{"document":{"slug":"rec-20250423-5125","title":"Motion to Intervene Out of Time and Comments of Antora Energy LLC in Response to FERC’s Co-location Order","issued":"2025-04-23","accession":"20250423-5125","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Antora Energy LLC","kind":"comments","file":"sources/filings/text/20250423-5125_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250423-5125","tier":"record","sha256":"5b4d5d99aad34893900a5d8e573661aa00726f7c83313b65ec88208ae60176f9","pages":20,"tokens":5852,"emptyPages":[],"textThemes":["flex","colo","study","adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":187,"text":"UNITED STATES OF AMERICA \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C. \nAllegheny Electric Cooperative, Inc. \nAmerican Transmission Systems, Incorporated \nAtlantic City Electric Company \nBaltimore Gas and Electric Company \nDelmarva Power & Light Company \nDuke Energy Ohio, Inc. \nDuke Energy Kentucky, Inc. \nEast Kentucky Power Cooperative, Inc. \nEssential Power Rock Springs, LLC \nHudson Transmission Partners, LLC \nJersey Central Power & Light Company \nMid-Atlantic Interstate Transmission, LLC \nNeptune Regional Transmission System, LLC \nOld Dominion Electric Cooperative \nPECO Energy Company \nPPL Electric Utilities Corporation \nPotomac Electric Power Company \nPublic Service Electric and Gas Company \nRockland Electric Company \nTrans-Allegheny Interstate Line Company \nTransource West Virginia, LLC \nUGI Utilities, Inc. \nMonongahela Power Company \nThe Potomac Edison Company \nCommonwealth Edison Company \nCommonwealth Edison Company of Indiana, Inc. \nThe Dayton Power and Light Company  \nAEP Appalachian Transmission Company, Inc. \nAEP Indiana Michigan Transmission Company, Inc. AEP \nKentucky Transmission Company, Inc. \nAEP Ohio Transmission Company, Inc. \nAEP West Virginia Transmission Company, Inc. \nAppalachian Power Company \nIndiana Michigan Power Company \nKentucky Power Company \nKingsport Power Company \nOhio Power Company \nWheeling Power Company \nDuquesne Light Company \nVirginia Electric and Power Company \nLinden VFT, LLC \nDocket Nos. EL25-49-000"},{"page":2,"startToken":187,"endToken":415,"text":"City of Cleveland, Department of Public Utilities, Division \nof Cleveland Public Power \nCity of Hamilton, OH \nSouthern Maryland Electric Cooperative, Inc. \nOhio Valley Electric Corporation \nAMP Transmission, LLC \nSilver Run Electric, LLC \nNextEra Energy Transmission MidAtlantic Indiana, Inc. \nWabash Valley Power Association, Inc. \nKeystone Appalachian Transmission Company \nLarge Loads Co-Located at Generating Facilities  \nConstellation Energy Generation, LLC \nv.  \nPJM Interconnection, L.L.C. \n \n \n \n \n \n \n \n \n \n \nAD24-11-000 \n \n \nEL25-20-000 \n(Consolidated) \n \n \n \n \n \nMotion to Intervene Out of Time and Comments of Antora Energy LLC In Response to the \nCommission’s Co-location Order \n \nPursuant to the Federal Energy Regulatory Commission’s (“FERC” or “Commission” \norder instituting a Federal Power Act (“FPA”) section 206 proceeding concerning PJM \nInterconnection, L.L.C.’s (“PJM”) rules regarding large loads co-located at generating facilities \nin the PJM footprint,1 as well as Rule 213 of the Commission’s Rules of Practice and Procedure,2 \nAntora Energy LLC (“Antora”) hereby provides comments on the order issued by the \nCommission in the above-captioned docket and PJM’s response thereto.3  Antora urges the \nCommission to find that the existing Tariff is not just and reasonable, and to require a \nreplacement rate that allows for the flexible nature of Antora’s thermal storage load to be \n3 Answer of PJM Interconnection (Mar. 24, 2025) (“PJM Answer”). \n2 18 C.F.R. § 385.213. \n1 PJM Interconnection, L.L.C., 190 FERC   61,115 (2025) (“Co-location Order”). \n2"},{"page":3,"startToken":415,"endToken":737,"text":"appropriately and efficiently accounted for in its study processes, procedures, and transmission \nrates.4  The Commission should direct PJM to build from Options 4 and 7 set forth in the PJM \nAnswer to create such a rate,5 while not precluding the development of additional rate designs \nand interconnection processes in the future or in other regions, as may be necessary to integrate \nflexible loads such as those of Antora’s thermal energy storage charging.  \nAntora is a U.S. manufacturer of thermal batteries, which are domestically built in San \nJose, California, and developer of thermal storage projects for industrial facilities in the U.S. and \nabroad.  Antora is at the forefront of an industry that holds tremendous potential to lower the cost \nof industrial processes.  Antora can help support American energy dominance by providing a \nmarket for off-peak, low-cost power during periods of low demand.  But as explained herein, \nappropriate regulation that facilitates interconnection and transmission service capable of \naccounting for the unique low load factor, highly flexible nature of thermal energy storage \ncharging loads is required for this industry to thrive and to maximize its benefits while \nminimizing costs for the grid and its customers.  