ER27-25-000 · 2026-10-23 · Bloom Energy

Limited Protest of Bloom Energy Corporation

Read topic-matched comments in ER27-25

Topics in the text: Connecting load and generation

What the document says

PDF p. 4

Bloom: the 200 MW floor has no impact data behind it; lower it to 50 MW.

LARS should therefore apply to loads of 50 MW or more that connect to the Transmission System. PDF p. 4
Filed comments: Connecting load and generation

PDF p. 2

Bloom: the 200 MW floor has no impact data behind it; lower it to 50 MW.

MISO presents no EPR results or other grid impact study for 200 MW, and none for loads below it. PDF p. 2

PDF p. 5

Bloom: accept LARS by December 2, then order a 60-day compliance filing on the threshold.

Bloom does not ask the Commission to delay LARS. PDF p. 5
Filed comments: Connecting load and generation

PDF p. 1

Bloom: accept LARS by December 2, then order a 60-day compliance filing on the threshold.

Bloom supports LARS and urges the Commission to accept it by MISO's requested December 2, 2026 effective date. PDF p. 1
Filed comments: Connecting load and generation

Responses and related views

MISO defends a higher entry threshold

Midcontinent Independent System Operator · Direct response

MISO defended 200 MW based on its experience with large-load studies. It said modeling the load and several associated plants together offered the largest potential savings where loads and upgrades were especially large.

PDF pp. 23–24

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Connecting load and generation

LARS solves a real problem: today, load and generation studies run on different timelines, so each must wait on the other.
Read this passage Filed comments: Connecting load and generation

I. Limited Protest

printed heading · Topic match: Connecting load and generation

MISO's other safeguards already screen out speculative and de minimis requests: the $250,000 non-refundable deposit, the milestone payment, full site control, and the bar on aggregating multiple loads.16 And the pairing agreement, the same LRZ requirement, and the 15-year commitment – not load size…
Read this passage Filed comments: Connecting load and generation

II. Conclusion

printed heading

II.
Read this passage

Conclusion

printed heading · Topic match: Connecting load and generation

Bloom respectfully requests that the Commission (1) accept LARS effective December 2, 2026; and (2) direct MISO, in a compliance filing within 60 days, either to (a) align LARS eligibility with MISO's Large Load definition, with a corresponding generation-side minimum, or (b) provide record…
Read this passage Filed comments: Connecting load and generation

Certificate of Service

printed heading

Dated at Falls Church, VA this 23rd day of October, 2026. /s/ Joel D.