{"document":{"slug":"rec-20250423-5168","title":"Answer of PPL Electric Utilities Corporation to PJM Interconnection, L.L.C.'s et al. Answers","issued":"2025-04-23","accession":"20250423-5168","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"PPL Electric Utilities Corporation","kind":"answer","file":"sources/filings/text/20250423-5168_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250423-5168","tier":"record","sha256":"cc6017a6fb5279beea6a13116734e313e55a9d029725097bcb763719dd3d809e","pages":17,"tokens":5055,"emptyPages":[],"textThemes":["colo","retail","adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":244,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C. et al. \nDocket Nos. EL25-49-000 \nLarge Load Co-Located at Generating \nFacilities \nAD24-11-111 \nConstellation Energy Generation, LLC  \nv.  \nPJM Interconnection, L.L.C. \nEL25-20-000  \n(Consolidated) \n \nANSWER OF PPL ELECTRIC UTILTIIES CORPORATION \n \nPursuant to Rules 212 and 213 of the Rules and Regulations of the Federal Energy Regu-\nlatory Commission (“FERC” or “Commission”),1 and pursuant to the instructions in the Order to \nShow Cause,2 PPL Electric Utilities Corporation (“PPL Electric”) hereby submits this Answer to \nthe PJM Answer3 as well as other answers submitted in this docket.4 \n \n1 18 C.F.R. §§ 385.212, 213 (2025).  \n2 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115, ¶ 87 (Feb. 20, 2025) (“Order to Show Cause”) (in-\nstructing “interested entities” to respond within 30 days of PJM and the transmission owners’ filings “ad-\ndressing either or both of: (1) whether the existing Tariff remains just and reasonable and not unduly dis-\ncriminatory or preferential; and (2) if not, what changes to the Tariff should be implemented as replace-\nment rates.”).  \n3 PJM Interconnection, L.L.C., Answer of PJM Interconnection, L.L.C., Docket Nos. EL25-49-000 et al. \n(Mar. 24, 2025) (“PJM Answer”).  \n4 PPL Electric also responds to Answers submitted by PSE&G, PJM Interconnection, L.L.C., et al., Re-\nsponse of Public Service Electric and Gas Company to the Order to Show Cause, Docket Nos. EL25-49 et"},{"page":2,"startToken":244,"endToken":567,"text":"1 \n \nI. \nINTRODUCTION \n \nThe electric industry is now well into its second year of intense focus on large loads co-\nlocating with wholesale generators. The Commission has numerous dockets, open and closed, on \nthe subject and has held an all-day technical conference where it heard detailed testimony from \nindustry experts on all sides of the question. Although the technical, jurisdictional, and economic \nissues are complex, the Commission can best proceed if it follows two hopefully non-controver-\nsial “North Star” principles:  \n(1) \nProtect the safety and reliability of the bulk electric system; and  \n(2) \nPrevent subsidization of new loads by network customers.   \nGuided by these principles, and utilizing the extensive records before it, the Commission can \ntake action to clarify its rules around behind-the-meter loads at regulated wholesale generators.  \n \nIn its Answer, PJM brings its experience—developed over several years of grappling \nwith these issues—to the myriad questions presented by co-location. PJM recognizes that there \nare limits to its ability to stop behind-the-meter load from interconnecting to the wholesale gen-\nerators interconnected with the grid. As a federally regulated public utility, PJM has no jurisdic-\ntion over these retail questions. In several PJM states, state law allows such behind-the-meter re-\ntail load. Instead, PJM focuses on what it can control: its own Tariff. Specifically, PJM defends \nthe justness and reasonableness of the Tariff, but it recognizes that the rules of the road can be \nunclear in certain cases. It outlines eight potential Options for large loads co-located with whole-\nsale generators. Four of these are already permitted by the Tariff (but may still benefit from \n \nal. (Mar. 24, 2025) (“PSE&G Answer”) and AES Ohio, PJM Interconnection, L.L.C., et al., Answer of \nthe Dayton Power and Light Company d/b/a AES Ohio to Order Instituting Proceeding Under Section \n206 of the Federal Power Act and Consolidating with Other Proceedings, Docket Nos. EL25-49, et al. \n(Mar. 24, 2025) (“AES Ohio Answer”)."