{"document":{"slug":"filing-er27-522-pjm-ride-through","title":"PJM files ride-through and operating requirements for large computational loads under section 205","issued":"2026-11-16","accession":"20261116-5309","docket":"ER27-522-000","group":"PJM filings","filer":"PJM Interconnection, L.L.C.","kind":"filing","file":"sources/originals/20261116-5309_01.pdf","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_Number=20261116-5309","sha256":"4fd2bb8c85194eae383a571c67dcf6b82e3ff555ec7401a0cebf3dc5b4125396","pages":27,"tokens":8260,"emptyPages":[]},"pages":[{"page":1,"startToken":0,"endToken":378,"text":"PJM Interconnection, L.L.C. \n2750 Monroe Blvd. \nAudubon, PA 19403 \n \nArleigh P. Helfer \nSr. Counsel \nT:  (610) 666-4370  \narleigh.helfer@pjm.com \n \n \n \n \n \n \n \n \nNovember 16, 2026 \n \nThe Honorable Debbie-Anne A. Reese \nSecretary  \nFederal Energy Regulatory Commission \n888 First Street, N.E. \nWashington, D.C. 20426-0001 \n \nRe: \nPJM Interconnection L.L.C., Docket No. ER27-____-000,  \nProposal to Address Operational Requirements for Large Computational Load and \nEstablish an Annual Transmission Service Reporting Requirement \n \nDear Secretary Reese: \n \nPursuant to Section 205 of the Federal Power Act1 and the August 14, 2026 letter order \nissued in Docket No. EL26-67-000,2 PJM Interconnection, L.L.C. (“PJM”) hereby submits \nrevisions to the PJM Open Access Transmission Tariff (“Tariff”)3 to establish disturbance ride-\nthrough requirements applicable to Eligible Customers taking transmission service on behalf of \nLarge Computational Loads, a targeted subset of Large Loads4 that may pose heightened \noperational risks to the Bulk Electric System and PJM Transmission System during grid \n \n1 16 U.S.C. § 824d. \n2 PJM Interconnection, L.L.C., 196 FERC ¶ 61,129, at P 10 (2026) (noting that to extent PJM submits “an FPA section \n205 filing addressing the Commission’s preliminary findings in the Show Cause Order on or before November 16, \n2026, then the obligation of the respondent(s) who have made such an FPA section 205 filing to file a response to the \nShow Cause Order will be suspended[.]”).  \n3 For the purpose of this filing, capitalized terms not defined herein shall have the meaning as contained in the Open \nAccess Transmission Tariff (“Tariff”), the Amended and Restated Operating Agreement of PJM (“Operating \nAgreement”), and the Reliability Assurance Agreement Among Load Serving Entities in the PJM Region (“RAA”). \n4 PJM Interconnection, L.L.C., 197 FERC ¶ 61,019, at PP 2, 16, 27–30 (2026) (accepting, effective October 12, 2026, \nPJM’s proposed definition of Large Load as “end-use customer(s) load that has a cumulative peak load of 50 [MW] \nor greater at a single electrical site behind one or more points of interconnection, where for configurations involving \nmultiple affiliated load facilities or multiple points of interconnection with affiliated load facilities behind them, all \naffiliated load facilities within a one-mile radius will be considered a single electrical site as further described in the \nPJM Manuals.”)."},{"page":2,"startToken":378,"endToken":792,"text":"Honorable Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 2 \n \n2 \n \ndisturbances.  PJM is also proposing additional Tariff language to address ramp rates and other \n“ongoing operational requirements,” as described in the June 18, 2026 Show Cause Order.5   PJM \nis also proposing, on compliance, an annual transmission service reporting requirement.6 \nThe Tariff language proposed herein is being filed in response to the Commission’s \npreliminary finding, in the Show Cause Order,7 “that PJM’s Tariff appears to be unjust and \nunreasonable because it lacks provisions addressing ongoing operational requirements for \ntransmission customers taking transmission service on behalf of large loads.”8  PJM submits this \nfiling pursuant to its independent authority to modify its Tariff under FPA section 205 pursuant to \nTariff, Part I, section 9.2(a) and the Consolidated Transmission Owners Agreement (“CTOA”), \nsection 7.5.1(ii), following the requisite consultation specified under Tariff, Part I, section 9.2(b) \nand the CTOA, section 7.5.1(ii). \n \n5 PJM Interconnection, L.L.C., et al., 195 FERC ¶ 61,211, at P 64 (2026) (“Show Cause Order”) (“[W]e preliminarily \nfind that PJM’s Tariff appears to be unjust and unreasonable because it lacks provisions addressing ongoing \noperational requirements for transmission customers taking transmission service on behalf of large loads.”  Those \nongoing operational requirements include: “ramp rates,” “ride-through requirements,” “PJM hourly forecasts, \ntelemetry data, and other data to ensure sufficient visibility,” “equipment to enable PJM to monitor large load for \nimpacts,” equipment “enabling PJM to remotely disconnect large loads when necessary,” and specification of \n“necessary control technologies or protection systems.”). \n6 PJM will promptly submit a letter in Docket Nos. EL25-49 and EL26-27 informing participants of today’s tariff \nfilings, some parts of which are submitted in compliance with Commission directives and others of which are \nsubmitted pursuant to Section 205 of the FPA.  In an abundance of caution, PJM requests waiver of any regulation or \nfiling requirements relating to submissions in Docket Nos. EL25-49 and EL26-27 relating to today’s tariff \nfilings.  Good cause exists to grant any necessary waivers because submission of these tariff filings in the structure \npresented efficiently addresses the complexity of the overlapping filing obligations and differing requested effective \ndates, PJM is providing prompt notice to participants in other relevant EL dockets of today’s filings, and PJM is \nrequesting a sixty-day comment period and 120 day Commission action date that affords interested participants \nreasonable time to engage in the tariff filing dockets. \n7 Id. \n8 Id. at P 64."},{"page":3,"startToken":792,"endToken":1134,"text":"Honorable Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 3 \n \n3 \n \nThe proposed Tariff revisions mitigate threats to the reliability of the Transmission System \nand Bulk Electric System posed by Eligible Customers taking transmission service on behalf of \nLarge Computational Loads by:     \n(1) defining Large Computational Loads, a subset of Large Loads that may pose \nheightened operational risks in the PJM Region, and thus trigger operational \nrequirements on Eligible Customers serving them;  \n(2) setting the framework for minimum voltage ride-through and frequency ride-through \nrequirements with which Eligible Customers taking transmission service on behalf of \nLarge Computational Load must comply, which establishes the necessary groundwork \nfor more detailed ride-through standards to be promulgated through revisions to PJM’s \nManuals; and \n(3) setting a framework for other operational requirements to be established in the \nManuals, with which Eligible Customers taking transmission service on behalf of Large \nComputational Load must comply, relating to:  ramp rate requirements, \nelectromagnetic transient performance requirements, operation, coordination, and \nmaintenance of necessary auxiliary equipment, control technologies and protection \nsystems, \nmaintenance \noutage \nprotocols, \nremote \ndisconnection \ncapabilities \nrequirements, telemetry/data exchange requirements, and data and communication \nrequirements. \nThe proposed Tariff provisions setting forth ride-through and other operational \nrequirements state that these requirements on Eligible Customers taking transmission service on \nbehalf of Large Computational Loads shall be set forth in PJM’s Manuals.9  At present, PJM is at \nan advanced stage of the process for developing Manual language for the ride-through \nrequirement.  