdiction.”79  Conversely, the retail market does not figure at 
all in the justifications for IRAS.80  
Other elements of PJM’s August 13 Filing are unquestionably within the 
Commission’s jurisdiction.  Specifically, the Large Load Registry, defining Large Load, 
establishing the policy New Large Loads must bring new capacity, and the treatment of 
large loads in the demand curve used to clear RPM Auctions.   
2. 
IRAS appropriately reflects the division of authority over wholesale 
and retail rates.  
 
Several protestors take issue with the IRAS framework’s division between federal 
and state responsibilities.  PPL argues that New Large Loads are “the entities actually 
‘providing’ IRAS as a wholesale, Commission-jurisdictional rate service to PJM[,]”81 and 
therefore IRAS represents an improper incursion on retail customers.  Constellation Energy 
Generation, LLC (“Constellation”) alleges that IRAS “takes a federal reliability 
 
515, 529 (1971) (Commission has the “responsibility to the public to assure reliable efficient electric 
service”); ISO New Eng., Inc., 118 FERC ¶ 61,157, at P 19 (2007)). 
78 PPL Protest and Request for Clarification at 6. 
79 PA Governor Answer at 7. 
80 See EPSA, 577 U.S. at 283. 
81 PPL Protest and Request for Clarification at 8.

PDF page 23

23 
function . . . and transforms it into a federal regulatory regime governing which categories 
of retail customers must procure generation” or accept potential load reductions.82   
But, as the PIOs note, “[t]hroughout every element of the proposed IRAS 
Framework, PJM has a specific and limited role with no direct control over retail end-use 
customers.”83  First, as to resource adequacy issues generally, the Commission has long 
“recognize[d] the traditional role of state and local entities in regulating resource 
adequacy” while also remaining “aware of [the Commission’s] responsibilities under the 
FPA to ensure that adequate service is provided, and that wholesale rates are just and 
reasonable.”84  The Commission “defer[s] to state and local entities’ decisions when 
possible on resource adequacy matters, but in doing so . . . must not shirk our 
congressionally-mandated responsibilities.”85  The Michigan v. Department of Energy 
decision, issued in September 2026 by the United States Court of Appeals for the District 
of Columbia, expressly held that “the complexity of state planning processes helps to 
explain why the Federal Power Act leaves resource adequacy to be managed by states, 
utilities, and their RTOs.”86   
Second, “the mechanism through which [IRAS] operates”87 falls squarely within 
the realm of PJM’s authority to require load reduction under real-time conditions that may 
give rise to system instability or a capacity shortfall.88 
 
82 Constellation Protest and Comments at 13. 
83 PIOs Limited Protest at 18 (citing EPSA, 577 U.S. at 281).  
84 PJM Interconnection, L.L.C., 119 FERC ¶ 61,318 at P 40 (requiring PJM to “allocate costs to data centers” 
in a manner similar to that as urged in the NEDC/PJM Governors’ Principles at 1). 
85 PJM Interconnection, 119 FERC ¶ 61,318 at P 40. 
86 Mich. v. Dep’t of Energy, 2026 U.S. App. LEXIS 27898, at *44 (D.C. Cir. Sep. 11, 2026) (emphasis added). 
87 EPSA, 577 U.S. at 283. 
88 PA Governor Answer at 9 (“In short, PJM is asserting no new novel authority in proposing IRAS, but 
rather is enhancing its deployment of existing tools to better ensure bulk system reliability (directing load

PDF page 24

24 
Third, the Commission has, by its own accounts, accepted proposed tariffs and 
agreements “related to large loads connecting to the transmission system . . . while rejecting 
those that exceed the Commission’s jurisdiction” in recent years.89  The Commission has, 
in recent years, reiterated that it “has exclusive authority over the rates, terms, and 
conditions for the sales from generating resources used to serve [generation co-located with 
large loads], as well as the practices directly affecting such sales, provided that they are 
sales for resale in interstate commerce.”90  In other words, the jurisdictional boundaries 
with respect to large load issues are not built on a tabula rasa.  Commission precedent 
provides valuable guidance. 
Much of that guidance was addressed in the August 13 Filing and PJM does not 
repeat itself here.91  As PJM noted in its August 13 Filing, under the IRAS framework, 
PJM “may issue directives to Electric Distributors to reduce load by a certain MW quantity 
during certain, limited emergency conditions.  The Eligible New Large Load Amount 
attributable to each Electric Distributor zone/area will be guided by the Large Load 
Registry. . . . PJM will not direct reductions to specific New Large Loads pursuant to 
IRAS.”92 
However, it is worth noting that, following PJM’s August 13 Filing, the 
Commission, in Tri-State Generation and Transmission Association, Inc. (“Tri-State”), 
 
shed to areas with concentrations of non-capacity backed new large loads) and equitable wholesale market 
rates (more fairly allocating the risk of curtailment to zones or areas of the grid that have most contributed to 
the problem.”). 
89 Interconnection of Large Loads to the Interstate Transmission System, 195 FERC ¶ 61,045, at P 2 (2026). 
90 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115 at P 71; see August 13 Filing, Transmittal Letter 
at 89-92.   
91 August 13 Filing, Transmittal Letter at 89-94.   
92 August 13 Filing, Transmittal Letter at 92.

PDF page 25

25 
held that, in its revised form, Tri-State Generation and Transmission Association, Inc.’s 
(“Tri-State”) proposed, amended tariff provisions addressing “concerns regarding the rapid 
growth of large loads,” do not constitute “an impermissible intrusion upon retail rate 
regulation.”93  
Specifically, Tri-State proposed a High Impact Load Tariff and pro forma High 
Impact Load Agreement (together, “HIL Program”) which, inter alia, defines a large load, 
i.e., HIL, in Tri-State,94 and imposes requirements on Tri-State Utility Members with large 
loads such as:  a biennial study cycle that begins with a “meeting with Utility Members 
and their potential HIL Customers[;]” payment of a “non-refundable HIL Evaluation Fee;” 
agreement “to a HIL Agreement to be executed by the Utility Member and Tri-State to 
facilitate the responsibility for serving the HIL project[;] and “security in the amount of 
$1.869 million/MW.”95  Despite all these mandates on Utility Members, however, the 
Commission found that the HIL Tariff is also appropriately limited, as it “imposes 
obligations only on Tri-State’s Utility Members and leaves those same Utility Members 
full discretion as to whether they will flow those terms through to their non-jurisdictional 
[retail customer contracts].”96 
The Commission reasoned that, although Tri-State’s HIL Program addresses 
“concerns regarding the rapid growth of large loads,”97 even where certain “requirements 
could affect [retail customers,] . . . the United States Supreme Court has explained that the 
 
93 Tri-State Generation & Transmission Ass’n., 196 FERC ¶ 61,127, at P 68 (2026). 
94 Tri-State, 196 FERC ¶ 61,127 at P 11 (“Tri-State proposes to define a HIL as load exceeding or forecasted 
to exceed 45 MW within four years and being served from a single Tri-State delivery point.”). 
95 Tri-State, 196 FERC ¶ 61,127 at PP 11-14. 
96 Tri-State, 196 FERC ¶ 61,127 at P 25. 
97 Tri-State, 196 FERC ¶ 61,127 at P 68.

PDF page 26

26 
spheres of federal and state authority over electricity are not ‘hermetically sealed’ from one 
another[.]”98  Thus, in Tri-State, the Commission concluded that, even if the HIL Program 
does affect the quantity or terms of retail sales, “Tri-State’s proposal does not present an 
impermissible intrusion on retail rate regulation.”99   
Likewise, while the IRAS framework may ultimately affect retail customers, it 
cannot be said to “present an impermissible intrusion upon retail rate regulation.”100  The 
IRAS proposal places terms and conditions on LSEs, not end-use retail customers. The 
LSEs in turn resell capacity and energy to their customers. The IRAS falls clearly within 
FERC’s authority over regulating the terms and conditions of sales for resale.   
By way of example, as several intervenors observe, the IRAS framework directs a 
wholesale response during an Interim Resource Adequacy Event.101  During such an event, 
PJM would determine the quantity of MW that load in a zone/area would need to be 
reduced by to maintain system reliability in the PJM Region and provides a directive to 
Electric Distributors accordingly, but would leave it to the states to “determine—under 
their own laws, policies, and definition of what constitutes ‘large load’—which resources 
will actually be called on at the retail level to reduce load.”102  In implementing IRAS, PJM 
will be issuing broad load reduction directives to Electric Distributors.  PJM “will not direct 
specific LSEs and/or specific customers of LSEs—including specific Large Loads—to 
reduce their load and/or switch to on-site backup resources.  Those decisions would be 
 
98  Tri-State, 196 FERC ¶ 61,127 at P 68 (quoting EPSA, 577 U.S. at 281). 
99 Tri-State, 196 FERC ¶ 61,127 at P 66. 
100 Tri-State, 196 FERC ¶ 61,127 at P 66. 
101 PIOs Limited Protest at 19 (“PJM will respect jurisdictional boundaries by directing IRAS Actions at the 
wholesale level.”); PPL Protest and Request for Clarification at 6 (“IRAS is a new wholesale rate service, 
with rates, terms, and conditions established under the jurisdictional authority of the Commission.”). 
102 August 13 Filing, Transmittal Letter at 87.

PDF page 27

27 
addressed in revised state retail tariffs,” which already provide rules for load reduction 
among various retail customer classes.103  Electric Distributors, in coordination “with the 
relevant state(s) or RERRA(s), individual Load Serving Entities, and customers served by 
the Load Serving Entities in its zone/area”104 will retain full discretion as to how PJM’s 
instructions to reduce MW in a zone/area to maintain system reliability in the PJM Region 
will ultimately be carried out just as they do today.   
Indeed, states are stepping up to the challenge.  For example, the PA PUC, on 
September 10, 2026, passed a Motion of Vice Chair Kimberly Barrow that directed staff 
to draft a “Tentative Order outlining proposed amendments and modifications that electric 
distribution companies must make to their tariffs to incorporate a pre-emergency provision 
that implements curtailment protocols” and to “outline proposed amendments and 
modifications that electric distribution companies must make to their emergency load 
control procedures for emergency events, unless the large load customer has secured 
incremental electric capacity for the entirety of its demand as proposed by PJM[.]”105 
In keeping with the United States Court of Appeals for the Third Circuit decision, 
New Jersey Board of Public Utilities v. FERC, IRAS permits states to retain authority over 
retail customers and retail rates while also “prevent[ing] the state’s choices from adversely 
affecting wholesale capacity rates.  Such action falls squarely within FERC’s 
jurisdiction.”106  The Commission’s recent findings on the jurisdictional divide on large 
 
103 August 13 Filing, Transmittal Letter at 86-87. 
104 August 13 Filing, Transmittal Letter at 87 (quoting proposed Tariff, Attachment DD-4, section III(c)). 
105 Vice Chair Kimberly Barrow, Directing Staff to Issue Tentative Order Pursuant to the Public Utility 
Commission’s Provisions at 52 Pa. Code Section 57.52 (Emergency load control and energy conservation 
by electric utilities) and Establish a Technical Conference On Large Computational Load Cost Allocation, 
Pennsylvania Public Utility Commission, 2 (Sep. 10, 2026), https://www.puc.pa.gov/pcdocs/1949305.pdf 
[https://perma.cc/7UFL-ZX6D]. 
106 N.J. Bd. of Pub. Utils. v. FERC, 744 F.3d 74, 98 (3d Cir. 2014).

