{"document":{"slug":"rec-20250324-5313","title":"Answer of PJM Interconnection, L.L.C. to the 02/20/2025 Order Instituting Proceeding Under Section 206 of the Federal Power Act and Consolidating with Other…","issued":"2025-03-24","accession":"20250324-5313","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"PJM Interconnection, L.L.C.","kind":"answer","file":"sources/filings/text/20250324-5313_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250324-5313","tier":"record","sha256":"c4dd59718570ea6e2ab4988d2aff6b355b53c560a9394e68a4a235cb62923d15","pages":74,"tokens":23335,"emptyPages":[],"textThemes":["colo","study","adequacy","cost"]},"pages":[{"page":1,"startToken":0,"endToken":169,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n  \nPJM Interconnection, L.L.C. \nAllegheny Electric Cooperative, Inc. \nAmerican Transmission Systems, \nIncorporated \nAtlantic City Electric Company \nBaltimore Gas and Electric Company \nDelmarva Power & Light Company \nDuke Energy Ohio, Inc. \nDuke Energy Kentucky, Inc. \nEast Kentucky Power Cooperative, Inc. \nEssential Power Rock Springs, LLC \nHudson Transmission Partners, LLC \nJersey Central Power & Light Company \nMid-Atlantic Interstate Transmission, LLC \nNeptune Regional Transmission System, \nLLC \nOld Dominion Electric Cooperative \nPECO Energy Company \nPPL Electric Utilities Corporation \nPotomac Electric Power Company \nPublic Service Electric and Gas Company \nRockland Electric Company \nTrans-Allegheny Interstate Line Company \nTransource West Virginia, LLC \nUGI Utilities, Inc. \nMonongahela Power Company \nThe Potomac Edison Company \nCommonwealth Edison Company \nCommonwealth Edison Company of \nIndiana, Inc. \nThe Dayton Power and Light Company  \nAEP Appalachian Transmission Company, \nInc. \nAEP Indiana Michigan Transmission \nCompany, Inc. AEP Kentucky \nTransmission Company, Inc. \nAEP Ohio Transmission Company, Inc. \nAEP West Virginia Transmission \nCompany, Inc. Appalachian Power \nCompany \nIndiana Michigan Power Company \nKentucky Power Company \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n)  \n) \n) \n) \n) \n) \n) \n)  \n) \n) \n) \n) \n) \n) \n)  \n) \n) \n) \n) \n) \n) \n)  \n) \n) \n) \n) \n) \n) \nDocket Nos. EL25-49-000"},{"page":2,"startToken":169,"endToken":310,"text":"2 \nKingsport Power Company \nOhio Power Company \nWheeling Power Company \nDuquesne Light Company \nVirginia Electric and Power Company \nLinden VFT, LLC \nCity of Cleveland, Department of Public \nUtilities, Division of Cleveland Public \nPower \nCity of Hamilton, OH \nSouthern Maryland Electric Cooperative, \nInc. \nOhio Valley Electric Corporation \nAMP Transmission, LLC \nSilver Run Electric, LLC \nNextEra Energy Transmission MidAtlantic \nIndiana, Inc. \nWabash Valley Power Association, Inc. \nKeystone Appalachian Transmission \nCompany \nLarge Loads Co-Located at Generating \nFacilities  \nConstellation Energy Generation, LLC \nv.  \nPJM Interconnection, L.L.C. \n)  \n) \n) \n) \n) \n) \n) \n)  \n) \n) \n) \n) \n) \n) \n)  \n) \n) \n) \n) \n) \n) \n)  \n) \n) \n) \n) \n) \n) \n)  \n) \n) \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \nAD24-11-000 \n \n \n \nEL25-20-000 \n(Consolidated) \n \n \n \n \n \n \nANSWER OF PJM INTERCONNECTION, L.L.C. \nPursuant to Rule 213 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (“Commission”),1 PJM Interconnection, L.L.C. (“PJM”) submits \nthis answer to the Order Instituting Proceeding Under Section 206 of the Federal Power \n                                                 \n1 18 C.F.R § 385.213."},{"page":3,"startToken":310,"endToken":679,"text":"3 \nAct and Consolidating with Other Proceedings2 issued in the above-captioned proceeding \non February 20, 2025. \nI. \nINTRODUCTION \nPJM remains committed to supporting its member companies, the states, and the \nCommission in the industry’s efforts to integrate large loads, including data centers (“large \nloads”), including through co-locating with generation (“co-location arrangements”).   \nPJM’s approach to large load expansion—co-located or not—focuses on:  \n(1) maintaining resource adequacy; (2) enabling reliable system operations; (3) facilitating \nthe states’ and stakeholders’ efforts to timely and effectively integrate large loads in a \nmanner that meets their unique needs; and (4) providing information and analysis that \nsupports the equitable alignment of transmission system usage and compensation.3  \nSubstantial progress can be made in these efforts by leveraging the tools in the existing \nTariff4 and exploring with the Commission and stakeholders other potential innovative \nmarket solutions, where allowed by state laws, that may specifically define and limit when \nand how load in a jurisdiction can be served by a supplier other than a franchised public \nutility.  This means that some existing state regulatory environments may permit certain \nco-location load arrangements while other existing state regulatory environments may not.  \nGiven the novelty and nascence of the issues presented in this proceeding, many of the \n                                                 \n2 PJM Interconnection, L.L.C., Order Instituting Proceeding Under Section 206 of the Federal Power Act and \nConsolidating with Other Proceedings, Docket Nos. EL25-49-000, et al. (Feb. 20, 2025) (“Order”). \n3 This is a role reserved to the PJM Transmission Owners for purposes of Network Integration Transmission \nService cost allocation.  See Linden VFT, LLC, 161 FERC ¶ 61,264, at P 31 n.44 (2017) (“Although PJM \nimplements the cost allocation provisions of Schedule 12 of the Tariff, the cost allocation method is \ndetermined by the PJM Transmission Owners, and it is the PJM Transmission Owners, not PJM, that have \nthe section 205 filing rights for the PJM cost allocation method.” (citing Atl. City Elec. Co. v. FERC, 295 \nF.3d 1 (D.C. Cir. 2002)).   \n4 The Order defines Tariff as including the PJM Open Access Transmission Tariff, the Amended and Restated \nOperating Agreement of PJM (“Operating Agreement”), and the Reliability Assurance Agreement Among \nLoad Serving Entities in the PJM Region (“RAA”)."},{"page":4,"startToken":679,"endToken":948,"text":"4 \nconcepts PJM presents require additional effort to identify and develop Tariff and manual \nprovisions necessary for implementation. \nRegardless of what co-location arrangements are ultimately sanctioned by the \nCommission, permitted by the states, and elected by developers, participants involved in \nco-location arrangements should pay the costs of any grid services they consume and the \narrangements must be reliable and operationally manageable.  As noted in Exhibit A and \nherein, many co-located load configurations utilize grid support and consume ancillary \nservices (including, for example, frequency regulation, black start service, and reactive \nservice).   \nPJM continues to work closely with the states and its members to realize the prompt \ndevelopment of substantial new infrastructure, most especially significant electric \ngeneration that at least matches if not exceeds load growth forecasts.  This infrastructure \nshould be promptly studied, sited, and constructed to facilitate the projected significant \nload growth.   \nWhat PJM and the industry need now is Commission guidance on a path forward \nbased on the record developed in this proceeding.  The record will support a finding that \nPJM’s existing Tariff remains just and reasonable, although improvements and \nclarifications may be appropriate based on Commission guidance.  Multiple existing \npathways are available to facilitate co-location arrangements.  Some potential additional \npathways are also proposed in this filing.  Given that this is an evolving area, if the \nCommission believes that the record supports consideration of additional options beyond \nthose that already exist, PJM requests that the Commission issue detailed guiding principles \nsuch as those PJM proposes in this filing that PJM can promptly operationalize in a section \n205 filing.  Although stakeholder input is critical, the Commission could also issue a"},{"page":5,"startToken":948,"endToken":1258,"text":"5 \ncompliance directive under its section 206 authority to set a clear deadline for future filings \ngiven the important national interests implicated.  The Commission’s continued leadership \nwill assist the industry in obtaining certainty and clarity about the available pathways for \nintegration of large loads consistent with the principles set forth herein. \nII. \nEXECUTIVE SUMMARY OF EXISTING AND POTENTIAL NEW \nOPTIONS TO FACILITATE CO-LOCATION ARRANGEMENTS \nAt least eight potential options for additional large load co-location (as well as large \nload integration in general) are summarized in a chart attached as Exhibit A.   This exhibit \nlays out the key attributes and impacts of each configuration and service option on  load \ncharacteristics, services consumed, studies required, rates, operations, and resource \nadequacy impacts.  Three of the options already exist under PJM’s Tariff.  The other five \nare potential options that have been proposed by others or developed by PJM in response \nto issues raised in the various predecessor co-located load proceedings.  \nTo be clear, PJM does not mean to suggest that all identified “options” in Exhibit \nA are equivalent, desirable, or even necessarily workable.  For example, state laws may \nspecifically limit when and how load in a jurisdiction can be served by a supplier other \nthan a franchised public utility.  Further, identified options are not mutually exclusive, as \nit is possible several of the options may be used seriatim or concurrently. Each new option \noutlined herein is conceptual and would benefit from continued input from stakeholders, \nCommission guidance, and a deadline for submission of any such proposals either in the \ncontext of a section 205 filing or in this docket.     \nBefore describing the options, a few points warrant emphasis.  First, as noted above, \nthe availability of various options is dependent on state law.  States may specifically define \nand limit when and how load in a jurisdiction can be served by a supplier other than a"},{"page":6,"startToken":1258,"endToken":1564,"text":"6 \nfranchised public utility.  This is a significant point that is explored in greater detail below \nin response to the Commission’s question A.i about federal and state jurisdiction.  At \nbottom, a state’s exclusive retail franchise territory law may restrict non-franchised \nsuppliers from serving co-located load.  Further, in deregulated states, state law may (or \nmay not) today (or in the future) require co-located load suppliers to be licensed energy \nproviders and/or otherwise impose limitations on such suppliers by, for example, obliging \nthe designation of the load as Network Load, with or without netting, or the taking of \ncertain types of transmission service that could compel the designation of co-located load \nas Network Load. \nSecond, large co-located loads that connect as Network Load realize significant \nbenefits (as discussed in greater detail in response to question B.iii, below).  Six of the \neight options PJM outlines (Options 1, 2, 3, 6, 7, and 8) are premised on large co-located \nload being Network Load.  The remaining two configurations (Options 4 and 5) provide \nthat the load may still be Network Load if designated as such by the customer (whether or \nnot required by state law), but it does not have to be Network Load.  Importantly, where \nNetwork Load is designated and coming onto the system, even where necessary \ntransmission upgrades are not yet in service, PJM operations will endeavor to implement \ninterim operating procedures to serve the Network Load in real time because there is an \nobligation to serve it. \nThird, an introductory note about study-related terminology used throughout this \nsubmission.  Co-located load arrangements implicate a variety of different but interrelated \nstudy frameworks and cost allocation constructs that PJM will describe here in an effort to \navoid repetition throughout and promote clarity about terminology used in Exhibit A.  First, \ntraditional Transmission Owner/Load Serving Entity (“LSE”)/Electric Distribution"},{"page":7,"startToken":1564,"endToken":1844,"text":"7 \nCompany (“EDC”) load interconnection processes (“traditional load interconnection \nprocesses”) to add Network Load are generally commenced by performing what PJM will \ncall a “Transmission Owner retail load integration study” to identify local upgrades \nneeded to reliably accommodate the load based on local transmission owner planning \ncriteria.  The results of this study identify local system needs that are presented at the \nTransmission Expansion Advisory Committee (“TEAC”).  Solutions to these needs \ntypically take the form of Supplemental Projects (following Tariff, Attachment M-3) and \nare also generally presented at the TEAC.   \nPJM then performs a “PJM Do No Harm study” to evaluate whether a proposed \nSupplemental Project will adversely impact the reliability of the Transmission System as \nrepresented in the planning models used in other PJM reliability planning studies.  If as a \nresult of the do no harm study, system upgrades are found to be required, such upgrades \nwill be considered part of the Supplemental Project and are the responsibility of the \nTransmission Owner sponsoring the Supplemental Project.  Supplemental Projects are cost \nallocated to the local Transmission Owner’s zone pursuant to individual Transmission \nOwner cost allocation frameworks.   \nNecessary studies (for additional information, see PJM’s response to question D.i, \ninfra) are essentially generator interconnection modification studies.  Such studies are only \nperformed when a generator is involved, and a party to the interconnection services \nagreement is proposing to change the interconnection.  Transmission Owners review PJM’s \nnecessary study analysis, and transmission owners may verify that analysis and/or perform \nadditional transmission owner analysis pursuant to their processes or requirements.  \nAn aggregation of large load additions could trigger regional (as opposed to local) \ntransmission system needs, which would be identified as part of the Regional"},{"page":8,"startToken":1844,"endToken":2159,"text":"8 \nTransmission Expansion Planning (“RTEP”) process in Schedule 6 of the Operating \nAgreement.  The load that could rise to regional RTEP needs is determined during the \nannual load forecasting process, when PJM makes a request to the EDCs/Load Serving \nEntities (“LSEs”) to submit large load additions that would not be captured in the \nparameters that are typically incorporated.  PJM presents what is ultimately accepted into \nthe Load Forecast for the subsequent year.  PJM then plans its transmission system in light of \nthis load forecast, and RTEP upgrades are identified and ultimately cost allocated pursuant \nto existing RTEP-specific methodologies.   \nBefore moving off the topic of studies, it is important to re-emphasize that  any \nconfiguration where the co-located load is Network Load (Options 2, 3, 7, and 8, and in \nsome circumstances Options 4 and 5) is limited in scope to generator interconnection \nmodifications.  As described above, Transmission Owner retail load integration studies \nwould be performed in addition to necessary studies.  While stakeholder (including the \nOrganization of PJM States, Inc.) and Commission comments and questions probe the \nsufficiency of the necessary study agreement/study process for load integrations, only two \nof the proposed options (Options 4 and 5 if load is not designated as Network Load) \ninvolve the use of a necessary study without any form of a load interconnection study.  To \nthe extent the Commission sanctions further exploration of Options 4 and 5 and the market \nis interested in pursuing such options, PJM will explore opportunities to enhance the \nvisibility of the necessary study process and results for interested stakeholders. \nFourth, as to the resource adequacy dimension to co-location arrangements where \nconditions are tight, any additional load on the system requires either the addition of supply \nresources to serve that load reliably, or flexibility on the part of the load to curtail its \nconsumption from the transmission system when necessary to maintain reliability.  For this"},{"page":9,"startToken":2159,"endToken":2481,"text":"9 \nreason,  PJM has outlined three potential options relating to adding additional supply and \noperational flexibility:  Option 6 (co-located load that elects to be Network Load and \nleverages provisional interconnection service or State Agreement Approach), Option 7 (co-\nlocated load that takes a new non-capacity backed service that could be curtailed in advance \nof emergency procedures), and Option 8 (co-located participates as Demand Response).  \nAnd as discussed below, see infra question F.2, PJM is also exploring with regulators and \ngenerators opportunities to leverage at least 50 hours (or more) of diesel back-up generator \nservice to enhance the available demand response portfolio.  And even where shorter term \nresource adequately may not be directly enhanced by a particular co-location arrangement \n(for example, where new load is not accompanied by additional generation or operational \nflexibility), longer term resource adequacy interests are certainly indirectly supported by \nany resulting increased prices from such scenarios.   \nThe options outlined in Exhibit A are briefly summarized as follows: \nOptions Already Existing in PJM’s Tariff \nOption 1: Load with a separate Point of Interconnection that is Network Load \n \nExisting Option 1 \n*note:  each option is subject to state laws that may \nspecifically define and limit when and how load in a \njurisdiction can be served by a supplier other than a \nfranchised public utility \nLoad with a separate Point of Interconnection (POI) that is Network Load  \n(Existing NITS rules) \nDescription \nThis option is where the load is network load and generation is a capacity resource and they are not \nelectrically co-located.  The load and generation may be physically located at the same location but they \nare electrically connected to the grid separately. \nPJM Preference \nYes - Highest Reliability \nLoad Status \nNetwork \nGeneration Capacity Status \nYes \nPJM obligation to serve \nYes \nLoad System Used and Charged \nNITS (Full load during coincident peak); Energy; Capacity (Full load during coincident peak) \nAncillary Services Used \nReactive, Black Start, Regulation, Sync, Non Sync, Day-ahead Scheduling Reserves"},{"page":10,"startToken":2481,"endToken":2787,"text":"10 \nAncillary Services Charged \nReactive, Black Start, Regulation, Sync, Non Sync, Day-ahead Scheduling Reserves (based on entire \nload) \nGeneration Revenue  \n• Capacity (based on full CIRs) \n• Energy and Ancillary Services (based on entire gen output) \nStudies \n• TO Load Integration study \n•PJM Do No Harm study \n•RTEP process inclusive of Load Forecast  \nLoad included in Load Forecast (RTEP) Yes \nLoad included in RPM Reliability \nRequirement \nYes \nCost Allocation for Interconnection \nUpgrades \n• Supplemental projects pursuant to local TO methodology \n• RTEP upgrades pursuant to RTEP cost allocation \n• No modification to generation. \nSystem Protection Requirements \nN/A \nDemand Response Eligibility \nYes \nTariff Modifications \nNo \n \nOption 1 contemplates load becoming traditional Network Load that takes Network \nIntegration Transmission Service (“NITS”) in accordance with traditional load \ninterconnection processes.  Under this existing option, the load has a separate Point of \nInterconnection with the grid even if physically at the same site.  Because the load is taking \nNITS, the load and generator do not have to be sited at the same location because the load \nand the generation are electrically connected to the grid separately with the load enjoying \nall the benefits of network integration.  For this option, the load uses and pays for NITS, \nEnergy, Ancillary Services, and Capacity.   \nOption 2: Co-located load that is at the same Point of Interconnection but \nseparately metered that is Network Load \n \n \nExisting Option 2 \n*note:  each option is subject to state laws that may \nspecifically define and limit when and how load in a \njurisdiction can be served by a supplier other than a \nfranchised public utility \nCo-located load that is at the same Point of Interconnection (POI) but separately metered that is \nNetwork Load  \n(Existing NITS rules) \nDescription \nThis option is where the load is network load and generation is a capacity resource and they are metered \nseparately \nPJM Preference \nYes - Highest Reliability \nLoad Status \nNetwork"},{"page":11,"startToken":2787,"endToken":3141,"text":"11 \nGeneration Capacity Status \nYes \nPJM obligation to serve \nYes \nLoad System Used and Charged \nNITS (Full load during coincident peak); Energy; Capacity (Full load during coincident peak) \nAncillary Services Used \nReactive, Black Start, Regulation, Sync, Non Sync, Day-ahead Scheduling Reserves \nAncillary Services Charged \nReactive, Black Start, Regulation, Sync, Non Sync, Day-ahead Scheduling Reserves (based on entire \nload) \nGeneration Revenue  \n• Capacity (based on full CIRs) \n• Energy and Ancillary Services (based on entire gen output) \nStudies \n• TO Load Integration study \n•PJM Do No Harm study \n•RTEP process inclusive of Load Forecast \n•Necessary Study \nLoad included in Load Forecast (RTEP) Yes \nLoad included in RPM Reliability \nRequirement \nYes \nCost Allocation for Interconnection \nUpgrades \n• Supplemental projects pursuant to local TO methodology \n• RTEP upgrades pursuant ot RTEP cost allocation \n• Generator for the changes to its facility to accommodate the load \nSystem Protection Requirements \nN/A \nDemand Response Eligibility \nYes \nTariff Modifications \nNo \n \nOption 2 is a co-located configuration, in which the load and generation are, by \nagreement, behind the same Point of Interconnection.  However, in this configuration, the \nload is Network Load and the generation is a Capacity Resource.  Each is separately \nmetered.  The load uses and pays for NITS, Energy, Ancillary Services, and Capacity.  \nAdditionally, the large load is studied and could be connected to the grid pursuant to the \nexisting Transmission Owner/EDC load interconnection process.  For clarity, there is no \nchange to the generator Capacity Interconnection Rights due to this co-located load \nconfiguration.   \nOption 3: Existing Behind the Meter Generation where the load is the customer \n \nExisting Option 3 \n*note:  each option is subject to state laws that may \nspecifically define and limit when and how load in a \njurisdiction can be served by a supplier other than a \nfranchised public utility \nExisting Behind The Meter Generation (BTMG) where the load is the customer \nDescription \nThis option reflects PJM's existing BTMG rules where the load is primary customer and nets with BTMG. \nReliability consideration:  Existing Non-Retail BTMG is annually capped because it does not carry \nreserves equal to the installed reserve margin (net is zero during coincident peak). \nLarge load behind generation was not intended."},{"page":12,"startToken":3141,"endToken":3450,"text":"12 \nPJM Preference \nNot for Large Loads \nLoad Status \nNetwork \nGeneration Capacity Status \nNo \nPJM obligation to serve \nYes \nLoad System Used and Charged \nNITS (Net withdrawal during coincident peak); Energy (Net withdrawal); Capacity (Net withdrawal during \ncoincident peak) \nAncillary Services Used \nReactive, Black Start, Regulation, Sync, Non Sync, Day-ahead Scheduling Reserves \nAncillary Services Charged \nReactive, Black Start, Regulation, Sync, Non Sync, Day-ahead Scheduling Reserves (Net withdrawal) \nGeneration Revenue  \n• Capacity (For portion of CIRs retained) \n• Energy and Ancillary Services (net injection only) \nStudies \n• TO Load Integration study \n•PJM Do No Harm study \n•RTEP process inclusive of Load Forecast \n•Necessary Study \nLoad included in Load Forecast (RTEP) Only if Net Withdrawal >0 during coincident peak \nLoad included in RPM Reliability \nRequirement \nOnly if Net Withdrawal >0 during coincident peak \nCost Allocation for Interconnection \nUpgrades \n• Supplemental projects pursuant to local TO methodology \n• RTEP upgrades pursuant ot RTEP cost allocation \n• Generator for the changes to its facility to accommodate the load \nSystem Protection Requirements \nN/A \nDemand Response Eligibility \nYes if net positive load \nTariff Modifications \nNo \n \nOption 3 utilizes PJM’s existing Behind the Meter (“BTM”) Generation rules.  \nThese rules are explained further below in PJM’s response to question D.iv.  PJM’s BTM \nGeneration rules would require the co-located load to be Network Load.  The rules charge \nload for its net use of the grid, after deducting BTM Generation.  This option is available \nin two configurations.  Either the load and generation are co-located at the same Point of \nInterconnection, or the load is served by municipal utilities or EDCs BTM through a \ndistribution system, if the owner or lessee of such distribution system has consented (which \nis called “Non-Retail” BTM Generation).  The load uses and pays for NITS, Energy, \nAncillary Services, and Capacity based on the net withdrawal quantity and dependent on \nif that withdrawal is during the Peak (NITS and Capacity)."},{"page":13,"startToken":3450,"endToken":3963,"text":"13 \nWhile this option is already available under the Tariff, it was conceived for, and \nhas been implemented for, substantially smaller loads (like a large warehouse with solar \npanels) and not on the scale of large data centers.5  \nNew Potential Options \n \nOption 4: Co-located load with connection to the grid with protections to avoid \ndelivery of system energy to serve the load \n \n \nNew Option 4 \n*note:  each option is subject to state laws that \nmay specifically define and limit when and how \nload in a jurisdiction can be served by a supplier \nother than a franchised public utility \nCo-located load with connection to grid with protections to avoid delivery of system energy to \nserve the load \nDescription \nThis option is when the load is located behind the generation and there are protection mechanisms in \nplace to prevent delivery of energy from the grid to serve the load in the event the generation is \noffline. \nPJM Preference \nLess preferred \nLoad Status \nNot unless designated in a manner consistent with state law \nGeneration Capacity Status \nOnly for portion of Generation > Load \nPJM obligation to serve \nNot unless designated in a manner consistent with state law \nLoad System Used and Charged \nIf not designated Network Load, assuming no withdrawal of energy during coincident peak then no traditional NITS \ncharges. However, system is still used to support co-location and delivery of ancillary services and should be part of \na new rate design. \nAncillary Services Used \nReactive, Black Start, Regulation, Sync, Non Sync, Day-ahead Scheduling Reserves \nAncillary Services Charged \nYes \nGeneration Revenue  \n• Capacity (For portion of CIRs retained) \n• Energy and Ancillary Services if injecting onto the PJM Grid \nStudies \nPJM Necessary Study \nLoad included in Load Forecast \n(RTEP) \nNo for load; only retained CIRs are included in RTEP \nLoad included in RPM Reliability \nRequirement \nNo for load; only retained CIRs are included in RTEP \nCost Allocation for Interconnection \nUpgrades \nGenerator for the changes to its facility to accommodate the load. \nGenerator also responsible for any system upgrades to serve the load. \nSystem Protection Requirements \nYes \nDemand Response Eligibility \nNo \nTariff Modifications \nYes \n \n                                                 \n5 The load in this configuration is not required to carry reserves and may lean on the PJM system when the \nco-located generation is on a full or partial outage or if the load exceeds the rating of the co-located \ngeneration.  Therefore, adding load to PJM without reserves will degrade reliability to worse than 1 in 10 \n(increase loss of load expectation (“LOLE”) to greater than 0.1 days/year).  PJM accommodates some level \nof this configuration through a settlement agreement in 2006 that allows the PJM LOLE to be relaxed from \n1 in 10 years to 1 in 9.5 years.  This analysis is updated each year and, because of the potential reliability \nimpacts of this option, use of this option has been capped at approximately 2000 megawatts (“MW”) of which \nabout 1300 MW are already used.  There are also performance requirements for generation associated with \nthis configuration.  Therefore, large load additions located behind generation are not ideal or contemplated \nunder this existing configuration."},{"page":14,"startToken":3963,"endToken":4291,"text":"14 \n  \nIn this option, where state law permits such a configuration, the load is located \nbehind the Point of Change of Ownership between the Transmission Owner and generator, \nand system protection facilities are installed to prevent delivery of energy from the grid \nshould the generator go offline.  In this configuration, load is not Network Load unless \ndesignated by the customer subject to applicable state law. \nThis configuration has been described as “fully” or “wholly” isolated by others, but \nthis characterization is inconsistent with engineering and economic principles.  This \nconfiguration relies on and takes grid services (for example, ancillary services) and should \npay its fair share of those charges.  Additionally, this configuration carries operational risk \nin that there is a dependency on the protection system to support reliability.  If the \nprotection system should fail,6 the large load would instantly withdraw significant energy \nfrom the system.  While a few of these configurations may seem tolerable to some, the \nanticipation of large quantities of these configurations increases the risk.  Tariff \nmodifications would be needed based on the Commission’s November 1, 2024 Order in \nDocket No. ER24-2172.7 \n \nOption 5: Co-located load with connection to the grid with protections to avoid \ndelivery of system energy to load, but with back-up service from PJM with \npermission \n \nNew Option 5 \n*note:  each option is subject to state laws that \nmay specifically define and limit when and how \nload in a jurisdiction can be served by a supplier \nother than a franchised public utility \nCo-located load with connection to grid with protections to avoid delivery of system energy to \nserve the load or receive back-up service from PJM with advanced authorization \n                                                 \n6 System protection facilities are discouraged per PJM Manual 7.  System Planning Division, PJM Manual \n07: \nPJM \nProtection \nStandards \n(May \n30, \n2019), \nhttps://www.pjm.com/-\n/media/DotCom/documents/manuals/m07.ashx. \n7 PJM Interconnection, L.L.C., Order Rejecting Amendments to Interconnection Service Agreement, Docket \nNos. ER24-2172-000, et al. (Nov. 1, 2024)."},{"page":15,"startToken":4291,"endToken":4721,"text":"15 \nDescription \nThis option is when the load is located behind the generation and there is protection mechanisms in \nplace to prevent delivery of energy from the grid to serve the load in the event the generation is \noffline. It also allows for back-up service from the PJM system with permission. \nPJM Preference \nLess preferred \nLoad Status \nNot unless designated in a manner consistent with state law \nGeneration Capacity Status \nOnly for portion of Generation > Load \nPJM obligation to serve \nNot unless designated in a manner consistent with state law \nLoad System Used and Charged \nIf not designated Network Load, assuming no withdrawal of energy during coincident peak then no \ntraditional NITS charges. However, network is still used to support co-location and delivery of \nancillary services and should be part of a new rate design \nAncillary Services Used \nReactive, Black Start, Regulation, Sync, Non Sync, Day-ahead Scheduling Reserves \nAncillary Services Charged \nReactive, Black Start, Regulation, Sync, Non Sync, Day-ahead Scheduling Reserves (based on entire \nload) \nGeneration Revenue  \n• Capacity (For portion of CIRs retained) \n• Energy and Ancillary Services if injecting onto the PJM Grid  \nStudies \nPJM Necessary Study, reduced generator CIRs studied in RTEP \nLoad included in Load Forecast \n(RTEP) \n• Load - Only if Net Withdrawal >0 during coincident peak. \n• Only CIRs retained included in RTEP. \nLoad included in RPM Reliability \nRequirement \n• Load - Only if Net Withdrawal >0 during coincident peak \n• Only CIRs retained included in RPM \nCost Allocation for Interconnection \nUpgrades \nGenerator for the changes to its facility to accommodate the load. \nGenerator also responsible for any system upgrades to serve the load. \nSystem Protection Requirements \nYes and back-up unit required to take forced outage \nDemand Response Eligibility \nNo \nTariff Modifications \nYes \n \nThis option is the same configuration as Option 4 above, but with the potential for \nthe load to receive back-up service from the grid with PJM’s advanced authorization \n(meaning unilateral action by the generator or load to draw from the grid is not permitted).  \nSuch authorization from PJM would follow coordination by and among the generator \nand/or load, PJM, and the Transmission Owner (for matters relating to generator outages \nor otherwise).  Any PJM approval to take back-up power from the grid would be subject to \nconditions including the potential withholding of authorization or withdrawing of \nauthorization under conditions that may threaten the integrity or reliability of the PJM \nRegion or the regional power system.  This option requires real-time, bespoke operational \ndecision-making to determine whether load can continue to be served.  Tariff modifications \nwould be needed based on the Commission’s order in Docket No. ER24-2172.8 \n                                                 \n8 See id."},{"page":16,"startToken":4721,"endToken":5049,"text":"16 \n \nOption 6: Co-located load that elects to be Network Load and bring its own \ngeneration \n \nNew Option 6 \n*note:  each option is subject to state laws that \nmay specifically define and limit when and how \nload in a jurisdiction can be served by a supplier \nother than a franchised public utility \nCo-located load that elects to be Network Load and bring own generation \nBYOG \nDescription \nThis option provides an opportunity for to bring your own generation with the incentive for faster \ninterconnection when the load is Network Load \nPJM Preference \nYes - maintains Resource Adequacy \nLoad Status \nNetwork \nGeneration Capacity Status \nYes \nPJM obligation to serve \nYes \nLoad System Used and Charged \nNITS (Full load during coincident peak); Energy; Capacity (Full load during coincident peak) \nAncillary Services Used \nReactive, Black Start, Regulation, Sync, Non Sync, Day-ahead Scheduling Reserves \nAncillary Services Charged \nReactive, Black Start, Regulation, Sync, Non Sync, Day-ahead Scheduling Reserves (based on entire \nload) \nGeneration Revenue  \n• Capacity (based on full CIRs) \n• Energy and Ancillary Services (based on entire gen output) \nStudies \n• TO Load Integration study \n•PJM Do No Harm study \n•RTEP process inclusive of Load Forecast \n•Generator Interconnection Study  \nLoad included in Load Forecast \n(RTEP) \nYes \nLoad included in RPM Reliability \nRequirement \nYes \nCost Allocation for Interconnection \nUpgrades \n• Supplemental projects pursuant to local TO methodology \n• RTEP upgrades pursuant to RTEP cost allocation \n• Generator for the generator interconnection \nSystem Protection Requirements \nN/A \nDemand Response Eligibility \nYes \nTariff Modifications \nMaybe \n \nUnder this option, large load additions interconnecting as Network Load could also \nbring to PJM additional generation that could serve as Capacity Resources.  The additional \ngeneration could be in the form of new incremental generation or arrangements with \ngeneration that otherwise has or is scheduled to deactivate.  This path would also be open \nfor existing generation that could serve the energy needs of the large loads so long as the \ngenerator would still be available to PJM as a Capacity Resource if it clears in the capacity \nmarket."},{"page":17,"startToken":5049,"endToken":5338,"text":"17 \nIncentives could be explored to offer faster processing of generation that enters the \nqueue through this option, including by way of example:  (1) providing options for \naccelerating interconnection studies of new generation proposed as part of this option; \n(2) enhancing existing provisional interconnection service options at discrete study points \nin the interconnection cycle so as to accelerate, in  a nondiscriminatory manner, the ability \nof new generation to achieve commercial operation; and (3) states could remove a barrier \nto entry for investment in large load infrastructure by assuming cost responsibility for \ntransmission upgrades in the Regional Transmission Expansion Plan (“RTEP”) pursuant \nto the State Agreement Approach9 to promote state policies to encourage large load \n(including data center) development in their jurisdictions. \nFor this Option 6, a physical co-located configuration can still be utilized but there \nis an additional opportunity for the new generation to enter into a bilateral agreement with \nthe load for financial and contractual purposes.  This scenario would require preparation of \nan interconnection study for the new generation resource.  Further, the large load would be \nstudied and could be connected to the grid pursuant to the existing Transmission \nOwner/EDC load interconnection process.  If transmission system upgrades are necessary \nto connect the load to the grid, the Attachment M-3 Process would be employed, and these \nupgrades would be proposed and studied as supplemental projects (and costs would be \nallocated pursuant to a Transmission Owner’s cost allocation methodology).  Other State \nAgreement Approach-related contracts might also be required on a case-by-case basis.   \nThis option offers a potentially faster interconnection path for generation resources \nsupporting co-located loads in states that want them.  It is possible that Tariff revisions \n                                                 \n9 Operating Agreement, Schedule 6, section 1.5.9 (State Agreement Approach)."},{"page":18,"startToken":5338,"endToken":5704,"text":"18 \nwould be required, especially for purposes of enhancing PJM’s existing provisional \ninterconnection service construct or facilitating options to accelerate interconnection \nstudies of new generation proposed as part of this option. \nOption 7:  Potential new non-capacity backed service as a Transitional Service  \n \n \n \nNew Option 7 \n*note:  each option is subject to state laws that \nmay specifically define and limit when and how \nload in a jurisdiction can be served by a supplier \nother than a franchised public utility \nCo-located load that takes Interruptible Service \n(Load willing to curtail in advance of Emergency Procedures) \nDescription \nThis option provides an opportunity for large load to integrate as a non-capacity backed load where it \navoids capacity costs if willing to curtail to support reliability in advance of emergency conditions.   \nPJM Preference \nYes - maintains Resource Adequacy \nLoad Status \nNetwork (advance curtailment) \nGeneration Capacity Status \nYes \nPJM obligation to serve \nYes but less priority \nLoad System Used and Charged \nNITS (Full load during coincident peak); Energy, Capacity (only for portion that is not non-capacity \nbacked)  \nAncillary Services Used \nReactive, Black Start, Regulation, Sync, Non Sync, Day-ahead Scheduling Reserves \nAncillary Services Charged \nReactive, Black Start, Regulation, Sync, Non Sync, Day-ahead Scheduling Reserves (based on entire \nload) \nGeneration Revenue  \n• Capacity (based on full CIRs) \n• Energy and Ancillary Services (based on entire gen output) \nStudies \n• TO Load Integration study \n•PJM Do No Harm study \n•RTEP process inclusive of Load Forecast \n•Necessary Study \nLoad included in Load Forecast \n(RTEP) \nYes \nLoad included in RPM Reliability \nRequirement \n• No for non-capacity backed load \n• CIRs included in RPM \nCost Allocation for Interconnection \nUpgrades \n• Supplemental projects pursuant to local TO methodology \n• RTEP upgrades pursuant ot RTEP cost allocation \n• Generator for the changes to its facility to accommodate the load \nSystem Protection Requirements \nN/A \nDemand Response Eligibility \nNo \nTariff Modifications \nYes \n \n \nThis potential new option would allow a large load to integrate as Network Load at \na potentially faster pace than under existing load integration frameworks subject to the load \nelecting a new transitional non-capacity backed service offering.  