PJM plans to commence stakeholder engagement in early 2027 to develop Manual \n \n9 PJM Large Computational Load Operational Review, PJM Interconnection, L.L.C., at slide 15 (Oct. 6, 2026), \nhttps://www.pjm.com/-/media/DotCom/committees-groups/committees/pc/2026/20261006/20261006-item-07-a---1-\nlcl-ride-through-requirements-background---presentation.pdf; \nid. \nat \nslide \n25, \nhttps://www.pjm.com/-\n/media/DotCom/committees-groups/committees/pc/2026/20261006/20261006-item-07-b---1-lcl-ride-through-\nrequirements-solution---presentation.pdf; PJM’s Response Matrix to the Large Load Show Cause Order \nOpportunities, \nPJM \nInterconnection, \nL.L.C., \nOperational \nRequirements \nsection \n(Oct. \n29, \n2026),  \nhttps://www.pjm.com/-/media/DotCom/committees-groups/committees/mc/2026/20261105-special/item-01---2-\nlarge-load-compliance-matrix.pdf."},{"page":4,"startToken":1134,"endToken":1552,"text":"Honorable Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 4 \n \n4 \n \nlanguage and requirements applicable to other operational requirements set forth in the Show \nCause Order.   \nPJM respectfully requests that the Commission accept the proposed Tariff revisions \naddressing ride-through requirements and the Tariff language establishing the framework for other \nproposed operational requirements in the Manuals, effective January 16, 2027, which is 61 days \nafter the date of this filing.10   \nFor the reasons set forth below, the proposed revisions are just and reasonable.  However, \nif the Commission deems necessary, and to help facilitate the Commission’s acceptance of this \nfiling without delay so that PJM can address the short-term needs for ride through requirements, \nPJM provides notice that it consents to the Commission’s exercise of authority to sever any \nelement of the proposed Tariff language to the extent necessary and permitted under sections 205 \nand 206 of the FPA and NRG Power Marketing, LLC v. FERC.11  In particular, PJM consents to \nseverance of the ride-through requirements from Tariff revisions proposed herein that pertain to \nother operational requirements because, as discussed further below, recent large load transfer \nevents have made it abundantly clear that PJM already faces the serious reliability concerns that \n \n10 In a separate FPA section 205 filing concurrently submitted today, PJM is proposing a later effective date of March \n16, 2027, for other proposed revisions to PJM’s governing documents, including the addition of transmission products \nfor Eligible Customers taking transmission on behalf of Large Loads.  Attachment D to that other filing includes a \nChart Mapping Order Directives to Tariff Changes, some of which are the subject of the instant filing.   \n11 NRG Power Mktg., LLC v. FERC, 862 F.3d 108 (D.C. Cir. 2017).  As the Commission has often stated, “[t]he \nUnited States Court of Appeals for the District of Columbia Circuit has held that, in certain circumstances, the \nCommission has ‘authority to propose modifications to a utility’s [FPA section 205] proposal if the utility consents to \nthe modifications.’”  N.Y. Indep. Sys. Operator, Inc., 188 FERC ¶ 61,051, at P 22 n.36 (2024) (alteration in original) \n(citing NRG Power Mktg., 862 F.3d at 114–15); see Midcontinent Indep. Sys. Operator, Inc., 180 FERC ¶ 61,141, at \nP 26 n.29 (2022) (same), order on reh’g, 182 FERC ¶ 61,096 (2023), aff’d sub nom., Entergy Ark., LLC v. FERC, 109 \nF.4th 583 (D.C. Cir. 2024); ISO New Eng. Inc., 175 FERC ¶ 61,172, at P 16 n.20 (2021) (same)."},{"page":5,"startToken":1552,"endToken":1852,"text":"Honorable Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 5 \n \n5 \n \nare driving the need for the ride-through requirements in the short term.  Indeed, the Manual \nlanguage for the ride-through requirements are in an advanced stage of development. \nLastly, PJM is also addressing the Commission’s compliance directive in the June 2026 \nCo-Located Load Order requiring an annual report regarding the provision of new transmission \nservices.12  PJM proposes to post on its website a report containing information about the demand \nfor and use of:  Network Integration Transmission Service to the extent Interim Network \nIntegration Transmission Service was also requested; Interim Network Integration Transmission \nService; Firm Contract Demand Service; and Non-Firm Contract Demand Service, in a manner \nconsistent with the method and substance of the Commission’s compliance directive.13  This \nproposed revision is just and reasonable because the annual report would give the Commission, \nstates, PJM market participants, and stakeholders the benefit of additional transparency about the \nnew transmission services being offered in PJM.  The Commission should accept this annual report \nproposal as just and reasonable or on compliance with the Co-Located Load Order.14     \nI. \nBACKGROUND \nA. \nPJM Already Faces Risks Arising from Large Load-Transfer Events that \nNecessitate Ride-Through Requirements \nUnlike many of the other Regional Transmission Organizations and Independent System \nOperators (“RTOs/ISOs”) in the country, PJM already has approximately 10 GW of computational \nload in its footprint and, in recent years, has already experienced the reliability and operational \nimpacts of large load transfer events.  For example: (1) on July 10, 2024, an approximately 1.5 \n \n12 PJM Interconnection, L.L.C., 195 FERC ¶ 61,209, at PP 579–580 (2026) (“Co-Located Load Order”). \n13 Proposed Tariff, Part III, section 28.2; Proposed Tariff, Part XI, section 718.2. \n14 PJM’s filing does not further address this proposed revision."},{"page":6,"startToken":1852,"endToken":2187,"text":"Honorable Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 6 \n \n6 \n \ngigawatt (“GW”) large load transfer event caused frequency to increase to 60.047 Hz and voltage \nto increase to 1.07 per unit (“p.u.”), (2) on February 17, 2025, an approximately 1.8 GW large load \ntransfer event caused frequency to increase to 60.047 Hz and voltage to increase to 1.07 per unit \n(“p.u.”),  and (3) on July 22, 2026, an approximately 3.9 GW large load event caused frequency in \nthe Eastern Interconnection to reach 60.092 Hz and voltage to increase with a peak of ~1.138 p.u.15  \nAs such, establishing minimum voltage ride-through and frequency ride-through requirements \nstandards for Eligible Customers serving large loads is particularly critical to the reliability of the \nPJM Region.   \nAccording to the testimony of PJM Senior Manager, Generation Modeling and Dynamics \nStudies in the Planning Division Mr. David Egan, transfer events such as the one that occurred this \npast July “demonstrate[] how large amounts of load can disconnect in a very short period of time \nin response to transmission system conditions” which “can unnecessarily introduce additional \ndynamic impacts and exacerbate the underlying disturbance.”16   \nCritically, Mr. Egan explains, “[w]hen a large block of load disconnects unexpectedly, the \nactual system response may differ substantially from the conditions anticipated by planners and \noperators. Such disconnects can alter power flows, voltage profiles, frequency response, and \nsystem dynamics across a broad geographic area.”17  Mr. Egan further explains:  \nWhen several thousand megawatts of load disconnect within a short period of time, \nthe resulting changes in voltage, frequency, and power flows can alter the response \nof generators throughout the interconnected system. These changes can affect the \noperation of excitation systems, voltage regulators, turbine-governor controls, and \n \n15 PJM Large Computational Load Operational Review, PJM Interconnection, L.L.C., (Sept. 15, 2026), \nhttps://www.pjm.com/-/media/DotCom/committees-groups/committees/pc/2026/20260915/20260915-item-02---lcl-\nride-through-requirements-background-education---presentation.pdf  \n16 Egan Declaration ¶ 14. \n17 Egan Declaration ¶ 15."