PDF page 28

28 
load issues is clear:  “[S]tates retain exclusive jurisdiction over the terms of retail sales” 
including “how the costs of the wholesale sale and transmission of electricity assigned to 
a wholesale customer are allocated among that wholesale customer’s retail customers.”107  
Likewise, states will retain authority over how IRAS responsibility is allocated among their 
retail customers.  
3. 
Intervenors make contradictory claims that IRAS imposes 
mandatory and involuntary rules on end-use retail customers and 
IRAS improperly foists responsibility on the states.  Neither are true. 
Several intervenors characterize IRAS as imposing mandatory and involuntary load 
reduction requirements directly on end-use retail customers, and thus improperly 
regulating retail rates.108  Simultaneously, protestors also assert that PJM’s proposal has 
“foisted onto the states the responsibility for implementing IRAS without consulting with 
them on the program’s design.”109  Moreover, the Data Center Coalition (“DCC”) argues 
for rejection of IRAS on one hand in favor of state jurisdiction but then bemoans that if 
states take different positions on curtailment, it will not be clear that IRAS will deliver its 
intended reliability benefits.110 But, as the Pennsylvania Governor’s Office observes, 
“protestors cannot logically claim both that PJM’s proposal unlawfully ‘targets retail 
customers’ and that PJM’s proposal is fatally flawed because it cannot guarantee which 
individual retail customers are curtailed. Both cannot be true.”111 
PPL argues, to no avail, that “[t]he issue is not about which entity gets to identify 
the specific individual Eligible New Large Loads that must provide IRAS when PJM calls 
 
107 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115 at P 68. 
108 See, e.g., PPL Protest and Request for Clarification at 10. 
109 Google Protest at 11. 
110 DCC Protest at 5. 
111 PA Governor Answer at 9-10.

PDF page 29

29 
for it.  The issue is that, when called upon to provide IRAS under that process, the Eligible 
New Large Load cannot say no.”112  First, the issue of jurisdiction is about which entity 
gets to identify the retail customers who ultimately respond to PJM’s directives to reduce 
load.  PJM’s answer is straightforward—the states and/or RERRAs, in coordination with 
Electric Distributors and their LSEs and retail customers served by those LSEs ultimately 
identify those retail customers.  Second, PJM has, in fact, been continuously consulting 
and communicating with states and other stakeholders on the design of IRAS for over a 
year.113  Third, the IRAS framework does not determine whether any specific retail 
customers can say no.  Just as the identity of the retail customers who are ultimately 
implicated by PJM’s directives to reduce a MW quantity of load is not decided by PJM, 
under the IRAS framework, it is also not up to PJM to determine whether, as PPL puts it,114 
retail customers can say no.  That—and the regulation of the terms and conditions of retail 
rates, and the regulation of retail customers—remains within the exclusive jurisdiction of 
the states.  As noted previously, PJM’s load reduction directives will be informed by the 
degree to which load in a certain zone/area’s IRAS responsibility has been reduced through 
MW of BYONC or Allocated RBP UCAP MW.  However, PJM will direct load reduction 
directives to Electric Distributors, while states/RERRAs may determine which retail 
customers will implement the load reduction directives.  
The division of labor between PJM and the states is firmly supported by 
Commission precedent.  In Tri-State, the Commission upheld an analogous division of 
 
112 PPL Protest and Request for Clarification at 10. 
113 NJ BPU Comments and Limited Protest at 3 (“PJM’s Proposal at the Federal Energy Regulatory 
Commission (“FERC”) reflects almost a year of deliberation and stakeholder engagement surrounding the 
feasibility and potential implications of implementing such a program.”). 
114 PPL Protest and Request for Clarification at 10.

PDF page 30

30 
responsibilities and ultimately found that Tri-State’s HIL Program “imposes obligations 
only on Tri-State’s Utility Members and leaves those same Utility Members full discretion 
as to whether they will flow those terms through to their non-jurisdictional [retail customer 
contracts].”115  The Commission was not persuaded by arguments, similar to those made 
in this proceeding, that “Tri-State’s proposal exceeds the Commission’s jurisdiction 
because Tri-State’s ‘encouragement’ that members include [Member Contract High Impact 
Load] provisions that are consistent with HIL requirements functionally dictates they do 
so.”116  Indeed, the Commission explains that this is not enough to “convert permissible 
Commission-jurisdictional 
requirements 
into 
impermissible 
retail 
terms 
and 
conditions.”117     
Similarly, the contention that PJM has “compelled states”118 to conform to IRAS is 
unavailing.  Under IRAS, PJM directs Electric Distributors to reduce MW quantities of 
load in a zone/area when PJM has determined that “the available economic real-time supply 
may be insufficient to maintain reserves to meet applicable Reserve Requirements and/or 
[IROL] within prescribed limits and prevent cascading outages.”119  PJM expressly 
declines to dictate which retail loads must be reduced.120      
 
115 Tri-State, 196 FERC ¶ 61,127 at P 25. 
116 Tri-State, 196 FERC ¶ 61,127 at P 68. 
117 Tri-State, 196 FERC ¶ 61,127 at P 68. 
118 DCC Protest at 3. 
119 August 13 Filing, Transmittal Letter at 2. 
120 August 13 Filing, Transmittal Letter at 82.

PDF page 31

31 
E. 
Calling for IRAS Load Reductions Before Pre-Emergency Load 
Management Properly Reflects the Resource Adequacy Risk of New 
Large Loads that Have Not Brought New Capacity and Protects Native 
Loads from the Cost and Reliability Impacts of Such New Large Loads. 
Interim Resource Adequacy Service will be an operational tool available for PJM’s 
operators to maintain system reliability when the system has exhausted all available 
economic resources (i.e., all available generation, storage, and Economic Load Response 
Participant resources), and before PJM calls upon Pre-Emergency Load Management.  “In 
other words, [as] the region is approaching a capacity event[,] . . . PJM [will] direct Electric 
Distributors to reduce those New Large Loads that have failed to cover their capacity 
obligations before relying on Demand Resources, through Pre-Emergency Load 
Management Reductions Actions, to maintain reliability.”121  This sequence is just and 
reasonable.  The Eligible New Large Loads available to provide IRAS have not satisfied 
their respective capacity needs through BYONC, and therefore, should not obtain the 
capacity benefit of Demand Resources.   
1. 
The states broadly recognize the benefits and purpose of calling 
IRAS before Pre-Emergency Load Management. 
OPSI, NJ BPU, the Pennsylvania Governor’s Office, Ohio FEA, and Ohio ELC 
each express strong support for PJM’s proposed placement of IRAS within the sequence 
of PJM’s operational tools for addressing emergency conditions.122  These entities 
recognize that PJM’s proposal:  
• “appropriately places the initial operational consequences of a capacity 
shortfall on the amount of demand associated with NLLs that entered 
the system without sufficient new capacity, with an eye towards 
 
121 August 13 Filing, Transmittal Letter at 79. 
122 For more discussion of how and when PJM would utilize IRAS to address emergencies, please see August 
13 Filing, Pilong Aff.

PDF page 32

32 
protecting existing customers and preserving demand response 
resources;”123 
• “reduces the likelihood that NLL-driven resource adequacy shortfalls 
will unnecessarily trigger scarcity conditions, which inflated escalates 
energy prices that all loads must pay;”124 
• “creates a strong incentive for New Large Loads to engage in bilateral 
agreements, which is the best way to protect ratepayers from the costs 
and risks associated with load growth from these customers while also 
resulting in new MW of supply to the system;”125 
• “will help maintain the participation of certain load management 
reduction resources, like [Demand Resources], by minimizing ‘fatigue’ 
that can occur from being over-called on during stress events;”126  
• “will avoid escalating emergency procedures that include but are not 
limited to shortage pricing and public calls for conservation, which 
would represent socialization of costs, both financial and reliability 
related, being imposed by non-capacity backed new large loads upon all 
customers;”127 and 
• “places curtailment responsibility where the associated resource 
adequacy risk originates.”128 
They also recognize that conversely: 
• calling on IRAS later “would impose significant financial impact and 
shift reliability risk to other customers”129 by “shift[ing] the 
consequences of that shortfall onto customers and resources that did not 
cause it;”130 and  
• “if PJM were to call IRAS Actions after Demand Response Resources 
have been exhausted, this would eliminate the incentive of NLL to 
contract for new capacity because they would be insulated from 
curtailment by Demand Response.”131 
 
123 OPSI Comments and Request for Clarification or to Sever at 4; see also Ohio FEA Comments at 7 (“[I]t 
is reasonable for large loads that do not play a role in remedying the supply and demand imbalance to be 
curtailed prior to other load.”). 
124 OPSI Comments and Request for Clarification or to Sever at 4. 
125 NJ BPU Comments and Limited Protest at 5. 
126 NJ BPU Comments and Limited Protest at 5. 
127 PA Governor Answer at 8. 
128 OPSI Comments and Request for Clarification or to Sever at 5. 
129Ohio FEA Comments at 7. 
130 OPSI Comments and Request for Clarification or to Sever at 5. 
131 Ohio FEA Comments at 7; Ohio ELC Comments and Limited Protests at 9.

PDF page 33

33 
Accordingly,  
• “prioritizing IRAS Actions is a necessary step to comply with the 
Statement of Principles Regarding PJM, as signed by the National 
Energy Dominance Council and the 13 PJM governors, and the 
Ratepayer Protection Pledge.”132  
As is evident, the states recognize the benefits and purpose of calling for IRAS prior to 
Pre-Emergency Load Management. 
In contrast, the DCC, Constellation, and the IMM argue against PJM being able to 
call on IRAS before Pre-Emergency Load Management.  Their arguments can be boiled 
down to the proposal (1) is not supported;133 (2) is contrary to cost causation principles;134 
and (3) will increase costs to load.135  None of these has merit, as demonstrated in turn 
below. 
2. 
Contrary to the DCC and IMM, the record clearly supports 
authorizing PJM to be able to manage emergency conditions by 
issuing an IRAS Action before Pre-Emergency Load Management. 
The DCC and IMM allege that “PJM has not provided a supportable reason to 
justify giving IRAS priority over existing compensated Demand Resources.”136  The 
allegation is belied by the record, which provides a number of reasons why such sequencing 
of operator actions is just and reasonable.137  In addition to the reasons stated above by 
 
132 Ohio FEA Comments at 7. 
133 DCC Protest at 16-19; IMM Protest at 17. 
134 DCC Protest at 19-22. 
135 IMM Protest at 16-18; Constellation Protest and Comments at 42-45. 
136 IMM Protest at 17; see also DCC Protest at 17 (“PJM has not demonstrated that it is just and reasonable 
to direct the curtailment of retail customers prior to deploying Demand Resources that have been committed 
precisely to avoid such service disruptions.”). 
137 See Pilong Aff. ¶ 15 (“while there is a sequence of escalating emergency action steps set forth in PJM 
Manual 13, the rapidness of system events influences the timing and order of actions necessary to maintain 
system reliability. Therefore, PJM Dispatchers “have the flexibility to implement emergency procedures in 
whatever order is required to ensure system reliability. Likewise, they have the flexibility to exit emergency 
procedures in a different order than they were implemented.” (citing PJM Manual 13, section 2.3)).

PDF page 34

34 
supporting commenters, the August 13 Filing explained that allowing PJM to issue an 
IRAS Action before calling on Pre-Emergency DR is justifiable and appropriate because 
these Eligible New Large Loads “failed to cover their capacity obligations.”138  PJM also 
explained that calling IRAS reductions after Pre-Emergency DR “would reduce the 
incentive for New Large Loads to bring new capacity to the system, as they would be 
insulated by the Demand Resource capacity products.”139  Neither the DCC nor the IMM 
refuted these arguments.   
Further, issuing IRAS Alerts after economic dispatch of all available resources 
through the Day-ahead and Real-time Energy Markets and before Pre-Emergency Load 
Management is consistent with PJM’s current processes to recall/curtail non-firm 
transmission service after economic generation and before Pre-Emergency Load 
Management.140  In both instances, these entities transact in the PJM Energy Market 
without having secured any capacity.  Therefore, it is reasonable to support these products, 
to the extent the owning entity wishes to schedule them, when the energy is available.  
When there is not sufficient energy, PJM takes action to ensure that capacity-backed loads 
are prioritized.  
3. 
Contrary to Constellation, IRAS load reductions will protect native 
loads from cost impacts of Eligible New Large Loads. 
Constellation contends that calling an IRAS Action, and having Eligible New Large 
Loads reduce their energy demand, would somehow increase costs to the rest of the 
customers.  Specifically, Constellation argues that calling on IRAS reductions before 
 
138 August 13 Filing, Transmittal Letter at 79. 
139 August 13 Filing, Transmittal Letter at 80. 
140 See August 13 Filing, Transmittal Letter at 78; Pilong Aff. ¶¶ 12, 39-40.

