{"document":{"slug":"filing-er27-527-miso-grits","title":"MISO files the Grid Responsive Integration Transmission Service under section 205","issued":"2026-11-16","accession":"20261116-5326","docket":"ER27-527-000","group":"MISO filings","filer":"Midcontinent Independent System Operator, Inc.","kind":"filing","file":"sources/originals/20261116-5326_01.pdf","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_Number=20261116-5326","sha256":"78dbd6e4e171f7e033521d948b5bcd0b7f935954d9cd3c9957428bec9e086239","pages":18,"tokens":6912,"emptyPages":[]},"pages":[{"page":1,"startToken":0,"endToken":348,"text":"Midcontinent Independent \nSystem Operator, Inc. \n317.249-5400 \nwww.misoenergy.org \n720 City Center Drive \nCarmel, Indiana 46032 \n2985 Ames Crossing Road \nEagan, Minnesota 55121 \n1700 Centerview Drive \nLittle Rock, AR 72211 \n \nMichael Kessler \nManaging Assistant General Counsel \nDirect Dial:  317-753-9434 \nEmail:  mkessler@misoenergy.org \nNovember 16, 2026 \nVIA ELECTRONIC FILING \nThe Honorable Debbie-Anne Reese  \nSecretary \nFederal Energy Regulatory Commission \n888 First Street, NE \nWashington, DC  20426 \nRe: \nMidcontinent Independent System Operator, Inc.’s  \nGrid Responsive Integration Transmission Service for Large Loads \nDocket No. ER27-___-000 \n \nDear Secretary Reese: \nThe Midcontinent Independent System Operator, Inc.  (“MISO”), through this filing,1 \nsubmits proposed revisions to its Open Access Transmission, Energy and Operating Reserve \nMarkets Tariff (“Tariff”),2 establishing the Grid Responsive Integration Transmission Service \n(“GRITS”).  GRITS provides a permanent firm and non-firm contract demand-based, \nTransmission Service option for Large Loads willing and able to limit their withdrawals under \nspecified price and reliability conditions.   \n \nMISO is submitting GRITS as a separate FPA section 205 filing from the Large Load \nProject Review (“LLPR”) process, cost recovery agreements, Firm Service Step Up (“FSSU”), \nand Interim Network Integration Transmission Service (“Interim NITS”).3  These initiatives are \naddressed in MISO’s separate large load omnibus filing submitted concomitantly.  The GRITS \nproposal is a stand-alone proposal and MISO describes the proposals contained in the omnibus \nfiling here only as necessary to explain the interfaces with GRITS. \n \nMISO requests that the Commission accept the proposed revisions effective 120-days from \nthe date of this filing (i.e., March 16, 2027) in order to facilitate MISO’s development of software \n \n1  \nThis filing is made pursuant to section 205 of the Federal Power Act (“FPA”), 16 U.S.C.  § 824d, and Part 35 of \nthe regulations of the Federal Energy Regulatory Commission (“FERC” or “Commission”), 18 C.F.R.  § 35.1, \net seq. \n2  \nUnless otherwise indicated by the text or context of this transmittal letter, all terms used herein have the definitions \nset forth in Module A of the Tariff. \n3  \nThese filings are being submitted contemporaneously in response to the associated concerns set forth in the Show \nCause Order."},{"page":2,"startToken":348,"endToken":852,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 2 \n \n \nsystems and related process modifications necessary to implement GRITS in early 2029, and to \ncontinue the development of rates applicable to GRITS in concert with the MISO Transmission \nOwners.  The GRITS proposal responds to the Commission’s concerns regarding the need for an \nongoing firm and non-firm contract demand service option for flexible Large Loads, including, \nbut not limited to, co-located arrangements.  The specific relationship to the proceeding in Docket \nNo.  EL26-70-000 is addressed below. \nI. \nEXECUTIVE SUMMARY \nMISO appreciates the collaborative efforts of its stakeholder community and the \nTransmission Owners in developing proposals for the reliable integration of Large Loads on an \nexpedited basis, consistent with the urgency created by the timelines established in the Show Cause \nOrder. \n \nThis filing provides the GRITS framework, which addresses the concerns raised by the \nCommission in the Show Cause Order with respect to the need for a permanent contract demand \ntransmission service in the MISO region.  As discussed in more detail below, the earliest MISO \nwill be able to implement GRITS is January 1, 2029.  This implementation timeline is driven by \nthe need for significant modifications to MISO’s software systems and processes to  facilitate the \nreservation, scheduling, market systems, and billing services for GRITS, which is a new \ntransmission service that does not conform with the transmission services offered today under \nMISO’s Tariff.  MISO recognizes the desire for the proposed service as noted by certain \nstakeholders and agrees that GRITS must provide a reliable and workable path for customers that \nelect permanent contract demand-based firm and/or non-firm transmission service and is \ncommitted to implementation of GRITS consistent with Commission acceptance and on a timeline \nthat is technically feasible. \n \nGiven the extended timeline for implementing GRITS, MISO and the Transmission \nOwners,  prioritized their efforts on solutions that can be delivered in the near term, including the \nZero Injection Generator Interconnection Agreement (“ZGIA”) proposal, Interconnection \nReliability Requirements (“IRR”), Load Addition Resource Study (“LARS”) proposal, Firm \nService Step Up, Interim NITS and LLPR, including the development of pro forma cost recovery \nagreements to prevent unjust cost shifts related to upgrades identified through the LLPR process.  \nThis prioritization was necessary given the competing priorities of MISO’s proposals in response \nto the Show Cause Order and the abbreviated time frame during which the multiple issues \nidentified in the Show Cause order needed to be addressed.  Moreover, GRITS is a novel and \ncomplex market-dependent approach to transmission service that was conceived later in the \nabeyance period (i.e., October 2026) and has necessitated greater stakeholder outreach and \neducation.  As stated above, considerable work remains including significant modifications to \nMISO’s, and as may be required, the Transmission Owner’s and other Market Participants’, \nsoftware systems and processes to accommodate GRITS.  As such, MISO requests Commission \nacceptance of the proposed GRITS framework to begin software development consistent with the \nCommission’s order and further requests the Commission permit MISO and the Transmission \nOwners to continue to develop a new rate structure applicable to GRITS and work with"},{"page":3,"startToken":852,"endToken":1302,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 3 \n \n \nstakeholders to continue to refine the proposal on a timeline that will facilitate GRITS \nimplementation in early 2029.   \n \nII. \nBACKGROUND \nThe scale and pace of large load development require transmission service options that \nreflect how a Large Load customer intends to use the Transmission System.  Some Large Load \nTransmission Customers may seek full firm service and need an interim arrangement while \nnecessary supporting upgrades are completed.  MISO is proposing in its omnibus filing both an \nInterim NITS product and Firm Service Step Up process that will be implemented within its \nexisting NITS framework to address these transmission service needs.  Other Large Load \nTransmission Customers may be able to accept continuing interruption of some or all of their \ndemand and seek an ongoing allocation between firm and non-firm service on a permanent basis.  \nGRITS addresses both of these needs as it provides the Large Load Transmission Customer the \noption to determine the appropriate combination of firm and non-firm contract demand \ntransmission services needed to meet its operational needs, but does not require the Large Load \nTransmission Customer to progress toward firm service for any or all of its GRITS Load Limit.4   \n \nIn the June 18, 2026, Show Cause Order, the Commission examined whether MISO’s \nTariff adequately addresses large and co-located load development, including service for loads \nwilling and able to limit their withdrawals under certain conditions.  The Commission identified a \npermanent contract-demand-like service option, treatment of regulation and black start service, \nand controls needed to enforce withdrawal limits among the matters requiring attention.5   \n \nThe Commission permitted respondents to develop regional solutions through section 205 \nfilings and subsequently held the proceeding in abeyance.  MISO has advanced related proposals \nthrough separate filings, including Zero Injection Generator Interconnection Agreements \n(“ZGIA”), Interconnection Reliability Requirements for Large Loads (“IRR”), and the Large Load \nAddition Resource Study (“LARS”) and the Large Load omnibus filing submitted separately \npursuant to FPA section 205.  GRITS provides a distinct Transmission Service option that can \noperate with the applicable study, interconnection, and reliability requirements.  Generator \nInterconnection Service does not itself provide the Transmission Service needed for associated \nload.6 \n \n \n4  \nGRITS Load Limit: The maximum amount of Load specified in the Form of Service Agreement for GRITS by \nthe Large Load Transmission Customer taking GRITS that may be scheduled at a Point(s) of Delivery pursuant \nto Module B of this Tariff. \n5  \nMidcontinent Indep.  Sys.  Operator, Inc., 195 FERC ¶ 61,212, PP 98–105 (2026), errata notice, 196 FERC ¶ \n61,123 (2026) (“Show Cause Order”). \n6  \nShow Cause Order P 37; Midcontinent Indep. Sys. Operator, Inc., 196 FERC ¶ 61,133, PP 8-11 (2026) \n(“Abeyance Order”); ZGIA Transmittal at 1-2, 6-7."},{"page":4,"startToken":1302,"endToken":1803,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 4 \n \n \nIII. \n  PROPOSED GRITS SERVICE \nA. \nEligibility, service quantities, and agreements. \n \nGRITS provides an ongoing service arrangement for a Large Load Transmission Customer \nserving a Large Load that may desire a combination of both firm and non-firm contract demand-\nlike transmission service and, with respect to any non-firm service, is willing and able to limit its \nwithdrawals under specified price and reliability conditions.  For example, a Large Load \nTransmission Customer representing a Large Load of 500 MW may desire to only take 200 MW \nof firm transmission service, allowing the remaining 300 MW to be served on a non-firm basis.  \nUnder Network Integration Transmission Service this participation model is not available while \nGRITS provides a pathway for such an arrangement. \n    \nGRITS will only be made available to a Large Load Transmission Customer, cannot be \ncombined with any other NITS transmission service, and is not limited to Large Load being served \nby a co-located generator.  GRITS Service requires that a Large Load Transmission Customer \nestablish a GRITS Load Limit and a Firm GRITS quantity that may range from zero to the full \nLoad Limit in the pro forma GRITS service agreement (“GRITS Service Agreement”), which \ncannot be exceeded without execution of a new pro forma GRITS Service Agreement.  Non-Firm \nGRITS may be reserved within the difference between those quantities as needed and as available.  \nThe GRITS Load Limit defines the maximum approved Load in the GRITS Service Agreement; \nit does not guarantee that the entire non-firm quantity will be available in every period. \n \nGRITS contains the firm and non-firm components within one GRITS Service Agreement.  \nMISO does not propose combining NITS and GRITS for the same load to create that allocation, \nand a change to the GRITS Load Limit or Firm GRITS quantity requires a new GRITS Service \nAgreement.  Where both firm and non-firm quantities are present, separate Commercial Pricing \nNodes (“CPNodes”) represent those components.  This representation supports the different \nreservation, interruption, billing, capacity, and Auction Revenue Rights (“ARR”) treatment \napplicable to each GRITS service component. \n \nFor example, a 300 MW GRITS Load Limit with 60 MW of Firm GRITS permits a \nmaximum non-firm quantity of 240 MW.  At 200 MW of operating demand, the proposed \nallocation assigns the first 60 MW to the CPNode representing the firm component and the \nremaining 140 MW to the CPNode representing the non-firm component.  That allocation is \nsubject to an available reservation and the applicable operating limit; the agreement’s 240 MW \nnon-firm maximum does not itself establish that 240 MW will be available for every hour. \n \nAs noted above, GRITS accommodates both stand-alone Large Loads and qualifying co-\nlocated arrangements.  A Large Load Transmission Customer must request GRITS through the \napplicable LLPR process and will be required to execute a GRITS Service Agreement and a \nGRITS Operating Agreement specifying the quantities, operational limits, communications, and \ncontrol requirements.  Service commences after Network Upgrades, Large Load Network \nUpgrades and/or Impacted Transmission Owner Large Load Network Upgrades identified through"},{"page":5,"startToken":1803,"endToken":2057,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 5 \n \n \nthe LLPR process are complete and the applicable service and operating prerequisites are satisfied.  \nAs explained by Ms. Xie, Firm Service Step-up, which is proposed in MISO’s Omnibus Filing, \ncannot be combined with GRITS because GRITS establishes its own ongoing allocation of firm \nand non-firm service within the GRITS Service Agreement.   \n \nB. \nReservations and service priority. \n \nNon-Firm GRITS will be reserved through the Open Access Same-Time Information \nSystem (“OASIS”) for periods ranging from one Day to one month.  The reservation rules use the \nexisting Point-To-Point Transmission Service framework, including priority for longer requested \nservice periods within the permitted range and the order of competing equal-duration requests.  A \nnew reservation receives its applicable position in that process.  The underlying Form of GRITS \nService Agreement does not reserve non-firm service indefinitely, and reservation priority of non-\nfirm service remains distinct from the priority applied when existing service must be curtailed. \n \nFirm GRITS is reserved for at least one year within the ongoing arrangement.  Reservation \npriority determines the order in which requests are evaluated; curtailment priority determines \nwhich existing service is reduced when the system cannot support scheduled use.  A customer’s \ncontinuing GRITS agreement does not establish an indefinite reservation of non-firm capability.  \nThe following depicts the priority of Firm and Non-Firm GRITS: \n \n \n \nC. \nTransmission charges and gross-load billing. \n \nGRITS will use reservation-based Transmission Service charges benchmarked to the rates \nfor GRITS service that will be filed in a subsequent FPA section 205 filing.  MISO notes that it"},{"page":6,"startToken":2057,"endToken":2567,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 6 \n \n \nwill continue working with its Transmission Owners specifically,7 and the broader stakeholder \ncommunity, to develop the rates applicable to GRITS transmission services.  MISO and the \nTransmission Owners intend to either submit the proposed GRITS transmission service rates prior \nto the proposed implementation date requested herein (i.e., March 16, 2027) or provide the \nCommission with a status report detailing the progress that has been made to establish such rates \nas well a revised date to propose such rates. \n \nGiven the expansive scope of issues that need to be addressed in the Show Cause Order, \nand the relatively limited amount of time to consider and address those issues, there has simply \nnot yet been sufficient opportunity for MISO and MISO Transmission Owners to finalize a rate \ndesign for GRITS.  Notwithstanding the lack of such rates being included in this filing, MISO has \ndeveloped a sufficiently detailed and robust transmission service that both complies with the intent \nof the Show Cause Order and merits Commission acceptance, subject to further compliance.  This \nis particularly the case because GRITS cannot be provided until January 2029.   \n \nThe GRITS proposal also applies gross-basis treatment to applicable service-related \ncharges, including regulation and black start, so that a co-located arrangement does not avoid \ncharges for services it receives merely because its net withdrawal is below its gross load.  These \nreservation-based charges and gross-basis billing serve different functions and apply through the \nbilling determinants established for the particular service. \n \nA reservation-based charge, such as that used for the existing Point-To-Point Transmission \nService rates, reflects the amount of Transmission Service reserved, rather than actual \nconsumption alone.  The applicable schedules govern any billing adjustment or credit for \ninterrupted service.  Co-located generation serving a Large Load receiving GRITS service must \nbe registered as a Generation Resource, and the Large Load Transmission Customer must procure \nTransmission Service to receive service from the co-located resource.  Co-location therefore does \nnot eliminate the obligation to procure Transmission Service or permit the customer to “net away” \ngross load relevant to regulation and black start billing.   \n \nD. \nPrice-based interruption. \n \nNon-Firm GRITS will be interrupted when the Locational Marginal Price at its CPNode \nexceeds the GRITS Offer Cap, which is $100/MWh.  Ms. Xie explains that historical data, \nincluding the 2025 State of the Market Report, indicates that historical data indicates this price \npermits service more than 95% of all Hours.8  To effectuate the GRITS Offer Cap in the Day-\nAhead Energy and Operating Reserve Market, the Market Participant representing the Large Load \nwill be required to submit a Price Sensitive Demand Bid for the CPNode representing the non-\n \n7  \nMISO’s Transmission Owners have filing rights with respect to the rates for transmission service pursuant \nAppendix K to the Agreement of Transmission Facilities Owners to Organize the Midcontinent Independent \nSystem Operator, Inc., Rate Schedule No. 1 of the Tariff (“Transmission Owners Agreement\"). \n8  \n2025 STATE OF THE MARKET REPORT FOR THE MISO ELECTRICITY MARKETS available at: \nhttps://www.potomaceconomics.com/wp-content/uploads/2026/07/2025-MISO-SOM_Appendix_Final.pdf."},{"page":7,"startToken":2567,"endToken":3030,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 7 \n \n \nfirm portion of the GRITS Load that is no greater than $100/MWh.  The GRITS Offer Cap will be \neffectuated in both the Day-Ahead and Real-Time Energy and Operating Reserve Markets by \nincorporating the Non-Firm GRITS portion of the GRITS Load into the Security Constrained Unit \nCommitment (“SCUC”) and Security Constrained Economic Dispatch (“SCED”) processes.  As \nsuch, Ms. Xie explains that the Large Load Transmission Customer’s election of Non-Firm GRITS \ntherefore includes the ability to comply with both the price condition and the resulting operating \ndirective. \n \nMs. Xie further explains that the GRITS Offer Cap serves two complementary objectives.9  \nFirst, by establishing the GRITS Offer Cap, MISO can use the Security Constrained Economic \nCommitment (“SCUC”) and Security Constrained Economic Dispatch (“SCED”) processes to \nefficiently issue Interruption directives to the Non-Firm GRITS Load without relying upon \nadministrative Emergency procedures. Requiring Non-Firm GRITS Loads to be included in the \nSCUC/SCED processes provides an automated and transparent way of curtailing these Loads as \nthe system conditions experienced reduced transmission or generation capacity.  