Under this offering, large \nloads would be offered the option to be classified as a non-capacity backed load for a \ntransitional period until any resource adequacy supply/demand imbalances associated with"},{"page":19,"startToken":5704,"endToken":6065,"text":"19 \nthe large load addition could be addressed and the load could assume full Network Load \nstatus with all of its attendant benefits.   \nIn return for agreeing to take non-capacity backed service, the load would avoid \ncapacity costs during the transition period in return for its willingness to curtail load (or \nserve its own load through on-site generation10) in those situations where, by way of \nexample, PJM has identified conditions that may threaten the integrity or reliability of the \nPJM Region or the regional power system. \nPotential variations on this option could be explored with the ultimate goal being \nto enhance resource adequacy and provide opportunities for large loads to efficiently \nconnect to the system by providing incentives for large loads to be more flexible.  The \nadvantage of a physical co-located configuration can still be utilized although all load \nwould be in front of the meter.  Tariff revisions would be required to develop this new type \nof service.   \n \nOption 8: Co-located load participating in Demand Response \n \nNew Option 8 \n*note:  each option is subject to state laws that \nmay specifically define and limit when and how \nload in a jurisdiction can be served by a supplier \nother than a franchised public utility \nCo-located Load  that elects to be Network Load  and that participates as Demand Response  \nDescription \nThis existing option provides an opportunity for the load to be Network Load and participate as a \nDemand Response resource.  Options to operate back-up generation provides a mechanism to serve \nthe co-located load when asked to curtail for DR. This option assume the co-located load and \ngeneration share the same POI. \n \nAdditional review of DR rules and opportunities for relaxation of federal and state emission \nrestrictions provide more incentives. \nPJM Preference \nYes - maintains Resource Adequacy \nLoad Status \nNetwork \nGeneration Capacity Status \nYes \nPJM obligation to serve \nYes \nLoad System Used and Charged \nNITS (Full load during coincident peak); Energy; Capacity (Full load during coincident peak) \nAncillary Services Used \nReactive, Black Start, Regulation, Sync, Non Sync, Day-ahead Scheduling Reserves \nAncillary Services Charged \nReactive, Black Start, Regulation, Sync, Non Sync, Day-ahead Scheduling Reserves (based on entire \nload) \n                                                 \n10 See infra PJM’s response to question F.ii."},{"page":20,"startToken":6065,"endToken":6295,"text":"20 \nGeneration Revenue  \n• Demand Response Revenue \n• Capacity (based on full CIRs) \n• Energy and Ancillary Services (based on entire gen output) \nStudies \n• TO Load Integration study \n•PJM Do No Harm study \n•RTEP process inclusive of Load Forecast \n•Necessary Study \nLoad included in Load Forecast \n(RTEP) \nYes \nLoad included in RPM Reliability \nRequirement \nYes \nCost Allocation for Interconnection \nUpgrades \n• Supplemental projects pursuant to local TO methodology \n• RTEP upgrades pursuant ot RTEP cost allocation \n• Generator for the changes to its facility to accommodate the load \nSystem Protection Requirements \nN/A \nDemand Response Eligibility \nYes \nTariff Modifications \nMaybe \n \nThis option provides an opportunity for the load to be Network Load and participate \nas a Demand Response resource.  Although this option already exists in PJM, there could \nbe an additional review of the PJM Demand Response rules.  Also, there may be \nopportunities for a targeted review of federal and state emission restrictions on back-up \ngeneration that would provide more incentives for this option (see infra the discussion of \ndiesel back-up generators in response to question F.ii).  Options to operate back-up \ngeneration provide a mechanism to serve the co-located load when asked to curtail for \nDemand Response.  This option may enhance resource adequacy under tight system \nconditions in the short term, and realizes other benefits of Network Load status.  For any \nenhancements to the existing demand response product, potential future Tariff revisions \nmay be required."},{"page":21,"startToken":6295,"endToken":6649,"text":"21 \nIII. \nPJM RESPONSE TO COMMISSION QUESTIONS \n \nA. \nGeneral \ni. \nDo you agree with the jurisdictional principles outlined in section \nVI.A and should the Commission reach any other conclusions \nregarding jurisdiction in a final order it may issue in this \nproceeding?  Why or why not? \nPJM Response:    \nAlthough section VI.A of the Commission’s Order outlines the Commission’s \njurisdiction in broad strokes, there is nuance regarding the Commission’s jurisdiction that \nis worth noting and was not addressed in the Order.   \nDue to deregulation at both the state and federal level, there is the potential for \nregulatory gaps with respect to co-located load arrangements.  The FPA was written to \nrespect the state’s traditional role with respect to electricity regulation.  To that end, the \nFPA provides: \n(a) It is declared that the business of transmitting and selling electric \nenergy for ultimate distribution to the public is affected with a public \ninterest, and that Federal regulation of matters relating to generation \nto the extent provided in this subchapter and subchapter III of this \nchapter and of that part of such business which consists of the \ntransmission of electric energy in interstate commerce and the sale \nof such energy at wholesale in interstate commerce is necessary in \nthe public interest, such Federal regulation, however, to extend only \nto those matters which are not subject to regulation by the States. \n(b) The provisions of this subchapter shall apply to the transmission \nof electric energy in interstate commerce and to the sale of electric \nenergy at wholesale in interstate commerce, but shall not apply to \nany other sale of electric energy or deprive a State or State \ncommission of its lawful authority now exercised over the \nexportation of hydroelectric energy which is transmitted across a \nState line. The Commission shall have jurisdiction over all facilities \nfor such transmission or sale of electric energy, but shall not have \njurisdiction, except as specifically provided in this subchapter and \nsubchapter III of this chapter, over facilities used for the generation \nof electric energy or over facilities used in local distribution or only \nfor the transmission of electric energy in intrastate commerce, or"},{"page":22,"startToken":6649,"endToken":6970,"text":"22 \nover facilities for the transmission of electric energy consumed \nwholly by the transmitter. \n(c) For the purpose of this subchapter, electric energy shall be held \nto be transmitted in interstate commerce if transmitted from a State \nand consumed at any point outside thereof; but only insofar as such \ntransmission takes place within the United States.11 \nThe foregoing grants the Commission three categories of jurisdiction:  \n(i) jurisdiction over “the transmission of electric energy in interstate commerce,” \n(ii) jurisdiction over “the sale of such energy at wholesale in interstate commerce,”12 and \n(iii) jurisdiction over the facilities used for such wholesale sales and transmission.   \nIn addition, the FPA expressly limits the Commission’s jurisdiction over:  (i)  sales \nof electricity that are not wholesale sales,13 (ii) facilities used for generation, (iii) local \ndistribution facilities (in other words, not associated with high-voltage transmission of \nelectric energy but where the transmitted power was “stepped down” to distribution \nvoltage), and (iv) facilities for the transmission of electric energy consumed wholly by the \ntransmitter (which does not appear implicated by most co-located load arrangements given \ndifferent identities between transmitter and consumer). \nWhen the FPA was enacted, the industry looked very different than it looks today.  \nGiven industry deregulation, the increased interconnectivity of the grid, and advancements \nin technology, the traditional dividing lines between state and federal jurisdiction have \nsomewhat blurred.  Although Organization of PJM States, Inc. contends that “there is no \nregulatory gap involving co-location arrangements,”14 it is unclear whether that is the case \n                                                 \n11 16 U.S.C. §§ 824(a)-(c). \n12 16 U.S.C. §§ 824(a), (b)(1); see N.Y. v. FERC, 535 U.S. 1, 7–8 (2002) (“New York”). \n13 See S. Cal. Edison Co. v. FERC, 603 F.3d 996, 1000-01 (D.C. Cir. 2010) (regarding station power); Ind. \nMun. Power Agency v. PJM, 173 FERC ¶ 61,243, at PP 89-102 (2020) (same).   \n14 Order at P 18."},{"page":23,"startToken":6970,"endToken":7343,"text":"23 \nacross PJM’s footprint.  The bottom line:  as discussed below, different state laws may \nimpact the permissibility of certain of the potential co-location arrangements summarized \nin Exhibit A and discussed above.15   \nTraditionally, utilities were vertically integrated and operated within a franchised \nservice territory selling bundled electricity to end users at state-regulated retail rates.16  Due \nto this vertical integration, a single company would own the electric generating facilities, \ntransmission lines, and distribution lines needed to serve retail customers.  This market \nstructure was due in part to state law and the Public Utility Holding Company Act of 1935 \n(“PUHCA”) (which was repealed in 2005).17  State laws typically granted an exclusive \nretail franchise within their jurisdictions and these utilities provided bundled electric \nservice, and state regulators and state laws typically defined (and still define) the extent of \na utility’s legal obligation to serve customers.  PUHCA, for its part, broke up a small \nnumber of existing electric utility holding companies into hundreds of smaller, local utility \ncompanies or holding company systems.18   \nOver the last few decades and particularly since the passage of the Public Utility \nRegulatory Policies Act of 1978 (“PURPA”),19 the electric power industry has evolved \n                                                 \n15 See Jon Wellinghoff & Steven Weissman, The Right to Self-Generate as a Grid-Connected Customer, \nEnergy Bar Association, 305 (2015), https://www.eba-net.org/wp-content/uploads/2023/02/11-23-305-326-\nWellinghoff_FINAL-11.10.pdf (“In those areas of the country where competitive retail access to electric \nservice does not exist, . . . [there is] a struggle to determine who has the right to supply all or a portion of the \nelectric energy services necessary to meet a consumer’s needs.”).   \n16 See FERC v. Elec. Power Supply Ass'n, 577 U.S. 260, 266-67 (2016) (“EPSA”). \n17 See Public Utility Holding Company Act of 1935, Pub. L. No. 74-333, 49 Stat. 821 (codified as 15 U.S.C. \n§§ 79-79z-6) (repealed 2005).  \n18 See The Repeal of the Public Utility Holding Company Act of 1935 (PUHCA 1935) and Its Impact on \nElectric \nand \nGas \nUtilities, \nCongressional \nResearch \nService \n(Nov. \n20, \n2006), \nhttps://www.everycrsreport.com/files/20061120_RL33739_19b253d11f6560b7153533b0430a157fe0effb5f\n.pdf.   \n19 Public Utility Regulatory Policies Act of 1978, Pub. L. No. 95-617, 92 Stat. 3117 (codified as 16 U.S.C. \n§ 261)."},{"page":24,"startToken":7343,"endToken":7735,"text":"24 \nfrom one where vertically integrated utility monopolies predominated to an environment \nthat supports more competitive generation supply.  Among other things, PURPA \nintroduced a new category of wholesale sellers exempt from PUHCA’s “integrated public-\nutility system” restriction called Qualifying Facilities (“QFs”)—which were either a \n“cogenerator” or a “small power producer.”  QFs may make retail sales in states where \npermitted to do so. \nA notable exception to the exclusive franchised utility construct that emerged after \nPURPA was customer self-service in the form of commercial and industrial electrical users \n(for example, in the pulp and paper industry) that installed “inside the fence” QF \ncogeneration facilities where permitted by state law.20  Such self-service arrangements \nappear distinguishable from co-location arrangements because co-location arrangements \ngenerally involve the sale of power from generators to intermediaries and then to load.21  \nEven where these self-servicing industrials consumed the entire output of their generation \nfacilities, these industrials still required electric distribution service from the local utility \nto provide power in the event on-site generation was on outage or was insufficient to satisfy \nthe full electrical requirements of the operation.  These industrials were not electrically \nislanded.  In fact, they established and maintained interconnections the terms of which \n                                                 \n20 See generally Jackie S. Levinson & Andrew D. Schifrin, Regulatory and Tax Treatment of Electric \nInterconnection Facilities, Energy Bar Association, 23 Energy L.J. 459, 462 (2002), https://www.eba-\nnet.org/wp-content/uploads/2023/02/6-Vol23_No2_2002_Art_Regulatory-and-Tax.pdf; Douglas M. Roe, \nMusings from Behind-the-Meter:  A 20th Century Model for a 21st Century World?, Energy Bar Association, \n44 Energy L.J. 251, 254-55 & n.16 (2023), https://www.eba-net.org/wp-content/uploads/2023/11/5-Roe251-\n300.pdf (“‘Competition for industrial loads from self-generation was present at the turn of [the twentieth] \ncentury.’”).     \n21 See Constellation Energy Generation, LLC v. PJM Interconnection, L.L.C., Comments of East Kentucky \nPower Cooperative, Inc., Docket No. EL25-20-000, at 3 & n.9 (Dec. 12, 2024) (“EKPC Comments”) (“The \ncolocation issue here is distinguishable from the situation of a load using its own on-site generation resource \nto provide all or part of its power supply, i.e., self- generation. . . .  Even in the case of back-up generation \n(in which the load has generation that it can use to self-supply when power from the utility is not available), \nthe load must comply with state law requirements.”)."},{"page":25,"startToken":7735,"endToken":8133,"text":"25 \n(including any back-up service) were frequently addressed in separately negotiated \nagreements or in utilities’ state-regulated retail tariffs.   \nSeveral other major changes in the regulatory landscape call into question the \nassumption that states necessarily regulate matters outside of the Commission’s \njurisdiction or over which the Commission has not affirmatively regulated.  Starting in the \n1990s the Commission ordered utilities that offered unbundled transmission service either \nvoluntarily or as the result of state retail choice programs, to offer non-discriminatory \naccess to their transmission systems.22  The Energy Policy Act of 1992 amended PUHCA \nto create Exempt Wholesale Generators (“EWGs”), which would—like a QF—be exempt \nfrom PUHCA’s restrictions.  This development further increased the number and diversity \nof potential wholesale generation competitors (as EWGs were not fuel-type limited).  By \ndefinition, an EWG engages in wholesale transactions and cannot make retail sales.23  Yet \nunder certain co-located load arrangements (Options 4 and 5 in Exhibit A, for example), \nEWGs could seek to sell power to an intermediary that then engages retail sales.24 \n                                                 \n22 See generally New York (upholding Order No. 888 and surveying industry regulatory developments); see \nPromoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Services by \nPublic Utilities; Recovery of Stranded Costs by Public Utilities and Transmitting Utilities, Order No. 888, \n75 FERC ¶ 61,080, 1991–1996 FERC Stats. & Regs., Regs. Preambles ¶ 31,036 (1996), order on reh’g, \nOrder No. 888-A, 78 FERC ¶ 61,220, 1996–2000 FERC Stats. & Regs., Regs. Preambles ¶ 31,048, order on \nreh’g, Order No. 888-B, 81 FERC ¶ 61,248 (1997), reh’g denied, Order No. 888-C, 82 FERC ¶ 61,046 \n(1998), aff’d in part & remanded in part sub nom. Transmission Access Policy Study Group v. FERC, 225 \nF.3d 667 (D.C. Cir. 2000), aff’d sub nom. New York v. FERC, 535 U.S. 1 (2002). \n23 18 C.F.R. § 366.1.  \n24 See, e.g., Jersey Cent. Power & Light Co., 1996 N.J. PUC Lexis 23 (May 23, 1996); O’Brien (Parlin) \nCogeneration, Inc., Application of O’Brien (Parlin) Cogeneration, Inc. for Determination of Exempt \nWholesale Generator Status, Docket No. EG96-60-000 (Apr. 29, 1996); O’Brien (Parlin) Cogeneration, Inc., \n75 FERC ¶ 61,326 (1996).  Congress would have to amend the FPA to allow EWGs to provide needed energy \ndirectly to co-located loads.  See Todd Glass, Achieving AI dominance through competitive power markets, \nUtility Drive, https://www.utilitydive.com/news/ai-data-centers-competitive-power-markets/738275/ (last \nvisited Mar. 21, 2025)."},{"page":26,"startToken":8133,"endToken":8698,"text":"26 \nAs a result of this unbundling, electric utilities restructured from vertically \nintegrated companies, to separately owning generation, transmission, and distribution \nfacilities.25  In addition, the Energy Policy Act of 2005 repealed the Public Utility Holding \nCompany Act of 1935.26  As a result, “any type of entity can own any type of utility asset \nand perform any type of electric service function, in any location.”27 \nFurther, between 1996 and 2000, many states in the PJM Region assessed whether \nto introduce competition for retail electricity service into historically exclusive service \nterritories.28  This is a significant point because under states that did not pursue \nderegulation, a state’s exclusive retail franchise territory law may restrict non-franchised \nsuppliers from serving co-located load.29  Further, in deregulated states, state law may (or \n                                                 \n25 EPSA at 267 (“Decades ago, state or local utilities controlled their own power plants, transmission lines, \nand delivery systems, operating as vertically integrated monopolies in confined geographic areas. That is no \nlonger so. Independent power plants now abound, and almost all electricity flows not through ‘the local power \nnetworks of the past,’ but instead through an interconnected ‘grid’ of near-nationwide scope.”). \n26 Energy Policy Act of 2005, Pub. L. No. 109-58, §§ 1261-77, 119 Stat. 594. \n27 Scott Hempling, Regulating Public Utility Performance: The Law of Market Structure, Pricing and \nJurisdiction 93 (2nd ed. 2021) (“Regulating Public Utility Performance”).  \n28 See Regulating Public Utility Performance at 93 & n.25 (identifying Delaware, District of Columbia, \nIllinois, Maryland, Michigan, New Jersey, Ohio, and Pennsylvania as among the states that allow retail \nelectricity competition).     \n29 Some parties have advanced arguments about such state law particulars in related dockets. See, e.g., EKPC \nComments at 3 (“Kentucky law is clear that ‘each retail electric supplier shall have the exclusive right to \nfurnish retail electric service to all electric-consuming facilities located within its certified territory.’” (citing \nKY. REV. STAT. ANN. § 278.018(1) (West))); Baltimore Gas & Electric Co., Comments of Southern \nMaryland Electric Cooperative, Inc., Docket No. EL24-149-000, at 3 (Oct. 30, 2024) (“[C]onsistent with \ncurrent Maryland law, a Maryland co-located data center or other large load is a ‘retail electric customer’ \nsimilar to any other resident or business situated in [Southern Maryland Electric Cooperative, Inc’s] southern \nMaryland electric service territory.  Only an ‘electric company’ with relevant franchise rights and other \nnecessary approvals is authorized to serve ‘retail electric customers’ in Maryland.”); State ex rel. Utils. \nComm’n v. N.C. Waste Awareness & Reduction Network, 255 N.C. App. 613, 618 (2017) (“Duke Energy has \nbeen granted an exclusive right to provide electricity in return for compensation within its designated territory \nand with that right comes the obligation to serve all customers at rates and service requirements established \nby the Commission.”), aff’d sub nom., 812 S.E.2d 804 (N.C. 2018).  Further, as others have explained, “some \nstates may require that franchise public utilities not co-locate load at existing generation facilities built and \npaid for by its retail customers.  Additionally, state law may specifically define and limit when load in a \nfranchise public utility’s territory can be served by a supplier other than the franchise public utility.”  