PDF page 35

35 
Pre-Emergency Load Management “violates the core least-cost dispatch principle because 
curtailment of IRAS load is likely to be significantly more costly than Demand 
Response.”141  While initially intriguing, this argument quickly falls apart under scrutiny.  
Constellation then goes on to argue that this is least-cost from the perspective of the 
Pre-Emergency Load Management because they have already made the calculus that the 
cost of the capacity payment outweighs the opportunity cost associated with reduced 
energy consumption, but the “[l]oads subject to IRAS may include customers that have not 
elected Demand Response precisely because their own interruption costs are too high or 
their operating characteristics prevent them from meeting the notice and response time 
required to provide Demand Response.”142   
Thus, in Constellation’s view, calling on IRAS first is problematic because the cost 
to the large loads that provide IRAS would be greater than the cost to loads that provide 
Pre-Emergency Load Management.  This is irrelevant here where the objective is to protect 
native loads from the costs and reliability issues posed by New Large Loads that failed to 
bring new capacity.  The Ratepayer Protection Pledge signed by a significant number of 
large load entities makes clear that protection of cost shifts to other ratepayers is the 
primary goal as opposed to Constellation’s concern about hypothetical higher costs that 
large loads might incur under certain ill-defined and unlikely circumstances.  Calling on 
IRAS before Pre-Emergency Load Management is consistent with the Ratepayer 
Protection Pledge, as it places the reliability and cost burden of New Large Loads’ failure 
to bring new capacity on those New Large Loads, while protecting native loads. 
 
141 Constellation Protest and Comments at 43. 
142 Constellation Protest and Comments at 44 (citing Affidavit of Aaron T. Patterson on Behalf of 
Constellation Energy Generations, LLC (Appendix A) ¶ 17).

PDF page 36

36 
4. 
Calling IRAS before Pre-Emergency Load Management will avoid 
the detrimental resource adequacy effects of Demand Resource 
“fatigue.” 
In addition, Constellation’s argument that calling on IRAS before Emergency Load 
Management is a more costly option frames the issue as the cost to the large load and not 
the cost to the system and ignores the opportunity cost inherent in calling on Emergency 
Load Management more often.  The issue of potential Demand Resource fatigue is real, as 
recognized by the NJ BPU.143  That is, while Demand Resources are paid the same daily 
rate as other Capacity Resources, the underlying resource is not the same as a generation 
or storage resource.  Inherently, a generation or storage resource is purpose built to 
participate in PJM’s markets; they are designed to provide energy and capacity.   
In contrast, the underlying resource of Demand Resources are energy users, and the 
provision of demand response is a secondary purpose.  As Constellation recognizes, 
Demand Resources only commit to provide load reductions when the payment exceeds the 
opportunity cost.  However, the opportunity cost calculation changes each time the 
underlying resources are directed to reduce energy consumption.  The more often a load 
center is asked to reduce consumption the more disruptive the provision of demand 
response and the greater the opportunity cost.  The result is load centers become less willing 
to provide demand response and support Demand Resources.  This is what is meant by 
Demand Resource “fatigue.”   
Were such Demand Resource fatigue to manifest, there would be a significant 
adverse effect on the reliability and resource adequacy for the PJM Region.  For the 
2027/2028 Delivery Year, the region is relying on 7,641 MW of Demand Resources to 
 
143 See NJ BPU Comments and Limited Protest at 5.

PDF page 37

37 
provide capacity.144  For a region that is already over 6,800 MW short of capacity, the loss 
of any MW of Demand Resource would be impactful; a sizeable loss would be 
considerable.  Accordingly, in addition to the legal and equitable reasons for sequencing 
IRAS Actions before Pre-Emergency Load Management, policy and reliability reasons 
dictate a similar result. 
F. 
PJM’s BYONC Rules Appropriately Incent the Development of New 
Capacity to Meet Long-Term Resource Adequacy Needs of New Large 
Loads.  
Most commenters and protestors support the concept that New Large Loads should 
bring new capacity to the PJM system to meet their resource adequacy needs.145  However, 
as discussed below, they generally quibble with various aspects of the BYONC rules.  For 
their part, commenters and protestors representing the interests of existing generation 
resources argue that the requirement that BYONC is “new” is unduly discriminatory.146   
 
144 2027/2028 BRA Report at 11, Table 6. 
145 See, e.g., Google Protest at 1 (“Specifically, Google agrees that New Large Loads that do not bring 
sufficient new capacity to offset their expected demand should be subject to curtailment prior to other firm 
wholesale customers during tight system conditions, ensuring service to residential and other commercial 
customers remains reliable.”); Va. Governor Chief Energy Officer Comments at 2 (“Virginia supports PJM’s 
recognition that large loads can contribute to reliability by bringing new capacity, reducing peak demand, or 
deploying distributed and demand-side solutions.”); Ohio FEA Comments at 5 (“The Ohio FEA supports a 
BYONC framework and PJM’s proposal to incent LSEs to bring new capacity resources to bear 
commensurate with the addition of NLL, which PJM defines to mean new or incremental large loads that go 
into service after June 1, 2027.  We agree that bringing new capacity to match new large load is the optimal 
solution to address resource adequacy concerns and is strongly preferred to IRAS.  However, given the 
challenges of bringing new capacity resources online to meet new demand in the near term, we find PJM’s 
BYONC proposal to be reasonable.”); ACORE Comments at 1 (“ACORE therefore supports the requirement 
for a new large load to contract for new capacity under BYONC to avoid being subject to potential 
curtailments under IRAS.  Such a requirement will strongly incent longer-term (at least 10 year) contracting 
with BYONC capacity by the large loads availing themselves of the IRAS BYONC provision.”); NRG 
Comments and Limited Protest at 5 (supporting PJM’s IRAS filing “in general” including proposal for LSEs 
to bring new capacity and that the BYONC capacity requirement be “new” generation). 
146 See, e.g., EPSA Protest at 2-10; Talen Protest at 5-7; Vistra Protest at 12-13.

PDF page 38

38 
1. 
PJM’s BYONC rules offer sufficient flexibility for vertically 
integrated LSEs. 
Dominion Energy Services, Inc. (“Dominion”) and EKPC each argue that the 
BYONC rules do not provide enough flexibility to vertically integrated entities with a 
portfolio of resources.147  Specifically, they contend that the BYONC requirement 
improperly “pushes Large Loads and their LSEs toward tagging specific resources to 
specific end consumer loads rather than utilizing portfolio planning,”148 and that the 
BYONC non-transferability requirement runs counter to “the flexibility [an LSE] needs to 
adjust its portfolio to cover its aggregate load obligation.”149  These arguments 
misunderstand PJM’s proposal.  As PJM explained, BYONC are simply MW of Unforced 
Capacity (“UCAP”).150  A New Large Load with a resource adequacy need of 75 MW 
should contract with 75 MW of BYONC.  Starting with the first year that the BYONC 
provides capacity to the PJM Region, the New Large Load is deemed to have satisfied its 
obligation to bring new capacity.151  There is no hint of a requirement that the BYONC 
must physically serve the New Large Load.  The issue is that the PJM Region is short of 
capacity.  Because as part of the transmission planning and interconnection processes all 
new capacity must ultimately be deliverable to the entire PJM Region (subject to 
transmission constraints), there does not need to be any locational requirement for 
BYONC.  These processes may result in new upgrades to ensure the new capacity is 
deliverable.  Requiring BYONC generation to continuously match specific large loads is 
 
147 EKPC Limited Protest at 21; Dominion Comments at 3. 
148 EKPC Limited Protest at 20. 
149 EKPC Limited Protest at 24. 
150 August 13 Filing, Transmittal Letter at 51. 
151 August 13 Filing, Transmittal Letter at 69; proposed Tariff, Attachment DD-4, section V(b).

PDF page 39

39 
simply not consistent with today’s generation interconnection requirements and would 
introduce a great deal of new uncertainty and lack of finality to the interconnection process.   
As for transferability, once an arrangement between a New Large Load and a 
BYONC is reported, the two are paired, unless the New Large Load goes out of business.152  
Allowing BYONC to be transferable runs counter to the notion that the New Large Load 
is bringing new capacity to the PJM system.  The requested liquidity in BYONC is not 
necessary for the scheme to be just and reasonable.  As proposed, for each MW of BYONC 
associated with a New Large Load, that New Large Load’s exposure to IRAS is 
permanently reduced.  This is clear and easy to understand and administer.  And, 
importantly, it makes the incentives clear for New Large Loads—they need to bring new 
capacity.  If none is available, then they need to work with suppliers to develop additional 
capacity.  
Conversely, allowing for a liquid market for already associated BYONC simply 
create a secondary market for existing BYONC, contrary to the root purpose of BYONC 
which is designed for New Large Loads to bring new capacity, not existing capacity that 
has already been deemed to offset the resource adequacy needs of a different New Large 
Load.  Further, as explained in the August 13 Filing, it would also create unnecessary 
complexity in ensuring the correct matching of New Large Load to BYONC and present 
opportunities for fraud where a MW of BYONC could be reported more than once.153   
 
152 See proposed Tariff, Attachment DD-4, section VII(e). 
153 August 13 Filing, Transmittal Letter at 65.

PDF page 40

40 
2. 
Measuring whether BYONC is new as of the 2027/2028 Delivery 
Year is just and reasonable. 
IMM, NJ BPU, and JCAs argue that whether BYONC is new should be measured 
at the time of the BYONC arrangement with the New Large Load and not, as PJM 
proposed, measured against the capacity on the PJM system today prior to the 2027/2028 
Delivery Year.154  While there may be some merit to an approach that further circumscribes 
BYONC consistent with commenters’ approach, they have not demonstrated that PJM’s 
approach is not just and reasonable.155  As discussed, PJM designed its proposal under FPA 
section 205, in part, to address the immediate resource adequacy issue facing the PJM 
Region starting with the 2027/2028 Delivery Year.  An advantage of PJM’s approach is 
that Capacity Resources ready to participate in RPM and commit to provide capacity are 
not disincentivized to do so while they wait for the BYONC marketplace to develop.  The 
BYONC rules should not impede or hinder new Capacity Resources from committing to 
provide capacity.  The reality is that the PJM Region needs new capacity right now.  This 
design to spur quicker participation of new Capacity Resources is just and reasonable in 
this context. 
3. 
The BYONC price taker requirement is just and reasonable in the 
context of IRAS, as the BYONC arrangement is akin to Self-Supply 
Capacity Resources. 
Several protestors allege that requiring BYONC to participate as a price taker (i.e., 
submit $0/MW-day Sell Offers) would “interfere” with RPM Auction price signals by 
“artificially lower[ing] the clearing price for capacity, depressing market prices for existing 
resources and further suppressing the ability of the RPM to send the proper price signals to 
 
154 IMM Protest at 19-20; JCA Protest and Comments at 29-31; NJ BPU Comments and Limited Protest at 
6-9. 
155 See, e.g., Cities of Bethany, 727 F.2d at 1136.

