{"document":{"slug":"rec-20250423-5147","title":"Comments and Intervention of Delaware Public Service Commission on the Show Cause Order issued on 02/20/2025","issued":"2025-04-23","accession":"20250423-5147","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Delaware Public Service Commission","kind":"comments","file":"sources/filings/text/20250423-5147_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250423-5147","tier":"record","sha256":"b9cb0fcba16f21f5c4c896f050eeff6e1dc1ed537949fb3feef612a791ac0e93","pages":9,"tokens":2077,"emptyPages":[],"textThemes":["adequacy","colo","study"]},"pages":[{"page":1,"startToken":0,"endToken":187,"text":"UNITED STATES OF AMERICA \nFEDERAL ENERGY REGULATORY COMMISSION \n \n  \nPJM Interconnection, L.L.C.  \n \n \n) \n Docket Nos. EL25-49-000 \nAllegheny Electric Cooperative, Inc.  \n \n)  \nAmerican Transmission Systems, Incorporated \n) \nAtlantic City Electric Company \n \n \n) \nBaltimore Gas and Electric Company \n \n) \nDelmarva Power & Light Company  \n \n) \nDuke Energy Ohio, Inc. \n \n \n \n) \nDuke Energy Kentucky, Inc.  \n \n \n) \nEast Kentucky Power Cooperative, Inc. \n \n) \nEssential Power Rock Springs, LLC  \n \n) \nHudson Transmission Partners, LLC  \n \n) \nJersey Central Power & Light Company \n \n) \nMid-Atlantic Interstate Transmission, LLC  \n) \nNeptune Regional Transmission System, LLC \n) \nOld Dominion Electric Cooperative  \n \n) \nPECO Energy Company \n \n \n \n) \nPPL Electric Utilities Corporation \n \n \n) \nPotomac Electric Power Company \n \n \n) \nPublic Service Electric and Gas Company \n \n) \nRockland Electric Company  \n \n \n) \nTrans-Allegheny Interstate Line Company  \n) \nTransource West Virginia, LLC \n \n \n) \nUGI Utilities, Inc. \n \n \n \n \n) \nMonongahela Power Company \n \n \n) \nThe Potomac Edison Company \n \n \n) \nCommonwealth Edison Company \n \n \n) \nCommonwealth Edison Company of Indiana, Inc. \n) \nThe Dayton Power and Light Company  \n \n) \nAEP Appalachian Transmission Company, Inc.  \n) \nAEP Indiana Michigan Transmission Company, Inc.) \nAEP Kentucky Transmission Company, Inc.  \n) \nAEP Ohio Transmission Company, Inc.  \n \n) \nAEP West Virginia Transmission Company, Inc.  \n) \nAppalachian Power Company \n \n \n) \nIndiana Michigan Power Company  \n \n) \nKentucky Power Company \n \n \n \n) \nKingsport Power Company \n \n \n \n) \nOhio Power Company \n \n \n \n) \nWheeling Power Company \n \n \n \n) \nDuquesne Light Company \n \n \n \n) \nVirginia Electric and Power Company \n \n) \nLinden VFT, LLC \n \n \n \n \n)"},{"page":2,"startToken":187,"endToken":407,"text":"City of Cleveland, Department of Public \n \n) \nUtilities, Division of Cleveland Public Power \n) \nCity of Hamilton, OH  \n \n \n \n) \nSouthern Maryland Electric Cooperative, Inc.  \n) \nOhio Valley Electric Corporation \n \n \n) \nAMP Transmission, LLC \n \n \n \n) \nSilver Run Electric, LLC \n \n \n \n) \nNextEra Energy Transmission MidAtlantic  \n) \nIndiana, Inc.  \n \n \n \n \n) \nWabash Valley Power Association, Inc.  \n \n) \nKeystone Appalachian Transmission Company \n) \n \n \n \n \n \n \n \n) \nLarge Loads Co-Located at Generating Facilities   ) \nAD24-11-000  \n \n \n \n \n \n \n \n) \n \n \n \n \n \n \n \n) \nConstellation Energy Generation, LLC   \n \n) \nEL25-20-000 \n \n \n \n \n \n \n \n) \n(Consolidated) \n          v.  \n \n \n \n \n \n) \n \n \n \n \n \n \n \n) \nPJM Interconnection, L.L.C.  \n \n \n) \n \nCOMMENTS AND INTERVENTION OF THE  \nDELAWARE PUBLIC SERVICE COMMISSION \n \nThe Delaware Public Service Commission (“DEPSC”) expresses its appreciation to the \nFederal Energy Regulatory Commission (“Commission” or “FERC”) for instituting this show \ncause proceeding pursuant to Section 206 of the Federal Power Act (“FPA”). Many of the questions \nasked by the Commission are of particular interest to Delaware including, in particular, issues \naround maintenance of adequate transmission and generation necessary to ensure local and \nregional resource adequacy in light of the unprecedented increase in load forecasts related to \nmostly data centers and some other large load additions. The issue of co-located loads is front and \ncenter to the DEPSC’s interests in ensuring that the energy needs of Delaware are met. \nI. \nBACKGROUND AND CONTEXT \nMore recent events in the PJM Interconnection, L.L.C. (“PJM”) region give the DEPSC \ngreat concern, and the DEPSC agrees with the Commission that the status quo tariff provisions in"},{"page":3,"startToken":407,"endToken":747,"text":"PJM will likely not maintain resource adequacy and reliability despite the best efforts of PJM.  \nPJM is to be commended for seeking to accelerate its interconnection queue process for new \ngeneration, reforming its Surplus Interconnection Service (“SIS”) provisions, and implementing a \nReliability Resource Initiative (“RRI”) to advance certain generation projects to enhance resource \nadequacy.  While all of these initiatives are likely to improve the ability of resources to connect to \nPJM’s system over the status quo, it is far from certain that resource adequacy will be maintained \nunder current and future Base Residual Auction (“BRA”) timelines, given the unprecedented \nincreases in demand related to co-located and non-co-located large loads, mainly new data centers. \nMore specifically, PJM’s most recent 2025 forecast is projecting load increases averaging \n6 GW per year in the summer peaks from 2024 through 2032, and 6.5 GW per year in the winter \npeaks over the same forecast period.  This forecast growth is almost entirely related to the addition \nof data centers to the grid, with some other minor industrial and manufacturing load adjustments.  \nIn short, predominantly very large data center load forecast adjustments are driving unprecedented \nincreases in PJM load growth forecasts. These are the types of facilities that are co-locating behind \ngeneration and are the focus of this proceeding. At the same time, PJM is projecting significant \nretirements of generation during this same forecast period. Between the period 2022 and 2030, \nPJM projected an average of approximately 4.4 GW per year of generation retirements. In order \nto maintain resource adequacy, PJM would then need to interconnect roughly 10.4 GWs of \nunforced capacity (“UCAP”) of new generation every year.  \nAs a reference point, in PJM’s last 2025/2026 BRA, PJM procured only 0.1103 GW of \ncapacity from new generation and 0.7538 GW from uprates to existing or planned generation. The \nquantity of new generation is down from the previous BRA, in which only 0.3285 GW of new \ngeneration was procured.  The 2025/2026 BRA procurement results were low despite an increase"},{"page":4,"startToken":747,"endToken":1089,"text":"in the Rest-of-RTO capacity clearing price from $28.92/MW UCAP to $269.92/MW UCAP.  Most \nconcerning, however, was that only 1.022 GW of Effective Load Carrying Capability (“ELCC”) \nadjusted MWs did not clear in the 2025/2026 BRA. Thus, there is almost no buffer to accommodate \nfuture load additions and generation retirements. New demand must be met from new generation \nand additional Demand Response (“DR”).  It should be noted that some recent PJM market reforms \nwill provide some very temporary boosts to supply, because Reliability Must-Run (“RMR”) units1 \nthat meet certain criteria, and all units (including intermittent and battery units) with Capacity \nInterconnection Rights (“CIRs”), will now be required to offer their generation into the BRA. \nAs PJM procures resources two or more BRAs out (Delivery Years 2027/2028 and later), \nPJM will need to rely on new generation resources, much of which will need to be in the current \ninterconnection queue.  Based on PJM’s queue of “active projects” as of December 31, 2024, even \nif every “active project” comes online, new generation would still be insufficient to meet PJM’s \nforecasted increase in large load additions, even at today’s ELCC ratings.2  There is almost zero \nchance that all “active projects” will come on-line, as only a relatively small number of projects \nactually makes it to the post-construction, in-service phase.   \nAt recent OPSI meetings, many stakeholders identified barriers such as siting, permitting, \nand continuing supply chain constraints, particularly for large equipment like transformers and \nturbines, as key drivers in the delays and outright termination of interconnection queue positions.  \nFurther, it is unlikely that DR would fully meet any remaining resource adequacy gap, as the day-\nto-day operational activation of DR would significantly increase, likely causing DR capacity \nmarket participation to decline. Further, this analysis assumes a fixed ELCC value for wind, solar, \n \n1 The must-offer requirements for certain RMR units are only applicable for the next two BRAs. \n2 Based on the Testimony of Manu Asthana referenced in spreadsheets and current ELCC ratings projected for the \n2026/2027 BRA."},{"page":5,"startToken":1089,"endToken":1383,"text":"and battery resources.  As a whole, PJM has been projecting significant decreases in battery and \nsolar resource ELCCs as the amount of these resources scales up.  Lastly, any future deactivations \nwould only add to this resource adequacy deficit.  In short, it will be increasingly difficult, if not \noutright unlikely, for the existing PJM queue, comprised mostly of new intermittent, limited \nduration resources, combined with future DR resources, to meet the growing demand associated \nwith large load additions.  \nII. \nCOMMENTS \nIn response to the Commission’s inquiry, the DEPSC expresses support for the Comments \nof OPSI in this proceeding as it relates to resource adequacy, transparency, consumer protection, \ncost allocation, and jurisdiction.  In addition, the DEPSC draws particular attention to the concerns \naround resource adequacy, underscored by the well-documented tightening of supply and future \nsupply shortage conditions that are rapidly approaching. These tightening conditions should be \naddressed immediately, as the status quo tariff provisions fail to address the cumulative impacts of \nlarge load additions via co-located and non-collocated configurations. More to the point, as \ndisruptive as it seems to subject new large load additions to further reliability analysis under \nconditions of resource adequacy shortages, the failure to adequately plan for and address these \nresource adequacy shortages will most certainly result in system load curtailments and extreme \nshortage prices, the impacts of which will be devasting to low and middle income customers, small \nbusinesses, and electricity price-sensitive industrial customers. To avoid these highly disruptive \nimpacts, the DEPSC supports solutions that can effectively mitigate future resource adequacy \nshortages and operational challenges related to the real-time adequacy of energy and reserves.   \nIn its response to the Commission’s show cause Order of February 20, 2025, PJM outlined \nthree potential options that focused acutely on additional supply and operational flexibility:  Option"},{"page":6,"startToken":1383,"endToken":1693,"text":"6 (co-located load that elects to be Network Load and leverages provisional interconnection service \nor a State Agreement Approach), Option 7 (co-located load that takes a new non-capacity backed \nservice that could be curtailed in advance of emergency procedures), and Option 8 (co-located \nparticipates as Demand Response).   The DEPSC is inclined to support these types of frameworks, \nprovided that they can effectively mitigate the risk of resource adequacy shortages and sustained \nshortage pricing events.   \nHowever, none of these solutions, on its own, may be adequate to address the fundamental \nproblem of PJM and others reacting to large load additions rather than addressing large load \nadditions proactively.  To date, many Electric Distribution Companies (“EDCs”) have enabled \nlarge load additions without ensuring that adequate on-site supply or adequate deliverable supply \nwas available to meet the energy needs of the large load additions. Rather, the large load is being \ninterconnected and permitted to go into service, forcing PJM, PJM stakeholders, this Commission, \nand others into a reactive mode, hurriedly scrambling to identify and implement solutions.  The \nproverbial cart appears to be dragging the proverbial horse.  