{"document":{"slug":"rec-20250423-5154","title":"Comments of Buckeye Power, Inc. in support of PJM Interconnection, L.L.C.’s 03/24/2025 response to the show cause order","issued":"2025-04-23","accession":"20250423-5154","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Buckeye Power, Inc.","kind":"comments","file":"sources/filings/text/20250423-5154_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250423-5154","tier":"record","sha256":"c25e51f357af07b6a464251de7fab7f974ff232a3a26288f1e7dc48add8654f0","pages":15,"tokens":4041,"emptyPages":[],"textThemes":["colo","cost","adequacy","flex"]},"pages":[{"page":1,"startToken":0,"endToken":172,"text":"UNITED STATES OF AMERICA\nBEFORE THE\nFEDERAL ENERGY REGULATORY COMMISSION\n      \nPJM Interconnection, L.L.C. \nAllegheny Electric Cooperative, Inc. \nAmerican Transmission Systems, Incorporated \nAtlantic City Electric Company \nBaltimore Gas and Electric Company \nDelmarva Power & Light Company \nDuke Energy Ohio, Inc. \nDuke Energy Kentucky, Inc. \nEast Kentucky Power Cooperative, Inc. \nEssential Power Rock Springs, LLC \nHudson Transmission Partners, LLC \nJersey Central Power & Light Company \nMid-Atlantic Interstate Transmission, LLC \nNeptune Regional Transmission System, LLC \nOld Dominion Electric Cooperative \nPECO Energy Company \nPPL Electric Utilities Corporation \nPotomac Electric Power Company \nPublic Service Electric and Gas Company \nRockland Electric Company \nTrans-Allegheny Interstate Line Company \nTransource West Virginia, LLC \nUGI Utilities, Inc. \nMonongahela Power Company \nThe Potomac Edison Company \nCommonwealth Edison Company \nCommonwealth Edison Company of Indiana, \nInc. \nThe Dayton Power and Light Company \nAEP Appalachian Transmission Company, Inc. \nAEP Indiana Michigan Transmission Company, \nInc. \nAEP Kentucky Transmission Company, Inc\nAEP Ohio Transmission Company, Inc.\nAEP West Virginia Transmission Company, \nInc. \nAppalachian Power Company \nIndiana Michigan Power Company \nKentucky Power Company\nKingsport Power Company \n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\nDocket Nos. EL25-49-000"},{"page":2,"startToken":172,"endToken":382,"text":"- 2 -\nOhio Power Company \nWheeling Power Company \nDuquesne Light Company \nVirginia Electric and Power Company \nLinden VFT, LLC \nCity of Cleveland, Department of Public \nUtilities, Division of Cleveland Public Power \nCity of Hamilton, OH \nSouthern Maryland Electric Cooperative, Inc. \nOhio Valley Electric Corporation \nAMP Transmission, LLC \nSilver Run Electric, LLC \nNextEra Energy Transmission\nMidAtlantic Indiana, Inc. \nWabash Valley Power Association, Inc. \nKeystone Appalachian Transmission Company\nLarge Loads Co-Located at Generating\nFacilities\nConstellation Energy Generation, LLC\nv.\nPJM Interconnection, L.L.C.\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\nAD24-11-000\nEL25-20-000 (Consolidated)\nCOMMENTS OF BUCKEYE POWER, INC.\nPursuant to the Federal Energy Regulatory Commission’s (“FERC” or “Commission”) \nFebruary 20, 2025 Order establishing this show cause proceeding under section 206 of the Federal \nPower Act,1 Buckeye Power, Inc. (“Buckeye”) respectfully files these comments in support of \nPJM Interconnection, L.L.C.’s (“PJM”) response to the show cause order.2   \nI.\nBACKGROUND\nNew large loads, primarily comprised of data centers, are creating a strain on the electric \ngrid nationwide, and particularly in the PJM region, putting front and center issues of reliability, \n1 Order Instituting Proceeding Under Section 206 of the Federal Power Act and Consolidating with Other \nProceedings, 190 FERC ¶ 61,115 (the “Order”).\n2 See PJM Response filed March 24, 2025 in this docket (“PJM Answer”)."},{"page":3,"startToken":382,"endToken":667,"text":"- 3 -\nresource adequacy, and just and reasonable rates.  Buckeye supports co-location of large loads that \nare visible to the network.  This includes generation arrangements where the co-located load pays \nfor its share of transmission costs and ensures the grid can continue to rely on existing generation \nresources.  Buckeye supports PJM’s position that the existing Open Access Transmission Tariff, \nthe Amended and Restated Operating Agreement of PJM, and the Reliability Assurance \nAgreement Among Load Serving Entities in the PJM Region (collectively, the “Tariff”) remains \njust and reasonable.  