Specifically, the flexible load profile of thermal \nenergy storage facilities allows them to contribute to grid reliability while minimizing grid \ncapacity costs and infrastructure costs and making greater use of existing generation and \ntransmission infrastructure.  The Commission’s Order to Show Cause creates an important \nopportunity for PJM’s regulatory framework to evolve to meet the needs of Antora and other \nsimilar customers, remedying deficiencies that render the existing tariff unjust and unreasonable.   \n5 See PJM Answer at 13-14, 18-19 (outlining Options 4 and 7 to facilitate co-location \narrangements).  \n4 See Co-location Order at P 87 (requesting comments addressing “(1) whether the \nexisting tariff remains just and reasonable and not unduly discriminatory or preferential” and (2) \n“what changes to the Tariff should be implemented as replacement rates.”)   \n3"},{"page":4,"startToken":737,"endToken":1044,"text":"I.​\nBackground \nAntora’s thermal batteries will provide heat to industrial operations.  Initial deployments \nwill focus on industrial process heat up to ~400C, and future deployments will include \nhigh-temperature processes such as mineral refining, cement, glass, aluminum, and steel.6  The \ntechnology uses low cost electricity to resistively super-heat carbon blocks that are capable of \nultra-fast charging and absorption of heat.  The carbon blocks store the energy as heat, at \ntemperatures over 2,000◦C, in a compact thermal battery.  The energy is discharged in the form of \nheat at the scale and temperature needed by large industrial operations.  Antora is also \ndeveloping thermal storage products that allow the energy stored as heat to produce electricity, \nthereby serving as electric energy storage devices. \nLike electro-chemical batteries, a significant portion of Antora’s thermal battery value \ncomes from flexibility.  The battery is charged during periods of high energy production and low \ndemand, thereby helping reduce curtailment of renewable resources and allowing the thermal \nbattery to absorb low value/negatively priced electricity.  Because thermal storage can provide \n24/7 heat over a multi-day period by charging only roughly 1/3 of the time, it can fully avoid \nperiods of high demand, high-capacity utilization and high electricity pricing.  This allows \nAntora’s industrial and manufacturing clients to gain the benefits of low-cost periods of excess \ngeneration without requiring the factories themselves to curtail when low cost power is not \navailable and during periods of coincident peak transmission system use and demand.  By \nco-locating an Antora thermal battery with a generation resource, Antora can provide factories \n6 CNN has described Antora’s technology and electricity usage. Weir, B., These hot rocks \ncan glow brighter than the sun. They could also help spell the end of fossil fuels (Dec. 18, 2023), \navailable at \nhttps://www.cnn.com/2023/12/16/climate/solution-hot-rocks-renewable-energy-battery/index.ht\nml  \n4"},{"page":5,"startToken":1044,"endToken":1320,"text":"with onsite power, heat for industrial processes, and energy storage if necessary.  Co-location of \nhighly flexible, low load factor thermal energy storage can allow better utilization of \nvariable renewable energy resources that might otherwise be curtailed, without causing \nadditional co-incident peak demand and without impacting the ability  of that renewable \nenergy project to support resource adequacy goals.  Co-location can also minimize or \neliminate the already low impacts on the transmission system because thermal energy storage can \nbe operated to use only energy from a co-located energy source (and only during hours when that \nresource is not needed for capacity). \nAntora is committed to paying its fair share of grid costs.  The pathway a resource takes \nto interconnect to the system, whether via a supply study process that incorporates co-located \nload or through an Electric Distribution Company (“EDC”) or Transmission Owner (“TO”) \nprocess for interconnecting load alone, should not itself cause disparate rate treatment \nindependent of the characteristics of the underlying load and generation facilities.  At the same \ntime, however, study processes should account for load shape, flexibility, and dispatchability \nwhen determining the infrastructure necessary to serve that load.  Companies like Antora should \nnot be required to fund infrastructure or secure network resources that they do not need.  Antora \ncan follow curtailment instructions from grid operators (including Regional Transmission \nOrganizations (RTOs) and EDCs) if doing so facilitates studying Antora’s load in a manner that \nappropriately accounts for its flexibility and low load-factor. \nII.​\nCommunications \nNoah Long​\n​\n​\n​\nJason Evans​\n \nAntora Energy LLC​ ​\n​\nAntora Energy  \n200 West De Vargas St​\n​\n1244 Reamwood Ave. \nSanta Fe, NM 87501​ ​\n​\nSunnyvale, CA 94089 \nnoah.long@antora.energy ​\n​\njason.evans@antora.energy \n \n5"},{"page":6,"startToken":1320,"endToken":1626,"text":"III.