{"document":{"slug":"rec-20250423-5165","title":"Comments of Electric Power Supply Association and the PJM Power Providers Group","issued":"2025-04-23","accession":"20250423-5165","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Electric Power Supply Association","kind":"comments","file":"sources/filings/text/20250423-5165_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250423-5165","tier":"record","sha256":"36c9530baf2d80d8b8f12c05a6ce050662ceadfe100a1ba8693c8c29bf53e592","pages":16,"tokens":4858,"emptyPages":[],"textThemes":["colo","flex","retail"]},"pages":[{"page":1,"startToken":0,"endToken":359,"text":"1 \n \nUNITED STATES OF AMERICA  \nBEFORE THE  \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nPJM Interconnection, L.L.C., et al. \nLarge Loads Co-Located at Generating Facilities  \nConstellation Energy Generation, L.L.C. \n   v.  \nPJM Interconnection, L.L.C. \nDocket Nos. EL25-49-000 \n \nAD24-11-000 \n \nEL25-20-000 \n \n(Consolidated) \n \n \nCOMMENTS OF THE ELECTRIC POWER SUPPLY ASSOCIATION \nAND THE PJM POWER PRODUCERS GROUP \n \nPursuant to Rules 212 and 213 of the Rules of Practice and Procedure of the \nFederal Energy Regulatory Commission (the “Commission” or “FERC”)1 and in \naccordance with the Commission’s February 21, 2025 Notice of Institution of Section \n206 Proceeding and Refund Effective Dates2 issued in the above-captioned \nconsolidated proceedings, the Electric Power Supply Association (“EPSA”)3 and The \nPJM Power Providers Group (“P3”)4 respectfully submit these comments on the Show \n \n1  \n18 C.F.R. §§ 385.212, 385.213 (2024). \n2  \nNotice of Institution of Section 206 Proceeding and Refund Effective Dates, Docket Nos. EL25-\n49-000, AD24-11-000, EL25-20-000 (consolidated) (issued February 21, 2025). \n3  \nEPSA is the national trade association representing competitive power suppliers in the U.S. \nEPSA members provide reliable and competitively priced electricity from environmentally responsible \nfacilities using a diverse mix of fuels and technologies. EPSA seeks to bring the benefits of competition to \nall power customers. This pleading represents the position of EPSA as an organization, but not \nnecessarily the views of any particular member with respect to any issue. EPSA filed a timely document-\nless Motion to Intervene in this proceeding on November 25, 2024. \n4  \nP3 is a non-profit organization dedicated to advancing federal, state, and regional policies that \npromote properly designed and well-functioning electricity markets in the PJM Interconnection, L.L.C. \n(“PJM”) region. Combined, P3 members own over 88,000 MWs of generation assets and produce enough \npower to supply over 63 million homes in the PJM region covering 13 states and the District of Columbia. \nThese comments represent the position of P3 as an organization but not necessarily the views of any \nparticular member with respect to any issue. For more information on P3, visit www.p3powergroup.com. \nP3 filed a timely document-less Motion to Intervene in this proceeding on November 25, 2024."},{"page":2,"startToken":359,"endToken":849,"text":"2 \n \nCause Order and answers submitted to that order on March 24, 2025, in particular the \nAnswer of PJM Interconnection, L.L.C. (“PJM Answer”).5  \nEPSA and P3 agree with the Commission that PJM needs to establish tariff \nprovisions and rules to accommodate the array of co-located load arrangements that \nwill facilitate the timely and effective integration of large loads locating in the region. As \nmany comments underscore,6 this is needed to support critical economic development \nas well as national security. Unfortunately, PJM’s Answer is insufficient as the RTO has \ntaken the position that its Tariff is just and reasonable regarding only an extremely \nlimited type of co-location configuration, largely aping the position expressed by many \nPJM Transmission Owners in the instant consolidated proceedings7 (as well as related \nproceedings before the Commission)8 and disregarding the direction in and intent of the \n \n5  \nAnswer of PJM Interconnection, L.L.C., Docket Nos. EL25-49-000, AD24-11-000, EL25-20-000 \n(consolidated) (March 24, 2025). \n6  \nShow Cause Order, P 15, 16, (summarizing comments in the record of Docket No. AD25-11-000, \nTechnical Conference on Large Loads Co-Located at Generating Facilities). \n7  \nAnswer of the Indicated PJM Transmission Owners to the Order Instituting the Proceeding Under \nSection 206 of the Federal Power Act and Consolidating With Other Proceedings, Docket Nos. EL25-49-\n000, AD24-11-000, EL25-20-000 (consolidated) (March 24, 2025), (“Answer of the Indicated PJM \nTransmission Owners”). “[T]he Indicated TOs support the Commission ruling, as part of its review in this \nproceeding, that the existing PJM Tariff and its existing two forms of transmission service—Network \nIntegration Transmission Service (“Network Service”) and Point-to-Point Transmission Service (“Point-to-  \nPoint Service”)—encompass and apply to these arrangements,” p. 2 (citations omitted); “Consequently, \nthe Commission should confirm that the existing PJM Tariff provisions regarding Network Service and \nPoint-to-Point Service are sufficiently inclusive to cover the treatment of co-located load,” p. 5.  \nSee also, Exelon Comments in Opposition to Complaint, Docket No. EL25-20-000, (December \n12, 2024); Post-Technical Conference Comments of PPL Electric Utilities Corporation, Docket No AD24-\n11-000, (December 9, 2024), Section III(A), Large Loads Should Locate in Front of the Meter, Whether or \nNot They Are Co-Located with Generation, pp. 9 – 12, and Section III(B), “The easiest solution to the \ndilemma of behind-the-meter co-located load would be to prohibit it,” p. 12.  \n8  \nSee six Exelon Companies’ utility FPA Section 205 Tariff Amendment Filings to revise PJM Tariff \nAttachment H-1 to unilaterally designate any transmission service to co-located load is Network \nIntegration Transmission Service (“NITS”) unless the load is designated to receive Point-to-Point service \n(rejected by the Commission in an order issued February 20, 2025). Tariff revision filings submitted \nAugust 28, 2024, as follows: Atlantic City Electric Company, Docket No. ER24-2888-000; Baltimore Gas \n& Electric Company, Docket No. ER24-2889-000; Commonwealth Edison Company, Docket No. ER24-\n2890-000; Delmarva Power & Light Company, Docket No. ER24-2891-000; PECO Energy Company, \nDocket No. ER24-2893-000; and Potomac Electric Power Company, Docket No. ER24-2894-000 (not \nconsolidated)."},{"page":3,"startToken":849,"endToken":1289,"text":"3 \n \nShow Cause Order.9 Rather than propose revised Tariff provisions to accommodate \nthese arrangements, PJM passes the buck back to the Commission, seeking extensive \nguidance from the Commission on a path forward, informed by the principles that the \nRTO says it offers in its Answer. There has been no showing that PJM’s Tariff is just \nand reasonable or not unduly discriminatory, or that changes are not needed to enable \nprogress, though PJM claims otherwise. \nIn light of the approach PJM has adopted, EPSA and P3 urge the Commission to \ndirect PJM to develop the Tariff revisions necessary to remove barriers to co-location \narrangements on an expedited, time-limited basis. At this stage, a clear and defined \nprocess is required to move forward in any way, much less expeditiously. Noting that \nthere is some novelty and innovation to the array of co-location configurations that may \nemerge, EPSA and P3 recommend that the Commission convene an expedited time-\nlimited settlement process10 so that PJM can work with its states and members to \nidentify and develop the improvements and clarifications needed to accommodate those \narrangements. This process should be confined to a 90-day period to provide certainty \n \n9  \nShow Cause Order, P 74, (“[W]e find that the existing Tariff appears to be unjust and \nunreasonable or unduly discriminatory or preferential because it does not contain provisions addressing \nwith sufficient clarity or consistency the rates, terms, and conditions of service that apply to co-location \narrangements. The absence of such provisions may leave entities unable to determine what steps they \ncan or must take to effectuate co-location arrangements of various configurations[.]”). \n10  \nSee Joint Comments and Motion to Stay Proceedings and Request to Establish Settlement Judge \nProcedures of the Electric Power Supply Association, the PJM Power Providers Group, Calpine \nCorporation, Cogentrix Energy Power Management, LLC, Constellation Energy Generation, LLC, and LS \nPower Development, LLC; Docket Nos. EL25-49-000, AD24-11-000, EL25-20-000 (consolidated) (filed \nApril 22, 2025). “[T]he Commission should issue a finding as expeditiously as possible that the PJM Tarff \nis unjust and unreasonable and unduly discriminatory and preferential.  In addition to making this finding, \nthe Commission should appoint a settlement facilitator and/or settlement judge to actively engage, \nthrough publicly-noticed settlement conferences, with PJM, the Transmission Owners, and any other \ninterested intervenors in a concerted, focused, and good faith effort to resolve this proceeding within a 90 \nday period.  