Second, \nestablishing the GRITS Offer Cap at the first non-zero step of the Market-Wide Short-Term \nReserve Demand Curve prevents reliability being degraded for all Transmission Customers by \nensuring the Non-Firm GRITS Load is offline before a shortfall of operating reserves occurs.  This \nlimitation reflects the “as-available” nature of Non-Firm GRITS and is consistent with the \nreliability rationale underlying the Tariff’s authorization to curtail Non-Firm Point-To-Point \nTransmission Service when an Emergency or other unforeseen condition threatens to impair or \ndegrade Transmission System reliability.   \n \nE. \nReliability based Curtailment and enforcement. \n \nNon-Firm GRITS Load is also subject to reliability-based Curtailment directives, including \nCurtailment upon the declaration of a Capacity Advisory in the same Local Balancing Authority \n(“LBA”).  During Transmission Emergencies, Non-Firm GRITS Load is curtailed with the same \npriority as Loads served using Non-Firm Point-To-Point Transmission Service of equal service \nduration and before Loads served through Interim NITS and Firm Transmission Service.  Ms. Xie \nexplains how Resource Adequacy is maintained if the Non-Firm GRITS Load is excluded from \nthe Planning Resource Auction because the GRITS Offer Cap will ensure these Loads are curtailed \nwhenever LMP rises above the GRITS Offer Cap.10  In the event a Capacity Advisory declaration \nis made while LMP is below the GRITS Offer Cap, MISO will issue the Curtailment directive for \nthe entire Non-Firm GRITS Load.11  Accordingly, Resource Adequacy is assured because these \nLoads will not be competing with other types of Load at the times when Resource Adequacy is \nunder pressure.  The portion of a Large Load served through Firm GRITS remains in the \nCoincident Peak Demand forecast and retains the corresponding capacity responsibility to procure \nZonal Resource Credits. \n \n9  \nXie at 9. \n10   Xie at 16. \n11   Id."},{"page":8,"startToken":3030,"endToken":3432,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 8 \n \n \n \nGRITS depends on observable and enforceable withdrawal limits.  Metering, telemetry, \nmodel representation, communications, and operating controls support MISO’s administration of \nthose limits.  The Transmission Owner will determine additional control technologies or protection \nsystems required for the arrangement.  MISO will communicate Interruption and Curtailment \ndirectives through the Market Participant representing the Load in MISO’s Energy and Operating \nReserve Markets, and applicable operating procedures will govern restoration.  \n \nMs. Xie explains that if the Large Load Transmission Customer with Non-Firm GRITS \nfails to interrupt when directed, the applicable Transmission Owner has the authority implement \nremote disconnect procedures, and the Large Load Transmission Customer will be subject to \nunreserved use penalties, additional financial penalties for repeated failure, and possible \ntermination of Transmission Service.12  These consequences support the operating limitations the \ncustomer accepts in electing GRITS.   \n \nF. \nResource Adequacy, ARR Entitlements, and market participation. \n \nFirm GRITS remains subject to the applicable Resource Adequacy and capacity obligations \nestablished in Module E of the Tariff and is eligible to register as a Load Modifying Resource.  \nMs. Xie explains, the portion of a Large Load served through Non-Firm GRITS service may be \nexcluded from the obligation to procure Zonal Resource Credits.13  This means this portion of the \nLarge Load will not be included in the Coincident Peak Demand forecast and a Market Participant \nis not eligible to enroll the Non-Firm GRITS portion of the Large Load as a Load Modifying \nResource. The portion of a Large Load served through Firm GRITS is required to procure Zonal \nResource Credits and is eligible to participate as a Load Modifying Resource.  \n \nMISO is not proposing changes to the eligibility requirements for a Load to receive Auction \nRevenue Rights (“ARR”).  The Tariff changes proposed herein clarify that ARR Entitlements are \nlimited to Firm GRITS Load only, and the non-firm component of GRITS Load is excluded from \nacquiring ARRs and from the Peak Usage determination.  \n \nThe proposal prohibits Non-Firm GRITS Load from participating as a Demand Response \nResource (“DRR”), Load Modifying Resource (“LMR”), or Emergency Demand Response \n(“EDR”) resource.  As explained by Ms. Xie, prohibition of Non-Firm GRITS Load from \nparticipating as a DRR is consistent with Order No. 745.  Prohibiting enrollment as a Load \nModifying Resource also follows from these Loads not having an obligation to procure Zonal \nResource Credits.14  \n \n \n12  Xie at 20. \n13  Xie at 16. \n14  Xie at 16."},{"page":9,"startToken":3432,"endToken":3852,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 9 \n \n \nG. \nPlanning and commercial model treatment. \n \nThe firm component of GRITS Load is included in ongoing MISO Transmission \nExpansion Plan (“MTEP”) planning, while the total GRITS Load remains subject to applicable \nInterconnection Reliability Requirements (“IRR”) and stability review.  The requirement to \nestablish separate CPNodes for Firm and Non-Firm GRITS Load respectively, and corresponding \nElemental Pricing Nodes allow the service allocation to be reflected in operations, forecasts, \nbidding, billing, and ARR treatment.  Actual  Energy Withdrawals associated with GRITS service \nare assigned first to the firm component, up to the Firm GRITS service quantity, with remaining \nwithdrawals assigned to the Non-Firm GRITS quantity.  This representation does not authorize \nwithdrawals beyond a valid Transmission Service Reservation or the applicable operating limit.   \n \nIV. \nRESPONSE TO THE SHOW CAUSE ORDER \n \nSection 205 requires jurisdictional rates and practices to be just and reasonable and \nprohibits undue preferences and unreasonable differences in service.15  GRITS ties the \nTransmission Customer’s rights to the service it requests: firm quantities retain firm treatment and \ncorresponding capacity obligations, while non-firm quantities receive as-needed and as-available \nservice, lower priority for reliability interruptions, and a price-based interruption condition.16  \nSeparate reservation requirements and model treatment for Firm and Non-Firm GRITS makes \nthose distinctions administrable. \n \nThe GRITS proposal responds to the ongoing flexible-service concerns in paragraphs 100 \nthrough 105 of the Show Cause Order by establishing a defined Load Limit, an elected firm \nquantity, separately reserved non-firm service, and enforceable operating conditions.17  The \nproposal’s gross-load treatment prohibits netting and addresses the regulation and black start \nconcerns identified in Paragraphs 98–100 of the Show Cause Order.  