PDF page 41

41 
incentivize new capacity and retain existing capacity.”156  This allegation is incorrect and 
myopically ignores both the purpose of the price taker requirement and the context of the 
BYONC rules. 
With respect to the impact on the market, protestors are mistaken that the price 
taker requirement would affect the clearing price.  Given that, under PJM’s proposal, New 
Large Loads would be excluded from the demand curve until they contract for BYONC, 
the one-for-one addition of new MW of load and new MW of supply would have offsetting 
effects on the clearing price.  In other words, as PJM explained in the August 13 Filing, the 
price taker treatment would “result[] in . . . effectively [a] price-neutral outcome.”157   
In any event, regardless of whether the Commission accepts PJM’s proposal to 
exclude New Large Loads from the VRR Curve until they bring new supply, the price taker 
requirement does not unlawfully interfere with RPM Auction price signals.  While true that 
all else held equal, adding a MW of supply at $0 will tend to reduce clearing prices 
(depending on the offered price of the next marginal MW), as noted below, the capacity 
market is not a vacuum, and whether the price taker treatment is not just and reasonable 
must be considered in context.  The Commission has found price taker treatment just and 
reasonable in multiple contexts. 
First, the simple fact is new demand is bringing new supply, and forcing that new 
supply to clear the capacity market.  This is no different from the Capacity Resources load 
entities have been able to offer as “Self-Supply” since the advent of RPM.158  Longstanding 
 
156 Constellation Protest and Comments at 52; see P3 Protest at 22.   
157 August 13 Filing, Transmittal Letter at 58. 
158 See PJM Interconnection, L.L.C., 117 FERC ¶ 61,331, at P 13 (2006) (“To meet the capacity needs of 
Load Serving Entities that failed to procure enough capacity through self-supply or bilateral contracts, PJM 
proposed to hold an auction each year, in which PJM would procure the remainder of the capacity 
requirement.”); id. at P 29 (“The Settlement preserves provisions of the August 31 filing that support

PDF page 42

42 
capacity market rules have allowed load to submit Sell Offers for Capacity Resources 
“deemed Self-Supply and . . . indicate whether it is committing the resource regardless of 
clearing price or with a price bid.”159  There is no question that this is just and reasonable.  
The analogous price taker treatment for BYONC caused to be committed as capacity by 
New Large Loads is similarly just and reasonable, as becoming BYONC is also the product 
of a voluntary choice by the resource seller; if the seller does not want price taker treatment 
for its resource it does not have to enter into a BYONC arrangement with a New Large 
Load. 
Second, BYONC resources will be able to contract for a revenue stream, that is the 
product of an arm’s length negotiation between a willing buyer and a willing seller, to 
incent a resource seller to undertake the BYONC requirements.  The Commission has 
previously found just and reasonable price taker treatment for resources considered in 
capacity markets where their going forward costs were adequately covered by 
out-of-market revenue streams, notably cost of service agreements to retain resources for 
transmission reliability or fuel security reasons.160  In this case, as part of being a BYONC 
 
self-supply and bilateral contracts through various means . . . “); Tariff, Attachment DD, section 1(b) (RPM 
provides:  “a competitive auction mechanism to secure the forward commitment of additional Capacity 
Resources and Qualifying Transmission Upgrades as necessary to satisfy the portion of LSEs’ Unforced 
Capacity Obligations not satisfied through Self-Supply, in order to ensure the reliability of the PJM Region 
for future Delivery Years.”); id. at Attachment DD, section 5.2 (rules for nominating Self-Supply into RPM 
Auctions). 
159 Tariff, Attachment DD, section 5.2. 
160 See, e.g., PJM Interconnection, L.L.C., 190 FERC ¶ 61,088, at P 50, order addressing arguments raised 
on reh’g, 192 FERC ¶ 61,135, at PP 31-34 (2025); Indep. Power Producers of N.Y. v. N.Y. Indep. Sys. 
Operator, Inc., 150 FERC ¶ 61,214 (2015), order granting in part & denying in part clarification & reh’g, 
170 FERC ¶ 61,118 (2020); N.Y. Indep. Sys. Operator, Inc., 150 FERC ¶ 61,116 (2015), order on reh'g & 
compliance, 155 FERC ¶ 61,076 (2016), order on reh'g & compliance, 161 FERC ¶ 61,189 (2017), order on 
clarification & reh’g, 163 FERC ¶ 61,047 (2018); see also ISO New Eng. Inc., 165 FERC ¶ 61,202, at PP 
82-88 (2018) (approving price taker treatment for resource retained for fuel security purposes), order 
addressing arguments raised on reh’g, 173 FERC ¶ 61,204 (2020).

PDF page 43

43 
resource there will be an agreement between the New Large Load and the Capacity 
Resource that will address compensation, among other issues.  
Within the context of IRAS, for the New Large Loads to get the benefit of the 
BYONC reducing its exposure to IRAS and ultimately exempting New Large Loads from 
IRAS, it is imperative that the BYONC secure capacity commitments for 10 consecutive 
Delivery Years.161  In the August 13 Filing, PJM explained that the 10-year capacity market 
participation requirement ensured that the BYONC was “real and lasting,”162 i.e., that the 
resource adequacy needs of the New Large Load would be addressed through the BYONC 
and the region could count on such BYONC to do so.  The price taker treatment is the best 
way to ensure that the BYONC clears the capacity market for each Delivery Year.  To 
contract for BYONC, New Large Loads must offer out-of-market revenues sufficient for 
the new supply to acquiesce to price taker treatment for 10 years.  The new supply would 
evaluate the revenue stream and revenue certainty available through the BYONC contract 
against unencumbered market participation.  New supply that elects to become BYONC is 
making an economic choice to do so.  Sellers of such supply can ensure their BYONC 
arrangements with New Large Loads sufficiently cover their going forward costs such that 
they are indifferent to the outcomes of the PJM capacity auctions.  The BYONC voluntarily 
agreeing to price taker treatment in this context is just and reasonable. 
 
161 Proposed Tariff, Attachment DD-4, section VIII(e).  FirstEnergy challenges the 10-year RPM 
participation requirement for BYONC resources, arguing that PJM provided “no basis” for this requirement.  
See FirstEnergy Limited Protest and Comments at 5-6, 15.  To the contrary, PJM explained that this 
requirement is “designed to ensure that this BYONC is real and lasting.”  August 13 Filing, Transmittal Letter 
at 56.  That is, because the New Large Load will continue to be served by the PJM system throughout those 
10 years, the BYONC resource should likewise serve to provide capacity during that period too.  If the New 
Large Load ceases to exist during that 10-year period, the BYONC resource is relieved of its obligations.  
See proposed Tariff, Attachment DD-4, section VIII(a) (Capacity participation requirements only apply to 
BYONC “in an arrangement with a New Large Load”). 
162 August 13 Filing, Transmittal Letter at 56.

PDF page 44

44 
4. 
Given the present resource adequacy shortfall, requiring New Large 
Loads to bring new capacity is not unduly discriminatory with 
respect to existing generation resources. 
Electric Power Supply Association (“EPSA”) and others representing the interests 
of existing generators contend that the rule that New Large Loads must contract with new 
capacity to address their resource adequacy needs is unduly discriminatory against existing 
Capacity Resources.163  In other words, it appears that their argument is that existing 
Capacity Resources are unlawfully being denied the opportunity to meet the resource 
adequacy needs of New Large Loads.  This argument lacks merit.  Discrimination is only 
undue if it lacks justification.  Here, the criterion that BYONC be “new” is easily 
justifiable.  The PJM Region needs new capacity.  This is not in dispute.  The immediate 
primary cause for the need for new capacity is the significant amount of New Large Load 
interconnecting without capacity.  Thus, PJM is proposing a requirement that the New 
Large Loads contract to bring new capacity to become exempt from being eligible to 
provide IRAS.  Allowing existing Capacity Resources to contract with New Large Loads 
would not solve the problem that the BYONC scheme is designed to address.   
5. 
BYONC’s ELCC risk is shared by New Large Loads. 
Several entities complain that PJM’s proposal to use the Accredited UCAP of the 
BYONC determined for the “RPM Auction in which the BYONC cleared for the initial 
Delivery Year the BYONC is in an arrangement with the New Large Load”164 as the 
permanent UCAP MW offset for determining the eligibility of a New Large Load to 
provide IRAS improperly shifts the BYONC resource’s ELCC risk to ratepayers.165  PJM’s 
 
163 See EPSA Protest at 3; Vistra Protest at 12-13; Constellation Protest and Comments at 37-40; America’s 
Power Protest at 5-11. 
164 Proposed Tariff, Attachment DD-4, sections VII(i)(i)-(ii). 
165 See, e.g., AMP Limited Protest at 4-6; IMM Protest at 20.

PDF page 45

45 
proposal is just and reasonable.  The impetus for IRAS is to incent New Large Loads to 
bring new capacity to meet their resource adequacy needs.  PJM’s proposal achieves that 
objective by allowing New Large Loads to reduce or zero-out their IRAS eligibility by 
each UCAP MW of BYONC they contract with.  Introducing uncertainty to that 
arrangement by re-evaluating the BYONC’s ELCC and degree to which it addresses the 
New Large Load’s resource adequacy needs for each Delivery Year would undermine the 
BYONC incentive.   
In the first instance, the risk is borne by the BYONC generator as its capacity value 
will be reduced in future years should its ELCC value decline.  Moreover, although 
potentially more capacity would need to be procured if the ELCC value in the aggregate of 
all resources declines, the associated New Large Load would share in the cost of procuring 
the additional capacity to make up the difference.  Conversely, the ELCC value of the 
BYONC generator may increase after the initial year and result in lower costs because less 
capacity would need to be procured.   
Accordingly, the risk of changes to ELCC values (both increases and decreases) 
remains just as it is today—on individual generators in the first instance and all customers 
in the event that PJM has to purchase more capacity due to an aggregate ELCC decline.  
Engrafting into ELCC administration a one-off IRAS exception to that paradigm is not 
justified, as there is no change to the status quo risk allocation associated with ELCC 
changes.

PDF page 46

46 
6. 
MW that do not meet BYONC gating criteria and requirements or 
provide Allocated RBP UCAP MW should not reduce potential IRAS 
exposure. 
Several intervenors assert that additional categories of MW should reduce IRAS 
exposure.166  Those intervenors miss the mark, as the purpose behind reducing IRAS 
exposure to account for BYONC is “to incent New Large Loads to facilitate the 
development of new capacity so that the PJM Region has sufficient capacity to maintain 
reliability without entering into a capacity shortage and/or having to shed existing native 
load customers.”167  PJM proposed, in its August 13 Filing, to permit Large Loads to 
exclude themselves, in whole or in part, from the MW eligible for IRAS by bringing new 
capacity to PJM.  Importantly, exclusion from IRAS is intended to incentivize Large Loads 
to address the capacity shortfall caused by their rapid growth in the PJM Region through 
BYONC arrangements.  To that end, PJM proposed specific gating criteria and categories 
of qualifying BYONC.  As PJM explained in its initial filing, a meaningful contribution to 
the capacity shortfall must not be ephemeral or dissipate quickly and, furthermore, must 
meet gating criteria designed to stimulate development of new capacity.168  For BYONC 
to address the capacity needs of New Large Loads, and thus appropriately reduce IRAS 
exposure, BYONC must be Capacity Resources, with all attendant rights and obligations, 
and obtain capacity commitments.  Thus, for example, BYONC would be subject to the 
“capacity must-offer requirements and exceptions set forth in Tariff, Attachment DD, 
sections 6.6 and 6.6A,” and that the BYONC would be prohibited from “seek[ing] an 
 
166 See, e.g., Va. Governor Chief Energy Officer Comments at 2-4; CEBA Protest at 2-3; Equinix Protest, 
Request for Clarification and Comments at 14-17; NRG Comments and Limited Protest at 7-13.  
167 August 13 Filing, Transmittal Letter at 59. 
168 August 13 Filing, Transmittal Letter at 50.

PDF page 47

47 
exception to the capacity must-offer requirement to provide an external sale” during this 
10-year period.169  
a. 
Peak Shaving Adjustment MW are not comparable to 
BYONC and should not reduce IRAS exposure. 
Some intervenors challenge PJM’s omission of Peak Shaving Adjustment MW 
from BYONC arrangements that may reduce a Large Load’s exposure to IRAS.170  But, as 
the name implies, Peak Shaving Adjustments are adjustments to PJM’s load forecasts, not 
resources that may participate in RPM Auctions.171   
In the RBP proceeding, for example, PJM permitted Peak Shaving Adjustment MW 
that qualify for an opt-out to potentially reduce the identified 2027/2028 Delivery Year 
capacity shortfall for which the RBP will procure, but did not contemplate that Peak 
Shaving Adjustment MW might serve as either Qualifying RBP Offset UCAP MW or 
eligible RBP Resources.172  As intervenors recognize, PJM has proposed that Peak Shaving 
Adjustments be reported in the proposed Large Load Registry, which provides PJM with 
situational awareness of relevant metrics concerning Large Loads in the PJM Region, but 
PJM is not permitting Peak Shaving Adjustments to reduce IRAS exposure in the same 
way as BYONC. 
 