},{"page":3,"startToken":567,"endToken":866,"text":"2 \n \nclarification when applied to behind-the-meter load) and four would require some degree of \namendment to the Tariff. Not all are equally desirable. In fact, PJM explicitly says that it does \nnot prefer the options that relieve behind-the-meter load of its network obligations. It also ex-\nplains why: this load cannot be fully isolated and inevitably brings operational risk to the system. \nNevertheless, such accommodation may be required by state law. PJM is obligated to do so in a \nway that minimizes these risks.  \n \nPPL Electric agrees with PJM. The PJM Tariff is already just and reasonable. But, there \nare clearly areas where the PJM Tariff (and other FERC-regulated tariffs) could benefit from in-\ncreased clarity and FERC guidance. Because the Commission has shown skepticism toward ad-\ndressing these questions through bespoke language in non-conforming interconnection agree-\nments, it is appropriate to set these rules of the road directly in the tariffs. The Commission \nshould not do so by mandating changes through this § 206 proceeding, but instead should issue \ndetailed guiding principles that PJM and other tariff administrators can incorporate utilizing their \n§ 205 authority. PPL Electric believes that these rules can, and should, accommodate behind-the-\nmeter load where required by state law, without violating the North Star principles laid out \nabove.  \nII. \nBACKGROUND \n \nPPL Electric is a Pennsylvania transmission and distribution utility, and a founding mem-\nber of PJM. PPL Electric’s interest in co-located load was laid out in detail in its Post-Technical \nConference Comments in Docket No. AD24-11, consolidated into this docket and incorporated \nby reference here.5 In addition to its general interest as a PJM transmission owner and market \n \n5 Large Loads Co-Located at Generating Facilities, Post Technical Conference Comments of PPL Elec-\ntric Utilities Corporation (“PPL Electric TC Comments”), Docket No. AD24-11-000 (Dec. 9, 2024)."},{"page":4,"startToken":866,"endToken":1147,"text":"3 \n \nparticipant, PPL Electric shares an electrical interconnection with its former affiliate at the Sus-\nquehanna Steam Electric Station (“Susquehanna”). For the last five years, Susquehanna has been \nworking, at first alone and later with contractual partners, to develop on-site, co-located load at \nits generation facility. Importantly, the load at Susquehanna, initially a crypto-mining facility and \nmore recently a large data center, was installed behind the Susquehanna meter. Rather than being \ninterconnected with the local utility, PPL Electric, and purchasing from a PJM wholesale sup-\nplier, as is normal for large customers in Pennsylvania, the customer instead purchases power di-\nrectly from Susquehanna in a private transaction.  \n \nSusquehanna and its parent company Talen Energy, as well as other generators, have \nlong sought clarity from PJM related to how its Tariff would treat questions of behind-the-meter \nload. In a familiar, if unproductive, process, PJM presented questions to its stakeholders, noting \nthe Tariff lacked clarity and presenting a problem statement and issue charge.6 The stakeholder \nprocess was unable to come to consensus on any contentious issues and largely went nowhere.7 \nInstead, Susquehanna informed PJM and PPL Electric of the changes to its wholesale intercon-\nnection caused by the behind-the-meter load and worked with them to accommodate those \nchanges in its Interconnection Service Agreement (the “Susquehanna ISA”).  \n \nAfter a few years, PJM unilaterally developed and posted a Guidance Document on Co-\nLocated Load Configurations in March 2024.8 The Guidance Document, which was clearly in-\nformed by lessons learned at Susquehanna, allowed PJM to express its clear, consistent prefer-\nences regarding co-located load:  \n \n6 See generally, PPL Electric TC Comments, Note 5 at 6–7.  \n7 Id.  \n8 Id. at 6–7."},{"page":5,"startToken":1147,"endToken":1481,"text":"4 \n \n• \nIt should be served in front of the meter.  \n• \nBehind-the-meter load will not be considered network load and will not receive \nthe benefits of network service. Generators installing behind-the-meter load will \nhave to reduce their capacity injection rights and load must have system protec-\ntions in place to protect the transmission system.  \n• \nNon-network load cannot become network load without going through the various \nstudy processes.9  \nPPL Electric shared many of the goals of the Guidance Document and supported PJM’s efforts to \nincorporate its guidance into the Susquehanna ISA. Following the November 1, 2024, denial of \nthe Susquehanna ISA and the technical conference on co-located load, PJM withdrew its Guid-\nance Document pending FERC action in this matter.10   \n \nThe instant docket was initiated on February 20, 2025, when FERC issued the Order to \nShow Cause11 and consolidated several other dockets for further consideration. Using its § 206 \nauthority, the Commission found that the PJM Tariff “appears to be unjust, unreasonable, unduly \ndiscriminatory or preferential” and directed PJM and the PJM Transmission Owners to show \ncause why the Tariff remains just and reasonable “without provisions addressing with sufficient \n \n9 See PJM Guidance on Co-located Load Configurations (Updated Apr. 17, 2024), available at \nhttps://www.pjm.com/-/media/markets-ops/rpm/rpm-auction-info/pjm-guidance-on-co-located-load.ashx. \nSee also, Co-Located Load Guidance, MIC Presentation (Apr. 3, 2024), available at \nhttps://www.pjm.com/-/media/commit-tees-groups/committees/mic/2024/20240403/20240403-item-07---\nco-located-load-guidance.ashx, and MRC Presentation (Apr. 25, 2024), available at \nhttps://www.pjm.com/-/media/committees-groups/commit-tees/mrc/2024/20240425/20240425-item-09---\n1-co-located-load-guidance---presentation.ashx.   \n10 After several changes to the Susquehanna ISA were accepted without incident, a broader set of changes \nwas protested and ultimately rejected by the Commission. See Order Rejecting Amendments to Intercon-\nnection Service Agreement, 189 FERC ¶ 61,078, Docket No. ER21-2172 (Nov. 1, 2024) (“ISA Rejection \nOrder”); upheld on rehearing, Order Addressing Argument on Rehearing and Granting Clarification, in \nPart, 191 FERC ¶ 61,025 (Apr. 10, 2025).  \n11 Order to Show Cause, Note 2, supra."},{"page":6,"startToken":1481,"endToken":1782,"text":"5 \n \nclarity or consistency the rates, terms, and conditions of service that apply to co-location arrange-\nments.”12 Alternatively, they were to “explain what changes … would remedy the identified con-\ncerns.”13  \n \nPJM responded to the Order to Show Cause on March 24 with an Answer stating that the \nTariff was just and reasonable, a detailed analysis of the policy issues related to co-located load \n(still largely reflective of the Guidance Document principles), and a presentation of potential \npaths forward. PJM stated that its approach to large loads, co-located or not, focuses on (1) re-\nsource adequacy, (2) reliable operations, (3) facilitating load integration, and (4) providing infor-\nmation to support equitable transmission costs.14 PJM’s preference remains that all load be con-\nsidered Network Load. PJM conceded that there is some uncertainty in the Tariff and there may \nbe call for clarification, especially if states allow co-location of retail load behind the generation \nmeters.15 The PJM Answer provides eight Options in its Answer. It recognizes that not all are \nequally desirable and some may be prohibited, at least in some states. In many cases, more than \none option can function simultaneously. The first three and eighth options are already permitted \nby the Tariff while the other four will likely require amendments.  \n \nThe PJM Transmission Owners also responded to the Show Cause Order. PPL Electric \njoined nearly every other PJM Transmission Owner in a joint Answer defending the justness and \nreasonableness of the PJM Tariff and rejecting subsidization by network load. As demonstrated \nin the response being filed today by the same group of transmission owners, that is the strong, \nconsistent view of the overwhelming majority of the transmission owners in PJM. Only one, \n \n12 Id. at ¶ 2.  \n13 Id.  \n14 PJM Answer at 3. \n15 PJM Answer at 4."},{"page":7,"startToken":1782,"endToken":2033,"text":"6 \n \nPSE&G, disagreed with this core position, arguing instead that co-located load should receive a \ndiscount on transmission service because it does not burden the grid the same as normal network \nload.16  \n \nPPL Electric remains in agreement with the other PJM Transmission Owners in defend-\ning the justness and reasonableness of the PJM Tariff and joins their reply being filed today. PPL \nElectric writes separately to respond more directly to PJM’s outlining of the jurisdictional and \npolicy issues and the various options available. Specifically, PPL Electric’s experience at Sus-\nquehanna gives it unique insight into the pitfalls of Options 4 and 5. While continuing to defend \nthe justness and reasonableness of the PJM Tariff, PPL Electric agrees that FERC should provide \nadditional clarity as to how federally regulated utilities should treat behind-the-meter co-located \nload where state law allows it.  \nIII. \nANSWER \nA. \nResponses to PJM \n \nPPL Electric’s experience with the Susquehanna ISA and with the failure of the stake-\nholder process to establish rules for behind-the-meter load brings it to the same conclusion drawn \nby PJM: “What PJM and the industry need now is Commission guidance on a path forward \nbased on the record developed in this proceeding. The record will support a finding that PJM’s \nexisting Tariff remains just and reasonable, although improvements and clarifications may be ap-\npropriate based on Commission guidance.”17 \n \n16 PSE&G Answer at 15. Other transmission owners filed shorter responses without detailed substantive \ndiscussion of co-located load.  \n17 PJM Answer at 4."},{"page":8,"startToken":2033,"endToken":2477,"text":"7 \n \n \nAs an initial matter, the PJM Answer accurately pinpoints the potential jurisdictional \ngaps that led to the situation at Susquehanna.18 Under prevailing Pennsylvania law, a single gen-\nerator providing service to a single customer is not a public utility and is not subject to the retail \njurisdiction of the Pennsylvania Public Utilities Commission.19 As this Commission is undoubt-\nedly aware, public utilities throughout the country have a long history of vigorously defending \ntheir state franchises to provide retail service. However, in this case, PPL Electric was not con-\nsulted or given the opportunity to serve what soon became (by a large margin) the single largest \nretail customer in its service territory.20 Instead, that behind-the-meter service was simply estab-\nlished by private contract. Sovereign states can allow, explicitly or implicitly, behind-the-meter \nload at generators. However, as PJM points out, the Commission retains jurisdiction over the \ntransmission system and the interstate energy markets.21 While it cannot (or at least should not) \ninfringe on the states’ jurisdiction over the behind-the-meter load itself, the Commission abso-\nlutely can take action to ensure its North Star principles that such facilities do not (1) impact the \nsafety or reliability of the bulk electric system, and (2) do not create conditions for improper sub-\nsidization by network customers. PJM and PPL Electric sought to use the limited tools available \n \n18 See PJM Answer at 27–28.  \n19 See PJM Interconnection, L.L.C., Comments of the Pennsylvania Public Utility Commission, Docket \nNos. EL25-49-000 et al. (Apr. 22, 2025) at 3 (“it is well-established in Pennsylvania law that when elec-\ntric service is provided to a ‘defined, privileged and limited group’ it is not provided ‘to or for the pub-\nlic,’” quoting Drexelbrook Assocs. v. Pennsylvania Pub. Util. Comm’n, 212 A.2d 237, 240 (Pa. 1965)).  \nPPL Electric is of course aware of the age of some of the Pennsylvania judicial rulings that set forth this \nlegal position and the significant developments in electric service and electricity markets that have \nchanged the underlying fact patterns since then. To PPL Electric’s knowledge, no Pennsylvania court has \nbeen presented with the question of retail jurisdiction over a large generator located behind the meter of a \nwholesale generator. All parties should proceed with the understanding that state law can change based on \nthese new conditions.  \n20 The fact pattern laid out in the Show Cause Order on this point is not entirely correct. PPL Electric did \nnot “allow[] a generator in its service territory to enter into a co-location arrangement.” Show Cause Or-\nder at ¶ 75. PPL Electric had no ability to withhold permission.  \n21 PJM Answer at 29–31."},{"page":9,"startToken":2477,"endToken":2762,"text":"8 \n \nto them, specifically the non-standard terms and conditions schedule of the Susquehanna ISA, to \nimprove an initially bad setup. Following the Commission’s denial of that effort, PPL Electric \nremains in agreement with PJM that the Commission should clarify its rules to ensure the tariffs \nit regulates do not allow behind-the-meter load to create the negative impact on the transmission \nsystem that existed at Susquehanna.  \nPPL Electric responds to the Options laid out in the PJM Answer below:  \n1. \nOptions 1 – 3  \n \nAs PJM recognizes, Options 1 – 3 already exist in the Tariff and are available options for \nload seeking to interconnect. PPL Electric agrees that Option 1 (which can be considered the de-\nfault for all load in its territory) and Option 2 (where load is at the same point of interconnection \nas a generator but metered separately) are the preferred options. They do not impact safety or re-\nliability and do not create any subsidization concerns—although PJM’s caveats regarding the \nscale of data center load sharing a point of interconnection are important.22 Neither Option re-\nquires any tariff changes to accommodate.  \n \nAs laid out by PJM in Option 3, the PJM Tariff already accommodates generation behind \nthe meter of network load. This arrangement is more complicated than “normal” load purchasing \nexclusively from the PJM markets, but behind-the-meter generation has generally proven to \nwork within the existing system and PPL Electric is not opposed to it. As PJM recognizes, be-\nhind the meter generation at an existing load differs both in kind and degree from load appearing \nbehind the meter of an existing generator, especially when attempted at the scale of a data center.  \n \n22 See PJM Answer at 13, Note 5."},{"page":10,"startToken":2762,"endToken":3120,"text":"9 \n \n2. \nOptions 4, 5 \n \nPJM’s Options 4 and 5 reflect a good faith attempt to accommodate a behind-the-meter \nload at an existing wholesale generator. PJM considers them “less preferred,” but recognizes that \nwhere retail load interconnects and is metered is a question of state law, beyond the ability of the \nlocal utility, regional transmission organization, or FERC to control.23 Specifically, these options \nreflect lessons learned through the Susquehanna ISA negotiations. Incorporating Options 4 and \npotentially 5 into the PJM Tariff would largely formalize the ad-hoc structure at Susquehanna \nwithout the need to reopen the most controversial portions of the Susquehanna ISA (although \ncertain protections and physical interconnection changes may still need to be incorporated into \nthat agreement). Making these tariff changes with no negative impact on reliability or cost subsi-\ndization will be difficult though, as behind-the-meter load is fundamentally less visible and less \ninteractive with the grid than “normal” front-of-meter load.24 PPL Electric thus agrees that these \noptions are not the preferred way forward, but may still be necessary where state law requires ac-\ncommodation of behind-the-meter load.25  \n \nOption 4 would accommodate co-located load behind the meter of a wholesale generator. \nIt requires “protection mechanisms … to prevent delivery of energy from the grid to serve the \nload in the event the generation is offline.”26 Ensuring such protection mechanisms were in place \nwas PPL Electric’s goal in amending the Susquehanna ISA in 2024.27 Specifically, the \n \n23 See PJM Answer at 14.  \n24 See PPL Electric TC Comments at 9–12 (large loads should interconnect in front of the meter to max-\nimize reliability and minimize cost shifts).  \n25 See id. at 12–15 (the Commission cannot regulate the retail relationship, but should set wholesale tariff \nrules that remove the incentive to locate behind the meter).  \n26 PJM Answer at 14. \n27 See PJM Interconnection, L.L.C., Motion for Leave to Answer Protest and Answer of PPL Electric \nUtilities Corporation, Docket No. ER24-2172 (Jul. 12, 2024) (“PPL ISA Answer”) at 3 (“PPL’s main goal \nin amending the ISA was to ensure the reliability of the PJM transmission system and to protect PPL’s"},{"page":11,"startToken":3120,"endToken":3541,"text":"10 \n \nunamended agreement did not adequately provide for real-time metering and telemetry of the be-\nhind-the-meter load, did not prevent additional backup generators being interconnected, did not \nadequately ensure separation of load in the case of loss of generation, did not condition recon-\nnection of the load on PJM or PPL Electric’s approval following an outage, and did not require \nPPL Electric be given an opportunity to review changes to the operating procedure of the behind-\nthe-meter load, among others.28 These ISA changes were necessary because the configuration at \nSusquehanna (and envisioned by PJM as Option 4) “carries operational risk.”29 Specifically, this \nconfiguration risks “large, unplanned, unmodeled” load appearing instantaneously on the system \nif the protection