Buckeye also supports the additional options PJM has proposed to facilitate \nfront-of-the-meter co-location arrangements where the co-located load is Network Load and \nresource adequacy is maintained.  \nWhile front-of-the-meter, Network Load co-location arrangements are a better alternative \nfor reliability and resource adequacy than non-Network Load behind-the-generator arrangements, \neven these front-of-the-meter, Network Load arrangements do not resolve all of the significant \nconcerns with the influx of large loads in the PJM footprint.  The risk of significant stranded \ntransmission investment is another critical issue that must be considered, regardless of whether the \ngeneration is co-located with load or not.  If the demand of large loads is as expected, that could \nbenefit existing customers by lowering transmission rates.  But there is serious concern that these \nlarge loads could drive significant transmission investment and then not show up to pay for it on a \nsustained basis, shifting costs to everyone else that relies on the expanded grid.  Buckeye supports \npolicies that ensure large loads pay for the costs and impact to the grid they cause.    \nII.\nINTEREST OF BUCKEYE\nBuckeye Power, Inc. is an Ohio non-profit generation and transmission cooperative that \nproduces, procures, and provides at wholesale all the electric capacity, energy, and transmission"},{"page":4,"startToken":667,"endToken":1016,"text":"- 4 -\nrequired by its member electric distribution cooperatives.3  Buckeye operates as a cooperative and \nis owned by its 25 member distribution cooperatives, which are in turn each owned by their \nmember-consumers.  Buckeye thus operates not for the benefit of shareholders, but for the benefit \nof its member-consumers.  Buckeye’s mission is to provide “to all member systems, stably and \ncompetitively priced, economical and highly reliable wholesale power, for the benefit of their \nmembers and their communities.”4\nBuckeye arranges transmission services for the delivery of generation to its member \nelectric distribution cooperatives at over 400 delivery points in the State of Ohio. Those member \ndistribution cooperatives serve over 400,000 residential, commercial, and industrial customers in \nservice territories encompassing primarily rural areas in 77 of Ohio’s 88 counties.  Buckeye is a \nTransmission Dependent Utility (“TDU”), meaning that it depends almost exclusively on PJM and \nfour transmission owners in Ohio (Duke Energy Ohio, Ohio Power Company/AEP Ohio \nTransmission Company, Inc., American Transmission Systems, Inc., and the Dayton Power & \nLight Company) for transmission of electricity to its member cooperatives.  As a TDU, Buckeye \nis subject to PJM’s Open Access Transmission Tariff, which includes cost recovery for \ntransmission upgrades and expansions made by each transmission owner in Ohio and regional \ntransmission projects assigned by PJM.  \n3 The 25 distribution cooperative members of Buckeye are: Adams Rural Electric Cooperative, Inc.; \nBuckeye Rural Electric Cooperative, Inc.; Butler Rural Electric Cooperative, Inc.; Carroll Electric Cooperative, Inc.; \nConsolidated Cooperative, Inc.; Darke Rural Electric Cooperative, Inc.; Firelands Electric Cooperative, Inc.; The \nFrontier Power Company; Guernsey-Muskingum Electric Cooperative, Inc.; Hancock-Wood Electric Cooperative, \nInc.; Holmes-Wayne Electric Cooperative, Inc.; Licking Rural Electrification, Inc.; Logan County Cooperative \nPower and Light Association, Inc.; Lorain-Medina Rural Electric Cooperative, Inc.; Mid-Ohio Energy Cooperative, \nInc.; Midwest Electric, Inc.; Midwest Energy & Communications; North Central Electric Cooperative, Inc.; North \nWestern Electric Cooperative, Inc.; Paulding-Putnam Electric Cooperative, Inc.; Pioneer Rural Electric Cooperative, \nInc.; South Central Power Company; Tricounty Rural Electric Cooperative, Inc.; Union Rural Electric Cooperative, \nInc.; and Washington Electric Cooperative, Inc.\n4 Buckeye’s mission statement can be found on its website at https://ohioec.org/buckeye-power."},{"page":5,"startToken":1016,"endToken":1266,"text":"- 5 -\nBuckeye also owns and operates generation resources to meet its members’ load \nrequirements and is a participant in the PJM capacity market as both a generation owner and a load \nserving entity (“LSE”).  