Consequently, in addition to the PJM \noptions that appear feasible, as identified above, the DEPSC would recommend that this \nCommission direct the North American Electric Reliability Corporation (“NERC”) to undertake \nan accelerated process to establish reliability and resource adequacy standards for new large load \nadditions that would apply to Electric Distribution Companies (“EDCs”), to generators involved \nwith co-located large load configurations, and other entities subject to NERC standards, to ensure \nthat regional and local operational reliability and resource adequacy will be maintained as large \nload additions interconnect to the grid or interconnect in a co-located configuration. As it stands \ntoday, reliability and resource adequacy gaps exist in the current regulatory construct. To help fill \nthis gap, the combination of this Commission and NERC could effectively empower and obligate"},{"page":7,"startToken":1693,"endToken":1842,"text":"all relevant entities involved with large load interconnections to ensure either that large load \nadditions are accompanied with their own adequate supply arrangements or that large load \nadditions can be met with deliverable supply before the large load additions are placed into service.  \nThis Commission can and should put the horse back in front of the cart.  \nIII. \nNOTICE OF INTERVENTION \n \nThe DEPSC hereby notifies the Commission of its intervention pursuant to 18 C.F.R. \n§385.214. The DEPSC is a State Commission as defined in the Commission’s Rules of General \nApplicability, 18 C.F.R. §1.101(k). The DEPSC's principal place of business is 861 Silver Lake \nBlvd., Suite 100, Dover, DE 19904. As the state regulator of investor-owned utilities in Delaware, \nthe DEPSC has an interest that may be directly affected by the outcome of the proceeding and its \nparticipation is in the public interest."},{"page":8,"startToken":1842,"endToken":2002,"text":"IV. \nCONCLUSION \nThe DEPSC is very concerned about the tightening supply/demand balance and urges this \nCommission to require PJM to file provisions to ensure that resource adequacy and operational \nreliability are maintained in light of unprecedented large load additions, anticipated large \ngeneration retirements, and current new generation development barriers. These large load \nprovisions should apply to both co-located and other large load additions. In addition, the \nCommission should direct NERC to establish standards to ensure that large load additions have \naccess to their own supply or to deliverable supply as a condition to grid interconnection. A sense \nof urgency is necessary given the alignment of all these factors, and the DEPSC commends this \nCommission for proactively identifying these issues and seeking solutions to address them. \nRespectfully submitted,  \nBy:  / s / Matthew Hartigan \nMatthew Hartigan, Executive Director \nDelaware Public Service Commission \n861 Silver Lake Blvd, Suite 100 \nDover, DE 19904 \nPhone:  302-736-7532 \nEmail: Matthew.Hartigan@delaware.gov \n \n \nDated:  April 23, 2025"},{"page":9,"startToken":2002,"endToken":2077,"text":"CERTIFICATE OF SERVICE \n \n \nI hereby certify that I have this day served, via first-class mail, electronic transmission, or \nhand-delivery, the foregoing Comments upon each person designated on the official service list \ncompiled by the Secretary in this proceeding. \nDated at Dover, DE this 23d day of April, 2025. \n \n/ s / Matthew Hartigan  \n \n \nMatthew Hartigan, Executive Director \nDelaware Public Service Commission \n861 Silver Lake Blvd, Suite 100 \nDover, DE 19904 \nPhone:  302-736-7532 \nEmail: Matthew.Hartigan@delaware.gov"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":1558,"startToken":0,"endToken":372},{"p":2,"at":1558,"title":"I. BACKGROUND AND CONTEXT","method":"printed heading","endPage":5,"endAt":519,"startToken":372,"endToken":1166},{"p":5,"at":519,"title":"II. COMMENTS","method":"printed heading","endPage":7,"endAt":366,"startToken":1166,"endToken":1750},{"p":7,"at":366,"title":"III. NOTICE OF INTERVENTION","method":"printed heading","endPage":8,"endAt":0,"startToken":1750,"endToken":1842},{"p":8,"at":0,"title":"IV. CONCLUSION","method":"printed heading","endPage":9,"endAt":0,"startToken":1842,"endToken":2002},{"p":9,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":9,"endAt":530,"startToken":2002,"endToken":2077}]}