{"document":{"slug":"rec-20250423-5162","title":"Comments of Mainspring Energy, Inc. on Co-located Generation and Data Center Integration","issued":"2025-04-23","accession":"20250423-5162","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Mainspring Energy","kind":"comments","file":"sources/filings/text/20250423-5162_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250423-5162","tier":"record","sha256":"2bc9da713b955c9418acb9f38d8957431db86e507964400329e88cfbfcf645c7","pages":15,"tokens":4902,"emptyPages":[],"textThemes":["colo","flex","study","cost"]},"pages":[{"page":1,"startToken":0,"endToken":209,"text":"Mainspring Energy, Inc.​\n3601 Haven Avenue \nMenlo Park, CA 94025​\nwww.mainspringenergy.com \nApril 23, 2025 \nKimberly D. Bose, Secretary​\nFederal Energy Regulatory Commission​\n888 First Street, N.E.​\nWashington, D.C. 20426 \nRe: Docket Nos. EL25-49-000, AD24-11-000, EL25-20-000 (Consolidated)​\nComments of Mainspring Energy, Inc. on Co-Located Generation and Data Center \nIntegration \nDear Secretary Bose: \nPursuant to Rule 211 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § \n385.211, Mainspring Energy, Inc. respectfully submits the attached comments in \nresponse to the Commission’s Order Instituting Proceeding issued on February 20, \n2025 and the subsequent filings by PJM Interconnection, L.L.C. and other parties on \nMarch 24, 2025. \nMainspring appreciates the Commission’s leadership in addressing the growing \nchallenge of integrating large, high-load-factor customers such as data centers while \nmaintaining grid reliability. We are a dispatchable generation technology provider \nactively developing co-located and behind-the-meter projects across the PJM footprint. \nIn the attached comments, Mainspring: \n●​ Supports PJM’s exploration of new flexibility frameworks, including Options 6 and \n7;​\n \n●​ Recommends preserving the two existing BTMG classes (retail and non-retail) \nwhile establishing a new tariff-defined class for repurposed legacy generation \n(Option 3);​\n \n●​ Proposes specific tariff language to support this third class and improve \ntransparency around cost allocation and interconnection study requirements;​"},{"page":2,"startToken":209,"endToken":286,"text":"●​ Urges the Commission to require PJM to enhance forecasting by gathering \nrelevant data on co-located generation; and​\n \n●​ Encourages FERC and state regulators to continue aligning incentives for \ndispatchable, on-site capacity deployment to support reliability and customer \naffordability.​\n \nWe look forward to continued collaboration with the Commission, PJM, and \nstakeholders to advance resilient, affordable, and U.S.-engineered energy solutions. \nRespectfully submitted,​\n  ​\n /s/ Brian Kauffman​\n Brian Kauffman​\n Director, Wholesale Market Development​\n Mainspring Energy, Inc.​\n brian.kauffman@mainspringenergy.com"},{"page":3,"startToken":286,"endToken":474,"text":"UNITED STATES OF AMERICA \nFEDERAL ENERGY REGULATORY COMMISSION \n1 \nPJM Interconnection, LLC, et al. \nAllegheny Electric Cooperative, Inc.  \nAmerican Transmission Systems, Incorporated  \nAtlantic City Electric Company  \nBaltimore Gas and Electric Company  \nDelmarva Power & Light Company \n Duke Energy Ohio, Inc.  \nDuke Energy Kentucky, Inc.  \nEast Kentucky Power Cooperative, Inc.  \nEssential Power Rock Springs, LLC  \nHudson Transmission Partners, LLC  \nJersey Central Power & Light Company  \nMid-Atlantic Interstate Transmission, LLC  \nNeptune Regional Transmission System, LLC  \nOld Dominion Electric Cooperative  \nPECO Energy Company  \nPPL Electric Utilities Corporation  \nPotomac Electric Power Company  \nPublic Service Electric and Gas Company  \nRockland Electric Company  \nTrans-Allegheny Interstate Line Company  \nTransource West Virginia, LLC \nUGI Utilities, Inc.  \nMonongahela Power Company  \nThe Potomac Edison Company  \nCommonwealth Edison Company  \nCommonwealth Edison Company of Indiana, Inc.  \nThe Dayton Power and Light Company  \nAEP Appalachian Transmission Company, Inc.  \nAEP Indiana Michigan Transmission Company, Inc. AEP \nKentucky Transmission Company, Inc.  \nAEP Ohio Transmission Company, Inc.  \nAEP West Virginia Transmission Company, Inc. Appalachia\nPower Company  \nIndiana Michigan Power Company \nKentucky Power Company  \nKingsport Power Company \nOhio Power Company  \nWheeling Power Company  \nDuquesne Light Company  \nVirginia Electric and Power Company \nLinden VFT, LLC   \n Docket Nos. \nEL25-49-000"},{"page":4,"startToken":474,"endToken":752,"text":"COMMENTS OF MAINSPRING ENERGY, INC. REGARDING CO-LOCATED \nGENERATION AND DATA CENTER INTEGRATION  \nExecutive Summary \nThe Utility-Data Center “seam” is bearing much of the brunt of tightening regional grid \nreserve margins and rising customer costs. Mainspring is providing solutions to utilities, large \nenergy users and grid operators to rapidly bring new capacity. Mainspring’s Linear Generator \ncan be configured as a new traditional grid-scale generator, new generators at retail customer \nsites behind the meter (BTMG), and non-retail BTMG deployed rapidly by public power entities. \nOther key takeaways:  \n●​ Upon close review, PJM’s tariff is not just and reasonable because it lacks explicit details \non how legacy generation can transition to become BTMG.  \n●​ PJM’s detailed analysis of Option 3 describes a new class of BTMG. What PJM \ndescribes as Option 3 is not currently addressed in the tariff in a coherent fashion. This \nis a meaningful omission in the Tariff as many large generators are considering \ntransitioning to this configuration to serve large loads. \n●​ In addition, we also respectfully urge the Commission to preserve the existing and \nhistoric BTMG classes for resources that enter service behind a customer’s meter \n(primarily under retail jurisdiction).  \n●​ Next, we also recommend eliminating the cap on Non-Retail BTMG. \n●​ We offer detailed recommendations on black start, ancillary service and specifically, \nreserve cost allocation. \n2 \nCity of Cleveland, Department of Public Utilities,  \nDivision of Cleveland Public Power  \nCity of Hamilton, OH  \nSouthern Maryland Electric Cooperative, Inc.  \nOhio Valley Electric Corporation  \nAMP Transmission, LLC \nSilver Run Electric, LLC  \nNextEra Energy Transmission MidAtlantic Indiana, Inc.  \nWabash Valley Power Association, Inc.  \nKeystone Appalachian Transmission Company \n \n  \nLarge Loads Co-Located at Generating Facilities \n AD24-11-000 \nConstellation Energy Generation, LLC  \n \nv. PJM Interconnection, LLC \n EL25-20-000 \n(Consolidated)"},{"page":5,"startToken":752,"endToken":1238,"text":"●​ After this, we explore implications to forecasting and request FERC to require PJM to \ngather information on customers with co-located generation to properly plan long-term \nand operationally. \n●​ Finally, we stand ready to work with states and all stakeholders to develop Options 6 and \n7 offered by PJM and other new flexibility solutions.  \nIntroduction \nMainspring Energy is actively developing on-site and co-located projects in the PJM \nregion and anticipates operating projects under one or more of the eight “Options” described in \nPJM’s March 24 Answer. We appreciate the vital work undertaken by the Commission, PJM, \nstates, utilities and other stakeholders to incorporate large loads into the grid quickly while \npreserving reliability and minimizing cost. We are regularly speaking with customers across the \ncountry about the “seam” that requires creative solutions. The high load factor, data center - \nutility seam, is a major area of focus for us and Mainspring’s Linear Generator was built for this \nmoment.  \nPJM is up for this challenge. PJM has been a global leader at integrating large loads. \nHowever, new co-located generation is likely needed to manage the ramp in new loads over the \nnext 5 to 10 years. As such, we are concerned that PJM’s comments and Tariff do not \nadequately distinguish the range of planning, markets and operational steps involved in \nre-purposing legacy, front of the meter PJM generation into behind the meter generation.  \nThe reliability challenge is indeed tremendous; PJM’s Board recently observed that, \n“Taking the anticipated 2025 load forecast into account, the PJM system could see a capacity \nshortage as soon as the 2026/27 Delivery Year.”1 As Mainspring describes in the enclosed \nwhitepaper, Bring Your Own Power (BYOP), data center availability is low while demand for \ncapacity is incredibly high, including in PJM’s footprint.2 PJM should not overlook the opportunity \nfor help from new retail and non-retail generation to offset the growth in large loads. \nData centers can not afford delays in interconnection. As we uncovered in the BYOP \nwhitepaper, many new loads are receiving 3-5 year estimates for grid delivery of power. For a \n100 MW data center, three years of delay translates to over $500M in lost revenue. In response \nto these pressures and the need to protect other captive ratepayers, PJM and its member states \nshould take extra effort to enable all forms of new generation: front of the meter PJM resources, \nretail resources at customer sites (BTMG), and non-retail BTMG deployed quickly by public \npower entities. We urge all stakeholders to think constructively about how new, dispatchable \nbehind the meter generation can be expanded within today’s existing paradigms.  \nPJM’s tariff is currently insufficient because it lacks details that explain the detailed \nprocess and costs to re-purpose legacy generation into behind the meter generation. The \n2 Whitepaper is also available on our website at https://www.mainspringenergy.com/byop/  \n1 \nhttps://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-disclosures/2024/20241209-board-let\nter-outlining-action-on-capacity-market-adjustments-rri-and-sis.pdf  \n3"},{"page":6,"startToken":1238,"endToken":1682,"text":"Commission should correct this omission by requiring the rules that PJM describes under \n“Option 3” to be inserted into the Tariff as a new class of BTMG resources.  \nSimultaneously, Mainspring agrees with PJM that it is time to prioritize enabling new \nframeworks that address the utility - data center seam. We are intrigued by PJM’s \nforward-looking proposals in Options 6 and 7. We are especially encouraged by PJM’s \nemphasis on “non-firm” grid service models aligned with on-site power. These opportunities, as \nPJM notes, depend on proactive state ratemaking to align customer incentives. The recent \nrelease of the first phase of Duke’s Rethinking Load Growth study in February 2025 provides a \nstrong foundation, though significant work remains to translate these findings into actionable \nplans that support customer affordability and incentivize flexible development.3  \nIn summary, Mainspring’s analysis focused on Option 3 at this juncture concludes that \nthe Tariff is not just and reasonable. In these comments, Mainspring highlights its rationale for \nwhy Option 3 requires Tariff additions, what those additions are, and provides support for PJM’s \nexpeditious enablement of new Options 6 and 7, among other recommendations. \nProcedural Background \nPursuant to Rule 211 of the Federal Energy Regulatory Commission’s (“Commission”) \nRules of Practice and Procedure, 18 C.F.R. § 385.211, Mainspring submits these comments in \nresponse to the Commission’s February 20, 2025 Order Instituting Proceeding under Section \n206 of the Federal Power Act and Consolidating with Other Proceedings (the “Show Cause \nOrder”).4 In the Show Cause Order, the Commission specifically invited comment on these \nissues after the filings dated March 24, 2025 of PJM Interconnection, L.L.C. (“PJM”), the \nIndicated PJM Transmission Owners, Public Service Gas & Electric, Allegheny Electric \nCooperative, Inc., Silver Run Electric, LLC, Dayton Power and Light Company, and NextEra \nEnergy Transmission MidAtlantic, Inc.  \nMainspring timely filed a doc-less motion to intervene on March 6, 2025 under EL25-49. \nEarlier, on December 9, 2024, Mainspring filed co-located generation post-technical comments \nunder AD24-11.5  \nAbout Mainspring \nFounded in 2010 by Stanford-trained engineers, Mainspring Energy is pioneering \nresilient, affordable, and clean generation technologies. Our flagship product, the Linear \nGenerator, is the result of years of research into high-efficiency electricity generation and is now \ndeployed across various sectors. With over 70 years of aggregated runtime and industry-leading \nuptime, our modular units deliver dispatchable power with flexible fuel options.  \nOur customers include Lineage Logistics, Prologis, Kroger, and utilities such as AEP and \nFlorida Power & Light. Mainspring joined the EPRI DCFlex initiative in January 2025, aimed at \n5 https://elibrary.ferc.gov/eLibrary/filedownload?fileid=AB9D8BB7-268E-CC2A-991D-93AC32200000  \n4 PJM Interconnection, L.L.C., et al., 190 FERC   61,115 (2025) \n3 https://nicholasinstitute.duke.edu/publications/rethinking-load-growth  \n4"},{"page":7,"startToken":1682,"endToken":2182,"text":"demonstrating how data centers can stabilize the grid and improve interconnection. \nMainspring’s small unit size enables five nines of uptime with minimal capacity overbuild.  \nSolutions for Data Centers \nIn 2025, Mainspring plans to construct several data center generation projects, including \nin a PJM state. We foresee implementing various configurations across these projects and \nemphasize that the Commission should preserve operational flexibility and opportunities for \nphased development.  \nFor instance, in Phase 1, we can deliver a power solution within 9 months to serve the \ndata center as a prime power source. In Phase 2, once grid interconnection is feasible, \nconfigurations may vary: the linear generators could supplement the grid on a continuous basis \n(operating as “behind the meter generation” to PJM). Alternatively, in Phase 2 linear generators \ncould be used only to manage peak on-site loads and/or grid peaks via an “interruptible \nprogram” (also as “behind the meter generation” to PJM). Or, as a third option in Phase 2, they \ncould serve as full backup in a diesel-free “2N” configuration (again, to PJM this would classify \nas “behind the meter generation”).6  \nIn Phase 3, as cleaner fuels become more available, our generators can transition to \nbiogas, green hydrogen, ammonia, or fuel blends—without major capital reinvestment. These \nphases are described in more detail in the enclosed 2024 whitepaper Bring Your Own Power \n(BYOP), co-authored by Stanford University Fellow, Susanna Kass, and Mainspring CEO \nShannon Miller. Another option and phase could involve Mainspring’s units transitioning into \nPJM front of the meter capacity (such as under PJM Option 1 or 2).  \nWe underscore that a menu of options is critical. The prime concerns for data centers \nare speed and reliability, as we underscore in Figure 1, below. Data centers and other large \nusers must have the ability to decide the fate of the generation that they are paying to bring to \nthe grid, especially given the higher reliability requirements data centers face relative to 99% of \nother customers on the grid. \nA broad range of industry participants are increasingly focused on adding mechanisms \nfor data center flexibility. Two of the most promising solutions are to (1) bring new, \naround-the-clock generation such that new demands do not put any new pressure on the grid \nand (2) run on-site generation for peaking (such as ~1,000 hours/year) non-emergency \npurposes to alleviate grid stress. Some U.S. utilities nationally are already developing programs \nthat fit into this second category and align incentives for data centers to be flexible.7 As \ndiscussed, Mainspring’s solutions fit critical reliability needs.  \n7 “Hearthland Energy Launches Interruptible Data Center Rate Policy for Customers”, American Public \nPower Association, March 28, 2025. \nhttps://www.publicpower.org/periodical/article/heartland-energy-launches-interruptible-data-center-rate-pol\nicy-customers; Portland General Electric, Oregon PUC Docket No. UE 430 proposal allows for large load \ncustomers to increase allocated capacity by participating in flexible load program \nhttps://apps.puc.state.or.us/edockets/DocketNoLayout.asp?DocketID=23949   \n6 “2N” here refers to full electric supply redundancy for data center load \n5"},{"page":8,"startToken":2182,"endToken":2728,"text":"Behind the Meter Generation (BTMG) \nBefore making specific recommendations, we highlight key attributes of BTMG. First, \nBTMG is a suitable configuration moving ahead in line with PJM preferences. Grid limitations \nhave led to growing reliance on “bridge to grid” models, where retail customers, in consultation \nwith their local utility, bring their own capacity at least for Phase 1. Once the load customer is \nconnected to PJM’s system, it becomes “network load” subject to the terms of the entity \nreceiving transmission service. Therefore, the BTMG models should satisfy PJM’s stated \npreference for co-located configurations to retain the load as network load. That said, the \nconcept of “network load” may need to evolve.  \nSecond, reducing customer demand has equivalent if not better results than adding \nformal PJM-qualified generation capacity. While PJM references “bring your own capacity” \n(Option 6) as formally qualified resources that add formal MWs on the supply side, adding \nBTMG reduces the demand on the PJM grid and can be done much faster. In addition, having \nmore generation on the distribution system reduces transmission and distribution losses. \nTherefore, at Mainspring we think of BTMG as “bringing” new capacity, also.   \nTwo Separate BTMG Classes are in the PJM Tariff and Manuals Today: \nRetail and Non-Retail BTMG \n“BTMG” refers to customer-sited generation not registered as a wholesale PJM \nresource.8 PJM described BTMG in 2004 at a single customer site. Later, “this definition was \nsubsequently expanded to permit inclusion of municipals and EDCs (“Non-Retail”) that use \ndistribution facilities to serve loads, with the consent of the owners or lessee of the distribution \nfacilities”.9 Mainspring agrees with PJM that these are in many important ways, separate \nconstructs. There exists a large body of rules, captured under PJM Manual 14D that pertain only \nto Non-Retail Behind the Meter Generation.  \nAs such, why does PJM’s Answer often lump these two classes together into its \nAnswer? PJM’s Answer often obscures their unique regulatory and operational characteristics. \nAny future analyses and reforms should more carefully distinguish between these two forms. \nFurther, it is critical that PJM retain these classes of BTMG as separate from existing PJM \ngeneration, such as legacy nuclear units, that transition to become BTMG.  \nA Third Class is Needed: Repurposed Generation Capacity into BTMG   \nMuch industry attention has focused on reassigning existing grid-connected capacity to \nlarge loads.PJM continues this trend in its Answer describing “Option 3”. As a company \ndeveloping new, greenfield on-site generation, Option 3 looks foreign and clearly distinct from \n9 PJM Answer p 35 \n8 PJM Tariff, Part VII, Subpart A, section 300 defines “‘Behind The Meter Generation’ shall refer to a \ngeneration unit that delivers energy to load without using the Transmission System or any distribution \nfacilities (unless the entity that owns or leases the distribution facilities has consented to such use of the \ndistribution facilities and such consent has been demonstrated to the satisfaction of the Office of the \nInterconnection); provided, however, that Behind The Meter Generation does not include (i) at any time, \nany portion of such generating unit's capacity that is designated as a Generation Capacity Resource; or \n(ii) in an hour, any portion of the output of such generating unit that is sold to another entity for \nconsumption at another electrical location or into the PJM Interchange Energy Market.” \n6"},{"page":9,"startToken":2728,"endToken":3052,"text":"the “behind the meter generation” configurations (retail and non-retail) that PJM has had in its \ntariff for decades: Option 3 describes significant studies; Options 3 describes generation as \npossibly earning capacity revenue and retaining CIRs; Option 3 describes cost allocation for \ninterconnection upgrades - all topics outside the scope of new, pure behind the meter \ngeneration project.   \nPJM in its table “Existing Option 3” was clearly focused on existing generation that is \nre-purposed to become behind the meter generation. To offer more details:  \n●​ PJM states BTMG is eligible for “Generation revenue” for the “capacity (for \nportion of CIRs retained)”, clearly indicating that the generation was previously \ngrid-studied generation that received CIRs \n●​ PJM indicates that significant studies are required, which are only needed when \ngeneration transitions to BTMG:  \n○​ “TO Load Integration study”  \n○​ “PJM Do No Harm study” \n○​ “RTEP process inclusive of Load Forecast” \n○​ “Necessary Study” \n●​ PJM specifies “Cost Allocation for Interconnection Upgrades” which are only \nrequired when existing generation transitions to BTMG: \n○​ “Supplemental projects pursuant to local TO methodology” \n○​ “RTEP upgrades pursuant to (sic) RTEP cost allocation” \n○​ “Generator for the changes to its facility to accommodate the load” \n●​ The column description, “Existing Behind the Meter Generation where the load is \nthe customer” should be clarified with the addition of four important missing \nwords to state “Existing Generation that repurposes to Behind the Meter \nGeneration where the load is the customer” \nBelow, we summarize several key differentiators across three classes of BTMG.  \n \nNew Retail BTMG \nNew Non-Retail \nBTMG \nRepurposed Legacy \nGen into BTMG \nExisting Tariff J&R? \nYes \nYes, but consider \nremoving the 3 GW \ncap \nNo. New tariff \nlanguage required \nEst. Length of \nPJM/Utility Studies \nRequired Prior to \nEnergization Under \nthis Class  \n<6 mos \n<1 year \n2-3 years+ \nBeginning electrical \nlocation of assets \nBehind retail \ncustomer meter \nBehind retail \ncustomer meter or \ndistribution system  \nPJM system; High \nvoltage transmission  \nFigure 1: Comparison of classes of BTMG. Study length estimates are for directional purposes only.   \n7"},{"page":10,"startToken":3052,"endToken":3407,"text":"Tariff Language Needed: Repurposed Generation Capacity into BTMG \n​\nClearly, repurposing existing assets to become behind the meter generation adds \ncomplexity, time and costs. Such steps should be available and transparent. These \nPJM-identified requirements described in PJM’s Answer under “Existing Option 3 “ should be \nadded to the PJM Tariff given their importance to all market participants. The Commission \nshould require PJM to add this tariff language describing this list of required studies and \napproaches to allocate study and interconnection upgrade costs appropriately for this class of \nexisting generation repurposed into BTMG.    \nRecommended Language: \n●​ Definition. Repurposed Behind the Meter Generation (BTMG) is generation that is \nlocated behind a retail customer meter that was previously a Generation Capacity \nResource. \n●​ Study Process for Becoming a Repurposed BTMG. The process is multi-staged and \nincludes the following phases10: \n○​ Complete Transmission Owner retail load integration study, \n○​ Present solutions at the Transmission Expansion Advisory Committee \n(traditionally, Supplemental Projects), \n○​ PJM will perform a “Do No Harm Study” to evaluate how a Supplemental Project \nwill impact the reliability of the Transmission System.  \n■​ If as a result of the do no harm study, system upgrades are found to be \nrequired such upgrades will be considered part of the Supplemental \nProject and are the responsibility of the Transmission Owner sponsoring \nthe Supplemental Project \n■​ Supplemental Projects are cost allocated to the local Transmission \nOwner’s zone pursuant to individual Transmission Owner cost allocation \nframeworks, \n○​ The generation owner will request a “Necessary Study” to change the \ninterconnection.  \n■​ PJM will conduct a Necessary Study \n■​ Transmission Owners review PJM’s study analysis to verify that analysis \nand/or perform additional transmission owner analysis pursuant to their \nprocesses or requirements \n○​ An aggregation of large load additions could trigger regional (as opposed to local) \ntransmission system needs, which would be identified as part of the Regional \nTransmission Expansion Planning process in Schedule 6 of the Operating \nAgreement. \n■​ That load could rise to regional RTEP needs when determined during the \nannual load forecasting process in collaboration with LSEs \n■​ With the updated load forecast, the RTEP process may incorporate the \nimpact of the transition of the Generation Capacity Resource. \n10 Adopted from PJM Answer, pp 6-8 \n8"},{"page":11,"startToken":3407,"endToken":3838,"text":"●​ Cost Allocation for Interconnection Upgrades. The following costs may be required when \nGeneration Capacity Resources become Repurposed BTMG. \n○​ Supplemental projects pursuant to local TO methodology \n○​ RTEP upgrades pursuant to RTEP cost allocation \n○​ Generator interconnection for the changes to its facility to accommodate the load \n \nBlack Start and Ancillary Services Cost Allocation  \nIndeed, proper cost allocation is critical. To that point, we also highlight PJM’s assertion \non page 36 that all co-located data center configurations “appear to require” grid ancillary \nservices and black start. To PJM’s credit, the RTO acknowledges that this conclusion is  \nuncertain. In our experience, technology matters: linear generators, unlike nuclear units, can \nprovide their own ancillary services and black start capabilities for on-site loads. Most likely, \nbehind the meter generation configurations with nuclear units will desire to leverage grid \nservices differently than those configurations with linear generators.  \nFor a hypothetical situation, imagine a 200 MW data center. The data center is served \n100 MW from standard grid power and 100 MW with MW BTMG nuclear generation. \nOperationally, the data center is sized for 200 MW interconnection to the PJM system but only \nuses 100 MW at 99% of the time. Charging customers for grid services the 1% of the time \nneeded to supplement the 100 MW co-located generation is appropriate when those services \nare necessary. In addition, from a planning perspective, the customer has already secured \nsufficiently sized interconnection to supplement its nuclear generation on-site, so that cost issue \nhas already been addressed.  \n \nReserves Cost Allocation \nPJM also erroneously suggests that all load with BTMG requires the use of PJM \nreserves above a reasonable threshold. In other words, PJM suggests if  the customer is \ngenerally receiving 100 MW of service from PJM and 100 MW from behind the meter \ngeneration, the customer should actually be paying for more than only 100 MW of reserves.  \nThis issue is nuanced and the answer changes with the exact scenario. Configurations \ncould be designed to entirely avoid relying on reserves for the extra 100 MW. For instance, \nsome loads are incredibly flexible and could drop immediately with the loss of on-site \ngeneration. \nFurther, the interconnection could be sized appropriately for this situation. A 200 MW \ndata center with a 100 MW load interconnection (and 100 MW BTMG) is different from a 200 \nMW data center with a 200 MW load interconnection (also with 100 MW BTMG). In the first \ncase, only 100 MW could ever flow from the grid to the customer. Whereas in the second case, \nthe customer could technically draw upon 200 MW if controls were not in place.   \n9"},{"page":12,"startToken":3838,"endToken":4303,"text":"Mainspring acknowledges that reforms may be needed to ensure BTMG benefits extend \nbeyond long-term resource adequacy to system reliability needs in real-time. Activities in the \ncurrent PJM Reserve Certainty Senior Task Force are proof that navigating this won’t be \neasy.Transitions in data center loads are generally speaking, increasingly impactful to the grid.11 \nHowever, this reserves issue does not appear to require urgent resolution and is likely better \nhandled through PJM’s stakeholder process. \n \nNon-Retail BTMG Cap Should be Lifted \n​\nPublic power entities have a unique opportunity to move quickly to develop to site and \nbuild new generation and implement new customer tariffs to address the “seam”. The Non-Retail \nBTMG model allows public power to operate generation on the distribution system, rather than \nonly behind an individual customer meter. Therefore, we encourage public power entities to \nleverage the Non-Retail BTMG pathway to introduce new generation quickly to the system. \n \nMainspring knows first-hand the advantages of public power entities to solve this \nproblem. Mainspring has been contracted by a public power entity to deliver 36 MW of \ngeneration on the distribution system to offset new build of a data center. While the project is \noutside of PJM, many of the same lessons apply. We are eager to bring our experience to the \nmunicipal and cooperative utilities in the PJM footprint.  \n \nPJM’s Answer emphasizes that innovation may be needed in the Non-Retail BTMG \nspace. Mainspring acknowledges that certain elements of the Non-Retail BTMG framework \nshould also be re-examined such as the fact that these resources “do not carry reserves equal \nto the installed reserve margin”.12 Any further action should also appreciate the potential for \nexpansion of Non-Retail BTMG, given the tremendous promise of this model to solve the \ncapacity gap quickly. The current limit poses a risk to the grid by limiting the amount of new \ncapacity available to add to the system. The Commission should ask PJM to lift the cap on \nNon-Retail BTMG above the current 3 GW limit.  \nSupport for Exploring Options 6 and 7 \nMainspring strongly supports further exploration of Options 6 and 7, recognizing the \npotential of each to offer complementary pathways for integrating large loads. However, these \nare not yet viable alternatives for near-term deployment. BTMG remains the most reliable \nnear-term solution and should be welcomed as “bridge to grid” pathways, capable of maturing \ninto, and working alongside Options 6 or 7. \nOption 6 appears best suited to a range of use cases, from baseload or prime power use \ncases to peaking; Option 7 to intermediate applications; and Option 8 to peaking needs. Each \nfaces emissions limitations, which low-emission technology like Mainspring’s can help navigate. \n12 PJM Answer, Table Option 3 \n11 See activities of NERC Large Loads Task Force https://www.nerc.com/comm/RSTC/Pages/LLTF.aspx  \n10"},{"page":13,"startToken":4303,"endToken":4645,"text":"Detailed Observations \nOption 6 – Bring Your Own Capacity (BYOC) \n●​ We are intrigued by this model, where customer-owned generation becomes a \nPJM resource serving both system needs and the load.  \n●​ However, PJM’s reluctance to create an expedited interconnection path for \nco-located generation is one reason among others that customers may default to \nBTMG.  \nOption 7 – Interruptible Service \n●​ Mainspring supports non-capacity backed service models in which loads can \nself-supply or curtail in exchange for avoided capacity and transmission charges.  \n●​ PJM should explore whether a new “non-firm” load category is needed in its \nplanning models, as current frameworks do not account for this at the \ntransmission level. \nOption 8 – Demand Response with Diesel Gensets \n●​ We agree on the value of generation-based demand response but caution that \ndiesel units are unsuitable for long run times. This approach faces regulatory \nuncertainty and concerns over local air quality impacts.  \n●​ PJM should instead throw its weight behind preparing for the future. As \ndiscussed in the enclosed BYOP whitepaper, “we need to examine if the concept \nof primary and backup systems is sustainable, in comparison to a resilient \nsystem that can operate as both”. \n●​ Linear generators are better suited due to lower emissions and longer runtime \ncapabilities, and they allow for larger installations without breaching emissions \nlimits. Mainspring’s Linear generator produces 97% fewer nitrous oxides than a \ntypical diesel generator.  \nForecasting Needs \nPJM’s load forecasting processes are robust but must evolve to integrate customer \nflexibility, including the ability to help local utilities and end-use customers to ascertain the \nfinancial value of accepting non-firm service. Specifically, PJM in concert with utilities, should \nallow customers to compare costs and time horizons for powering large loads.  \nCustomers should be able to compare a range of wired and on-site generation solutions \nprior to committing to a final infrastructure build. This has important implications to other rate \nclasses, as well, who may be saddled with the costs of infrastructure for decades into the future. \nFurther, large loads should be equipped to communicate evolving data center build phases and \noperations to PJM in real time.   \n11"},{"page":14,"startToken":4645,"endToken":4846,"text":"Conclusion: Mainspring’s Linear Generator and Key \nRecommendations to the Commission  \nAs PJM faces rising loads and tightening reserves, flexible technologies are critical. \nMainspring’s Linear Generator offers: \n• Rapid Deployment: Modular, scalable, and available now. \n• Operational Flexibility: Reliable 24/7 operation with load-following. \n• Fuel Agility: Ready for natural gas, hydrogen, biogas, propane, and ammonia. \n• Environmental Leadership: Substantial emissions reductions. \n• Resilience: Redundant design and multiple fuel pathways. \nWe urge the Commission to affirm the reliability value of new retail and non-retail behind \nthe meter generation and require PJM to file tariff language that clarifies the rules around \n“transitioned” or “repurposed” legacy generation into BTMG generation (Option 3). We support \nPJM’s exploration of Options 6–7. We also encourage states to pursue policies enabling local, \ndispatchable generation for large loads. These tools will help ensure that the region remains a \nglobal leader in digital infrastructure and grid reliability at least cost. \nMainspring is ready to collaborate with stakeholders to deliver on these goals. For further \ninformation, please contact RTO/FERC lead: \nBrian Kauffman​\n​\nDirector, Wholesale Market Development​\n​\nMainspring Energy, Inc.​\n​\nbrian.kauffman@mainspringenergy.com​\n \nSincerely, \n/s/ Brian Kauffman​\nApril 23, 2025 \nEnclosure: Bring Your Own Power (BYOP) by Susanna Kass and Shannon Miller (2024) \n12"},{"page":15,"startToken":4846,"endToken":4902,"text":"CERTIFICATE OF SERVICE  \n \nI hereby certify that I have served a copy of the foregoing document upon all parties \nlisted on the official service list compiled by the Secretary in this proceeding. Dated at Merion \nStation, Pennsylvania this 23rd day of April, 2025. \n \n \n/s/ Brian Kauffman \nBrian Kauffman \nDirector, Wholesale Market Development​\nMainspring Energy, Inc. \n13"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":4,"endAt":99,"startToken":0,"endToken":486},{"p":4,"at":99,"title":"Executive Summary","method":"printed heading","endPage":5,"endAt":347,"startToken":486,"endToken":804},{"p":5,"at":347,"title":"Introduction","method":"printed heading","endPage":15,"endAt":0,"startToken":804,"endToken":4846},{"p":15,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":15,"endAt":373,"startToken":4846,"endToken":4902}]}