{"document":{"slug":"rec-20250324-5240","title":"Answer of The Dayton Power and Light Company d/b/a AES Ohio to Order Instituting Proceeding Under Section 206 of the Federal Power Act and Consolidating…","issued":"2025-03-24","accession":"20250324-5240","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Dayton Power and Light Company, The","kind":"answer","file":"sources/filings/text/20250324-5240_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250324-5240","tier":"record","sha256":"7642d080d5e5ebe454a6931ebf90e54ebc36b564f2876dec2fc9e831058fc419","pages":16,"tokens":3864,"emptyPages":[],"textThemes":["colo","study","adequacy","cost"]},"pages":[{"page":1,"startToken":0,"endToken":194,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C., et al. \n \n) \nDocket No. EL25-49-000 \n \nLarge Loads Co-Located at Generating \nFacilities \n) \nDocket No. AD24-11-000 \nConstellation Energy Generation, LLC \n \nv. \n \nPJM Interconnection, L.L.C. \n) \nDocket No. EL25-20-000 \n(consolidated) \n \nANSWER OF  \nTHE DAYTON POWER AND LIGHT COMPANY D/B/A AES OHIO  \nTO ORDER INSTITUTING PROCEEDING  UNDER SECTION 206 OF THE \nFEDERAL POWER ACT  AND CONSOLIDATING WITH OTHER \nPROCEEDINGS \n \nPursuant to Rules 206 and 213 of the Rules of Practice and Procedure of the Federal \nEnergy Regulatory Commission (“FERC” or “Commission”),1 The Dayton Power and \nLight Company d/b/a AES Ohio (“AES Ohio”) submits this answer and attachment below \nproviding responses to the Commission’s Order Instituting Proceeding Under Section 206 \nof the Federal Power Act and Consolidating with Other Proceedings, issued on February \n20, 2025.2   As discussed in the  responses  below,  AES Ohio believes that a framework \nfor co-location configurations is addressed by the PJM Tariff, and that the Tariff is just and \n \n1 18 C.F.R. §§ 385.206, 385.213 (2024). \n2 PJM Interconnection, L.L.C., 190 FERC ¶ 61,195 (2025) (“Show Cause Order”)."},{"page":2,"startToken":194,"endToken":412,"text":"reasonable as to service to such co-located load taken under PJM Network Integration \nTransmission Service or Firm Point to Point Service.3  However, other approaches may \nalso be just and reasonable and not unduly discriminatory to the extent that they incentivize \nco-located load that provides reliability benefits and cost savings.  AES Ohio is open to \nworking with PJM and stakeholders to explore alternative transmission service \narrangements for certain co-located load configurations that may be appropriate to reflect \nspecific co-located load circumstances and associated system needs. If alternative \narrangements are considered, co-located load should pay for its use of the PJM \nTransmission System in a manner that avoids unjust and unreasonable outcomes and that \nholds other transmission customers harmless. AES Ohio respectfully thanks the \nCommission for seeking input on this important and highly impactful topic.  \nRespectfully submitted,  \n \n \n \n \n \n \n \n/s/ William M. Rappolt \n \n           \n \n \n \nWilliam M. Rappolt \nAssistant General Counsel, FERC \nAES US Services LLC \n4300 Wilson Blvd \nArlington, VA 22203 \nTel: 571-533-9018 \nEmail: william.rappolt@aes.com \n \nCounsel for The Dayton Power and Light \nCompany d/b/a AES Ohio \nDated: March 24, 2025\n \n3  \nAs noted below, for many of specific questions asked by the Commission, AES Ohio generally agrees \nwith the response provided by the Indicated TOs in response to show cause order and filed today in this \nproceeding."},{"page":3,"startToken":412,"endToken":724,"text":"Attachment A \n \na. General \ni. \nDo you agree with the jurisdictional principles outlined in section \nVI.A and should the Commission reach any other conclusions \nregarding jurisdiction in a final order it may issue in this \nproceeding?  Why or why not?   \n \nAES Ohio generally agrees with the Indicated TOs response. \n \nii. \nDoes the Tariff sufficiently address co-location arrangements with \nrespect to each issue listed in this order?  Please include specific \ntariff provisions or other governing documents that may apply;   \n \nAES Ohio believes that a framework for co-location is addressed by the PJM Tariff, and \nthat the Tariff is just and reasonable as to service to co-located load taken under PJM \nNetwork Integration Transmission Service or Firm Point to Point Service.  However, \nrecognizing that co-location is rapidly developing and evolving, AES Ohio is open to \nworking with PJM and stakeholders to explore alternative transmission service \narrangements for certain co-located load configurations that may be appropriate to reflect \nspecific co-located load circumstances and associated system needs. In certain \ncircumstances, co-located large loads may benefit the grid by providing reliability \nbenefits, decreasing congestion costs or limiting transmission upgrades.  