Large \nLoads Co-located at Generation Facilities, Comments of Dominion Energy Services, Inc., Docket No. \nAD24-11-000, at 10 (Dec. 9, 2024) (“Dominion Energy Comments”); Dominion Energy Comments at 2 \n(noting Dominion Energy Virginia is a vertically integrated utility that owns regulated electric transmission,"},{"page":27,"startToken":8698,"endToken":9126,"text":"27 \nmay not) today (or in the future) require co-located load suppliers to be licensed energy \nproviders and/or otherwise impose limitations on such suppliers by, for example, obliging \nthe designation of the load as Network Load, with or without netting, or take certain types \nof transmission service that could compel the designation of co-located load as Network \nLoad.30 \nState law does not necessarily regulate companies making sales to these end users.  \nThere are instances where industrial customers’ self-supply of electricity has been found \nto fall outside the scope of public utility regulation.  Indeed, even when one large industrial \nend-user sold electricity to another large industrial end-user within the same complex, such \nsales were found neither to render the seller a public utility under state law nor violate the \nlocal utility’s exclusive franchise territory because it was not offering such sales to the \npublic generally.31 \nBy way of further example, Pennsylvania defines a “public utility” as a person or \ncorporation that transmits or distributes electricity “to or for the public for \ncompensation.”32  To the extent a company is found to be a public utility, it would be \nsubject to regulation by the Pennsylvania Public Utilities Commission (“PA PUC”).  \n                                                 \ndistribution, and generation assets (including two nuclear facilities) and Northern Virginia is in its franchise \nservice territory).  Under Virginia Law, Dominion Energy Virginia appears to have been granted an exclusive \nfranchise by the State Corporation Commission to serve customers as a public utility within its certificated \nservice territory.  See VA. CODE ANN. § 56-265.3A.  It is a monopoly provider of such service and, in \naccord with that franchise, has an obligation to provide it to all customers within its territory.  See VA. CODE \nANN. §§ 56-265.4, 56-234A. \n30 Some states appear to have jurisdiction over the terms and conditions in state retail tariffs like Electric \nGeneration Supplier Coordination Tariffs or Supplier Coordination Tariffs.   \n31 See, e.g., U.S. Steel Corp. v. N. Ind. Pub. Serv. Co., 951 N.E.2d 542, 554-57 (Ind. Ct. App. 2011) (finding \nthat Steel Producer’s sale of electricity to industrial end user within the same complex did not render the \nSteel Producer a public utility as defined by the Indiana code).  Given the national security interests that may \nattach to the AI infrastructure co-located load arrangements, it is not clear if state regulators would view new \ndata center loads as being in furtherance of the public interest and the public generally, such that state \nregulation may be appropriate. \n32 66 PA. CONS. STAT. § 102(1)(i) (regarding definition of “public utility”)."},{"page":28,"startToken":9126,"endToken":9549,"text":"28 \nHowever, the PA PUC and Pennsylvania appellate courts have found that service to a \nclosed, limited, and privileged class of customers pursuant to contract is not service to the \n“public” and, therefore, PA PUC jurisdiction does not attach.33  In Pennsylvania, these \ndeterminations are made based on the control over who can receive service and whether \nthe corporation holds itself out as willing to provide service to the public.34  Because the \ncompanies agreeing to sell electricity to data centers may not be offering that service to the \npublic generally, it is possible that courts and state regulators would find that these sales \nlikely will not be subject to public utility regulation in Pennsylvania.35  PJM is unaware of \nany Pennsylvania state law objections to the proposed co-location arrangement advanced \nin Docket No. ER24-2172 relating to the Third Revised Co-Located Load Susquehanna \nNuclear, LLC (“Susquehanna”) Interconnection Service Agreement (“ISA”) docket.36   \nPennsylvania is not the only state that has declined to regulate sales to large end \nusers in this way.  New Jersey has similarly declined to exercise public utility regulation \nover sales to large end users.  In 1999, the New Jersey Board of Public Utilities disclaimed \njurisdiction over a special purpose entity that was created to resell power from a \ncogeneration plant to an inside-the-fence retail customer to allow the owner of the \n                                                 \n33 See, e.g., Drexelbrook Assocs. v. Pa. Pub. Util. Comm’n, 212 A.2d 229 (Pa. Super. Ct. 1964) (holding that \na landlord who controlled who could be a tenant via a lease was not a public utility). \n34 See, e.g., Warwick Water Works, Inc. v. Pa. Pub. Util. Comm’n, 699 A.2d 770 (Pa. Commw. Ct. 1997) \n(holding that condo association was a public utility because it did not control who could become a condo unit \nowner). \n35 The Philadelphia Navy Yard is similarly regarded as not being subject to Pennsylvania public utility \nregulation, and holds itself out as an unregulated electric grid.  See Kevin B. Jones, et al., The Urban \nMicrogrid:  Smart Legal and Regulatory Policies to Support Electric Grid Resiliency and Climate Mitigation, \nFordham \nUrban \nLaw \nJournal, \n1695, \n1717-19 \n(2014), \nhttps://ir.lawnet.fordham.edu/cgi/viewcontent.cgi?article=2552&context=ulj (“The microgrid structure at \nthe Navy Yard is an anomaly—it operates independent of state regulation” because it is not a “public utility” \nunder applicable law).   \n36 See, e.g., PJM Interconnection, L.L.C., Comments of the Pennsylvania Public Utility Commission, Docket \nNo. ER24-2172-000 (July 10, 2024) (identifying no state law obstacles)."},{"page":29,"startToken":9549,"endToken":9965,"text":"29 \ncogeneration unit to obtain EWG status from the Commission.37  Under New Jersey law, a \npublic utility is defined as an entity that owns, operates, or manages any electrical light \nplant or equipment for public use.38  In that case, because the entity created would not own \nor operate any equipment, the New Jersey Board of Public Utilities declined to regulate \nthat entity as a public utility.39 \nAs these examples illustrate, there is risk in painting with too broad a brush.  State \nlaw regulatory particulars may, in certain instances, determine whether particular co-\nlocation arrangements will be regulated by the states or permitted by states with a \nfranchised public utility model.  As such, the propriety of the co-location arrangements \nproposed in Exhibit A are subject to different state law requirements that could disqualify \ncertain options.   \nTransmission \nThe Commission’s jurisdiction over the ‘“the transmission of electric energy in \ninterstate commerce,”’ 16 U.S.C. § 824(b)(1), extends to energy ‘“transmitted from a State \nand consumed at any point outside thereof.”’40  A jurisdictional determination, therefore, \n                                                 \n37 See Jersey Cent. Power & Light Co., 1996 N.J. PUC Lexis 23 (May 23, 1996); O’Brien (Parlin) \nCogeneration, Inc., Application of O’Brien (Parlin) Cogeneration, Inc. for Determination of Exempt \nWholesale Generator Status, Docket No. EG96-60-000 (Apr. 29, 1996); O’Brien (Parlin) Cogeneration, Inc., \n75 FERC ¶ 61,326 (1996). \n38 Jersey Cent. Power & Light Co., 1996 N.J. PUC Lexis 23, at *7. \n39 Id. at *8.  The Commission’s precedent regarding what is acceptable to do through an affiliate while \nretaining EWG status is somewhat at odds.  For example, for purposes of determining whether a generating \nunit qualifies as an EWG under the Public Utility Holding Company Act of 1935, the Commission has found \nthat a company cannot qualify for EWG status if it is engaging in any business even if the company transfers \nthe relevant business to an affiliate.  See PSEG Fossil, LLC, 95 FERC ¶ 61,405 (2001) (rejecting company’s \nrequest to confirm EWG status if the company transferred business activities other than wholesale sales of \nelectricity to an affiliate because allowing the company to transfer the business to an affiliate would “elevate \nform over substance”).  However, the Commission has allowed a company to retain EWG status while selling \npower to an end-user through an affiliate that was created specifically to effectuate the sale to the end-user.  \nO’Brien Parlin Cogeneration, 75 FERC ¶ 61,326 (1996). \n40 Fed. Power Comm’n v. Fla. Power & Light Co., 404 U.S. 453-54 (1972)."},{"page":30,"startToken":9965,"endToken":10308,"text":"30 \nturns on a factual question regarding the flow of energy.41  To find the Commission has \njurisdiction over wholesale transmission, there must be substantial evidence of energy \nflowing across state lines.42  However, there is no requirement to trace individual electrons \nto make a jurisdictional finding (as it would not be possible to do so).  Instead, where a \nutility’s lines are connected to the interstate grid—even indirectly—this can be sufficient \nto support a finding of interstate transmission due to the nature of how electricity flows.43  \nIn this regard, the Commission’s jurisdiction can be established through circumstantial \nevidence that interstate transmission has taken place.44 \n \nAt a minimum, co-located arrangements implicate the Commission’s transmission \njurisdiction due to PJM’s provision of ancillary services and in light of the wholesale sales \ntaking place over certain facilities.  Even to the extent a co-located data center is primarily \nobtaining energy from a co-located generator, that data center will be interconnected to the \ngrid such that it will benefit from PJM’s provision of ancillary services, including load \nfollowing, frequency regulation, and black start.  Therefore, at a minimum, the \nCommission has jurisdiction regarding the transmission service associated with the \nancillary services utilized in co-location arrangements.  These ancillary services cannot be \ndelivered without the grid.   \n                                                 \n41 Id. at 454-55.   \n42 Id. at 458.   \n43 New York at 7–8 (“It is only in Hawaii and Alaska and on the ‘Texas Interconnect’—which covers most of \nthat State—that electricity is distributed entirely within a single State.  In the rest of the country, any \nelectricity that enters the grid immediately becomes a part of a vast pool of energy that is constantly moving \nin interstate commerce.  As a result, it is now possible for power companies to transmit electric energy over \nlong distances at a low cost.” (footnote omitted)). \n44 Ind. & Mich. Elec. Co. v. Fed. Power Comm’n, 365 F.2d 180 (7th Cir. 1966) (finding evidence that there \nwas not sufficient generation in state to meet the load as sufficient to show an interstate transmission took \nplace)."},{"page":31,"startToken":10308,"endToken":10614,"text":"31 \n \nFurther, the Commission’s jurisdiction over transmission service in interstate \ncommerce is also necessarily implicated in matters relating to co-located load arrangements \nwhere generator interconnections are being modified.  The Commission has jurisdiction \nover interconnections to the grid, and no entities are disputing the Commission’s \njurisdiction over such interconnections, including modifications to add load (which again \nmay include a wholesale sale and transmission).45 \nWholesale Sales \nThe FPA empowers the Commission to regulate wholesale sales of electricity (i.e., \nsales for resale) in interstate commerce, but reserves to the states the authority to regulate \nall other sales.46  The Commission’s jurisdiction extends to sales for resale even to the \nextent such sales are taking place entirely within one state provided sale involves electricity \nflowing across states lines.47  Given the interconnectivity of the grid, advancements in \ntechnology, and industry deregulation, whether or not a wholesale sale has taken place has \nbecome an increasingly complicated question.  Moreover, the way the Commission has \ngone about answering that question depends on the context and has evolved over time. \n                                                 \n45 Standardization of Generator Interconnection Agreements and Procedures, Order No. 2003, 104 FERC \n¶ 61,103 (2003), order on reh’g, Order No. 2003-A, 106 FERC ¶ 61,220, order on reh’g, Order No. 2003-\nB, 109 FERC ¶ 61,287 (2004), order on reh’g, Order No. 2003-C, 111 FERC ¶ 61,401 (2005), aff’d sub nom. \nNat’l Ass’n of Regul. Util. Comm’rs v. FERC, 475 F.3d 1277 (D.C. Cir. 2007), cert. denied, 552 U.S. 1230 \n(2008) (the Commission will continue to have exclusive jurisdiction over the rates, terms, and conditions in \nservice agreements). \n46 Order at P 67. \n47 Fed. Power Comm’n, 376 U.S. 205 (upholding Federal Power Commission jurisdiction over sales of \nelectric energy at wholesale in interstate commerce where a sale was intrastate but power flowing originated \nout of state)."},{"page":32,"startToken":10614,"endToken":10893,"text":"32 \nii. \nDoes the Tariff sufficiently address co-location arrangements with \nrespect to each issue listed in this order?  Please include specific \ntariff provisions or other governing documents that may apply. \nPJM Response:    \nPJM’s Tariff remains just and reasonable.  The Tariff today permits co-located \nloads to interconnect through existing load interconnection processes, albeit processes \nwhereby the load is designated Network Load and reported to PJM via the Transmission \nOwners/Load Serving Entities/EDCs.  Certain entities may prefer, for their own business \nreasons, alternative pathways to co-location.  But such preferences do not render the Tariff \nunjust and unreasonable because they do not accommodate such business goals while \nproviding alternative pathways to service.48  \nNevertheless, clarifications and enhancements could well be in order given that this \nis an evolving area and Tariff provisions did not contemplate the type of arrangements at \nissue in this docket or their implications.  PJM is committed to facilitating and supporting \nco-location arrangements where permitted by applicable state law.  PJM is proposing \nvarious options to facilitate the development of Artificial Intelligence (“AI”)-infrastructure \nas discussed above and in Exhibit A to this filing.  Pending Commission and stakeholder \ninput, PJM remains open to modifying its Tariff as necessary to clarify any rates, terms, or \nconditions relating to co-location arrangements to provide the industry with needed \nregulatory clarity, certainty, and optionality.  \nAs noted previously, given the national interest in development of data centers to \nensure the domestic development of AI (among other reasons), PJM’s efforts would be \ngreatly assisted by Commission guidance as to the reasonableness of any of the existing \n                                                 \n48 See Anbaric Dev. Partners, L.L.C. v. PJM Interconnection, L.L.C., 171 FERC ¶ 61,241 (2020)."},{"page":33,"startToken":10893,"endToken":11155,"text":"33 \nand proposed options for co-located load set forth in Exhibit A and described in this \nsubmittal.  Moreover, progress on these issues would be greatly enhanced by the \nCommission setting a deadline for either submittals of a compliance filing or Section 205 \nfilings to provide a clear pathway of options that meet the Commission’s and industry’s \nshared interests in advancing this important issue.  \niii. \nIf the Tariff does not sufficiently address co-location arrangements, \nhow should the Tariff be modified to do so?  As part of your answer, \naddress whether portions of the Guidance Document may serve as \na just and reasonable and not unduly discriminatory or preferential \nreplacement rate.  Alternatively, address whether existing rules in \nthe Tariff may or should be modified to address co-location \narrangements. \nPJM Response:    \nAs a threshold matter, PJM rescinds its previously issued Guidance Document \npending Commission guidance in this docket about a Commission-approved path forward \n(including the propriety of Option 4).  As explained in PJM’s submissions in Docket \nNo. EL25-20, the heavily caveated Guidance Document was issued by PJM as an initial \nattempt to provide limited guidance after over a year’s worth of unfruitful stakeholder \ndiscussions.  The Commission has rejected a modified ISA informed by this Guidance \nDocument.49  \nIn this submittal, PJM has set forth possible options for co-location. Some options \nare already embodied in the existing Tariff while others would require new or enhanced \nTariff provisions.  Stakeholder and Commission feedback on these and other options is \nnecessary, as is Commission guidance both on the propriety of proposed options and also \n                                                 \n49 See Docket No. ER24-2172."},{"page":34,"startToken":11155,"endToken":11457,"text":"34 \nthe timeline for any additional compliance or Section 205 filings to implement such \nguidance.   \niv. \nParties may also address how co-located loads are similar to or \ndisparate from other types of arrangements where load and \ngeneration share the same point of interconnection (such as Behind \nthe Meter Generation as defined in PJM’s Tariff or non-retail \nbehind the meter generation) and should consider how any \nproposed replacement rate would interact with these other \narrangements.   \nPJM Response:    \nThe co-located load arrangements at issue here, large data centers, could be viewed \nas similar to BTM Generation that currently exists under PJM’s Tariff (as reflected in \nExhibit A, Option 3).  But as explained herein, the BTM Generation paradigm does not fit \nco-location arrangements particularly well because it was not designed with large load co-\nlocation in mind. \nBTM Generation is defined as: \n[A] generation unit that delivers energy to load without using \nthe Transmission System or any distribution facilities (unless the \nentity that owns or leases the distribution facilities has consented to \nsuch use of the distribution facilities and such consent has been \ndemonstrated \nto \nthe \nsatisfaction \nof \nthe Office \nof \nthe \nInterconnection); provided, however, that Behind The Meter \nGeneration does not include (i) at any time, any portion of such \ngenerating unit's capacity that is designated as a Generation \nCapacity Resource; or (ii) in an hour, any portion of the output of \nsuch generating unit that is sold to another entity for consumption at \nanother electrical location or into the PJM Interchange Energy \nMarket.50 \nAs PJM described in 2004 when it proposed its BTM Generation Tariff revisions, \nBTM Generation “refers to generating units that are located with load at a single electrical \nlocation such that no transmission or distribution facilities are used to deliver energy from \n                                                 \n50 Tariff, Part I, Definitions – A - B."},{"page":35,"startToken":11457,"endToken":11893,"text":"35 \nthe generating unit to the load.”51  This definition was subsequently expanded to permit \ninclusion of municipals and EDCs (“Non-Retail”) that use distribution facilities to serve \nloads, with the consent of the owner or lessee of the distribution facilities.52  Notably, \n“BTM[] G[eneration] netting is only available to entities that have Network Integration \nTransmission Service agreements with PJM[,]”53 and are thus taking NITS, as the netting \nprovisions appear in PJM’s NITS Tariff.54 \nAlthough all load served by BTM Generation must be designated Network Load \n(as the Tariff does not exempt such load from the definition of Network Load), PJM’s BTM \nGeneration rules permit a different rate treatment in the form of netting of loads served \nBTM.  Under such netting provisions, the Network Customer’s daily load “does not include \nload served by operating Behind The Meter Generation.”55  The extent to which netting \ncould or should apply to co-located data center load is not clear at this time.   \nMoreover, while the BTM Generation netting concept was justified as a means of \nrecognizing that certain market participants “rely to a lesser degree on the PJM integrated \n                                                 \n51 PJM Interconnection, L.L.C., 107 FERC ¶ 61,113, at P 4 (2004).   \n52 PJM Interconnection, L.L.C., 113 FERC ¶ 63,024 (2005), aff’d, 113 FERC ¶ 61,279.   \n53 Operations Planning Division, PJM Manual 14D: Generator Operational Requirements, PJM \nInterconnection, \nL.L.C., \nAppendix \nA \n¶ 4 \n(Dec. \n18, \n2024), \nhttps://www.pjm.com/-\n/media/DotCom/documents/manuals/m14d.pdf (“PJM Manual 14D”).   \n54 Tariff, Part III, sections 34.2 and 34.3. \n55 Id. at section 34.2; PJM Manual 14D, Appendix A ¶ 6.  