{"document":{"slug":"rec-20250324-5299","title":"Response of Public Service Electric and Gas Company to Show Cause Order issued on 02/20/2025","issued":"2025-03-24","accession":"20250324-5299","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Public Service Electric and Gas Company","kind":"filing","file":"sources/filings/text/20250324-5299_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250324-5299","tier":"record","sha256":"03849587ef1a1cfe2934e606a8c1a435fe01a042b1c0f23104c91f7c0a9cc964","pages":26,"tokens":6854,"emptyPages":[],"textThemes":["colo","cost"]},"pages":[{"page":1,"startToken":0,"endToken":226,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n) \n \nPJM Interconnection, LLC et al. \n \n) \n) \nDocket Nos. EL25-49 \nLarge Loads Co-Located at Generating \nFacilities \n) \n) \nAD24-11 \nConstellation Energy Generation, LLC \nv. \nPJM Interconnection, L.L.C. \n) \n) \n) \nEL25-20 \n(Consolidated) \n \n) \n \n \nRESPONSE OF  \nPUBLIC SERVICE ELECTRIC AND GAS COMPANY  \nTO THE ORDER TO SHOW CAUSE  \n \nData centers have vast importance for economic development and national security \nin the United States.  To foster data center development and to maintain U.S. leadership in \nthis transformative industry, the Commission should act expeditiously to reduce any \nregulatory barriers that may hinder their development.  As relevant to this proceeding, data \ncenters should have the option to select a configuration that best fits their particular \ncircumstances and needs – whether this is in front of the meter or a co-location \narrangement.  While there has been significant litigation regarding co-location \narrangements in recent months, the fact is that co-locating load with generation is not \nsomething new, but has been available in PJM for over two decades based on the \nCommission’s recognition that locating load in close proximity to generation resources \nwill reduce system costs and benefit customers.  Within the Public Service Electric and \nGas Company (“PSE&G”) service territory and elsewhere in PJM, there are numerous \ncustomers, such as universities, industrial customers, pharmaceutical companies, and \nrooftop solar customers, that have behind the meter generation (“BTMG”) resources to"},{"page":2,"startToken":226,"endToken":572,"text":"2 \nmeet their load requirements.  Because such BTMG customers have reduced their use of \nthe transmission system, under the PJM Tariff, they have been allocated costs based on \ntheir actual use of the system consistent with cost causation principles.  There is no \njustification to treat behind the meter load any differently than BTMG, and the \nCommission should ensure that there is no undue discrimination in the treatment of co-\nlocated arrangements.  Both should pay (and in the case of BTMG customers continue to \npay) based only on actual usage of the transmission system.   \nPSE&G submits this Response to the Commission’s February 20, 2025 Order \nInstituting Proceeding under Section 206 of the Federal Power Act and Consolidating with \nOther Proceedings (the “Show Cause Order”).1  In our Response,2 PSE&G proposes a \nprinciple-based approach to address the Commission’s issues and concerns and suggest a \npath forward to obtain timely and needed clarity with respect to co-located load rules that \n(i) aligns with the Commission’s cost causation principles; (ii) does not adversely impact \nexisting BTMG customers on PSE&G’s system and across the various PJM Transmission \nOwner systems in PJM; and (iii) preserves co-location as a viable option to support data \ncenter development in New Jersey and elsewhere in PJM, appropriately recognizing the \nbenefits of locating data centers close to generation – whether behind the meter or in front \nof the meter – to reduce transmission system usage and the need for new transmission \ninfrastructure, the costs of which are ultimately borne by customers.   \n \n1 PJM Interconnection, L.L.C., et al., 190 FERC ¶ 61,115 (2025). \n2 PSE&G is not responding to all of the questions posed in the Show Cause Order.  Instead, as \ndirected by the Commission, PSE&G is principally responding to issues relating to transmission \ncost allocation and transmission rate design, which fall within the filing rights of the PJM \nTransmission Owners under the Consolidated Transmission Operating Agreement (CTOA).  See, \ne.g., CTOA Section 7.3 (provisions regarding PJM Transmission Owners’ filing rights over \ntransmission rates and rate design under FPA Section 205)."},{"page":3,"startToken":572,"endToken":870,"text":"3 \nIn the Show Cause Order, the Commission established an accelerated schedule, \nstating that it intends to issue a decision within three months.  Just last week, Chairman \nMark C. Christie reaffirmed the Commission’s commitment to an expeditious resolution \nof this proceeding stating:  “we want to act quickly on this issue,” and that the \nCommission intends to “conduct and complete this important proceeding expeditiously, \nso we can provide clarity and certainty to all, from consumers to investors to load-\nserving utilities and independent generators.”3  PSE&G respectfully urges the \nCommission to effectuate a prompt resolution of this co-location proceeding, as \nexpeditiously arriving at clear co-location rules is essential to allow states like New Jersey \nand data center customers to move forward with their development plans. \nI. \nEXECUTIVE SUMMARY  \nOver the past nine months, there has been significant controversy and litigation \nbefore the Commission relating to co-location load arrangements.  The Commission, \nhowever, recognized that co-location load arrangements are not new but are “becoming \nincreasingly common in PJM.”4  The principal controversy before the Commission boils \ndown to a basic transmission ratemaking question – specifically do co-located load \narrangements use or benefit from the transmission system, and if so, what level of \n \n3 See, e.g., March 18, 2025 Letter from Office of the Chairman, Mark C. Christie, responding to \nOctober 2, 2024 Letter from Governor Josh Shapiro, Docket Nos. EL25-49, EL24-149, ER24-\n2172, and ER24-2888 et al. (emphasis added).  