{"document":{"slug":"rec-20250324-5298","title":"Answer of the Indicated PJM Transmission Owners to the Order Instituting the Proceeding Under Section 206 of the Federal Power Act and Consolidating with…","issued":"2025-03-24","accession":"20250324-5298","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Exelon CorporationAmerican Electric Power CorporationAMP Transmission, LLC ,City of Cleveland, Department of Public Utilities, Division ,City of Hamilton, OH ,Dominion Energy Services, Inc. ,Duke Energy Corporation ,Duquesne Light Energy, LLC ,The FirstEnergy Transmission Companies ,East Kentucky Power Cooperative, Inc. ,Old Dominion Electric Cooperative ,PPL Electric Utilities Corporation ,Rockland Electric Company ,southern maryland electric cooperative ,Wabash Valley Power Association, Inc. ,UGI Utilities Inc. ,","kind":"answer","file":"sources/filings/text/20250324-5298_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250324-5298","tier":"record","sha256":"9afc8dfeed3325c8ce7b906e5cb378b5b71a706e6cd70ab6bea23214c75a5e9c","pages":47,"tokens":17206,"emptyPages":[],"textThemes":["colo","study","retail","adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":347,"text":"1 \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C., et al. \n) \nDocket No. EL25-49-000 \nLarge Loads Co-Located at Generating \nFacilities \n) \nDocket No. AD24-11-000 \nConstellation Energy Generation, LLC \nv. \nPJM Interconnection, L.L.C. \n) \nDocket No. EL25-20-000 \n(consolidated) \nANSWER OF THE INDICATED PJM TRANSMISSION OWNERS \nTO THE ORDER INSTITUTING THE PROCEEDING  \nUNDER SECTION 206 OF THE FEDERAL POWER ACT  \nAND CONSOLIDATING WITH OTHER PROCEEDINGS \nPursuant to Rules 206 and 213 of the Rules of Practice and Procedure of the Federal \nEnergy Regulatory Commission (“FERC” or “Commission”),1 the Indicated PJM Transmission \nOwners, comprised of the majority of the named respondents and inclusive of investor-owned \nutilities, municipalities, and cooperatives (hereinafter, “Indicated TOs”)2 submit this unified \n1 18 C.F.R. §§ 385.206, 385.213. \n2 The Indicated PJM Transmission Owners include: American Electric Power Service Corporation, on behalf of \nAppalachian Power Company, Indiana Michigan Power Company, Kentucky Power Company, Kingsport Power \nCompany, Ohio Power Company, Wheeling Power Company, AEP Appalachian Transmission Company, Inc., AEP \nIndiana Michigan Transmission Company, Inc., AEP Kentucky Transmission Company, Inc., AEP Ohio \nTransmission Company, Inc., and AEP West Virginia Transmission Company, Inc.; AMP Transmission, LLC; City \nof Cleveland, Department of Public Utilities, Division of Cleveland Public Power; City of Hamilton, OH; Dominion \nEnergy Services, Inc. on behalf of Virginia Electric and Power Company d/b/a Dominion Energy Virginia; Duke \nEnergy Corporation on behalf of its affiliates Duke Energy Ohio, Inc., Duke Energy Kentucky, Inc., and Duke \nEnergy Business Services LLC; Duquesne Light Company; East Kentucky Power Cooperative; Exelon Corporation, \non behalf of Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison \nCompany, Commonwealth Edison Company of Indiana, Inc., Delmarva Power & Light Company, PECO Energy \nCompany, and Potomac Electric Power Company; FirstEnergy Service Company, as agent for its affiliates \nAmerican Transmission Systems, Incorporated, Jersey Central Power & Light Company, Mid-Atlantic Interstate \nTransmission LLC, Keystone Appalachian Transmission Company, The Potomac Edison Company, Monongahela \nPower Company and Trans-Allegheny Interstate Line Company (collectively, the “FirstEnergy Transmission \nCompanies”); Old Dominion Electric Cooperative; PPL Electric Utilities Corporation; Rockland Electric Company; \n(cont'd)"},{"page":2,"startToken":347,"endToken":626,"text":"2 \n \nAnswer to the Commission’s Order Instituting Proceeding Under Section 206 of the Federal \nPower Act3 and Consolidating with Other Proceedings, issued on February 20, 2025.4  The \nIndicated TOs support co-location and appreciate the Commission’s leadership in addressing this \nissue.  It is vital to our national economy and energy security to ensure that the rules of the road \nare clear with respect to the interconnection, service, and cost allocation for co-located \narrangements.   \nCo-located load can and does fit within the current constructs for providing transmission \nservice under the Commission’s pro forma open access transmission tariff (“OATT”) and PJM \nInterconnection, L.L.C.’s (“PJM”) Open Access Transmission Tariff (“PJM Tariff”).  The \nexisting PJM Tariff provisions are just and reasonable.  The Indicated TOs appreciate that further \nclarification of how those existing provisions apply to co-located load arrangements could be \nbeneficial for all parties involved in those arrangements and the industry as a whole.  Thus, the \nIndicated TOs support the Commission ruling, as part of its review in this proceeding, that the \nexisting PJM Tariff and its existing two forms of transmission service—Network Integration \nTransmission Service (“Network Service”) and Point-to-Point Transmission Service (“Point-to-\nPoint Service”)5—encompass and apply to these arrangements.  \n \nSouthern Maryland Electric Cooperative, Inc.; UGI Utilities Inc; and Wabash Valley Power Association, Inc. \n3 16 U.S.C. § 824e. \n4 PJM Interconnection, L.L.C., 190 FERC ¶ 61,195 (2025) (“Show Cause Order”). \n5 All capitalized terms not otherwise defined herein shall have the meaning set forth in the PJM Tariff, Amended \nand Restated Operating Agreement of PJM Interconnection, L.L.C. and/or Reliability Assurance Agreement Among \nLoad Serving Entities in the PJM Region (“RAA”)."},{"page":3,"startToken":626,"endToken":961,"text":"3 \n \nI. \nEXECUTIVE SUMMARY \nThe Indicated TOs agree with the recommendation of PJM that co-located end-use loads \nshould be treated as load in front of the meter and designated as Network Load.6  Co-located load \nshould be treated as load in front of the meter and designated as Network Load because it will \nensure that such loads are appropriately studied, charged, and factored in operationally by PJM \nand transmission owners.  Doing otherwise would undercut reliability and exacerbate \naffordability concerns.  This approach offers the most reliability benefits and a cost allocation \nframework that addresses charges for use of, and reliance on, the transmission system.  \nOtherwise, a customer that co-locates avoids “wires charges”—the fixed costs of the poles, \nwires, transformers, and substations that comprise the transmission and distribution network.  \nThese avoided costs are then subsidized by other customers, allowing co-location customers a \nfree ride.  Beneficiaries of the transmission system must pay their share to avoid inappropriately \nshifting costs to other customers.   \nPJM’s Independent Market Monitor (“IMM”) has correctly submitted that “it is simply \nnot possible to be off the grid if you are interconnected to the grid.”7  The North American \nElectric Reliability Corporation (“NERC”) recognized in its 2024 Long-Term Reliability \nAssessment (“2024 LTRA”) that, in PJM, “[t]he trends in demand growth and resource additions \ncreate resource adequacy and system planning challenges for PJM as it carefully manages \ngenerator deactivation requests from the aging fossil and nuclear fleet.”8  PJM is experiencing \n \n6 See PJM, PJM Guidance on Co-Located Load, at 1 (originally issued Mar. 22, 2024 and updated Apr. 17, 2024), \nhttps://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-info/pjm-guidance-on-co-located-load.ashx \n(“PJM continues to recommend that all co-located load be served from the PJM Transmission System as PJM \nNetwork Load with applicable firm transmission service (e.g., Regional Network Integration Transmission Service \n(NITS) under PJM Tariff, Part III).”) (“PJM Guidance on Co-Located Load”). \n7 IMM Answer at 4, Docket No. EL25-20 (Dec. 20, 2024). \n8 NERC, 2024 LTRA, at 16 (Dec. 2024), \n(cont'd)"},{"page":4,"startToken":961,"endToken":1329,"text":"4 \n \nincreased load growth.9  NERC has also explained that there are reliability challenges that attend \nthis demand growth: \nPJM’s 2023 Load Forecast Report addressed the impact of industry \nchanges that are reshaping system hourly loads.  As a result, the \nlevel and timing of coincident peak and non-coincident peak \ndemands across PJM have begun to shift.  Solar-power penetration, \nexpected impacts of EVs, state electrification programs, home \nbattery storage, and a significant increase in data center loads are \nmarkedly increasing the complexity of PJM’s load forecasting \nprocess.  Driven by discrete and localized load growth, like Data \nCenter Alley in Loudoun County, Virginia, in 2022, PJM and \nstakeholders conducted a review of data center load growth and \nidentified growth rates of over 300% in some instances.  As a result, \nthe 2023 PJM Load Forecast Report incorporates adjustments to \nspecific zones for data center load growth.10 \n \nThe foregoing underscores the importance of ensuring that when there are co-location \narrangements that must rely on the transmission system, and receive system benefits, for any \nperiod of time, the loads should be located and treated just like load in front of the meter and \ndesignated as Network Load so that their demand is transparent and known, so that they can be \ncharged the costs commensurate with the benefits they are receiving, and to ensure PJM and \ntransmission owners are adequately studying the load to ensure effective system planning. \nThe concept of placing end-use load near generation, and vice versa, is not new.  As \nindustry analysts have recognized, new large loads located at generating facilities are seeking \nways to interconnect to the PJM system faster than current process timelines for addressing the \ngeneration and transmission needs of the system.  The Indicated TOs recognize that FERC, PJM, \n \nhttps://www.nerc.com/pa/RAPA/ra/Reliability%20Assessments%20DL/NERC_Long%20Term%20Reliability%20\nAssessment_2024.pdf. \n9 See id. at 92 (“PJM is experiencing large growth in data centers that are in turn driving higher demand forecasts. \nLoudoun County, Virginia, in the PJM assessment area, is home to ‘Data Center Alley,’ the largest concentration of \ndata centers in the world. Electrification in transportation, heating, and industrial sectors is also spurring demand \ngrowth.”). \n10 Id. at 93."},{"page":5,"startToken":1329,"endToken":1676,"text":"5 \n \nand stakeholders are working diligently and are in the process of implementing queue reforms \nand proposals to address bringing needed capacity online to serve the increased demand. \nCo-location can offer a valuable option for hyperscalers to address transmission capacity \nconstraints and to spur economic growth.  The contractual arrangement between a generator and \nco-located load also has the potential to provide generation assets an alternative to retirement.  \nHowever, co-location must be done in a responsible and fair manner to ensure configurations do \nnot threaten the reliability and security of the grid,11 and co-location should not result in other \ncost-shifting that requires customers to pay costs caused by or for the benefit of co-location \ncustomers.  If co-located load is interconnected to the transmission system, it is unequivocally \nusing and benefitting from the transmission system and therefore must pay for its share of \nwholesale transmission service and other essential grid services. \nThis is the case regardless of whether the load contracts for power directly from a \ngenerator connected to the PJM transmission system.  The transmission system must be planned \nand built to support every MW of load on the system, including co-located load.  Co-located load \ndepends on and uses the grid.  As stated above, if the framework for cost allocation for the \ntransmission system does not reflect co-located load’s use of the system, then such co-located \nload will get a free ride, and costs will be shifted to and borne by other customers.  \nConsequently, the Commission should confirm that the existing PJM Tariff provisions regarding \nNetwork Service and Point-to-Point Service are sufficiently inclusive to cover the treatment of \nco-located load.   \n \n11 Should behind-the-meter co-location configurations be permitted even when such configurations depend on the \ntransmission system, there will be reliability and resource adequacy risks that will follow.  As the Commission \nrecognized in its Show Cause Order, “[t]he risk that co-located loads will not be reflected in resource adequacy \nplanning mechanisms with sufficient forward notice is particularly concerning given how long it takes to add new \ngeneration capacity or upgrade transmission facilities.”  Show Cause Order at P 85."},{"page":6,"startToken":1676,"endToken":1973,"text":"6 \n \nThat said, as the Commission has acknowledged, co-located load arrangements are \nbecoming increasingly common in PJM,12 in part due to variations to the Commission’s pro \nforma OATT that are specific to PJM.  Thus, the time is ripe to underscore and clarify the \napplicability of the existing types of PJM transmission service to co-location arrangements to \nprovide certainty to participants in those arrangements and other stakeholders, ensure that the \nCommission’s principles for open access and non-discriminatory transmission service persist, \nand that beneficiaries pay for the services they receive.  \nIn the Show Cause Order, the Commission also instructed PJM and the Indicated TOs to \nfile responses to a list of questions, together with supporting evidence and analysis.13  Thus, \nalong with the fundamental principles and arguments raised herein, the Indicated TOs submit \nanswers to the questions in Attachment A of this filing.14  \nII. \nBACKGROUND \nA. Procedural Overview \nThe Show Cause Order is the culmination of several proceedings addressing the issue of \nco-location, both in specific circumstances and on an industry-wide basis.  The Commission \nconsolidated this new proceeding in Docket No. EL25-49-000 with Docket Nos. AD24-11-000 \n(the co-location technical conference) and EL25-20-000 (the “Complaint”).15  While the co-\nlocation phenomenon is not limited to a single region, the Show Cause Order is specific and \nlimited to PJM.  In its Show Cause Order, the Commission directed the respondents to: \n \n12 Show Cause Order at P 3. \n13 See id. at P 88. \n14 Because the dockets have been consolidated, the answers submitted by Exelon, PPL Electric Utilities, AEP, \nDominion Energy Services, and others, on December 12, 2024, including the testimony appended thereto, and \nJanuary 7, 2025, in response to the Technical Conference and Complaint, are already part of the record here.     \n15 Show Cause Order at P 65."