{"document":{"slug":"rec-20250423-5148","title":"Reply Comments of Southern California Edison Company and Pacific Gas and Electric Company in response to PJM Interconnection, L.L.C.'s Answer filed on…","issued":"2025-04-23","accession":"20250423-5148","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Southern California Edison Company and Pacific Gas and Elect","kind":"answer","file":"sources/filings/text/20250423-5148_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250423-5148","tier":"record","sha256":"33e130cebe41877423d8c26b628535bbead04fd92386e62df3a6052ec5f1145a","pages":11,"tokens":2992,"emptyPages":[],"textThemes":["colo","retail","adequacy","cost"]},"pages":[{"page":1,"startToken":0,"endToken":159,"text":"1 \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nTechnical Conference on Large Loads  \nCo-Located at Generating Facilities  \n(AD24-11-000); Constellation Energy \nGeneration, LLC v. PJM Interconnection, \nL.L.C. (EL25-20-000) (Consolidated) \n) \n) \n) \n) \n) \nDocket No. EL25-49-000 \nREPLY COMMENTS  \nOF SOUTHERN CALIFORNIA EDISON COMPANY AND PACIFIC GAS AND \nELECTRIC COMPANY \nI. \nINTRODUCTION \nPursuant to Rule 213 of the Federal Energy Regulatory Commission’s (FERC or \nCommission) Rules of Practice and Procedure,1 Southern California Edison Company \n(SCE) and Pacific Gas and Electric Company (PG&E) (jointly California Utilities) \nrespectfully submit these Reply Comments to the Answer filed on March 24, 2025 by \nPJM Interconnection, L.L.C. (PJM Answer) in response to the Commission’s February \n20, 2025 Order Instituting Proceeding Under Section 206 of the Federal Power Act \n(Order to Show Cause).  The California Utilities seek to provide additional information \nthat the California Utilities believe will assist the Commission in its decision-making \nprocess. \n \n1 \n18 C.F.R. § 385.213 (2025)."},{"page":2,"startToken":159,"endToken":418,"text":"2 \nII. \nREPLY COMMENTS \nThe California Utilities fully support the development of co-located load \narrangements, which have the potential to create a number of benefits to ratepayers.2  For \ninstance, co-located data centers may provide savings to ratepayers by reducing \ncongestion charges, as these facilities are often drawn to locations with low-cost power, \nwhich could include areas with heavily curtailed renewables.  Co-located load \nconfigurations can reduce line losses, result in more efficient utilization of existing \ninfrastructure, and free up delivery capacity on the grid.  Co-location arrangements may \nalso provide a cheaper alternative to network upgrades.  However, without proper cost \nallocation of transmission costs, reliability services, and Resource Adequacy, traditional \ncustomers could be forced to subsidize co-located load, or suffer impaired reliability.  \nNeither outcome is acceptable.   \nIn addressing issues related to co-located load, the Commission must ensure that:  \n• States retain their exclusive authority to determine who may serve co-\nlocated load and the rates and regulations for co-located load; \n• Co-located loads are adequately studied for Resource Adequacy and \nreliability impacts, including impacts relating to the co-located generation \nbeing off-line (momentarily, temporarily, or permanently); and  \n• Co-located load connected to the transmission network pays a fair share of \nFERC-jurisdictional transmission costs, as determined by its state or local \nregulator. \n \n2  As used herein, co-located loads do not include retail load served behind the meter of Qualifying \nFacilities (QF) or by behind the retail meter generation (i.e., net metered load).  Rather, co-located \nload refers to a load connected to a non-QF, non-customer owned/leased generator that is \nsynchronized to the electric system."},{"page":3,"startToken":418,"endToken":720,"text":"3 \nA. \nJurisdictional Issues \nIn its Order to Show Cause, the Commission invited PJM and the parties to opine \non the jurisdictional principles outlined in section VI.A.3 \nThe California Utilities appreciate the Commission’s clarification in the Order to \nShow Cause that “under the FPA, the states get to determine which entities are legally \npermitted to provide electricity to retail customers in co-location \narrangements…irrespective of where the load interconnects (i.e., to the distribution \nsystem, the transmission system, or the generator itself).”4  The Commission also noted \nthat although it “has not historically exercised jurisdiction over any and all transmission-\nlevel interconnections