In a March 18, 2025 Letter, Chairman Christie \nmade a similar commitment in response to an October 31, 2024 letter from Governor Glenn \nYoungkin in Docket No. AD24-11.    \n4 Show Cause Order at P 3.  See also Id. P 65 (stating that “the surge of interest in co-location \narrangements in PJM has put before the Commission several significant and novel issues.”)."},{"page":4,"startToken":870,"endToken":1178,"text":"4 \ntransmission or ancillary charges should be imposed to comport with the Federal Power \nAct’s “just and reasonable” standard and cost causation principles. \nThere are now six dockets pending before the Commission relating to co-located \nload.  In November 2024, the Commission rejected one FPA Section 205 filing that sets \nforth a proposal under which the fully isolated co-located load would have paid no \ntransmission or ancillary charges.5  In February 2025, the Commission rejected another \nFPA Section 205 filing proposing that all located load arrangements pay full network \nintegration transmission service (“NITS”) and ancillary service charges on a gross load \nbasis.6  It appears that the Commission was not satisfied that neither of the two Section \n205 filings (representing opposite ends of the transmission pricing spectrum) passed \nmuster under the just and reasonable standard and cost causation principles.  In issuing the \nShow Cause Order, the Commission is effectively sending PJM and the PJM Transmission \nOwners back to the “drawing board” to develop a clear solution that reflects the co-located \nload’s use of the transmission system based on the specific configuration employed and to \ndevelop appropriate charges reflecting the degree of usage.  In so doing, the Commission \nis not acting on a blank slate.  Instead, informed by the extensive briefings and the robust \nrecords in the various dockets, the Commission provided certain findings and \nobservations, as discussed herein, that should provide guideposts for this proceeding.  \nSignificantly, the Commission also recognized that any remedy or replacement rate \nadopted in this proceeding could impact existing customers throughout PJM with BTMG \n \n5 PJM Interconnection, L.L.C., 189 FERC ¶ 61,078 (2024) (rejecting the amended ISA for failing \nto meet the requisite burden of proof).   \n6 Atlantic City Electric Co., et al., 190 FERC ¶ 61,109 (2025) (rejecting the Section 205 filings for \nexceeding the filing entities’ filing rights under the CTOA)."},{"page":5,"startToken":1178,"endToken":1523,"text":"5 \nand has asked for ways to address this problem.  Certain key principles should inform the \nnext steps in this proceeding. \nFirst, the Show Cause Order appropriately recognizes that (i) there are different \nco-location load configurations available; (ii) their use or impact on the power grid is \ndifferent; and (iii) any transmission charges should reflect actual use of the grid.7  \nAccordingly, it logically follows that transmission charges, if imposed, must be based on \nusage of the power grid and should not be imposed on a blanket, one-size-fits-all basis.  \nTo comply with cost causation principles, which courts have described as adding “flesh to \nthe bare statutory bones of the just and reasonable requirement” under the Federal Power \nAct,8  any charges imposed must reflect the use or benefit of the specific co-located load \narrangement.  A transmission pricing methodology that reflects cost causation would also \nprovide the appropriate incentives for data centers to locate in close proximity to \ngeneration resources to reduce transmission costs.   \nSecond, from a technical, engineering perspective, there is no material difference \nbetween co-located loads and other types of arrangements where load and generation share \nthe same point of interconnection, such as BTMG.9  As discussed in Section III.B of this \nResponse and illustrated in Figure 1, co-located load arrangements and BTMG \narrangements result in the same reduced use or impact on the transmission grid.  \n \n7 See, e.g., Show Cause Order at P 77 (questioning whether Network Integration Transmission \nService is the appropriate transmission service for all co-location arrangements or that such service \nwould be consistent with cost causation principle.). \n8 See Old Dominion Electric Cooperative v. FERC, et al., 898 F.3d 1254, 1255 (D.C. Cir. 2018) \n(citing K N Energy v. FERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992)). \n9 See Show Cause Order, P 88, Section General, Question (iv) (asking whether “co-located loads \nare similar to or disparate from other types of arrangements where load and generation share the \nsame point of interconnection, such as Behind the Meter Generation (BTMG) as defined in PJM’s \nTariff.”)."},{"page":6,"startToken":1523,"endToken":1824,"text":"6 \nAccordingly, in imposing transmission charges, if any, that would apply to co-located \nloads, the Commission should be mindful that there are many existing customers \nthroughout PSE&G’s service territory as well as across the PJM footprint who have \nBTMG to meet a portion of their load requirements and have been allowed to net their \nBTMG against their network load for purposes of transmission cost allocation for more \nthan twenty years.  The Commission should allow existing BTMG customers to continue \nto net and should take no action that would disadvantage these existing customers.   \nAt the same time, however, to comply with the requirement under the Federal \nPower Act that rates may not be “unjust and unreasonable or unduly discriminatory or \npreferential,”10 the Commission should treat behind the meter load customers and BTMG \ncustomers in the same manner.  One path forward is to allow BTM load customers to net \nso that they only pay for what they use, just as BTMG customers are allowed to net.  \nApplying a transmission pricing approach that ignores actual use or impact on the \ntransmission system would violate cost causation principles and treat these two classes of \ncustomers differently, resulting in harm to both classes of customers. \nThird, both the Commission and the states have recognized that data centers are \nvital to the U.S. economy and national security.  To maintain US leadership in this critical \nindustry, regulatory flexibility is needed to encourage and keep data center development in \nthe United States.  The Commission’s decision in this proceeding is an important one, and \nthe Commission should avoid picking sides with respect to co-located configurations vs. \nfront of the meter arrangements.  In many instances, as noted, co-location – and the \nassociated geographic proximity between the data center and the generator in this \n \n10 18 U.S.C. 824e."},{"page":7,"startToken":1824,"endToken":2079,"text":"7 \narrangement – will reduce the need for new transmission infrastructure, resulting in \naffordability benefits for customers.  Co-location represents an efficient use of the \ntransmission system by reducing the need for upgrades, and the Commission should not \nimpose policies that discourage this option. \nII. \nBACKGROUND \nA. \nDescription of PSE&G  \nPSE&G is a regulated electric and gas utility and owns 1,600 circuit miles of \nelectric transmission lines within the PJM region.  PSE&G also has 2.4 million electric \ncustomers in its franchised service territory and an obligation to reliably serve those \ncustomers.  Many customers on the PSE&G system are large load customers, such as \nuniversities, government agencies, manufacturers, and pharmaceutical companies, who \nrely on solar, cogeneration, reciprocating engine, gas turbine generation, combined heat \nand power (“CHP”), and other types of generation resources on a behind the meter basis to \nmeet all or some of their power needs.  In fact, according to the New Jersey Board of \nPublic Utilities’ (“NJBPU”) Office of Clean Energy, there are currently over 200,000 \nbehind the meter solar projects in New Jersey.11  Of this number, there are approximately \n90,000 behind-the-meter solar installations in PSE&G’s service territory.  For 23 \nconsecutive years, PSE&G has won reliability awards in the Mid-Atlantic region and has a \nproven record of providing reliable and affordable service to customers.12 \n \n11 https://njcleanenergy.com/renewable-energy/project-activity-reports/project-activity-\nreports. \n \n12 PSE&G has an affiliate that has an ownership interest in approximately 3,800 MW of reliable, \nbaseload carbon-free nuclear generation."},{"page":8,"startToken":2079,"endToken":2389,"text":"8 \nB. \nThe Show Cause Order  \nThe Show Cause Order found based on the records of both the technical \nconference and the Constellation complaint proceeding, the existing PJM Tariff “appears \nto be unjust and unreasonable or unduly discriminatory or preferential because it does not \ncontain provisions addressing with sufficient clarity or consistency the rates, terms, and \nconditions that apply to co-location arrangements.”13  The Commission directed PJM and \nthe PJM Transmission to respond to a number of issues and concerns raised in the Show \nCause Order.  \nThroughout the Show Cause Order, the Commission pointed out that there are \ndifferent co-location arrangements that use or impact the transmission system in different \nways.  The Commission provided two examples of co-location arrangements: (1) a \nnetwork load that co-locates with a generator that is not a grid resource “that either serves \nthe load as an off-grid back-up or that reduces the Network Load’s consumption during \npeak hours,” and (2) a fully isolated co-located load configuration.14  The Commission \nthen stressed the importance of determining “which wholesale services, if any, would be \nnecessary for that arrangement, and the appropriate charges for those services.”15  In \nthis respect, the Commission recognized that existing customers with onsite or BTMG \nmay be affected and asked parties to explain how “co-located loads are similar to or \ndisparate from other types of arrangements where load and generation share the same \n \n13 Show Cause Order at PP 2, 74, 78.  See also Show Cause Order at P 3 (adopting PJM’s \ndefinition of co-located load “as a configuration through which end-use customer load is \nphysically connected to the facilities of an existing or planned generation unit.”   \n14 Show Cause Order at P 76.     \n15 Show Cause Order at P 74 (emphasis added).  See also Show Cause Order at P 76 (stating that \ndifferent configurations will have different impacts on the transmission system)."},{"page":9,"startToken":2389,"endToken":2682,"text":"9 \npoint of interconnection (such as Behind the Meter Generation as defined in the PJM \nTariff or non-retail behind the meter generation) and should consider how any proposed \nreplacement rate would interact with these other arrangements.”16   \nIII. \nRESPONSE  \nA. \nThe Commission Recognizes The Variety of Co-Located \nConfigurations And Should Establish Transmission and Ancillary \nService Charges For Co-Located Customers Based On Actual Use \nConsistent With Cost Causation Principles17  \nIn the Show Cause Order, the Commission found that the current PJM Tariff does \nnot have a “process for determining what transmission service different co-located \nconfigurations must take, including what costs, if any, should be allocated to co-location \narrangements.”18  Importantly, throughout the Show Cause Order, Commission repeatedly \nemphasized that there are “various configurations” available for co-location load \narrangements and importantly, depending upon the specific co-location arrangements \nemployed, they are likely to use or benefit from the transmission system in different ways \ndepending on how it is configured and moreover, those configurations will themselves \nlikely have different impacts on the transmission system.”19  For example, the \nCommission pointed out that, under its regulations, “transmission service” is defined to \ninclude a variety of transmission products, such as “network, point-to-point service, \n \n16 Show Cause at P 88, Section a (General) Question iv. The Commission also explained that \nunlike the technical conference in Docket No. AD24-11, which focused on large co-located loads, \nin the Show Cause Order, the Commission did “not similarly limit this proceeding to co-located \nloads of a certain size.”  