{"document":{"slug":"rec-20250324-5261","title":"Answer of Allegheny Electric Cooperative, Inc. to the Show Cause Order Issued in Connection with the Treatment of Co-Located Load within PJM…","issued":"2025-03-24","accession":"20250324-5261","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Allegheny Electric Cooperative, Inc.","kind":"answer","file":"sources/filings/text/20250324-5261_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250324-5261","tier":"record","sha256":"c2516e9e4d01bc42893a363536a6e08c728f6681297d217d436a90d720aa6862","pages":10,"tokens":2584,"emptyPages":[],"textThemes":["colo"]},"pages":[{"page":1,"startToken":0,"endToken":206,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nPJM Interconnection, L.L.C., et al. \n \n) \n) \nDocket No. EL25-49-000 \n \nLarge Loads Co-Located at Generating \nFacilities \n \n) \n) \n) \nDocket No. AD24-11-000 \nConstellation Energy Generation, LLC \n \nv. \n \nPJM Interconnection, L.L.C. \n) \n) \n) \n) \n) \n) \nDocket No. EL25-20-000 \n(consolidated) \n \nANSWER OF  \nALLEGHENY ELECTRIC COOPERATIVE, INC. \nTO SHOW CAUSE ORDER  \nISSUED IN CONNECTION WITH THE TREATMENT OF  \nCO-LOCATED LOAD WITHIN PJM INTERCONNECTION, L.L.C.  \n \n \nAllegheny Electric Cooperative, Inc. (“Allegheny”) respectfully tenders for filing to the \nFederal Energy Regulatory Commission (“FERC” or “Commission”) this Answer in the above-\ncaptioned proceeding concerning the treatment of large loads located at the same site as \ngenerating facilities (“Co-Located Load”) within the PJM Interconnection, L.L.C. (“PJM”) \nfootprint.  Allegheny submits this Answer pursuant to Rule 213 of the FERC Rules of Practice \nand Procedure1 and the Commission’s February 20, 2025 Order Instituting Proceeding Under \nSection 206 of the Federal Power Act and Consolidating with Other Proceedings (“Show Cause \nOrder”).2  The Show Cause Order directs PJM as well as each of the PJM Transmission Owners \n(“TOs”) to address the treatment of Co-Located Load by PJM’s Open Access Transmission \n \n1   18 C.F.R. § 385.213. \n2   PJM Interconnection, L.L.C., 190 FERC ¶ 61,195 (2025)."},{"page":2,"startToken":206,"endToken":525,"text":"2 \n \nTariff, the Amended and Restated Operating Agreement of PJM, and the Reliability Assurance \nAgreement Among Load Serving Entities in the PJM Region (collectively, “PJM Tariff”).  \nSpecifically, the Show Cause Order directs PJM and the TOs to either (1) show cause that the \nPJM Tariff remains just and reasonable and not unduly discriminatory or preferential without \nrates, terms, and conditions of service specific to Co-Located Load or (2) explain what changes \nto the Tariff would be necessary to address Co-Located Load.  In the Answer below, Allegheny \nacknowledges both the growth of interest in Co-Located Load and the importance of clarity in \ntransmission rate and policies as to the treatment of Co-Located Load within the PJM Tariff.  \nThe Show Cause Order is the culmination of a number of contentious proceedings before \nthe Commission addressing issues related to Co-Located Load.  In these proceedings, market \nparticipants have espoused a number of views as to (1) whether specific configurations of Co-\nLocated Load may sufficiently sever itself from the transmission grid such that it receives no \nbenefits from the grid, (2) whether Co-Located Load should be assessed transmission charges, \n(3) what rates, terms, and conditions of transmission service would encourage or discourage Co-\nLocated Load, and (4) whether the PJM Tariff should be revised to accommodate Co-Located \nLoad.  Allegheny itself has taken no position on these questions, and it remains uncommitted as \nto whether the current PJM Tariff sufficiently addresses Co-Located Load and the more \nfundamental question of whether Co-Located Load should be allocated transmission costs.  \nUltimately, by the conclusion of this proceeding, the Commission will have a substantial record \non which to determine whether to direct revisions to the PJM Tariff to accommodate Co-Located \nLoad.  