{"document":{"slug":"rec-20250324-5310","title":"Answer of Silver Run Electric, LLC to the 02/20/2025 Order Instituting Proceeding Under Section 206 of the Federal Power Act","issued":"2025-03-24","accession":"20250324-5310","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Silver Run Electric, LLC","kind":"answer","file":"sources/filings/text/20250324-5310_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250324-5310","tier":"record","sha256":"ecad773bdcd24132f48216e196e80062610346790eb5fde5a497f76f4373af7d","pages":4,"tokens":891,"emptyPages":[],"textThemes":[]},"pages":[{"page":1,"startToken":0,"endToken":348,"text":"March 24, 2025 \n \nThe Honorable Debbie-Anne A. Reese, Esq. \nSecretary \nFederal Energy Regulatory Commission \n888 First Street, N.E. \nWashington, DC 20426 \n \n \nRe: \nSilver Run Electric, LLC, Docket Nos. EL25-49-000, AD24-11-000, EL25-20-000 \nResponse to the Commission’s Order Instituting Proceeding under Section 206 of the Federal \nPower Act  \n \nDear Secretary Reese: \n \nPursuant to the Federal Energy Regulatory Commission’s (“Commission” or “FERC”) February 20, \n2025 order issued in the above-captioned proceeding,1 Silver Run Electric, LLC (“Silver Run”), as PJM \nInterconnection, L.L.C. (“PJM”) Transmission Owner, respectfully submits this response in accordance \nwith the Commission’s directive and explains that it takes no position on the matters that the \nCommission raises in its order.  Silver Run commits to working with PJM, the other PJM Transmission \nOwners, and the other stakeholders in this proceeding as necessary to implement any Tariff changes \nthat may be required as part of this proceeding. \n \n \nI. \nBACKGROUND \nThe February 20 Order instituted a proceeding under section 206 of the Federal Power Act (“FPA”), \nwherein the Commission directed PJM and the PJM Transmission Owners to show cause as to why the \nPJM Open Access Transmission Tariff, Amended and Restated Operating Agreement of PJM, and \nReliability Assurance Agreement Among Load Serving Entities in the PJM Region (collectively, the \n“Tariff”) (a) remains just and reasonable and not unduly discriminatory or preferential with regards to \nthe rates, terms, and conditions of service applying to co-location arrangements or (b) explain what \nchanges would remedy the Commission’s identified concerns if FERC were to determine the Tariff has \nbecome unjust and unreasonable or unduly discriminatory or preferential and, therefore, establishes a \nreplacement Tariff. \n \nSilver Run is an electric transmission-only utility company established to develop, own, and operate \ntransmission facilities within the PJM region, and is organized under the laws of the State of Delaware.  \nSilver Run is an indirect subsidiary of LS Power Associates, L.P.  Silver Run owns and operates discrete \nand limited transmission facilities.  Specifically, Silver Run owns and operates one substation in New \n \n1  \nSee PJM Interconnection, L.L.C., et al., 190 FERC ¶ 61,115 (2025) (“February 20 Order”)."},{"page":2,"startToken":348,"endToken":787,"text":"2/3 \nCastle County, Delaware (the Silver Run Substation) and a 5.5-mile, 230 kV transmission line, which \nincludes an approximately 3-mile submarine crossing of the Delaware River, connecting the Silver Run \nSubstation to the Hope Creek Nuclear Plant Switchyard located in Salem County, New Jersey.  Silver \nRun built these transmission assets as part of PJM’s Order No. 1000-compliant competitive solicitation \nprocess associated with the Artificial Island Project, which was needed to improve transmission system \nperformance in the area.2  These transmission assets, which commenced operations on April 28, 2020, \nwere the first and, thus far, only transmission assets owned by Silver Run. \n \nII. \nRESPONSE \nSilver Run has carefully reviewed each of the issues raised in the February 20 Order, including the \nbriefing questions reflected in Section VI.D of the February 20 Order.  Silver Run, however, is asserting \nno position in this proceeding but is committed to working alongside PJM, the other PJM Transmission \nOwners, and other stakeholders in this proceeding to implement any related Tariff changes that the \nCommission may require to be made. \n \nSilver Run is taking no position on this matter, because it is a PJM Transmission Owner with no \nservice territory, no load, and no generator interconnection customers, pending or otherwise.  \nFurthermore, as explained above, Silver Run’s sole assets are transmission facilities under PJM’s \noperational control.  Consequently, if and when any load or generator customers seek to interconnect \nto Silver Run’s transmission facilities, co-located or not, PJM will oversee the processing thereof, and \nSilver Run will abide by any Tariff provisions effective at that time. \n \nIII. \nCONCLUSION \nSilver Run looks forward to the opportunity of working with the Commission, its staff, PJM, and \nother stakeholders in this proceeding on any Tariff revisions that the Commission may find are \nnecessary.  Please contact the undersigned with any questions regarding this filing. \n \n  \nRespectfully submitted, \n \n \n \n \n \n \n \n \n/s/Blake R. Urban \n \n \n \n \n \n \nBlake R. Urban \n \n \n \n \n \n \nSeth Yeazel \nLS Power Development, LLC \n \n2  \nIn 2013, PJM selected Northeast Transmission Development, LLC’s (“Northeast Transmission”) proposal to improve \noperational performance and reliability in the Artificial Island area.  In 2018, Northeast Transmission merged with \nSilver Run.  The Commission accepted Silver Run’s Notice of Succession and corresponding changes to the Intra-\nPJM Tariffs.  PJM Interconnection, L.L.C., Docket No. ER18-1983-000 (Aug. 24, 2018) (delegated letter order).  \nFurthermore, on October 26, 2022, the New Jersey Board of Public Utilities selected Silver Run to expand its \nexisting project as part of PJM’s State Agreement Approach, to facilitate the successful delivery of offshore wind to \nNew Jersey customers.  Order on the State Agreement Approach SAA Proposals, Docket No. QO20100630 (N.J. Bd. \nof Pub. Util., Oct. 26, 2022)."},{"page":3,"startToken":787,"endToken":812,"text":"3/3 \n16150 Main Circle Drive, Suite 310  \nChesterfield, MO  63017  \n636-231-0475 \n240-904-5109 \nburban@lspower.com \nsyeazel@lspower.com \n \nAttorneys for Silver Run Electric, LLC"},{"page":4,"startToken":812,"endToken":891,"text":"CERTIFICATE OF SERVICE \n \n \nPursuant to Rule 210 of the Commission’s Rules of Practice and Procedure, I hereby certify that \nI, on this day, have served the foregoing document upon each person designated on the official service \nlists compiled by the Secretary of the Commission in these proceedings. \n \nDated at Washington, DC, this 24th day of March 2025. \n \n \n \n/s/ Seth Yeazel \n \n \n \n \n \n \nSeth Yeazel \nLS Power Development, LLC \n16150 Main Circle Drive, Suite 310  \nChesterfield, MO  63017  \n240-904-5109 \nsyeazel@lspower.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":1022,"startToken":0,"endToken":147},{"p":1,"at":1022,"title":"I. BACKGROUND","method":"printed heading","endPage":2,"endAt":696,"startToken":147,"endToken":451},{"p":2,"at":696,"title":"II. RESPONSE","method":"printed heading","endPage":2,"endAt":1733,"startToken":451,"endToken":608},{"p":2,"at":1733,"title":"III. CONCLUSION","method":"printed heading","endPage":4,"endAt":0,"startToken":608,"endToken":812},{"p":4,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":4,"endAt":530,"startToken":812,"endToken":891}]}