The load in this configuration is not required to \ncarry reserves and may lean on the PJM system when the co-located generation is on a full or partial outage \nor if the load exceeds the rating of the co-located generation.  Therefore, adding load to PJM without reserves \nwill degrade reliability to worse than 1 in 10 (increase loss of load expectation (LOLE) to greater than 0.1 \ndays/year).  PJM accommodates some level of this configuration through a settlement agreement in 2006 that \nallows the PJM LOLE to be relaxed from 1 in 10 years to 1 in 9.5 years.  This analysis is updated each year \nand historically has resulted in a cap of approximately 2000 MW of which about 1300 MW is already used.  \nTariff, Part III, section 34.3; PJM Manual 14D, Appendix A ¶ 66.  There are also performance requirements \nfor generation associated with this configuration.  Therefore, large load additions located behind generation \nis not ideal or was contemplated."},{"page":36,"startToken":11893,"endToken":12223,"text":"36 \ntransmission system to serve load,”56 20-years later cost causation principles may dictate a \ndifferent outcome for co-located data center loads that appear to have different customer \nprofile and load characteristics.57  At the very least, co-located data center configurations \nappear to require certain ancillary services (load following) and black start service.  In \norder for a co-location arrangement (i.e., the generator plus data center) to obtain these \nservices, the grid itself must exist.  Ancillary services pass through transmission lines, not \nthe air.  Therefore, cost causation principles appear to support allocating co-located \narrangements ancillary service costs (at a minimum).  Further, simple netting may not \ncapture the costs “caused” by co-located data center arrangements.  Indeed, it is possible \nthat such arrangements (depending on how they are structured) could avoid all costs \nbecause they would always net to zero (meaning the entire data center load is supplied by \nthe co-located generator).   \nIn addition, the current BTM Generation concept has been used by relatively small \nloads and there is a Tariff cap on non-retail BTM Generation.  Allowing very large loads \nlike data centers to net is problematic because loads in this configuration do not carry \nreserves.  Planning and resource adequacy will not account for loads in this configuration.  \nSee supra Section II, discussion of Option 3 including note 5 and accompanying text. \nIn sum, discussions in the record regarding PJM’s BTM Generation rules raise \nquestions about the status of those rules.  PJM is open to exploring whether large, co-\nlocated load additions can and should be differentiated from instances where the current, \nBTM Generation rules apply and whether the 20-year-old method of allocating costs \n                                                 \n56 PJM Interconnection, L.L.C., 107 FERC ¶ 61,113, at P 7.   \n57 See generally Cities of Bethany v. FERC, 727 F.2d 1131, 1138 (D.C. Cir. 1984) (recognizing different rates \ncould be charged to different customer groups); Ala. Elec. Coop., Inc. v. FERC, 684 F.2d 20, 27-28 (D.C. \nCir. 1982) (explaining undue discrimination)."},{"page":37,"startToken":12223,"endToken":12504,"text":"37 \npursuant to the BTM Generation netting rules remains consistent with cost causation \nprinciples. \nB. \nTransmission Service \ni. \nPlease explain whether and to what extent different configurations \nof co-located load rely on or otherwise use the transmission system \nto receive power, directly or indirectly, from the co-located \ngenerator. \nPJM Response:    \nPlease see the chart attached as Exhibit A to this submission and the Executive \nSummary which describes the various options identified, which explain how different \nconfigurations rely on the transmission system.  By way of further response, PJM also \ndirects the Commission to the statement of Stu Bresler filed in the Technical Conference, \nDocket No. AD24-11, which is attached hereto as Exhibit B.58 \nii. \nPlease explain whether and to what extent different co-location \nconfigurations impose costs on the transmission system or increase \ntransmission costs allocated to other parties.  How can those costs \nbe approximated, given that certain co-location configurations may \nchange power flows on the grid and necessitate upgrades to the \ntransmission system?  Retail loads typically take service from \nwholesale entities that pay for Network Integration Transmission \nService that allocates these costs; co-located loads may not.  \nNetwork Loads pay directly for Network Integration Transmission \nService.  How should PJM estimate the effects that different \nconfigurations of co-located load have on the transmission system?  \nShould these costs be passed through to co-location arrangements \nin some way, and, if so, how?   \nPJM Response:    \nPJM looks forward to continued engagement with the Transmission Owners and \nother stakeholders on these important questions of cost allocation, in particular how PJM \n                                                 \n58 Large Loads Co-located at Generation Facilities, Statement of Frederick S. “Stu” Bresler on Behalf of \nPJM Interconnection, L.L.C., Docket No. AD24-11-000 (Nov. 4, 2024)."},{"page":38,"startToken":12504,"endToken":12877,"text":"38 \nshould estimate the effects that different configurations of co-located load have on the \ntransmission system and how costs should be passed through.  A few initial observations \ninclude that incremental load gives rise to incremental system costs.  But the extent of those \ncosts appears to vary based on the nature of the particular co-location arrangement under \ndiscussion.  PJM’s identified options attempt to follow this causal approach when \ndiscussing potential grid services consumed and associated charges.  In some co-location \narrangements, it may be worthwhile to consider new rate design constructs and compare \nthem to see how they align with cost causation principles.  These are details that PJM and \nits stakeholders must continue to work through together.   \niii. \nPlease explain whether co-location arrangements are or should be \nrequired to take Network Integration Transmission Service or \nPoint-to-Point Transmission Service; or whether a more tailored \nnew category of transmission service is warranted.  Please also \naddress any cost allocation implications of your position on this \nissue. \nPJM Response:     \nPlease see the chart attached as Exhibit A to this submission.  \nBy way of further response, PJM continues to prefer that co-location arrangements \nbe designated “Network Load”59 in front of the meter.  This may be required in some states \npursuant to state exclusive franchise territory law, and it may otherwise follow in \njurisdictions where the load is designated as such consistent with PJM’s Tariff.  However, \n                                                 \n59 Tariff, Part I, Definitions – L - M - N (“Network Load” shall mean the load that a Network Customer \ndesignates for Network Integration Transmission Service under Tariff, Part III.  The Network Customer’s \nNetwork Load shall include all load (including losses, Non-Dispatched Charging Energy, and Load Serving \nCharging Energy) served by the output of any Network Resources designated by the Network Customer.  A \nNetwork Customer may elect to designate less than its total load as Network Load but may not designate \nonly part of the load at a discrete Point of Delivery.  Where an Eligible Customer has elected not to designate \na particular load at discrete points of delivery as Network Load, the Eligible Customer is responsible for \nmaking separate arrangements under Tariff, Part II for any Point-To-Point Transmission Service that may be \nnecessary for such non-designated load.  Network Load shall not include Dispatched Charging Energy.”)."},{"page":39,"startToken":12877,"endToken":13521,"text":"39 \nPJM does present two options (Option 4 and 5) where the co-located load may not be \ndesignated as Network Load depending on specific state laws.   \nPJM prefers “Network Load” status because there is: \n• Less operating complexity and reduced dependence on protective schemes, which \nare designed to address N-1 conditions and can misoperate;60 \n• More reliable service for these critical loads;61 \n• Enhanced ability to manage load curtailment priority in emergency conditions;62 \n• Greater access to potential Demand Response capabilities of large co-located loads, \nincluding from switching to backup generation (e.g., diesel units) on site; 63 \n• More comprehensive and holistic system planning based on Network Load status; \nand64 \n                                                 \n60 See PJM Interconnection, LLC, Exelon and AEP Request for Leave to Answer and Answer to Susquehanna \nNuclear LLC, PJM, Constellation, Vistra, Calpine, and PPL, Docket No. ER24-2172-000, at 23 (July 17, \n2024) (“We know that a unit at this facility had an unplanned outage in November 2023, and it appears no \nload was dropped—suggesting that the load just relied on PJM for its supply.”); Event Notification Report \nfor November 13, 2023, United States Nuclear Regulatory Commission, https://www.nrc.gov/reading-\nrm/doc-collections/event-status/event/2023/20231113en.html (last visited Mar. 21, 2025).   \n61 When a customer takes Network Service, the transmission provider (here, PJM) offers the Network \nCustomer the ability to serve its Network Load in a manner comparable to that in which each Transmission \nOwner utilizes the Transmission System to serve its Native Load Customers consistent with their obligation \nto serve.  Tariff, Part III, Preamble (“Network Integration Transmission Service allows the Network \nCustomer to integrate, economically dispatch and regulate its current and planned Network Resources to \nserve its Network Load in a manner comparable to that in which each Transmission Owner utilizes the \nTransmission System to serve its Native Load Customers.  Network Integration Transmission Service also \nmay be used by the Network Customer to deliver economy energy purchases to its Network Load from non-\ndesignated resources on an as-available basis without additional charge.”); Tariff, Part I, Definitions — L - \nM - N (\"Native Load Customers\" defined as “the wholesale and retail power customers of a Transmission \nOwner on whose behalf the Transmission Owner, by statute, franchise, regulatory requirement, or contract, \nhas undertaken an obligation to construct and operate the Transmission Owner's system to meet the reliable \nelectric needs of such customers.”).  \n62 See Tariff, Part III, section 33 (Load Shedding and Curtailments).   \n63 See infra PJM response to question F.ii.   \n64 The transmission provider incorporates the Network Customer’s resources and loads into its own long-\nterm planning.  See Transmission Access Pol'y Study Grp. v. FERC, 225 F.3d 667, 725 (D.C. Cir. 2000).  In \nthe context of new Network Load, for planning purposes, PJM assumes that it must serve the customer’s full \nload during peak conditions on the system.  See id. at 726 (“[N]etwork service, as the Commission defined it, \nmeans that network customers can call upon the transmission provider to supply not just some, but all of their \nload at any given moment, when for instance they experience blackouts or brownouts.”).  As a result, PJM \nwill include the customer’s full load in the RPM for purposes of procuring adequate capacity to serve the \nload.  In addition, PJM will include the full load in the Load Forecast for purposes of PJM’s transmission \nplanning with RTEP.  Tariff, Part III, section 28.2 (“The Transmission Provider shall include the Network \nCustomer's Network Load in the Transmission System planning and the Transmission Owners shall, \nconsistent with the terms and conditions of the Tariff, the Operating Agreement, and Good Utility Practice, \nendeavor to construct and place into service sufficient transfer capability to deliver the Network Customer's \nNetwork Resources to serve its Network Load on a basis comparable to the delivery of each Transmission \nOwner's own generating and purchased resources to its Native Load Customers.”)."},{"page":40,"startToken":13521,"endToken":13914,"text":"40 \n• Less negative implications for resource adequacy if it is accompanied by some of \nthe optional service offerings (such as Demand Response, incentives for bringing \nincremental generation or the use of a new non-capacity backed service).  \nPursuant to the Tariff, new Network Customers must provide PJM as much notice \nas reasonably practicable to be added to the system.65  The affected Transmission Owners \nthen use due diligence to install any transmission facilities required to interconnect the new \nNetwork Load.66  The costs of new facilities required to interconnect the new Network \nLoad are charged to the Network Customer in accordance with Commission policies.67 \nIn addition, the Commission has previously and recently rejected an argument that \nwhere a generator and load “are all in the same state, NITS charges should not be \nassessed[.]”68  It may be an open question what level of NITS charges, if any, should be \nassessed in certain co-location arrangements in accordance with cost causation principles.   \n                                                 \n65 Id. at section 31.2. \n66 Id. (“The affected Transmission Owners, in accordance with the terms and conditions of the Tariff and the \nOperating Agreement, will use due diligence to install any transmission facilities required to interconnect a \nnew Network Load designated by the Network Customer.”). \n67 Id. \n68 Nat'l R.R. Passenger Corp. v. PPL Elec. Utils. Corp., 171 FERC ¶ 61,237, 62,763, at P 43 (“Amtrak \nconcedes that, when power from Safe Harbor is insufficient, it uses PPL transmission facilities to obtain \npower. This is what it means to take and rely on network service. As the Commission and the D.C. Circuit \nhave recognized, and as PPL argues in this proceeding, this is one of the significant benefits of network \nservice, i.e., the transmission provider plans and provides for firm transmission capacity sufficient to meet \nthe customer's current and projected peak loads and, as a result, a customer can call upon the transmission \nsystem to supply all of the customer's load at any given moment, even when behind the meter or alternative \nsupply is unavailable.  Given these benefits, it is appropriate that Amtrak bears the costs associated with \nits reliance on the transmission system, as its retail supplier, CNE, is a Network Customer relying on a \nNetwork Resource.” (emphasis added) (citation omitted)) & n.101, order denying clarification & addressing \narguments raised on reh’g, 173 FERC ¶ 61,043 (2020)."},{"page":41,"startToken":13914,"endToken":14108,"text":"41 \niv. \nWhat changes to the rates, terms, and conditions of Network \nIntegration Transmission Service or Point-to-Point Transmission \nService or, alternatively, what new form of transmission service(s) \nmay be necessary for different configurations of co-location to \nensure that the Tariff is consistent with cost causation principles \nand the beneficiary pays principle.  \nPJM Response:    \nPlease see the chart attached as Exhibit A to this submission for some of PJM’s \npreliminary observations.  \nBy way of further response, for purposes of NITS cost allocation, “[a]lthough PJM \nimplements the cost allocation provisions of Schedule 12 of the Tariff, the cost allocation \nmethod is determined by the PJM Transmission Owners, and it is the PJM Transmission \nOwners, not PJM, that have the section 205 filing rights for the PJM cost allocation \nmethod.”69 PJM retains more robust filing rights over changes to ancillary services cost \nallocation.  PJM looks forward to continued engagement with the Transmission Owners \nand other stakeholders on these important questions of cost allocation. \n                                                 \n69 See Linden VFT, LLC v. Pub. Serv. Elec. and Gas Co., 161 FERC ¶ 61,264, at P 31 n.44 (2017) (citing Atl. \nCity Elec. Co.,295 F.3d 1)."},{"page":42,"startToken":14108,"endToken":14427,"text":"42 \nv. \nParties may also wish to address how to determine which co-located \nload configurations should be required to take Network Integration \nTransmission Service or Point-to-Point Transmission Service or a \nnew form of transmission service (i.e., whether generalized policies \nor tests, such as a multi-factor test, to be applied case-by-case, may \nbe appropriate), as well as the magnitude (i.e., how the service taken \nby co-located load compares to service by other types of load).  For \nexample, if a co-located generator is synchronized to the grid but \nthe load can be configured to be wholly isolated from the grid in the \nevent the co-located generator trips offline, what technical and \noperational factors should determine whether the co-location \narrangement still relies on the transmission system in ways that \nwarrant a requirement that the co-located load take Network \nIntegration Transmission Service or Point-to-Point Transmission \nService or a new form of transmission service?  Are there potential \nco-located load configurations for which tailored approaches may \nbe appropriate. \nPJM Response:    \nPlease see the chart attached as Exhibit A to this submission for some of PJM’s \npreliminary observations regarding this question. \nBy way of further response, PJM objects to the question’s use of the phrase “wholly \nisolated from the grid” as it is contrary to engineering and economic principles.  The notion \nthat any of the proposed co-location arrangements can be “wholly isolated” is misleading.  \nThe load and generator are connected to and synchronized with the multi-state bulk power \nsystem.  It is not operating as a micro grid (nor can it if the generating facility is a nuclear \nunit).  Nor is the generator delivering power through an intermediary to a load with a \nbreaker open.  Further, by way of example, there are obligations to ensure power to nuclear \nplants to ensure safe shutdown (among other things).  The load and generator are benefiting \nfrom ancillary services (including but not limited to black start).  Any system protection"},{"page":43,"startToken":14427,"endToken":14666,"text":"43 \nfacilities are designed to only handle less complex N-1 conditions, and can misoperate (and \nindeed have misoperated).70  \nvi. \nWith respect to the Guidance Document, please explain what it \nmeans to be “electrically connected and synchronized to the PJM \nTransmission System when consuming power” and how that \nimplicates the use of Network Integration Transmission Service or \nPoint-to-Point Transmission Service or a new form of transmission \nservice.  \nPJM Response:    \nPlease see the chart attached as Exhibit A to this submission for some of PJM’s \npreliminary observations regarding the implications of being connected and synchronized \nto the grid.   \nSynchronizing to the grid means the generator matches the voltage, frequency, and \nphase of the entire grid (including all load connected to the system) before connecting to \nthe grid in order to facilitate safe and stable power transfer.   \nAs noted above, co-located load is connected to and synchronized with the multi-\nstate bulk power system.  At bare minimum, it is benefiting from ancillary services.   \nvii. \nWhat operational or commercial factors of a co-location \narrangement would result in a co-located load not needing to take \nany form of transmission service, including what types of special \nprotection schemes or backup arrangements may be necessary to \nensure the co-located load never takes any form of transmission \nservice? \nPJM Response:    \nPlease see the chart attached as Exhibit A to this submission for some of PJM’s \npreliminary observations. \n                                                 \n70 See also infra response to question B.vii."},{"page":44,"startToken":14666,"endToken":14948,"text":"44 \nAbsent an arrangement where both the load and the generator are completely \nisolated and physically disconnected from the grid, (a situation which is very different from \nthe claimed “totally isolated” configuration offered by some in these proceedings), PJM is \nnot aware of a configuration that would “ensure the co-located load never takes any form \nof transmission service.”  As noted above, grid-connected facilities benefit from their \nconnection and should pay for grid services consumed.    \nThe challenge with an arrangement where there is load located behind a generator \nPoint of Interconnection lies in how such a configuration or special protection scheme \ncould be designed to never fail and cover all potential operating conditions (including \ngenerator outages and complex scenarios beyond the N-1 conditions addressed by the \nsystem protection facilities).71  \nFor example, it is possible to develop a special protection scheme that could \ndisconnect the load if the local generator trips.  This scheme could be developed with \nsufficient redundancy to help better ensure activation.  However, it is always possible that \nthe protection system could misoperate, be disabled, or degrade.  If this occurs, the load \nwould end up taking service from the grid until manual action could be taken to remove \nthe load.  In fact, in the few conditions where such schemes exists on the PJM system, PJM \nhas observed these protection schemes can fail, and the load has taken service from the \ngrid.  \nIn addition to the special protection scheme concerns, there are other challenges \nwith isolating the load that come into play and could not be covered by a special protection \nscheme.  These include unplanned generator run-backs or reductions in output, generator \n                                                 \n71 See also supra PJM’s response to question B.v."},{"page":45,"startToken":14948,"endToken":15184,"text":"45 \nMW output oscillations, and co-located load utilization fluctuations.  When these \nconditions occur, they result in brief, but routine, imbalances between the load and the \ngeneration that would need to rely on the grid to balance. \nC. \nAncillary or other wholesale services \ni. \nPlease explain whether and to what extent different configurations \nof co-location arrangements rely on or benefit from ancillary \nservices or black start services and, if so, provide specific details \nabout the type of service and how the co-location arrangement relies \non it.  To what extent are these benefits distinct from the benefits \nthat other Network Integration Transmission Service and Point-to-\nPoint Transmission Service customers derive from ancillary \nservices?  \nPJM Response:    \nPlease see the chart attached as Exhibit A to this submission and associated \nexplanation above, see supra Section II, for some of PJM’s preliminary observations.  PJM \nlooks forward to continued engagement with the Transmission Owners and other \nstakeholders on these important questions of cost allocation. \nii. \nPlease explain whether and to what extent co-location \narrangements impose costs related to ancillary services or black \nstart services or increase the costs for such services allocated to \nother parties and how those costs could be approximated. \nPJM Response:    \nPlease see the chart attached as Exhibit A to this submission and associated \nexplanation above, see supra Section II, for some of PJM’s preliminary observations.  By \nway of further response, please see PJM’s responses to questions A.iv."},{"page":46,"startToken":15184,"endToken":15469,"text":"46 \niii. \nPlease explain whether and to what extent co-location \narrangements use, benefit from, provide, or contribute to the need \nfor transmission system services in a manner that does not fit into a \npre-existing category of ancillary services or black start services, \nand, if so, should new categories of services be created to \naccommodate that use?  Alternatively, please explain whether an \nalternative mechanism of cost allocation for pre-existing ancillary \nservices would be more appropriate. \nPJM Response:    \nPlease see the chart attached as Exhibit A to this submission for some of PJM’s \npreliminary observations.  PJM looks forward to continued engagement with the \nTransmission Owners and other stakeholders on these important questions of cost \nallocation.   \niv. \nWhat changes to rates, terms, and conditions of ancillary services, \nincluding ancillary services procured in PJM’s markets, are \nnecessary for different configurations of co-location arrangements \nto ensure that the Tariff is consistent with cost causation principles \nand the beneficiary pays principle. \nPJM Response:    \nPlease see the chart attached as Exhibit A to this submission for some of PJM’s \npreliminary observations.  PJM looks forward to continued engagement with the \nTransmission Owners and other stakeholders on these important questions of cost \nallocation.  \nv. \nPlease explain how PJM should determine which co-located load \nconfigurations take ancillary services or black start services (i.e., \nwhether generalized policies or tests, such as a multi-factor test, to \nbe applied case-by-case may be appropriate), as well as the amount \nof such service (i.e., how the service taken by co-located load \ncompares to service taken by other types of load). \nPJM Response:    \nPlease see the chart attached as Exhibit A and associated explanation above, see \nsupra Section II, to this submission for some of PJM’s preliminary observations.  PJM"},{"page":47,"startToken":15469,"endToken":15762,"text":"47 \nlooks forward to continued engagement with the Transmission Owners and other \nstakeholders on these important questions of cost allocation. \nD. \nInterconnection Procedures and Cost Allocation \ni. \nDoes the necessary study process adequately address potential \nimpacts caused by a co-location arrangement or is an additional \nstudy or new study process warranted, e.g., a system impact study \nor generator deactivation study?  PJM should provide the details \nregarding the geographic scope of the existing necessary study \nprocess, what is studied, and how the results are reported, including \nwhat opportunities stakeholders, the interconnected transmission \nowner, or the PJM IMM have to review the results, if any. \nPJM Response:    \nAs discussed elsewhere in this submission, the necessary study process is among \nseveral methods of study that may employed to evaluate co-location arrangements, \nalthough the extent to which necessary studies apply and for what purposes varies \ndepending upon the type of co-location arrangement under study. \nThe necessary study recognizes and evaluates changes that have been made to a \ngenerator’s facilities that typically have relatively small MW impacts on its ability to \ndeliver less power to the grid than the configuration reflected in an existing service \nagreement.  PJM does not have a tariffed study process for load (that is not PJM Network \nLoad) locating behind a generator’s Point of Interconnection.  As a result, PJM has used \nthe necessary study consistent with the Tariff’s intended use:  to study modification to an \nexisting interconnection.  The type of interconnection and whether that load is Network \nLoad or behind the meter load largely drives the scope of the necessary studies process.  \nBefore providing a broader overview of the necessary study process, understanding a few \nthreshold points will assist in navigating the discussion about this type of study and when \nit is implicated."},{"page":48,"startToken":15762,"endToken":16084,"text":"48 \nAs explained above, any configuration where the load is Network Load (Options  \n2, 3, 6, 7, and 8, and in some circumstances Options 4 and 5) results in a necessary study \nthat is limited in scope to generator interconnection modifications.  Load studies would be \nperformed through traditional Transmission Owner/Electric Distribution Company-driven \nretail load integration processes.72  While stakeholder (including the Organization of PJM \nStates, Inc. and Exelon) and Commission comments and questions probe the sufficiency of \nthe necessary study agreement/study process for load integrations, only two of the proposed \noptions (Options 4 and 5 if load is not designated as Network Load) could involve a load \nmodification study.  Given the other options for co-locating load, concerns about the nature \nof the necessary study process implicated by Options 4 and 5 may be somewhat relieved.  \nIn any event, should the Commission sanction further exploration of Options 4 and 5, PJM \nwill explore opportunities to enhance the visibility of the necessary study process and \nresults where load integrations are introduced through such a process (subject to potential \nCEII and other concerns). \nFor a load co-locating with an existing generation resource and not seeking to be a \nNetwork Load, a necessary study request must be submitted.  PJM’s necessary study \nprocess proceeds pursuant to PJM Tariff, Part VI, Attachment O, Appendix 2, section 3, \nPJM Tariff, Part IX, Subpart B, Appendix 2, section 3, and section 4.5 of PJM Manual \n14G.  In the general run of cases involving co-location arrangements requiring \nmodifications to the interconnection, the generator provides PJM and the Transmission \nOwner with notice of any planned modifications to a co-located Customer Facility and \n                                                 \n72 Where Network Load or when designated as such, the load would submit a request to the relevant \nTransmission Owner or EDC.  The Transmission Owner would perform load studies to identify upgrades to \nensure deliverability and analyze relay and protection scheme changes required to accommodate the load."},{"page":49,"startToken":16084,"endToken":16369,"text":"49 \nshall provide the relevant drawings, plans, specifications, and models to PJM and the \nTransmission Owner in advance of beginning the work.  Such advance notification is \nrequired so that PJM and the Transmission Owner can evaluate potential reliability impacts \nof the proposed co-located load configuration, including verification about whether and if \nadequate protection is in place to prevent the unexpected withdrawal of power at the Point \nof Interconnection for the co-located Customer Facility as may be necessary depending \nupon the requested configuration.  \nThe necessary studies process provides PJM and the interconnecting Transmission \nOwner an opportunity to perform studies to evaluate the potential reliability impact of a \nproposed addition or reduction of a co-located load configuration on the PJM Transmission \nSystem, and determine what, if any, system reinforcements are required prior to the \naddition or reduction of the planned co-located load configuration.  PJM’s studies of co-\nlocated load that is not designated as Network Load would be for the full amount of load \nand reflecting any Capacity Interconnection Rights reductions, and involve generation \ndeliverability, N-1 and N-1-1 thermal and voltage studies, special protection systems \nreview, baseline stability, and, if applicable, a nuclear plant interface requirements voltage \nanalysis. \nPrior to beginning the necessary studies process, a necessary studies agreement \nmust be drafted and executed by PJM and the Interconnection Customer, a necessary study \ndeposit provided, and all required technical data submitted. In some instances, the \nTransmission Owner may require additional studies (such as protection system or metering \nmodifications) based on the planned co-located load configuration, and such studies may \nresult in additional study costs. The execution of a Construction Service Agreement may \nbe required if the results of the necessary studies process identifies the need to construct"},{"page":50,"startToken":16369,"endToken":16560,"text":"50 \nsystem reinforcements and the related PJM interconnection service agreement would be \namended to reflect these necessary system upgrades, related costs, and posting of the \nrequisite security.  \nAny applicable PJM interconnection service agreement must be executed and/or \namended by all three parties (PJM, the interconnecting Transmission Owner, and the \nInterconnection Customer) to reflect all changes resulting from the incorporation of a co-\nlocated load configuration.  Service to the co-located load pursuant to the co-located load \nconfiguration may not commence until the necessary PJM interconnection service \nagreement(s) has been fully executed by the parties, filed with and accepted by the \nCommission, and all required system reinforcements, system protection facilities, and \nmetering are in place. \nBy way of comparison to the necessary study, a deactivation study would not be \nappropriate for co-location arrangements, because deactivation studies do not contemplate \nthe complete retirement of the generation resource.  Deactivation studies are designed for \nthe complete cessation of operations by a generator.  In a co-location arrangement, the \ngenerator will remain interconnected with the PJM grid and capable of injecting power \nonto the grid, which is why the facility will retain its Maximum Facility Output."},{"page":51,"startToken":16560,"endToken":16821,"text":"51 \nii. \nPlease explain whether PJM’s necessary study process allows a co-\nlocation arrangement to demonstrate its capability to flexibly adjust \nits withdrawals from or injections to the transmission system (e.g., \nby using secondary backup generation or by curtailing on-site load), \nand reflect this capability in the operating assumptions PJM \nconsiders when estimating the co-location arrangement’s impacts \non the transmission system?  If not, would it be appropriate to \nestablish a new or revised study process that allows for such a \ndemonstration? \nPJM Response:    \nYes.  By way of further information, where certain co-located load configurations \nare involved (particularly Options 4 and 5 in Exhibit A), the base case configuration for \nthe PJM necessary study reflects the generator’s Capacity Interconnection Rights (“CIRs”) \nbeing reduced by the expected peak MW utilization of the co-located load.  Under this \nconfiguration and study, the load is assumed to never take power from the grid.  And the \nMaximum Facility Output of the generator is not adjusted in this study, but with the co-\nlocated load modeled as always on, this offsets the net generator output.  No sensitivity \nstudies are run with this load taking service from the grid or from any other PJM Network \nResource. \nIf the results of the necessary study indicate a thermal or voltage violation \nconsistent with PJM and/or local Transmission Owner Planning criteria, this violation must \nbe mitigated before the load can be added.  Such violations have been mitigated by \ngenerators, and this has been memorialized through an agreed-upon Construction Services \nAgreement with the Transmission Owner to reflect changes needed on Transmission"},{"page":52,"startToken":16821,"endToken":17139,"text":"52 \nOwner systems and associated costs,73 or it is the responsibility of the Generation Owner \nif the changes are to take place behind the Point of Interconnection.  \nUnder certain co-located load arrangements, it is possible that the Generation \nOwner could propose a special protection scheme or Remedial Action Scheme (“RAS”) to \nreduce the load under certain conditions (where, for example, the generating unit comes \noffline).  If such a configuration were permitted by the Commission, PJM would require \nlanguage similar to the protection facilities language proposed in the most- recently filed \nSusquehanna ISA.74  If and where such facilities might misoperate, additional new \nlanguage should be developed to require the generator to take immediate steps to stop the \nflow of energy from the grid to any co-located load or risk breach and non-compliance \n(given the absence of contractual privity by and among PJM, the Transmission Owner, and \nthe co-located load in certain situations).   \niii. \nWhat changes to interconnection procedures and agreements may \nbe necessary to ensure that PJM identifies the reliability impact to \nthe transmission system of load co-locating with existing generation \nincluding the need for dynamic response models?  \nPJM Response:    \nPJM’s sets forth more detailed information about the nature of the studies \nperformed relating to co-located load by and among the various involved entities \nthroughout this submission.   \n                                                 \n73 See PJM Interconnection, L.L.C., 190 FERC ¶ 61,080 (2025) (accepting interconnection construction \nservice agreement assigning upgrade costs to generator seeking to modify interconnection to accommodate \nco-located load).   \n74 See, e.g., Susquehanna ISA, Schedule F, Part F.4.b (PJM and Transmission “reserve their respective rights \nto take all actions each may deem necessary to protect the Transmission System, up to and including declaring \nan Emergency Condition and taking Immediate Action to disconnect the Customer Facility . . . and the Co-\nLocated Load will not be reconnected as co-located load without approval of Transmission Provider and \nInterconnected Transmission Owner”)."},{"page":53,"startToken":17139,"endToken":17330,"text":"53 \nIn response to this question’s specific prompt about dynamic response models, \ntoday, PJM conducts dynamic studies for co-located load projects.  All applicable North \nAmerican Electric Reliability Corporation (“NERC”), PJM, and Transmission Owner-\nspecific contingencies and criteria are evaluated.  \nFor such dynamic studies, co-located loads are modeled in detail within both power \nflow and dynamic models.  Step-down transformers are explicitly represented, and co-\nlocated loads are modeled using composite load models, which capture the dynamic \nbehaviors of power electronics, cooling, and lighting loads. \nSince 2024, PJM has been also collecting more granular data using the NERC Data \nCenter Load Information Survey template to evaluate the impact of large data center co-\nlocated load ramping behaviors.  PJM typically assesses the stability impact of co-located \nloads under light-load and summer-peak conditions in accordance with its stability analysis \nmethodology. \nBy way of further response, PJM awaits Commission guidance and stakeholder \nengagement on the options presented in Exhibit A and on any other options that may be \noffered in this proceeding.  PJM will continue to evaluate what, if any, changes to \ninterconnection procedures and agreements may be necessary pending receipt of that \nguidance and feedback."},{"page":54,"startToken":17330,"endToken":17618,"text":"54 \niv. \nTo what extent does a co-location arrangement raise potentially \ndistinct cost-allocation issues relative to a deactivating generator \nthat causes the need for transmission upgrades?  What principles \nshould the Commission apply to allocate the costs of any \ntransmission upgrades needed to mitigate the impacts of co-locating \nload?  What steps should PJM take to ensure these costs are \ntransparent to all parties? \nPJM Response: \nTransmission upgrade costs arising from a deactivating generator are allocated to \nload consistent with existing RTEP processes and cost allocation methodologies.  And the \ndeactivation process proceeds pursuant to Part V of the PJM Tariff, and relates to situations \nin which a generating unit will cease to operate in its entirety in a state disconnected from \nthe grid.  \nIn contrast, the transmission upgrade costs for co-location arrangements identified \nduring the necessary study process may be cost allocated differently than the deactivation-\nrelated upgrade costs.  For example, in a situation where state law may permit a co-located \nload to be directly connected to the grid with no back flow (New Options 4 and 5), \ntransmission upgrades may be cost allocated directly to the generator seeking to modify its \ninterconnection to accommodate this configuration.75   \nIn a situation where a co-located load will be Network Load (either outright or in a \nconfiguration where it may seek back-up service from the local utility), the large load is \nstudied and could be connected to the grid pursuant to the existing traditional load \ninterconnection processes.  These processes and associated cost allocation methodologies \nare discussed at the beginning of this submission. \n                                                 \n75 See PJM Interconnection, L.L.C., 190 FERC ¶ 61,080 (accepting interconnection construction service \nagreement assigning upgrade costs to generator seeking to modify interconnection to accommodate co-\nlocated load)."