In order for Buckeye to provide reliable and affordable electric supply to \nits members and their retail members, it is essential that the PJM capacity market ensures resource \nadequacy and reliability of electric service.    \nBuckeye appreciates the Commission’s issuance of the Order to address these issues. \nCommunications regarding these proceedings should be directed to:\nKurt P. Helfrich\nGeneral Counsel\nLija Kaleps-Clark\nAssociate General Counsel\nBuckeye Power, Inc.\n6677 Busch Boulevard\nColumbus, Ohio 43229\nTelephone: (614) 681-5151\nkhelfrich@ohioec.org \nlkaleps@ohioec.org \nIII.\nCOMMENTS\nA. Large Load Co-located with Generation Should be Network Load in Front of the Meter\nBuckeye supports co-location arrangements where the large loads are Network Load and \nin “front of the meter” because these arrangements will ensure visibility to the grid operator, allow \nPJM to conduct appropriate planning to ensure grid reliability, ensure the load pays for its share \nof grid costs, and ensure generation resources remain available for the entire grid.  Conversely, co-\nlocated large load arrangements where the load is located “behind the meter” of the generator, and \nis not Network Load, may create significant impacts to the grid, increase costs, and decrease \nreliability for everyone else that relies on the grid for affordable and reliable electricity.  While \ncertain parties have advocated that these so-called “fully isolated” arrangements will avoid"},{"page":6,"startToken":1266,"endToken":1596,"text":"- 6 -\ntransmission investments, those potential cost savings are outweighed by significant concerns \nabout the impacts to reliability, resource adequacy, and just and reasonable rates.5   \nFront-of-the-meter arrangements where the load is Network Load avoids many of the \nconcerns associated with “behind-the-generator” co-location arrangements that are not Network \nLoad:  \nImproved Grid Reliability.  When load is located in front of the generation meter rather \nthan behind the generation meter, the generation resource is available for full grid operation, rather \nthan having all or a portion of the generator’s output dedicated to a specific load.  This arrangement \nprovides significant reliability benefits by avoiding reliance on protective relays to operate (which \ncan fail) in the event of a generator outage, provides enhanced ability for PJM to manage which \nload to curtail and prioritize in response to emergency conditions, and enhances PJM’s visibility \nand control over the co-located load.  As a result, front-of-the-meter, Network Load arrangements \nwill improve system planning and operation and will have less negative impacts on resource \nadequacy (particularly if the arrangement is consistent with PJM Options 6, 7, and/or 8).6  \nIn contrast, so-called “fully isolated” co-location arrangements would essentially remove \nthe associated generation (assuming it is existing generation) off the grid so that it can no longer \nbe relied upon by everyone else.  This is particularly problematic because co-location \narrangements often seek to use large baseload generation that is needed for grid reliability.  \nAlthough the ultimate balance of demand and supply is arguably the same whether the load is co-\nlocated with the generation and behind the transmission meter, rather than in front of the \n5 See, e.g., “The Co-Located Load Solution” at p. 2, authored by Michael Kormos and submitted in Docket \nAD24-11 on November 4, 2024 (“Because the new load has no ability to ‘lean’ on the grid, there is no need for \nexpensive new network transmission projects to connect the load or the associated regional cost allocations to other \ncustomers.”).\n6 PJM Answer, pp. 16-20."},{"page":7,"startToken":1596,"endToken":1911,"text":"- 7 -\ntransmission meter, a behind the transmission meter, non-Network Load co-location arrangement \nhas the potential to accelerate the pace with which the incremental demand arrives on the system, \npotentially without sufficient, if any, additional incremental supply—exacerbating resource \nadequacy concerns.7  In addition, the existing transmission system was (and continues to be) \nplanned and built based on studies that consider the locations of loads and generation across the \nsystem.  