With the voluminous record in the consolidated proceedings and the burgeoning number \nof proceedings related to the issue of Co-Located Load, Allegheny is certain that the need for \nclarity from the Commission is both essential and urgent."},{"page":3,"startToken":525,"endToken":762,"text":"3 \n \n \nI.  \nPRELIMINARY STATEMENT \n \nThis Answer is submitted pursuant to Rule 213 of the Rules of Practice and Procedure of \nthe Commission and the Commission’s February 20, 2025 Show Cause Order, which established \nMarch 24, 2025 as the date by which PJM and the TOs are required to submit answers in this \nSection 206 proceeding. \nII. \nDESCRIPTION OF ALLEGHENY \nAllegheny is a non-profit electric generation and transmission cooperative corporation \n(“G&T Cooperative”), incorporated under the Electric Cooperative Law of the Commonwealth \nof Pennsylvania, and it is the exclusive wholesale supplier of its 14 distribution cooperative \nmembers.  Similar to other G&T Cooperatives, Allegheny is owned entirely by its members.  Its \nBoard of Directors, which governs Allegheny, is comprised exclusively of representatives of \neach of its members.  Thirteen of Allegheny’s members are located in Pennsylvania, and one is \nlocated in New Jersey.  Allegheny provides service to its members, which in turn serve over \n600,000 rural consumer-members in Pennsylvania and New Jersey.   \nAllegheny is a PJM TO with transmission facilities included in the PPL Zone, the zone \nwhich also includes PPL’s transmission facilities.  Allegheny serves load in five PJM zones:  the \nPPL Zone, the Allegheny Power Zone, the Penelec Zone, the Met-Ed Zone, and the JCP&L \nZone.  Allegheny is a ten-percent co-owner and Nuclear Regulatory Commission co-licensee of \nthe Susquehanna Steam Electric Station, an approximately 2,600 megawatt, two-unit nuclear \npower plant located in Luzerne County, Pennsylvania."},{"page":4,"startToken":762,"endToken":1028,"text":"4 \n \nIII. \nBACKGROUND \nThe Commission has addressed issues related to Co-Located Load within PJM in a \nnumber of recent proceedings. \nIn Docket No. ER24-2172, the Commission considered amendments to a non-conforming \nInterconnection Service Agreement (“ISA”) among PJM, Susquehanna Nuclear, LLC and PPL \nElectric Utilities Corporation that would have increased the amount of Co-Located Load at the \nSusquehanna Steam Electric Station from 300 MW to 480 MW.  The proceeding attracted over \n60 intervenors and drew comments from industry participants throughout the nation, weighing in \non the questions raised in the opening paragraphs of this Answer.  On November 1, 2024, the \nCommission rejected the proposed amendments to the ISA, finding that PJM had failed to meet \nthe burden of demonstrating that the non-conforming provisions of the ISA were necessary.3  In \nparticular, the Commission stated that the proceeding raised questions as to whether PJM would \noffer the same terms and conditions of service to similarly situated Co-Located Load \ninterconnection customers.4   \nIn Docket Nos. ER24-2888 et al., on August 28, 2024, several subsidiaries of Exelon \nCompany submitted for Commission approval proposed revisions to their respective \ntransmission rate schedules contained in Attachment H of the PJM Open Access Transmission \nTariff to address Co-Located Load.  Specifically, the Exelon Company subsidiaries proposed to \nrevise their transmission rate schedules to clarify that Co-Located Load must be designated as \neither Network Load or receive Point-to-Point Transmission Service and thus be allocated costs \nof the transmission grid.  On February 20, 2025, the Commission issued an order rejecting the \n \n3  \nPJM Interconnection, L.L.C., 189 FERC ¶ 61,078, at P 87 (2024). \n4  \nId."},{"page":5,"startToken":1028,"endToken":1332,"text":"5 \n \nExelon Company subsidiaries’ proposal as outside the scope of rights afforded to PJM TOs by \nthe PJM Tariff.5      \nIn Docket No. AD24-11, the Commission convened a technical conference on November \n1, 2024 to examine technical, legal, and policy issues in connection with Co-Located Loads.  