},{"page":7,"startToken":2187,"endToken":2465,"text":"Honorable Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 7 \n \n7 \n \nother plant control systems that are responding to system conditions. As the \nmagnitude and concentration of load transfers increase, so does the potential for \nthese impacts to affect the broader interconnected system and complicate the \nrestoration of stable system conditions following a disturbance.18 \n \nSuch events pose serious threats to the reliability and safety of the Bulk Electric System in \nthe PJM Region.  In this regard, the Commission’s Show Cause Order states that PJM’s Tariff \nappears to be unjust and unreasonable because it “does not specify ramp rate or ride-through \nrequirements which the transmission customer taking transmission service on behalf of the large \nload must comply.”19 The Show Cause Order also recognizes the “unique nature of . . . large loads \ncreates challenges for operation of the transmission system and necessitates greater visibility and \noperational control when providing transmission service to transmission customers on behalf of \nlarge loads, without which the reliability of the transmission system could be at risk.”20 \n \nThe industry is facing unprecedented load growth, driven largely by data centers. PJM’s \nload forecast predicts peak load growth of 32 GW from 2024 to 2030, 30 GW of which is \nattributable to data centers.21 PJM is expected to host as much as 70% of future U.S. data center \ndevelopment, representing highly concentrated demand, especially in northern Virginia’s “data \ncenter alley.”  Thus, the proposed Tariff revisions are not only directly responsive to the Show \nCause Order but are necessary to ensure the reliability and safety of PJM’s systems. \n \n18 Egan Declaration ¶ 16. \n19 Show Cause Order at P 64. \n20 Id. \n21 Id. at P 8."},{"page":8,"startToken":2465,"endToken":2760,"text":"Honorable Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 8 \n \n8 \n \nB. \nConsultation with Stakeholders in the Development of the Proposed Tariff \nLanguage Regarding Large Computational Load and Ride Through \nRequirements \nThe proposed Tariff language addresses concerns raised by the Commission.  First, the \nproposed Tariff revisions are directly responsive to the express, preliminary findings set forth in \nthe Order to Show Cause.   \nSecond, the proposed definition of Large Computational Load and the Tariff revisions \nassociated with ride-through requirements were presented to stakeholders during the September 8, \n2026 Planning Committee meeting.22  Concurrently, throughout the stakeholder process, PJM has \npresented stakeholders with proposed Manual language setting forth the proposed technical ride \nthrough performance requirements for Large Computational Loads.  \nThird, on September 15, 2026, PJM held a special session of the Planning Committee \ndedicated to educating stakeholders about the impetus for the proposed ride-through requirements, \nincluding reliability concerns.23   \nFourth, PJM presented revised Tariff and Manual language defining Large Computational \nLoad and addressing ride-through requirements during the October 6, 2026 Planning Committee \nmeeting, including a comprehensive page-by-page review of the proposed provisions and \n \n22 The agenda from PJM’s June 16, 2026 special Market Implementation Committee meeting is available at \nhttps://www.pjm.com/-/media/DotCom/committees-groups/committees/mic/2026/20260616-special/agenda.pdf.  \n23 PJM Large Computational Load Operational Review, PJM Interconnection, L.L.C., Item 02 (Sept. 15, 2026), \nhttps://www.pjm.com/-/media/DotCom/committees-groups/committees/pc/2026/20260915/20260915-item-02---lcl-\nride-through-requirements-background-education---presentation.pdf; id., Item 03 – 1 LCL Ride-Through \nRequirements \nSolution \nEducation \n– \nPresentation, \nhttps://www.pjm.com/-/media/DotCom/committees-\ngroups/committees/pc/2026/20260915/20260915-item-03---1-lcl-ride-through-requirements-solution-education---\npresentation.pdf; id. Item 03 -2 LCL Ride-Through Requirements Proposed Language – Redline, \nhttps://www.pjm.com/-/media/DotCom/committees-groups/committees/pc/2026/20260915/20260915-item-03---2-\nlcl-ride-through-requirements-proposed-language---redline.pdf."},{"page":9,"startToken":2760,"endToken":3124,"text":"Honorable Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 9 \n \n9 \n \nimplementation details.  PJM also considered and responded—both in writing24 and during and \nafter the meeting—to submitted stakeholder questions and comments about the proposals, which \nsubsequently gave rise to further refinements to various aspects of the proposed requirements.   \nFifth, as described further, below, and in the declaration of Mr. Egan, the proposal is \ninformed by PJM’s ongoing participation in the North American Electric Reliability Corporation’s \n(“NERC”) development of operational standards and reliability criteria, including ride-through \nreliability standards, as well as PJM’s assessment and analysis of how other Regional \nTransmission Organizations and Independent System Operators (“RTOs/ISOs”) have addressed \nride-through requirements for large loads.  At bottom, the proposed solution has benefited from \nseveral months of stakeholder input, coordinated efforts with NERC, and careful consideration of \nindustry standards and initiatives. \nC. \nAdditional Tariff Provisions Setting the Groundwork for Future Development of \nOther Operational Requirements Applicable to Eligible Customers Taking \nTransmission Service on Behalf of Large Computational Loads \nPJM’s submission also proposes Tariff language for other operational components to \naddress potential gaps in processes for evaluating reliability impacts and transmission needs of \nLarge Loads.  PJM has not yet commenced stakeholder discussions to develop these requirements \nalthough they have been acknowledged in stakeholder consultations.25 PJM has indicated that \n \n24 Q &  A on Large Computational Load Ride-Through Requirements, PJM Interconnection, L.L.C. (Oct. 6, 2026), \nhttps://www.pjm.com/-/media/DotCom/committees-groups/committees/pc/2026/20261006/20261006-item-07-b---3-\nqa-on-lcl-rt-requirements.pdf  \n25 See, e.g., PJM’s Response Matrix to the Large Load Show Cause Order Opportunities, PJM Interconnection, L.L.C., \nat \npages \n3 \nthrough \n6 \n(Oct. \n29, \n2026), \nhttps://www.pjm.com/-/media/DotCom/committees-\ngroups/committees/mc/2026/20261105-special/item-01---2-large-load-compliance-matrix.pdf; Overview of June 18 \nCo-Located Load and Large Load Show Cause Orders, PJM Interconnection, L.L.C., at slides 14–15 (July 30, 2026), \nhttps://www.pjm.com/-/media/DotCom/committees-groups/workshops/cllsco/2026/20260730/20260730-item-02---\nco-located-load-and-large-load-show-cause-orders---presentation.pdf; PJM LCL Ride-through Requirements, PJM \nInterconnection, L.L.C., at slide 7 (Sept. 8, 2026), https://www.pjm.com/-/media/DotCom/committees-\ngroups/committees/pc/2026/20260908/20260908-item-05---1-large-load-ride-through---presentation.pdf; PJM Large"},{"page":10,"startToken":3124,"endToken":3466,"text":"Honorable Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 10 \n \n10 \n \ndevelopment of these other operational components will comprise significant ongoing work in \n2027 to develop details in Manual language relating to ramp rate and other operational \nrequirements.26  \nUnder these additional proposed Tariff provisions, PJM is committing to develop \nrequirements in the Manuals for Eligible Customer taking transmission service on behalf of Large \nComputational Loads to comply with in order to address other operational requirements for fast-\nramping load that may impact the transmission system, as described in the Large Load Show Cause \nOrder.27  The Manual language will be developed and specified in the PJM Manuals only after \nPJM has undergone the requisite additional study and stakeholder engagement in 2027.28    \nII. \nTHE PROPOSED TARIFF REVISIONS ARE JUST AND REASONABLE \nA. \nPJM Proposes to Define Large Computational Loads, the Relevant Subset of \nLarge Loads in PJM for Purposes of the Proposed Operational Requirements  \nAs a preliminary matter, PJM proposes to apply the ride-through requirements for large \nloads to Eligible Customers taking transmission service on behalf of a subset of Large Loads, \nwhich PJM refers to as “Large Computational Load.”  