169 Proposed Tariff, Attachment DD-4, section VIII(b). 
170 See, e.g., Voltus Comments at 23-24; Equinix Protest, Request for Clarification and Comments at 14-17; 
Sunrun Comments at 5; Tesla Comments at 2; AEU Comments at 3; CEBA Protest at 8. 
171 Resource Adequacy Planning, PJM Manual 19: Load Forecasting and Analysis, PJM Interconnection, 
L.L.C., section 3.2, Development of the Forecast (rev. 39, June 30, 2026), https://www.pjm.com/-
/media/DotCom/documents/manuals/m19 [https://perma.cc/2JBC-BBDC] (“PJM Manual 19”). 
172 PJM Interconnection, L.L.C., Reliability Backstop Procurement to Address Resource Adequacy Concerns 
Stemming from Large Loads, Docket No. ER26-3380-000, Transmittal Letter at 36, 46-52 (July 31, 2026); 
id. at 51 (“RBP is designed to attract new supplies of capacity (i.e., new [Installed Capacity]), not merely 
incremental resource efficiencies, to address the current capacity shortfall and provide a stable, long-term 
source of capacity.”).

PDF page 48

48 
BYONC is, at bottom, new supplies of capacity needed to address the current 
shortfall and provide a stable, long-term source of capacity.  Peak Shaving Adjustments 
MW are not, by comparison, a real-time dispatchable product.  Depending on the Peak 
Shaving Adjustment plan, a program requires peak shaving on days in which a trigger is 
met or exceeded based on the actual maximum daily temperature-humidity index for the 
relevant PJM zone, scored over a rolling three-year period.173  Peak Shaving Adjustments 
are entirely dependent on the specific plan’s temperature-humidity index and are captured 
through forecast adjustment MW values.  Peak Shaving Adjustments are, at bottom, not a 
product that PJM can dispatch in real-time to provide reliable operations.  Thus, Peak 
Shaving Adjustments cannot and should not qualify as BYONC MW capable of reducing 
IRAS exposure. 
b. 
Demand Resources and DER Capacity Aggregation 
Resources that fail to meet the BYONC qualifications and 
gating requirements should not reduce IRAS exposure. 
With exception to the clarifications discussed in Part I.K below, offered in response 
to issues related to locations eligible to support BYONC based on Demand Resources 
and/or DER Capacity Aggregation Resources, intervenors’ arguments174 for expanding the 
categories of Demand Resources and DER Capacity Aggregation Resources that should 
qualify as BYONC, and thus reduce IRAS exposure, are unavailing.  Intervenors propose 
expansion of these categories as a means of “unlock[ing] new, and readily available, 
capacity quickly.”175  Again, intervenors’ positions fail to recognize the underlying purpose 
of BYONC, and the reason BYONC may reduce IRAS exposure—is to incentivize new 
 
173 PJM Manual 19, section 3.2. 
174 NRG Comments and Limited Protest at 7-13; AEU Comments at 5-6. 
175 SEIA Comments at 7.

PDF page 49

49 
and lasting capacity contributions to the capacity shortfall, with all attendant rights and 
obligations, and obtain capacity commitments.176  
IRAS is an operational tool designed to address the shortfall created by the absence 
of new Capacity Resources that offer lasting solutions to the capacity shortfall.  
Furthermore, as such, Demand Resources and DER Capacity Aggregation Resources that 
cannot demonstrate the Accredited UCAP requirement each year of the 10-year BYONC 
period is not a lasting solution.177  Some intervenors assert that Demand Resources and 
Aggregated DER Resources are improperly held to standards not imposed on other 
resources participating in a BYONC.178  But, the difference in the gating criteria for 
generation/storage resources and Demand Resources/DER is by design.  It is the outgrowth 
of PJM’s recognition that generation/storage resources are tied to physical assets.  For such 
resources, once there is “steel in the ground,” it becomes costly for such assets to exit the 
market early.  By contrast, Demand Resources and Aggregated DER Resources are, by 
nature, contracts or agreements.  Demand Resource and Aggregated DER Resource 
contracts and agreements are not inherently tied to one dedicated asset.  In addition, there 
are near-zero sunk costs associated with exiting the market or re-entering it, year-to-year.  
In other words, by design, that Demand Resources and Aggregated DER Resources may 
enter and exit the market year-to-year based on economic and other business decisions.  
 
176 August 13 Filing, Transmittal Letter at 50. 
177 In response to Calibrant Energy’s (“Calibrant”) request, PJM clarifies that this 10-year requirement is for 
participation in the capacity market, see August 13 Filing, Transmittal Letter at 55-57, and is not a 
requirement that any BYONC resource “must remain in service for the life of the New Large Load that it 
serves.”  Calibrant Comments at 8.  PJM further clarifies that BYONC once paired with a New Large Load 
cannot be paired with a different New Large Load unless the initial New Large Load goes out of business.  
See August 13 Filing, Transmittal Letter at 64.  The permanence of this arrangement relates to accounting 
for the BYONC resource’s capacity attributes with the New Large Load, and does not mean that the BYONC 
resource must remain in service permanently as long as the New Large Load is in service. 
178 SEIA Comments at 7.

PDF page 50

50 
Indeed, the ability for that Demand Resources and Aggregated DER Resources to easily 
enter and exit the market is one reason why, as NRG notes, Demand Resources and 
Aggregated DER Resources may serve as a “bridge to power.”179   
Finally, Advanced Energy United’s (“AEU”) recommendation that “PJM 
separately develop additional [Demand Response] product options, calibrated to a capped 
number of event hours per year” to allow New Large Loads to self-provide a meaningful 
share of its BYONC obligation is beyond the scope of this proceeding180 and, in any event, 
suggests that untested types of capacity contributions be credited for BYONC.    
G. 
Excluding New Large Loads from the VRR Curve Until They Bring New 
Capacity Properly Gives Effect to the Ratepayer Protection Pledge and 
Sends Appropriate Price Signals. 
Several entities challenge PJM’s proposal to remove New Large Loads (to the 
extent they have not brought capacity to offset their resource adequacy needs) from the 
VRR Curve used to clear RPM Auctions.  These entities each overlook that, pursuant to 
the Ratepayer Protection Pledge, the New Large Loads have committed to “build, bring, or 
buy the new generation resources and electricity needed to satisfy their new energy 
demands” and “add more capacity that serves the broader public by increasing supply” in 
order to “advance[] self-sufficiency and protect[] Americans from higher prices.”181  
 
179 NRG Comments and Limited Protest at 4. 
180 AEU Comments at 8. 
181 Ratepayer Protection Pledge; Ratepayer Protection Pledge Announcement; July 2026 Ratepayer 
Protection Pledge Update (identifying over 300 organizations that include over 250 utilities, cooperatives, 
and transmission cooperatives to municipal utilities and state associations, 44 data center developers, 7 
Artificial Intelligence companies, and 23 governors that joined the Ratepayer Protection Pledge.  The 44 data 
center developers include:  Aligned Data Centers, LLC; Amazon.com, Inc.; Applied Digital Corporation; 
Beale Infrastructure Group, LLC; Bitdeer Technologies Group; CleanSpark LLC; Cloud HQ LLC; Cologix, 
Inc.; Compass Datacenters, LLC; Core Scientific, Inc.; CoreWeave, Inc.; Corscale, LLC; Crusoe 
Technologies LLC; CyrusOne, Inc.; DataBank Holdings, Ltd.; Digital Realty Trust, Inc.; Diode Ventures, 
LLC, a Black & Veatch company; EdgeConnex Inc.; EdgeCore Digital Infrastructure (d/b/a EdgeCore 
Internet Real Estate, LLC); Equinix, Inc.; Google (d/b/a Alphabet Inc.); Iron Mountain Incorporated; Keel 
Infrastructure Corp.; Lambda; Meta Platforms, Inc.; Microsoft Corporation; Nebius Group N.V.; NTT Global 
Data Centers (d/b/a NTT DATA, Inc.); OpenAI, L.L.C.; Oracle Corporation; Oppidan Connect Data Centers

PDF page 51

51 
Excluding New Large Loads that have not yet brought new capacity from the VRR Curve 
recognizes and gives meaning to this commitment.   
The DCC claims that PJM “cannot expect new supply resources to appear if the 
price signals sent by the market do not reflect—as will be the case under PJM’s IRAS 
proposal--the actual load that must be served in the region.”182  The DCC completely 
ignores that the New Large Loads (many of which may be brought by members of the 
DCC) have committed, under the Ratepayer Protection Pledge, to “build, bring, or buy the 
new generation resources” need to meet their demand.  PJM expects new supply resources 
to appear to match the demand represented in the VRR Curve; the demand outside the VRR 
Curve—the New Large Loads—have committed to procure new capacity “build, buy, or 
bring” new capacity,183 actions which generally would occur outside the capacity market.  
PJM’s proposal merely effectuates the expectation that New Large Loads will follow 
through on their commitment, and if they do not, they will address their resource adequacy 
needs through the provision of IRAS.   
Similar to the DCC, EPSA contends that “existing resources ‘will presumably face 
lower prices and will never get the benefit of price formation that will price in new entry 
in the market as it is needed.’”184  But, this claim fails for the same reason—it presumes 
that New Large Loads should be served through the capacity market.  EPSA and the DCC 
 
(d/b/a Oppidan Investment Company); Prologis, Inc.; Quality Technology Services, LLC; Rowan Digital 
Infrastructure Pty. Ltd.; Skybox Datacenters, LLC; Skylar Opportunities LLC; STACK Infrastructure, Inc.; 
Starwood Digital Ventures (d/b/a Starwood Capital Operations, LLC); Stream Data Centers, L.P.; Switch, 
Inc.; T5Data Centers, LLC; TA Realty LLC; Vantage Data Centers Management Company, LLC; and x.AI 
LLC). 
182 DCC Protest at 25. 
183 Ratepayer Protection Pledge. 
184 EPSA Protest at 7 (quoting Affidavit of Paul M. Sotkiewicz, Ph.D. on Behalf of Electric Power Supply 
Association (Attachment A) ¶ 80).

PDF page 52

52 
would have everyone forget about or otherwise discount the commitments in the Ratepayer 
Protection Pledge and maintain the status quo so as to allow New Large Loads to continue 
to drive cost increases to ratepayers.185  Moreover, PJM’s capacity market was never 
designed to be the sole mechanism by which loads procure capacity.  Rather, it was always 
designed as producing a forward price signal that load and generation can contract around 
through bilateral arrangements.186  Adopting EPSA’s position would put the Commission 
in the anomalous position of ignoring the desire for long-term bilateral arrangements 
informed by the capacity price signal and instead exalting the capacity market as the 
exclusive means for setting capacity prices, terms, and conditions.  
Google echoes these arguments, asserting that removing certain New Large Loads 
from the VRR Curve would “mut[e] the demand signal and forc[e] capacity prices to a 
level that is lower than what is needed to attract investment in new generation.”  To put a 
finer point on it—the price signal that will result from the auction will reflect the loads the 
auction is designed to procure.  As such, contrary to Vistra Corp.’s (“Vistra”) claim 
otherwise, PJM’s proposal will not “disincentivize the entry [of new supply] needed to 
close any reliability gap remaining after the backstop auction.”187  Rather, the auction will 
continue to produce a price signal that incents supply to meet the needs of the 
 
185 See, e.g., Independent Market Monitor for PJM, State of the Market Report for PJM (May 14, 2026) 
https://www.monitoringanalytics.com/reports/PJM_State_of_the_Market/2026/2026q1-som-pjm.pdf 
[perma https://perma.cc/4DSL-2SCK] (“Based on actual auction clearing prices and quantities and uplift 
MW, inclusion of existing and forecast data center load growth resulted in a combined total increase in 
capacity market revenues for the 2025/2026 [Base Residual Auction], the 2026/2027 [Base Residual 
Auction], and the 2027/2028 [Base Residual Auction]of $23,100,955,341.  This total will continue to grow 
until the issues associated with the addition of large data center loads are addressed.”). 
186 See Tariff, Attachment DD, sections 1(b), 4.6, 5.2; PJM Interconnection, L.L.C., 119 FERC ¶ 61,318, at 
P 91 (2007) (“PJM adds that likely benefits of forward commitment include long-term contracting, incentives 
for investment, and a stable forward price signal that encourages long-term forward contracting, which in 
turn provides greater forward certainty for both capacity price and capacity adequacy.”). 
187 Vistra Protest at 20.