In addition, the proposal’s \nmetering and control requirements address the withdrawal-limit concerns in paragraph 102 of the \nShow Cause Order.  Those features connect the service received with the obligations accepted by \nthe customer.18   \n \nThe planning provisions of the GRITS proposal, which require requests for GRITS to be \nevaluated through the LLPR process consistent with all other requests for Transmission Service \nmade by Large Load Transmission Customers, also address the issue identified in Paragraph 124 \nof the Show Cause Order.19  Through this process requests for Firm GRITS will be subject to the \nanalysis for ongoing firm service, which reflects the Firm GRITS quantity, while total GRITS \n \n15  16 U.S.C. § 824d(a)–(b). \n16  Show Cause Order at PP 100-105; Xie at 6, 20. \n17  Xie at 18-21. \n18  Show Cause Order at PP 98–105. \n19  Xie at 7; Show Cause Order at P 124."},{"page":10,"startToken":3852,"endToken":4237,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 10 \n \n \nLoad remains subject to reliability and stability assessment.20  The GRITS accreditation provisions \nfor co-located ZG Resources addresses the portion of paragraph 127 of the Show Cause Order \nconcerning the relationship between capacity recognition and the associated load’s service.21  \nThese provisions supplement the separately proposed study and generator-interconnection \nframeworks.22   \n \nReservation-based charges, gross-load ancillary service billing, price-based interruption, \nand firm-only ARR eligibility address different aspects of cost responsibility.23  The separately \nproposed cost recovery agreements submitted in the omnibus filing are required for all address \nobligations associated with covered Large Load Network Upgrades and Impacted Transmission \nOwner Network Upgrades.  Because requests for GRITS are required to be evaluated through the \nLLPR, all Large Load Transmission Customers granted GRITS will be required to enter into the \nForm of Agreement for Large Load Cost Recovery Agreement (proposed Attachment LLL) and \nForm of Agreement for Large Load Impacted Transmission Owner Cost Recovery Agreement \n(proposed Attachment MMM).24 \n \nGRITS service is only available to Large Load Transmission Customers capable of meeting \noperational requirements for GRITS and these enforcement mechanisms ensure that the approved \nservice quantities are not merely contractual limits but are limits that MISO can enforce in real \ntime.25  Large Load Transmission Customers electing GRITS are subject to the same applicable \nservice conditions.  The distinct treatment of Firm and Non-Firm GRITS quantities reflects the \nunique characteristics, firmness, curtailment and interruption obligations of each respective \nservice.   \n \nV. \nDESCRIPTION OF PROPOSED TARIFF REVISIONS \n \nAs discussed, GRITS is an independent, stand-alone proposal that can be accepted and \nimplemented separate from MISO’s other FPA section 205 filing submitted in response to the \nShow Cause Order.  Because MISO’s omnibus filing has been submitted prior to this filing, MISO \nhas built the GRITS Tariff revisions to include (i.e., on top of) the proposed revisions to the Tariff \nsubmitted in the omnibus filing.  MISO has highlighted all Tariff language pending Commission \nacceptance in the Tariff records submitted in Tab A hereto.   \n \nThe proposed Tariff records establish GRITS eligibility and defined quantities; application, \nestablish a Form of GRITS Service Agreement, and Operating Agreement requirements; \n \n20  Xie at 7, 19-21. \n21  Xie at 17-18. \n22  Show Cause Order at PP 124, 127. \n23  Xie at 15-16, 19-20. \n24  Xie at 7. \n25  Xie at 20-21."},{"page":11,"startToken":4237,"endToken":4632,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 11 \n \n \nreservation duration and priority; price and reliability interruption; control, enforcement, and \nrestoration requirements; and changes to the Load Limit or firm quantity.  Conforming revisions \nto Module C of the Tariff implement separate commercial model representation requirements, \nestablish ARR eligibility only for Firm GRITS, establish Resource Adequacy treatment, \nparticipation restrictions, and the co-located ZG Resource accreditation interface.   \n \nA. \nDefinitions \n \n \nMISO proposes the following, new definitions for GRITS: \n \nFirm Grid Response Integration Transmission Service (Firm GRITS):  The amount of \nfirm Transmission Service that is reserved and/or scheduled to a specific Point(s) of \nDelivery pursuant to the Form of Service Agreement for GRITS.  A Large Load \nTransmission Customer taking Firm GRITS may reserve and/or schedule between 0 MW \nand the GRITS Load Limit. \n \nGrid Response Integration Transmission Service (GRITS):  A Transmission Service \nprovided under Module B of this Tariff that permits a Large Load Transmission Customers \nto take Transmission Service.  GRITS permits the reservation of Capacity and of Energy \non either a firm or non-firm basis from Network Resources to the Point(s) of Delivery.  \nGRITS is comprised of three components; GRITS Load Limit, Firm GRITS, and Non-Firm \nGRITS.  A Transmission Customer may not change the GRITS Load Limit or the amount \nof Firm GRITS without a new Form of Service Agreement for GRITS. \n \nGRITS Load Limit:  The maximum amount of Load specified in the Form of Service \nAgreement for GRITS by the Large Load Transmission Customer taking GRITS that may \nbe scheduled at a Point(s) of Delivery pursuant to Module B of this Tariff. \n \nGRITS Offer Cap:  The maximum Locational Marginal Price at the Commercial Pricing \nNode associated with a Large Load taking Non-Firm GRITS service that a Market \nParticipant may submit in a Bid.  Non-Firm GRITS may be Interrupted if the Locational \nMarginal Price rises above the GRITS Offer Cap. \n \nNon-Firm GRITS:  The amount of Non-Firm Transmission Service that is reserved and \nscheduled on an as-available basis and is subject to Curtailment or Interruption as set forth \nin Section 37B of this Tariff.  Non-Firm GRITS is available only to Large Load \nTransmission Customers for periods ranging from one (1) Day to one (1) Month.  