},{"page":7,"startToken":1973,"endToken":2383,"text":"7 \n \n(1) \nshow cause as to why the [Open Access Transmission \nTariff], the Amended and Restated Operating Agreement of PJM, \nand Reliability Assurance Agreement Among Load Serving Entities \nin the PJM Region [(collectively, the “PJM Tariff”)] remains just \nand reasonable and not unduly discriminatory or preferential \nwithout provisions addressing with sufficient clarity or consistency \nthe rates, terms, and conditions of service that apply to co-location \narrangements; or  \n(2) \nexplain what changes to the Tariff would remedy the \nidentified concerns if the Commission were to determine that the \nTariff has in fact become unjust and unreasonable or unduly \ndiscriminatory or preferential and, therefore, proceeds to establish a \nreplacement Tariff.16 \nB. Co-location of Load \nCo-located load is network or point-to-point load that has contractual arrangements to be \nserved by an adjacent generation resource that is physically interconnected to and synchronized \nwith the transmission and/or distribution grid.  Indeed, it must be interconnected to the grid.17  \nCo-located load uses and depends on the grid, causing changing flows on the grid from second to \nsecond.  There is an alternative arrangement where a load and accompanying generation never \nuse the transmission or distribution system—they are islanded—but neither the Show Cause \nOrder nor Commission jurisdiction extend to islanded non-interconnected arrangements.  Load \ncannot be both connected to the transmission and/or distribution grid and “fully isolated,” in the \nmanner certain generation and large load interests have asserted.18 \n \n16 Id. at P 2. \n17 FERC adopts the definition of a co-located load arrangement used in PJM’s Guidance Document for purposes of \nthe Show Cause Order: “A co-located load configuration refers to end-use customer load that is physically \nconnected to the facilities of an existing or planned Customer Facility on the Interconnection Customer’s side of the \nPoint of Interconnection (‘POI’) to the PJM Transmission System (co-located Customer Facility).”  Show Cause \nOrder at P 3 n.4.  This definition obscures the engineering and economic truth that the load relies upon the \nfunctioning grid and grid services whichever side of the meter it is located on.   As explained below, the Indicated \nPJM TOs support that the preferred treatment of the load is in front of the meter to ensure reliability, transparency, \nand appropriate cost allocation.  \n18   See infra note 11.  See, also, e.g., Atlantic City Electric Co., et al., Docket Nos. ER24-2888-000, et al., Motion to \nIntervene and Protest of MachH2 LLC at 3 (Oct. 2, 2024) (“Requiring hydrogen projects that rely on PJM-\n(cont'd)"},{"page":8,"startToken":2383,"endToken":2914,"text":"8 \n \nThroughout the proceedings leading up to this Show Cause Order, several parties argued \nthat co-located load could be “fully isolated” by connecting with their own generation and \ntherefore not relying on the transmission grid.19  Connecting the load near generation with which \nit has a contractual arrangement for the supply of electricity, however, does not isolate that load \nfrom the grid.  It continues to use services provided by the grid and the arrangement continues to \nrely on the grid connection for the generator to operate.  As long as the load remains connected \nto the grid, including through facilities also connecting a generator to the grid, the load would \nstill be able to be served from the transmission system, and therefore, the transmission system \nmust be planned and built to account for the load.  The fact that the load is not constant does not \nreduce the capital investment or operation and maintenance costs that are incurred to ensure that \nthe system is available to the customer.  The same applies to generators connected to the \ndistribution system. \n \nsanctioned co-location arrangements to pay the transmission owner for a transmission system they are not using will \nadd costs to already tight clean hydrogen economics, making it less likely these hubs will blossom, contrary to the \ngoals of the DOE’s clean hydrogen programs.”); Docket Nos. ER24-2888-000, et al., Protest of the PJM Industrial \nCustom Coalition at 9–11 (Oct. 2, 2024) (arguing that Exelon’s gross-load-basis proposal would not charge network \ncustomers based on their “actual use” of the transmission system); Pre-Technical Conference Comments of the \nClean Energy Buyers Association at 21 n.50, Docket No. AD24-11-000 (Oct. 25, 2024) (“As Constellation explains \nin a related docket, load can be fully isolated from the grid such that it ‘does not rely on the grid’s ancillary \nservices . . . .’” (quoting Docket No. ER24-2172, Answer of Constellation Energy Generation at 5–6 (Oct. 9, \n2024))); Soluna Holdings, Inc., Post-Conference Comments at 2, Docket No. AD24-11-000 (Dec. 1, 2024) (“We \nhave also observed instances where generators have successfully completed studies to ensure fully isolated co-\nlocated loads cannot draw power from the grid.”). \n19  See, e.g., Constellation Complaint at 4, Docket No. EL25-20 (Nov. 22, 2024) (“One longstanding option that has \nbeen available to any load since the beginning of open access has been to connect directly to a generator either fully \nindependent of the network grid or with a reduced reliance on the grid.”); Constellation Answer at 5, Docket No. \nEL25-20 (Dec. 24, 2024) (“Since the beginning of open access, load has been able to connect directly to a generator \neither fully independent of the network grid or with a reduced reliance on the grid.”); id. at 20 (“The Commission \nshould also reject Exelon’s factually incorrect claims, repeated from other dockets, that Fully Isolated Co-Located \nLoad is impossible and always relies on the grid . . . .” (footnotes omitted)); id. (suggesting it is a “faulty premise \nthat the Fully Isolated Co-Located Load is taking transmission service”); PJM Interconnection, L.L.C., Docket No. \nER24-2172-001, Answer of Susquehanna Nuclear, LLC at 3 (Oct. 22, 2024) (“[T]he record here demonstrates that \nload can in fact be fully-isolated behind-the-meter and not considered Network Load.”)."},{"page":9,"startToken":2914,"endToken":3209,"text":"9 \n \nIndeed, any characterization of co-located load as “fully isolated” is false and misleading \nunless the load is not connected to either the transmission or distribution system.  If loads were \n“fully isolated” from the grid, then both the generation and the load would be islanded from the \ngrid, and the PJM Tariff would not apply to them at all.  No interconnection under the PJM \nTariff process would be needed.  The Indicated TOs consider all the arrangements being \ncontemplated or requested as being interconnected with and synchronized with the transmission \nand/or distribution grid and thus not “fully isolated.”   \nAlthough the existing PJM Tariff already accommodates co-located load, the \nCommission may have an interest in providing further clarity.  If so, a definition of “co-located \nload” could be added to the PJM Tariff that clarifies the expectations and obligations associated \nwith such load.  Specifically, the Indicated TOs suggest that the following definition could be \nadded to the PJM Tariff:  \n“Co-located Load” shall mean load that has contractual \narrangements to be served by an adjacent generation resource that is \nphysically interconnected to and synchronized with the transmission \nor distribution grid.  Co-located Load is either Network Load or load \nbeing served using Point-to-Point Transmission Service, as \napplicable.  Such adjacent generation resource shall not meet the \ndefinition of Behind The Meter Generation.  Arrangements for Co-\nlocated Load must have separate metering for load consumption and \ngenerator output as required under PJM Tariff, Part III.   \n \nThis proposed definition is consistent with the provisions of the existing PJM Tariff but \nwould provide additional clarity to those directly impacted by co-located load arrangements.  At \nthe same time, this proposed language would ensure that PJM and its transmission owners have \nadequate visibility of the loads affecting the transmission system for planning and reliability \npurposes."},{"page":10,"startToken":3209,"endToken":3630,"text":"10 \n \nIII. \nDISCUSSION \nA. Classification of Co-located Load as Network Load Is Just and Reasonable. \nThe PJM Tariff, in its current form, allows for co-location of load and generation on \nterms that are just, reasonable, and not unduly discriminatory or preferential.  The PJM Tariff \nallows end-use load and generation to co-locate expeditiously and on terms that are also fair to \nall other users of the grid and commensurate with cost causation principles.  To allow this, the \nPJM Tariff, consistent with the pro forma OATT, provides for two types of transmission service \nto be used in accommodating co-location arrangements: Network Service and Point-to-Point \nService.  Both long-standing types of transmission service recognize that those that benefit from \nthe transmission system must contribute to its costs.  \nThe rate design in PJM, incorporated into the PJM Tariff, permits owners to recover, on a \npostage stamp basis without consideration of the distance between load and generation, the \nembedded costs of their respective portions of the transmission grid from network customers.20  \nAs the Commission has explained, “PJM recovers the full revenue requirements of existing \nfacilities (embedded costs) through its firm transmission rates.”21   \nThis concept of embedded costs of the transmission grid and associated cost \nresponsibility of load based on fairness principles predates Order No. 888,22 FERC’s landmark \n \n20 See, e.g., Pennsylvania-New Jersey-Maryland Interconnection, et al., 81 FERC ¶ 61,257 (1997) (adopting PJM \npricing proposal to allow recovery of embedded transmission revenue requirement from network customers), \ncorrected by 82 FERC ¶ 61,103 (1998), and clarified in part by 92 FERC ¶ 61,282 (2000), and review granted in \npart, vacated in part by 295 F.3d 1 (D.C. Cir. 2002); PJM Tariff, Section 34.1 (providing for payment by network \ncustomers of load ratio share of embedded cost of their zone); PJM Tariff, Attachments H-1, H-1A, H-2, H-2A, H-3, \nH-3D, H-7, H-7A, H-9, H-9A, H-13, and H-13A (establishing network revenue requirements for each of the Exelon \nUtilities based on the embedded costs of their respective transmission systems). \n21 PJM Interconnection L.L.C., 139 FERC ¶ 61,243, at P 78 n.105 (2012). \n22 See also Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Servs. by \nPub. Utils.; Recovery of Stranded Costs by Pub. Utils. and Transmitting Utils., Order No. 888, FERC Stats. & Regs. \n¶ 31,036, at 31,707 (1996) (cross-referenced at 75 FERC ¶ 61,080), order on reh’g, Order No. 888-A, FERC Stats. \n& Regs. ¶ 31,048 (cross-referenced at 78 FERC ¶ 61,220), order on reh’g, Order No. 888-B, 81 FERC ¶ 61,248 \n(cont'd)"},{"page":11,"startToken":3630,"endToken":4070,"text":"11 \n \nopen access transmission order, which was “issued in 1996 with the stated purpose of \n‘Promoting Wholesale Competition Through Open Access Non–Discriminatory Transmission \nServices by Public Utilities.’”23  In a 1994 order directing Florida Power & Light Company to \nprovide network transmission service to Florida Municipal Power Authority, the Commission \nexplained that Florida Municipal Power Authority could not simply reduce its network service \ntransmission cost obligations based on hourly economic dispatch decisions.  The Commission \nstated:   \nSince Florida Power must plan its transmission system to meet load, \nnot based on FMPA’s actual hourly or yearly demands, its \ncompensation for the network transmission service should not be \ndriven by FMPA’s hourly economic dispatch decisions.  Since \nFMPA wants to be able to use the transmission system exactly as \nfreely as does Florida Power, it must pay a rate that reflects that \nequality.  It must share the costs of the system on the same basis as \ndoes Florida Power—on the basis of its load.24 \nThe Commission solidified this concept in its pro forma definition of “Network Load,” which \ndoes not allow a Network Customer to designate only part of the load at a discrete Point of \nDelivery as Network Load unless arrangements for Point-to-Point Service are made.25  The \nCommission summed up the transmission service choices in Order No. 888-A: “The bottom line \nis that all potential transmission customers, including those with generation behind the meter, \n \n(1997), order on reh’g, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub nom. Transmission \nAccess Pol’y Study Grp. v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff’d sub nom. New York v. FERC, 535 U.S. 1 \n(2002). \n23 New York v. FERC, 535 U.S. 1, 5 (2002). \n24 FMPA v. FPL, 67 FERC ¶ 61,167 at 61,482 (1994).  \n25 See Order No. 888, FERC Stats. & Regs. ¶ 31,036 at Appendix D (Apr. 24, 1996) (defining “Network Load” as: \n“The load that a Network Customer designates for Network Integration Transmission Service under Part III of the \nTariff.  The Network Customer's Network Load shall include all load served by the output of any Network \nResources designated by the Network Customer.  A Network Customer may elect to designate less than its total load \nas Network Load but may not designate only part of the load at a discrete Point of Delivery.  Where an Eligible \nCustomer has elected not to designate a particular load at discrete points of delivery as Network Load, the Eligible \nCustomer is responsible for making separate arrangements under Part II of the Tariff for any Point-To-Point \nTransmission Service that may be necessary for such non-designated load.”)."},{"page":12,"startToken":4070,"endToken":4369,"text":"12 \n \nmust choose between network integration transmission service or point-to-point transmission \nservice.”26  It is with these physical realities and legal principles in mind that the Commission \nmust assess the PJM Tariff.   \nThe existing PJM Tariff is just and reasonable.  With that said, the Indicated TOs remain \nopen to and anticipate the potential for further discussion regarding possible changes to tariffs to \nexpressly specify that co-located load must be served by the existing forms of transmission \nservice—Network Service or Point-to-Point Service—while recognizing the evolving co-location \nconfiguration landscape.   \nB. Co-Located Load Benefits From Essential Services Provided Using the Grid. \nIn addition to FERC-jurisdictional transmission charges, PJM also assesses service \ncharges to users of the grid for essential reliability services, such as ancillary services.  As PJM \nacknowledged, there is no question that “[a]lthough co-located load is located behind the [point \nof interconnection], it still is electrically connected and synchronized to the PJM Transmission \nSystem when consuming power and therefore benefits from the use of the Transmission System \nand Ancillary Services.”27  The same is true even when the co-located load is only connected to \nthe distribution system, because ancillary services are required by both the transmission and \ndistribution system operators to maintain the integrity and stability of the transmission and \ndistribution system, as well as the power quality.28  In other words, co-located load cannot \nreceive the benefits of such essential reliability services without the physical and synchronous \ninterconnection to the transmission (and/or distribution) system.  