PDF page 53

53 
capacity-backed loads that are included in the demand curve, and the New Large Loads 
that have not entered into BYONC arrangements are appropriately excluded from the 
demand curve until such loads procure their own new supply.  Those entities that fail to 
arrange for BYONC will still be paying for capacity but may be eligible to provide IRAS 
and reduce consumption at a much earlier stage than their New Large Load counterparts 
who did arrange to bring new capacity to the market.  
Another complaint is that excluding the New Large Loads that have not entered 
into BYONC arrangements from the VRR Curve is “breaking supply and demand 
fundamentals.”188  This is incorrect.  The exclusion of New Large Loads from the demand 
curve is akin to the exclusion of energy-only resources from the supply curve in the 
capacity market.  That is, the purpose of the RPM Auction is to procure resources that are 
capable of providing capacity for loads that seek to receive capacity service.  New Large 
Loads that do not BYONC are effectively electing not to receive capacity service (at 
1-in-10 LOLE) so such loads are appropriately excluded from the demand curve because 
they are not electing to receive the capacity-backed service that RPM is designed to 
procure.  This is the same concept as why PJM excludes energy-only resources from the 
supply curve since those resources do not provide capacity to the system. In both cases, it 
is proper to exclude non-capacity backed loads and energy-only resources from the demand 
and supply curves, respectively, since the RPM Auction is designed to procure Capacity 
Resources to meet the needs of capacity-backed loads.189 
 
188 Google Protest at 14. 
189 The IMM also challenges PJM’s proposal but on the grounds that it does not go far enough.  The IMM 
advocates for permanently removing all data center loads from the capacity market, regardless of whether 
they have brought new capacity.  See IMM Protest at 11-12.  The IMM’s arguments are made in an effort to 
further its preferred approach of pulling all data centers out of PJM’s markets and procuring capacity for 
them in a separate process.  See id. at 37-40 & Attachment A.  The Commission has already rejected the 
IMM’s approach of allowing data centers to connect to the PJM system “only when they can be served

PDF page 54

54 
H. 
The IRAS Compensation Mechanism Benefits Ratepayers, Adheres to 
Cost Causation Principles, and Reflects a Division of Labor that Respects 
States’ Jurisdictional Authority over Retail Customers and Rates. 
The IRAS compensation mechanism adheres to cost causation principles by 
compensating LSEs, which are NITS customers who were requested to, and did in fact, 
reduce load in response to an IRAS Action.  The mechanism recognizes that, to the extent 
that LSEs serving Eligible New Large Loads are required to reduce consumption before 
Pre-Emergency Load Management in response to an IRAS Action, those LSEs are called 
on to reduce consumption before other NITS customers.  The mechanism targets wholesale 
rates for wholesale customers and, thus, falls squarely within the scope of PJM’s 
authority.190 
Nevertheless, several intervenors request that PJM clarify the IRAS rate and 
compensation mechanism,191 allege that the IRAS compensation mechanism is an 
improper attempt to create a retail compensation scheme for curtailed large loads,192 or 
assert that PJM has impermissibly delegated its authority to establish wholesale rates for 
wholesale service pursuant to the FPA.193  DCC asserts that, in spite of the IRAS 
compensation mechanism, requiring some NITS customers to reduce load prior to others 
would violate cost causation.194  None of these arguments pass muster.  The IRAS 
 
reliably as defined both by transmission and capacity adequacy.”  Indep. Market Monitor for PJM v. PJM 
Interconnection, L.L.C., 194 FERC ¶ 61,227, at P 1 (2026).  Leaving aside that PJM’s proposal is just and 
reasonable, consistent with both the applicable FPA section 205 standard and the Commission’s past rejection 
of this proposal from the IMM, the Commission likewise can easily dismiss the IMM’s proffered approach. 
190 EPSA, 577 U.S. at 264; see also PA Governors Answer at 12 (“PJM’s provision of wholesale 
compensation for a wholesale service . . . envisions making that wholesale compensation level subject to 
change by the relevant retail authority.”). 
191 See, e.g., OPSI Comments and Request for Clarification or to Sever at 7-8; Microsoft Comments at 4; PA 
Governor Answer at 14-15. 
192 FirstEnergy Limited Protest and Comments at 4.  
193 PPL Protest and Request for Clarification at 16. 
194 DCC Protest at 5.

PDF page 55

55 
compensation mechanism is, in fact, a balanced approach that is beneficial to ratepayers, 
adheres to cost causation principles, and respects the division of authority over wholesale 
and retail rates. 
1. 
The proposed compensation mechanism recognizes that LSEs 
subject to an IRAS Action that have been called on before 
Pre-Emergency Load Management should be compensated, in 
keeping with cost causation principles. 
The IRAS compensation mechanism recognizes that LSEs serving Eligible New 
Large Load customers are NITS customers.  Like other NITS customers, these LSEs would 
have their transmission service curtailed after non-firm customers.195  And, like other NITS 
customers, these LSEs would be allocated capacity charges based on their peak load.   
Indisputably, however, under IRAS, some LSEs serving Eligible New Large Loads 
may not receive all of the benefits of NITS customers despite having paid for capacity 
charges like other NITS customers.  Specifically, if LSEs serving New Large Loads are, 
pursuant to IRAS, called on to reduce their consumption before PJM calls on 
Pre-Emergency Load Management, such LSEs cannot be said to have received the benefit 
of the Pre-Emergency Load Management in the same way that other NITS customers 
would.   
DCC alleges that, under IRAS, calling on LSEs serving Eligible New Large Loads 
before Pre-Emergency Load Management would violate cost causation principles because 
Eligible New Large Loads will “pay the costs of capacity that only will be deployed after” 
they have been asked to reduce energy consumption.196   
 
195 August 13 Filing, Transmittal Letter at 94. 
196 DCC Protest at 20; see also Google Protest at 13 (arguing that being removed from the VRR Curve and 
assessed capacity charges “is not just and reasonable or consistent with cost causation”).

PDF page 56

56 
To be clear, while DCC is correct that “NITS customers serving Eligible New Large 
Loads still would be required to pay charges reflecting the cost of capacity committed 
through PJM’s capacity market,”197 DCC incorrectly alleges that the IRAS framework 
“forces . . . NITS customers to bear the costs of capacity that would not be available to 
meet their needs.”198   
The IRAS compensation mechanism addresses DCC’s concern by compensating 
LSEs serving Eligible New Large Loads under the limited circumstance in which an LSE 
has paid for but, unlike other NITS customers, not received the full benefit of, 
Pre-Emergency Load Management.  In the event the loads of those LSEs are, unlike other 
NITS customers, reduced under IRAS before Pre-Emergency Load Management, they 
would be compensated for such load reduction, in part, to account for the fact that these 
LSEs are, in the context of an IRAS Action, not treated as capacity-backed loads.  That is, 
in developing IRAS, PJM recognized that Eligible New Large Loads would not be able to 
obtain the full benefit, and therefore, consistent with cost causation principles, PJM 
proposed to compensate them for the load reduction service—both for the load reduction 
service provided and in exchange for the avoided capacity service not provided.  Thus, 
when viewed globally, PJM’s proposal is just and reasonable 
2. 
The IRAS compensation rate establishes a default, maximum rate, 
but provides states with the flexibility to establish lower 
compensation rates.  
As PJM notes in its initial filing, the proposed IRAS compensation rate neither 
mandates state-specific action nor imposes specific terms and conditions on retail rates.199  
 
197 DCC Protest at 5. 
198 DCC Protest at 5. 
199 August 13 Filing, Transmittal Letter at 104-08.

PDF page 57

57 
PJM has proposed a default IRAS compensation rate set at the Commission-accepted 
maximum rate of 50% of the Non-Performance Charge Rate.200  However, the IRAS 
compensation rate may be reduced, even to 0%, by the states and/or appropriate RERRAs 
at the retail level.  In short, PJM is using its authority to set the rates, terms and conditions 
associated with operational actions to reduce energy consumption as part of the 
Commission’s “sales for resale” jurisdiction.  As with all other aspects of ratemaking, the 
application of that rate to different retail customer classes is left to state jurisdictions.201  
The absence of state action will result in the application of a default rate of 50% of 
the Non-Performance Charge Rate.  As PJM’s initial filing furthermore notes,202 and the 
Pennsylvania Governor’s Office likewise explains, consistent with the Commission’s 
respect of state law choices in the demand response context, “provision of particular levels 
of compensation depend on certain conditions at retail.  In other words, just as eligibility 
to participate as wholesale demand response depends on permission under the relevant state 
laws and regulations, wholesale compensation for IRAS at a reduced level depends on 
RERRA action specifying such an alternate compensation level within the acceptable, just 
and reasonable range.”203   
 
200 August 13 Filing, Transmittal Letter at 102. 
201 See PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 at P 70 (“We expect that the additional cost 
transparency measures proposed in the following section will give state public utility commissions and other 
state regulators the information necessary to allow them to understand which transmission costs are caused 
by which transmission customers, so that they can sub-allocate these costs to the appropriate retail customers. 
Indeed, the Commission's objective in this proceeding is to respect the cooperative federalism approach 
established under the FPA. Specifically, one of the benefits of providing transparency on the costs of Network 
Upgrades necessary to provide transmission service to Eligible Customers on behalf of large loads is so that 
state regulators can use that information to protect residential and small commercial customers by 
incorporating those costs into the retail rates as they see fit given their authority to set rates for different 
classes of retail customers.”). 
202 August 13 Filing, Transmittal Letter at 102. 
203 PA Governor Answer at 15.

PDF page 58

58 
Lest there be any ambiguity, proposed Tariff, Attachement DD-4, Section X 
contemplates that the entities to be paid the rate and the loads to be charged to support such 
compensation are determined at the state level, in collaboration with relevant retail 
customers, and consistent with the Electric Distributor’s state-approved load reduction 
plans and other state-approved programs, rates, and rules.204   
 
The appropriate states and/or RERRAs, conferring with Electric Distributors, 
LSEs, and the relevant New Large Loads, may—but are not required to under PJM’s 
proposed Tariff provisions—reduce that rate and to even decide when and whether the 
IRAS rate should be reduced to zero.  PJM has, as the Pennsylvania Governor’s Office 
observes, “appropriately provided solicitude to the states by granting retail authorities a 
direct role in determining whether to provide wholesale compensation based on the 
curtailments directed under IRAS and, if so, how much compensation up to the cap 
proposed by PJM.”205 
I. 
IRAS Does Not Unduly Discriminate Against New Large Loads. 
Several protests assert that the IRAS framework unduly discriminates against New 
Large Loads based on vintage, size, or type.206  For reasons that PJM explained at length 
in its August 13 Filing, those arguments are unavailing, particularly when considered in 
the context of longstanding precedent. 
 
204 To the extent the Commission finds ambiguity, PJM consents to clarifying the proposed Tariff, 
Attachement DD-4, section X on compliance, consistent with the description of the provision in this section, 
if the Commission so directs.  Given the need to have the rules in place in a timely manner, PJM respectfully 
requests that the Commission prescribe the compliance requirement in as much detail as possible.   
205 PA Governor Answer at 3. 
206 See, e.g., Constellation Protest and Comments at 29.  Other intervenors argue that BYONC discriminates 
against Capacity Resources based on vintage and type (see, e.g., Vistra Protest at 3; Constellation Protest and 
Comments at 37; EPSA Protest at 2; America’s Power Protest at 8-10; NRG Comments and Limited Protest 
at 9).  Those arguments are addressed in this answer, above, in Part I.F.4.

