{"document":{"slug":"amendment-er27-432-spp-chills","title":"SPP corrects the Upper Missouri rate sheet for conditional large-load service","issued":"2026-11-10","accession":"20261110-5175","docket":"ER27-432-001","group":"SPP filings","filer":"Southwest Power Pool, Inc.","kind":"tariff amendment","file":"sources/originals/20261110-5175_01.pdf","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_Number=20261110-5175","sha256":"f0142df24e3abb50c39b84be343fb7ea02fdbf2be8baad99c9606a5d1b40dc6d","pages":5,"tokens":1168,"emptyPages":[]},"pages":[{"page":1,"startToken":0,"endToken":260,"text":"November 10, 2026 \nVIA ELECTRONIC FILING \n \nThe Honorable Debbie-Anne A. Reese \nSecretary \nFederal Energy Regulatory Commission \n888 First Street, N.E. \nWashington, D.C. 20426 \nRe: \nSouthwest Power Pool, Inc., Docket No. ER27-432-___ \nAmendment to Tariff Filing \nDear Secretary Reese: \nPursuant to Sections 35.17 and 385.215 of the Federal Energy Regulatory \nCommission’s (“Commission”) Rules and Regulations, 18 C.F.R. §§ 35.17 and \n385.215, Southwest Power Pool, Inc. (“SPP”) submits this amendment to the proposed \nrevisions to the SPP Open Access Transmission Tariff (“Tariff”)1 submitted by SPP in \nDocket No. ER27-432-000 on November 6, 2026 (“November 6 Filing”).2 Pursuant to \nthe Commission’s regulations, a public utility may file to amend a tariff that has not \nbecome effective and upon which no Commission or delegated order has yet been \nissued.3 Amendment of the November 6 Filing is permitted because no Commission or \ndelegated order has been issued in the docket. SPP respectfully requests the \nCommission issue an order accepting the November 6 Filing as amended herein, with \nthe originally requested effective date of February 1, 2027.\n \n1  \nSouthwest Power Pool, Inc., Open Access Transmission Tariff, Sixth Revised Volume \nNo. 1. References in this filing to “Tariff” refer to the version of SPP’s Tariff currently \nin effect.  “Proposed Tariff” refers to a version reflecting the revisions proposed in this \nproceeding. \n2  \nSubmission of Tariff Revisions to Revise Schedule 15 and Attachment T for the SPP \nWest Region of Southwest Power Pool, Inc., Docket No. ER27-432-000 (November 6, \n2026). \n3  \n18 C.F.R. § 35.17(b)."},{"page":2,"startToken":260,"endToken":639,"text":"The Honorable Debbie-Anne A. Reese \nNovember 10, 2026 \nPage 2 \n \nI. \nBACKGROUND \n \nSPP submitted the November 6 Filing to add provisions for Conditional High \nImpact Large Load Service (“CHILLS”) for pricing Zones in the SPP West Region, \nand to make other clarifying edits.  \n \nII. \nDESCRIPTION OF AMENDED FILING \n \nIn the November 6 Filing, SPP proposed revisions to rate sheets for Point-To-\nPoint Transmission Service in the SPP West Region. SPP inadvertently omitted \nrevisions to the rate sheet for the Upper Missouri Zone to add references to Schedule \n14 and Incremental Market Efficiency Use revenues. SPP proposes the following \nrevisions: \n \nPoint-To-Point Transmission Service and Conditional High Impact Large \nLoad Service Revenue Crediting for Point-To-Point Rates \nRates for Point-To-Point Transmission Service under this Attachment T shall \nreflect any adjustments for Schedules 7, and 8 revenues, 14, Schedule and 15 \nrevenues, Incremental Market Efficiency Use revenues, and revenues \ndistributed and allocated under Attachment AU, implemented in accordance \nwith Section 34.1(2) of this Tariff. The rates, including any applicable \nadjustments for Schedules 7, and 8, 14 revenues, andSchedule 15 revenues, \nIncremental Market Efficiency Use revenues, and revenues distributed and \nallocated under Attachment AU, shall be set forth in the RRR File.4 \n \nIn SPP’s filing to expand its Regional Transmission Organization,5 SPP added \nZone 19 West to include the geographic area of the Upper Missouri Zone located in the \nWestern Interconnection. The rate sheet for the Upper Missouri Zone is applicable to \nentities located in the Upper Missouri Zone East (“Zone 19 East”) and the Upper \nMissouri Zone West (“Zone 19 West”). \n \n First, SPP adds a reference to Schedule 14 for the DC Tie Access Charge. The \nDC Tie Access Charge is defined as “[a] charge on a transmission reservation utilizing \na West DC Tie that sinks outside of the Zone where the West DC Tie is located.”6 The \nTransmission Customer is responsible for the DC Tie Access Charge determined in \n \n4  \nProposed Tariff, Attachment T Upper Missouri Zone. \n5  \nSouthwest Power Pool, Inc., Submission of Revisions to Tariff, Bylaws, and \nMembership Agreement to Expand the Regional Transmission Organization into the \nWestern Interconnection (Part 1 of 2), Docket No. ER24-2184-000 and (Part 2 of 2), \nDocket No. ER24-2185-000 (June 4, 2024). \n6  \nTariff, Part I, Section 1 – Definitions D."