Id. at P 3, n.5.   \n17 This section responds to the Commission’s briefing questions set forth at P 88, Section b \n(Transmission Service, Questions (i), (ii) and Section c (Ancillary Services), Questions (i), (iv).  \n18 Show Cause at P 78. \n19 Id. at P 74."},{"page":10,"startToken":2682,"endToken":2942,"text":"10 \nancillary service, other methods of electric transmission, or the interconnection with \njurisdictional transmission facilities.”20  Importantly, the Commission stressed that \ndifferent co-location arrangements are likely to use or benefit from the transmission \nsystem differently, stating as follows:  \nThe record demonstrates that different co-location arrangements are \nlikely to use or benefit from the transmission system in different ways \ndepending on how they are configured and, moreover, that those \ndifferent configurations will themselves likely have different impacts on \nthe transmission system.  For example, Network Load may co-locate with \na generator that is not a grid resource and that either serves the load as an \noff-grid backup or that reduces the Network Load’s consumption during \npeak hours.21 \n \nIt is telling that the Commission acknowledged that while PJM’s preference is that “large \nloads be in front of the meter and designated as PJM Network Load,” the Commission \nstated that the PJM Tariff does not appear to require this service.22  Moreover, the \nCommission expressed skepticism that this is the appropriate type of transmission service \nthat should be required of all co-located configurations, stating: “there is no clear record \nbefore us that Network Integration Transmission Service is the appropriate transmission \nservice for all co-location arrangements or that such service would be consistent with the \ncost causation principle (i.e., that Network Integration Transmission Service \nappropriately aligns costs and benefits in a manner that is roughly commensurate) for \nsuch arrangements.”23   \n \n20 Id. at P 76. \n21 Id. (Emphasis added). \n22 Id. at P 77. \n23 Show Cause Order at P 78 (emphasis added)."},{"page":11,"startToken":2942,"endToken":3237,"text":"11 \n \nThe Show Cause Order’s findings and observations align with the technical \nrealities associated with various co-location arrangements.  For example, the data center \nload could be structured on a front of the meter basis with the co-located generator \nproviding primary power and with back-up power coming from the grid; or the data center \nload could be fully isolated behind the meter with system protection facilities in place to \nensure that there is no flow of power from the grid to the load.    \nIn determining what transmission service charges, if any, should be imposed in the \ncontext of different co-located configurations, the Commission should simply apply well-\nestablished cost causation principles that courts have recognized as informing the just and \nreasonable standard. 24 A bedrock ratemaking principle is that all FERC-jurisdictional \nrates and charges must “reflect to some degree the costs actually caused by the customer \nwho must pay for them,” and that costs must be allocated in a manner that is “at least \ncommensurate with the benefits that entity receives.”25  Under this principle, which has \nbeen the foundation of the Commission’s transmission pricing policies, transmission \ncharges to be assessed based on a party’s “actual use” of the transmission system.  \nCommission precedent in the co-location context teaches that in circumstances in which \ncertain customers “rely to a lesser degree on the PJM integrated transmission system” than \nothers, the transmission charges must reflect the parties’ actual use of the transmission \nsystem because this would ensure that “PJM allocates its transmission charges to those \n \n24 See, e.g., Old Dominion Electric Cooperative v. FERC, et al., 898 F.3d 1254, 1255 (D.C. Cir. \n2018). \n25 See Show Cause Order at P 74 (citing Ill. Com. Comm’n v. FERC, 576 F.3d 470, 476 (7th Cir. \n2009))."},{"page":12,"startToken":3237,"endToken":3560,"text":"12 \nusing the system on peak and helps to ensure that customers have the incentives to curtail \nload during peak periods.”26   \nCourts and the Commission has applied this basic ratemaking principle in \nnumerous cases.  For instance, the Court of Appeals for D.C. Circuit stated, “[f]or \ndecades, the Commission and the courts have understood the [just and reasonable] \nrequirement to incorporate a cost-causation principle – the rates charged for electricity \nshould reflect the costs of providing it.”27  The D.C. Circuit explained the cost-causation \nprinciple requires a comparison of the “costs assessed against a party to the burdens \nimposed or benefits drawn by that party.”28  Additionally, the court stressed that “the cost-\ncausation principle, by allocating project costs consistent with project benefits, creates the \nbest incentives for PJM member utilities themselves to agree on when to invest their \nscarce resources in transmission improvements.”29  \nOn the same day that the Commission issued the Show Cause Order, the \nCommission issued another order rejecting tariff revisions proposing to charge all co-\nlocated load based on a gross load basis.30  It is clear that in the Show Cause Order, the \nCommission is looking for a more fine-tuned or calibrated cost allocation methodology \nthat aligns with cost-causation and that a blanket, catch-all approach is untenable under \n \n26 See e.g., Occidental Chem. Corp. v. PJM Interconnection, L.L.C., et al., 101 FERC ¶ 61,005 \n(2002), order on compliance filing and reh’g, 102 FERC ¶ 61,275 at P 2 (2003), order on \ncompliance filing and reh’g, 104 FERC ¶ 61,142 (2003), order on reh’g, 105 FERC ¶ 61,348 \n(2003). \n27 See Old Dominion Electric Cooperative v. FERC, et al., 898 F.3d 1254, 1255 (D.C. Cir. 2018) \n(reversing a FERC cost allocation decision finding that it “involves a wholesale departure from the \ncost-causation principle.”). \n28 Id.  \n29 Id. at 1263. \n30 Atlantic City Electric Co., et al., 190 FERC ¶ 61,109 (2025)."},{"page":13,"startToken":3560,"endToken":3858,"text":"13 \nthe just and reasonable standard.  The Show Cause Order emphasizes that the “record \ndemonstrates that different co-location arrangements are likely to use or benefit from the \ntransmission system in different ways depending on how they are configured and, \nmoreover, that those different configurations will themselves likely have different impacts \non the transmission system.”31  This is the heart of the Commission’s concerns in the \nShow Cause Order. \nIn moving forward, the Commission must continue to be guided by and apply the \nabove-articulated cost causation principles.  Specifically, to the extent that co-located \ncustomers cause transmission owners to incur costs to serve these customers, the \ncustomers should pay for such services.  But cost responsibility must match actual cost \nincurrence.  If, for example, a particular co-located arrangement uses the grid as a back-up \nsource, then the co-load customers should pay for that type of usage.  \nAn approach that aligns with cost causation principles is one that treats all co-\nlocated customers as NITS customers with netting rules applied.  Indeed, this is the \ncurrent construct for BTMG customers under the PJM Tariff.  Customers all across the \nPJM system, such as universities, hospitals, refineries, rooftop solar, are allowed to net \nBTMG out of their transmission charges reflecting the fact that when they are generating \nbehind the meter, they are not using the system.32 There is no reason to treat behind the \nmeter load any differently than BTMG.  As discussed below, from an engineering and \nphysics perspective, there is no difference between behind the meter load and BTMG.  \nCourts and Commission precedents teach that that it is unduly discriminatory and \n \n31 Order at P 76. \n32 Section 34.2 of the PJM Tariff states:  “The daily load of a Network Customer does not include \nload served by operating Behind the Meter Generation.”"},{"page":14,"startToken":3858,"endToken":4188,"text":"14 \nunlawful to treat similarly-situated parties differently.33  The Commission should ensure \nthat there is no undue discrimination in the treatment of co-located arrangements.   \nB. \nThe Commission Should Recognize That There Are Many Customers \nWith BTMG And Any Remedy or Replacement Rate Adopted In This \nProceeding Must Not Adversely Impact Those Customers34  \nIn the Show Cause Order, the Commission recognized that there are a number of \ncustomers in PJM that have BTMG, and asked the parties to “address how co-located \nloads are similar to or disparate from other types of arrangements where load and \ngeneration share the same point of interconnection (such as Behind the Meter Generation \nas defined in the PJM Tariff or non-retail behind the meter generation) and should \nconsider how any proposed replacement rate would affect the existing arrangements.”35  \nCo-located loads are very similar to load and generation that share the same point of \ninterconnection, such as large load customers with BTMG.  In fact, they use or impact the \ntransmission in the same way.  Figure 1 sets forth a side-by-side comparison of the \nphysical configuration of a co-located load at a generator site and a behind the meter \ngeneration co-located at the customer’s (load) site.  \n \n \n \n33  See, e.g., New England Power Generators Ass’n v. FERC, 881, F.3d 202, 210 (D.C. Cir. 2018) \n(remanding to FERC a decision that treated new generation capacity market entrants differently \nfrom existing capacity due to a lack of reasoned explanation departing from its past precedent); \nEnergy Partners, L.P., 120 FERC ¶ 61,086 at P 169 (2007) (there is undue discrimination when \ntwo classes of customers are treated differently and the two classes of customers are similarly-\nsituated); PacifiCorp Elec. Operations, 54 FERC ¶ 61,296 at 61,855 (“undue discrimination can \nonly occur when two similarly situated customers are treated differently and there is no \njustification for the differing treatment.”). \n34 This section III.B responds to Show Cause Order, P 88, Section a., Question iv. \n35 Id."},{"page":15,"startToken":4188,"endToken":4399,"text":"15 \n \nFigure 1: Co-located load at a generator site and Behind-the-Meter at a \nCustomer (Load) site have the same impact on the transmission system.  \n \nSpecifically, the left illustration in Figure 1 shows a 5 MW load that is co-located at an \nexisting 10 MW generator behind the generator meter.  In this scenario, there is a net \npower flow to the grid of 5 MW.  The right illustration in Figure 2 is a depiction of a 10 \nMW load that has 5 MW behind the meter generation; there is a net power flow of 5 MW \nfrom the grid to the load.  Importantly, in either scenario, there is a reduced power flow on \nthe transmission system of 5 MW.  From a technical perspective, there is no material \ndistinction between a BTM load arrangement relative to a BTMG arrangement.  Both \narrangements result in the reduced use or burden of the transmission system (thereby \nminimizing transmission upgrades) that the Commission has recognized as beneficial to \nall customers.  Co-located load is not using or impacting the transmission system any \ndifferently than other BTMG customers.  