A Large \nLoad Transmission Customer taking Grid Responsive Integration Transmission Service \nmay reserve and/or schedule between 0 MW and the difference of GRITS Load Limit and \nFirm GRITS."},{"page":12,"startToken":4632,"endToken":4946,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 12 \n \n \n \nB. \nModule B \n \n \nMISO has revised the introduction of Module B of the Tariff to establish GRITS as a \nservice available only to Large Load Transmission Customers.  In addition, MISO has established \nSection 37B of the Tariff to include the terms and conditions of GRITS.  The following table \nprovides a brief overview of the proposed GRITS Tariff revisions in addition to the definitions. \n \n \nThe marked and clean Tariff records submitted as Tab A and B respectively, set out the \nrevisions.  The following table of Tariff revisions is provided for reference and informational \npurposes only.  The language filed in the proposed Tariff revisions shall control in the event of any \ndiscrepancies between the information provided in this table and the proposed Tariff revisions.  \n \nTariff Section \nTariff Section Title \nBrief Description of changes \nModule B \n \n \n37B.1 \nGRITS Term \nEstablishes the minimum service \nterms for Firm GRITS and Non-Firm \nGrits \n37B.2 \nGRITS Reservation Priority \nEstablishes the reservation priority for \nFirm GRITS and Non-Firm GRITS \nrelative to other Transmission \nServices under the Tariff \n37B.3 \nGRITS Service Agreement \nEstablishes the requirement that a \nLarge Loat Transmission Customer \ntaking GRITS must execute a Form of \nService Agreement for GRITS. \n37B.4 \nGRITS Change in Service Request \nEstablishes the requirement that a \nLarge| Loat Transmission Customer \nseeking to change the amount of \nGRITS must submit a new application \nfor GRITS. \n37B.5 \nGRITS Transmission Provider \nResponsibilities \nEstablishes MISO’s responsibilities \nfor revising GRITS requests. \n37B.6 \nSecondary Service to Firm GRITS \nEstablishes the treatment of Firm \nGRITS from non-Designated Network \nResources and the associated priority \nof the service. \n37B.7 \nGRITS Restrictions on Use of \nService \nRequires any Large Load \nTransmission Customer to use Point-\nto-Point Transmission Service for \nthird-party sales outside of the MISO \nRegion. \n37B.8 \nGRITS Application Procedures \nEstablishes the application and \nprocedures for requesting GRITS, and"},{"page":13,"startToken":4946,"endToken":5221,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 13 \n \n \nprovides detail regarding the \nevaluation of a GRITS request. \n37B.9 \nGRITS Arrangement to be \nCompleted Prior to Service \nEstablishes the requirement to \ncomplete installation of all equipment \nspecified under the GRITS Operating \nAgreement prior to service. \n37B.10 \nGRITS Transmission Customer \nFacilities \nEstablishes responsibility for \nconstruction, maintenance and \noperation of facilities used to provide \nGRITS. \n37B.11 \nGRITS Study Procedures \nEstablishes the study procedures for \nrequests for Non-Firm GRITS. \n37B.12 \nGRITS Procedures \nRequires that procedures for Load \nShedding, Curtailment and \nInterruption be established by MISO, \nthe Transmission Owner and Large \nLoad Transmission Customer prior to \ncommencement of GRITS. \n37B.13 \nGRITS Transmission Constraints \nStates that MISO will take actions \nnecessary to maintain Transmission \nSystem reliability if necessary to \naddress a transmission constraint. \n37B.14 \nGRITS Cost Responsibility for \nRelieving Transmission Constraint \nEstablishes that curtailment of \nscheduled deliveries may occur in \naccordance with the applicable \nGRITS Operating Agreement or \nNERC / NAESB TLR procedures. \n37B.15 \nGRITS Curtailment of Scheduled \nDeliveries \nEstablishes the procedure for \ncurtailing Firm GRITS. \n37B.16 \nGRITS Load Shedding \nEstablished the procedures for Load \nShedding relative to Firm GRITS. \n37B.17 \nGRITS System Reliability \nEstablishes the provisions for \ncurtailment of Firm and Non-Firm \nGrits, and the costs associated with a \nLarge Load Transmission Customer’s \nfailure to respond to MISO’s \ncurtailment directives. \n37B.18 \nClassification of Firm GRITS \nLimits the use of FIRM GRITS to the \nlevels specific in the applicable \nGRITS Service Agreement. \n37B.19 \nClassification of Non-Firm GRITS \nEstablishes unreserved use penalties \nfor Non-Firm GRITS \n37B.20  \nScheduling of Non-Firm GRITS \nRequires Non-Firm GRITS schedules \nto be submitted consistent with the"},{"page":14,"startToken":5221,"endToken":5541,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 14 \n \n \nrequirements of Attachment J to the \nTariff. \n37B.21 \nNon-Firm GRITS Curtailment or \nInterruption of Service \nEstablishes the rules for curtailment or \ninterruption of Non-Firm GRITS and \nthe priority of Non-Firm GRITS in \nrelation to other Transmission \nServices. \n37B.22 \nGRITS Offer Cap \nEstablishes the GRITS Offer Cap of \n$100/MWh. \n37B.23 \nGRITS Operating Agreement \nEstablishes the components of the \nGRITS Operating Agreement. \nModule C \n \n  \n38.6 \nAggregators of Retail Customers \nRequires an ARC to attest that no part \nof a DRR, LMR, or EDR is being \nserved by Non-Firm GRITS. \n39.2.2 \nDemand Bid Rules in the Day-\nAhead Energy and Operating \nReserve Markets \nLimits the amount of Price Sensitive \nDemand Bid from Large Load taking \nNon-Firm GRITS to the GRITS Offer \nCap. \n40.2.15.s \nReal-Time Energy and Operating \nReserve Market Process \nEstablishes that Non-Firm GRITS is \nsubject to Interruption when the Real-\nTime Ex Ante LMP exceeds the \nGRITS Offer Cap. \n40.2.20 \nCapacity Shortage Conditions in \nthe Real-Time Energy and \nOperating Reserve Market \nEstablishes Step Zero in the priority \nof Interruption for Capacity Shortage \nConditions in the Real Time market. \n42.6 \nPartial-Year FTR Allocation \nProcess for New ARR Zones \nIncludes Firm GRITS as an eligible \nservice for nominations. \n43.2.4 \nNomination and Allocation of \nARRs and MTPS ARRs \nIncludes Firm GRITS as an eligible \nservice for nominations. \n69A.1.1 \nForecasted Demand Identification \nExcludes Non-Firm GRITS from \nCoincident Peak Demand forecast. \n69A.1.2 \nDaily Assignment of Coincident \nPeak Demand Obligations \nExcludes Demand from a Large Load \ntaking Non-Firm GRITS from an \nLSE’s portion of such Demand. \n69A.3.1.G \nDetermination of Deliverability \nMakes explicit deliverability of a ZG \nResource to a ZG Associated Load \nrequires Firm Transmission Service or \nInterim NITS Transmission Service. \n69A.3.3 \nLoad Modifying Resources \nNon-Firm GRITS cannot participate \nas a Load Modifying Resource \nAttachments"},{"page":15,"startToken":5541,"endToken":5968,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 15 \n \n \nAttachment F-1 \nForm of Service Agreement for \nGrid Responsive Integration \nTransmission Service \nForm of Service Agreement for \nGRITS and related exhibits including \nspecification sheets. \nAttachment G-1 \nForm of GRITS Operating \nAgreement for Grid Responsive \nIntegration Transmission Service \nForm Operating Agreement for \nGRITS service. \n   \nVI. \nSTAKEHOLDER ENGAGEMENT \n \nMISO developed the GRITS proposal through successive discussions with the Large Load \nWorking Group (“LLWG”).  