​\nMotion to Intervene Out of Time \nAs the developer of facilities with large and flexible thermal battery loads that may often \nbe co-located with generation facilities, Antora’s interests cannot be represented by any other \nparty and its intervention is in the public interest.  Antora respectfully requests that the \nCommission grant this request to intervene out-of-time.  Antora accepts the record as it stands, \nand this intervention will not place any additional burden on any other party, nor will it disrupt or \ndelay Commission proceedings in this matter. \nIV.​\nComments \nPJM’s existing tariff is unjust, unreasonable, and unduly discriminatory because it does \nnot offer any study process or form of transmission service that properly accounts for highly \nflexible and low load factor loads such as Antora’s thermal energy storage.  This yields higher \ncosts or delays for the developers of flexible load facilities and for other customers, delays the \ninterconnection of new loads, and fails to use the full capabilities of these loads to enhance \nsystem reliability.   \nThe Commission should order PJM to remedy these deficiencies by developing a \nreplacement rate that builds from Options 4 and 7 set forth in PJM’s Answer.  Specifically, the \nCommission should direct PJM to enable Option 4 by modifying its interconnection procedures \nto facilitate the study of co-located loads.7  In addition, the Commission should direct PJM to \nbuild out Option 7 by developing a new non-capacity backed service offering.  However, unlike \nOption 7 in PJM’s filing which suggests only a transitional service product, the Commission \nshould direct PJM to provide such service on a permanent or transitional basis, subject to the \n7 As described in Section IV.B.1 below, Antora supports potential modifications to Option \n4 to limit reliability risk and resource adequacy and capacity price risks for other customers, to \nthe extent the Commission deems such modifications necessary.  \n \n6"},{"page":7,"startToken":1626,"endToken":2001,"text":"election of the transmission customer.  These tariff revisions are not mutually exclusive with the \ndevelopment of additional options set forth in the PJM Answer that may be beneficial, such as \nOption 6 to provide a faster path to studying new generation co-located with new load or Option \n8 to facilitate more effective participation of Network Load as demand response.8  The \nCommission could integrate the new flexible service interconnection pathways with any of the \nother options it may direct PJM to pursue, and should make clear that its order remedying PJM’s \ntariff does not preclude the development of additional pathways to interconnect and serve \nco-located load in PJM or elsewhere.  \nA.​\nPJM’s tariff is unjust, unreasonable and unduly discriminatory in failing to \nappropriately study and incorporate flexible loads \nPJM outlines two sets of potential pathways for co-located load to connect to the system, \nbut neither of them appropriately incorporates highly flexible, low load factor flexible loads.   \nThe first set of potential pathways relies on the generator interconnection procedures, \nwith loads connecting behind a generator’s Point of Interconnection using PJM’s necessary study \n8 PJM explains that Option 6 “would also be open for existing generation that could serve \nthe energy needs of the large loads so long as the generator would still be available to PJM as a \nCapacity Resource.”  PJM Answer at 16.  Antora facilities could co-locate with existing \ngeneration in this manner, drawing from the co-located generation only when it is not needed for \ncapacity purposes.  To operationalize such a process, PJM could develop a mechanism through \nwhich it can provide automated curtailment instructions to the load so that the load can avoid \ndrawing from the generation whenever the generation is needed for resource adequacy.  \nModifications may be required to PJM’s capacity accreditation to ensure that credit is based on \nthe generation’s availability to PJM when needed, rather than on its total energy output to the \nPJM system.  Option 8 is beneficial insofar as it may facilitate more effective demand response \nparticipation, but it does nothing to remedy the problems in PJM’s study processes that fail to \naccount for or leverage the flexibility of load to minimize transmission infrastructure costs and \nrely on fewer Network Resources to serve the same amount of load.   \n7"},{"page":8,"startToken":2001,"endToken":2347,"text":"process.9   These pathways offer a significant efficiency advantage over studying load separately \nfrom the colocated generation, as they assess the electrical impacts of proposed new generation \nand load in a single interconnection process.  As the record in Docket No. AD24-11 makes clear, \nco-location offers a host of potential benefits, including reduced infrastructure costs.10  A single \nstudy process will better ensure that these savings are accurately captured.  It also reduces project \nrisk for the developer where the proposed new energy supply resource and co-located load are \ncommercially reliant on one another, as being studied in a single process allows the different \nproject components to receive study results on the same timeline, make decisions about \nmilestone payments, and demonstrate commercial readiness in a single forum.  