PDF page 59

59 
According to well-settled precedent, “[w]hether a rate or practice is unduly 
discriminatory depends on whether it provides different treatment to different classes of 
entities and turns on whether those classes of entities are similarly situated.”207  When 
differences in treatment “can be explained by some factor deemed acceptable by the 
regulators (and the courts)”208 or “are predicated upon factual differences between 
customers,”209 they are justified and therefore not unduly discriminatory nor preferential.   
First, for reasons PJM has already explained at length in its initial filing and which 
PJM declines to repeat here,210 and as the PIOs state in their limited protest, “Large load 
customers are differently situated than traditional residential and commercial customers 
and warrant new rules and obligations.”211   
Second, as explained in PJM’s initial filing, the Commission has found that large 
loads constitute “a separate category of load[,]”212 and repeatedly highlighted the 
uniqueness of large loads.213  Far from being “legally irrelevant differences,” as Google 
alleges,214 these distinctions have repeatedly served as the foundation for the Commission’s 
 
207 Calpine Corp. v. PJM Interconnection, L.L.C., 171 FERC ¶ 61,035, at P 318, order on compliance, 
granting waiver request, addressing arguments raised on reh’g & setting aside prior order, in part, 173 
FERC ¶ 61,061 (2020), order on compliance & clarification, 174 FERC ¶ 61,036, order setting aside prior 
order, in part, 174 FERC ¶ 61,109 (2021). 
208 Town of Norwood v. FERC, 202 F.3d 392, 402 (1st Cir. 2000) (“[D]ifferential treatment does not 
necessarily amount to undue preference where the difference in treatment can be explained by some factor 
deemed acceptable by the regulators (and the courts).”). 
209 Cities of Newark v. FERC, 763 F.2d 533, 546 (3d Cir. 1985) (“[D]ifferences in rates are justified where 
they are predicated upon factual differences between customers.”). 
210 August 13 Filing, Transmittal Letter at 95-97. 
211 PIOs Limited Protest at 13.  
212 August 13 Filing, Transmittal Letter at 96 & n.257 (citing June 2026 Order to Show Cause, 195 FERC 
¶ 61,211 at P 50; FPA section 215, 16 U.S.C. § 824o). 
213 August 13 Filing, Transmittal Letter at 96-97 & nn.259, 261-62 (citing 2026 Order to Show Cause, 195 
FERC ¶ 61,211 at P 58; Sw. Power Pool, 195 FERC ¶ 61,196, at PP 84-85, 87 (2026)). 
214 Google Protest at 12.

PDF page 60

60 
finding that unique characteristics of large loads have given rise to unique, 
Commission-jurisdictional challenges.  Most recently, and indeed, as the Pennsylvania 
Governor’s Office notes, the IRAS proposal “focuses on distinctions among customers that 
are relevant to ensuring just and reasonable rates and reliable operation of the bulk power 
system.  Large load customers that today drive completely novel degrees of load growth 
pose unique operational challenges to the transmission system.”215 
Third, the applicability of IRAS is limited and narrowly tailored to address the 
specific situation where PJM may require that Electric Distributors reduce consumption by 
a MW quantity of load during certain, specifically defined emergency situations in years 
when a capacity shortfall triggers IRAS due to the influx of large loads.  IRAS is applicable 
only when New Large Loads that have not brought their own capacity and have not been 
allocated sufficient RBP UCAP MW cause a PJM Region Reliability Requirement 
shortfall.  Where the Commission has found that the treatment of large loads is “tailored to 
the specific and unique nature of” of such loads, the Commission has found that treatment 
just and reasonable and not unduly discriminatory or preferential.216  IRAS was developed 
to address the specific and unique issues caused by New Large Loads in the PJM Region, 
while also enabling New Large Loads to nevertheless be served by PJM.   
Fourth, the contention that IRAS unduly discriminates against large loads based on 
vintage—i.e., by distinguishing existing Large Loads from New Large Loads—fails to 
recognize that the relevant law on undue discrimination turns on whether the different 
treatment is justified.  Here, that different treatment has been fully justified. 
 
215 PA Governor Answer at 18.   
216 Sw. Power Pool, 195 FERC ¶ 61,196 at PP 85, 87.

PDF page 61

61 
As PJM explains in the August 13 Filing, only New Large Load may be eligible to 
provide IRAS.  At the beginning of IRAS, New Large Loads will consist of loads in-service 
after June 1, 2027.  In subsequent years, if the need for IRAS re-emerges, New Large Load 
will be designated as Large Load entering service after June 1 of the first Delivery Year 
that the PJM Region is short capacity.  The reasoning is straightforward.  IRAS applies in 
Delivery Years when the amount of Capacity Resources committed falls short of the PJM 
Region Reliability Requirement, because new load has come onto the PJM system without 
bringing their own capacity.217  New, not existing load, is the reason for the shortfall, which 
drives the need for IRAS.  Failing to make a distinction between New Large Loads and 
Large Loads for purposes of applying IRAS would fail to account for causation.  
Furthermore, as the Pennsylvania Governor’s Office correctly notes, the Commission 
regularly accepts new rules that apply only to new entrants.218 
J. 
PJM’s Proposal to Require FRR Entities to Bring New Capacity to Meet 
the Needs of New Large Loads Regardless of Need for IRAS in a Given 
Delivery Year Is Just and Reasonable and Treats All LSEs in PJM 
Equally. 
American Electric Power Service Corporation (“AEP”) seeks several clarifications 
regarding the proposed rules applicable to Fixed Resource Requirement (“FRR”) Entities.  
AEP’s proposed clarifications can be boiled down to this:  When the IRAS is not needed 
because the capacity market has secured sufficient capacity to meet the applicable 
 
217 August 13 Filing, Transmittal Letter at 39. 
218 PA Governor Answer at 18 & n.42 (citing Midcontinent Indep. Sys. Operator, Inc., 150 FERC ¶ 61,180, 
at P 21 (2015) (rejecting arguments that differing treatment between interconnection customers constitutes 
undue preference, where that difference is due to the fact that certain interconnection customers are subject 
to generator interconnection procedures and agreements that pre-date new reforms); ISO New Eng. Inc., 162 
FERC ¶ 61,205, at P 47 (2018) (rejecting protestors’ arguments that ISO New England Inc.’s inclusion of a 
cut-off date in the definition of resource types to which a particular capacity market rule would apply 
constitutes undue discrimination); December 2025 Show Cause Order, 193 FERC ¶ 61,217 at P 224 (“To the 
extent an entity is a party to an existing contract for such a purpose, we find that it is appropriate to grandfather 
such entity so that it may continue using BTMG for the current term remaining under the existing contract.”).

PDF page 62

62 
reliability requirement, PJM should relax the proposed rule prohibiting an FRR Entity from 
relying on Existing Generation Capacity Resources in its FRR Capacity Plan in excess of 
those Capacity Resources owned or contracted by the FRR Entity prior to June 1, 2027, as 
New Large Load.219  Such relaxation would allow an FRR Entity to use existing PJM 
Capacity Resources to meet the resource adequacy needs of its New Large Loads.   
The Commission should reject this request, as granting it would undermine the 
overarching policy driving IRAS and the Ratepayer Protection Pledge:  The resource 
adequacy needs of New Large Loads will be met through new capacity.  PJM proposed 
new RAA, section 7.8 to memorialize this policy as an obligation on all LSEs, including 
the LSEs within FRR Entities’ service territories.220  As PJM explained in the August 13 
Filing, “[t]he growth of Large Loads is an issue facing the entire PJM Region, and new 
capacity should arrive to serve their needs, regardless of whether the New Large Load is 
to be located in an FRR Service Area or the region served by RPM.”221  It is just and 
reasonable that all LSEs in PJM adhere to the same requirement of bringing new capacity 
to meet the needs of New Large Loads.  This is true regardless of whether the LSE meets 
its capacity needs under the capacity market rules or FRR rules.  Thus, an FRR Entity 
cannot utilize existing capacity outside of the FRR Entities’ territory to meet the resource 
adequacy needs of any New Large Load through its FRR Capacity Plan.222 
For its part, EKPC alleges that PJM’s exclusion of New Large Loads located in 
FRR Entities’ territories “unduly discriminates against RPM Capacity Market LSEs.”223  
 
219 AEP Comments and Request for Clarification at 9-17. 
220 See August 13 Filing, Transmittal Letter at 49-50; see supra Part I.C. 
221 August 13 Filing, Transmittal Letter at 74. 
222 See August 13 Filing, Transmittal Letter at 52. 
223 EKPC Limited Protest at 33.

PDF page 63

63 
Specifically, EKPC contends that “[i]t is unduly discriminatory to allow an FRR Entity that 
potentially could have an insufficient FRR Plan to avoid IRAS while load of a Self-Supply 
Entity participating in the RPM Capacity Market would be subject to IRAS.”224  This 
argument is without merit.  It is well established that “a finding of undue discrimination 
requires a showing that (1) two classes of customers are treated differently; and (2) the two 
classes of customers are similarly situated.”225  With respect to resource adequacy, FRR 
Entities are not similarly situated to LSEs participating in the capacity market.  By 
definition, FRR Entities must bring new capacity for all new loads within their territory.226  
If an FRR Entity does not include sufficient capacity in its FRR Capacity Plan, the FRR 
Entity is subject to “an FRR Commitment Insufficiency Charge, in an amount equal to two 
times the Cost of New Entry for the relevant location” multiplied by the MW of capacity 
short.227  In contrast, LSEs participating in RPM have no requirement to bring capacity 
sufficient to meet their needs—which is a primary reason why PJM is trying to incent New 
Large Loads to bring new capacity for their resource adequacy needs.  
 
224 EKPC Limited Protest at 33. 
225 TranSource, LLC v. PJM Interconnection, L.L.C., 168 FERC ¶ 61,119, at P 240 & n.769 (2019) (citing 
“Complex” Consol. Edison Co. of N.Y., Inc. v. FERC, 165 F.3d 992, 1012 (D.C. Cir. 1999); Advanced Energy 
Mgmt. All. v. FERC, 860 F.3d 656, 670-71 (D.C. Cir. 2017); Transmission Agency of N. Cal. v. FERC, 628 
F.3d 538, 549 (D.C. Cir. 2010) (“A rate is not ‘unduly’ preferential or ‘unreasonably’ discriminatory if the 
utility can justify the disparate effect. The court will not find a Commission determination to be unduly 
discriminatory if the entity claiming discrimination is not similarly situated to others.”) (internal quotations 
and citations omitted). 
226 See RAA, Article 1 (defining FRR Service Area and stating that “the FRR Entity has or assumes the 
obligation to provide capacity for all load (including load growth) within such area”).   
227 RAA, Schedule 8.1D, section 7.

PDF page 64

64 
K. 
Following Review and Stakeholder Feedback, PJM Consents to a Few 
Revisions to the Proposed Tariff Language.  
In addition, stakeholders have identified some clarifications to the proposed 
language that PJM agrees with and is willing to make on compliance, if directed by the 
Commission.228   
In particular, Calibrant and Voltus identify a clarifying revision to the text in 
proposed Tariff, Attachment DD-4, section VI(b)(ii)(1) related to the composition of 
Demand Resources or DER Capacity Aggregation Resources that may qualify as 
BYONC.229  PJM agrees that the “not” included in this section should be removed, as 
shown below, and provides additional clarifying language.   
(ii) For Demand Resources or DER Capacity Aggregation 
Resources, the resource must qualify as a Planned Demand 
Resource or DER Capacity Aggregation Resource, as described in 
the RAA, Schedule 6 and Schedule 6.2 and: 
(1) be composed of, or reliant on, the incremental amount of 
any location not registered in or prior to the 2026/2027 
Delivery Year at which an such incremental amount at that 
location is the result of the registration of new generation or 
storage assets at the location. However, to the extent three 
consecutive Delivery Years meet the requirements of Tariff, 
Attachment DD-4, section IV(b)(iii), then will be composed 
of, or reliant on, the incremental amount of any location 
registered in the Delivery Year prior to the first Delivery 
Year for which the requirements of Tariff, Attachment 
DD-4, section IV(b)(iii) are not met; and/or 
This “not” was inadvertently included in the proposed Tariff language.  With this 
correction and the additional clarifying language, the provision logically provides that only 
 
228 Cal. Indep. Sys. Operator Corp., 134 FERC ¶ 61,140, at P 1 (2011); id. PP 13-14, 42-43 (accepting 
changes to tariff language identified by the California Independent System Operator Corporation (“CAISO”) 
in its answer where CAISO agreed with intervenors that changes to the tariff would be consistent with 
CAISO’s intentions and CAISO indicated that it was willing to correct the error; accepting other tariff 
revisions correcting typographical and other errors). 
229 See Calibrant Comments at 6-7; Voltus Comments at 7-8.