It \nsubsequently issued a notice requesting post-technical conference comments.   \nIn Docket No. EL25-20, Constellation Energy Generation, LLC (“Constellation”) filed a \ncomplaint with the Commission on November 22, 2024, arguing that the PJM Tariff is unjust \nand unreasonable for failing to contain rules for interconnection customers to follow when \nseeking a Co-Located Load configuration that is fully isolated from the transmission grid.   \nIn Docket No. EL25-49, the Commission issued the February 20, 2025 Show Cause \nOrder to which Allegheny now responds.  In initiating this Federal Power Act Section 206 \nproceeding, the Commission also consolidated this investigation with the Constellation \ncomplaint proceeding in Docket No. EL25-20 and the inquiry it launched in Docket No. AD24-\n11 to examine the technical, legal, and policy implications presented by Co-Located Load.  \nIV. \nANSWER \nElectricity and capacity markets are in a state of flux as the nation experiences  \nunprecedented load growth forecasts for the first time in decades.  This load growth is driven by \nincreased electrification including the embrace of electric vehicles,6 considerable manufacturing \ninvestments spurred by federal legislation,7 and perhaps most prominently the advancement of \n \n5  \nAtlantic City Elec. Co., 190 FERC ¶ 61,109 (2025). \n6  \nErik Delarue & KU Leuven, Load Electrification Impact, ENERGY SYSTEMS INTEGRATION GROUP (Nov. 25, \n2024), www.esig.energy/load-electification-impact (last visited Mar. 18, 2025). \n7  \nBrad Plumer & Nadja Popovich, A New Surge in Power Use is Threatening U.S. Climate Goals, N.Y. TIMES \n(Mar. 14, 2024), available at https://www.nytimes.com/interactive/2024/03/13/climate/electric-power-climate-\nchange.html (last visited Mar. 18, 2025)."},{"page":6,"startToken":1332,"endToken":1625,"text":"6 \n \nartificial intelligence (“AI”) and data center development.8  Increasingly, large load is looking to \nsecure a dedicated source of generation as a means of ensuring both reliability and affordability.  \nAccordingly, Co-Located Load configurations are attractive options to many new large loads.   \nAs demonstrated both by the litany of FERC proceedings identified above and the \nsubstantial number of intervenors in those FERC proceedings, the issue of the appropriate \ntreatment of Co-Located Load has perplexed industry.  Yet, foundational, but ultimately \ntechnical, questions remain unanswered:  Does Co-Located Load sited with generation that is \ninterconnected to the transmission grid benefit from the generator’s interconnection to the \ntransmission grid?  What, if any, transmission services does Co-Located Load receive from the \ntransmission grid under the various configuration models?  Can Co-Located Load ever \nsufficiently sever itself from the transmission grid so as not benefit from the transmission grid?    \nSophisticated technical experts and market participants have weighed the evidence in the FERC \nproceedings identified above and have reached entirely conflicting answers to these questions.   \nIn this proceeding, the Commission must layer legal and policy considerations atop the \ntechnical questions identified above.  Thus, it is important to recognize that the Commission is \npresented with these technical questions regarding the interconnection of new large loads at the \nsame time that the industry is grappling with a dearth of capacity and, more broadly, ever-\nincreasing transmission costs.  The loss of large baseload generation is having real-world impacts \nfor load-serving entities.  As one example, in PJM, the 2025/2026 Base Residual Auction \n(“BRA”) produced a capacity auction clearing price nearly ten times that of the 2024/2025 \n \n8  \nDEPARTMENT OF ENERGY, 2024 UNITED STATES DATA CENTER ENERGY USAGE REPORT (Dec. 2024), available \nat https://www.energy.gov/articles/doe-releases-new-report-evaluating-increase-electricity-demand-data-centers \n(last visited Mar. 18, 2025)."