At the August 12, 2026 LLWG meeting, MISO presented its Flexible \nLarge-Load Interconnections and Transmission Service (“FLITS”) concept, which contemplated \nboth interim and permanent non-firm service.  MISO requested written feedback by August 19, \n2026, with particular emphasis on resource adequacy.  Stakeholders addressed curtailment, \ncapacity obligations, and the implications of offering permanent non-firm service.  The \nenvironmental sector recommended developing separate interim and permanent products given \ntheir different purposes and operating requirements.26 \n \nAt the September 9, 2026 LLWG meeting, MISO presented interim FLITS and a separate \npermanent Contract Demand service and requested written comments by September 16. \nStakeholders addressed how the proposed services would differ in rates, curtailment priority, \nresource adequacy treatment, and ARR eligibility.  At the September 23, 2026  LLWG meeting, \nMISO focused its presentation on Interim NITS and confirmed during the discussion that it \ncontinued to develop the permanent service and would return with an update on October 8, 2026.  \nThe September 23, 2026 feedback request set an October 2, 2026 deadline for comments on the \nInterim NITS design and an October 16 deadline for comments on the anticipated Interim NITS \nTariff redlines.27 \n \nAt the October 8, 2026 LLWG meeting, MISO presented the permanent service as GRITS \nand requested written feedback by October 16, 2026.  The proposal allowed customers to combine \na firm service quantity with short-term, as-available non-firm reservations.  MISO also proposed \nexcluding the non-firm portion from the Coincident Peak Demand forecast and requiring \ninterruption under specified reliability and price conditions.  Stakeholders commented on the \nproposed price trigger, coordination and enforcement of curtailment, capacity forecasting and \nmodeling, and the treatment of co-located resources.  They also asked how a customer could \nincrease its firm service quantity after service began.  \n \n26   MISO, LLWG, Flexible Large-Load Interconnections and Transmission Service (FLITS) Proposal, LLWG-2026-\n5 (Aug. 12, 2026) (feedback request and submitted comments, including Environmental Sector comments). \n(misoenergy.org, misoenergy.org). \n \n27  MISO, LLWG, Non-Firm Large Load, Item 6 (Sept. 9, 2026), and associated feedback request and comments, \nLLWG-2026-5. See also MISO, LLWG, Conditional Non-Firm Transmission Service, Item 7, slide 2 (Sept. 23, \n2026), and associated Interim NITS feedback request, LLWG-2026-5. (misoenergy.org, cdn.misoenergy.org, \nmisoenergy.org)."},{"page":16,"startToken":5968,"endToken":6401,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 16 \n \n \n \nAt the October 29, 2026 LLWG meeting, MISO presented GRITS alongside Interim NITS \nand reviewed the differences in reservation terms, service priority, billing, and resource adequacy \ntreatment.  After receiving stakeholder feedback on the October 8, 2026 proposal, MISO reported \nthat it was evaluating whether to use a GRITS Offer Cap as a price-based interruption trigger and, \nif so, where to set it.  Stakeholders submitted additional written comments on November 4 \naddressing, among other matters, non-firm transmission charges, the proposed price trigger, and \nresource adequacy treatment.28 \n \nVII. \nDOCUMENTS SUBMITTED IN THIS FILING \n \nIn addition to this Transmittal Letter, this submission includes the following materials, with \nthe final tab and exhibit designations identified in the filing index: \n \nTab A – Redline Tariff29 \n \nTab B – Clean Tariff \n \nTab C – Testimony of Zhaoxia Xie \n \nVIII. \nEFFECTIVE DATE AND REQUEST FOR CONTINUED ABEYANCE \n   \nMISO requests an effective date 120-days from the date of this filing (i.e., March 16, 2027), \nwith implementation of GRITS to begin January 1, 2029.  Acceptance of the GRITS proposal by \nthe requested effective date is necessary to facilitate the planned implementation timeline because \nsuch implementation requires significant modifications to MISO’s existing software systems and \nprocesses, coordinated service agreements, models, market registration, billing arrangements, \noperating controls, and communications. \n \n \n28  MISO, LLWG, Interim NITS and Grid Responsive Integration Transmission Service, Item 5, slides 2, 8, 20–24 \n(Oct. 29, 2026). Antora Energy comments (Nov. 4, 2026, posted Nov. 9, 2026). (cdn.misoenergy.org, \ncdn.misoenergy.org, misoenergy.org, misoenergy.org). \n29  Language currently pending before the Commission in the following, unrelated dockets is highlighted in yellow: \nER26-3552-000 and ER26-3650-000.  Also highlighted is pending language filed in MISO’s Large Load Omnibus \nfiling being submitted contemporaneously.  MISO requests that the Commission treat such highlighted language \nas subject to the outcome of those pending proceedings.  If needed, MISO commits to file any revisions to this \nhighlighted language as necessary to comply with any Commission orders in the proceeding. \nIn addition, MISO has not included language that has future effective dates of 6/1/2027, 9/1/2027, 6/12/2028, \n6/1/2029, under Docket Nos. ER22-1640-007, ER22-1640-006, and ER22-1640-003, respectively. MISO has also \nremoved language that has a future effective date of 9/1/2027 and is pending in Docket No. ER25-1886-000. If \nneeded, MISO commits to file any revisions to comply with any Commission orders in these proceedings and \nMISO commits to make subsequent filings with the Commission to reflect the most up-to-date version of the \nthen-current Tariff provisions prior to the effective dates of the language."