The Commission should direct parties to this settlement process to identify an acceptable \nreplacement rate that reasonably establishes the services, if any, used by co-located loads, and allocates \nany costs to such loads (or the generator serving them) consistent with cost causation principles.,” p. 2."},{"page":4,"startToken":1289,"endToken":1529,"text":"4 \n \nand direction to generation suppliers and large load customers negotiating and \ndeveloping critical co-location contractual arrangements.  \nI.   \nBACKGROUND \nThe Show Cause Order makes an initial finding that the PJM Open Access \nTransmission Tariff (“OATT”) appears to be unjust, unreasonable, and unduly \ndiscriminatory or preferential regarding rules to address co-location configurations \nbetween interconnected generators and co-located load customers. Therefore, the \nCommission directs PJM and its Transmission Owners to either show cause as to why \nthe PJM OATT and related rules and agreements (“the Tariff”) are just and reasonable \nfor the accommodation of co-location configurations without provisions specific to those \narrangements, or to explain what changes are needed to remedy any insufficiency in \nthe clarity or consistency of rates, terms, and conditions available to co-location \narrangements. To ensure a robust record on the co-location issues, the Commission \nhas consolidated the Section 206 Show Cause proceeding with two related dockets – \neach with established and extensive records addressing co-location in PJM. \nIn its Answer, PJM identifies “at least eight potential options for additional large \nload co-location,”11 summarizing each in reference to “key attributes and impacts of \neach configuration and service option on load characteristics, services consumed, \nstudies required, rates, operations, and resource adequacy impacts.”12 This includes \nwhether each co-location option is preferred by PJM and whether Tariff modifications \nare necessary.  \n \n11  \nPJM Answer, p. 5. See also Exhibit A, “Options for Service to Large Loads,” pp. 75-77. \n12  \nId., p. 5."},{"page":5,"startToken":1529,"endToken":1852,"text":"5 \n \nOf the eight options, PJM states that three currently exist under its Tariff – \nnotably two of those are full Network Load and the other is a Behind-the-Meter (“BTM”) \ngeneration configuration that PJM says is not intended for use by large loads and is, in \nfact, capped market-wide because that BTM load does not carry reserves.13 \nFor the remaining five “new” options, PJM notes that Tariff modifications are \nneeded or likely needed. Of those, PJM “prefers” (at a lower level) three – two which \nrequire the large load to be categorized as Network Load (Options 6 and 8) and one \nwhich requires the load to be interruptible so that it may be curtailed to support reliability \nin advance of emergency conditions (Option 7). Notably, PJM explains that its list of \noptions is not exhaustive but rather it is conceptual and thus would benefit from \n“continued input from stakeholders, Commission guidance, and a deadline for \nsubmission of any such proposals either in the context of a section 205 filing or in this \ndocket.”14 \nMore generally, PJM states that “participants involved in co-location \narrangements should pay the costs of any grid services they consume and the \narrangements must be reliable and operationally manageable.”15 Further, PJM \nemphasizes that certain options are dependent on state law, which varies across the \nregion and in some instances may impact certain co-located arrangements.16 In part \nthis discussion of state regulatory regimes leads PJM to seek guidance from the \n \n13  \nId., p. 13, fn 5, “[B]ecause of the potential reliability impacts of this option, use of this option has \nbeen capped at approximately 2000 megawatts (“MW”) of which about 1300 MW are already used. There \nare also performance requirements for generation associated with this configuration. Therefore, large \nload additions located behind generation are not ideal or contemplated under this existing configuration.” \n14  \nId., p. 5. \n15  \nId., p. 4 \n16  \nId., pp. 23, 26-31, and fn 29."