Removing generation that is associated with a “fully-isolated” co-location arrangement \n(i.e., a behind-the-generator, non-Network Load arrangement) from the rest of the grid is \ninconsistent with the grid’s planning and operational foundations and thus threatens to alter flows \nin a manner that could require additional transmission upgrades and impair the operational \nflexibility that is essential to reliability.  Finally, the abrupt removal of large baseload resources \nfrom the system may have additional impacts to grid operation and costs that are not immediately \napparent.  \nFair Cost Allocation.  Front-of-the meter arrangements also ensure that the co-located load \nwill pay its fair share of transmission costs as Network Load.  Under behind-the-generator \narrangements, co-located load will not be subject to any transmission costs, even though the load \nwill be both causing costs and receiving the benefits of the grid (including, at a minimum, ancillary \nservices and black start capabilities).  Indeed, there seems to be no question that these loads will \ncreate costs and will receive benefits from the grid, but as non-Network Load will pay for neither. \nAvoids Conflicts with State Law.  As PJM noted in its answer, non-Network Load, “behind-\nthe-generator” co-location arrangements may not be permissible in all states within the PJM \nfootprint based on whether the state is deregulated for generation supply and the state’s laws on \n7 See statements of Stu Bresler on behalf of PJM during the Technical Conference at p. 39, lines 13-24 of \nthe Transcript from Co-Located Large Load Technical Conference in Docket AD24-11."},{"page":8,"startToken":1911,"endToken":2190,"text":"- 8 -\nrequiring the franchised utility to be the sole provider of generation supply to the load.8  The front-\nof-the-meter, Network Load arrangements currently permitted by the Tariff and as proposed in \nPJM’s preferred options respect those state laws while providing for consistent application of the \nTariff across the PJM footprint.  To the extent a patchwork approach were adopted, with different \narrangements possible in certain states but not others, that would only add further complexity and \nchallenges to the important reliability, system planning, and rate issues discussed above.  \nUltimately, the advantages of front-of-the-meter, Network Load arrangements far \noutweigh these numerous concerns with behind-the-generator, non-Network Load arrangements.  \nMoreover, the alleged potential benefits of the non-Network Load, behind-the-generator \narrangements rely largely on the fiction that the arrangement is “fully isolated” from the grid.  As \nnoted by PJM’s answer, this is not accurate from either an engineering or economic standpoint \nbecause the large co-located load receives services from the grid (e.g., ancillary services), but does \nnot pay for it, and because the “full isolation” is dependent on a protection system that could fail \n(and has in some circumstances) dumping significant load onto the grid with little notice.9  If these \nlarge loads have the potential to appear on the system, even for a short time, this could have a \nsignificant impact on the grid.  \nB. Buckeye Supports PJM’s “Preferred” Options\nBuckeye agrees with PJM that the existing Tariff is just and reasonable because it “permits \nco-located loads to interconnect through existing load interconnection processes,” and the fact that \n“certain entities may prefer, for their own business reasons, alternative pathways to co-location,” \n8 PJM Answer, pp. 5-6.\n9 PJM Answer, p. 42."},{"page":9,"startToken":2190,"endToken":2474,"text":"- 9 -\ndoes not render the existing Tariff invalid.10  Accordingly, Options 1 and 2 described by PJM are \njust and reasonable and currently accommodated by the existing Tariff.11 \nBuckeye supports additional flexibility for large load co-location as spelled out in Options \n6, 7, and 8, as each of these options provide flexibility to the load while supporting resource \nadequacy.  \n•\nOption 6: supports co-located load that elects to be Network Load and bring its own \ngeneration, whether that is new generation or generation expecting to be retired and \nprovides incentives for faster interconnection processing of the associated generation.12 \n•\nOption 7: allows co-located load to be classified as “non-capacity backed load” for a \ntransitional period until the appropriate resource adequacy balance is obtained.  