In such cases, \nco-location could be incentivized by appropriately allocating costs, and allowing such \nload to share in the benefits, of the arrangement.  However, in all cases, co located load \nmust pay for its use of the PJM Transmission System in a manner that avoids unjust and \nunreasonable outcomes and that holds other AES Ohio transmission customers harmless. \n \niii. \nIf the Tariff does not sufficiently address co-location \narrangements, how should the Tariff be modified to do so?  As part \nof your answer, address whether portions of the Guidance \nDocument may serve as a just and reasonable and not unduly \ndiscriminatory or preferential replacement rate.  Alternatively, \naddress whether existing rules in the Tariff may or should be \nmodified to address co-location arrangements; \n \nSee response to a.ii above."},{"page":4,"startToken":724,"endToken":1051,"text":"iv. \nParties may also address how co-located loads are similar to or \ndisparate from other types of arrangements where load and \ngeneration share the same point of interconnection (such as Behind \nthe Meter Generation as defined in PJM’s Tariff or non-retail \nbehind the meter generation) and should consider how any \nproposed replacement rate would interact with these other \narrangements.    \n \nAs explained by PJM in the Guidance Document, the PJM Tariff allows for generation to \nbe treated as being “behind the meter” when such generation is co-located with a load \nand meets the specific defined criteria in the PJM Tariff.  AES Ohio agrees with PJM’s \nexplanation of (1) how such “Behind the Meter Generation” interacts with the co-located \nload for the purposes of energy netting and (2) the restrictions placed on such “Behind \nthe Meter Generation” with respect to that generation’s participation in the PJM market.  \nAES Ohio does not view “Behind the Meter Generation” as disparate to other co-location \narrangements, but rather as one of the arrangements under which co-location may occur \nin PJM.  To the extent that parties wish to expand or revisit the definition of “Behind the \nMeter Generation” with respect to current or future co-location configurations, AES Ohio \nbelieves that these discussions could be considered through the PJM stakeholder process, \nsubject to the requirement that such additional configurations do not unduly discriminate \nagainst other transmission customers.  See response to a.ii.  \n \nb. Transmission Service \n \ni. \nPlease explain whether and to what extent different configurations \nof co-located load rely on or otherwise use the transmission system \nto receive power, directly or indirectly, from the co-located \ngenerator; \n \nUnless it is physically islanded without any connection to the PJM Transmission System, \nco-located is connected to, uses, and benefits from the PJM Transmission System.  In \nthese cases, and as noted in response to a.ii above, co-located load should pay an \nappropriate share of system costs. However, there may be a range of potentially \nappropriate cost allocation frameworks."},{"page":5,"startToken":1051,"endToken":1360,"text":"ii. \nPlease explain whether and to what extent different co-location \nconfigurations impose costs on the transmission system or increase \ntransmission costs allocated to other parties.  How can those costs \nbe approximated, given that certain co-location configurations may \nchange power flows on the grid and necessitate upgrades to the \ntransmission system?  Retail loads typically take service from \nwholesale entities that pay for Network Integration Transmission \nService that allocates these costs; co-located loads may not.  \nNetwork Loads pay directly for Network Integration Transmission \nService.  How should PJM estimate the effects that different \nconfigurations of co-located load have on the transmission system?  \nShould these costs be passed through to co-location arrangements \nin some way, and, if so, how?   \n \nAES Ohio generally agrees with the Indicated TOs response.  See responses to b.i and a.ii \nabove. \n \niii. \n Please explain whether co-location arrangements are or should be \nrequired to take Network Integration Transmission Service or \nPoint-to-Point Transmission Service; or whether a more tailored \nnew category of transmission service is warranted.  Please also \naddress any cost allocation implications of your position on this \nissue; \n \nAES Ohio generally agrees with the Indicated TOs response with respect to the current \noptions available to load customers in PJM (i.e. Network Integration Transmission \nService or Point to Point Transmission Service).  