},{"page":7,"startToken":1625,"endToken":1999,"text":"7 \n \nBRA.9  One of many converging factors that produced an increase of this magnitude is the fact \nthat supply offered into the capacity market declined by nearly 9% from the 2024/2025 BRA to \nthe 2025/2026 BRA.10  Escalating capacity prices is one symptom of a lack of sufficient \ngeneration resources to meet needs, but a far more significant concern is the ability to meet \nexisting service obligations.  This concern was highlighted by the December 9, 2024 warning \nissued by PJM Board Chair Mark Takahashi that a capacity shortage may affect the PJM system \nas early as the 2026/2027 Delivery Year.11  Additionally, the lack of generation capacity has a \ndirect impact on transmission prices as well because, as baseload generation resources retire, grid \noperators must approve additional and more costly transmission projects to serve existing load.  \nFor example, in February 2025, PJM approved a new Regional Transmission Expansion Plan \n(“RTEP”) that included costly transmission projects necessitated by generation retirements, \nincluding one project whose costs more than doubled from the prior RTEP.12   \nBecause certain Co-Located Load configurations may eliminate an existing resource from \nthe capacity market and potentially exempt Co-Located Load from transmission charges, a legal \nand policy question that the Commission must address in this proceeding is whether Co-Located \n \n9  \nPJM INTERCONNECTION, L.L.C., 2025/2026 BASE RESIDUAL AUCTION REPORT at 5 (July 30, 2024) \n(documenting the increase in the clearing price from $28.92 in the 2024/2025 Base Residual Auction to $269.92 \nin the 2025/2026 Base Residual Auction).    \n10  Id. at 3.   \n11  Letter from Mark Takahashi, Chair, Board of Managers, PJM Interconnection, L.L.C., to Stakeholders (Dec. 9, \n2024), available at https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-\ndisclosures/2024/20241209-board-letter-outlining-action-on-capacity-market-adjustments-rri-and-sis.pdf (last \nchecked Mar. 19, 2025). \n12  Ethan Howland, PJM Board Approves $6.7B Transmission Expansion Plan, Utility Drive, Feb. 27, 2025, \navailable at https://www.utilitydive.com/news/pjm-rtep-transmission-expansion-plan-aep-dominion-\nfirstenergy/741097 (last checked Mar. 20, 2025); PJM Interconnection, L.L.C., Transmission Expansion \nAdvisory Committee (TEAC) Recommendations to the PJM Board at 4-5 (Feb. 2005) (identifying the costs of \nthe transmission projects designed to ameliorate reliability issues associated with the retirement of the Brandon \nShores coal-fired power project)."},{"page":8,"startToken":1999,"endToken":2300,"text":"8 \n \nLoad configurations will exacerbate current strains on the transmission system, potentially \nimpairing reliability and increasing capacity and transmission costs to ratepayers.  Allegheny \ndoes not oppose Co-Located Load configurations but insists that the interconnection and \ntreatment of Co-Located Load be accomplished in a manner that is fair to existing load and \nadheres rigidly to the Commission’s long-standing cost causation principle.  In short, if Co-\nLocated Load benefits from the transmission system, it must be allocated the costs of those \nbenefits to ensure that all users of the transmission system pay their fair share of the costs of \nmaintaining and expanding the transmission system.    \nUltimately, resolutions of the technical questions identified above will assist the \nCommission in answering the legal and policy questions presented by Co-Located Load.  With \nthe record to be produced in response to the Show Cause Order, combined with the record in the \nConstellation complaint proceeding and in the FERC-convened technical conference, the \nCommission will be well-positioned to respond to an industry that is clamoring for certainty.  \nThough a party to many of the proceedings identified above, Allegheny has taken no position on \nthe foundational technical questions at issue in this proceeding related to whether Co-Located \nLoad benefits from the transmission grid.  The Commission should make its determinations in \nthis proceeding based on the record evidence as to technical, legal, and policy implications of \ninterconnecting Co-Located Load.  Because Allegheny has no direct experience with \ninterconnecting Co-Located Load, it respectfully defers to the findings of the Commission on \nthese important questions but asks that the Commission act with expediency for the benefit of \nowners and users of the PJM transmission system, ensuring adherence to the Commission’s long-\nstanding cost causation principle and keeping in mind that load-serving entities rely on the PJM \ntransmission system to provide reliable and affordable service."},{"page":9,"startToken":2300,"endToken":2498,"text":"9 \n \nV. \nRESERVATION OF RIGHTS \nAllegheny reserves the right to posit and address any issues that it or others may identify \nor raise herein that are developed in any other phase of this proceeding. \nVI.  \nCONCLUSION \nThe present proceeding presents the Commission with many legal and policy \nquestions that should be answered by a robust review of the technical aspects of Co-\nLocated Load.  Answering these questions is necessary to provide clarity to ensure that \nthe United States retains technology-driven large load, including those related to data \ncenters and AI, that is capable of locating elsewhere but is important for national security.  \nMost importantly, resolving these outstanding questions will provide clarity to load-\nserving entities as to how they will meet their existing load obligations reliably and \naffordably at a time of diminishing generation resources.  Allegheny supports the \nCommission’s efforts to provide certainty on an expedited basis to the questions posed by the \ngrowth of Co-Located Load configurations in the PJM region.   \n \nDated:  March 24, 2025 \n \n \nRespectfully submitted, \n  /s/ Joshua E. Adrian  \n \n \n \n \n \n \nJoshua E. Adrian \n \n \n \n \n \n \nThompson Coburn, LLP \n \n \n \n \n \n \n1909 K Street, NW  Suite 600 \n \n \n \n \n \n \nWashington, DC  20006 \n \n \n \n \n \n \n(202) 585-6922 \n \n \n \n \n \n \njadrian@thompsoncoburn.com \n \n \n \n \n \n \n \nCounsel for  \n \n \n \n \n \n \nAllegheny Electric Cooperative, Inc."},{"page":10,"startToken":2498,"endToken":2584,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have on this 24th day of March, 2025, caused a copy of the \nforegoing document to be sent by electronic mail or United States mail to all parties on the list \ncompiled by the Secretary of the Commission in this proceeding. \n \n \n     /s/  Joshua E. Adrian \n \n \nJoshua E. Adrian \n \n \n \n \n \n \n \nCounsel for  \n \nAllegheny Electric Cooperative, Inc. \nLaw Offices of: \n \n \nThompson Coburn LLP \n \n1909 K Street, N.W. \n \nSuite 600 \n \nWashington, D.C.  20006-1167 \n \n202.585.6900 \n \n202.585.6969 (facsimile)"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":7,"startToken":0,"endToken":526},{"p":3,"at":7,"title":"I. PRELIMINARY STATEMENT","method":"printed heading","endPage":3,"endAt":334,"startToken":526,"endToken":580},{"p":3,"at":334,"title":"II. DESCRIPTION OF ALLEGHENY","method":"printed heading","endPage":4,"endAt":5,"startToken":580,"endToken":763},{"p":4,"at":5,"title":"III. BACKGROUND","method":"printed heading","endPage":5,"endAt":1184,"startToken":763,"endToken":1200},{"p":5,"at":1184,"title":"IV. ANSWER","method":"printed heading","endPage":9,"endAt":5,"startToken":1200,"endToken":2301},{"p":9,"at":5,"title":"V. RESERVATION OF RIGHTS","method":"printed heading","endPage":9,"endAt":200,"startToken":2301,"endToken":2334},{"p":9,"at":200,"title":"VI. CONCLUSION","method":"printed heading","endPage":10,"endAt":0,"startToken":2334,"endToken":2498},{"p":10,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":10,"endAt":546,"startToken":2498,"endToken":2584}]}