},{"page":17,"startToken":6401,"endToken":6800,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 17 \n \n \nMISO also moves to extend the existing abeyance period under Rule 212 of the \nCommission’s Rules of Practice and Procedure.30  As the Abeyance Order explained, the \nCommission encouraged MISO, the Transmission Owners, and stakeholder to continue to \ncollaborate in order to develop one or more FPA section 205 proposals to address the requirements \nof the Show Cause Order.31  The GRITS proposal is one output from this ongoing stakeholder \nprocess.  As stated, MISO cannot implement GRITS until January 1, 2029, subject to the \nCommission accepting a rate, which as explained above will be submitted in for Commission \nreview in a future filing.  MISO, therefore, moves to extend the abeyance period until the \nCommission accepts the GRITS proposal and applicable rate for Firm and Non-Firm GRITS.  \nMISO respectfully submits that this extension to the abeyance is necessary to avoid a lapse in the \nexisting abeyance period while the GRITS rate is determined.  Moreover, granting the continued \nabeyance is reasonable, especially in light of the limited scope of request as compared to the \nsignificant proposals filed in response to the Show Cause Order. \n \nIX. \nCOMMUNICATIONS \nMISO respectfully requests waiver of Rule 203(b)(3) of the Commission’s Rules of \nPractice and Procedure, 18 C.F.R. § 385.203(b)(3) (2026), to the extent necessary to permit the \ndesignation of more than two persons for service on behalf of MISO in this proceeding and requests \nall communications related to this filing be directed to: \nMichael Kessler  \nManaging Assistant General Counsel \nMidcontinent Independent System   \nOperator, Inc. \n720 City Center Drive  \nCarmel, Indiana 46032  \nTelephone: (317) 753-9434 \nmkessler@misoenergy.org \n \n \nJames C. Holsclaw \nLauren A. Stenger \nCalfee, Halter & Griswold LLP \n3900 Salesforce Tower \n111 Monument Circle \nIndianapolis, Indiana 46204 \nTelephone: (317) 308-4266 \njholsclaw@calfee.com \nlastenger@calfee.com  \n \nX. \nNOTICE AND SERVICE \nMISO has served a copy of this filing electronically, including attachments, upon all Tariff \ncustomers, MISO Members, Member representatives of Transmission Owners and non-\nTransmission Owners, as well as all state commissions within the MISO Region and the \nOrganization of MISO States.  The filing has been posted electronically on MISO’s website at \nhttps://www.misoenergy.org/legal/ferc-filings/ for other interested parties in this matter. \n \n \n30  See 18 C.F.R.  § 385.212 (2026).   \n31  Midcontinent Indep.  Sys.  Operator, Inc., 196 FERC P 61,133, at PP 8-9 (2026) (“Abeyance Order”)."},{"page":18,"startToken":6800,"endToken":6912,"text":"The Honorable Debbie-Anne Reese \nNovember 16, 2026 \nPage 18 \n \n \nXI. \nCONCLUSION \nFor all of the foregoing reasons, MISO respectfully requests that the Commission accept \nthis filing and grant waiver of any Commission regulations the Commission deems in order for the \nCommission to accept it as proposed. \nRespectfully submitted, \n \n/s/ Michael Kessler \nMichael Kessler  \nManaging Assistant General Counsel \nMidcontinent Independent System   \nOperator, Inc. \n720 City Center Drive  \nCarmel, Indiana 46032  \nTelephone: (317) 753-9434 \nmkessler@misoenergy.org \n \nJames C. Holsclaw \nLauren A. Stenger \nCalfee, Halter & Griswold LLP \n3900 Salesforce Tower \n111 Monument Circle \nIndianapolis, Indiana 46204 \nTelephone: (317) 308-4266 \njholsclaw@calfee.com   \nlastenger@calfee.com \n \nAttorneys for the Midcontinent Independent \nSystem Operator, Inc. \nAttachments"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":578,"startToken":0,"endToken":431},{"p":2,"at":578,"title":"I. EXECUTIVE SUMMARY","method":"printed heading","endPage":3,"endAt":189,"startToken":431,"endToken":879},{"p":3,"at":189,"title":"II. BACKGROUND","method":"printed heading","endPage":4,"endAt":64,"startToken":879,"endToken":1311},{"p":4,"at":64,"title":"III. PROPOSED GRITS SERVICE","method":"printed heading","endPage":4,"endAt":96,"startToken":1311,"endToken":1315},{"p":4,"at":96,"title":"A. Eligibility, service quantities, and agreements.","method":"PDF bookmark","endPage":5,"endAt":412,"startToken":1315,"endToken":1863},{"p":5,"at":412,"title":"B. Reservations and service priority.","method":"PDF bookmark","endPage":5,"endAt":1571,"startToken":1863,"endToken":2022},{"p":5,"at":1571,"title":"C. Transmission charges and gross-load billing.","method":"PDF bookmark","endPage":6,"endAt":2413,"startToken":2022,"endToken":2405},{"p":6,"at":2413,"title":"D. Price-based interruption.","method":"PDF bookmark","endPage":7,"endAt":1881,"startToken":2405,"endToken":2829},{"p":7,"at":1881,"title":"E. Reliability based Curtailment and enforcement.","method":"PDF bookmark","endPage":8,"endAt":1119,"startToken":2829,"endToken":3171},{"p":8,"at":1119,"title":"F. Resource Adequacy, ARR Entitlements, and market participation.","method":"PDF bookmark","endPage":9,"endAt":64,"startToken":3171,"endToken":3441},{"p":9,"at":64,"title":"G. Planning and commercial model treatment.","method":"PDF bookmark","endPage":9,"endAt":947,"startToken":3441,"endToken":3559},{"p":9,"at":947,"title":"IV. Response to the Show Cause Order","method":"PDF bookmark","endPage":10,"endAt":1815,"startToken":3559,"endToken":4095},{"p":10,"at":1815,"title":"V. DESCRIPTION OF PROPOSED TARIFF REVISIONS","method":"printed heading","endPage":11,"endAt":528,"startToken":4095,"endToken":4302},{"p":11,"at":528,"title":"A. Definitions","method":"printed heading","endPage":12,"endAt":67,"startToken":4302,"endToken":4641},{"p":12,"at":67,"title":"B. Module B","method":"printed heading","endPage":15,"endAt":65,"startToken":4641,"endToken":5550},{"p":15,"at":65,"title":"Attachment F-1","method":"printed heading","endPage":15,"endAt":255,"startToken":5550,"endToken":5574},{"p":15,"at":255,"title":"Attachment G-1","method":"printed heading","endPage":15,"endAt":411,"startToken":5574,"endToken":5593},{"p":15,"at":411,"title":"VI. STAKEHOLDER ENGAGEMENT","method":"printed heading","endPage":16,"endAt":670,"startToken":5593,"endToken":6063},{"p":16,"at":670,"title":"VII. DOCUMENTS SUBMITTED IN THIS FILING","method":"printed heading","endPage":16,"endAt":972,"startToken":6063,"endToken":6107},{"p":16,"at":972,"title":"VIII. EFFECTIVE DATE AND REQUEST FOR CONTINUED ABEYANCE","method":"printed heading","endPage":17,"endAt":1226,"startToken":6107,"endToken":6592},{"p":17,"at":1226,"title":"IX. COMMUNICATIONS","method":"printed heading","endPage":17,"endAt":2010,"startToken":6592,"endToken":6705},{"p":17,"at":2010,"title":"X. NOTICE AND SERVICE","method":"printed heading","endPage":18,"endAt":65,"startToken":6705,"endToken":6809},{"p":18,"at":65,"title":"XI. CONCLUSION","method":"printed heading","endPage":18,"endAt":857,"startToken":6809,"endToken":6912}]}