of retail load,” the Commission “encourage[d] parties to address \nwhen and under what circumstances a co-located load is interconnected to the \ntransmission system in interstate commerce”5 and “whether the Commission must, \nshould, or can exercise jurisdiction over the interconnection of co-location arrangements \nto the transmission system in interstate commerce as an element of transmission service, \nincluding where the purpose is to facilitate a retail sale.”6 \nThough PJM acknowledges that the various options it presents for co-location \narrangements in Exhibit A “are subject to different state law requirements that could \ndisqualify certain options,”7 PJM contends that the Commission has jurisdiction over \nPJM’s co-located arrangements “due to PJM’s provision of ancillary services and in light \nof the wholesale sales taking place over certain facilities. . . .Therefore, at a minimum, \nthe Commission has jurisdiction regarding the transmission service associated with the \nancillary services utilized in co-location arrangements.”8  The California Utilities agree \nwith PJM that FERC has jurisdiction over the allocation of transmission, ancillary \n \n3  Order to Show Cause at P 88. \n4  Order to Show Cause at P 69. \n5  Id. at P 73. \n6  Id.  \n7  PJM Answer at p. 29. \n8  Id. at p. 30."},{"page":4,"startToken":720,"endToken":1055,"text":"4 \nservices, and other related costs between customers (such as investor-owned utilities \n(IOUs) or other load-serving entities) using or benefitting from the transmission system.  \nHowever, this does not mean that a state or local regulator cannot reallocate transmission \ncosts in another manner in setting retail rates.9  The Commission indicates that it concurs: \n[W]hile “a State may not conclude in setting retail rates that \nthe FERC-approved wholesale rates are unreasonable,” it is \nwithin a state’s exclusive jurisdiction to determine how those \nFERC-approved rates are collected among the relevant retail \nconsumers along with the rates for state-jurisdictional \nmatters.10   \nPJM contends that “the Commission’s jurisdiction over transmission service in \ninterstate commerce is also necessarily implicated in matters relating to co-located load \narrangements where generator interconnections are being modified.”11  This statement is \nvague.  It is well established that “unless a transaction falls within FERC’s wholesale or \ntransmission authority, it doesn’t matter how FERC characterizes it,”12 and that retail \nrates and service are governed by the states.  Though the Commission rightfully dictates \nthe terms and conditions of a wholesale generator interconnection, that does not mean it \ncan bootstrap such jurisdiction to dictate the terms and conditions of service to retail load.  \nMatters related to retail service to a co-located load do not belong in a FERC-\n \n9  State regulators routinely perform such reallocation with regard to load located behind generators.  \nFor example, the California Independent System Operator (CAISO) charges for transmission service \non a kWh basis.  Grandfathered net metering customers, however, are charged for transmission only \nif their net output is less than their net consumption over a monthly billing period.  Thus, the CAISO \nmay count load of grandfathered net metered customers in allocating transmission charges to SCE, \nbut SCE reallocates those transmission charges to its other retail customers, as do the other California \nutilities. \n10  Order to Show Cause at P 68. \n11  PJM Answer at p. 31. \n12  S. Cal. Edison Co. v. FERC, 603 F.3d 996, 1001 (D.C. Cir. 2010)."},{"page":5,"startToken":1055,"endToken":1490,"text":"5 \njurisdictional generator interconnection agreement at all, even where the state has not \ndecided to regulate that retail service.13 \nThe Commission does not obtain authority over what are, in essence, retail sales of \nelectricity to end-use, co-located load solely because the sales may impact a FERC-\njurisdictional generator interconnection.  As previously noted in SCE’s Comments in \nEL25-20-000, jurisdiction over retail load interconnections generally rests with state or \nlocal regulators regardless of where the load connects.14  At least in California, regardless \nof size or service voltage connection to the grid, business or commercial end-use load has \nalways been considered retail load.  