This \nwould allow the large load to avoid capacity costs during the transitional period and \nallow PJM to curtail the large load in emergencies.  This option may allow large loads \nto be interconnected to the grid more quickly than traditional interconnection \nprocesses.13   \n•\nOption 8: co-located load may participate as demand response with potential \nexpansions on the use of diesel generators as back-up generation.14  \nBuckeye supports the Commission providing additional clarity or guidance to support these \noptions which provide flexibility for the co-located load, while also addressing resource adequacy \nissues.    \n10 PJM Answer, p. 32.  \n11 Co-location arrangements that are not Network Load are also potentially permissible under the existing \nTariff under Option 3, but as recognized by PJM, the Non-Retail Behind the Meter Generation program provided for \nin the Tariff was not intended for this type of large load arrangement.  PJM Answer, pp. 11-13.  \n12 PJM Answer, pp. 16-18.  \n13 PJM Answer, pp. 18-19.  \n14 PJM Answer, pp. 19-20."},{"page":10,"startToken":2474,"endToken":2875,"text":"- 10 -\nC. Transmission Cost Impacts of Large Load\nThe Commission has raised concerns with issues of transmission cost allocation and \nforecasting relating to co-location arrangements.15  PJM recognizes in its response that inaccurate \nforecasting can result in overbuilt transmission infrastructure, and that this risk is true with respect \nto all large load additions—not just those co-located with generation.16  PJM notes that for both \ntransmission and capacity costs, “[t]o the extent the forecasted load additions do not actually \nmaterialize, these higher capacity [and transmission] costs would be allocated to all other load on \nthe system.”17  Buckeye agrees that forecasting and cost allocation issues associated with large \nloads are a significant concern and one that the Commission should address, regardless of whether \nthat load is co-located with generation or not.  \nLoad growth of approximately 10,000 MW driven by data centers in the Dominion Zone \nresulted in approximately $13 billion in transmission investment to accommodate this load.18  \nCentral Ohio is also experiencing massive load increases that will require significant transmission \ninvestment, impacting the transmission rates for everyone in the AEP Zone, including Buckeye \nand its members.  PJM’s load forecast analysis that drives transmission investment anticipates \n15 See Questions (g)(v), (b)(iii), and (f)(iv) from the Order.    \n16 PJM Answer, p. 65.\n17 Id.\n18 For the 10,000MW of new load in the Dominion zone, see slide 9 from the PJM Interconnection, L.L.C., \nTransmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board (Jan. 2025), available at \nhttps://www.pjm.com/-/media/DotCom/committees-groups/committees/teac/2025/20250107/20250107-item-12---\nreliability-analysis-update.pdf.  Upgrades in the Dominion Zone developed during 2022 RTEP Window 3 (and \napproved by PJM in Dec 2023) totaled $5.143 billion.  See PJM Interconnection, L.L.C., Transmission Expansion \nAdvisory Committee (TEAC) Recommendations to the PJM Board (Dec. 2023), available at https://pjm.com/-\n/media/committees-groups/committees/teac/2023/20231205/20231205-pjm-teac-board-whitepaper-december-\n2023.ashx. Baseline improvements in the Dominion Zone developed during 2024 RTEP Window 1 totaled $5.919B. \nSee page 1 of the February 2025 TEAC Whitepaper available at https://www.pjm.com/-/media/DotCom/committees-\ngroups/committees/teac/2025/20250204/20250204-pjm-board-whitepaper-february-2025.pdf.  Adding other baseline \nimprovements approved during 2023 RTEP Window 1 and 2 and prior to 2022 RTEP Window 1 equates to \napproximately $13 billion.  These costs do not include the costs of supplemental projects associated with large load \ngrowth."},{"page":11,"startToken":2875,"endToken":3326,"text":"- 11 -\n10,000 MW of new load in the AEP Zone of PJM by 2030.19  AEP Ohio20 has stated that it has \nreceived requests for 30,000 MW of new data center load in Central Ohio, indicating the 10,000 \nMW may only be the beginning of massive load growth in Ohio and the AEP Zone generally.21  \nIf the load shows up as expected, the massive investments in new transmission should not \nresult in cost increases to wholesale transmission customers, and ultimately retail ratepayers.  