These services are fundamental \n \n26 Order No. 888-A, FERC Stats. & Regs. ¶ 31,048, at 30,260 (Mar. 4, 1997). \n27 PJM Guidance on Co-Located Load at 1. \n28 Union of the Electricity Industry, Ancillary Services Unbundling Electricity Products – an Emerging Market, at 9 \n(Feb. 2004), https://pierrepinson.com/31761/Literature/Eurelectric2004-ancillaryservices.pdf."},{"page":13,"startToken":4369,"endToken":4747,"text":"13 \n \nto maintaining reliable operation of the grid.  Assignment of ancillary services to co-located load \nshould be treated like any other load.  Because the co-located load is interconnected with the grid \nand relies on the grid, PJM’s Tariff remains just and reasonable.  The PJM Tariff currently \nrequires no amendment or alteration for this class of customers, and there is no basis for the \nCommission to act under FPA section 206.  However, as previously noted, the Indicated TOs \nremain open to and anticipate the potential for further discussion regarding possible changes to \ntariffs.    \nIt is undeniable that the synchronized configurations associated with co-located load \nbenefit from essential reliability services provided by the regional PJM grid.29  By way of \nexample: load served by a nuclear unit necessarily depends on a grid interconnection because the \nnuclear unit is not permitted by its license to operate without a robust grid interconnection.30  \nFurther, load that is co-located with a nuclear unit depends on services such as load following, \nvoltage support, black start, and other ancillary services that will be and can only be delivered \nover the grid.31  Nuclear units cannot move their output up and down from moment to moment to \nmatch variations in the load, and because the nuclear units cannot provide these services, they \nmust instead be provided through connection to the grid.32  That is, remote generators increase \nand decrease their output in synchrony with the co-located load, and power flows on the grid \nlikewise move in synchrony with the co-located demand.  Those services are used every hour, \n \n29 See, e.g., Declaration of David Weaver, PE at P 17, Attachment 1 to Exelon Comments, Docket No. EL25-20 \n(Dec. 12, 2024) (“Weaver Decl.”) (explaining that because nuclear units are unable to provide black start services, \nco-located load must rely on those services from other resources in PJM that are connected to the grid in order to \ncome back online); id. at P 19 (explaining that the co-located load will most of the time take service that is \ndependent “on a strong interconnection with the grid that is supported by reactive power, operating reserves, and \nblack start”).  \n30 See id. at PP 11–12. \n31 See id. at PP 14–19. \n32 See id. at PP 14, 18."},{"page":14,"startToken":4747,"endToken":5029,"text":"14 \n \nnot just when the generator fails or the load exceeds the output of the connected unit.  Moreover, \nin a recently submitted co-location arrangement and in the arrangements proposed and discussed \nin the Complaint, the co-located load depended upon another nuclear unit at the same facility for \nits backup supply of real power—which is to say, a PJM capacity resource that is interconnected \nwith, serves, and relies entirely upon the grid.33  The proposed backup arrangement, including \nany “replacement capacity” mechanism, depends upon the delivery of energy from other \nlocations on the network through PJM’s transmission system.34 \nBecause these arrangements irrefutably rely on the transmission grid, there can be no \nneed for some new kind of service for these arrangements.  The PJM Tariff already has \nmechanisms that lay out how transmission users connect loads—those mechanisms work.  Any \nproposed tariff changes to be considered by the Indicated TOs as part of a separate process \nwould be for the sake of clarification that the existing service categories and requirements apply \nto co-located load; the fundamental principles established by the PJM Tariff cover co-location \narrangements.    \nC. All Load, Including Co-located Load, Is Used to Plan the Transmission \nSystem. \nAs explained above, the existing PJM Tariff can accommodate co-location arrangements.  \nAny end-use load, co-located or otherwise, can request retail service from the retail utility, \nconnect its facility, and receive service under the applicable retail rates.35  All of PJM’s load \ngrowth has happened through those established tariff mechanisms, and all that load growth was \n \n33 See Constellation Complaint and Application, Docket No. ER24-2172. \n34 See Weaver Decl. at PP 21–24. \n35 Depending upon the jurisdiction, states often limit who can serve retail."},{"page":15,"startToken":5029,"endToken":5314,"text":"15 \n \naccommodated through PJM’s requirement that it serve its customers through either Network \nService or Point-to-Point Service.36   \nThe PJM Reliability Assurance Agreement (“RAA”) sets forth the basic obligations of \nLoad Serving Entities in PJM and defines such entities to include any entity lawfully serving \nend-use load in the region.  Specifically,  \n“Load Serving Entity” or “LSE” shall mean any entity (or the duly \ndesignated agent of such an entity), including a load aggregator or \npower marketer, (i) serving end-users within the PJM Region, and \n(ii) that has been granted the authority or has an obligation pursuant \nto state or local law, regulation or franchise to sell electric energy to \nend-users located within the PJM Region.37 \n \nLSEs are required to become parties to the RAA, as that agreement provides that “every \nentity which is or will become a Load Serving Entity within the PJM Region is to become and \nremain a Party to this Agreement.”38  The RAA also provides that:  \nEach Party shall cooperate with the other Parties in the coordinated \nplanning and operation of their owned or contracted for Capacity \nResources to obtain a degree of reliability consistent with the \nReliability Principles and Standards.  In furtherance of such \ncooperation each Party shall:  \n \n. . . .  \n \n(c) provide or arrange for Network Transmission Service or Firm \nPoint-to-Point Transmission Service for service to the projected load \nof the Party . . . .39 \nTaken together, these provisions mean that any entity that is serving an end-use load, such as a \ngenerator supplying co-located load (or if the generator is selling to a middleman that is serving \n \n36 See PJM Tariff at Parts II and III. \n37 RAA, Definition of Load Serving Entity. \n38 RAA, Art. 2. \n39 RAA, Art. 9.1."},{"page":16,"startToken":5314,"endToken":5721,"text":"16 \n \nthe load, then the middleman), becomes an LSE, and is responsible for ensuring that its load is \ntaking Network Service or Point-to-Point Service. \nThe PJM Tariff spells out the process for accommodating new load for Network or Point-\nto-Point Customers, and for adding new loads for existing Network Customers.  Section 31.1 of \nthe PJM Tariff requires that Network Loads are to be specified in the Service Agreement.  \nSections 31.2 and 31.3 provide the procedures for identifying new Network Loads that will be \nserved by the Network Customer.40  If, and to the extent that, a study is required of the request, \nsection 32 of the PJM Tariff details that process.  And, because loads may change after \ncommencement of service, section 31.5 provides the process by which to report changing \nloads.41  Those provisions apply to, and work for, co-located load just as for any other end-use \nload.   \nIf co-located load is interconnected to the transmission system, it is using the \ntransmission system and must pay for its share of wholesale transmission service.  For wholesale \ntransmission service in PJM, the allocation of these wholesale charges should continue to be \nbased on the FERC-approved cost allocation methodologies employed today.  Specifically, if a \ncustomer has the option, capability, or is requesting such capability to serve their full load from \nthe PJM Transmission System, then the full load amount should be included in the LSE’s total \nload used to determine its share of total system costs, even if they choose not to use that full suite \nof services at times.  No free ridership should be enabled for grid-connected customers.  They are \n \n40 A “Network Service User” “mean[s] an entity using Network Transmission Service.”  PJM Tariff, Definitions.  \n“Network Transmission Service” “mean[s] transmission service provided pursuant to the rates, terms and conditions \nset forth in Tariff, Part III, or transmission service comparable to such service that is provided to a Load Serving \nEntity that is also a Transmission Owner.”  PJM Tariff, Definitions. \n41 While Point-to-Point Service would ordinarily not make sense for serving load within PJM, the provisions for \nrequesting such service are likewise clear and spelled out in the PJM Tariff.  For example, the Application process is \nspelled out in Section 17 of the PJM Tariff, and the study procedure is spelled out in Section 19 of the PJM Tariff.  \nOf course, Point-to-Point Service does not accommodate load growth—it allows only a specified reservation."},{"page":17,"startToken":5721,"endToken":6077,"text":"17 \n \npaying to use the transmission system and for the transmission system to be available to them \nwhen needed.  The fact that their load may not be constant does not reduce the possible need for \ninvestment in the transmission system or operation and maintenance costs that transmission \nowners incur to ensure that the system is available to them and that they receive reliable service.  \nPJM should not treat co-located load differently simply because of its contract drafting or \nplacement of the meter.  Because all loads physically connected to and synchronized with the \ntransmission system benefit from the transmission system, any attempt to isolate or piecemeal \nwholesale transmission services to quantify costs would be discriminatory because it would \ndisregard the interconnected nature of the transmission system. \nD. Creating A New, Non-Paying Category of Service Under the PJM Tariff \nWould Be Preferential and Unduly Discriminatory and Allow Co-Located \nLoad to Avoid Paying for Transmission Service. \nThe current PJM Tariff is just and reasonable with respect to co-location; as such, no \nchanges to the existing tariff are necessary because it accommodates any kind of co-location \narrangement.  Allowing a work-around for co-located load, which effectively gives that class of \ngrid users drastically reduced rates (or no charge at all) for use of the grid, is impermissible.42  \nNo reasoned basis has thus far been articulated for why the existing rates are unjust or \nunreasonable.   \nFurther, as previously explained, the PJM Tariff comports with the holding of Order No. \n888 that established and defined two basic types of transmission service provided by \ntransmission owner/operators: Network Service and Point-to-Point Service.  This holding \nremains good law, and the Commission has in recent years continued to reject requests that some \n \n42 16 U.S.C. § 824d(b) (“No public utility shall, with respect to any transmission or sale subject to the jurisdiction of \nthe Commission, (1) make or grant any undue preference or advantage to any person or subject any person to any \nundue prejudice or disadvantage, or (2) maintain any unreasonable difference in rates, charges, service, facilities, or \nin any other respect, either as between localities or as between classes of service.”)."},{"page":18,"startToken":6077,"endToken":6448,"text":"18 \n \nloads should somehow be treated as special third categories, not required to take transmission \nservice,43 and should continue to do so here. \nA new, special non-paying treatment for co-located load would undermine the very \npremise of open access, which is the fundamental principle by which the Commission regulates \nthe transmission system.  That is, under Order No. 888 and open access transmission tariffs to \ndate, all users of the grid pay costs commensurate with benefits, in the same way as the \ntransmission owners themselves must pay when transmitting power to loads that they serve.  \nThere is no justification for creating a new class of cost-free load that would not share in the \ncosts of the grid.  Far from being unjust and unreasonable, the existing PJM Tariff, which \nrequires that all load pay for using the grid, complies with, and enforces the mandates of Order \nNo. 888 and the Federal Power Act. \nA fundamental ratemaking principle establishes that “the costs assessed against a party \nmust bear some resemblance ‘to the burdens imposed or benefits drawn by that party.’”44  The \nPJM Tariff complies with these cost allocation requirements and appropriately accounts for the \ncost of the benefits drawn by such load from use of the grid and grid services.  But allowing co-\nlocated loads to evade ordinary and established tariff charges for grid usage by carving out this \nload from Network Service or Point-to-Point Service would violate these principles.   \nAs explained in answers to the Complaint,45 carving a 480 MW co-located load in the \nCommonwealth Edison territory (which hosts multiple nuclear units) out from Network Service \n \n43  See, e.g., Nat’l R.R. Passenger Corp. v. PPL Elec. Utils. Corp. et al., 171 FERC ¶ 61,237, order on reh’g, 173 \nFERC ¶ 61,043 (2020). \n44 Pub. Serv. Elec. & Gas Co. v. FERC, 989 F.3d 10, 13 (D.C. Cir. 2021) (“PSE&G”) (quoting Midwest ISO \nTransmission Owners v. FERC, 373 F.3d 1361, 1368–69 (D.C. Cir. 2004)). \n45 Exelon Comments, Docket No. EL25-20, at 25–26 (Dec. 12, 2024).  The underlying calculations are explained in \nthe Reed/Powers Declaration, which is Attachment 2 to those Exelon Comments, and detailed at Attachment A to \nthe Reed Powers Declaration."},{"page":19,"startToken":6448,"endToken":6854,"text":"19 \n \nwould avoid approximately $121 million in annual charges, leading to a 1.53% increase in \nrepresentative residential customer bills, or about $25.57 annually, compared to a similar load \ncustomer who paid its share of the costs of the grid.   \n• A 1 GW co-located load in the Commonwealth Edison territory would avoid \napproximately $253 million in annual charges, resulting in a 3.19% increase in \nrepresentative residential customer bills or about $45.16 annually.   \n• Similarly, a 480 MW co-located load in the PECO territory (which is the home of \nthe Limerick nuclear facility) would avoid approximately $43 million in annual \ncharges, leading to a 0.96% increase in representative residential customer bills, \nor about $23.16 annually.   \n• A 1 GW co-located load in the PECO territory would avoid approximately $89 \nmillion in annual charges, resulting in a 1.99% increase in representative \nresidential customer bills or about $48.26 annually.   \n• Finally, a 480 MW co-located load in the Southern Maryland Electric Cooperative \n(“SMECO”) territory (where the Calvert Cliffs nuclear facility is located) would \navoid just over $53 million in annual charges, leading to an 11.10% increase in \nrepresentative residential customer bills, over $208 annually.  A 1 GW co-located \nload in the SMECO territory would avoid approximately $112 million in annual \ncharges, resulting in a 23.11% increase in representative residential customer bills \nor about $433.72 annually.   \nThese are costs that the co-located load would avoid paying if the PJM Tariff is altered to \nallow such arrangements to evade grid charges.  The inevitable result would be that the co-\nlocated load’s share of the grid expenses would be unlawfully shouldered by all the other \ncustomers who would be required to make up the difference.46  \n \nThe PJM Tariff applies, and will continue to apply, to all who seek transmission service \nin PJM, and it ensures that all customers pay their fair share of the transmission network from \nwhich they benefit.  Co-location configurations can be accommodated under the current PJM \n \n46 PJM compensates Transmission Owners for use of the grid using the load-ratio share method—that is, each \nNetwork Customer pays its load ratio share, and the sum of the payments reimburses the Transmission Owner for \nthe full cost of the grid.  If Co-Located Load is not designated as the load of a Network Customer, the load ratio \nshare for all other customers will be higher.  There is an automatic cost shift to other customers."},{"page":20,"startToken":6854,"endToken":7089,"text":"20 \n \nTariff.  Entities are entitled to request retail service from a local distribution company or sign up \nas a Network Customer in PJM (or have the LDC act as Network Customer), and their load will \nbe served like every other user of the system, and they will pay the same costs that every other \nuser pays.   \nIV. \nCONCLUSION \nFor the reasons stated above, the Indicated TOs respectfully request that the Commission \nreaffirm the justness and reasonableness of the current, non-discriminatory—and functional—\nPJM Tariff, because PJM’s Tariff already accommodates co-location arrangements through the \ntwo types of service specified in the PJM Tariff: Network Service and Point-to-Point Service. \n \nRespectfully submitted, \n \n \n \n \n/s/ William Sauer \nWilliam Sauer \nVice President, Federal Regulatory Affairs  \nExelon Corporation  \n701 Ninth St. N.W.  \nWashington, DC 20001  \nTelephone: 202-868-7499  \nEmail: william.sauer@exeloncorp.com   \n/s/ Max Minzner \n \nMax Minzner \nVice President and Deputy General Counsel \nExelon Corporation \n701 Ninth St. N.W.  \nWashington, DC 20001  \nTelephone: 202-934-4740 \nEmail: max.minzner@exeloncorp.com \n \n \nOn behalf of Exelon Corporation \n \n/s/ Stacey Burbure \nStacey Burbure \nVice President FERC, RTO Strategy & Policy \nAmerican Electric Power Service Corporation \n1 Riverside Plaza  \nColumbus, OH 43215 \nTelephone: 614-716-2502  \nEmail: slburbure@aep.com \n \n/s/ Lisa G. McAlister \nLisa G. McAlister \nAMP Transmission, LLC \n1111 Schrock Road, Suite 100 \nColumbus, Ohio 43229 \nTelephone: 614-540-6400 \nEmail: lmcalister@amppartners.org \n \nOn behalf of American Electric Power \nService Corporation \nOn behalf of AMP Transmission, LLC"},{"page":21,"startToken":7089,"endToken":7304,"text":"21 \n \n \n/s/ Martin J. Keane \nMartin J. Keane \nDirector of Public Utilities \nCleveland Public Power \n1300 Lakeside Ave. \nCleveland, OH 44114 \nTelephone: 216-664-2444 ext. 75604 \nEmail: martin_keane@clevelandwater.com \n \n/s/Debra D. Roby \nDebra D. Roby \nWashington Energy Law LLP \n900 17th Street N.W., Suite 500-A \nWashington, D.C. 20006 \nTelephone: 703-785-9270 \nEmail: droby@washingtonenergylaw.com \n \nOn behalf of City of Cleveland, Department of \nPublic Utilities, Division of Cleveland Public \nPower \n \nOn behalf of the City of Hamilton, OH \n \n/s/ Wesley Walker \nWesley Walker \nSenior Assistant General Counsel \nDominion Energy Services, Inc. \n120 Tredegar Street \nRichmond, VA 23219 \nTelephone: 804-819-2345 \nEmail: wesley.walker@dominionenergy.com \n \n/s/ Molly Suda  \nMolly Suda \nAssociate General Counsel \nAnnelise Rickert  \nFederal Government Affairs Director \nDuke Energy Corporation \n1301 Pennsylvania Ave NW, Suite 200 \nWashington, DC 20004 \nTelephone: 202-824-8011 \nEmail:  molly.suda@duke-energy.com  \nAnnelise.rickert@duke-energy.com         \n   \nOn behalf of Dominion Energy \nOn behalf of Duke Energy \n \n/s/ Michael Brechlin \nMichael Brechlin \nPA Bar # 335424 \nDuquesne Light Company \n411 7th Ave \nPittsburgh, PA 15219 \nTelephone: 412-393-6431 \nEmail: mbrechlin@duqlight.com \n/s/   Amanda P. Parker \nAmanda P. Parker \nAttorney \nFirstEnergy Service Company \n76 South Main Street \nAkron, OH 44308 \nTelephone: (330) 384-4592 \nEmail: aparker@firstenergycorp.com  \n \nOn behalf of Duquesne Light Company \nOn behalf of The FirstEnergy Transmission \nCompanies"},{"page":22,"startToken":7304,"endToken":7518,"text":"22 \n \n/s/ Denise R. Foster Cronin \nDenise R. Foster Cronin \nVice President, Federal and RTO Regulatory \nAffairs \nEast Kentucky Power Cooperative, Inc. \n4775 Lexington Road, P.O. Box 707 \nWinchester, KY 40392-0707 \nTelephone: 859-745-9615 \nEmail: denise.cronin@ekpc.coop \n \n/s/ Daniel E. Frank                  \nDaniel E. Frank \nKelly Cuthbertson \nEversheds Sutherland (US) LLP \n700 Sixth St., N.W., Suite 700 \nWashington, DC 20001-3980 \nTelephone: 202-383-0100 \nEmail:  \ndanielfrank@eversheds-sutherland.com \nkellycuthbertson@eversheds-sutherland.com \n \n \n \nOn Behalf of East Kentucky Power \nCooperative, Inc. \n \n/s/ Adrienne E. Clair \nAdrienne E. Clair \nThompson Coburn LLP \n1909 K Street, N.W., Suite 600 \nWashington, D.C.  20006-1167 \nTelephone: 202-585-6900 \nEmail: aclair@thompsoncoburn.com \n \n/s/ Steve Nadel \nSteven M. Nadel \nSenior Counsel \nPPL Services Corp.  \n645 Hamilton Street, Suite 601 \nAllentown, PA 18101 \nTelephone: 610-774-4775   \nEmail: SMNadel@pplweb.com \n \nOn behalf of Old Dominion Electric \nCooperative \n \nOn behalf of PPL Electric Utilities Corp. \n \n/s/David Burns  \nDavid Burns  \nSenior Manager,  \nFERC Policy & Regulatory Affairs  \nConsolidated Edison Company of New York, \nInc.   \n4 Irving Place \nNew York, NY 10003   \nTelephone: 571-678-9152  \nEmail: burnsd@coned.com \n/s/Joshua Kirstein \nJoshua A. Kirstein  \nSenior Attorney  \nLaw Department \nConsolidated Edison Company of New York, \nInc.  \n4 Irving Place, 18th Floor  \nNew York, NY 10003  \nTelephone: 929-656-5971 \nEmail: kirsteinj@coned.com \n \n \nOn behalf of Rockland Electric Company"},{"page":23,"startToken":7518,"endToken":7658,"text":"23 \n \n/s/ Damon L. Krieger \nDamon L. Krieger \nGroup Vice President, Legal, Strategy, and \nSustainability, and Deputy General Counsel \nSouthern Maryland Electric Cooperative, Inc. \n15035 Burnt Store Road \nP.O. Box 1937 \nHughesville, Maryland 20637-1937 \nTelephone: 301-274-4323 \nEmail: Damon.Krieger@SMECO.coop \n \n/s/ Jeremy L. Fetty \n \nJeremy L. Fetty \nParr Richey \n251 N. Illinois, Suite 1800 \nIndianapolis, Indiana 46204  \nTelephone: 317-269-2500 \nEmail: j_fetty@wvpa.com \n \n \nOn behalf of Southern Maryland Electric \nCooperative \n \nOn behalf of Wabash Valley Power \nAssociation, Inc. \n \n/s/ Lindsay Berkstresser \nLindsay Berkstresser \nCounsel – Energy & Regulatory \nUGI Corporation \n500 North Gulph Road \nKing of Prussia, PA 19406 \nTelephone: 717-504-9925 \nEmail: berkstresserl@ugicorp.com \n \n/s/ Richard P. Bonnifield \nRichard P. Bonnifield \nHusch Blackwell \n1801 Pennsylvania Avenue, NW, \nSuite 1000 \nWashington, DC 20006-3606 \nTelephone: 202-243-8844 \nEmail: \nrichard.bonnifield@huschblackwell.com \n \n \n \nOn behalf of UGI Utilities Inc. \n \n \nMarch 24, 2025"},{"page":24,"startToken":7658,"endToken":7660,"text":"ATTACHMENT A"},{"page":25,"startToken":7660,"endToken":8143,"text":"1\n \na. General \n \ni. \nDo you agree with the jurisdictional principles outlined in section VI.A \nand should the Commission reach any other conclusions regarding \njurisdiction in a final order it may issue in this proceeding?  Why or why \nnot?   \n \nThe Indicated TOs generally agree with the jurisdictional principles as outlined by the Commission \nin section VI.A of the Show Cause Order.  The Federal Power Act (“FPA”) provides the \nCommission with jurisdiction over the wholesale sale of electricity in interstate commerce and \nover the rates, terms, and conditions of service of the transmission of electricity in interstate \ncommerce, including the physical interconnection of wholesale generators.  FERC has jurisdiction \nto determine allocation of wholesale regional costs to transmission zones.  The FPA preserves state \njurisdiction over the regulation of end-use sales (i.e., retail sales), including to load that is co-\nlocated at generating stations, and the connection of that end-use load to the electric system.  \nAdditionally, Section 212(h) of the FPA1 affirmatively prohibits the Commission from requiring \nretail wheeling.  \n \nThe Indicated TOs believe that the Show Cause Order is helpful in rearticulating important guiding \nprinciples in this context.  In particular, the Commission clearly confirmed that states have \nexclusive jurisdiction over retail sales, which means the states decide which entities are legally \npermitted to provide electricity to retail customers and how the costs of providing wholesale power \nare recovered from retail customers.2  What this means is that FERC can set a transmission rate \nthat Network Customers serving all Network Load must pay for services and associated charges, \nbut how a state chooses to assign and allocate the recovery of the cost of that charge between \nindividual retail customers or among classes of end-use load may vary, as long as there is no cost-\ntrapping.  For example, some states may have non-bypassable charges that are direct pass-throughs \nbased on load.   \n \nLarge load customers can continue to co-locate and contract for power directly from generators \nwhere state laws and regulations addressing retail electric service allow.3  A few key things flow \n \n1 16 U.S.C. § 824k(h). \n2 The Indicated TOs note that the Organization of PJM States, Inc. also agrees with this principle.  See Organization \nof PJM States, Inc., Post Technical Conference Comments of the Organization of PJM States, Inc., Docket No. \nAD24-11-000, at 4–5 (Dec. 9, 2024) (“Finally, FERC should confirm that the sale between co-located generation \nand load is a retail transaction subject to state jurisdiction.  The Federal Power Act gives the Commission \njurisdiction to regulate the transmission of electricity in interstate commerce.  There is no regulatory gap.  Sales of \nelectricity from a generator to an end use customer in intrastate commerce are subject to state jurisdiction.” (footnote \nomitted)). \n3 Cf. New York v. FERC, 535 U.S. 1, 23 (2002) (explaining that “the legislative history [of the FPA] demonstrates \nCongress’ interest in retaining state jurisdiction over retail sales”)."},{"page":26,"startToken":8143,"endToken":8566,"text":"2\n \nfrom this jurisdictional foundation and guidance the Commission has provided in this and other \ndecisions: \n \n• First, state jurisdiction must be recognized and respected.  Consistent with basic principles \narticulated by the Commission in the Show Cause Order, transmission service for co-\nlocation arrangements must be applied to customers taking service under a state \njurisdictional rate filed by an electric distribution company (EDC)/load serving entity \n(LSE) and approved by the state regulator.   \n• Second, it is important and necessary to implement retail metering of the end-use load at \nall times.  No matter the terms of the Commission-jurisdictional rates, the end-use load is \ndefinitionally taking retail service, and the load data necessary for the administration and \napplication of retail rates must be collected by the LSE and made available.  \n \nThe Indicated TOs would welcome the Commission reaffirming that PJM generator \ninterconnection procedures apply to the interconnection of and service to generation, including \ngeneration at which load is co-located, but not to the load itself, and the interconnection of that \nload is a matter of state, not federal, jurisdiction. \n \nIn addition, consistent with the jurisdictional principles as outlined by the Commission in section \nVI.A of the Show Cause Order, otherwise lawful state law rate structures are not federally \npreempted by any PJM Tariff language. \n \nFurther, the Commission and PJM should affirm that co-located loads that are physically \ninterconnected to and synchronized with the PJM transmission system are utilizing the \ntransmission system, which is not to say that the loads would be charged directly—such charges \nare instead charged to the Network Customer (or where appropriate Point-to-Point Customer) who \nwill either be the Load Serving Entity or will in turn pass the charges on to the Load Serving Entity.  \nCo-located loads that utilize essential reliability services require use of the transmission system \nthat is subject to FERC’s jurisdiction. Only when a facility is disconnected from the grid and fully \nislanded is it not using or benefitting from the transmission system.     \n \nii. \nDoes the Tariff sufficiently address co-location arrangements with respect \nto each issue listed in this order?  Please include specific tariff provisions \nor other governing documents that may apply;   \n \nThe current PJM Tariff addresses and encompasses co-location arrangements, including the \ninterconnection of generators where load is co-located and transmission service provided is to co-\nlocated load.  Under the PJM Tariff, all load in PJM must be designed as Network Load and be \nserved by a Network Customer paying Network Integration Transmission Service (Network \nService) rates or, as and when appropriate, take and arrange for Point-to-Point Transmission"},{"page":27,"startToken":8566,"endToken":9039,"text":"3\n \nService (Point-to-Point Service).  This construct is reflected in the PJM Reliability Assurance \nAgreement (RAA).4  These rules have been consistently applied since Order No. 888.  Because \nthese requirements apply to co-located load just like all other load on the system, the PJM Tariff \naddresses these arrangements.5  Designation of co-located load as PJM Network Load ensures that \nthis load pays its fair share of transmission costs and essential reliability services.  This is equitable \nand consistent with cost causation principles and the current tariff framework in which load pays \nfor the transmission system.  