The California Utilities do not believe that the \nCommission is permitted to exercise jurisdiction over the interconnection of a co-located \nload to the transmission system as an element of transmission service in interstate \ncommerce where the purpose of the arrangement is to facilitate a retail sale.15   \nIn many states, including California, state regulators generally do not permit \ngenerators who are not public utilities to make retail sales directly.16  Except under \nlimited circumstances, California end-use load (including data centers) must purchase \nretail service from a utility whose retail rates are set by the state or from a community \nchoice aggregator (who can only supply a limited set of services, while the regulated \n \n13  See, e.g., Consol. Edison Co. of New York, Inc., 101 FERC ¶ 61,185 at P 43 (2002) (“Therefore, we \nwill require ConEd to remove all language with respect to the sale of station power by ConEd to \nPSEG because it is beyond our jurisdiction. We suggest that the parties raise the issue of the sale of \nstation power by ConEd to PSEG in a forum that has jurisdiction.”). \n14  EL25-20-000, Comments of Southern California Edison Company, at p. 2. \n15  See S. Cal. Edison Co. v. FERC, 603 F.3d 996 at 999 (holding that the Commission had no \njurisdiction to regulate sales of station power under the Commission’s “jurisdiction over \ntransmission,” as those were retail sales regulated by the states).  \n16  One exception is limited retail sales by QFs under the Public Utility Regulatory Policies Act of 1978 \n(PURPA).  In California, QFs may make sales to up to two physically adjacent customers.  See Pub. \nUtils. Code § 218(b)(2) (“‘Electrical corporation’ does not include a corporation…producing power \nfrom other than a conventional power source for the generation of electricity solely for... [t]he use of \nor sale to not more than two other corporations or persons solely for use on the real property on which \nthe electricity is generated or on real property immediately adjacent thereto...”)."},{"page":6,"startToken":1490,"endToken":1779,"text":"6 \nutility provides delivery and other services).17  Any consideration of jurisdictional issues \nshould recognize that states retain the exclusive authority to set rates for sales to end-use \ncustomers, including co-located data centers.  States must retain their authority to assess \nappropriate public policy charges, such as charges for wildfire mitigation, wildfire \nrecovery, and state-sponsored equity programs, and to regulate the types of generation \nused in serving retail load.  Moreover, states must retain the ability to regulate the \ninterconnection of retail loads. \nFinally, the California Utilities agree with PJM that “many co-located load \nconfigurations utilize grid support and consume ancillary services (including, for \nexample, frequency regulation, black start service, and reactive service).”18  The \nCommission has jurisdiction to determine the cost for services deemed to be used by \nvarious wholesale loads, which in turn requires tariffs such as the PJM Tariff to dictate \nhow the retail load, including co-located load, of its wholesale customers will be \nmeasured.  Based on well-established cost causation principles, as discussed below at \nSection II.C, the Commission should ensure that FERC-jurisdictional tariffs measure the \namount of end-use load allocated to wholesale customers in a manner that is just and \nreasonable.  That said, as already noted, state and local regulators retain authority to \nreallocate wholesale costs among retail customers as long as they permit full cost \nrecovery.  \nB. \nAny Tariff Revisions Should Adequately Address Resource Adequacy \nand Other Reliability Concerns \nThe California Utilities appreciate the Commission’s recognition that large co-\nlocated loads have the potential to negatively impact Resource Adequacy (i.e., capacity \nrequirements) for existing customers.  Though FERC generally lacks authority to prevent \n \n17  Retail choice was suspended decades ago in California, with a few grandfathered retail customers \nremaining. \n18  PJM Answer at p. 68."},{"page":7,"startToken":1779,"endToken":2094,"text":"7 \na generator from ultimately making direct or indirect sales to retail co-located load (even \nthose that erode reliability), it is important for the Commission to recognize, when setting \npolicy, that allowing co-located loads may reduce available capacity and accordingly, \nincrease consumer electricity prices.  \nThe Commission does have authority, however, to require wholesale customers to \nprocure adequate capacity.  