But this set of \npathways fails to provide an adequate pathway for flexible loads because, as PJM explains, it \n“does not have a tariffed study process for load.”11  The Tariff’s study procedures lack the \nnecessary detail to inform customers such as Antora how their charging loads will be studied and \nconfirm that the loads’ flexibility will be accounted for.  The process has high transaction costs, \nas it requires the development of bespoke agreements.  In a recent proceeding, the Commission \nrejected a non-conforming interconnection agreement providing for a load to be studied under \nthis process where the underlying agreement presented generalized co-location issues rather than \nunique concerns particular to the individual customer.12   \n12 PJM Interconnection, L.L.C., 189 FERC   61,078 (2024), order on reh’g, 191 FERC   \n61,025 (2025). \n11 PJM Answer at 47.  The Commission suggests that PJM’s necessary study process is \nnot adequate to study the reliability impacts of co-located loads.  See Co-location Order at P 79.  \n10 See, e.g., Pre-technical Conference Comments of the Clean Energy Buyers Association, \nDocket No. AD24-11, at 17-19 (Oct. 25, 2024).  \n \n9 See PJM Answer at 47-50 (outlining how and when PJM conducts its necessary study \nprocess for co-located load and explaining that load studied pursuant to this path way may or \nmay not register as Network Load).  \n8"},{"page":9,"startToken":2347,"endToken":2723,"text":"The second set of pathways requires load to register as Network Load.  But as PJM states, \nits transmission planning, operating protocols, and procedures for providing service to Network \nLoad do not account for load shape and flexibility.  Instead, PJM “assumes that it must serve the \ncustomer’s full load during peak conditions on the system.”13  This assumption is a poor match \nfor loads such as Antora’s, which only draw from the system roughly 1/3 of the time and never \nduring peak conditions, and are capable of responding immediately to curtailment instructions \nsent by PJM or the relevant EDC.14   \nWhile PJM’s necessary study process to some extent captures the flexibility of co-located \nload, PJM does not capture those benefits where the load is required to register as Network \nLoad.15  Per PJM’s response, state law may require a customer to designate load as Network \n15 The Commission directly asked PJM to “explain whether PJM’s necessary study \nprocess allows a co-location arrangement to demonstrate its capability to flexibly adjust its \nwithdrawals from or injections to the transmission system” such as “by curtailing on-site load.”  \nCo-location Order at P 88.d.ii.  \n \n14 While PJM offers demand response and price responsive demand programs that \nflexible loads may take advantage of in order to capture the value of avoiding electric energy \nconsumption during peak demand, these programs do not reflect load flexibility in PJM’s \ntransmission planning and operating procedures, which currently do not have a mechanism to \nallow load to respond to transmission system constraints in addition to generation constraints. \n13 PJM Answer at 39 n. 64.  As PJM explains, in “any configuration where the co-located \nload is Network Load” the relevant EDC would conduct “load integration studies . . . in addition \nto necessary studies” performed in PJM’s generation interconnection process.  Id. at 8.  But the \nassumptions that PJM uses for Network Load in its own transmission planning and operations \nare highly relevant for those state-jurisdictional processes, as they define the scope of \ntransmission service that will be studied in those processes for non Native Load Customers, and \nNetwork Service is designed to be comparable to the transmission service that Transmission \nOwners provide to Native Load Customers.  See id. at 39 n. 61 (highlighting the principle of \ncomparable service). \n9"},{"page":10,"startToken":2723,"endToken":3050,"text":"Load.16  Further, the necessary study process applies only in the limited circumstance where “the \nload is assumed to never take power from the grid.”17   \nFurther, as discussed above, PJM’s tariff lacks general language as to how this necessary \nstudy process will be applied to loads.  PJM notes that “it is possible that the Generation Owner \ncould propose a special protection scheme or Remedial Action Scheme (‘RAS’) to reduce the \nload under certain conditions (where, for example, the generating unit comes offline),” but PJM \ndoes not have any standard language to provide for any such arrangement and appears to \ncontemplate load modulation as something that would occur only in an emergency rather than as \na matter of course, as would occur with Antora’s thermal battery charging.  