},{"page":6,"startToken":1852,"endToken":2121,"text":"6 \n \nCommission and to confer with stakeholders on treatment of certain co-location \nscenarios. \nOf note, the Indicated PJM Transmission Owners submitted an answer stating \nthat PJM’s existing Tariff includes provisions that apply to co-located load arrangements \npursuant to two forms of transmission service – Network Integration Transmission \nService (“Network Service”) and Point-to-Point Transmission Service.17 They contend \nthat co-located end-use loads can only be treated as front of the meter load and \ndesignated as Network Load. \nII. \nCOMMENTS \nA. Certain Restructured States in PJM Have Chosen to Unbundle and Not \nRegulate Transmission; the Commission Has Duly Exercised Its \nJurisdiction Over Transmission to Non-Utility Network Customers Who \nServe Retail Customers \nThe Commission laid out a series of principles in its Order concerning the extent to \nwhich it may exercise jurisdiction over the transmission services used to facilitate co-\nlocated loads. Purporting to agree with the Commission’s nuanced statements in the \nOrder, the Indicated PJM Transmission Owners aver that “[S]tate jurisdiction must be \nrecognized and respected. Consistent with basic principles articulated by the Commission \nin the Show Cause Order, transmission service for co-location arrangements must be \napplied to customers taking service under a state jurisdictional rate filed by an electric \ndistribution company (EDC)/load serving entity (LSE) and approved by the state \nregulator.”18 Yet, the Indicated PJM Transmission Owners evade the reality of states’ \npolicy choices as they relate to retail restructuring, which is that states in many \ncircumstances have no tariff which applies to customers’ transmission rates.  \n \n17  \nSee generally, Answer of the Indicated PJM Transmission Owners. \n18  \nAnswer of the Indicated PJM Transmission Owners, Attachment A, at 2."},{"page":7,"startToken":2121,"endToken":2549,"text":"7 \n \nIn PJM, most states that passed laws and regulations adopting competition at the \nretail level also made the decision to unbundle transmission charges from the regulated \nelectric distribution company tariffs approved by the relevant state public utility \ncommission. In those states, some or all retail customers pay for transmission costs \nthrough a load-serving entity that is not their state-regulated electric distribution \ncompany.19 In those circumstances, there is no tariff that purports to contain the “state \njurisdictional rate filed by an electric distribution company” for transmission service.20 In \nthose states and for those customers, there is no remaining nexus between state \nregulation and the transmission rates established by this Commission. Instead, \ntransmission is exclusively an act perforce of Commission-approved tariffs, whose costs \nare passed to PJM Network Customers (the non-utility load-serving entities, in this case), \nand thereafter to end-use customers as part of their competitive energy supply rates. Just \nas states have decided to leave the retail price of electric energy to be determined by \n \n19  \nFor example, in Maryland, “competitive power supply” includes “unbundled energy, capacity, and \ntransmission services.” Potomac Electric Power Co. (Pepco), Electricity Supply Coordination Tariff, 4th \nRev’d Pg. 1 (emphasis added). \nhttps://www.pepco.com/cdn/assets/v3/assets/bltbb7c204688a1a6a8/blt8d284546a2ec90cd/6687db00996\n4731dae53e697/Pepco_MD_CURRENT_Clean_Supplier_Tariff_updates_effective_070124.pdf \n(accessed Apr. 21, 2025). As Pepco’s own tariff on file at its state regulator makes clear, “The [Maryland] \nCustomer Choice Act gives the customer the option to receive all electricity services (generation, \ntransmission, and distribution) …The [Maryland] Customer Choice Act also gives the customer the option \nto receive generation and transmission services from an alternate Electricity Supplier. If this option is \nchosen, Pepco will continue to provide distribution service…If the customer chooses to receive \ngeneration and transmission service from an Electricity Supplier, the customer should contract with an \nElectricity Supplier.” Pepco, Pepco, General Terms and Conditions for Furnishing Electric Service in \nMaryland, 5th Rev’d Pg. 14. \nhttps://www.pepco.com/cdn/assets/v3/assets/bltbb7c204688a1a6a8/bltb770f5b6804c804c/6512d7d4290\n1d5000d9424f1/MD_Terms_and_Conditions_-_Connection_Fee_effective_090123_FINAL_Filing.pdf \n(accessed Apr. 21, 2025). \n20  \nId. And Maryland is not alone. In Pennsylvania, certain state-approved utility tariffs expressly \ndisavow the application of state-established transmission rates to customers who make a selection of \nalternative provider. See, for example, PECO Rate HT-High Tension Power, which applies transmission \ncharges only for “Transmission Service for Customers Receiving Default Service” Available at: \nhttps://azure-na-\nassets.contentstack.com/v3/assets/blt1b5616c79bacadb4/blt20cfd1b271b632de/67e3f09e9af786d1f4ea1\nb77/Rate_HT_Eff_April_1_2025.pdf (accessed Apr. 16, 2025)."