If an ISO/RTO Tariff sets rules dictating which types of retail \nload that load-serving entities must purchase capacity for, at a minimum, the Tariff must \nbe clear as to how co-located load will be treated and who will be responsible for \nprocuring capacity for the load.  Cost allocation principles dictate that the entity directly \nselling at retail to the co-located load should pay capacity costs because of the grid \nreliability impact the load creates; how these costs are passed on to the co-located load is \na matter between the load serving entity and its retail customer. \n \nAdditionally, if existing generator capacity is diverted to co-located load rather \nthan selling its energy into the market, this choice may cause power flow changes in a \nlocal area that need to be studied.  Thus, it is important for planners to know sufficiently \nfar in advance if an existing generator is going to connect co-located load.  For generators \nin the queue, knowledge of intent to connect co-located load is similarly important for \nplanning and reliability purposes. \nC. \nCo-Located Loads Must Pay Their Fair Share of Costs \nThe Commission expressed concern that the absence of PJM Tariff provisions \nregarding co-located facilities “creates the potential that participants in a co-location \narrangement may not be required to pay for wholesale services that they receive, as \nrequired by the cost causation principle.”19  Further, the Commission has reiterated that \nin designing its rates, PJM must ensure that costs are “allocated in a manner that is at \n \n19  Order to Show Cause at P 74."},{"page":8,"startToken":2094,"endToken":2444,"text":"8 \nleast roughly commensurate with the benefits that entity receives.”20  The Commission \nnoted that “different co-location arrangements are likely to use or benefit from the \ntransmission system in different ways depending on how they are configured and, \nmoreover, that those different configurations will themselves likely have different \nimpacts on the transmission system.”21   \nAs an initial matter, there is no such thing as fully isolated co-located load unless \nneither the source generator nor the co-located load is electrically connected to the \nelectric transmission system.22  Thus, this configuration does not need to be addressed by \nthe PJM Tariff. \nAssuming a state or local regulator allows a generator, whether directly or through \na sleeving entity, to serve co-located load and the generator is synchronized to the electric \ngrid, and the regulator does not require the co-located load to pay for retail transmission \nservice in the same manner as retail loads served by front of the meter generators, there \nare a variety of cost allocation options that can be explored.  The Commission should \nrecognize that there will be no uniformity in the PJM region, as states and local regulators \nmay make very different decisions on retail transmission service.  The California \nUtilities’ thoughts on situations where the state/local regulator does not require that co-\nlocated load be treated the same as front of the meter retail load are discussed below.   \nFirst, the California Utilities do not support generators synchronized to the grid \nserving co-located load paying no ancillary services costs, as they do not agree that either \nthe generator or the co-located load are fully isolated.  For example, synchronized \ngenerators utilize ancillary services (such as Regulation) and benefit from reliability and \nrecovery services such as Spinning Reserve and Black Start.  In such cases, it is up to the \n \n20  Id. \n21  Id. at P 76. \n22  In this limiting case, it is not obvious that the Commission has any jurisdiction over such a \nconfiguration.  The Commission would, however, have jurisdiction over transmission charges \nassessed to co-located load where either the co-located load or the generator is connected to the \ntransmission system."},{"page":9,"startToken":2444,"endToken":2810,"text":"9 \ngenerator how or whether such cost is passed onto the co-located load.  If the generator is \nusing a middleman to sleeve power to the co-located load, the PJM Tariff would need to \ndetermine if the generator or load-serving middleman should be allocated such charges.  \nAs to transmission service, if PJM is going to permit netting of load for \ntransmission purposes, one option to ensure fair cost allocation is to require the co-\nlocated load to pay for retail stand-by transmission services.23  But, even if a state or local \nregulator permits co-located load to be on a standby tariff, the regulator may still impose \nstate public policy charges on the gross load of the co-located load.  