Further, it ensures consistent application of just and reasonable rates \nand protects against undue discrimination.  Just like all other customers using the transmission \nsystem, interconnected co-located load must pay for all the services it receives. \n \nThe Indicated TOs, however, acknowledge that the level and growth in the interest of co-located \nload has been accompanied by questions, posed by customers and others, about the services co-\nlocated load uses and the rates that are applicable to co-location arrangements.  The Indicated TOs \nhave also benefited from hearing from many of these customers over the past several months and \ntheir primary interest appears to be in obtaining necessary certainty that can help the ultimate goal \nof speed to market.  With direction from the Commission, the Indicated TOs are open to working \nwith PJM and other stakeholders to incorporate appropriate PJM Tariff revisions to expressly \nspecify that co-located load must be served by the existing forms of transmission service—\nNetwork Service or Point-to-Point Service.  Any such change to the existing just and reasonable \nPJM Tariff—and the fundamental Network Load provisions it contains—must not inadvertently \nor deliberately suggest a new third class of service. \n \niii. \nIf the Tariff does not sufficiently address co-location arrangements, how \nshould the Tariff be modified to do so?  As part of your answer, address \nwhether portions of the Guidance Document may serve as a just and \nreasonable and not unduly discriminatory or preferential replacement rate.  \nAlternatively, address whether existing rules in the Tariff may or should \nbe modified to address co-location arrangements; \n \nThe core ratemaking principle at issue here—that co-located load, like all load in PJM, must be \nincluded in Network Load using Network Service or be a Point-to-Point Service customer—is \nalready reflected in the PJM Tariff and longstanding Commission policy.  Thus, no changes to the \nexisting PJM Tariff are needed. \n \n \n4 See Definition of Load Serving Entity; Article 2 (requiring all LSE’s to be party to agreement); Article 9.1 \n(requiring all LSEs to arrange for Network or Point-to-Point Service). \n5 See PJM Tariff, Sections 31.1, 31.2, 31.3 and 31.5 (addressing designation of loads for Network Customers and \nprocedures to address new loads and load growth); Sections 17 and 19 (addressing designation of receipt points for \nPoint-to-Point Customers and study procedures)."},{"page":28,"startToken":9039,"endToken":9547,"text":"4\n \niv. \nParties may also address how co-located loads are similar to or disparate \nfrom other types of arrangements where load and generation share the \nsame point of interconnection (such as Behind the Meter Generation as \ndefined in PJM’s Tariff or non-retail behind the meter generation) and \nshould consider how any proposed replacement rate would interact with \nthese other arrangements.    \n \nThe PJM Tariff recognizes that, under defined circumstances, limited generation can be treated as \nbeing “behind the meter” of the load and that the load served by this Behind the Meter Generation \n(BTMG) is entitled to a reduction in their billing determinants for Network Transmission Service, \nbased on the net load on the system.6  Of note, the PJM Tariff definition of BTMG applies to \narrangements that “deliver[] energy to load without using the Transmission System” and thus \nwould be inapplicable to all co-located load that is Network Load.  Further, the PJM Tariff \nprovisions relating to BTMG7 provide for an adjustment to the billing determinants for “Network \nCustomers”—those provisions are unavailable for entities that are not Network Customers.8  That \ndoes not, of course, affect the treatment of the arrangement, or the measurement of the load, for \nstate retail ratemaking purposes.  That is not within the jurisdiction of the Commission.  \n \nb. Transmission Service \n \ni. \nPlease explain whether and to what extent different configurations of co-\nlocated load rely on or otherwise use the transmission system to receive \npower, directly or indirectly, from the co-located generator; \n \nCo-located load that is physically interconnected with and synchronized to the grid uses the \ntransmission system.  Neither the fact that co-located load is geographically near a generator, nor \nits agreement to buy energy from the co-located generator, changes that, legally or physically.    \nThis is a straight-forward, engineering-based decision.  End-use load can only fully avoid use of, \nreliance on, and benefit from the grid if the load is truly physically islanded without any connection \nto the transmission or distribution system at any time.   \n \n6 Non-Retail BTMG must operate at its full output during the first ten occurrences of Maximum Generation \nEmergency conditions each year in the zone where the unit is located, providing a significant contribution to grid \nreliability when it is needed most. PJM Tariff, Schedule 15. Additionally, the total amount of Non-Retail BTMG in \nthe PJM Region is capped in any specific year and sets a maximum ceiling of 3,000 MW (unless increased through a \nsection 205 filing), providing PJM the opportunity to ensure that Non-Retail BTMG does not detrimentally affect \nsystem operations.  To be entitled to a reduction in their billing determinants for Network Transmission Service, co-\nlocated Customer Facilities would have to demonstrate that they meet each of the eligibility requirements. \n     \n7 PJM Tariff, section 34.2 (all Network Customers) and 34.3 (certain further provisions relating to Non-Retail \nBehind the Meter Generation). \n8 The provisions would also be inapplicable to loads that are served by a contractual intermediary, rather than being \nserved directly by a generator.  In such a situation, the generator is just an upstream supplier."},{"page":29,"startToken":9547,"endToken":10038,"text":"5\n \n \nCo-located load that is connected to the grid also takes advantage of essential reliability services, \nsuch as ancillary services, including black start, regulation, and reserves, has the potential to draw \nreal or reactive power from the grid at any time, and relies on and benefits from its connection to \nthe transmission system at all times.  Essential reliability services require use of the transmission \nsystem to deliver those services.  If such co-located load arrangement does not need essential \nreliability services, then it would not need to interconnect to the transmission system altogether.  \nIndeed, without that connection and the facilities that make it up, the co-location arrangement \ncould not exist.  Therefore, since co-located load is connected to the transmission system, it should \npay for its share of the embedded costs of the grid. \n \nii. \nPlease explain whether and to what extent different co-location \nconfigurations impose costs on the transmission system or increase \ntransmission costs allocated to other parties.  How can those costs be \napproximated, given that certain co-location configurations may change \npower flows on the grid and necessitate upgrades to the transmission \nsystem?  Retail loads typically take service from wholesale entities that \npay for Network Integration Transmission Service that allocates these \ncosts; co-located loads may not.  Network Loads pay directly for Network \nIntegration Transmission Service.  How should PJM estimate the effects \nthat different configurations of co-located load have on the transmission \nsystem?  Should these costs be passed through to co-location arrangements \nin some way, and, if so, how?   \n \nIn general, service to loads in PJM is paid for on an embedded cost basis.  PJM’s rate design, \nincorporated into the PJM Tariff, permits transmission owners to recover, on a postage stamp basis \nwithout consideration of the distance between load and generation, the embedded costs of their \nrespective portions of the transmission grid from network customers.9  As the Commission has \nexplained, “PJM recovers the full revenue requirements of existing facilities (embedded costs) \nthrough its firm transmission rates.”10   \n \nIf co-located load is interconnected to the transmission system, it is using the transmission system \nand must pay for its share of wholesale transmission service.  For wholesale transmission service \n \n9 See, e.g., Pennsylvania-New Jersey-Maryland Interconnection, et al., 81 FERC ¶ 61,257 (1997) (adopting PJM \npricing proposal to allow recovery of embedded transmission revenue requirement from network customers), \ncorrected by 82 FERC ¶ 61,103 (1998), and clarified in part by 92 FERC ¶ 61,282 (2000), and review granted in \npart, vacated in part by 295 F.3d 1 (D.C. Cir. 2002); PJM Tariff, Section 34.1 (providing for payment by network \ncustomers of load ratio share of embedded cost of their zone); PJM Tariff, Attachments H-1, H-1A, H-2, H-2A, H-3, \nH-3D, H-7, H-7A, H-9, H-9A, H-13, and H-13A (establishing network revenue requirements for each of the Exelon \nUtilities based on the embedded costs of their respective transmission systems). \n10 PJM Interconnection L.L.C., 139 FERC ¶ 61,243 at P 78 n.105 (2012)."},{"page":30,"startToken":10038,"endToken":10565,"text":"6\n \nin PJM, the allocation of these wholesale charges should continue to be based on the FERC-\napproved cost allocation methodologies employed today.  \n \nSpecifically, if a customer has the option, capability, or is requesting such capability to serve their \nfull load from the PJM Transmission System, then the full load amount should be included in the \nLSEs’ total load used for determining its share of total system costs, even if they choose not to \nutilize that full suite of services at times.  No free ridership should be enabled for grid connected \ncustomers.  They are paying for the transmission system to be available to them.  The fact that \ntheir load may not be constant does not reduce the possible need for investment in the transmission \nsystem or O&M costs that transmission owners incur to ensure that the system is available to them \nand that they receive reliable service.  In fact, intermittent or switched loads can increase burdens \nand associated costs for the system. \n  \nThe addition of co-located load, like other load additions, can require system upgrades, including \nto transmission and distribution facilities.  PJM Transmission Owners are required to plan their \ntransmission systems to ensure that energy can be delivered to all network customers on the system, \nincluding the LSEs responsible for all end-use load. 11   This ensures compliance with the \nrequirements, imposed by the states, not PJM, that the end-use load itself must be served.  In \ngeneral, transmission upgrades required for a co-located load will be similar or the same as those \nrequired for an equivalent load addition close to, but not co-located with, the relevant generator, \nwith the only real distinction between the two loads being the placement of a meter.  The costs of \nthese transmission upgrades are typically recovered from all load on the system via the Network \nService rate.  As explained above, retail sales, including to load that is co-located at generating \nstations, is regulated by the states, rather than the Commission.   \n \nBecause co-located loads or their LSEs are required under the current PJM Tariff to take either \nNetwork Service or Point-to-Point Service, co-located load customers must pay for the costs of \nthose and all other transmission upgrades along with all other customers.  PJM should not treat co-\nlocated load differently simply because of its contract drafting or placement of the meter.  Because \nall loads physically connected to and synchronized with the transmission system benefit from the \ntransmission system, any attempt to isolate or piecemeal wholesale transmission services to \nquantify costs would be discriminatory since it would disregard the interconnected nature of the \ntransmission system.  Allowing co-located load to avoid paying network service charges would \n \n11 PJM Tariff, Part III, Section 28.2 (stating, “[t]he Transmission Provider shall include the Network \nCustomer’s Network Load in the Transmission System planning and the Transmission Owners shall, consistent with \nthe terms and conditions of the Tariff, the Operating Agreement, and Good Utility Practice, endeavor to construct \nand place into service sufficient transfer capability to deliver the Network Customer’s Network Resources to serve \nits Network Load on a basis comparable to the delivery of each Transmission Owner’s own generating and \npurchased resources to its Native Load Customers”)."},{"page":31,"startToken":10565,"endToken":11001,"text":"7\n \nprovide that load with the benefits of the network while leaving others to shoulder the burden of \npaying for the transmission system.    \n \niii. \nPlease explain whether co-location arrangements are or should be \nrequired to take Network Integration Transmission Service or Point-to-\nPoint Transmission Service; or whether a more tailored new category of \ntransmission service is warranted.  Please also address any cost \nallocation implications of your position on this issue; \n \nNo new category of service is required or warranted in the PJM Region.  Under existing \nCommission policy and under the currently effective PJM Tariff, load is served either as a Network \nService or as Point-to-Point Service customer.12  Co-located load simply needs to take service \nunder one of those two frameworks as well as retail service under an appropriate state-\njurisdictional tariff.  There has been no allegation in any of the related proceedings leading up to \nthe Commission’s Show Cause Order that the current regime requiring one of those two specified \nservices has impaired any load’s ability to secure service safely, reliably, and at reasonable cost, \nor that service had been unobtainable as a result of the PJM Tariff’s longstanding requirements.  \nThere have been allegations that efforts to request service outside of the PJM Tariff provisions \nwere thwarted,13 but such allegations do not contend that the PJM Tariff provisions, which require \nthat requests proceed through a Network Customer or through Point-to-Point Service, failed.  As \nstated above in the answer to question b.ii., any alteration to the current PJM Tariff that would \nallow co-located load to avoid paying network service charges would provide that load with the \nbenefits of the network while leaving others to shoulder the burden of paying for the transmission \nsystem.   \n \niv. \nWhat changes to the rates, terms, and conditions of Network Integration \nTransmission Service or Point-to-Point Transmission Service or, \nalternatively, what new form of transmission service(s) may be necessary \nfor different configurations of co-location to ensure that the Tariff is \nconsistent with cost causation principles and the beneficiary pays \nprinciple?   \n \nNetwork Service and Point-to-Point Service in the PJM Region meet the needs of co-located \ncustomers.  The existing rules are adequate to provide safe, reliable service at just and reasonable \nrates.  Those that have argued for an alternative form of service appear to do so primarily out of \n \n12 See discussion and RAA cites in Response ii above. \n13 See Complaint at 9 (“PJM has implemented practices that substantially affect rates, terms and conditions \napplicable to generation interconnection to the grid and wholesale market participation that are outside the Tariff \nand can be changed by PJM without notice at any time.”)."},{"page":32,"startToken":11001,"endToken":11449,"text":"8\n \nconcern about the charges associated with the existing rules—not because the existing rules are \ninadequate to provide safe, reliable service at just and reasonable rates.  The Commission has \npreviously rejected attempts to create new forms of service for those who claim to use the grid in \na lesser fashion than others—nothing has changed.14   \n \nHaving said this, the Indicated TOs are open to working collaboratively with PJM—and with their \nretail customers, state regulators, and other stakeholders—to consider clarifications to the PJM \nTariff to expressly specify that co-located load must be served by the existing forms of \ntransmission service—Network Service or Point-to-Point Service.  The Indicated TOs would \nfurther commit to working with PJM to revise its Manuals and Guidance to address details of how \nthe entities serving co-located load would satisfy Network Service and PTP requirements in a \nmanner that also respects equitable principles and state jurisdiction over retail rates.      \n \nv. \nParties may also wish to address how to determine which co-located load \nconfigurations should be required to take Network Integration \nTransmission Service or Point-to-Point Transmission Service or a new \nform of transmission service (i.e., whether generalized policies or tests, \nsuch as a multi-factor test, to be applied case-by-case, may be \nappropriate), as well as the magnitude (i.e., how the service taken by co-\nlocated load compares to service by other types of load).  For example, if a \nco-located generator is synchronized to the grid but the load can be \nconfigured to be wholly isolated from the grid in the event the co-located \ngenerator trips offline, what technical and operational factors should \ndetermine whether the co-location arrangement still relies on the \ntransmission system in ways that warrant a requirement that the co-located \nload take Network Integration Transmission Service or Point-to-Point \nTransmission Service or a new form of transmission service?  Are there \npotential co-located load configurations for which tailored approaches \nmay be appropriate? \n \nUnder existing Commission policy and under the PJM Tariff, load is served either by Network \nService or Point-to-Point Service.  Those rules apply to co-located load regardless of whether the \nco-located load is “in front of” or “behind” the generator’s interconnection because the co-located \nload remains connected to and reliant on the grid, takes grid services, and benefits from the grid.  \nA new category of service is not warranted.  Co-located load that is physically connected to and \nsynchronized with the grid benefit from their interconnection to the network and the essential \nreliability services provided by the network.  Indeed, those customers demand interconnection—\n \n14 See, e.g., Nat’l R.R. Passenger Corp. v. PPL Elec. Utils. Corp. et al., 171 FERC ¶ 61,237, order on reh’g, 173 \nFERC ¶ 61,043 (2020)."},{"page":33,"startToken":11449,"endToken":11905,"text":"9\n \nbecause they need it.  Only in cases of true, physical disconnection, such as islanding, can the load \nclaim not to receive benefits from the transmission network.  Situations where an abnormal event \nor response to a Reliability, Availability and Serviceability (RAS) operation that result in the \ngenerating facility disconnecting from the grid do not equate to islanding.  In such situations, if \nthe load can continue being served from the transmission system while that generation unit is \noffline, it must be interconnected to the transmission system and take appropriate services.  It \nwould, therefore, not be islanded. \n \nvi. \nWith respect to the Guidance Document, please explain what it means to \nbe “electrically connected and synchronized to the PJM Transmission \nSystem when consuming power” and how that implicates the use of \nNetwork Integration Transmission Service or Point-to-Point Transmission \nService or a new form of transmission service;  \n \nPJM’s Commission-approved pro forma tariffs and interconnection agreements that cover terms \nof service for interconnection to the transmission grid require that all interconnecting customers \nbe synchronized to the grid as a condition of service.15  This synchronization is necessary to \npreserve voltage stability and reliability and, as such, is foundational to safe and reliable operation \nof the physical facilities that comprise the transmission grid. 16  Thus, it follows that to be \n“electrically connected and synchronized” is a system operating condition that is separate from \ntransmission rates.  Instead, it concerns physical safety, reliability, and security of the physical \nfacilities that are in play.  Given these considerations, it has long been settled policy and law that \nany party that desires to interconnect to the grid must synchronize and keep its facilities \nsynchronized to the grid at all times. \n \nvii. \nWhat operational or commercial factors of a co-location arrangement \nwould result in a co-located load not needing to take any form of \ntransmission service, including what types of special protection schemes \nor backup arrangements may be necessary to ensure the co-located load \nnever takes any form of transmission service? \n \nAs indicated above, the only arrangement where the end-use load does not need to take some form \nof transmission service is one in which the load is completely islanded and does not connect to, \ntake service from, or rely on the transmission or distribution system in any way, for any type of \n \n15 See, e.g., PJM Tariff, Attachment O, Appendix 2, Section 1.4.5. \n \n16 See Reliability Standard FAC-001-0, R.2.1.12 (the Transmission Owner’s facility connection requirements shall \naddress, but are not limited, to synchronizing of facilities) (note that the currently-effective version of FAC-001 (-4) \nhas omitted this language); Reliability Standard EOP-005-3, R.8.4 (“Each Transmission Operator shall include \nwithin its operations training program . . . training on . . . Synchronizing (re-energized sections of the System).”)."},{"page":34,"startToken":11905,"endToken":12418,"text":"10\n \ngrid services, at any time.  Even if operational protection and control technologies, such as relay \nswitches, are used with co-located load and generation, the load still benefits from and utilizes grid \nservices when 1) the load and generator are both connected to the system, and 2) the load is \nconnected and the generator is disconnected from the system, even if the load is connected \nmomentarily before it trips.  For example, an RAS system operation that provides engineering and \ndesign practices to ensure reliability may fail, thrusting the full burden of the co-located load onto \nthe grid to continue operating if the co-located generation is offline for any reason.  The co-located \nload is relying on the grid for every moment it is connected to the transmission system, including \nwhen the system is standing by.  The grid must be ready to accommodate the full burden of the \nload irrespective of what that load is doing at any given moment and must be planned for \naccordingly.  Complete physical islanding from the grid is the only way to avoid taking any form \nof transmission service.17  Equally importantly, regardless of the load’s use of services, the entire \nco-location arrangement relies on the grid and grid facilities without which the generator could not \noperate, and the load-generation arrangement could not exist.   \n \nc. Ancillary or other wholesale services \n \ni. \nPlease explain whether and to what extent different configurations of co-\nlocation arrangements rely on or benefit from ancillary services or black \nstart services and, if so, provide specific details about the type of service \nand how the co-location arrangement relies on it.  To what extent are these \nbenefits distinct from the benefits that other Network Integration \nTransmission Service and Point-to-Point Transmission Service customers \nderive from ancillary services? \n  \nCo-located load uses the same essential reliability services, such as ancillary services, as all other \nload on the transmission and distribution systems and receives the same benefits from those \nservices as defined in Section 3 of Part I of the PJM Tariff and Schedules 2 through 6 of the PJM \nTariff.  If co-located load is interconnected to and synchronized with the transmission system, it \nimpacts the grid and uses essential reliability services delivered by the transmission system.  This \nfact is perhaps most readily apparent with load co-located with nuclear generation because nuclear \nunits typically cannot provide regulation service, nor can they provide black start.  Nuclear units \ncan provide reactive power support and operating reserves, but the co-located load arrangements \ndepend on a functioning grid that has more than the reactive power support and operating reserves \nprovided by the nuclear unit.  Because co-located load depends on essential reliability services and \ntransmission service, co-located load depends on the transmission and/or distribution system.  You \n \n17 This situation would be entirely up to the state to decide if and how to regulate since it would not be within \ninterstate commerce.  Fed. Power Comm’n v. Florida Power & Light Co., 404 U.S. 453, 466 (1972) (“The elusive \nnature of electrons renders experimental evidence that might draw the fine distinctions required by this case \npractically unobtainable.”)."},{"page":35,"startToken":12418,"endToken":12766,"text":"11\n \ncannot separate depending on those services, and accordingly cost allocation, from how those \nservices are delivered. \n \nii. \nPlease explain whether and to what extent co-location arrangements \nimpose costs related to ancillary services or black start services or increase \nthe costs for such services allocated to other parties and how those costs \ncould be approximated; \n \nCo-located load uses the same essential reliability services as all other load on the transmission \nand distribution system and receives the same benefits from those services.  To the extent that the \ncosts of those services are avoided by co-located load, other customers will necessarily be allocated \nall costs for these services.  \n \niii. \nPlease explain whether and to what extent co-location arrangements use, \nbenefit from, provide, or contribute to the need for transmission system \nservices in a manner that does not fit into a pre-existing category of \nancillary services or black start services, and, if so, should new categories \nof services be created to accommodate that use?  Alternatively, please \nexplain whether an alternative mechanism of cost allocation for pre-\nexisting ancillary services would be more appropriate; \n \nCo-located load uses and benefits both from the transmission system physically and from services \nprovided and delivered by that system just like all other load on the system.  Co-located load’s \nreliance on the grid for essential reliability services is constant, as long as it is interconnected to \nand synchronized with the grid.  These services are fundamental to maintaining reliable operation \nof the grid.  It is not appropriate to assign portions or segments of services to co-located load. \n \nThe existing approach of cost allocation to load is appropriate for co-located load.   \n \niv. \nWhat changes to rates, terms, and conditions of ancillary services, \nincluding ancillary services procured in PJM’s markets, are necessary for \ndifferent configurations of co-location arrangements to ensure that the \nTariff is consistent with cost causation principles and the beneficiary pays \nprinciple? \n \nChanges to these rules are not necessary.  If co-located load is designated as Network Load or \ntakes Point-to-Point Service, the relevant charges for essential reliability services already apply \nand those are consistent with cost causation principles."},{"page":36,"startToken":12766,"endToken":13203,"text":"12\n \nv. \nPlease explain how PJM should determine which co-located load \nconfigurations take ancillary services or black start services (i.e., whether \ngeneralized policies or tests, such as a multi-factor test, to be applied case-\nby-case may be appropriate), as well as the amount of such service (i.e., \nhow the service taken by co-located load compares to service taken by \nother types of load); \n \nAll co-located load arrangements that are interconnected to and synchronized with the PJM \ntransmission system or the LSE/EDC’s distribution system take and/or benefit from essential \nreliability services, such as black start services.  Co-located load, like all other load on the system, \nshould take Network Service or Point-to-Point Service.  The standard rules under the PJM Tariff \nwill apply and no separate determination will be necessary. \n \nd. Interconnection Procedures and Cost Allocation \n \ni. \nDoes the necessary study process adequately address potential impacts \ncaused by a co-location arrangement or is an additional study or new study \nprocess warranted, e.g., a system impact study or generator deactivation \nstudy?  PJM should provide the details regarding the geographic scope of \nthe existing necessary study process, what is studied, and how the results \nare reported, including what opportunities stakeholders, the interconnected \ntransmission owner, or the PJM IMM have to review the results, if any; \n \nIn the Show Cause Order, the Commission expressed concern “that the necessary study process \nmay not be fully capturing the transmission system impacts of co-locating load, which could result \nin such arrangements not paying the costs of network upgrades that would be caused by the co-\nlocation.”18  The necessary study process, together with other studies and analysis, which include \nthe individual TOs’ feasibility/engineering studies, are designed to ensure appropriate evaluation \nof, among other things, generator interconnections, modifications, and retirements and load \nadditions.  A necessary study itself evaluates the impact, if any, on the Transmission System, of \nplanned modifications to, as relevant here, a Generating Facility.19  With respect to load addition \nstudies, the Indicated TOs perform such studies to determine what, if any, new or upgraded system \nfacilities are necessary to reliably support the load interconnections based on the near-term and \nlonger-term ramp rates.  