Both classes of customers employ similar co-\nlocation configurations and should pay for transmission services based on their actual \nsystem usage (i.e., based on net use of the transmission system)."},{"page":16,"startToken":4399,"endToken":4753,"text":"16 \n \nIn his opening remarks during the November 1, 2024 Technical Conference, \nCommissioner Rosner observed that there are obvious benefits with co-locating large \nloads with generation, noting that such arrangement would reduce system costs.  He also \nstated that the “physics” of co-location load arrangements with BTMG arrangements are \nidentical:   \n [T]he potential benefits of co-locating large loads with generation are \npretty obvious.  There’s nothing new about this concept.  It’s been \nhappening for many years.  You know, siting generation near load \nreduce system costs, that’s kind of logical.  And what’s happening \nhere is the inverse we’re siting load near generation, and the physics \nare kind of – they kind of work the same.36 \n \nTo expand upon Commissioner’s Rosner’s observation that co-location is nothing new, \nthe co-location construct has been part of the PJM Tariff for over twenty years – since \n2004.37  The PJM Tariff defines BTMG as:  \n“Behind the Meter Generation” shall refer to a generation unit that delivers \nenergy to load without using the Transmission System or any distribution \nfacilities (unless the entity that owns or leases the distribution facilities has \nconsented to such use of the distribution facilities and such consent has \nbeen demonstrated to the satisfaction of the Office of Interconnection).38 \nTo reflect that there is no use of the transmission system by BTMG arrangements \nand that customers do not need to pay transmission charges for the load served by BTMG \n \n36 November 1 Technical Conference Transcript at 14 (emphasis added). \n37 See PJM Interconnection, L.L.C., 107 FERC ¶ 61,113 at P 3 (2004) (“2004 BTMG Order”), \nreh’g denied, 108 FERC ¶ 61,302 (2004) (approving PJM’s behind the meter tariff provisions as \njust and reasonable and not unduly discriminatory, and finding that no transmission or distribution \nfacilities are used to deliver energy from the generating unit to the load.).  \n38 PJM Tariff, Definition of “Behind the Meter Generation.”  (emphasis added).  The PJM \nOperating Agreement and Reliability Agreement contain the same “Behind the Meter Generation” \nterm.  See also PJM Manual 14G, Section 1.6 (explaining that Behind the Meter Generation “must \ndeliver energy to load without using the Transmission System.”)."},{"page":17,"startToken":4753,"endToken":5037,"text":"17 \narrangements (either in whole or in part), the PJM Tariff expressly states that the load of a \nnetwork customer “does not include the load served by operating Behind the Meter \nGeneration.”39  The key characteristic of a BTMG configuration is that it provides for the \ndelivery of power from the generator to the co-located load “without using the \nTransmission System.”40  \nIn 2004, when the Commission approved PJM’s tariff revisions to implement the \nBTMG rules, the Commission recognized the benefits of co-location, stating that the \nBTMG tariff provisions would “encourage qualifying entities with behind the meter \ngeneration to reduce their use of the PJM transmission system.”41  As the Commission \nheld, PJM’s BTMG provisions would allocate costs based on the market participant’s \n“actual use of PJM’s system . . . ” and that this is “consistent with the principle of cost \ncausation.”42   \nSince 2004, many PSE&G customers have relied upon these netting provisions in \nthe PJM Tariff to reduce their actual use of the PJM’s system to the benefit of customers \nthroughout PJM.  These customers use BTMG resources such as solar, reciprocating \nengine, and gas turbine generation facilities.  In New Jersey alone, there are over 200,000 \nBTMG solar installations, 90,000 of which are located on PSE&G’s system.43  These \ncustomers are able to offset their peak load with behind-the-meter solar systems.  Indeed, \n \n39 See Section 34.2 of the PJM Tariff (emphasis added). \n40 Id. \n41 2004 BTMG Order at P 27 (emphasis added). \n42 Id. at PP 2, 28 (finding that PJM’s meter generation tariff revisions would benefit “customers by \nallowing PJM to more appropriately allocate the operating costs of its transmission system.”). \n \n43 See https://njcleanenergy.com/renewable-energy/project-activity-reports/project-activity-reports."},{"page":18,"startToken":5037,"endToken":5355,"text":"18 \nhomeowners with solar panels are often able to fully offset their electricity usage during \npeak demand times, therefore eliminating any charge for transmission service. \n In addition, PSE&G has a number of large customers who rely on BTMG, \nincluding universities like Rutgers, the State University of New Jersey (“Rutgers”), \ngovernment agencies like the Bergen County Utilities Authority (“BCUA”), \nmanufacturers, real estate companies and pharmaceutical companies.  Exhibit 1 to this \nResponse shows that a number of customers on the PSE&G system will experience \nsignificant cost increases if the Commission were to adopt gross load pricing.  For \ninstance, large university systems in PJM have installed onsite generation to help to meet \ncampus needs for electricity.44  With multiple campuses located on PSE&G’s system, \nRutgers owns and operates a number of onsite generating facilities.45  Charging \ntransmission based on a gross load approach would have broad application and adverse \nimpacts on entities like Rutgers and on the customers of QFs across the PJM footprint, and \nwould disrupt the settled expectations of these entities that they need not take transmission \nservice when relying on their on-site generation resources.  Accordingly, any replacement \nrate that the Commission may adopt must not adversely impact existing customers with \nBTMG and their ability to net and reduce the use of the transmission system.   \n \n44 The University of Maryland installed a natural gas-turbine in 1999 to serve its campus load. \nhttps://today.umd.edu/new-generation-campus-energy-production-62a512c9-aa8b-4567-ae7c-\n5d39051d73b1. \n45 With the assistance of the New Jersey Board of Public Utilities, Rutgers began construction of a \nsolar energy facility in 2008 to serve a portion of the needs of one of its campuses.  \nhttps://www.rutgers.edu/news/rutgers-university-breaks-ground-largest-campus-solar-energy-\nfacility-nation.  Rutgers more recently contracted in 2023 to have solar canopies installed on \nparking lots at 17 locations that would meet a portion of its power needs, meeting sustainability \nobjectives and allowing it to capture purchased power cost savings."},{"page":19,"startToken":5355,"endToken":5690,"text":"19 \nC. \nCo-Located Load Arrangements Are Viable Options For The \nDevelopment Of Data Centers And Should be Encouraged46  \nThe Commission and the states have recognized the vital importance for data \ncenter development and its importance to the economy and national security.  For \nexample, former Chairman (now Commissioner) Phillips has stressed the importance of \nhaving “regulatory flexibility” for data centers to “maintaining U.S. leadership in \nArtificial Intelligence” and “maintaining our national security.”47  He expressed the \nconcern that data centers, artificial intelligence and other information related technologies \nmay be “moving overseas due to lack of power supply and infrastructure, or regulatory \nbarriers, which raise national security concerns for our nation.”   \nSo let me put my cards on the table.  In my opinion, data centers, artificial \nintelligence, indeed the full panoply of information related-technologies \nthat are transforming the world are national resources, with generational \nsignificance, and vast national security and national economic \nconsequences.  They belong in the United States, and I believe the federal \ngovernment, including this agency, should be doing very best they can to \nnurture and foster their development.48 \n \nHe emphasized that “FERC can and should play a leadership role” in moving forward \nwith a “positive national initiative.”49  Other FERC Commissioners have similarly \nexpressed support for this sentiment.50    \n \n46 This section addresses Show Cause Order, P 88, Section (e), Question (vi).  \n47 See PJM Interconnection, L.L.C., 189 FERC ¶ 61,078 (2024), Phillips, Chairman, dissenting \nstatement at P 3.  \n48 Large Loads Co-Located at Generating Facilities, Docket No. AD24-11, November 1, 2024 \nTechnical Conference, Tr. at 8 (emphasis added). \n49 Id. at 9. \n50 See, e.g., November 1 Technical Conference, Tr. at 16-17 (Commissioner See stating “Data \ncenters and the promise of AI as critical for our economy, and for matters of national security, and \nI share an eagerness to find new ways to accommodate these important and increasing loads, and I \nunderstand the urgency of the issues in front of us.”); November 1 Technical Conference, Tr. at 19"},{"page":20,"startToken":5690,"endToken":5951,"text":"20 \nAt the state level, New Jersey has taken steps to attract data centers to the state.  In \n2024, New Jersey adopted the “Next New Jersey Program” that will provide tax credits to \neligible businesses engaged in artificial intelligence work or large-scale artificial data \ncenters.  This program is designed to attract new investment into the state’s artificial \nintelligence industry and recognizes that “AI will be a transformative industry that will \nchange lives and grow our economy and New Jersey is ready to take the lead.”51  \nIn recognition of the importance of data center for economic development and \nnational security issues, the Commission should expeditiously take action in this \nproceeding to provide much needed clarity and certainty as to the “rules of the road” for \nco-located load arrangements.  In so doing, the Commission should maintain optionality \nso that customers have the ability to select the best configuration for their particular \ncircumstances and needs.  In particular, the Commission should continue to keep in mind \nof the significant benefits that co-location arrangements provide, including the importance \nof providing the proper pricing incentives to encourage entities to reduce their usage of the \ntransmission system.  This means allocating costs based on the co-located load’s actual \nuse of the transmission system.   \n \n \n \n(Commissioner Chang stating  “the U.S. is leading the world in data science and artificial \nintelligence.  Our role in the energy industry is to support that development in the United States.”).  \n51 See Governor Murphy signs Legislation to Spur Investment in New Jersey’s AI Sector, \nhttps://www.nj.gov/governor/news/news/562024/20240725a.shtml."},{"page":21,"startToken":5951,"endToken":6075,"text":"21 \nIV. \nCONCLUSION  \nWHEREFORE, for the reasons discussed herein, the Commission should \nexpeditiously issue an order that provides timely and needed clarity with respect to co-\nlocated load rules and that leads to a result that is (i) consistent with cost causation \nprinciples; (ii) avoids adversely impacting existing BTMG customers in PJM;  and (iii) \npreserves co-location as a viable option to support data center development. \n \nJodi L. Moskowitz \nVice President, Regulatory,  \nDeputy General Counsel and  \nRTO Strategy Officer \nPSEG Services Corp. \n80 Park Plaza, T-20 \nNewark, NJ 07102 \n(973) 430-6409 \nJodi.Moskowitz@pseg.com \n \n \n/s/ Viet H. Ngo                          \nViet H. Ngo \nAssociate Counsel – Federal Regulatory \nPSEG Services Corporation \n601 New Jersey Ave, NW Suite 310 \nWashington, DC 20001 \n(202) 460-9356 \nViet.Ngo@pseg.com"},{"page":22,"startToken":6075,"endToken":6088,"text":"Exhibit 1 \n \nIllustration of Adverse Customer Impacts  \nAssociated with a Gross Load Approach"},{"page":23,"startToken":6088,"endToken":6449,"text":"23 \nTo the extent that BTMG customers are assessed on a gross load basis, this will in \nsignificant adverse impacts on customers on the PSE&G system who have BTMG resources and \nwho have been relying upon the netting provisions under the PJM Tariff for many years.   \n \nExamples are provided below.  Note that (i) this is not an exhaustive list of all of \nPSE&G’s BTMG customers; (ii) certain PSE&G BTMG customers have asked for anonymity in \nthe context of disclosing their customer data; and (ii) PSEG would expect the same types of \nimpacts would be experienced by BTMG customers throughout the PJM footprint.    \n \nExample 1: Rutgers has 3 gas turbine generators totaling 15 MW (nameplate capacity)52 at its \nRutgers Biomedical and Health Sciences (“RBHS”) site, and three gas turbine generators totaling \n17 MW (nameplate capacity) at its Busch/Livingston Campuses.  The overall annual impact of a \ngross load approach for both locations is approximately $4.1M. \n \nRutgers – RBHS \n \nNet Load \nGross Load \nChange \nLoad \nMW \n16.5 \n26 \n9.5 \nCost \n$ \n$2,889,648 \n$4,561,024 \n$1,671,376 \n \n \nRutgers–\nBusch/Livingston \nCampuses \n \nNet Load \nGross Load \nChange \nLoad \nMW \n20.46 \n34.51 \n14.05 \nCost \n$ \n$3,589,060 \n$6,053,943 \n$2,464,883 \n \nExample 2:  Large Customer #1 with 3 gas turbine generators totaling 19 MW (nameplate \ncapacity) at two locations is estimated to experience an annual increase of $3.4M. \n \nLarge Customer #1 \nLocation 1 \n \nNet Load \nGross Load \nChange \nLoad \nMW \n5.0 \n14.9 \n9.9 \nCost \n$ \n$877,230 \n$2,617,436 \n$1,740,206 \nLarge Customer #1 \nLocation 2 \n \nNet Load \nGross Load \nChange \nLoad \nMW \n1.2 \n10.6 \n9.4 \nCost \n$ \n$203,495 \n$1,852,481 \n$1,648,986 \n \nExample 3: Large Customer #2 has a 10 MW gas turbine generator (nameplate capacity) and is \nexpected to experience an approximately $934K annual increase.   \n \n \n52 For the customers in Exhibit 1, the nameplate value of the BTMG differs from the value that is used to \nnet against gross load (which is based on the output of the BTMG resource coincident with the relevant \npeak hours on PSE&G’s system)."},{"page":24,"startToken":6449,"endToken":6659,"text":"24 \nLarge Customer #2 \n \nNet Load \nGross Load \nChange \nLoad \nMW \n0.12 \n5.44 \n5.32 \nCost \n$ \n$20,269 \n$953,875 \n$933,607 \n \nExample 4:  The College of New Jersey (“TCNJ”) with a 5.2 MW solar turbine dual fuel natural \ngas and oil generator would experience an estimated annual increase of $733k. \n \nTCNJ \n \nNet Load \nGross Load \nChange \nLoad \nMW \n5.14 \n9.32 \n4.18 \nCost \n$ \n$901,755 \n$1,634,326 \n$732,571 \n \nExample 5:  Large Customer #3 with a solar facility of 17 MW (nameplate) would be \nexperience an increase of $2 million annually. \n \nLarge Customer #3 \n \nNet Load \nGross Load \nChange \nLoad \nMW \n3.47 \n14.69 \n11.22 \nCost \n$ \n$609,361 \n$2,576,756 \n$1,967,395 \n \nExample 6:  Large Customer #4 with a 10 MW gas turbine generator would experience an \nestimated annual increase of $2M: \n \nLarge Customer #4 \n \nNet Load \nGross Load \nChange \nLoad \nMW \n2.22 \n13.41 \n11.19 \nCost \n$ \n$389,608 \n$2,351,884 \n$1,962,275 \n \nExample 7:  Essex County Correctional Facility with two engines totaling 6 MW (nameplate) \nwould experience an estimated annual impact of $594k: \n \nEssex County \n \nNet Load \nGross Load \nChange \nLoad \nMW \n0.001 \n3.385 \n3.384 \nCost \n$ \n$175 \n$593,810 \n$593,635"},{"page":25,"startToken":6659,"endToken":6807,"text":"25 \nExample 8:  Large Customer #5 with a 4 MW gas turbine generator would have an estimated \nannual increase of $515k. \n \nLarge Customer #5 \n \nNet Load \nGross Load \nChange \nLoad \nMW \n0.01 \n2.94 \n2.93 \nCost \n$ \n$1,054 \n$515,854 \n$514,800 \n \nExample 9: Bergen County Utilities Authority (BCUA) with a gas turbine generator of 2.69 \nMW (nameplate) would experience an estimated annual increase of $472k. \n \nBCUA \n \nNet Load \nGross Load \nChange \nLoad \nMW \n3.48 \n6.47 \n2.69 \nCost \n$ \n$610,455 \n$1,135,730 \n$471,891 \n \nExample 10: Large Customer #6 with a 15 MW generator and a 16 MW solar facility, and \nwould experience an estimated annual increase of $4.3 million (an increase of over 700%):  \n  \nLarge Customer #6 \n \nNet Load \nGross Load \nChange \nLoad \nMW \n3.28 \n27.59 \n24.31 \nCost \n$ \n$575,739 \n$4,839,419 \n$4,263,680"},{"page":26,"startToken":6807,"endToken":6854,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list compiled by the Secretary in the proceeding.  \nDated at Newark, New Jersey this 24th day of March, 2025. \n/s/ Robert Gardinor \n \n \nRobert Gardinor"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":842,"startToken":0,"endToken":697},{"p":3,"at":842,"title":"I. EXECUTIVE SUMMARY","method":"printed heading","endPage":7,"endAt":308,"startToken":697,"endToken":1866},{"p":7,"at":308,"title":"II. BACKGROUND","method":"printed heading","endPage":7,"endAt":325,"startToken":1866,"endToken":1868},{"p":7,"at":325,"title":"A. Description of PSE&G","method":"printed heading","endPage":8,"endAt":3,"startToken":1868,"endToken":2080},{"p":8,"at":3,"title":"B. The Show Cause Order","method":"printed heading","endPage":9,"endAt":245,"startToken":2080,"endToken":2426},{"p":9,"at":245,"title":"III. RESPONSE","method":"printed heading","endPage":9,"endAt":262,"startToken":2426,"endToken":2428},{"p":9,"at":262,"title":"A. The Commission Recognizes The Variety of Co-Located","method":"printed heading","endPage":14,"endAt":181,"startToken":2428,"endToken":3882},{"p":14,"at":181,"title":"B. The Commission Should Recognize That There Are Many Customers","method":"printed heading","endPage":19,"endAt":4,"startToken":3882,"endToken":5356},{"p":19,"at":4,"title":"C. Co-Located Load Arrangements Are Viable Options For The","method":"printed heading","endPage":21,"endAt":4,"startToken":5356,"endToken":5952},{"p":21,"at":4,"title":"IV. CONCLUSION","method":"printed heading","endPage":26,"endAt":0,"startToken":5952,"endToken":6807},{"p":26,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":26,"endAt":298,"startToken":6807,"endToken":6854}]}