},{"page":55,"startToken":17618,"endToken":17846,"text":"55 \nv. \nAre changes needed to how PJM allocates the costs of any \ntransmission upgrades needed to mitigate the transmission system \nimpacts of co-locating load, if any, including whether the costs of \nthose upgrades can ever be allocated to a party other than the co-\nlocated \ngenerator, \nco-located \nload, \nand/or \nco-location \narrangement? \nPJM Response:    \nPlease see the chart attached as Exhibit A to this submission for some of PJM’s \npreliminary observations, and PJM’s response to question D. iv, supra. \nvi. \nAre changes to the pro forma interconnection-related agreements \nnecessary to accommodate the addition of co-located load to \nexisting generation? \nPJM Response:    \nPJM awaits Commission guidance and stakeholder engagement on the options \npresented in Exhibit A and other options that may be offered in this proceeding.  PJM will \nevaluate what, if any, changes to interconnection-related agreements may be necessary \npending receipt of that guidance and feedback. \nvii. \nPlease explain whether changes to interconnection procedures and \nagreements are necessary to accommodate new generation \ninterconnecting with co-located load, including whether the existing \nqueue process is sufficient for such arrangements?    \nPJM Response:    \nPlease see the chart attached as Exhibit A to this submission for some of PJM’s \npreliminary observations.  To the extent any changes to interconnection procedures and \nagreements are necessary, PJM awaits Commission guidance on New Option 6 and any \nguidance on enhancing the transparency of the necessary study process."},{"page":56,"startToken":17846,"endToken":18092,"text":"56 \nviii. \nPlease explain whether or not it would be appropriate to establish \nan interconnection study process outside of PJM’s interconnection \nqueue process for newly interconnecting co-location arrangements \nthat do not exchange power with the transmission system and do not \nrequire network upgrades? \nPJM Response:    \nIt would not be appropriate to establish an interconnection study process outside of \nPJM’s interconnecting queue process.  The necessary study process is already a study \nprocess that exists outside the queue and is subject to terms and conditions of Commission-\naccepted interconnection agreements.  As PJM explained above, the necessary study \nprocess is capable of incorporating and evaluating the impact of co-located arrangements.  \nAn additional queue, beyond the existing queue and the necessary study process, is not \nnecessary.  Moreover, large load additions that are Network Load are principally studied \nby individual Transmission Owners/EDCs through their own processes.  \nix. \nA generator with a co-located load that is not a party to a \ntransmission service agreement is arguably distinguishable from \nother generators.  To the extent co-located arrangements create \ncosts, or benefit from bulk power system services, but the generator \nand load are not exposed to these costs because of their contractual \nrelationship, should PJM modify the Tariff and related agreements \nto allocate those costs to the generator directly?  \nPJM Response: \nYes.  PJM anticipates that it (and the Transmission Owners) would have to modify \nits Tariff and related agreements to allocate costs to generators and/or load as the \nCommission determines necessary and appropriate."},{"page":57,"startToken":18092,"endToken":18385,"text":"57 \nE. \nPJM Capacity Market, Reliability, and Resource Adequacy \ni. \nWhat changes to PJM’s capacity market rules are necessary to \nensure that the Tariff specifies how co-located generation and/or \nload participates in the capacity market in a way that reflects the \npotentially unique physical and operational characteristics of the \nco-location arrangement (e.g., the presence of secondary backup \ngeneration, the capability to curtail on-site load or other \noperational flexibilities, among others) and is otherwise just, \nreasonable, and not unduly discriminatory or preferential? \nPJM Response:    \nPJM’s option 5 addresses the means by which a secondary backup unit at a \nCustomer Facility may operate, and what follows is a rationale for this option and a \ndiscussion of factors a generator considering this option should evaluate before pursuing \nit.  For discussions of other potential operational flexibilities, see the discussions \nthroughout regarding Demand Response/Option 8 and a curtailable non-capacity backed \nservice/Option 7. \nAs a baseline, PJM does not believe that any changes to PJM’s capacity market \nrules are necessary to accommodate co-location arrangements.  Depending on the \nconfiguration, co-location has the same implications for resource adequacy as load that is \nnot co-located.  These implications then impact the quantities of resources available to clear \nin the market and the resulting prices paid by customers.  PJM does not believe that broad \nchanges in capacity market design are warranted based on co-located load.  \nAll Generation Capacity Resources must offer their full Accredited Unforced \nCapacity into the capacity market, unless PJM has granted an exception to the must-offer \nrequirement pursuant to the existing rules in Tariff, Attachment DD, section 6.6.  While \nthere is an exception from the must-offer requirement where the Capacity Market Seller \n“has entered into a unit-specific bilateral transaction for service to load located outside the"},{"page":58,"startToken":18385,"endToken":18704,"text":"58 \nPJM Region,”76 there is no exception allowing Capacity Resources to not offer capacity \nbilaterally committed to serve load in the PJM Region.  Rather, the capacity market was \ndesigned with such bilateral intra-PJM arrangements in mind,77 allowing sellers to offer \nsuch contracted capacity as “self supply” into RPM Auctions.78  This is consistent with the \nnotion that PJM’s resource adequacy responsibility extends to all load within the PJM \nRegion, and PJM and the Load Serving Entities are responsible for procuring sufficient \nCapacity Resources to maintain reliability.  Thus, to the extent the co-located load expects \nto receive PJM’s resource adequacy benefits, then the generation resource must participate \nas Capacity Resource and could offer as “self supply” and secure a capacity commitment. \nTo the extent the co-located load is not considered Network Load and PJM does \nnot have any resource adequacy obligation with respect to such load, such load may not be \nserved by installed capacity associated with an Existing Capacity Resource, as such \nExisting Capacity Resource has a legal obligation to offer such capacity to the PJM Region \nto serve PJM Region Network Load.  Accordingly, before an Existing Generation Capacity \nResource (or any portion of the resource) may be allowed to exclusively serve non-PJM \nload, the Capacity Market Seller must request and obtain removal of Capacity Resource \nstatus for the portion of the Existing Generation Capacity Resource to be designated to \nserve the co-located load.  The process and timelines for removing Capacity Resource \nstatus are set forth in Tariff, Attachment DD, section 6.6(g).  The Market Monitor is \nrequired to “analyze the effects of the proposed removal of a Generation Capacity Resource \n                                                 \n76 See Tariff, Attachment DD, section 6.6(g). \n77 See, e.g., Tariff, Attachment DD, sections 3.1 (Support for Self Supply and Bilateral Transactions), 4.6 \n(Bilateral Capacity Transactions). \n78 See Tariff, Attachment DD, section 5.2 (Nomination of Self Supplied Capacity Resources)."},{"page":59,"startToken":18704,"endToken":19033,"text":"59 \nfrom Capacity Resource status with regard to potential market power issues.”79  A request \nto remove Capacity Resource status will be granted only if the Market Monitor approves it \nand PJM agrees, or the Commission issues an order terminating the Capacity Resource \nstatus.80  Capacity Resources that give up any portion of their Capacity Resource status \nalso forfeit the CIRs supporting such status.81 \nThe following addresses situations that could arise in Options 4 or 5 where the co-\nlocated load is not designated Network Load, where there are multiple units at a co-located \ngenerator, and where the generator desires to use one of those units to serve as a back up \nto other units that may have co-located load service obligations.  Absent contrary approval \nfrom the Commission and authorization from PJM as contemplated in the Third Revised \nCo-Located Load filed in Docket No. ER24-2172, no portion of a committed Capacity \nResource (whether composed of one or multiple physical generating units) may prioritize \nserving load that PJM is not responsible for serving.  Simply put, absent Commission \nguidance to the contrary and PJM authorization, PJM cannot be in competition with non-\ncapacity backed co-located loads for the output of a Capacity Resource.  PJM cannot be \nsimultaneously responsible for ensuring the energy needs of the PJM Region and unsure \nwhether a Capacity Resource will decide to serve PJM loads or co-located loads.  Sellers \nshould not be afforded the economic choice of following through on capacity commitments \nor incurring Capacity Resource Deficiency Charges and/or Non-Performance Charges.  \nAny portion of an Existing Generation Capacity Resource that would prioritize serving co-\n                                                 \n79 Tariff, Attachment DD, section 6.6(g). \n80 Id. \n81 Id. (“A Generation Capacity Resource that is removed from Capacity Resource status shall no longer \nqualify as an Existing Generation Capacity Resource, and the Capacity Interconnection Rights associated \nwith such facility shall be subject to termination in accordance with the rules described in Tariff, Part VI, \nsection 230.3.3.”)."},{"page":60,"startToken":19033,"endToken":19377,"text":"60 \nlocated loads over following PJM dispatch—whether on a primary or backup basis—\nshould seek removal of Capacity Resource status.   \nii. \nWhat Tariff change or changes to the interconnection service \nagreement are necessary to ensure that PJM and the interconnected \ntransmission owner have sufficient visibility into the co-located load \nconfiguration?  \nPJM Response:    \nUnder PJM’s existing governing documents, there are numerous provisions in the \nTariff, Amended and Restated Operating Agreement, RAA, and service agreements that \nrequire generators to provide PJM with extensive transmission level equipment modeling \nand data.82  That being said, unique operational procedures and data exchange requirements \nlike those proposed in the Susquehanna ISA should be developed and specified. \nTo ensure that the overall system will continue to operate reliably as designed or as \nimposed by any temporary operational conditions on the system, the service agreement (as \nwell as other government documents) may need to further be revised.  These revisions may \ninclude obligations on the generator and the co-located end use load (to the extent they can \nbe bound directly or indirectly) to ensure the needed protection schemes (including RAS) \nwill continue to operate as designed and directed by PJM.  Any changes to the co-located \nload type, connected load level, or how it is served need to be communicated with PJM \n                                                 \n82 See, e.g., Tariff, Attachment O, Appendix 2, schedules A-D (requiring site plans, single-line diagrams, list \nof metering equipment, and technical specification); Operating Agreement, section 11.3.1(b) requiring \nmembers to provide facilities as necessary for coordination with the Office of Interconnection);  RAA, Article \n9, Section 3 (“[E]ach Party shall submit to the Office of the Interconnection the data and other information \nnecessary for the performance of this Agreement as may be more fully described, in RAA, Schedule 11.”).; \nSystem Operations Division, PJM Manual 01: Control Center and Data Exchange Requirements, PJM \nInterconnection, L.L.C., section 5 & Attachment A (Jan. 23, 2025), https://www.pjm.com/-\n/media/DotCom/documents/manuals/m01.ashx.  Attachment A to Manual 01 lists the meter requirements and \ndata specification and collections requirements."},{"page":61,"startToken":19377,"endToken":19696,"text":"61 \nprior to these changes taking place and the necessary amendments to the service \nagreements are approved and implemented. \nIf the co-located load is PJM Network Load, PJM and the Transmission Owners \nhave means through existing Tariff provisions and agreements to obtain the information to \nhave both sufficient visibility and sufficient control of this load and ensure the load could \nbe served reliably without compromising overall system reliability.  In addition, these \ndocuments provide a means for mitigation through Commission action if they are not \nadhered to. \nUnder certain configurations, if the co-located load is not PJM Network Load, \nquestions arise as to how any requirements for visibility and control of the co-located load \nconfiguration are applied to that customer.  Any interconnection agreement would be \nbetween PJM and the Generation Owner because the third-party load is not a signatory to \nthese agreements.  Pro forma agreements may require modification to specify, where \napplicable:  the entity(ies) that own any co-located load, what people and contact \ninformation at the co-located load should be used to communicate with such co-located \nload during both emergency and non-emergency situations, and whether the generator with \nco-located load is now functioning as an Electric Distributor under the Tariff (and \nanalogous North American Electric Reliability Corporation requirements pursuant to the \ncurrent Compliance Registry Criteria).83  In the case of the Susquehanna ISA, for example, \nPJM requested non-conforming provisions requesting such information relating to the co-\n                                                 \n83 Operating Agreement, section 1, Definitions – E - F (defining “Electric Distributor” as “a Member that: 1) \nowns or leases with rights equivalent to ownership electric distribution facilities that are used to provide \nelectric distribution service to electric load within the PJM Region; or 2) is a generation and transmission \ncooperative or a joint municipal agency that has a member that owns electric distribution facilities used to \nprovide electric distribution service to electric load within the PJM Region”); Operating Agreement, section \n11.3.3."},{"page":62,"startToken":19696,"endToken":19988,"text":"62 \nlocated load.84  In that situation, the generator reaffirmed its continued rights, duties, and \nobligations under the ISA, notwithstanding any actions by a third party.85  This provision \nwas in recognition of the fact that “regardless of what entity may be responsible for \noperational activities of the transmission facilities of the Co-Located Load [at issue in that \narrangement] and regardless of the entity that may own or control the Co-Located Load \nitself, any breaches or non-compliances under this agreement attributed to the activities of \nsuch entities or that remain [the generator’s] obligations are the duty and responsibility of \n[the generator] to cure.”86  Absent such provisions, a regulatory and communication gap \ncould arise increasing risks to reliability, among other possible concerns.   \nBy way of further response, see the response to question D.ii, supra.   \n \niii. \nPlease explain whether the existing Tariff rules are sufficient to \nensure resource adequacy if increasing numbers of large existing \ngenerators choose to co-locate with load. \nPJM Response:    \nAny additional load on the system requires either the addition of supply resources \nto serve that load reliably, or flexibility on the part of the load to curtail its consumption \nfrom the transmission system when necessary to maintain reliability.  For this reason, PJM \nhas outlined three potential options relating to these considerations:  Option 6 (co-located \nload that elects to be Network Load and leverages provisional interconnection service or \nState Agreement Approach), Option 7 (co-located load that takes a new non-capacity \nbacked service that could be curtailed in advance of emergency procedures), and Option 8 \n(co-located participates as Demand Response).  And as discussed below, see infra question \n                                                 \n84 See Susquehanna ISA, Schedule F, Part G.1. \n85 Susquehanna ISA, Schedule F, Part G.2. \n86 Susquehanna Deficiency Response at 24."},{"page":63,"startToken":19988,"endToken":20297,"text":"63 \nF.2, PJM is also exploring with regulators and generators opportunities to leverage at least \n50 hours (or more) of diesel back-up generator service to enhance the available demand \nresponse portfolio. \nFurthermore, the PJM markets, including the capacity market, are utilized to \nprocure commitments from resources to provide sufficient capacity and energy to maintain \nreliability.  PJM has, and continues to, take steps to ensure that needed resources to serve \nfuture load requirements, particularly given anticipated resource deactivations due to \npolicy requirements, can be integrated onto the transmission system.  PJM continues to \nwork through the transition to the new interconnection process, and is also in the process \nof implementing the Reliability Resource Initiative recently approved by the \nCommission.87  Additional efforts that are largely out of PJM’s control are also necessary, \nsuch as more streamlined permitting and siting, to support the addition of resources that \nwill be needed in the future on the timeline by which they will be required. \nThese markets though, were designed and intended to be residual in nature (in fact, \nthe primary auction in the PJM capacity market is called the Base Residual Auction for this \nreason) to provide physical asset owners and load servers with an additional option to \nsatisfy their obligations, and also to establish prices that represent the marginal cost of \nsatisfying the system’s capacity and energy requirements.  Self-supply, either through \ndirect ownership or longer-term bilateral contracting, is a critical part of how these markets \nfunction to ensure resource development to support future reliability.  PJM looks forward \nto continuing to work with the Commission, states and other stakeholders to enhance \n                                                 \n87 Only a few days ago, PJM announced that its Reliability Resource Initiative attracted 94 applications \ntotaling 26.6 gigawatts of nameplate capacity.  See  Reliability Resource Initiative Draws 94 Applications, \nPJM Inside Lines (Mar. 21, 2025), https://insidelines.pjm.com/reliability-resource-initiative-draws-94-\napplications/."},{"page":64,"startToken":20297,"endToken":20582,"text":"64 \nopportunities for forward contracting that can serve to simulate the resource additions that \nwill be necessary to maintain system reliability. \niv. \nWhat deactivation or interconnection modification studies should \nPJM undertake to ensure resource adequacy and/or protect \nreliability should an existing generator seek to enter into a co-\nlocation arrangement?  If PJM finds that the co-location would \ncause reliability standards violations, what remediation techniques \nwould be appropriate (e.g., reliability must-run contracts, delaying \nthe co-location arrangement until the reliability violations are \naddressed, etc.)?  \nPJM Response:    \nWhether a co-location arrangement results in the capacity associated with the co-\nlocated load leaving the capacity market is an open question that varies based upon the \npotential configuration and timing of the arrangement.  \nAs discussed throughout PJM’s response, there are a number of types of co-location \narrangements, and how each arrangement affects the capacity market would necessitate a \nfact-specific inquiry some details of which are previewed in Exhibit A.  To the extent the \nExisting Generation Capacity Resource relinquishes Capacity Resource status \ncommensurate with its obligation to the co-located load, PJM’s capacity market is designed \nto send a price signaling the relative need for additional capacity.  If the arrangement results \nin the Locational Deliverability Area in which the co-location is sited needing additional \ncapacity, the clearing price for that Locational Deliverability Area may separate from the \nrest of the regional transmission organization and capacity prices will increase.   \nFurther, except as otherwise stated above, PJM is not aware of any modification to \nPJM’s deactivation or interconnection studies required to accommodate a co-location \narrangement.  To the extent the resource seeks removal of its Capacity Resource status, \nbefore such request may be granted, the Market Monitor must “analyze the effects of the"},{"page":65,"startToken":20582,"endToken":20866,"text":"65 \nproposed removal of a Generation Capacity Resource from Capacity Resource status with \nregard to potential market power issues.”88 \nTo the extent PJM determines that the co-location arrangement would result in \ntransmission reliability issues, upgrades would have to be funded and constructed.  