PDF page 65

65 
incremental increases in load reduction capability above that which was previously 
registered due to the registration of new generation or storage at the underlying location 
will qualify as BYONC—which was PJM’s intent.230   
Similarly, in response to Voltus’s request,231 PJM agrees that “dormant” registered 
locations should be allowed to be reactivated to support BYONC resources.  Such locations 
are not currently supporting Capacity Resources, and therefore any capacity capability they 
can provide would be new as compared to the capacity on the system for the 2026/2027 
Delivery Year.  Accordingly, PJM consents to revising proposed Tariff, Attachment DD-4, 
section VI(b)(ii)(2) to make clear that registered locations not used in the capacity market 
for the 2026/2027 Delivery Year are eligible to support a BYONC arrangement. 
(2) be composed of, or reliant on, locations that did were not 
previously supported a Capacity Resource, a Peak Shaving 
Adjustment, or Price Responsive Demand for or prior to the 
2026/2027 Delivery Year. However, to the extent three 
consecutive Delivery Years meet the requirements of Tariff, 
Attachment DD-4, section IV(b)(iii), then will be composed 
of, or reliant on, locations that did were not previously 
supported a Capacity Resource, a Peak Shaving Adjustment, 
or Price Responsive Demand for the Delivery Year prior to 
the first Delivery Year for which the requirements of Tariff, 
Attachment DD-4, section IV(b)(iii) are not met. 
In addition, since PJM submitted the August 13 Filing, PJM identified a couple 
“clean-up” type ministerial revisions needed to the proposed Tariff, which are described 
below and that PJM is willing to make these clean up changes on compliance, if directed 
by the Commission.  Specifically, PJM identified the following ministerial clean-up 
changes to proposed Tariff, Attachment DD, section 5.10(a)(i): 
 
230 In response to Calibrant’s request, see Calibrant Comments at 7-8, PJM also clarifies that the measurement 
of the “incremental amount” will be a comparison of the location’s prior demand reduction capability against 
the location’s capability following the registration of new generation or storage assets at that location.   
231 See Voltus Comments at 10-11.

PDF page 66

66 
• For the Variable Resource Requirement curve for the 2029/2030 Delivery Year, 
the language describing point (1) includes two extraneous end parentheses.  
Specifically, the “)” should be deleted after “0.2 times Cost of New Entry” and 
at the end after “multiplied by 99%;” and 
• For the Variable Resource Requirement curve for the 2030/2031 Delivery Year 
and subsequent Delivery Years, the language describing point (1) includes an 
extraneous bracket after “multiplied by 99%” and the language for point 
(3) includes an extraneous bracket after “multiplied by 106.0%.” 
II. 
CONCLUSION 
PJM asks that the Commission consider this answer and accept the Tariff and RAA 
revisions proposed in this proceeding, effective October 12, 2026, as requested. 
Respectfully submitted, 
 
 /s/ Ryan J. Collins 
 
Craig Glazer 
Vice President–Federal Government Policy 
PJM Interconnection, L.L.C. 
1200 G Street, NW, Suite 600 
Washington, DC  20005 
(202) 423-4743  
craig.glazer@pjm.com 
 
Ryan J. Collins 
Vivian W. Chum 
Anne Marie Hirschberger 
Wright & Talisman, P.C. 
1200 G Street, NW, Suite 600 
Washington, DC  20005 
(202) 393-1200  
collins@wrightlaw.com 
chum@wrightlaw.com 
hirschberger@wrightlaw.com 
 
Mark J. Stanisz 
Associate General Counsel 
PJM Interconnection, L.L.C.  
2750 Monroe Blvd. 
Audubon, PA  19403 
(610) 666-8800 
mark.stanisz@pjm.com  
 
 
On Behalf of 
PJM Interconnection, L.L.C. 
 
September 23, 2026

PDF page 67

Appendix A 
 
Protests, Comments, Requests for Clarification, and Answers Filed to Date  
Docket No. ER26-3515-000

PDF page 68

Appendix A 
Protests, Comments, Requests for Clarification, and Answers Filed to Date  
Docket No. ER26-3515-000 
• ACORE Comments on PJM Interconnection LLC Interim Resource Adequacy 
Service Proposal (Sep. 3, 2026) (“ACORE Comments”) 
• Comments of Advanced Energy United (Sep. 3, 2026) (“AEU Comments”) 
• Comments and Request for Clarification of American Electric Power Service 
Corporation (Sep. 3, 2026) (“AEP Comments and Request for Clarification”) 
• Limited Protest of American Municipal Power, Inc. (Sep. 3, 2026) (“AMP Limited 
Protest”) 
• Protest of America’s Power (Sep. 3, 2026) (“America’s Power Protest”) 
• Motion to Intervene and Comments of Appalachian Voices (Sep. 3, 2026) 
(“Appalachian Voices Comments”) 
• Limited Comments of Buckeye Power, Inc. (Sep. 3, 2026) (“Buckeye Limited 
Comments”) 
• Motion for Leave to Answer and Answer of Buckeye Power, Inc. (Sept. 18, 2026) 
(“Buckeye Answer”) 
• Comments of Calibrant Energy (Sep. 3, 2026) (“Calibrant Comments”) 
• Comments of the Chief Energy Officer for the Governor of Virginia (Sep. 3, 2026) 
(“Va. Governor Chief Energy Officer Comments”) 
• Protest and Comments of Constellation Energy Generation, LLC (Sep. 3, 2026) 
(“Constellation Protest and Comments”) 
• Motion to Intervene and Protest of Corporate Energy Buyers Association (Sep. 3, 
2026) (“CEBA Protest”) 
• Motion for Leave to File Comments Out-of-Time and Comments of CyrusOne, LP 
(Sep. 11, 2026) (“CyrusOne Comments”) 
• Motion to Intervene and Protest of the Data Center Coalition (Sep. 3, 2026) (“DCC 
Protest”) 
• Comments of Dominion Energy Services, Inc. (Sep. 3, 2026) (“Dominion 
Comments”) 
• Limited Protest of East Kentucky Power Cooperative, Inc. (Sep. 3, 2026) (“EKPC 
Limited Protest”) 
• Protest of the Electric Power Supply Association (Sep. 2, 2026) (“EPSA Protest”)

PDF page 69

ii 
• Protest, Request for Clarification and Comments of Equinix Inc. on the Proposal of 
PJM Interconnection, L.L.C. to Establish Interim Resource Adequacy Service and 
a Large Load Registry to Address System Reliability (Sep. 4, 2026) (“Equinix 
Protest, Request for Clarification and Comments”) 
• Limited Protest and Comments of FirstEnergy Service Company (Sep. 3, 2026) 
(“FirstEnergy Limited Protest and Comments”) 
• Protest of Google LLC (Sep. 3, 2026) (“Google Protest”) 
• Answer of Google LLC (Aug. 31, 2026) (“Google Answer”) 
• Comments of Hans Royal (Sep. 3, 2026) (“Hans Royal Comments”)  
• Protest of the Independent Market Monitor for PJM (Sep. 3, 2026) (“IMM Protest”) 
• Comments of Industrial Energy Consumers of America (Sep. 15, 2026) (“IECA 
Comments”) 
• Protest and Comments of Joint Consumer Advocates (Sep. 3, 2026) (“JCA Protest 
and Comments”) 
• Comments of Microsoft Corporation (Sep. 3, 2026) (“Microsoft Comments”) 
• Motion to Intervene and Protest of Nicholas Max Neal and David Neal, Delaware 
Standard Offer Service Ratepayers (Sep. 3, 2026) (“Nicholas Max Neal and David 
Neal Protest”)  
• Supportive Comments and Limited Protest of the New Jersey Board of Public 
Utilities (Sep. 3, 2026) (“NJ BPU Comments and Limited Protest”) 
• Motion for Leave to Answer and Answer of the New Jersey Board of Public 
Utilities (Sept. 18, 2026) (“NJ BPU Answer”) 
• Limited Comments of North Carolina Electric Membership Corporation (Sep. 3, 
2026) (“NCEMC Limited Comments”) 
• Comments and Limited Protest of the NRG Companies (Sep. 3, 2026) (“NRG 
Comments and Limited Protest”) 
• Protest by Office of the Ohio Consumers’ Counsel (Sep. 3, 2026) (“OCC Protest”) 
• Comments and Limited Protests of Ohio Energy Leadership Council (Sep. 3, 2026) 
(“Ohio ELC Comments and Limited Protests”) 
• Comments of Old Dominion Electric Cooperative (Sep. 3, 2026) (“ODEC 
Comments”) 
• Comments, Request for Clarification, and, in the Alternative, Request to Sever of 
the Organization of PJM States, Inc. (Sep. 4, 2026) (“OPSI Comments and Request 
for Clarification or to Sever”)

PDF page 70

iii 
• Motion for Leave to Answer and Answer of Pennsylvania Governor Josh Shapiro 
(“PA Governor Answer”) 
 
• Comments of the Pennsylvania Public Utility Commission (Sep. 3, 2026) (“PA 
PUC Comments”) 
• Comments of Persistence Analytics Group LLC (Aug. 14, 2026) (“Persistence 
Analytics Comments”) 
• Supplemental Comments of Persistence Analytics Group LLS Regarding IRAS 
Performance Verification and Compensation (Sep. 2, 2026) (“Persistence Analytics 
Supplemental Comments”) 
• Comments of the PJM Industrial Customer Coalition (Sep. 3, 2026) (“PJMICC 
Comments”) 
• Protest of PJM Power Providers Group (Sep. 3, 2026) (“P3 Protest”) 
• Motion to Intervene, Protest, and Request for Clarification of PPL Electric 
Corporation (Sep. 3, 2026) (“PPL Protest and Request for Clarification”) 
• Limited Protest of Public Interest Organizations (Sep. 3, 2026) (“PIOs Limited 
Protest”) 
• Comments of the Public Service Commission of West Virginia (Sep. 3, 2026) 
(“PSCWV Comments”) 
• Comments of the Public Utilities Commission of Ohio’s Office of the Federal 
Energy Advocate (Sep. 3, 2026) (“Ohio FEA Comments”) 
• Motion to Intervene and Comments of the Retail Energy Supply Association (Sep. 
3, 2026) (“RESA Comments”) 
• Comments of the Solar Energy Industries Association (Sep. 3, 2026) (“SEIA 
Comments”) 
• Comments and Limited Protest of Southern Maryland Electric Cooperative, Inc. 
(Sep. 3, 2026) (“SMECO Comments and Limited Protest”) 
• Motion to Intervene and Comments of Sunrun Inc. (Sep. 3, 2026) (“Sunrun 
Comments”) 
• Motion to Intervene and Protest of Talen Energy Corporation (Sep. 3, 2026) 
(“Talen Protest”) 
• Comments of Tesla, Inc. (Sep. 3, 2026) (“Tesla Comments”) 
• Motion for Acceptance of Late-Filed Comments and Comments of the Virginia 
State Corporation Commission (Sep. 8, 2026) (“VSCC Comments”) 
• Protest of Vistra Corp. (Sep. 3, 2026) (“Vistra Protest”) 
• Comments of Voltus (Sep. 4, 2026) (“Voltus Comments”)

PDF page 71

CERTIFICATE OF SERVICE 
 
I hereby certify that I have this day served the foregoing document upon each 
person designated on the official service list compiled by the Secretary in this proceeding. 
 
Dated at Washington, D.C., this 23rd day of September 2026. 
 
 
 
 
 
 
 
 
 /s/ Ryan J. Collins 
  
Ryan J. Collins 
Wright & Talisman, P.C. 
1200 G Street, NW, Suite 600 
Washington, DC  20005 
collins@wrightlaw.com 
(202) 393-1200 
 
 
Attorney for 
PJM Interconnection, L.L.C.