{"document":{"slug":"rec-20250409-5178","title":"Answer of Talen Energy Corporation in Opposition to Vistra Corp.'s Motion for Clarification and Request for Expedited Treatment","issued":"2025-04-09","accession":"20250409-5178","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Talen Energy Corporation","kind":"rehearing request","file":"sources/filings/text/20250409-5178_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250409-5178","tier":"record","sha256":"f38c50222cc4da367fa8270b8d30ce36597ef3053d4465d477f49baddd974210","pages":4,"tokens":880,"emptyPages":[],"textThemes":["colo"]},"pages":[{"page":1,"startToken":0,"endToken":300,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C., et al. \n \n) \n \nDocket No. EL25-49-000 \nPJM Interconnection, L.L.C.  \n \n) \n \nDocket No. ER24-2172-000 \n \n \n \n \n \n \n \n \n(not consolidated) \n \nANSWER OF  \nTALEN ENERGY CORPORATION \nIN OPPOSITION TO \nVISTRA CORP.’S MOTION FOR CLARIFICATION \nAND REQUEST FOR EXPEDITED TREATMENT1 \n \nTalen Energy Corporation (“Talen”) urges the Commission to act as soon as possible to \nopine on the merits of Talen’s November 20, 2024 Request for Rehearing in Docket No. ER24-\n2172-000 (the “SSES ISA Docket”).2  The Motion for Clarification and Request for Expedited \nTreatment filed by Vistra Corp. (“Vistra”) in Docket No. EL25-49-000 (the “Co-Location Show \nCause Docket”) requests that the Commission act on a narrow subset of the issues raised in Talen’s \nRequest for Rehearing and closely mirrors the issues Vistra raised in the Motion for Clarification \nit filed in the SSES ISA Docket.3  With respect, the Commission should not, at Vistra’s request, \nact in a piecemeal manner.  Talen does not seek piecemeal answers and therefore asks that the \nCommission deny Vistra’s motion.  Instead, the Commission should issue an order as \nexpeditiously as possible that substantively addresses all of the issues raised in Talen’s Request \nfor Rehearing.4 \n \n1 This answer is submitted pursuant to Rule 213 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (“Commission” or “FERC”). \n2 PJM Interconnection, L.L.C., Docket No. ER24-2172-000, Request for Rehearing of Susquehanna Nuclear, LLC \n(Nov. 20, 2024) (“Request for Rehearing”).  \n3 PJM Interconnection, L.L.C., Docket No. ER24-2172-000, Motion for Clarification of Vistra Corp. (Dec. 2, 2024). \n4 Talen filed a Petition for Review with the United States Court of Appeals for the Fifth Circuit that broadly challenges \nthe Commission’s Order Rejecting Amendments to Interconnection Service Agreement issued in Docket No. ER24-"},{"page":2,"startToken":300,"endToken":621,"text":"2 \nI.  \nANSWER \nTalen filed a Request for Rehearing in response to the Susquehanna ISA Order several \nmonths ago and waits for the Commission to take substantive action on its request.5  When it does \nspeak, the Commission should provide more certainty on all the issues raised in Talen’s rehearing \nrequest.  For instance, Talen avers in its Request for Rehearing that the Commission departed from \nthe “necessity standard” it has historically used to evaluate the need for deviations from the pro \nforma Interconnection Service Agreement in the Susquehanna ISA Order.6  The Request for \nRehearing also asks the Commission to clarify its usage of the new “unique interest” standard \nwhich it used to evaluate Susquehanna’s amended Interconnection Service Agreement.7  Without \nan understanding of the circumstances under which the unique interest standard will be applied \nand how to meet the standard, Regional Transmission Organizations and Independent System \nOperators will be unable to detail the rationale for essential modifications with terms acceptable \nto the Commission.  \nThe Commission’s November 1, 2024 order erred in its rulings on these issues and an \nappeal is pending.  Redress on these issues is just as important to Talen as the issues Vistra \nselectively included in its motion.  Talen would welcome a prompt and comprehensive order \ngranting rehearing.  Indeed, granting Talen’s Request for Rehearing would be logically consistent \nwith, and inclusive of, the findings Vistra seeks.  Talen would welcome these findings as part of a \ncomprehensive order granting Talen’s rehearing request.8 \n \n2172-000 on November 1, 2024, including issues that go beyond those raised by Vistra in its motion.  Susquehanna \nNuclear, LLC v. Federal Energy Regulatory Commission, No. 25-60019 (5th Cir. 2025).  \n5 See generally Request for Rehearing,  \n6 Id. at 8-12. \n7 Id. \n8 Vistra requests the Commission to clarify that “the Susquehanna ISO Order should not be read to (1) prejudge the \npermissibility of any particular co-location configuration, (2) indicate that the Commission generally opposes fully"},{"page":3,"startToken":621,"endToken":828,"text":"3 \nSimply put, the clarifications Vistra seeks should be made in the SSES ISA Docket, where \nthe Commission can address all the issues pending before it.  As such, rather than issuing an order \nresponding to Vistra’s selective requests in the Co-Location Show Cause Order docket,9 the \nCommission should deny Vistra’s motion and promptly issue an order granting Talen’s Request \nfor Rehearing in the SSES ISA Docket.  \nII.  \nCONCLUSION \nFor the aforementioned reasons, we respectfully ask the Commission to deny Vistra’s \nmotion and provide the relief Talen requests.  \n \nRespectfully submitted, \n/s/ William S. Scherman \nWilliam S. Scherman \nMelinda J. Warner \nVinson & Elkins LLP \n2200 Pennsylvania Avenue NW \nSuite 500 West \nWashington, DC 20037 \n \nJennifer Mansh \nTalen Energy Corporation \nSenior Vice President, Regulatory and \nExternal Affairs \n600 Hamilton St. \nSuite 600 \nAllentown, PA 18101 \nJennifer.Mansh@TalenEnergy.com \nCounsel for Talen Energy Corporation \nApril 9, 2025 \n \n \n \nisolated behind the meter co-located load, or (3) prohibit parties form following the currently effective tariff rules and \nnegotiating the terms of non-conforming ISAs pursuant to existing tariff provisions.”  Motion at 5. \n9 PJM Interconnection, L.L.C., et al., Docket No. EL25-49-000, Order Instituting Proceeding Under Section 206 of \nthe Federal Power Act and Consolidating with Other Proceedings (“Show Cause Order”)."},{"page":4,"startToken":828,"endToken":880,"text":"4 \nCERTIFICATE OF SERVICE \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service lists compiled by the Secretary in these proceedings. \nDated at Washington, DC, this 9th day of April 2025. \n/s/ Melinda J. Warner \nMelinda J. Warner \nVinson & Elkins LLP"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":3,"startToken":0,"endToken":301},{"p":2,"at":3,"title":"I. ANSWER","method":"printed heading","endPage":3,"endAt":419,"startToken":301,"endToken":688},{"p":3,"at":419,"title":"II. CONCLUSION","method":"printed heading","endPage":4,"endAt":3,"startToken":688,"endToken":829},{"p":4,"at":3,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":4,"endAt":318,"startToken":829,"endToken":880}]}