PJM proposes to add a definition of Large \nComputational Load to the Tariff: \n“Large Computational Load” shall mean Large Load containing 25 MW or greater \n \nComputational Load Operational Review, PJM Interconnection, L.L.C., at slide 15 (Oct. 6, 2026); \nhttps://www.pjm.com/-/media/DotCom/committees-groups/committees/pc/2026/20261006/20261006-item-07-a---1-\nlcl-ride-through-requirements-background---presentation.pdf.    \n26 PJM has spoken of additional operational requirements, like ramp rates, as being the subject of additional study and \nstakeholder engagement before they could be implemented.  More precisely stated, the particulars of these additional \noperational requirements will be discussed and developed with stakeholders as Manual language is developed.     \n27 Paragraph 64 \n28 PJM Large Computational Load Ride-Through Requirements, PJM Interconnection, L.L.C., at slide 25 (noting \nramp \nrate \nand \ndesign \nenvelope \nwork \nplan \nfor \n2027) \n(Oct. \n6, \n2026), \nhttps://www.pjm.com/-\n/media/DotCom/committees-groups/committees/pc/2026/20261006/20261006-item-07-b---1-lcl-ride-through-\nrequirements-solution---presentation.pdf."},{"page":11,"startToken":3466,"endToken":3790,"text":"Honorable Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 11 \n \n11 \n \nof maximum load served through power electronic conversion equipment.  Large \nComputational Load shall include: \n \nA) New Large Computational Load. Any Large Computational Load on whose \nbehalf an Eligible Customer enters the Transmission Provider or Transmission \nOwner study processes on or after [61 days from filing]. \n \nB) Materially Modified Large Computational Load. Existing Large Load that \notherwise meets the definition of Large Computational Load but does not meet the \naggregate load 50 MW threshold that is subsequently modified in a manner \nresulting in the aggregate load becoming 50 MW or greater or otherwise \nconstituting a material modification as determined by Transmission Provider and \nthe applicable Transmission Owner on or after [61 days from filing]. \n \nC) Transitional Large Computational Load. Any Large Computational Load, \nincluding a Large Computational Load undergoing a Material Modification, on \nwhose behalf, prior to [61 days from filing], an Eligible Customer serving such load \nhas: \n− formally initiated or completed an interconnection study with the \nTransmission Owner, \n− executed an interconnection agreement, service agreement, or other \nagreement authorizing interconnection, \n− commenced construction, or \n− achieved commercial operation. \nLarge Computational Load is Large Load that “contain[s] 25 MW or greater of maximum \nload served through power electronic conversion equipment.”29  As Mr. Egan testifies, the 25 MW \n“evolved from PJM’s experience evaluating large co-located loads, stakeholder feedback on earlier \ndraft language, and a review of approaches being developed by other regions, particularly \nMISO.”30  Furthermore, as Mr. Egan testifies, PJM tied the definition of Large Computational \nLoad to a threshold quantity of “power electronic conversation equipment” because: \nPJM observed through its co-location and large load analyses that Large \nComputational Load facilities generally consist of two primary categories of load: \n(1) cooling and support infrastructure loads used to remove heat and maintain \nfacility operation, and (2) electronics-based loads supplied through power \n \n29 Tariff, Part I, Definitions L–M–N (Large Computational Load). \n30 Egan Declaration ¶ 20."},{"page":12,"startToken":3790,"endToken":4095,"text":"Honorable Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 12 \n \n12 \n \nelectronic conversion equipment, including the AC-to-DC systems that serve \ninformation technology equipment and similar technologies. The reliability \nconcern underlying PJM’s proposed requirements is primarily associated with the \nelectronics-based portion of the load, as these systems can rapidly alter their \ndemand or transfer off the Bulk Electric System during disturbance conditions. \nWhile the proportion of facility load attributable to cooling versus electronics varies \nacross facility vintages and designs, PJM concluded that the defining reliability \ncharacteristic is the presence of substantial power electronic conversion equipment \nrather than the specific end use served by that equipment.31 \n \nThe targeted application of ride-through requirements to Large Loads that meet the Large \nComputational Load definition is just and reasonable.  First, the proposed definition recognizes \nthat ride-through and other operational requirements being developed are intended to apply only \nto Eligible Customers serving Large Loads with operating characteristics warranting additional \nreliability consideration.  Thus, for purposes of managing operational risk, defining Large \nComputational Load supports a more targeted approach than applying the same ride-through and \nother operational requirements to all Eligible Customers serving Large Loads without regard to \nfacility type or operating behavior.   \nSecond, the proposed definition of Large Computational Load is aligned with NERC’s \nproposed definition of computational load entities, which has likewise recognized that \ncomputational loads may warrant reliability requirements distinct from those applicable to \ntraditional loads.32  Both PJM’s proposed definition of Large Computational Load and NERC’s \ndeveloping definition recognize that power electronic conversion equipment that serves \ninformation technology, such as servers, storage, and networking hardware, similarly focus on the \n \n31 Egan Declaration ¶ 22. \n32 See Petition of the North American Electric Reliability Corporation for Approval of Revisions to the NERC Rules \nof Procedure Regarding Computational Load and Request for Expedited Action, Docket No. RD26-7 (“NERC \nPetition”), 4–5."},{"page":13,"startToken":4095,"endToken":4355,"text":"Honorable Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 13 \n \n13 \n \nunderlying electronic equipment and characteristics of the Large Load rather than a particular \nindustry or customer type.  As Mr. Egan explains, PJM’s definition of Large Computational Load \nis tailored to the specific needs of the PJM Region, while NERC’s developing definition of \ncomputational load, along with relevant registration criteria and Reliability Standards, is intended \nto determine which Large Loads will be subject to NERC’s mandatory reliability requirements.  \nSpecifically, “PJM concluded that the relevant reliability characteristic” of Large Loads in PJM \n“is not limited to servers or computational facilities, but rather the presence of large quantities of \npower electronic conversion equipment capable of exhibiting similar disturbance-response \ncharacteristics.”33 Defining Large Computational Loads as Large Loads meeting a threshold \nquantity of power electronic conversion equipment, “encompasses data centers” within the \ndefinition of Large Computational Load “while also remaining applicable to other emerging load \ntypes that rely heavily on power-electronic conversion technologies, such as certain hydrogen \nproduction facilities and other future industrial processes.”34 \nThird, the differences in PJM’s definition of Large Computational Load and NERC’s \ndeveloping definition reflect the different purposes and responsibilities of PJM and NERC.  \nIndeed, as described further, below, the proposed Tariff language establishing ride-through \nrequirements for Large Computational Load allows an Eligible Customer or Transmission Owner \nto modify its ride-through requirements “to address changes in system conditions, reliability needs, \napplicable NERC Reliability Standards or Transmission Provider operating requirements, \nprovided such requirements continue to meet or exceed the minimum requirements established by \n \n33 Egan Declaration ¶ 21 \n34 Id."},{"page":14,"startToken":4355,"endToken":4629,"text":"Honorable Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 14 \n \n14 \n \nTransmission Provider in the PJM Manuals.”35 \nFourth, PJM’s proposed approach to defining a specific subset of Large Load reflects \nPJM’s review and evaluation of emerging large-load and computational-load definitions under \ndevelopment by industry organizations and transmission providers.36 These industry efforts reflect \na common recognition that certain computational loads present reliability considerations that differ \nfrom those associated with traditional commercial and industrial loads.  PJM’s proposed definition \nis generally consistent with the applicability thresholds being adopted or proposed elsewhere in \nthe industry.  For example, MISO has similarly identified a subset of large load as computational \nload to which its proposed ride-through requirements will apply.  MISO has also similarly \nproposed to define computational load as “Large Load comprised of 25 MW or more of Demand \nfrom information technology equipment, such as servers, storage, and network hardware.”37  \nAlthough specific criteria vary across regions, these frameworks reflect a common \nrecognition that large computational facilities can present unique reliability considerations \nrequiring enhanced planning, modeling, and operational oversight.  Consistent with these industry \ndevelopments, PJM’s proposed Large Computational Load definition identifies facilities \ncontaining substantial computational load that may create material reliability impacts if they \nrespond to transmission disturbances in a coordinated manner. PJM’s proposed criteria are \ninformed by these industry efforts but were ultimately developed based on PJM’s own reliability \nassessments, operational experience, planning studies, and analyses of Large Computation Load \n \n35 Proposed Tariff, Part III, section 28.2. \n36 See Egan Declaration ¶¶ 19–22, 25. \n37 Midcontinent Indep. Sys. Op., Inc., Interconnection Reliability Requirements for Large Loads, Transmittal Letter, \nDocket No. ER26-3650-000, at 22 (Aug. 28, 2026)."},{"page":15,"startToken":4629,"endToken":4909,"text":"Honorable Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 15 \n \n15 \n \nbehavior on the PJM system. As such, PJM’s proposed definition is consistent with the broader \nindustry trend toward recognizing computational loads as a distinct category of load for reliability \npurposes while tailoring the specific criteria to the reliability needs of the PJM region.38 \nB. \nPJM Is Proposing Ride-Through Requirements Applicable to Eligible Customers \nTaking Transmission Service on Behalf of Large Computational Loads \nPJM is proposing to revise its Tariff to establish a framework for setting minimum voltage \nand frequency ride-through requirements, with which Eligible Customers taking transmission \nservice on behalf of both existing and new Large Computational Loads must comply.39  Under the \nproposed language in Tariff, Part III, section 28.2, the Transmission Provider shall establish \n“minimum voltage ride-through and frequency ride-through requirements with which Eligible \nCustomers taking transmission service on behalf of Large Computational Load must comply, \nwhich shall be set forth in the PJM Manuals.”  The proposed language sets a floor for disturbance \nride-through requirements while also leaving room for Transmission Owners or Eligible \nCustomers to establish ride-through requirements that are “no less stringent than the minimum \nrequirements established by Transmission Provider in the PJM Manuals[]” where “the \nTransmission Owner determines that such requirements are necessary to maintain the reliability, \nsecurity, or operational performance of its transmission facilities or the Transmission System.”40  \nFurthermore, any ride-through requirements established by an Eligible Customer or Transmission \nOwner must “be based upon reliability, planning, operational, stability, protection coordination, \nvoltage performance, frequency performance, restoration, balancing, reserve management or other \n \n38 Egan Declaration ¶ 25. \n39 Proposed Tariff, Part III, section 28.2.   \n40 Proposed Tariff, Part III, section 28.2."},{"page":16,"startToken":4909,"endToken":5304,"text":"Honorable Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 16 \n \n16 \n \nreliability-related considerations and shall be applied in a not unduly discriminatory manner to \nsimilarly situated Large Computational Load.”41  \nFinally, it is worth noting that establishing minimum ride-through requirements applicable \nto Eligible Customers taking transmission service on behalf of Large Computational Loads has the \nnecessary effect of also establishing consequences for failure to comply with such requirements, \nincluding, but not limited to, referrals to the Market Monitoring Unit and the North American \nElectric Reliability Corporation and its Regional Entities and action at or before the Commission.  \n1. \nThe Proposed Ride-Through Requirements Apply Whether Large \nComputational Loads Are Served Through Network Transmission Service \nor One of the New Transmission Services Available to Large Loads \nPJM’s proposed ride-through requirements apply whether Eligible Customers are serving \nLarge Computational Loads by taking Network Service, under Part III of the Tariff,42 or by taking \nany one of the new transmission services for Large Loads, pursuant to Part XI of the Tariff.43  The \napplication of the ride-through requirements to Eligible Customers taking any of these \ntransmission services on behalf of Large Computational Loads adheres to the Show Cause Order, \nwhich provides:  \n[T]he provision of transmission service to Eligible Customers on behalf of large \nloads [is intended] to encompass the provision of new, modified, or additional \njurisdictional transmission service to Eligible Customers on behalf of large loads.  \nWe note that this phrase is not limited to instances where an Eligible Customer \nsubmits an application to request new transmission service.  It also includes \n \n41 Proposed Tariff, Part III, section 28.2.   \n42 Proposed Tariff, Part III, section 35.1 (“The Network Customer shall plan, construct, operate and maintain its \nfacilities in accordance with Good Utility Practice and in conformance with the Network Operating Agreement.  \nEligible Customer taking transmission service to serve Large Computational Load shall ensure compliance with all \nthe requirements established in accordance with Tariff, Part III, section 28.2, and set forth in the PJM Manuals.”). \n43 Proposed Tariff, Part XI, section 718.2 (“Eligible Customer taking Transmission Service under Part XI to serve \nLarge Computational Load shall ensure compliance with all the requirements established in accordance with Tariff, \nPart III, section 28.2, and set forth in in the PJM Manuals. Transmission Provider shall prepare the annual report \nconsistent with Tariff, Part III, section 28.2.”)."},{"page":17,"startToken":5304,"endToken":5675,"text":"Honorable Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 17 \n \n17 \n \ninstances where an Eligible Customer requests a new or modified point of delivery \nto serve a large load, where a large load seeks a new or modified delivery point as \nan unbundled retail transmission service customer, or where large loads are \notherwise included in an Eligible Customer’s reported load growth and that Eligible \nCustomer is taking [Network Integrated Transmission Service (“NITS”)].”44   \n \nIndeed, the ride-through requirements are necessitated by the operational characteristics of \nthe underlying Large Computational Load, not by the type of transmission service that an Eligible \nCustomer is using to serve such load.  