Studies must show that the transmission system can serve them.  With the \naddition of co-located load, the relevant studies are jointly performed by PJM and the individual \nTOs in the zones where the load is being interconnected.  These Commission-jurisdictional studies \nare compatible with retail load addition studies and can typically be conducted in a coordinated \n \n18 See Show Cause Order at P 79.  \n19 See PJM Tariff, Part IX, Subpart G, Form of Necessary Studies Agreement."},{"page":37,"startToken":13203,"endToken":13674,"text":"13\n \nmanner.20  Collectively, these existing individual processes are sufficient for studying new and \nmodifications to existing generating facilities and new load, inclusive of co-located load, being \nadded onto the system as Network Service or Point-to-Point Service customers.  A separate \ninterconnection study process for co-located load is not necessary or appropriate in the PJM \nRegion. \n \nii. \nPlease explain whether PJM’s necessary study process allows a co-\nlocation arrangement to demonstrate its capability to flexibly adjust its \nwithdrawals from or injections to the transmission system (e.g., by using \nsecondary backup generation or by curtailing on-site load), and reflect this \ncapability in the operating assumptions PJM considers when estimating \nthe co-location arrangement’s impacts on the transmission system?  If not, \nwould it be appropriate to establish a new or revised study process that \nallows for such a demonstration? \n \nThe PJM necessary study process does not include this “flexibility” analysis, nor should it.  \nWhether the end-use load and generation in a co-location arrangement has the capability to adjust \nits collective withdrawal or injection or the load has the ability to use secondary backup generator \nbehind the end-use customer’s retail meter may potentially reduce that load’s need for energy from \nits primary generation source, but it does not guarantee how the end-use load or the generation \nload will operate in real time.  We must plan the transmission system to serve the full co-located \nload amount both because we cannot be sure how it will behave operationally and because that \nload, independent of the association, has a right to receive retail service.  Outside of response to \nextreme operational conditions on the transmission system, the terms and conditions under which \nend-use load can choose or be required to be flexible in its use of energy is a matter of state, not \nfederal, jurisdiction.  However, flexibility of the load should be captured as part of the \nEDC’s/LSE’s inputs into PJM’s large load forecast where it is known, assured, and can be \nmodelled.  The Indicated TOs emphasize the importance of understanding the nature and durability \nof any load behavioral commitments.  In the absence of a state law or retail tariff allowing for a \nmore durable commitment, any contractual commitment by end-use load to interrupt its operations \nor its use of retail electric service will at best be limited to the current contracting party.   \n \niii. \nWhat changes to interconnection procedures and agreements may be \nnecessary to ensure that PJM identifies the reliability impact to the \ntransmission system of load co-locating with existing generation including \nthe need for dynamic response models?  \n \n20 The Indicated TOs note that while the necessary study process is useful for evaluating modifications at a \nGenerating Facility related to a co-location arrangement, load addition studies performed by local utilities are \nrequired to determine any necessary interconnection facilities and upgrades to reliably support the co-located load \ninterconnection."},{"page":38,"startToken":13674,"endToken":14136,"text":"14\n \n \nTo the extent that an existing generation interconnection is being modified to allow that \ninterconnection to be shared with end-use load, such a change would likely require amendments \nto the applicable interconnection service agreement acceptable to all parties if for no other reason \nthan to reflect equipment changes and necessary physical and operational changes to protect the \ntransmission system.  Moreover, the addition of load may require state specific agreements \nbetween EDCs/LSEs and load customers and are typically governed by the retail tariff in the \nabsence of customer-specific agreements.  PJM and FERC should confirm that all co-located load \nis Network Load unless alternative arrangements are made for Point-to-Point Service.  With that \nload being treated as Network or PTP load, existing procedures are adequate to protect the \nreliability of the system.  TOs utilize separate procedures to study load and generation \ninterconnections, including requesting specific modeling information.  Such analysis can result in \ncase-specific determinations.  Again, a separate or unified process interconnection process for co-\nlocated load is not necessary or appropriate in the PJM Region. \n \niv. \nTo what extent does a co-location arrangement raise potentially distinct \ncost-allocation issues relative to a deactivating generator that causes the \nneed for transmission upgrades?  What principles should the Commission \napply to allocate the costs of any transmission upgrades needed to mitigate \nthe impacts of co-locating load?  What steps should PJM take to ensure \nthese costs are transparent to all parties? \n \nPJM Tariff, Section V outlines the process for requesting and studying proposed generator \ndeactivations for potential reliability impacts.  There are no distinct cost-allocation issues \nregarding potential transmission upgrades because of a deactivating unit associated with a co-\nlocated load arrangement.  Under existing rules, if the generator changes its Interconnection \nService Agreement to enable it to operate in a co-located load arrangement, then any upgrades \nwould need to be paid for by the generator.  There are also no distinct reliability issues for the co-\nlocated generating unit that PJM would not already study. \n \nThe addition of new end-use load is regulated by state law in contrast to the broad Commission \njurisdiction over wholesale sales and generators participating in interstate commerce.  However, \nthe costs of transmission upgrades required to serve co-located end-use load, like the costs of \ntransmission upgrades for all end-use load customers, are recovered through transmission rates.  \nThe addition of load, including co-located load, benefits other customers because the shared \nembedded costs of the grid are paid by all customers, so that new load additions spread those costs \nmore broadly when that new load takes service as a Network or PTP customer.  If and to the extent \nthere is a need for customer-specific facilities for a particular customer, issues associated with such \nfacilities, including an assessment of the jurisdiction over the issue, are best addressed in individual"},{"page":39,"startToken":14136,"endToken":14553,"text":"15\n \nproceedings.  It would be inappropriate for the Commission to attempt to devise some general rule \napplicable to service to end-use customers. \n \nThe Indicated TOs believe that co-located load should be in front of the meter and treated as \nNetwork Load.  If the Commission (or state) allows behind-the-meter arrangements and then the \ngenerator the load is co-located with retires, the load can potentially “appear” on the PJM \ntransmission system very quickly.  This could result in reliability impacts to the PJM transmission \nsystem. \n \nv. \nAre changes needed to how PJM allocates the costs of any transmission \nupgrades needed to mitigate the transmission system impacts of co-\nlocating load, if any, including whether the costs of those upgrades can \never be allocated to a party other than the co-located generator, co-located \nload, and/or co-location arrangement? \n \nThe current PJM Tariff correctly apportions the costs of the transmission among those who use \nand benefit from it.  The costs of transmission upgrades as a result of new end-use load additions \nare shared among transmission customers.  There are no special FERC-jurisdictional rules for the \nspecific end-use load that is co-located.  If and to the extent there is a need for customer specific \nfacilities for a particular customer, issues associated with such facilities, including an assessment \nof the jurisdiction over the issue, are best addressed in individual proceedings.  It would be \ninappropriate for the Commission to attempt to devise some general rule applicable to service to \nend-use customers. \n \nHaving said this, the Indicated TOs agree with the Commission that as this co-location space \ncontinues to rapidly evolve, the focus remains to ensure that all Commission-jurisdictional rates \nand charges “reflect to some degree the costs actually caused by the customer who must pay for \nthem,” and that costs are allocated in a manner that is at least roughly commensurate with the \nbenefits that entity receives. \n \nvi. \nAre changes to the pro forma interconnection-related agreements \nnecessary to accommodate the addition of co-located load to existing \ngeneration? \n \nAs noted in PJM’s Guidance Document and as summarized in a response above, existing \ninterconnection agreements address the generation interconnection and the injection of energy onto \nthe grid.  These agreements would need to be amended with the consent of all parties to the \nagreement if the configuration is altered to address site specific peculiarities, which could include \nload at the same location.  The relevant pro forma agreements were not designed for large load \ninterconnections, and service to such load is a matter of state, not federal, jurisdiction.  The relevant"},{"page":40,"startToken":14553,"endToken":14914,"text":"16\n \npro forma agreements should not be altered for the specific purpose of accommodating these \nconfigurations which, as both project proponents and the Commission have explained, are likely \nto vary significantly from configuration to configuration.  \n \nvii. \nPlease explain whether changes to interconnection procedures and \nagreements are necessary to accommodate new generation interconnecting \nwith co-located load, including whether the existing queue process is \nsufficient for such arrangements?  \n \nThe existing queue process is designed to study the interconnection of generation and is sufficient \nfor that process.  All load and, separately, all generation, that wants to connect to the grid needs to \ngo through the established study processes to ensure the reliability of the grid, given that the \ngeneration and load can operate independently despite co-location. \n   \nviii. \nPlease explain whether or not it would be appropriate to establish an \ninterconnection study process outside of PJM’s interconnection queue \nprocess for newly interconnecting co-location arrangements that do not \nexchange power with the transmission system and do not require network \nupgrades? \n \nOnly truly islanded systems where load does not connect to, take service from, or rely on the \ntransmission and distribution system in any way would meet the requirement that they “do not \nexchange power with the transmission system and do not require network upgrades.”  All other \narrangements require study and potential upgrades, which are already performed by the local \nEDCs/LSEs/TOs, as described above. \n \nIf a customer has the option, capability, or is requesting such capability to serve their full load \nfrom the transmission system, then the full load amount should be included when studying the \ninterconnecting co-location arrangement.  Having the ability to temporarily or intermittently \noperate does not mean that the co-location arrangement is not “exchanging power” for purpose of \nthe PJM interconnection study process. \n \nix. \nA generator with a co-located load that is not a party to a transmission \nservice agreement is arguably distinguishable from other generators.  To \nthe extent co-located arrangements create costs, or benefit from bulk \npower system services, but the generator and load are not exposed to these \ncosts because of their contractual relationship, should PJM modify the \nTariff and related agreements to allocate those costs to the generator \ndirectly?"},{"page":41,"startToken":14914,"endToken":15356,"text":"17\n \nGeneration and end-use load cannot enter into contractual arrangements that exempt the load from \nits obligations under the PJM Tariff to take service as a Network or PTP customer and to pay the \ncosts that come with the service that it receives.  Those are requirements of the applicable \ntransmission rates.  There is no need to modify the PJM Tariff to change the incidence of \ntransmission service and facilities costs from load to generation.   \n \ne. PJM Capacity Market, Reliability, and Resource Adequacy \n \ni. \nWhat changes to PJM’s capacity market rules are necessary to ensure that \nthe Tariff specifies how co-located generation and/or load participates in \nthe capacity market in a way that reflects the potentially unique physical \nand operational characteristics of the co-location arrangement (e.g., the \npresence of secondary backup generation, the capability to curtail on-site \nload or other operational flexibilities, among others) and is otherwise just, \nreasonable, and not unduly discriminatory or preferential? \n \nTreating co-located end-use load like all other end-use load on the system by requiring it to take \nNetwork Service or Point-to-Point Service avoids the need to modify the capacity market rules \nand ensures that those rules are not unduly discriminatory or preferential against any customer.  \nTo be clear, and as discussed above, the PJM RAA requires all LSEs in PJM to subject \nthemselves to those requirements.  Of course, a generator cannot both dedicate its capacity to \ndirectly serve co-located end-use load and separately offer that same capacity into the capacity \nmarket.  However, the existing rules already accommodate bilateral capacity transactions \nbetween specific generating units and load customers.  Those rules work for co-located load and \nits relationship to the co-located generator as long as the load is treated as a Network Customer.  \nThis straightforward approach to handling co-located load with regard to the capacity market has \nthe considerable benefit of not requiring changes to PJM’s capacity market.  The broader \ncircumstances and challenges currently facing PJM’s capacity market would not benefit from \nfurther intervention and reform due to co-located load arrangements at a time when there are \nconsiderable resource adequacy concerns in the PJM footprint and there are efforts being made \nto advance certainty in the capacity market design.  \n \nii. \nWhat Tariff change or changes to the interconnection service agreement \nare necessary to ensure that PJM and the interconnected transmission \nowner have sufficient visibility into the co-located load configuration?  \n \nIn general, changes to the applicable pro forma service agreements are not appropriate.  As long \nas co-located load is treated like all other load on the system, including as to metering and telemetry, \nand is a retail customer of the relevant distribution utility, the relevant state retail tariffs provide"},{"page":42,"startToken":15356,"endToken":15765,"text":"18\n \nthe appropriate visibility into the co-located load configuration, just as they do for any other load \ninterconnection. \n \nInterconnection agreements should include appropriate metering requirements. As stated above, \nco-located loads served from the transmission system under PJM Tariff, Part III, must have \nseparate metering for load consumption and generator output. \n \niii. \nPlease explain whether the existing Tariff rules are sufficient to ensure \nresource adequacy if increasing numbers of large existing generators \nchoose to co-locate with load; \n \nAdding load located at a generator site to the system, like adding any other new load, introduces \nchallenges to the existing resource adequacy problem.  But as with other such load, existing PJM \nTariff rules should be sufficient to study the impacts as long as co-located load is recognized as \nthe load addition that it is, comparable to other new load additions to the system.  Co-located load \ndesignated as Network Load will be included in the load forecasts and will receive appropriate \ntreatment in the capacity market auctions, as discussed above. \n \niv. \nWhat deactivation or interconnection modification studies should PJM \nundertake to ensure resource adequacy and/or protect reliability should an \nexisting generator seek to enter into a co-location arrangement?  If PJM \nfinds that the co-location would cause reliability standards violations, what \nremediation techniques would be appropriate (e.g., reliability must-run \ncontracts, delaying the co-location arrangement until the reliability \nviolations are addressed, etc.)?  \n \nCo-located end-use load should be studied under the relevant state jurisdictional process for new \nload additions and PJM’s role should be limited to the standard transmission planning process for \nall new load additions.  Additionally, the loss of capacity from an existing generator seeking to \nenter into a co-location arrangement should be studied by PJM.  Because the federal role in end-\nuse load additions is limited, PJM and the Commission should not create processes in the PJM \nTariff that would interfere with state jurisdiction.  However, all load, and separately, all generation, \nthat want to connect to the grid should go through the established PJM study processes to ensure \nthe reliability of the grid.  As stated above, if an existing generator proposes modifications to \nenable it to operate in a co-located arrangement, then any transmission upgrades related to the \ngenerator modifications would need to be paid by that generator. \n \nv. \nWhat changes are necessary, if any, to other PJM planning processes to \nbetter plan for and address the resource adequacy and reliability impacts \nof co-location arrangements, including, for example, whether or not the"},{"page":43,"startToken":15765,"endToken":16136,"text":"19\n \nfrequency of such processes might be changed?  Similarly, should PJM \nconsider changes to load forecasting methods, informational postings, or \nthe reserve margin study process to better plan for and address the \nresource adequacy and reliability impacts of co-location arrangements?   \n \nAll load additions create new demands for energy regardless of their location.  The resource \nadequacy and reliability challenges exist regardless of whether end-use load is connected to the \ngrid at a generator site or elsewhere, and regardless of whether the point of connection lies “behind” \nor “in front of” the generator’s meter.  Changes to the planning and load forecasting processes \nshould not be needed solely to address end-use load that is located at a generator as long as co-\nlocated load is treated like all other load on the system and takes either Network Service or Point-\nto-Point Service. \n \nvi. \nUnder what circumstances can PJM direct the operators of co-location \narrangements to shed such load if deemed necessary to preserve system \nreliability during a declared emergency? \n \nIf treated as Network Load, co-located end-use load can only be shed by PJM when required under \nthe relevant NERC and PJM standards as documented in PJM’s Manual 13 on Emergency \nOperations.  The general terms and conditions governing service to co-located end-use load are \nregulated by states, which are free to offer optional or mandatory interruptible service rates.   \n \nWe note that failure to meter the co-located load will lead to anomalous results.  For example, if \nthe generator trips offline without disconnecting from the transmission system, the unmetered load \n“appears” on the system and draws power from the grid.  In an extreme case, this can create a \nsystem emergency that requires load drop—which must come from other network load that did \nnot cause the emergency. \n \nf. Other  \ni. \nAre any changes to PJM’s energy or ancillary services market rules \nnecessary to address co-location arrangements? \n \nOther changes are not necessary.  If co-located end-use load is treated like all other end-use load \non the system, served through either Network Service or Point-to-Point Service, there is no gap in \nthe existing rules.   \n \nii. \nPlease discuss whether back-up service can provide benefits to customers \nor otherwise help minimize system costs, including with specific examples \nor best practices, if possible;"},{"page":44,"startToken":16136,"endToken":16561,"text":"20\n \nIn general, having reliable backup generation can benefit any end-use load by providing alternative \nsources of power in times of system emergency.  That capability can also benefit other end-use \nload customers if it can and is used for their benefit as well.  However, the presence of on-site \nbackup generation does not exempt load from paying the costs of transmission service, because it \nstill benefits from the transmission system.  It does not matter whether that load is co-located with \ngeneration.  Notably, nuclear units must be interconnected with the transmission grid to operate, \nso any backup service provided by a nuclear unit is dependent on continued grid operation to \nfunction at all. \n \niii. \nParties may also choose to address how co-location arrangements may \nprovide benefits, including potentially reducing required transmission \nupgrades to interconnect large loads, reducing congestion, or providing \noperational flexibility during system peaks or emergencies?   \n \nA study is necessary to determine, on a case-by-case basis, whether co-located load generally \nwould result in a reduction of required transmission upgrades, reduction in congestion, or provide \noperational flexibility during system peaks or emergencies.  Thus, although the Indicated TOs \nrecognize that there could be some instances in which co-location of load, like other load, may \nprovide benefits to the transmission system, that cannot be determined until after full studies are \ncompleted.   \n \niv. \nParties may also address whether, and if so, how, the Tariff should be \nmodified to best accommodate or encourage co-location arrangements to \nbe constructed in such a way as to minimize total system costs or \notherwise provide certain benefits, including protections for existing \ncustomers and allocation of costs consistent with the cost-causation \nprinciple; \n \nNo federal tariff changes are needed to promote co-location because the current PJM Tariff and \nstate regulatory regimes can and do accommodate reliable and economic co-located configurations \nunder existing rules.  If there is a hurdle to locating end-use load at generation sites, that hurdle is \nnot the lack of a rate discount, but of confusion over the applicability of the established tariffs.  \nThe best way to ensure cost-effective co-location is to maintain consistent rules: treat co-located \nload as any other load on the system.  The Indicated TOs also note that states may choose to \npromote co-location arrangements through, for example, appropriate distribution tariffs or tax \nincentives—whether the states choose to do so is not within FERC’s jurisdiction or control.   \n \nv. \nWhat Tariff provisions, if any, are necessary to ensure clarity regarding \nthe aspects of service to co-located load and generation facilities that may \nbe administered through the Tariff versus state jurisdictional retail tariffs?"},{"page":45,"startToken":16561,"endToken":16998,"text":"21\n \n \nConsistent with existing precedent, the Commission might clarify that generator interconnection \nagreements do not themselves provide for or confer the right to serve end-use retail load or the \nright of new load to take retail service at a specific point or under particular rates; instead, such \nservices are regulated under state law.  Potential customers could benefit from clarification by the \nCommission that co-located load is Network Load and must be included in the load of either a \nNetwork Customer or arranged for Point-to-Point Service.  Alternatively, the Indicated TOs are \nopen to working with PJM and other stakeholders to incorporate appropriate PJM Tariff revisions \nto expressly specify that co-located load must be served by the existing forms of transmission \nservice—Network Service or Point-to-Point Service.   \n \nvi. \nWe also encourage parties to address any national security implications \nassociated with co-location arrangements, including with respect to the \nspecific issues discussed in this show cause order, and what actions, if \nany, the Commission should take in response. \n \nAllowing co-location arrangements to move forward rapidly and without regulatory ambiguity is \nthe best way to achieve the national security goals of this Commission and this administration.  \nThe most straightforward way to accomplish that goal is simply to recognize that co-located load \nis Network Load like all other load on the system and should pay for Network Service like all other \ncustomers.  A clear statement from this Commission that the existing rules work, and that co-\nlocated load can be served under existing rules is the fastest path to data center interconnections \nneeded to win the artificial intelligence (AI) race.  In contrast, development of new forms of service, \nand efforts to mesh those new forms of service with the existing rules, will certainly get bogged \ndown in extended litigation that will impede efforts to develop AI. \n \nAny delays associated with interconnection of co-located load experienced thus far have not been \nbecause the rates do not provide for artificial exemption of the arrangements from transmission \nrates, but because of efforts to dispute the applicability of those rates.  Importantly, this does not \npreclude PJM and the PJM TOs from considering and pursuing beneficial enhancements as the \nbusiness areas surrounding co-location continue to evolve.  As previously noted, the Indicated TOs \nare attempting to consider potential beneficial enhancements collectively and with PJM, consistent \nwith existing rights and responsibilities.    \n \nvii. \nFinally, for generation units paid for originally by consumers in base rates \nprior to restructuring, is it fair and/or just and reasonable if these units are \ntaken out of the system’s supply stack and devoted exclusively to serving \nco-location arrangements with one or a few large customers?"},{"page":46,"startToken":16998,"endToken":17160,"text":"22\n \nThere are two issues here: generation costs and transmission costs.  In general, the continued \nobligation, if any, of generation to serve classes of end-use customers who pay for that generation \nis a matter of state jurisdiction and concern.  Transmission costs are certainly a matter of FERC \nconcern.  The addition of end-use load, including co-located load, at established cost-based rates \ntypically benefits other customers with respect to transmission costs, because the shared embedded \ncosts of the grid are paid by all customers, so that new load additions spread those costs more \nbroadly.  Treating co-located end-use load like all other load additions by requiring them to take \neither Network Service or Point-to-Point Service ensures that other customers are protected.  In \ncontrast, creating a new class of service where transmission costs are not paid, particularly one \nthat exempts those customers for either paying for services or simply for reliance on the shared \nsystem, does not ensure equitable treatment of other customers on the system."},{"page":47,"startToken":17160,"endToken":17206,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list in the above captioned dockets. \nDated at Chicago, IL this 24th day of March, 2025. \n \n/s/ Geneva Kennedy  \nGeneva Kennedy  \nExelon Corporation"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":5,"startToken":0,"endToken":627},{"p":3,"at":5,"title":"I. EXECUTIVE SUMMARY","method":"printed heading","endPage":6,"endAt":952,"startToken":627,"endToken":1819},{"p":6,"at":952,"title":"II. BACKGROUND","method":"printed heading","endPage":6,"endAt":969,"startToken":1819,"endToken":1821},{"p":6,"at":969,"title":"A. Procedural Overview","method":"printed heading","endPage":7,"endAt":759,"startToken":1821,"endToken":2082},{"p":7,"at":759,"title":"B. Co-location of Load","method":"printed heading","endPage":10,"endAt":6,"startToken":2082,"endToken":3210},{"p":10,"at":6,"title":"III. DISCUSSION","method":"printed heading","endPage":10,"endAt":24,"startToken":3210,"endToken":3212},{"p":10,"at":24,"title":"A. Classification of Co-located Load as Network Load Is Just and Reasonable.","method":"printed heading","endPage":12,"endAt":637,"startToken":3212,"endToken":4159},{"p":12,"at":637,"title":"B. Co-Located Load Benefits From Essential Services Provided Using the Grid.","method":"printed heading","endPage":14,"endAt":1214,"startToken":4159,"endToken":4932},{"p":14,"at":1214,"title":"C. All Load, Including Co-located Load, Is Used to Plan the Transmission","method":"printed heading","endPage":17,"endAt":832,"startToken":4932,"endToken":5846},{"p":17,"at":832,"title":"D. Creating A New, Non-Paying Category of Service Under the PJM Tariff","method":"printed heading","endPage":20,"endAt":314,"startToken":5846,"endToken":6910},{"p":20,"at":314,"title":"IV. CONCLUSION","method":"printed heading","endPage":24,"endAt":0,"startToken":6910,"endToken":7658},{"p":24,"at":0,"title":"ATTACHMENT A","method":"printed heading","endPage":47,"endAt":0,"startToken":7658,"endToken":17160},{"p":47,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":47,"endAt":295,"startToken":17160,"endToken":17206}]}