See the \nresponse to question D.iv, supra. \nv. \nWhat changes are necessary, if any, to other PJM planning \nprocesses to better plan for and address the resource adequacy and \nreliability impacts of co-location arrangements, including, for \nexample, whether or not the frequency of such processes might be \nchanged?  Similarly, should PJM consider changes to load \nforecasting methods, informational postings, or the reserve margin \nstudy process to better plan for and address the resource adequacy \nand reliability impacts of co-location arrangements?   \nPJM Response:    \nThere may be opportunities to clarify or enhance existing planning processes.  One \npossible area of exploration could relate to addressing risks that arise based on the existing \nload forecasting process.   \nDuring the annual load forecasting process, PJM makes a request to the EDCs/Load \nServing Entities (“LSEs”) to submit large load additions that would not be captured in the \nparameters that are typically incorporated.  This request is made in July of each year for \nthe following year’s forecast.  EDCs/LSEs submit their additions and PJM reviews each \none and consults with the submitter to ask questions and conform the data for use in the \nforecast (e.g. converting capacity to demand, assessing contractual obligations, etc.).  The \nEDCs/LSEs must present this data at the September/October Load Analysis Subcommittee \nand defend their submissions to stakeholders.  Finally, PJM presents what is ultimately \naccepted into the Load Forecast for the subsequent year. \n                                                 \n88 Tariff, Attachment DD, section 6.6(g)."},{"page":66,"startToken":20866,"endToken":21161,"text":"66 \nWith any forecast of future load growth, additional transmission and generation \ncapacity may be required, and there is the risk of overbuilding due to a forecast that is too \nhigh, or underbuilding due to a forecast that is too low.  The same is true with respect to \nlarge load additions, regardless of whether the load is co-located with generation.  Given \nthe potential size of these individual, large load additions that are in the forecast, \nuncertainty with respect to whether the large loads are actually added to the system could \ncause either overbuild or underbuild to occur based on a single customer addition.   \nThe method by which any required generation and/or transmission capacity \nadditions are procured also has implications for who carries the risk of forecasted large \nload additions not materializing.  For example, if large load additions are added to the load \nforecast utilized in forward capacity auctions, the additional demand can result in price \nincreases applicable to all demand.  To the extent the forecasted load additions do not \nactually materialize, these higher capacity costs would be allocated to all other load on the \nsystem.  Were the large loads to enter into bilateral or self-supply arrangements to serve \ntheir capacity needs, the parties to those arrangements would wear the risk of the large load \nnot actually coming on line.  Similar implications may exist for transmission cost allocation \nas well. \nGiven these dynamics, opportunities to enhance the load forecasting process and \naddress the potential consequences of that process may be worthy of exploration.  \nCommission guidance and stakeholder engagement on this specific issue and the options \ndiscussed herein and presented in Exhibit A and any other options that may be lodged in \nthis proceeding will assist PJM in evaluating and identifying  any changes to planning \nprocesses."},{"page":67,"startToken":21161,"endToken":21692,"text":"67 \nvi. \nUnder what circumstances can PJM direct the operators of co-\nlocation arrangements to shed such load if deemed necessary to \npreserve system reliability during a declared emergency? \nPJM Response:    \nPJM has existing authority under its governing documents to direct PJM Members, \nboth generators and electric distributors, to take certain mitigating actions during an \nemergency.89  However, PJM does not presently have authority to direct retail end-users, \nwho are not PJM Members and who do not participate in PJM’s markets, to reduce their \nload consumption.  Such action would have to be coordinated through the applicable PJM \nMember—whether a generator or an electric distributor—in the context of shedding a co-\nlocated load. If a load is registered as Demand Response, then \n                                                 \n89 See, e.g., Tariff, Attachment K-Appendix, section 1.7.15 (“Consistent with Good Utility Practice, the \nOffice of the Interconnection shall be authorized to direct or coordinate corrective action, whether or not \nspecified in the PJM Manuals, as necessary to alleviate unusual conditions that threaten the integrity or \nreliability of the PJM Region, or the regional power system.”); Operating Agreement, Section 11.3.1 (“To \nfacilitate and provide for the work of the Office of the Interconnection and of the several committees \nappointed by the Members Committee, each Member shall, to the extent applicable . . . (e) Comply with the \nrequirements of the PJM Manuals and all directives of the Office of the Interconnection to take any action \nfor the purpose of managing, alleviating or ending an Emergency, and authorize the Office of the \nInterconnection to direct the transfer or interruption of the delivery of energy on their behalf to meet an \nEmergency and to implement agreements with other Control Areas interconnected with the PJM Region for \nthe mutual provision of service to meet an Emergency, and be subject to the emergency procedure charges \nspecified in Operating Agreement, Schedule 9 for any failure to follow the Emergency instructions of the \nOffice of the Interconnection.”); id. at section 11.3.3 (“In addition to any of the foregoing responsibilities \nthat may be applicable, each Member that is an Electric Distributor, whether or not that Member votes in the \nMembers Committee in the Electric Distributor sector or meets the eligibility requirements for any other \nsector of the Members Committee, shall . . . (a) Accept, comply with or be compatible with all standards \napplicable within the PJM Region with respect to system design, equipment ratings, operating practices and \nmaintenance practices as set forth in the PJM Manuals, or be subject to an interconnected Member’s \nrequirements relating to the foregoing, so that sufficient electrical equipment, control capability, information \nand communication are available to the Office of the Interconnection for planning and operation of the PJM \nRegion . . . (c) Maintain or arrange for a portion of its connected load to be subject to control by automatic \nunder frequency, under-voltage, or other load-shedding devices at least equal to the levels established \npursuant to the Reliability Assurance Agreement, or be subject to another Member’s control for these \npurposes . . . (e) Shed connected load, share Generation Capacity Resources and take such other coordination \nactions as may be necessary in accordance with the directions of the Office of the Interconnection in \nEmergencies.”)."},{"page":68,"startToken":21692,"endToken":21960,"text":"68 \nPJM may direct curtailment service providers to direct their customers to shed load. \nIf Network Load but that load is not serving as Demand Response, then PJM may issue a \nload shed directive to a Transmission Owner who in turn determine what customers will \nshed load. If Network Load but that load is not serving as Demand Response, then PJM \nmay issue a load shed directive to a Transmission Owner who in turn determine what \ncustomers will shed load. \nF. \nOther  \ni. \nAre any changes to PJM’s energy or ancillary services market rules \nnecessary to address co-location arrangements? \nPJM Response:    \nRegardless of what co-location arrangements are ultimately sanctioned by the \nCommission, permitted by the states, and elected by developers, participants involved in \nco-location arrangements should pay the costs of any grid services they consume and the \narrangements should be reliable and operationally manageable.  As noted in Exhibit A and \nherein, many co-located load configurations utilize grid support and consume ancillary \nservices (including, for example, frequency regulation, black start service, and reactive \nservice).  By way of further response, see PJM’s response to question A.iv, supra. \nii. \nPlease discuss whether back-up service can provide benefits to \ncustomers or otherwise help minimize system costs, including with \nspecific examples or best practices, if possible. \nPJM Response:  \nEven when co-located with an existing generator, co-located load is often (but not \nalways) built with an on-site backup generator to ensure continuity of operations in the \nevent its primary power source is disrupted.  These back-up generators have the potential \nto provide benefits to customers and minimize system costs by participating in the PJM"},{"page":69,"startToken":21960,"endToken":22258,"text":"69 \nmarkets, but currently their use is limited by the Environmental Protection Agency’s \n(“EPA”) National Emissions Standards for Hazardous Air Pollutants (“NESHAP”) for \nstationary reciprocating internal combustion engines (“RICE”) regulations as well as other \nenvironmental restrictions depending on their particular location and permit restrictions. \nPJM understands that most back-up generators installed at large load centers for \nbackup power are Tier 2 under the EPA’s regulations.  Under the EPA’s NESHAP \nregulations, a Tier 2 RICE that provides back-up power for a co-located load may only be \nused in emergency situations as declared by the Reliability Coordinator or other authorized \nentity or for limited periods for non-emergency purposes.  For non-emergencies, the \nNESHAP regulations generally prohibit Tier 2 RICE units from providing non-emergency \ndemand response, generating income for a facility to an electric grid, or otherwise \nsupplying power as part of a financial arrangement with another entity.90  In certain \nsituations, the RICE Tier 2 units may provide demand response or peak load shaving in \nnon-emergencies when local system conditions could lead to a blackout.  Specifically, \nthese Tier 2 units may run for up to 50 hours a year when called upon by the local balancing \nauthority or local transmission system and distribution operator to mitigate or avert voltage \ncollapse or line overloads that could interrupt power.91  However, this run-time counts \ntowards the unit’s overall 100-hour annual run-time limit.  As a result, these back-up \ngenerators have historically been viewed as limited in being able to provide customer and \nsystem benefits by either being a demand response resource or selling excess power into \nthe market.  Therefore, regulatory changes to allow such unit’s ability to provide additional \n                                                 \n90 40 C.F.R. § 60.4211(f)(3).   \n91 78 Fed. Reg. 6674, 6680 (2013); 40 C.F.R. § 60.4211(f)(3)(i)."},{"page":70,"startToken":22258,"endToken":22483,"text":"70 \nback-up service during the pendency of a declared energy emergency could be an important \nmechanism to address resource adequacy concerns in the short term.  Accessing this \nadditional capability more actively may also facilitate large load interconnections, which \nis why PJM has included Option 8 in this response.  PJM will continue to engage with \ngenerators and state and federal regulators on these issues to further realize potential \nopportunities relating to back-up capabilities. \niii. \nParties may also choose to address how co-location arrangements \nmay provide benefits, including potentially reducing required \ntransmission upgrades to interconnect large loads, reducing \ncongestion, or providing operational flexibility during system peaks \nor emergencies?   \nPJM Response:    \nPJM acknowledges that participants in these proceedings have offered for \nconsideration potential benefits of co-location arrangements, including efficiencies of \nsiting load close to generation to conserve certain facility construction and siting costs.  \nPJM looks forward to continued engagement with stakeholders on this issue. \niv. \nParties may also address whether, and if so, how, the Tariff should \nbe modified to best accommodate or encourage co-location \narrangements to be constructed in such a way as to minimize total \nsystem costs or otherwise provide certain benefits, including \nprotections for existing customers and allocation of costs consistent \nwith the cost-causation principle. \nPJM Response:    \nPJM looks forward to engagement with stakeholders and the Commission regarding \nthe eight options outlined in Exhibit A."},{"page":71,"startToken":22483,"endToken":22855,"text":"71 \nv. \nWhat Tariff provisions, if any, are necessary to ensure clarity \nregarding the aspects of service to co-located load and generation \nfacilities that may be administered through the Tariff versus state \njurisdictional retail tariffs? \nPJM Response:    \nGenerators are obliged to comply with applicable law and requirements, including \nstate law.92  So, too, is PJM.93  While additional Tariff revisions may not be necessary to \nclarify the division of labor between PJM’s federally regulated Tariff and the state retail \ntariffs, generators, load, and PJM will need to have assurances and an understanding of \nrelevant law to respect the jurisdictional principles described in PJM’s answer to \nquestion A.i. \nvi. \nWe also encourage parties to address any national security \nimplications associated with co-location arrangements, including \nwith respect to the specific issues discussed in this show cause order, \nand what actions, if any, the Commission should take in response.  \nPJM Response:    \nPJM acknowledges that participants in these proceedings have offered for \nconsideration national security implications associated with co-location arrangements, \nparticularly where large data center loads are involved.  It is a matter of public record that \nthere is data center development focused on directly supporting national security interests \n                                                 \n92 See, e.g., Tariff, Attachment O, Appendix 2, section 23.1.4 (Consent and Approval) (“Such Interconnected \nEntity has sought or obtained, or, in accordance with the Interconnection Service Agreement will seek or \nobtain, each consent, approval, authorization, order, or acceptance by any Governmental Authority in \nconnection with the execution, delivery and performance of the Interconnection Service Agreement and it \nwill provide to any Governmental Authority notice of any actions under this Appendix 2 that are required \nby Applicable Laws and Regulations.”); Tariff, Part IX, subpart B, Appendix 2, section 23.1.4 (Consent and \nApproval) (“Such Interconnected Entity has sought or obtained, or, in accordance with the Generation \nInterconnection Agreement will seek or obtain, each consent, approval, authorization, order, or acceptance \nby any Governmental Authority in connection with the execution, delivery and performance of the \nGeneration Interconnection Agreement and it will provide to any Governmental Authority notice of any \nactions under this Appendix 2 that are required by Applicable Laws and Regulations.”). \n93 See, e.g., Tariff, Attachment O, Appendix 2, section 23.1.4."},{"page":72,"startToken":22855,"endToken":23212,"text":"72 \nin collaboration with various government agencies.  In addition, the need to serve large \ndata center loads is essential to furthering the nation’s strategic interests in supporting the \ncontinued growth of our nation’s AI capabilities.  PJM continues to support and facilitate \nattempts to develop the critical infrastructure needed to support these national security \nimperatives, and looks forward to continued engagement with the Commission and \nstakeholders on this issue. \nvii. \nFinally, for generation units paid for originally by consumers in \nbase rates prior to restructuring, is it fair and/or just and reasonable \nif these units are taken out of the system’s supply stack and devoted \nexclusively to serving co-location arrangements with one or a few \nlarge customers?  \nPJM Response:    \nExhibit A and the explanations contained herein identify potential negative \nimplications for resource adequacy based on the various options identified.  This question \ngoes further and asks about whether customers have an ongoing entitlement to units \nremaining as capacity resources based on their previous regulatory status prior to \nrestructuring.  Whether a specific cost is eligible for recovery is for stakeholders, the \nCommission, and/or appropriate state or local entities to decide.94   \nRespectfully submitted, \n \n \n \n \n \n \n \n/s/ Andrew T. Swers  \n  \nCraig Glazer \nVice President–Federal Government Policy \nPJM Interconnection, L.L.C. \n1200 G Street, N.W., Suite 600 \nWashington, D.C.  20005 \n(202) 423-4743 \ncraig.glazer@pjm.com \nRyan J. Collins \nAndrew T. Swers  \nRuth M. Porter \nWright & Talisman, P.C. \n1200 G Street, N.W., Suite 600 \nWashington, D.C.  20005 \n(202) 393-1200 \n                                                 \n94 See, e.g., Tariff, Part V, section 119 (“[A] Generation Owner with a generating unit proposed for \nDeactivation that continues operating beyond its proposed Deactivation Date may file with the Commission \na cost of service rate to recover the entire cost of operating the generating unit until such time as the generating \nunit is deactivated.”); Operating Agreement, Schedule 6, section 1.5.8(e) (“In evaluating any cost, ROE \nand/or capital structure proposal, PJM is not making a determination that the cost, ROE or capital structure \nresults in just and reasonable rates, which shall be addressed in the required rate filing with the FERC.”)."},{"page":73,"startToken":23212,"endToken":23255,"text":"73 \n \nMark J. Stanisz  \nAssociate General Counsel \nPJM Interconnection, L.L.C. \n2750 Monroe Blvd. \nAudubon, PA  19403 \n(610) 666-8800 \nmark.stanisz@pjm.com \ncollins@wrightlaw.com \nswers@wrightlaw.com \nporter@wrightlaw.com \n \n \n \n \n \n \nAttorneys for  \nPJM Interconnection, L.L.C. \nMarch 24, 2025"},{"page":74,"startToken":23255,"endToken":23335,"text":"DRAFT  3-23-25 (6am EPT) \nCERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served the foregoing document upon each \nperson designated on the official service list compiled by the Secretary in this proceeding. \n \nDated at Washington, D.C., this 24th day of March 2025. \n/s/ Andrew T. Swers  \n \n \n \n \n \n \n \n \nAndrew T. Swers \n \n \n \n \n \n \n \nWright & Talisman, P.C. \n1200 G Street, N.W., Suite 600 \nWashington, D.C.  20005 \n(202) 393-1200 \n \n \n \n \n \n \n \nswers@wrightlaw.com \n \nAttorney for  \nPJM Interconnection, L.L.C."}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":114,"startToken":0,"endToken":326},{"p":3,"at":114,"title":"I. INTRODUCTION","method":"printed heading","endPage":5,"endAt":362,"startToken":326,"endToken":999},{"p":5,"at":362,"title":"II. EXECUTIVE SUMMARY OF EXISTING AND POTENTIAL NEW","method":"printed heading","endPage":21,"endAt":4,"startToken":999,"endToken":6296},{"p":21,"at":4,"title":"III. PJM RESPONSE TO COMMISSION QUESTIONS","method":"printed heading","endPage":21,"endAt":50,"startToken":6296,"endToken":6302},{"p":21,"at":50,"title":"A. General","method":"printed heading","endPage":37,"endAt":102,"startToken":6302,"endToken":12237},{"p":37,"at":102,"title":"B. Transmission Service","method":"printed heading","endPage":45,"endAt":237,"startToken":12237,"endToken":14984},{"p":45,"at":237,"title":"C. Ancillary or other wholesale services","method":"printed heading","endPage":47,"endAt":145,"startToken":14984,"endToken":15489},{"p":47,"at":145,"title":"D. Interconnection Procedures and Cost Allocation","method":"printed heading","endPage":57,"endAt":4,"startToken":15489,"endToken":18093},{"p":57,"at":4,"title":"E. PJM Capacity Market, Reliability, and Resource Adequacy","method":"printed heading","endPage":68,"endAt":461,"startToken":18093,"endToken":21772},{"p":68,"at":461,"title":"F. Other","method":"printed heading","endPage":74,"endAt":26,"startToken":21772,"endToken":23259},{"p":74,"at":26,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":74,"endAt":530,"startToken":23259,"endToken":23335}]}