However, as noted in its responses \nabove, co-located large loads may bring benefits to the system that could be incentivized \nthrough one or more alternative transmission service arrangements, and AES Ohio is \nopen to working with stakeholders and regulators to explore such alternatives, provided \nthat any such alternative results in a just and reasonable outcome that remains equitable \nto all current and future transmission customers.  See response to a.ii.   \n \n \niv. \nWhat changes to the rates, terms, and conditions of Network \nIntegration Transmission Service or Point-to-Point Transmission \nService or, alternatively, what new form of transmission service(s)"},{"page":6,"startToken":1360,"endToken":1657,"text":"may be necessary for different configurations of co-location to \nensure that the Tariff is consistent with cost causation principles \nand the beneficiary pays principle?   \n \nAES Ohio generally agrees with the Indicated TOs response. See response to a.ii.  As \nindicated above, AES Ohio will continue to work collaboratively with stakeholders. \n      \nv. \nParties may also wish to address how to determine which co-\nlocated load configurations should be required to take Network \nIntegration Transmission Service or Point-to-Point Transmission \nService or a new form of transmission service (i.e., whether \ngeneralized policies or tests, such as a multi-factor test, to be \napplied case-by-case, may be appropriate), as well as the \nmagnitude (i.e., how the service taken by co-located load compares \nto service by other types of load).  For example, if a co-located \ngenerator is synchronized to the grid but the load can be \nconfigured to be wholly isolated from the grid in the event the co-\nlocated generator trips offline, what technical and operational \nfactors should determine whether the co-location arrangement still \nrelies on the transmission system in ways that warrant a \nrequirement that the co-located load take Network Integration \nTransmission Service or Point-to-Point Transmission Service or a \nnew form of transmission service?  Are there potential co-located \nload configurations for which tailored approaches may be \nappropriate? \n \nAES Ohio generally agrees with the Indicated TOs response. As indicated above and \nconsistent with the Indicated TOs response, AES Ohio will continue to work \ncollaboratively with stakeholders to determine whether enhancements to the PJM Tariff \nwould be appropriate.  See response to a.ii. \n \n \n \nvi. \nWith respect to the Guidance Document, please explain what it \nmeans to be “electrically connected and synchronized to the PJM \nTransmission System when consuming power” and how that \nimplicates the use of Network Integration Transmission Service or"},{"page":7,"startToken":1657,"endToken":1940,"text":"Point-to-Point Transmission Service or a new form of transmission \nservice;  \n \nAES Ohio generally agrees with the Indicated TOs response. \n \n \n \nvii. \nWhat operational or commercial factors of a co-location \narrangement would result in a co-located load not needing to take \nany form of transmission service, including what types of special \nprotection schemes or backup arrangements may be necessary to \nensure the co-located load never takes any form of transmission \nservice? \n \nAES Ohio generally agrees with the Indicated TOs response.  So long as a co-located \nload is interconnected to the transmission system, it will be required to take some form of \ntransmission service. However, different configurations may result in different forms of \nservice.  As noted in responses above, AES Ohio is open to working with stakeholders to \ndetermine whether a form of service other than full Network Integration Transmission \nService or Firm Point to Point Service could be appropriate for certain configurations.   \n   \n \nc. Ancillary or other wholesale services \ni. \nPlease explain whether and to what extent different configurations \nof co-location arrangements rely on or benefit from ancillary \nservices or black start services and, if so, provide specific details \nabout the type of service and how the co-location arrangement \nrelies on it.  To what extent are these benefits distinct from the \nbenefits that other Network Integration Transmission Service and \nPoint-to-Point Transmission Service customers derive from \nancillary services? \n  \nAES Ohio generally agrees with the Indicated TOs response.  Co-located load connected \nto the PJM Transmission System may use the same ancillary services as all other load \nconnected to the system. However, AES Ohio is open to working with stakeholders to \ndetermine what might constitute an acceptable showing that a particular configuration \nreceives, or does not receive, co-location benefits."