},{"page":8,"startToken":2549,"endToken":2901,"text":"8 \n \ncustomer choice and retail competition through load-serving entities entering into contracts \nwith retail customers, so too have transmission costs that are charged to these load-\nserving entities been recouped through private contract between them and their retail \ncustomers, and not through state-approved rates.21  \nThis situation creates obvious implications for this Commission’s jurisdiction. First, it \nmeans that there are no transmission rates, other than those the Commission has \napproved, which related procedures like interconnection may directly affect.22 Second, \nbecause these are non-rate terms and conditions that regulatory commissions traditionally \nclaim jurisdiction over because they “directly affect” rates, it logically follows that such \ntransmission procedures are regulable by the Commission. Third, these jurisdictional \nquestions depend less on whether there is a co-location arrangement in place, and instead \non whether a state has restructured in a manner that unbundles transmission rates from \nstate-regulated tariffs. \nThe Commission should restate what is obvious – that it does have jurisdiction over \nunbundled transmission rates – and its logical implication, that it has jurisdiction over \nmatters like interconnection that directly affect those rates. The Commission may of course \nalso make clear, as the Supreme Court recognized in New York v. FERC, that there may \nbe some instances when the Commission, even in possession of jurisdiction, does not \nactively exercise it.23  \n \n21  \nThe rates this Commission sets for transmission of course inform those retailers’ costs but does \nnot dictate the retail rate, and for good reason; as one example, certain competitively established energy \nprices that include transmission have contract terms that do not allow adjustments during the term of the \ncontract, even as the Commission’s formula rates adjust over that time.  \n22  \n16 U.S.C. §824d, e; FERC v. Electric Power Supply Assoc., 577 U.S. 260 (2016) (agreeing that \nthe Commission has jurisdiction over compensation for a not directly jurisdictional practice because it \n“directly affects” Commission-established rates). \n23  \nNew York v FERC 535 U.S. 1 (2002), pp. 26-27, (determining that a §206 proceeding could be \nresolved by determining to apply a remedy only to situations wherein transmission rates were unbundled \nfrom utility retail energy sales)."},{"page":9,"startToken":2901,"endToken":3193,"text":"9 \n \nB. PJM’s Answer is Not Responsive to the Commission and Fails to \nDemonstrate its Tariff is Just and Reasonable \n \nAs highlighted in EPSA’s post-conference comments and the extensive record in \nthat administrative proceeding (consolidated in this instant proceeding),24 co-location \narrangements are important bilateral scenarios emerging very quickly to meet the rapid \ndemand growth posed by large load end-users like data centers. This is the precise type of \ninnovation that competitive markets like PJM should foster and support. With numerous \nproceedings pending before the Commission touching on the array of issues raised by and \nrelated to enabling co-location arrangements, the Commission correctly consolidated three \nof those dockets here, offering PJM the opportunity to respond to the Commission’s \ndirectives and establish the needed market and Tariff certainty to allow generation \ndevelopers/operators and new large load customers to move forward and begin \noperations. \nPJM’s Answer has not risen to that challenge, however. While comprehensive, the \nRTO’s interpretation of its Tariff as just and reasonable – despite clear barriers to a range \nof co-located load arrangements – is based on an extremely limited pool of pre-set co-\nlocation configurations. PJM’s agreement that its Tariff supports certain Network Load \nscenarios – two, to be specific (Options 1 and 2) – does not mean that PJM has \nresponded to the task at hand. In the face of myriad formal proceedings, policymaker \ndialogues and inquiries, industry conversations, and press coverage over the past year \nfocused on how to serve significant demand growth spurred by large loads like data \ncenters, PJM’s task is to ensure it has tariff provisions in place that accommodate co-\nlocation arrangements in a range of forms, enabling optionality rather than crystalizing \n \n24  \nPost-Conference Comments of the Electric Power Supply Association, Docket No. AD24-11-000, \n(December 9, 2024)."