The \nexpansion in the load paying for the increased rate base should maintain or decrease the rates for \nexisting transmission customers.  However, other customers in the applicable zone could face \nsignificant cost increases if massive transmission costs are incurred, and the load does not show \nup as planned for in the transmission expansion, is or becomes significantly lower than the original \nrequest, or has the ability to bypass the transmission cost allocation mechanism.22  \nCurrently, other customers are exposed to the potential for these significant cost shifts.  In \nthe AEP Zone of PJM, transmission costs are allocated to wholesale transmission customers based \non an annual single coincident peak (1 CP) – meaning that transmission costs are allocated to \nwholesale transmission customers/LSEs based on their usage during a single hour of the entire \nyear.  Because the massive transmission investments that are driven by these large loads are sunk \ncosts that are recovered over time through transmission rates, rather than directly assigned to the \n19 See Slide 10 of the “Load Adjustment Requests Summary for 2025 Load Forecast – Preliminary” presented \nat the Load Analysis Subcommittee on November 25, 2024 available at https://www.pjm.com/-\n/media/DotCom/library/reports-notices/load-forecast/2025-load-report.pdf; see also Slide 26 of the “2025 PJM Long-\nTerm \nLoad \nForecast \nReport” \ndated \nJanuary \n24, \n2025 \navailable \nat \nhttps://www.pjm.com/-\n/media/DotCom/library/reports-notices/load-forecast/2025-load-report.pdf. \n20 Ohio Power Company d/b/a AEP Ohio is the LSE serving the Central Ohio region and other parts of \nOhio.  \n21 See Supplemental Testimony of Matthew S. McKenzie at p. 4 filed in In the Matter of the Application of \nOhio Power Company for New Tariffs Related to Data Centers and Mobile Data Centers, Case No. 24-508-EL-\nATA.    \n22 The load may not show up as expected as the result of any number of factors – the load decided not to \nbuild or built less than initially planned for, the load installed behind the meter generation reducing peak demands \nafter transmission has been built to serve the load, the load relocated after coming online, the load uses demand \nresponse to reduce its peak demand, or the load gains efficiencies that reduces its energy needs."},{"page":12,"startToken":3326,"endToken":3675,"text":"- 12 -\nloads, reduction in the load during a single hour after building the transmission infrastructure to \nserve that load will not reduce overall costs.  Rather, it would shift the costs from the LSE for \nwhich the costs were incurred to other LSEs, and their retail customers, in the transmission zone.  \nTo address these cost-shifting concerns caused by new large loads, the Commission should \nconsider the following solutions, as more fully addressed in Buckeye’s Comments filed on \nDecember 9, 2024 in Docket AD24-11:\nLSE Responsibility.  The Commission should consider requiring the LSE that is driving the \ntransmission investment (i.e., the LSE in whose territory the retail large load is locating) to be \nresponsible for any cost-shifting caused by large loads that do not show up as expected, thereby \ncovering the costs of transmission investments caused by their retail load.  The LSE with the large \nnew load should be the entity that receives this price signal, because it has a retail relationship with \nthe large load that creates the potential for stranded transmission investment and is therefore able \nto pass the stranded cost responsibility to that retail load.  For instance, the LSE could enter into \nretail-level agreements with the large loads driving such transmission investments that address cost \nresponsibility in the event that load does not materialize as anticipated (e.g., through a minimum \ndemand charge, and minimum contract term, backed by appropriate credit support requirements). \nImportantly, any costs collected under such retail arrangements should be credited to the wholesale \ntransmission revenue requirement to ensure that any stranded transmission costs associated with \nsuch large loads are not shifted to other LSEs in the zone.23  \n12 CP or NCP Billing Determinants.  