While PJM’s existing \nBehind the Meter (“BTM”) Generation rules provide one limited pathway to interconnection that \npartially accounts for load flexibility insofar as PJM allows load to be netted with generation \nwhen calculating Network Load,18 this structure is primarily concerned with rate treatment and \ndoes not provide for planning, forecasting, and operations procedures that fully leverage the \nflexibility of the underlying load to contribute to grid reliability and use less network \ninfrastructure. \nPJM’s failure to offer a service that matches the needs of flexible loads such as those of \nAntora facilities or other co-located facilities with flexible operations capabilities is unjust and \nunreasonable and unduly discriminatory19 because it may delay or prevent the interconnection of \n19 See Calpine Corp. et al. v. PJM Interconnection, L.L.C., 163 FERC   61,236, at P 68 n. \n112 (2018) (“Typically, undue discrimination cases involve a seller charging a different rate to \nsimilarly-situated customers; but undue discrimination can also occur when a seller charges the \n18 Id. at 35. \n17 PJM Answer at 51.  Under this study process, “the generator’s Capacity \nInterconnection Rights” are “reduced by the expected peak MW utilization of the co-located \nload.”  Id. \n16 PJM Answer at 14. \n \n10"},{"page":11,"startToken":3050,"endToken":3412,"text":"these loads,20 trigger the construction of infrastructure that is not needed to serve them, and fail \nto incentivize customers to provide operational flexibility that could benefit the system.  \nTo the extent PJM requires all loads to register as Network Load and assumes it must \nserve the customer’s full peak load during peak conditions even if the load is flexible and could \nbe curtailed at PJM’s direction, this is likely to overcharge both the interconnecting load \ncustomer, and other customers on the system for transmission service or interconnecting \nfacilities.  It overcharges the interconnecting loads because, as PJM explains, “[t]he costs of new \nfacilities required to interconnect the new Network Load are charged to the Network \nCustomer.”21  Where a customer could have instead taken curtailable transmission service that \nallows PJM and/or the EDC to curtail its load if that service were offered, the failure to provide a \nservice option that incorporates load flexibility will directly lead to costs for the interconnecting \ncustomer that do not appropriately reflect its flexibility and resulting ability to avoid using high \nvalue energy or grid capacity.22  And it will lead to increased costs for other customers because \nPJM’s transmission and interconnection study processes and operating protocols will apply a \nlack of headroom in its system based on its assumed need to serve the entirety of the Network \n22 Depending on how PJM interprets its Tariff, this requirement may also require a \nflexible load to secure more Network Resources than would be necessary to provide service to \nthe load if its flexibility were properly accounted for.  In the context of developing a project in \nanother RTO, the RTO has indicated that the LSE serving Antora must secure an amount of \nnetwork resources to match the non-coincident peak load of the proposed Antora facility, a \nrequirement that would substantially increase the project’s costs. \n21 PJM Answer at 40. \n20 While interconnection processes for retail customers are generally administered by \nEDCs pursuant to state jurisdictional processes, an EDC taking Network Integration \nTransmission Service from PJM must account for the terms of that service when designing retail \nrates, services, and interconnection processes.  \n \nsame rate to differently-situated customers.”).  \n \n11"},{"page":12,"startToken":3412,"endToken":3728,"text":"Load at any given moment, despite the fact that the customer is capable of dispatching down \npursuant to PJM and/or EDC instructions.23  This, in turn, will trigger identification of \ninfrastructure upgrades that could have been avoided, with such costs either allocated pursuant to \nPJM’s applicable transmission planning process or else attributed to other Network Customers or \ninterconnecting supply resources, depending on which study process identifies a need for \ninfrastructure based on the assumption that the load may need to be served at any moment even \nthough it is flexible and dispatchable. \nBy failing to offer a transmission service suited to flexible load, PJM also provides a \ndisincentive to load flexibility that will yield higher capacity supply costs.  PJM explains that \nwhether or not Network Load is flexible, “PJM will include the customer’s full load in the RPM \nfor purposes of procuring adequate capacity to serve the load.”24  As PJM explains, “where \nconditions are tight, any additional load on the system requires either the addition of supply \nresources to serve that load reliably, or flexibility on the part of the load to curtail its \nconsumption from the transmission system when necessary to maintain reliability.”25  To the \nextent that rates do not facilitate “supply and operational flexibility,” the system will require \nmore resources to provide the same level of reliability in service to customers, rendering rates \nunjust and unreasonable.”26  If properly incorporated into PJM’s operations, fully flexible load \nsuch as that of Antora’s facilities need not impose any new resource adequacy burden.  