},{"page":10,"startToken":3193,"endToken":3506,"text":"10 \n \naround pre-set structures. This requires a baseline set of provisions to address the \narrangements that impact the PJM system, allowing space for different types of \narrangements and leaving regulation of certain fully isolated behind-the-meter \narrangements largely to the states in which they locate. PJM’s baseline is critical for this \nregion and will inevitably provide guidance if not a pathway for other regions and markets \non what is needed to accommodate co-location configurations. \nBased on the limitations that PJM has read into its existing Tariff – that it essentially \nprecludes most co-location options other than NITS billed on a gross load basis – EPSA \nand P3 contend that the lack of clarity has rendered it unjust and unreasonable and it is in \nfact unduly discriminatory against certain forms of co-located loads in its current form. To \nrevise the Tariff to meet the stated needs in the Show Cause Order does not require \nextensive provisions added to identify, prescribe, and address every type of co-location \nconfiguration. Rather, PJM’s Tariff must foster and accommodate the innovation that we \nwill see in the coming months and years. PJM should work with stakeholders in a time-\nlimited process to develop those revisions needed to establish the basic rates, terms, and \nconditions of service that would enable and accommodate a broader range of co-location \narrangements while preserving reliability and cost efficiency for all PJM end-use \ncustomers. Frankly, PJM underestimates its ability to support several types of co-located \nloads pursuant to its existing Tariff. Today, much new load and generation enters the PJM \nsystem as Behind-the-Meter arrangements. The RTO needs to give greater consideration \nto how those provisions can be extended to co-located scenarios. \nPJM’s Answer indicates that it has fallen prey to several distractions in its \nconsideration of its Tariff regarding co-located loads. For instance, PJM focuses on how \ndifferent state laws and regulatory regimes impact co-located loads. However, navigating"},{"page":11,"startToken":3506,"endToken":3811,"text":"11 \n \nvarying state requirements is not directly relevant to PJM’s task here, and it misses the \npoint. There undoubtedly will be various state requirements that apply to behind-the-meter \nscenarios that are fully within the authority of the state in which they are located. \nGeneration developers/operators and large load customers will locate in states that will \naccommodate their projects. But at bottom, state requirements across PJM’s footprint are \noutside of PJM’s authority or purview and should not limit or unnecessarily complicate \nPJM’s efforts to advance Tariff revisions subject to federal jurisdiction. \nAdditionally, there are degrees of “isolation” and technical characteristics that must \nbe taken into account when developing just and reasonable rules and rates for co-located \narrangements. PJM’s rules must recognize that there are protective schemes that can \nshield the system from impacts of a large co-located load and, conversely, that can shield \nthe co-located load from system disturbances. The stakeholder work that EPSA and P3 \nrecommend below must acknowledge how these various structures could operate and \ninteract with the system under normal utility practice – and the rules should reflect that \nreality, just as they do for other system participants. It is unduly discriminatory to establish \nunreasonable costs or penalties for varying degrees of isolated co-location scenarios \nbecause protective measures or equipment might hypothetically fail. Large loads like Data \nCenters and AI businesses present new challenges, but they do not vary so significantly \nfrom existing large loads that they can be discriminated against simply due to their size or \nnovelty. This means that large load customers willing to rely solely on their co-located \ngeneration resource should be allowed to do so.  \nAnother distraction has been PJM’s presumption that the Commission has \nsomehow indicated that certain co-location arrangements are impermissible. In its Answer, \nPJM interprets a recent FERC decision – the only formal Commission action to address"},{"page":12,"startToken":3811,"endToken":4108,"text":"12 \n \nco-location issues directly – as prohibitive of certain co-location arrangements and creating \nconfusion regarding capacity constructs and other treatment in PJM’s markets.25 \nFortunately, FERC has just resolved this issue in its rehearing order on the Susquehanna \nAmended Interconnection Services Agreement (“Susquehanna ISA”), in which the \nCommission stated, “[W]e clarify that the [Susquehanna ISA] Rejection Order does not \nprevent entities from filing non-conforming interconnection agreements to address matters \nrelated to a generator serving co-located load, or prejudge any such future filing.”26 That \ncleared up, EPSA and P3 urge PJM to take its blinders off and fully consider the Tariff \nrevisions required to remove barriers to co-location arrangements and, certainly, to \ndismiss the notion that issues related to the Commission’s standards for non-conforming \nISAs pose barriers to co-located load configurations. \nC. The Transmission Owners’ Litigation Position is Anti-Competitive and \nStifles Co-Location Innovation \nIndividual PJM Transmission Owners in this and related proceedings before the \nCommission27 have adopted the litigation position that there are two – and only two – \noptions for co-located arrangements that they will allow: Network Load customers \nbeholden to taking Network or Point-to-Point firm transmission service on the TO’s terms \n(and at their pace), or fully isolated and completely disconnected Behind-the-Meter subject \nto state jurisdiction. In its Answer, PJM has leaned into this vision and, while \nacknowledging up to eight variations for co-location configurations, largely lands where the \nIndicated Transmission Owners have led. The Indicated Transmission Owners position not \nonly violates open access requirements under federal law, but also is reductive, limiting, \n \n25  \nSee e.g., PJM Answer, p. 52, 59. \n26  \nOrder Addressing Arguments on Rehearing and Granting Clarification, In Part, PJM \nInterconnection, L.L.C., Docket No. ER24-2172-002, 191 FERC ¶ 61,025 (issued April 10, 2025), P. 30. \n27  \nSee fns 7, 8 above."},{"page":13,"startToken":4108,"endToken":4393,"text":"13 \n \nand self-serving. Their anti-competitive approach will not help meet these large loads – \nwhich are coming and which serve an urgent national priority – reliably, efficiently, or \naffordably.  \nStakeholders in this proceeding must adopt a shared and rational view about how \ndifferent co-location configurations use and impact the PJM system, and how that may \nvary greatly across potential arrangements; many scenarios will have minimal if not \nminiscule impacts on the system (or use of system services). Co-located parties have \nmade it abundantly clear that they are willing to pay for their system use, which will vary. \nThus, PJM should work with stakeholders to determine what tariff provisions, rate \nschedules, or market rules are required to address and enable different scenarios. That \nmust include assessing netting of charges in a non-discriminatory manner in order to \nreflect cost causation, for instance. Based on the Indicated Transmission Owners’ Answer, \nand disappointingly PJM’s Answer, these critical nuances have been largely disregarded, if \nnot impeded. \nThe key here is that the presumption for Behind-the-Meter co-location \nconfigurations should be that some – perhaps even many or most – do not require full \nNetwork Service for the gross load, and work up from there, based on individual \nconfigurations. Thus, there may be a need to either extend existing Behind-the-Meter \ngeneration provisions and rules to co-located loads or to develop new rules that \nacknowledge a more limited use of the system and PJM/Transmission Owner services. \nPJM’s stated preference for Network Service scenarios is reductive and antithetical to the \ninnovation needed to serve this burgeoning demand. This innovation can (and must) be \nsupported while also ensuring the reliability of the PJM system and designating cost \nresponsibilities based on causation and protecting other customers –priorities for power"},{"page":14,"startToken":4393,"endToken":4672,"text":"14 \n \nsuppliers as well. Though complicated, it may not be as complicated as characterized and \nis certainly in PJM’s wheelhouse as system operator of the nation’s largest organized \npower market. \nD. The Commission Should Direct PJM to Convene a Time-Limited \nSettlement Process for Stakeholders to Develop Tariff Provisions for \nFERC Approval \nRather than digging in heels