Thus, the ride-through requirements apply equally to NITS \nand non-NITS customers. \n2. \nPJM’s Proposal Imposes Ride Through Requirements on Eligible \nCustomers Serving Large Computational Loads  \nAs proposed, the ride-through requirements apply to Eligible Customers45 taking \ntransmission service on behalf of Large Computational Load.  Placing the onus on Eligible \nCustomers to meet these requirements when procuring transmission service on behalf of Large \nComputational Loads ensures that the proposed Tariff language falls squarely within the \nCommission’s “exclusive jurisdiction over the rates, terms, and conditions of interstate \ntransmission service to Eligible Customers on behalf of large loads connecting to the transmission \nsystem, and the practices directly affecting the provision of such interstate transmission of \nelectricity.”46  This is just, reasonable, and not unduly discriminatory because it applies equally to \nall Eligible Customers taking service on behalf of LCLs in order to maintain the reliability and \n \n44 Show Cause Order at P 42. \n45 PJM’s Tariff defines an Eligible Customer as “(i) Any electric utility (including any Transmission Owner and any \npower marketer), Federal power marketing agency, or any person generating electric energy for sale for resale . . .  (ii) \nAny retail customer taking unbundled transmission service pursuant to a state requirement that the Transmission \nProvider or a Transmission Owner offer the transmission service, or pursuant to a voluntary offer of such service by \na Transmission Owner, is an Eligible Customer under the Tariff.  As used in Tariff, Part VIII, Eligible Customer shall \nmean only those Eligible Customers that have submitted an Application and Study Agreement.”  Tariff, Part I, section \n1, Definitions E – F. \n46 Show Cause Order at P 47."},{"page":18,"startToken":5675,"endToken":6009,"text":"Honorable Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 18 \n \n18 \n \nsafety of the Bulk Electric System. \nFurthermore, the ride-through requirements apply to Eligible Customers, rather than \nTransmission Customers.  PJM recognizes that the Show Cause Order notes that “ongoing \noperation requirements should apply to transmission customers, rather than Eligible Customers, as \nthese requirements apply after the Eligible Customer has an executed (or a filed unexecuted) \nservice agreement for transmission service and have become transmission customers under the \nTariff.”47  However, in PJM the term Transmission Customer is circumscribed to specific types of \ncustomers, which may unnecessarily constrain the scope of the application of these ride-through \nrequirements.48  PJM proposes that Eligible Customers meet minimum ride-through requirements \nas a condition of interconnection.   \n3. \nPJM’s Proposes to Apply Ride-Through Requirements to Eligible \nCustomers Serving Existing and New Large Computational Load  \nAs noted above, PJM already has approximately 10 GW of existing computational load in \nits region and has, in recent years, already experienced the significant consequences of large load \ntransfers.  Thus, PJM’s proposed definition does not exempt existing Large Computational Loads \nfrom the proposed ride-through requirements.  Nevertheless, PJM’s proposed ride-through \nrequirements are mindful of the Commission’s directive that any section 205 filing submitted in \nresponse to the Show Cause Order should “provide a reasoned explanation for how the proposal \n \n47 Order to Show Cause at P 57 n.140. \n48 The PJM Tariff defines Transmission Customers as “any Eligible Customer (or its Designated Agent) that (i) \nexecutes a Service Agreement, or (ii) requests in writing that the Transmission Provider file with the Commission a \nproposed unexecuted Service Agreement, to receive transmission service under Tariff, Part II.  This term is used in \nTariff, Part I and Tariff, Part VI to include customers receiving transmission service under Tariff, Part II and Tariff, \nPart III. Where used in Tariff, Attachment K-Appendix and the parallel provisions of Operating Agreement, Schedule \n1, Transmission Customer shall mean an entity using Point-to-Point Transmission Service.” Tariff, Part I, section 1, \nDefinitions T – U – V."},{"page":19,"startToken":6009,"endToken":6304,"text":"Honorable Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 19 \n \n19 \n \nwill avoid disrupting existing commercial arrangement and clearly identify a reasonable effective \ndate that accommodates such existing commercial arrangements.”49  Specifically, PJM proposes \nto accommodate existing commercial arrangements by granting additional time for a category of \nLarge Computational Loads, called “Transitional Large Computational Load Facilities” to achieve \ncompliance with the proposed disturbance ride-through requirements.  As proposed, “where an \nEligible Customer is taking transmission service on behalf of  Transitional Large Computational \nLoad for purposes of these requirements, the Eligible Customers shall achieve compliance with \nrespect to the Transitional Large Computational Load no later than [61 days from filing plus one \nyear], or within one (1) year of its Commercial Operation Date, whichever is later.”50 \nApplying the ride-through requirements to existing Large Computational Load through a \ntransitional mechanism is just and reasonable and, furthermore, recognizes that Eligible Customers \ntaking transmission service on behalf of Large Computational Load poses operational risks to the \nPJM Region, regardless of whether the Large Computational Load is new or existing. \nIndeed, the PJM Tariff already requires that Network Customers “plan, construct, operate \nand maintain [their] facilities in accordance with Good Utility Practice[.]”  Good Utility Practice, \nin turn, is defined to “mean any of the practices, methods and acts engaged in or approved by a \nsignificant portion of the electric utility industry during the relevant time period, or any of the \npractices, methods and acts which, in the exercise of reasonable judgment in light of the facts \nknown at the time the decision was made, could have been expected to accomplish the desired \nresult at a reasonable cost consistent with good business practices, reliability, safety and \n \n49 Show Cause Order at P 38. \n50 Proposed Tariff, Part III, section 28.2."},{"page":20,"startToken":6304,"endToken":6562,"text":"Honorable Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 20 \n \n20 \n \nexpedition.  Good Utility Practice is not intended to be limited to the optimum practice, method, \nor act to the exclusion of all others, but rather is intended to include acceptable practices, methods, \nor acts generally accepted in the region; including those practices required by Federal Power \nAct, section 215(a)(4).”   \nFederal Power Act, section 215(a)(4) defines “reliable operation” as meaning “operating \nthe elements of the bulk-power system within equipment and electric system thermal, voltage, and \nstability limits so that instability, uncontrolled separation, or cascading failures of such system will \nnot occur as a result of a sudden disturbance, including a cybersecurity incident, or unanticipated \nfailure of system elements.”   \nThus, Network Customers must operate existing facilities consistent with Good Utility \nPractice to avoid significant grid reliability events caused by, among other things sudden system \ndisturbances unique to new and existing Large Computational Loads.51 As Dr. Choi explains in \nhis declaration, not doing so “would exempt a substantial portion of the current reliability risk \nfrom the proposed [ride-through] requirements.”52  \nAs discussed above, PJM faces a unique risk unlike other regions where the existing \ninstalled Large Computational Load base is comparatively small, as demonstrated by the fact that \nPJM has already experienced several load-transfer events attributable to voltage ride-through \nperformance issues, including the nearly 4 GW event on July 22, 2026.53 Unlike ERCOT and \nMISO, for example, PJM cannot exempt existing computational load and its demonstrated \n \n51 Choi Declaration ¶ 8. \n52 Id. \n53 Id."},{"page":21,"startToken":6562,"endToken":6823,"text":"Honorable Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 21 \n \n21 \n \noperational effects: the requirements must apply to new and existing facilities, allowing reasonable \ntime for Transitional Large Computational Load Facilities to achieve compliance.54 The additional \ncompliance period applicable to Transitional Large Computational Load \nprovides \naccommodations to Eligible Customers serving existing Large Computation Load, thus \nminimizing potential disruptions to existing commercial arrangements while upholding Network \nCustomers’ obligations to operate consistent with Good Utility Practice and affirming PJM’s \nmandate to ensure the reliability of the transmission system in its region. \n4. \nSpecific ride-through requirements applicable to Eligible Customers \nserving Large Computational Load shall be set forth in PJM’s Manuals \nThe proposed ride-through requirements require that any Eligible Customer taking \ntransmission service on behalf of Large Computational Load adhere to minimum voltage and \nfrequency ride-through requirements that “shall be set forth in the PJM Manuals.”55  PJM notes \nthat this approach—establishing the core ride-through requirement in the Tariff and the technical \ncriteria in the manual—is consistent with the approach recently proposed by the Southwest Power \nPool, Inc. (“SPP”) and accepted by the Commission.  SPP’s ride-through requirements for \ntransmission customers providing service to Large Loads requires transmission customers to \ncomply with ride-through requirements set forth as guidelines in “a non-Tariff document that was \nseparately approved by SPP stakeholder working groups.”56  Likewise, PJM is concurrently \nundergoing the process of developing and receiving feedback from its stakeholders on proposed \n \n54 Id. \n55 Proposed Tariff, Part III, section 28.2. \n56 Sw. Power Pool, Inc., 194 FERC ¶ 61,031, at P 20 (2026)."},{"page":22,"startToken":6823,"endToken":7167,"text":"Honorable Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 22 \n \n22 \n \nManual language.57      \nC. \nPJM Is Proposing Tariff Language Authorizing the Development of Other \nOperational \nRequirements \nApplicable \nto \nEligible \nCustomers \nTaking \nTransmission Service on Behalf of Large Computational Loads  \nThe Show Cause Order additionally found the PJM Tariff appeared to be unjust and \nunreasonable because it lacks other “provisions addressing ongoing operational requirements for \ntransmission customers taking transmission service on behalf of large loads.”58  PJM also proposes \nTariff language to address the other operational requirements to be imposed on Eligible Customers \ntaking transmission service to serve Large Computational Loads.   For the reasons cited above, as  \nset forth at length for the ride through requirements specifically, and given the Commission’s \nacceptance of similar operational requirements provisions in other Regions and the Commission’s \nobservations in the Large Load Show Cause Order, the Commission should accept these proposed \nrevisions establishing the framework for other operational requirements to be developed in the \nManuals as just and reasonable.59  PJM will work with stakeholders to develop the particular \nrequirements necessary to implement each of these provisions through vetted Manual language, \nwith due consideration for implementation dates, before these requirements can be of any force \nand effect.   \n \n57 See October 6, 2026 Planning Committee meeting agenda, available at https://www.pjm.com/-\n/media/DotCom/committees-groups/committees/pc/2026/20261006/20261006-agenda.pdf. \n58 Show Cause Order at P 64. \n59 See, e.g., Sw. Power Pool, Inc., 194 FERC ¶ 61,031 (2026) (accepting SPP Tariff language in SPP Tariff, \nAttachment AE, section 2.22, requiring SPP’s market participants registering High Impact Large Loads to, among \nother things, “Have remote capability to disconnect the load from the Transmission System made available to the \ntransmission operator; . . . Have an effective up and down ramp rate not exceeding the specified limit outlined in the \nMarket Protocols unless otherwise directed by the SPP Balancing Authority, Reliability Coordinator, or local \ntransmission operator; . . . Provide registration information as specified in the Market Protocols; . . . Not have a \nnegative withdrawal at the load delivery point without appropriate Transmission Service.”)."},{"page":23,"startToken":7167,"endToken":7466,"text":"Honorable Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 23 \n \n23 \n \nD. \nPro Forma Provisions in Transmission Service Agreements Exist or Will Exist \nto Memorialize Ongoing Operational Requirements \nThe Commission’s order also notes opportunities for pro forma provisions in a \nTransmission Service Agreement between PJM and the Eligible Customer taking transmission \nservice on behalf of a Large Load in order to memorialize the ongoing operational requirements.60   \nPJM’s transmission service agreements (those existing today and those proposed) memorialize \nongoing operational requirements for Eligible Customers taking transmission service.61  The pro \nforma Network Integration Transmission Service Agreement in the Tariff provides that the \n“Network Customer agrees to  take and pay for Network Transmission Service in accordance with \nthe provisions of the Tariff, including the Network Operating Agreement (which is incorporated \nherein by reference), and this Service Agreement as they may be amended from time to time.”62   \nThe Network Operating Agreement is the Restated and Amended Operating Agreement of PJM \nInterconnection, L.L.C.63  Pursuant to the Operating Agreement, entities must “[c]omply with the \nrequirements of the PJM Manuals.”64  Similar constructs will exist for customers taking the newly \nproposed transmission services.65  Since the operational requirements addressed in this filing are \nbeing memorialized in the Tariff with details to be set forth in the Manuals, the desired pro forma \nprovisions exist or will exist in the relevant service agreements to address the Commission’s \nconcern.   \n \n60 Show Cause Order at P 65. \n61 Show Cause Order at P 64. \n62 Tariff, Attachment F-3, section 4.0. \n63 Tariff, Part III, section 35.2; Tariff, Attachment G. \n64 Operating Agreement, section 11.3.1(e). \n65 Proposed Tariff, Part XI, Subpart C, section 720.2; Proposed Tariff, Attachment F-3A, section 4.0; Proposed Tariff, \nAttachment F-4, section 4.0."},{"page":24,"startToken":7466,"endToken":7729,"text":"Honorable Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 24 \n \n24 \n \nIII. \nSTAKEHOLDER ENGAGEMENT \nThe proposed Tariff revisions defining Large Computational Load and establishing ride-\nthrough requirements follow an expedited stakeholder engagement effort.  PJM presented its initial \nproposal to stakeholders at the September 8, 2026 Planning Committee meeting.66 PJM \nsubsequently conducted a dedicated Planning Committee education session on September 15, \n2026, during which Planning and Operations subject matter experts presented the July 22, 2026 \nload transfer event, the associated reliability concerns, and the technical basis supporting the \nproposed ride-through requirements.67  PJM then presented revised Tariff and Manual language at \nthe October 6, 2026 Planning Committee meeting.68 \nWith respect to other ongoing operational requirements applicable to Eligible Customers \ntaking transmission on behalf of Large Computational Load, PJM is committed to developing \nManual language through the stakeholder process starting in early 2027.  