},{"page":8,"startToken":1940,"endToken":2200,"text":"ii. \nPlease explain whether and to what extent co-location \narrangements impose costs related to ancillary services or black \nstart services or increase the costs for such services allocated to \nother parties and how those costs could be approximated; \n \nAES Ohio generally agrees with the Indicated TOs response. \n \n \niii. \nPlease explain whether and to what extent co-location \narrangements use, benefit from, provide, or contribute to the need \nfor transmission system services in a manner that does not fit into a \npre-existing category of ancillary services or black start services, \nand, if so, should new categories of services be created to \naccommodate that use?  Alternatively, please explain whether an \nalternative mechanism of cost allocation for pre-existing ancillary \nservices would be more appropriate; \n \nSo long as it is connected to the transmission system (i.e. not physically islanded), co-\nlocated load uses and benefits both from the transmission system and from services \nprovided and delivered by that system just like any other load on the system.  However, \nco-located load could also provide benefits to the transmission system. Approaches other \nthan the existing tariff may be just and reasonable and not unduly discriminatory to the \nextent that they incentivize co-located load that provides reliability benefits and cost \nsavings.  See response to a.ii.  \n \niv. \nWhat changes to rates, terms, and conditions of ancillary services, \nincluding ancillary services procured in PJM’s markets, are \nnecessary for different configurations of co-location arrangements \nto ensure that the Tariff is consistent with cost causation principles \nand the beneficiary pays principle? \n \nAES Ohio generally agrees with the Indicated TOs response."},{"page":9,"startToken":2200,"endToken":2482,"text":"v. \nPlease explain how PJM should determine which co-located load \nconfigurations take ancillary services or black start services (i.e., \nwhether generalized policies or tests, such as a multi-factor test, to \nbe applied case-by-case may be appropriate), as well as the amount \nof such service (i.e., how the service taken by co-located load \ncompares to service taken by other types of load); \n \nAll co-located load that is directly physically connected to the system takes ancillary and \nblack start services.  If co-located load continues to take NITS or PTP Service, the \nexisting rules under the PJM Tariff will apply \n \nd. Interconnection Procedures and Cost Allocation \ni. \nDoes the necessary study process adequately address potential \nimpacts caused by a co-location arrangement or is an additional \nstudy or new study process warranted, e.g., a system impact study \nor generator deactivation study?  PJM should provide the details \nregarding the geographic scope of the existing necessary study \nprocess, what is studied, and how the results are reported, \nincluding what opportunities stakeholders, the interconnected \ntransmission owner, or the PJM IMM have to review the results, if \nany; \n \nAES Ohio generally agrees with the Indicated TOs response. \n \nii. \nPlease explain whether PJM’s necessary study process allows a co-\nlocation arrangement to demonstrate its capability to flexibly \nadjust its withdrawals from or injections to the transmission system \n(e.g., by using secondary backup generation or by curtailing on-site \nload), and reflect this capability in the operating assumptions PJM \nconsiders when estimating the co-location arrangement’s impacts \non the transmission system?  If not, would it be appropriate to \nestablish a new or revised study process that allows for such a \ndemonstration? \n \nAES Ohio generally agrees with the Indicated TOs response."},{"page":10,"startToken":2482,"endToken":2743,"text":"iii. \nWhat changes to interconnection procedures and agreements may \nbe necessary to ensure that PJM identifies the reliability impact to \nthe transmission system of load co-locating with existing \ngeneration including the need for dynamic response models?  \n \nAES Ohio generally agrees with the Indicated TOs response. \n \n   \n \niv. \nTo what extent does a co-location arrangement raise potentially \ndistinct cost-allocation issues relative to a deactivating generator \nthat causes the need for transmission upgrades?  What principles \nshould the Commission apply to allocate the costs of any \ntransmission upgrades needed to mitigate the impacts of co-\nlocating load?  What steps should PJM take to ensure these costs \nare transparent to all parties? \n \nSection V of the PJM Tariff addresses how PJM studies the reliability impacts associated \nwith potential generator deactivations.  