},{"page":3,"startToken":639,"endToken":960,"text":"The Honorable Debbie-Anne A. Reese \nNovember 10, 2026 \nPage 3 \n \nSchedule 14 of the Tariff. SPP adds this reference to the Upper Missouri Zone rate \nsheet because the DC Tie Access Charge is applicable in this Zone. \n \nSecond, SPP adds a reference to Incremental Market Efficiency Use revenues. \nThe Incremental Market Efficiency Use Charge is “[a] market recovery mechanism to \ncompensate West DC Tie Transmission Owners for the expected loss of life of certain \nWest DC Tie facilities due to increased utilization of the West DC Ties by the \nIntegrated Marketplace.”7 SPP adds this reference to the Upper Missouri Zone rate \nsheet because Incremental Market Efficiency Use revenues are applicable in this Zone. \n \nSPP is not including revisions, as proposed in the November 6 Filing to other \nrate sheets, to remove the references to Attachment AU revenues from this rate sheet \nbecause the Upper Missouri Zone includes utilities in the SPP East Region. \n \nIII. \nADDITIONAL INFORMATION \n \nA. \nInformation Provided Per Commission Regulations8 \n \n1. \nDocuments submitted with this filing: \nIn addition to this Transmittal Letter, Clean and Redlined Tariff \nrevisions under the Sixth Revised Volume No. 1. \n2. \nService: \nSPP has electronically served a copy of this filing on all its \nMembers, Transmission Customers, and Market Participants. A \ncomplete copy of this filing will be posted on the SPP web site, \nwww.spp.org, and is also being served on all affected state \ncommissions. \n3. \nRequisite agreements: \nNot Applicable. \nB. \nCommunications \nCorrespondence and communications regarding this filing should be \nsent to, and SPP requests that the Secretary include on the official \nservice list, the following: \nJustin A. Hinton \nSenior Attorney \nTessie Kentner \nDirector & Associate General Counsel \n \n7  \nTariff, Part I, Section 1 – Definitions I. \n8  \nBecause the revisions to the Tariff submitted herein do not involve any changes in \nrates, the use of the abbreviated filing procedures set forth in 18 C.F.R. § \n35.13(a)(2)(iii) is appropriate."},{"page":4,"startToken":960,"endToken":1108,"text":"The Honorable Debbie-Anne A. Reese \nNovember 10, 2026 \nPage 4 \n \nSouthwest Power Pool, Inc. \n201 Worthen Drive \nLittle Rock, AR 72223 \nTelephone: (501) 482-2468 \njhinton@spp.org  \n \nSouthwest Power Pool, Inc. \n201 Worthen Drive \nLittle Rock, AR 72223 \nTelephone: (501) 688-1782 \ntkentner@spp.org  \nIV. \nCONCLUSION \n \nSPP is not requesting any other amendments or modifications to the November \n6 Filing. As stated previously, amendment of the November 6 Filing in this proceeding \nis permitted because no Commission or delegated order has been issued on the \nNovember 6 Filing, For the reasons stated herein, SPP respectfully requests that the \nCommission issue an order accepting the November 6 Filing, as amended herein, as \njust and reasonable, with an effective date of February 1, 2027. \n \nRespectfully submitted, \n \n/s/ Justin A. Hinton \nJustin A. Hinton \nSouthwest Power Pool, Inc. \n201 Worthen Drive \nLittle Rock, AR  72223-4936 \n  \nAttorney for  \nSouthwest Power Pool, Inc."},{"page":5,"startToken":1108,"endToken":1168,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have this day served the foregoing document upon each \nperson designated on the official service list compiled by the Secretary in this proceeding. \n \nDated at Little Rock, AR, this 10th day of November, 2026.  \n \n \n \n \n \n \n/s/ Michelle Harris \n \n \n \n \n \n \nMichelle Harris \n \n \n \n \n \n \nSouthwest Power Pool, Inc. \n \n \n \n \n \n \n201 Worthen Drive \n \n \n \n \n \n \nLittle Rock, AR 72223-4936 \n \n \n \n \n \n \n(501) 614-3200"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":65,"startToken":0,"endToken":270},{"p":2,"at":65,"title":"I. BACKGROUND","method":"printed heading","endPage":2,"endAt":279,"startToken":270,"endToken":303},{"p":2,"at":279,"title":"II. DESCRIPTION OF AMENDED FILING","method":"printed heading","endPage":3,"endAt":959,"startToken":303,"endToken":793},{"p":3,"at":959,"title":"III. ADDITIONAL INFORMATION","method":"printed heading","endPage":3,"endAt":991,"startToken":793,"endToken":796},{"p":3,"at":991,"title":"A. Information Provided Per Commission Regulations8","method":"printed heading","endPage":3,"endAt":1530,"startToken":796,"endToken":878},{"p":3,"at":1530,"title":"B. Communications","method":"printed heading","endPage":4,"endAt":298,"startToken":878,"endToken":1004},{"p":4,"at":298,"title":"IV. CONCLUSION","method":"printed heading","endPage":5,"endAt":0,"startToken":1004,"endToken":1108},{"p":5,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":5,"endAt":459,"startToken":1108,"endToken":1168}]}