over Network Load designations or looking to the \nCommission for guidance, PJM should be working with stakeholders to develop the set of \nprovisions needed to address co-location costs, requirements, and participation in the PJM \nmarket and eliminate current Tariff barriers to these arrangements. The Commission \nshould direct PJM and stakeholders to develop a rate design that reasonably addresses \nhow certain configurations use the system – which may be limited or minimal in certain \ncircumstances – and that provides the certainty that co-location developers need while not \nerecting artificial barriers to these critical and innovative business arrangements. \nThere are certain issues that must be prioritized to reach a just and reasonable \nTariff. PJM should address how its Tariff can clearly support load flexibility and how its \nTariff can enable the netting of charges in a non-discriminatory manner, as is done with \nBehind-the-Meter generation and certain industrial loads today. Among the identified \noptions, several could utilize versions of tariff provisions that apply to Behind-the-Meter \ngeneration currently. \nPJM should also consider how its Tariff can enable co-located loads to opt into \nflexible or interruptible transmission services, again noting that accessing netting of \ncharges would support these options. This flexibility will support grid reliability and could \nenable speed to the market – which is a priority for new large load customers and should \nbe a priority for PJM as well."},{"page":15,"startToken":4672,"endToken":4789,"text":"15 \n \nIII. \nCONCLUSION \nWHEREFORE, EPSA and P3 urge the Commission to consider the comments \nherein and establish a 90-day settlement process to allow PJM to work with \nstakeholders on the tariff provisions needed to address co-location arrangements \nsufficiently and fully. \n \nRespectfully submitted,  \n \n \n \n        /s/  N. Bagot \n__________________________ \nNancy Bagot, Senior Vice President \nSharon Theodore, Vice President Regulatory Affairs \nElectric Power Supply Association \n1401 New York Avenue, N.W., Suite 950 \nWashington, D.C. 20005 \n(202) 628-8200 \nNancyB@epsa.org \n \nOn behalf of the Electric Power Supply Association \n \n \n/s/  G. Thomas \n \nGlen Thomas  \nLaura Chappelle  \nDiane Slifer  \nGT Power Group  \n101 Lindenwood Drive, Suite 225  \nMalvern, PA 19355  \n \nOn behalf of The PJM Power Providers Group  \n \n \n \n \n \n \n Dated: April 23, 2025"},{"page":16,"startToken":4789,"endToken":4858,"text":"16 \n \n \nCERTIFICATE OF SERVICE \n \nI hereby certify that on this day I have served via email the foregoing document \nupon each person designated on the Official Service List compiled by the Secretary in \nthis proceeding.  \n \nDated at Washington, D.C., this 23rd day of April, 2025. \n \n \nOn behalf of the Electric Power Supply Association \nand the PJM Power Providers Group \n \n \n \n      /s/  N. Bagot \n __________________________________  \n \n \n                                 Nancy Bagot, Senior Vice President, EPSA"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":2718,"startToken":0,"endToken":759},{"p":2,"at":2718,"title":"Attachment H-1 to unilaterally designate any transmission service to co-located load is Network","method":"printed heading","endPage":4,"endAt":145,"startToken":759,"endToken":1306},{"p":4,"at":145,"title":"I. BACKGROUND","method":"printed heading","endPage":6,"endAt":542,"startToken":1306,"endToken":1927},{"p":6,"at":542,"title":"II. COMMENTS","method":"printed heading","endPage":6,"endAt":557,"startToken":1927,"endToken":1929},{"p":6,"at":557,"title":"A. Certain Restructured States in PJM Have Chosen to Unbundle and Not","method":"printed heading","endPage":9,"endAt":5,"startToken":1929,"endToken":2902},{"p":9,"at":5,"title":"B. PJM’s Answer is Not Responsive to the Commission and Fails to","method":"printed heading","endPage":12,"endAt":939,"startToken":2902,"endToken":3942},{"p":12,"at":939,"title":"C. The Transmission Owners’ Litigation Position is Anti-Competitive and","method":"printed heading","endPage":14,"endAt":198,"startToken":3942,"endToken":4423},{"p":14,"at":198,"title":"D. The Commission Should Direct PJM to Convene a Time-Limited","method":"printed heading","endPage":15,"endAt":6,"startToken":4423,"endToken":4673},{"p":15,"at":6,"title":"III. CONCLUSION","method":"printed heading","endPage":16,"endAt":8,"startToken":4673,"endToken":4790},{"p":16,"at":8,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":16,"endAt":515,"startToken":4790,"endToken":4858}]}