The PJM Tariff \nshould state affirmatively that regulators retain such authority, in order to avoid future \ndisputes. \nD. \nRegional Differences May Require Different Approaches \nThe California Utilities submit these Reply Comments relating to the PJM Tariff \nrecognizing that the Commission’s decision here may impact the conversation in future \nproceedings regarding other RTO tariffs.  Nevertheless, it is important to recognize that \napproaches to co-located facilities will need to be tailored to account for different state \nregulators, self-regulated non-jurisdictional utilities, and regions.  For instance, as \nrelevant to the California Utilities, any future CAISO Tariff provisions relating to co-\nlocated facilities must necessarily function within California’s unique regulatory \nenvironment.  The California Utilities respectfully request that the Commission’s Order \non PJM’s Tariff acknowledge state/local regulatory rights to prevent confusion and \ndisputes.  Moreover, even without the state and local jurisdictional differences, there is no \n“one size fits all” just and reasonable approach to this complex issue.   \n \n23  In the past, the Commission was able to ensure that certain generators with behind the meter load \nwere permitted to net their load for CAISO Tariff purposes by allowing such netting only if the \ngenerator purchased retail standby service.  See Cal. Indep. Sys. Operator Corp., 104 FERC ¶ 61,196 \n(2003).  There, however, the behind the meter load was not a retail customer of the utility; the \ngenerator was a retail customer.  The situation being addressed here, in contrast, assumes that the co-\nlocated load must have its own retail account because separate legal entities are involved."},{"page":10,"startToken":2810,"endToken":2914,"text":"10 \nIII. \nCONCLUSION \nThe California Utilities appreciate the opportunity to provide these Reply \nComments to the Commission and respectfully request that the Commission consider the \nforegoing comments in its Order addressing PJM’s Tariff.   \nRespectfully submitted, \nELLEN C. KENNEY \n/s/ Ellen C. Kenney \nBy: \nEllen C. Kenney \nAttorneys for \nSOUTHERN CALIFORNIA EDISON COMPANY \n2244 Walnut Grove Avenue \nPost Office Box 800 \nRosemead, California 91770 \nTelephone: (626) 302-9519 \nE-mail: \nEllen.Kenney@sce.com \n \n \nCHARLES MIDDLEKAUFF \n/s/ Charles Middlekauff \nBy: \nCharles Middlekauff \nAttorneys for \nPACIFIC GAS AND ELECTRIC COMPANY \n300 Lakeside Drive \nOakland, California  94612 \nTelephone: (650) 766-9147 \nEmail:  \nCharles.Middlekauff@pge.com \nDated:  April 23, 2025"},{"page":11,"startToken":2914,"endToken":2992,"text":"11 \nCERTIFICATE OF SERVICE \nI hereby certify that I have this day served the foregoing REPLY COMMENTS \nOF SOUTHERN CALIFORNIA EDISON COMPANY AND PACIFIC GAS AND \nELECTRIC COMPANY upon each person designated on the official service list \ncompiled by the Secretary in this proceeding. \nDated at Rosemead, California, this 23rd day of April 2025. \n \n \n/s/ Leslie Trujillo \n \n \n \nLeslie Trujillo \nSenior Legal Administrative Assistant \nSOUTHERN CALIFORNIA EDISON COMPANY \n2244 Walnut Grove Avenue \nPost Office Box 800 \nRosemead, California 91770"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":403,"startToken":0,"endToken":49},{"p":1,"at":403,"title":"I. INTRODUCTION","method":"printed heading","endPage":2,"endAt":3,"startToken":49,"endToken":160},{"p":2,"at":3,"title":"II. REPLY COMMENTS","method":"printed heading","endPage":3,"endAt":3,"startToken":160,"endToken":419},{"p":3,"at":3,"title":"A. Jurisdictional Issues","method":"printed heading","endPage":6,"endAt":1534,"startToken":419,"endToken":1710},{"p":6,"at":1534,"title":"B. Any Tariff Revisions Should Adequately Address Resource Adequacy","method":"printed heading","endPage":7,"endAt":1496,"startToken":1710,"endToken":2010},{"p":7,"at":1496,"title":"C. Co-Located Loads Must Pay Their Fair Share of Costs","method":"printed heading","endPage":9,"endAt":815,"startToken":2010,"endToken":2578},{"p":9,"at":815,"title":"D. Regional Differences May Require Different Approaches","method":"printed heading","endPage":10,"endAt":4,"startToken":2578,"endToken":2811},{"p":10,"at":4,"title":"III. CONCLUSION","method":"printed heading","endPage":11,"endAt":4,"startToken":2811,"endToken":2915},{"p":11,"at":4,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":11,"endAt":541,"startToken":2915,"endToken":2992}]}