Antora \nsupports a rate mechanism and operations protocols that would allow PJM to direct Antora to \n26 Co-location Order at P 85. \n25 Id. at 8.  \n24 Id. at 39 n. 64.  \n23 PJM explains that it “will include the full load in the Load Forecast for purposes of \nPJM’s transmission planning with RTEP.”  PJM Answer at 39 n. 64.  \n12"},{"page":13,"startToken":3728,"endToken":4066,"text":"fully curtail its load whenever called upon to do so by PJM and ensure that the Antora load does \nnot draw from the system when the grid is stressed either due to insufficient generation supply or \ndue to a transmission system constraint. \nThe costs of this unnecessary infrastructure and capacity are substantial.  A recent study \nby researchers at the Nicholas Institute for Energy, Environment & Sustainability at Duke \nUniversity suggests that nearly 100 GW of additional load could be served using existing \ninfrastructure if the load were flexible.27        \nB.​\nThe Commission can order a just and reasonable and not unduly \ndiscriminatory replacement rate that builds from Options 4 and 7 set forth \nby PJM  \nTo address the deficiencies that render PJM’s existing tariff unjust, unreasonable, and \nunduly discriminatory, the Commission should direct PJM to revise its tariff so as to enable \nOption 4, and to provide for a non-capacity backed transmission service like that described in \nOption 7 but available on a permanent basis.  These tariff revisions would facilitate the \nintegration of highly flexible, low load factor loads co-located with supply resources.  These \ntariff revisions are not mutually exclusive with other tariff mechanisms to support co-location, so \nthe Commission should make clear that they do not preclude the development and submission of \nother options set forth in PJM’s filing, or other potential tariff designs not included therein.  \n1.​ The Commission should require PJM to revise its tariff so as to facilitate \ninterconnection pursuant to PJM’s Option 4 \nThe Commission should require PJM to enable its proposed Option 4, as this is the only \n27 Tyler Norris et al., Rethinking Load Growth: Assessing the Potential for Integration of \nLarge Flexible Loads in US Power Systems (2025), available at \nhttps://nicholasinstitute.duke.edu/sites/default/files/publications/rethinking-load-growth.pdf.  \nWhile the study focused on headroom to serve peak demand and did not account for certain \ntechnical constraints of power plants or transmission constraints, it nevertheless suggests very \nsignificant potential system benefits of integrating flexible load.  Id. at 3, 23. \n13"},{"page":14,"startToken":4066,"endToken":4483,"text":"pathway that allows for the fully coordinated study of co-located generation and load.  As PJM \nexplains, tariff modifications are required to implement Option 4 in the wake of the \nCommission’s decision in Docket No. ER24-2172.28  Further, PJM indicates that were it to \npursue this option, tariff changes would be appropriate to provide for the collection of ancillary \nservices charges used by the co-located facilities.29  \nWhile PJM identifies certain aspects of Option 4 that cause PJM to not prefer this option, \nthese risks would be mitigated for low-load factor loads such as Antora’s.  Antora would also \nsupport modifications to this option to ensure that its use does not compromise resource \nadequacy or increase capacity costs for other customers.   \nThe principal risk cited by PJM with regard to Option 4 is the risk associated with system \nprotection facilities needed to prevent delivery of the energy from the grid should the generator \ngo offline.”30  This risk is inherently lower for Antora’s thermal battery facilities, as its low load \n30 Id. at 14.  PJM also indicates that it prefers “Network Load” status because it allows for \n“[m]ore comprehensive and holistic system planning based on Network Load status” and \nprovides for “[e]nhanced ability to manage load curtailment priority in emergency conditions.”   \nId. at 39.  But as discussed above, PJM’s system planning processes for Network Load do not \nappropriately capture flexible loads.  Antora supports integrating co-located facility loads into \nN-1 operating procedures, but including fully flexible loads in load forecasts and transmission \nplans will overbuild the system.  With regard to load shedding and curtailment, Antora would \nsupport implementing Option 4 in a manner that ensures the required system protection schemes \ncurtail the co-located load in advance the curtailment of other system loads.  PJM also cites a \npotential drawback in not registering co-located load as Network Load of losing “access to \npotential Demand Response capabilities of large co-located loads.”  Id. at 39.  However, \nanalogous system benefits could be captured through the design of the relevant protection \nscheme and rules regarding the capacity accreditation of the co-located generation resource.  \nFERC should require PJM to design these mechanisms such that the load can be curtailed in \nresponse to PJM’s direction, thereby leaving the co-located generation available to fully \ncontribute to resource adequacy.  \n \n29 Id. at 13.  The design of ancillary services charges should reflect the services the \nco-located facility needs.  Inverter-based resources, for example, will require a different mix of \nservices than synchronous generating facilities. \n \n28 PJM Answer at 14. \n \n14"},{"page":15,"startToken":4483,"endToken":4813,"text":"factor facilities only charge at times when energy is abundant and low cost.  When the grid is \nstressed, the facilities will not draw from the grid or the co-located generation, allowing the \nco-located generation to support the grid’s needs.  Antora would support limits on the use of \nOption 4, restricting its use only to co-located loads that exhibit these characteristics and thereby \nlimiting operational risk.  And while PJM argues that Option 4 “carries operational risk in that \nthere is a dependence on the protection system to support reliability,”31 no equipment is immune \nfrom failure.  PJM can ensure that the use of these protection schemes does not increase overall \nreliability risk to the system by implementing operational standards for such protection schemes, \nand by incorporating them into its N-1 operating protocols.  With these measures in place, a \nfailure of system protection equipment would be equivalent to an outage of a generation or \ntransmission element on PJM’s system, which the system is designed to reliably overcome. \nFurther, while the use of Option 4 potentially raises concerns insofar as it may provide a \nfaster pathway to interconnecting new loads to existing generation facilities, thereby impacting \nresource adequacy and capacity costs, these concerns do not apply to Antora’s thermal battery \nloads given their load profile.  Specifically, Antora facilities are designed to draw electric energy \nfrom the system for charging only when it is abundant and low cost, allowing the co-located \ngeneration facility to continue to support resource adequacy for the PJM system.  So long as \naccreditation and co-location rules allow for these resources to continue to contribute to system \nresource adequacy, the addition of low-load factor, highly flexible loads such as Antora’s to \nexisting facilities will not impact capacity prices or reduce resource adequacy.  Protection \nschemes could ensure not only that co-located loads never draw power from the grid, but also \ncould ensure that the loads do not draw energy during times the PJM system requires it for \n31 Id. at 14. \n \n15"},{"page":16,"startToken":4813,"endToken":5088,"text":"resource adequacy, thereby preserving the capacity value of the co-located resource for the \nsystem.  Antora would support rules that require the use of such protection schemes, and urges \nthe Commission to require modification to capacity accreditation rules as necessary to \nappropriately reflect their use.  \n2.​ The Commission should require PJM to implement tariff changes that enable \ncustomers to take non-capacity backed transmission service on a permanent \nbasis \nThe Commission should also require PJM to develop a new transmission service offering \nlike that described in Option 7, but offered on a permanent basis.  PJM’s proposed Option 7 \nwould provide for “a new non-capacity backed service that could be curtailed in advance of \nemergency procedures.”32  As PJM explains, this service “would allow a large load to integrate \nas Network Load at a potentially faster pace than under existing load integration frameworks.”33  \n“[T]he load would avoid capacity costs . . . in return for its willingness to curtail load . . . in those \nsituations where, by way of example, PJM has identified conditions that may threaten the \nintegrity or reliability of the PJM Region or the regional power system.”34 \nPJM suggests offering this service to customers “for a transitional period until any \nresource adequacy supply/demand imbalances associated with the large load addition could be \naddressed and the load could assume full Network Load status with all of its attendant \nbenefits.”35  But it also explains that “[p]otential variations on this option could be explored with \nthe ultimate goal being to enhance resource adequacy and provide opportunities for large loads to \n35 Id. at 18-19.  \n34 Id. at 19.  \n33 Id. at 18.  \n32 Id. at 9.  \n16"},{"page":17,"startToken":5088,"endToken":5392,"text":"efficiently connect to the system by providing incentives for large loads to be more flexible.”36 \nAntora urges the Commission to require PJM to offer customers the option of taking this \nservice on a permanent rather than transitional basis.  As Antora has explained, its thermal \nstorage charging load is inherently flexible.  Unlike high load factor loads which may see \nflexible interconnection as a sub-optimal option that makes sense on a temporary basis in \nexchange for faster interconnection, Antora seeks flexible transmission service throughout the \nlife of the facility.  Offering non-capacity backed transmission service on a permanent basis \nwould allow PJM to capture the benefits discussed above, serving the same amount of total load \nat lower cost, with less transmission infrastructure and fewer capacity resources.  \n​\nWhile PJM’s filing is a significant step forward in indicating a willingness to offer \nnon-capacity backed transmission service, it leaves several questions unanswered.  To \noperationalize this proposal, PJM would need to propose detailed tariff provisions describing the \nnew type of service and setting forth obligations for the transmission provider and transmission \ncustomer.  PJM would need to provide a mechanism for PJM and/or the relevant EDC to \ncommunicate curtailment instructions to the relevant load, providing for operational protocols \nconsistent with NERC requirements, as well as a rate structure for the new service.  And it would \nneed to provide for operations protocols, including revised N-1 procedures that leverage this \ncapability.  PJM should explain how its operations protocols and transmission planning and \ninterconnection study assumptions will be adjusted to account for load flexibility and \ndispatchability, as well as describe how it will revise its load forecasting used for determining the \namount of capacity required to serve customers.  Given that EDCs would continue to administer \nstate-jurisdictional processes for load, the Tariff should explain how these processes interact with \n36 Id. at 19.  \n17"},{"page":18,"startToken":5392,"endToken":5668,"text":"PJM’s operations protocols and planning processes for the new transmission service.  By \nenabling load-flexible, non-capacity backed transmission service at the wholesale level, EDCs \ncould take this service and secure commitments from their retail customers so as to take \nadvantage of the benefits of this service and comply with the operational requirements it \nimposes. \nAntora notes that in taking such service (either at the PJM level or passed through a \nrelevant EDC, as appropriate given the facility configuration), it would be willing to respond to \ncurtailment instructions from PJM or the relevant EDC.  Further, Antora facilities could provide \nfor load flexibility not solely during emergency conditions.  Rather, they modulate charging load \nas a matter of routine operations.  \nBy requiring PJM to build out Option 7 so as to offer permanent transmission service and \noperations protocols that more fully leverage flexible load, the Commission can facilitate the \nintegration of more load, more quickly, at lower total cost to customers, while also reducing \ncurtailment and thereby supporting the addition of new low-cost variable generation resources.  \nV.​\nConclusion \nWhile the Commission’s inquiry into co-location was initiated in response to a discrete \nchallenge involving load locating behind-the-meter of large generating facilities, it has \nspotlighted a broader challenge in serving rapidly growing load with an aging grid and outdated \ninterconnection processes for load and generation that too frequently result in unacceptable \ndelays.  The Commission’s Co-Location Order takes an important step forward in finding that \nthe PJM tariff may be unjust and unreasonable in several respects, and the Commission \nappropriately highlights the potential benefits of flexible facilities.   \nTo its credit, PJM expresses a willingness to take significant steps forward in evolving its \n18"},{"page":19,"startToken":5668,"endToken":5791,"text":"transmission service and study processes to meet the needs of load and generation in a timelier \nand more affordable way.  But to make rapid progress, the Commission must give PJM clear \ninstructions in developing its replacement rate.  By implementing Option 4, PJM can provide for \nan efficient study process and more fully capture the benefits of co-located facilities.  And \nfacilitating non-capacity backed transmission service by offering Option 7 on a permanent as \nwell as temporary basis is a ‘no regrets’ measure that will help PJM and the nation address the \nbuilding crisis in serving load without precluding the pursuit of other service or options, and \nwithout inappropriately shifting system costs.   \n \nRespectfully submitted, \nNoah Long​\n​\n \nDirector, State and Regulatory Affairs​\n​\n \nAntora Energy LLC​   \n \n \n19"},{"page":20,"startToken":5791,"endToken":5852,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have this day served the foregoing document upon each person designated \non the official service list compiled by the Secretary in this proceeding. Dated at Santa Fe New \nMexico, this 23rd day of April, 2025. \n/s/ Noah Long \nNoah Long​\n​\n​\n​\n \nAntora Energy LLC​ ​\n​\n \n200 West De Vargas St​\n​\n \nSanta Fe, NM 87501​  \n \n \n \n \n \n \n \n \n \n \n20"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":4,"endAt":4,"startToken":0,"endToken":738},{"p":4,"at":4,"title":"Background","method":"printed heading","endPage":18,"endAt":1177,"startToken":738,"endToken":5565},{"p":18,"at":1177,"title":"Conclusion","method":"printed heading","endPage":20,"endAt":0,"startToken":5565,"endToken":5791},{"p":20,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":20,"endAt":388,"startToken":5791,"endToken":5852}]}