AES Ohio’s understanding is that, pursuant to the \nPJM Tariff, if the generator changes its ISA to enable it to operate in a co-located load \narrangement, then any system upgrades must be paid for by the existing removed \ngenerator in order to avoid cost subsidization by existing transmission customers.  This is \ndifferent than if a generator actually retires and shuts down, as any necessary system \nreinforcements resulting from shut down are paid by transmission customers.  \n \n \nv. \nAre changes needed to how PJM allocates the costs of any \ntransmission upgrades needed to mitigate the transmission system \nimpacts of co-locating load, if any, including whether the costs of \nthose upgrades can ever be allocated to a party other than the co-\nlocated generator, co-located load, and/or co-location \narrangement? \n \nAES Ohio generally agrees with the Indicated TOs response."},{"page":11,"startToken":2743,"endToken":3002,"text":"vi. \nAre changes to the pro forma interconnection-related agreements \nnecessary to accommodate the addition of co-located load to \nexisting generation? \n \nAES Ohio generally agrees with the Indicated TOs response. \n \nvii. \nPlease explain whether changes to interconnection procedures and \nagreements are necessary to accommodate new generation \ninterconnecting with co-located load, including whether the \nexisting queue process is sufficient for such arrangements?  \n \nAES Ohio generally agrees with the Indicated TOs response. \n   \nviii. \nPlease explain whether or not it would be appropriate to establish \nan interconnection study process outside of PJM’s interconnection \nqueue process for newly interconnecting co-location arrangements \nthat do not exchange power with the transmission system and do \nnot require network upgrades? \n \nAES Ohio generally agrees with the Indicated TOs response. \n \nix. \nA generator with a co-located load that is not a party to a \ntransmission service agreement is arguably distinguishable from \nother generators.  To the extent co-located arrangements create \ncosts, or benefit from bulk power system services, but the \ngenerator and load are not exposed to these costs because of their \ncontractual relationship, should PJM modify the Tariff and related \nagreements to allocate those costs to the generator directly?  \n \nAES Ohio does not believe that there is any need to modify the PJM Tariff to change the \nincidence of transmission service and facilities costs from load to generation. \n \n \ne. PJM Capacity Market, Reliability, and Resource Adequacy \ni. \nWhat changes to PJM’s capacity market rules are necessary to \nensure that the Tariff specifies how co-located generation and/or \nload participates in the capacity market in a way that reflects the"},{"page":12,"startToken":3002,"endToken":3246,"text":"potentially unique physical and operational characteristics of the \nco-location arrangement (e.g., the presence of secondary backup \ngeneration, the capability to curtail on-site load or other \noperational flexibilities, among others) and is otherwise just, \nreasonable, and not unduly discriminatory or preferential? \n \nAES Ohio generally agrees with the Indicated TOs response. \n \nii. \nWhat Tariff change or changes to the interconnection service \nagreement are necessary to ensure that PJM and the interconnected \ntransmission owner have sufficient visibility into the co-located \nload configuration?  \n \nAES Ohio generally agrees with the Indicated TOs response. \n \niii. \nPlease explain whether the existing Tariff rules are sufficient to \nensure resource adequacy if increasing numbers of large existing \ngenerators choose to co-locate with load; \n \nAES Ohio generally agrees with the Indicated TOs response. \n \niv. \nWhat deactivation or interconnection modification studies should \nPJM undertake to ensure resource adequacy and/or protect \nreliability should an existing generator seek to enter into a co-\nlocation arrangement?  If PJM finds that the co-location would \ncause reliability standards violations, what remediation techniques \nwould be appropriate (e.g., reliability must-run contracts, delaying \nthe co-location arrangement until the reliability violations are \naddressed, etc.)?  \n \nAES Ohio generally agrees with the Indicated TOs response. \n \nv. \nWhat changes are necessary, if any, to other PJM planning \nprocesses to better plan for and address the resource adequacy and \nreliability impacts of co-location arrangements, including, for \nexample, whether or not the frequency of such processes might be \nchanged?  Similarly, should PJM consider changes to load"},{"page":13,"startToken":3246,"endToken":3486,"text":"forecasting methods, informational postings, or the reserve margin \nstudy process to better plan for and address the resource adequacy \nand reliability impacts of co-location arrangements?   \n \n \nAES Ohio generally agrees with the Indicated TOs response.  However, to the extent, \nnew rules are developed through the PJM stakeholder process associated with co-located \nload arrangements, such modifications should be taken into account in the PJM planning \nprocess.  AES Ohio also believes that should consider whether forecast frequency  and \nload addition certainty are adequate considering the pace of large load additions. \n \n \nvi. \nUnder what circumstances can PJM direct the operators of co-\nlocation arrangements to shed such load if deemed necessary to \npreserve system reliability during a declared emergency? \n \nAES Ohio generally agrees with the Indicated TOs response.  However, to the extent, \nnew rules are developed through the PJM stakeholder process associated with co-located \nload arrangements, such modifications should be taken into account in the relevant \nNERC and PJM standards.   PJM should also be required to advise stakeholders whether \nthey reasonably expect to serve all load including co-located loads reliability particularly \nin periods of rapid load growth.   \n \n \n \nf. Other  \ni. \nAre any changes to PJM’s energy or ancillary services market rules \nnecessary to address co-location arrangements? \n \nSee responses above.  \n \nii. \nPlease discuss whether back-up service can provide benefits to \ncustomers or otherwise help minimize system costs, including with \nspecific examples or best practices, if possible; \n \nAES Ohio generally agrees with the Indicated TOs response."},{"page":14,"startToken":3486,"endToken":3731,"text":"iii. \nParties may also choose to address how co-location arrangements \nmay provide benefits, including potentially reducing required \ntransmission upgrades to interconnect large loads, reducing \ncongestion, or providing operational flexibility during system \npeaks or emergencies?   \n \nAs noted above, the co-location of load may, in some cases, reduce the need for \nadditional transmission system upgrades, with benefits flowing to existing transmission \ncustomers who would otherwise pay for such upgrades.   \n \niv. \nParties may also address whether, and if so, how, the Tariff should \nbe modified to best accommodate or encourage co-location \narrangements to be constructed in such a way as to minimize total \nsystem costs or otherwise provide certain benefits, including \nprotections for existing customers and allocation of costs \nconsistent with the cost-causation principle; \n \nSee responses above. \n   \nv. \nWhat Tariff provisions, if any, are necessary to ensure clarity \nregarding the aspects of service to co-located load and generation \nfacilities that may be administered through the Tariff versus state \njurisdictional retail tariffs? \n \nNo changes are necessary. \n \nvi. \nWe also encourage parties to address any national security \nimplications associated with co-location arrangements, including \nwith respect to the specific issues discussed in this show cause \norder, and what actions, if any, the Commission should take in \nresponse. \n \nAES Ohio believes that certainty is critical in order to foster the national security goals of \nthe United States and the Commission associated with the development of AI.  As noted \nabove, once that certainty is established, AES Ohio is open to working through the"},{"page":15,"startToken":3731,"endToken":3825,"text":"stakeholder process to encourage and incentivize co-location arrangements that benefit \nthe grid and provide more reliable service. \n \nvii. \nFinally, for generation units paid for originally by consumers in \nbase rates prior to restructuring, is it fair and/or just and reasonable \nif these units are taken out of the system’s supply stack and \ndevoted exclusively to serving co-location arrangements with one \nor a few large customers?   \n \nIn general, the continued obligation, if any, of generation to serve classes of end-use \ncustomers to pay for that generation is a matter of state jurisdiction and concern."},{"page":16,"startToken":3825,"endToken":3864,"text":"CERTIFICATE OF SERVICE \nI hereby certify that on March 24, 2025, I have served the forgoing document upon each \nperson designated in the official list compiled by the Secretary in this proceeding. \n \n \n \n \n \n \n \n \n \n/s/ William M Rappolt \n \n \n \n \n \n \n \n \nWilliam M. Rappolt"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":0,"startToken":0,"endToken":412},{"p":3,"at":0,"title":"Attachment A","method":"printed heading","endPage":16,"endAt":0,"startToken":412,"endToken":3825},{"p":16,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":16,"endAt":273,"startToken":3825,"endToken":3864}]}