PJM has in other fora \nand in posted materials – particularly at and for the Co-Located Load Workshops, the Markets and \nReliability Committee, and the Special Members Committee convened on November 5, 2026 \npreceding this Section 205 filing – noted the operational requirements described in the Show Cause \nOrder.  \n \n66 See September 8, 2026 Planning Committee meeting agenda, available at https://www.pjm.com/-\n/media/DotCom/committees-groups/committees/pc/2026/20260908/20260908-agenda.pdf. \n67 See September 15, 2026 Planning Committee–Special Session agenda, available at https://www.pjm.com/-\n/media/DotCom/committees-groups/committees/pc/2026/20260915/20260915-agenda.pdf. \n68 See October 6, 2026 Planning Committee meeting agenda, available at https://www.pjm.com/-\n/media/DotCom/committees-groups/committees/pc/2026/20261006/20261006-agenda.pdf."},{"page":25,"startToken":7729,"endToken":7922,"text":"Honorable Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 25 \n \n25 \n \nIV. \nPROPOSED EFFECTIVE DATE \nPJM proposes an effective date of January 16, 2027, for the proposed Tariff revisions \nreferenced herein.  PJM requests that the Commission issue an order on this filing by January 15, \n2027.  \nV. \nDESCRIPTION OF SUBMITTAL \nThis filing consists of the following: \n1. This transmittal letter; \n2. Attachment A – Revisions to the Tariff, in redline format;  \n3. Attachment B – Revisions to the Tariff, in clean format; \n4. Attachment C – Declaration of David Egan;  \n5. Attachment D – Declaration of Byoungkon Choi. \nVI. \nCORRESPONDENCE \nThe following individuals are designated for inclusion on the official service list in this \nproceeding and for receipt of any communications regarding this filing: \nArleigh P. Helfer \nSr. Counsel \nPJM Interconnection, L.L.C. \n2750 Monroe Boulevard \nAudubon, Pennsylvania 19403 \n(610) 666-4370 \narleigh.helfer@pjm.com   \n \nMark Stanisz \nAssociate General Counsel \nPJM Interconnection, L.L.C. \n2750 Monroe Boulevard \nAudubon, PA 19403 \n(610) 666-2255 \nmark.stanisz@pjm.com \n \nCraig Glazer  \nVice President - Federal \nGovernment Policy \nPJM Interconnection, L.L.C. \n1200 G Street, N.W, Suite 600 \nWashington, D.C. 20005 \n(202) 423-4743 \ncraig.glazer@pjm.com"},{"page":26,"startToken":7922,"endToken":8144,"text":"Honorable Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 26 \n \n26 \n \nVII. \nSERVICE \nPJM has served a copy of this filing on all PJM Members and on all state utility regulatory \ncommissions in the PJM Region by posting this filing electronically.  In accordance with the \nCommission’s regulations,69 PJM will post a copy of this filing to the FERC filings section of its \ninternet site, located at the following link: https://www.pjm.com/library/filing-order with a \nspecific link to the newly-filed document, and will send an e-mail on the same date as this filing \nto all PJM Members and all state utility regulatory commissions in the PJM Region70 alerting them \nthat this filing has been made by PJM and is available by following such link.  If the document is \nnot immediately available by using the referenced link, the document will be available through the \nreferenced link within 24 hours of the filing.  Also, a copy of this filing will be available on the \nFERC’s eLibrary website located at the following link: http://www.ferc.gov/docsfiling/ \nelibrary.asp in accordance with the Commission’s regulations and Order No. 714. \n \n69 See 18 C.F.R. §§ 35.2(e) and 385.2010(f)(3). \n70 PJM already maintains, updates and regularly uses e-mail lists for all PJM Members and affected state commissions."},{"page":27,"startToken":8144,"endToken":8260,"text":"Honorable Debbie-Anne A. Reese, Secretary \nNovember 16, 2026 \nPage 27 \n \n27 \n \nVIII. CONCLUSION \nBased on the foregoing, PJM respectfully requests that the Commission accept proposed \nrevisions to PJM’s Tariff. \nRespectfully submitted, \n/s/ Arleigh P. Helfer       \n \n \nCraig Glazer \nVice President – Federal Government Policy \nPJM Interconnection, L.L.C. \n1200 G Street, N.W. \nSuite 600 \nWashington, D.C. 20005 \n(202) 423-4743 \ncraig.glazer@pjm.com \nArleigh P. Helfer \nSr. Counsel \nPJM Interconnection, L.L.C. \n2750 Monroe Boulevard \nAudubon, PA 19403 \n(610) 666-4370 \narleigh.helfer@pjm.com \n \n \n \nMark Stanisz \nAssociate General Counsel \nPJM Interconnection, L.L.C. \n2750 Monroe Boulevard \nAudubon, PA 19403 \n(610) 666-2255 \nmark.stanisz@pjm.com \n \n \nOn behalf of \nPJM Interconnection, L.L.C."}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":5,"endAt":1284,"startToken":0,"endToken":1736},{"p":5,"at":1284,"title":"I. BACKGROUND","method":"PDF bookmark","endPage":5,"endAt":1300,"startToken":1736,"endToken":1738},{"p":5,"at":1300,"title":"A. PJM Already Faces Risks Arising from Large Load-Transfer Events that Necessitate Ride-Through Requirements","method":"PDF bookmark","endPage":8,"endAt":77,"startToken":1738,"endToken":2476},{"p":8,"at":77,"title":"B. Consultation with Stakeholders in the Development of the Proposed Tariff Language Regarding Large Computational Load and Ride Through Requirements","method":"PDF bookmark","endPage":9,"endAt":1054,"startToken":2476,"endToken":2900},{"p":9,"at":1054,"title":"C. Additional Tariff Provisions Setting the Groundwork for Future Development of Other Operational Requirements Applicable to Eligible Customers Taking Transmission Service on Behalf of Large Computational Loads","method":"PDF bookmark","endPage":10,"endAt":834,"startToken":2900,"endToken":3247},{"p":10,"at":834,"title":"II. THE PROPOSED TARIFF REVISIONS ARE JUST AND REASONABLE","method":"PDF bookmark","endPage":10,"endAt":894,"startToken":3247,"endToken":3256},{"p":10,"at":894,"title":"A. PJM Proposes to Define Large Computational Loads, the Relevant Subset of Large Loads in PJM for Purposes of the Proposed Operational Requirements","method":"PDF bookmark","endPage":15,"endAt":370,"startToken":3256,"endToken":4684},{"p":15,"at":370,"title":"B. PJM Is Proposing Ride-Through Requirements Applicable to Eligible Customers Taking Transmission Service on Behalf of Large Computational Loads","method":"PDF bookmark","endPage":22,"endAt":104,"startToken":4684,"endToken":6837},{"p":22,"at":104,"title":"C. PJM Is Proposing Tariff Language Authorizing the Development of Other Operational Requirements Applicable to Eligible Customers Taking Transmission Service on Behalf of Large Computational Loads","method":"PDF bookmark","endPage":23,"endAt":79,"startToken":6837,"endToken":7178},{"p":23,"at":79,"title":"D. Pro Forma Provisions in Transmission Service Agreements Exist or Will Exist to Memorialize Ongoing Operational Requirements","method":"PDF bookmark","endPage":23,"endAt":1965,"startToken":7178,"endToken":7461},{"p":23,"at":1965,"title":"Attachment F-4, section 4.0.","method":"printed heading","endPage":24,"endAt":79,"startToken":7461,"endToken":7477},{"p":24,"at":79,"title":"III. STAKEHOLDER ENGAGEMENT","method":"PDF bookmark","endPage":25,"endAt":79,"startToken":7477,"endToken":7740},{"p":25,"at":79,"title":"IV. PROPOSED EFFECTIVE DATE","method":"PDF bookmark","endPage":25,"endAt":303,"startToken":7740,"endToken":7775},{"p":25,"at":303,"title":"V. DESCRIPTION OF SUBMITTAL","method":"PDF bookmark","endPage":25,"endAt":624,"startToken":7775,"endToken":7823},{"p":25,"at":624,"title":"VI. CORRESPONDENCE","method":"PDF bookmark","endPage":26,"endAt":79,"startToken":7823,"endToken":7933},{"p":26,"at":79,"title":"VII. SERVICE","method":"PDF bookmark","endPage":27,"endAt":79,"startToken":7933,"endToken":8155},{"p":27,"at":79,"title":"VIII. CONCLUSION","method":"PDF bookmark","endPage":27,"endAt":795,"startToken":8155,"endToken":8260}]}