In addition to the LSE responsibility, another \npotential mechanism that should be considered to help mitigate unreasonable cost shifts is \n23 For an example of this approach, see the Transmission Customer New or Upgraded Service Construction \nService Agreement tariff filing submitted by The Dayton Power and Light Company in FERC Docket No. ER25-\n192 on October 23, 2024, accession number 20241023-3047, and accepted by FERC on December 20, 2024."},{"page":13,"startToken":3675,"endToken":3919,"text":"- 13 -\nchanging the 1 CP billing determinant for the PJM transmission cost allocation for wholesale \ntransmission rates under the PJM Open Access Transmission Tariff to twelve coincident peaks (12 \nCP) or to one or more non-coincident peaks (NCP).  This billing determinant adjustment may not \naddress stranded costs in the event that a large load fully fails to materialize, or reduces or \nterminates operations contrary to expectations, but it would make it more difficult for large loads, \nparticularly hyperscale data centers, to reduce peak load during the single coincident peak, thereby \nshifting costs to other wholesale customers and their retail members without reducing any of the \nactual transmission costs that have already been incurred.  A 12 CP approach is a more accurate \nway to assign transmission costs to the loads based on their actual use of the system.  This approach \nwas recently proposed by Virginia Electric and Power Co., d/b/a Dominion Energy Virginia \n(“Dominion”) and approved by FERC.24  And it is also being considered by the Texas Legislature \nin the Electric Reliability Council of Texas (ERCOT) region in response to the large influx of data \ncenter load in that region.25\n24 See PJM Interconnection, L.L.C. and Virginia Electric and Power Company, FERC Docket Nos. ER19-\n1661-000, ER19-1661-001 and PJM Interconnection, L.L.C., 169 FERC ¶ 61,041, October 17, 2019.\n25 See Senate Bill 6 Relating to electricity planning and infrastructure costs for large loads, introduced in \nFebruary 2025."},{"page":14,"startToken":3919,"endToken":4001,"text":"- 14 -\nIV.\nCONCLUSION\nWHEREFORE, Buckeye requests that the Commission give full consideration to these \ncomments and concerns in connection with its examination of the issues surrounding large loads \nco-locating with generation resources and the larger impact of large loads on the electric grid.\nRespectfully submitted,\n/s/ Lija Kaleps-Clark\nKurt P. Helfrich\nGeneral Counsel\nLija Kaleps-Clark\nAssociate General Counsel\nBuckeye Power, Inc.\n6677 Busch Boulevard\nColumbus, Ohio 43229\nTelephone: (614) 681-5151\nkhelfrich@ohioec.org \nlkaleps@ohioec.org \nIts counsel\nDated:  April 23, 2025"},{"page":15,"startToken":4001,"endToken":4041,"text":"- 15 -\nCERTIFICATE OF SERVICE\nI hereby certify that on this 23rd day of April, 2025, I have caused the foregoing to be served \nupon each person listed on the Official Service List for this proceeding.\n /s/ Lija Kaleps-Clark\n Lija Kaleps-Clark"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":1088,"startToken":0,"endToken":314},{"p":2,"at":1088,"title":"I. BACKGROUND","method":"printed heading","endPage":3,"endAt":1783,"startToken":314,"endToken":638},{"p":3,"at":1783,"title":"II. INTEREST OF BUCKEYE","method":"printed heading","endPage":5,"endAt":795,"startToken":638,"endToken":1132},{"p":5,"at":795,"title":"III. COMMENTS","method":"printed heading","endPage":5,"endAt":809,"startToken":1132,"endToken":1134},{"p":5,"at":809,"title":"A. Large Load Co-located with Generation Should be Network Load in Front of the Meter","method":"printed heading","endPage":8,"endAt":1496,"startToken":1134,"endToken":2133},{"p":8,"at":1496,"title":"B. Buckeye Supports PJM’s “Preferred” Options","method":"printed heading","endPage":10,"endAt":7,"startToken":2133,"endToken":2475},{"p":10,"at":7,"title":"C. Transmission Cost Impacts of Large Load","method":"printed heading","endPage":14,"endAt":7,"startToken":2475,"endToken":3920},{"p":14,"at":7,"title":"IV. CONCLUSION","method":"printed heading","endPage":15,"endAt":7,"startToken":3920,"endToken":4002},{"p":15,"at":7,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":15,"endAt":242,"startToken":4002,"endToken":4041}]}