mechanisms fail.30 At the scale of a data center, this risk is significant and the \nCommission’s concern with such a setup is well-placed.31  \n \nBecause the Commission denied the amendments to the Susquehanna ISA on other \ngrounds,32 the PJM Tariff still does not include sufficient protections against load appearing \n \ncustomers.”). See also, PJM Interconnection, L.L.C., Motion for Leave to Answer and Answer of PPL \nElectric Utilities Corporation, Docket No. ER24-2172 (Oct. 9, 2024) at 2–3 (“PPL’s position in favor of \nthe ISA amendments at issue here should not be interpreted as anything other than its belief that those \namendments improve the reliability of the transmission grid and protect PPL’s and other customers from \npotential negative effects caused by the customer’s behind-the-meter facility.”).  \n28 See PPL ISA Answer at 4–6.  \n29 PJM Answer at 14.  \n30 PPL Electric TC Comments at 10–11.  \n31 See Order to Show Cause at ¶ 83 (“We are also concerned about the reliability and resource adequacy \nimplications of co-location arrangements. … we are concerned that the Tariff may be unjust and unrea-\nsonable and unduly discriminatory or preferential insofar as it lacks rules necessary to provide PJM with \nsufficient information to perform appropriate analysis to ensure reliable system operations given the char-\nacteristics of co-location arrangements.”). \n32 ISA Rejection Order at ¶ 87 (finding the proposed provisions that “mirror provisions that PJM has in-\ncluded in the PJM Guidance Document, do not meet the requisite standard” for non-conforming provi-\nsions), id. at ¶ 88 (leaving “multiple important questions unresolved,” including the specific non-con-\nforming provisions proposed in the Susquehanna ISA); but see Phillips (dissenting) at ¶ 1 (“we are reject-\ning protections that the interconnected transmission owner says will enhance reliability while also creat-\ning unnecessary roadblocks to an industry that is necessary for our national security”)."},{"page":12,"startToken":3541,"endToken":3804,"text":"11 \n \ninstantaneously on the system due to an inadvertent loss of generation in a behind-the-meter load \narrangement as laid out in Option 4 or as continues to exist at Susquehanna. PPL Electric thus \nagrees strongly with PJM that “Tariff modifications would be needed” to move forward with Op-\ntion 4.33 Should the Commission agree, it should focus on its clear jurisdiction over the genera-\ntor—not the retail behind-the-meter load itself which is regulated by the state. The PJM Tariff \ncan be amended to incorporate the North Star principles, compelling the generator to prevent any \nimpact on the safety or reliability of the transmission grid and to prevent subsidization of the \nload by network customers. In all likelihood, these protections will reduce the incentive for large \nloads to locate behind-the-meter in the first place, but the option will formally remain for them in \nstates that allow it.  \n \nPPL Electric’s concerns with behind-the-meter load are perhaps even more acute under \nOption 5, where the load can also “receive back-up service from the grid.”34 PJM insists that any \nsuch approval to “take back-up power from the grid would be subject to conditions” related to \nreliability, and would require “real-time, bespoke operational decision-making to determine \nwhether load can continue to be served.”35 Imposing these conditions and establishing the au-\nthority for this decision-making would clearly require Tariff changes. Under Pennsylvania law \nPPL Electric cannot deny backup service properly requested under its General Tariff, which \n \n33 Such modifications could include changes to the pro forma ISA.  \n34 PJM Answer at 14–15.  \n35 Id."},{"page":13,"startToken":3804,"endToken":4208,"text":"12 \n \nallows for both backup36 and temporary37 service. These rules also apply to behind-the-meter \ncustomers who can properly take service under the General Tariff (although doing so requires a \nmeter, changing the nature of the load). To be sure, for PJM to condition such service as pro-\nposed, “Tariff modifications would be needed.”38  \n \nPPL Electric reiterates that Options 4 and 5 are not preferred. Even if properly governed \nunder the PJM Tariff, they offer less reliability than other methods of interconnecting co-located \nload. They also risk subsidization of the behind-the-meter load by network customers, as was \nhighlighted by protests in the Susquehanna ISA docket39 and commentators to the technical con-\nference, including PPL Electric.40 Nevertheless, Pennsylvania and some other PJM states allow \nat least some form of behind-the-meter load and the PJM Tariff may need clarification or amend-\nment to accommodate them. PPL Electric thus joins PJM in calling for increased clarity from the \nCommission here.  \n \n36 PPL Electric Utilities Corporation General Tariff, Rule 6, available at https://www.pplelectric.com/-\n/media/PPLElectric/At-Your-Service/Docs/Current-Electric-Tariff/rule6.pdf (providing for “[s]ervice to \ncustomers who have another source of power which can be substituted for Company’s service for any of \ncustomer's operations”).  \n37 PPL Electric Utilities Corporation General Tariff, Rule 7, available at https://www.pplelectric.com/-\n/media/PPLElectric/At-Your-Service/Docs/Current-Electric-Tariff/rule7.pdf (providing for “[t]emporary \nservice … for less than one year or for a year or more when Company must install facilities that will be \nused solely for a service that is known to be limited in duration.”).   \n38 PJM Answer at 15.  \n39 See, e.g., PJM Interconnection, L.L.C., Declaration of John J. Reed and Danielle S. Powers in Support \nof Protest of Exelon Corporation and American Electric Power Services Corporation, Docket No. ER24-\n2172 (Jun. 24, 2024) at ¶ 9 (“If this proposed Co-Located Load is permitted to avoid significant costs, it \ncould encourage other generators and large consumers to pursue similar arrangements, leading to wide-\nspread cross-subsidization issues and leaving unresolved questions of cost responsibility for grid use.”).  \n40 See, e.g., PPL Electric TC Comments at 14 (“An equitable energy market requires that this load not re-\nceive power and grid services subsidized by other customers on the grid. It also requires that the generator \nnot be able to capture a portion of this subsidy by selling at a premium to its private customer.)."},{"page":14,"startToken":4208,"endToken":4557,"text":"13 \n \n3. \nOptions 6–8  \nPJM’s other Options are less controversial, but are also less directly relevant to the ques-\ntions raised regarding how the PJM Tariff should address co-located load behind-the-meter of a \nlarge wholesale generator. All three remaining Options instead primarily focus on the larger is-\nsue of resource adequacy. As PPL Electric explained in its Post-Technical Conference Com-\nments, data center growth is critical for economic development and will require new generation \nand market adjustments.41  \nOption 6 would incentivize data centers to “Bring Your Own Generation” by speeding \nthe interconnection process for those new generators if they serve as capacity resources. This \nproposal mirrors the Reliability Resource Initiative (“RRI”) currently in progress.42 PJM is fac-\ning significant resource adequacy concerns and speeding the interconnection process for genera-\ntion resources that can help is likely to be a beneficial step. Although this option appears to be \nindependent from questions around co-located load, PPL Electric generally supports it.  \n \nOption 7 would allow large loads to integrate as non-capacity backed load and avoid ca-\npacity costs so long as the load is willing to curtail earlier in the stack to support reliability dur-\ning emergency conditions. PPL Electric reserves comment on this option as there are not suffi-\ncient details in the PJM filing to understand the potential changes necessary to the PJM Tariff or \nany potential conflicts with state law. Finally, Option 8 recognizes that co-located loads have the \nability to provide demand response under the existing PJM Tariff and offers potential changes to \n \n41 See id. at 1–2 (“Robust data center development is critical to keeping the United States at the forefront \nof information technology development and to protect national security.”), 15 (“new data centers will tie \nup generation and impact resource adequacy regardless of whether they are located behind-the-meter”).  \n42 See PJM Interconnection, L.L.C., Tariff Revisions for Reliability Resource Initiative, Docket No. \nER25-712 (Dec. 13, 2024); accepted Order Accepting Tariff Revisions, 190 FERC ¶ 61,084 (Feb. 11, \n2025) (speeding interconnection process for certain capacity additions by adding them to existing queue)."},{"page":15,"startToken":4557,"endToken":4871,"text":"14 \n \nthe rules that could make this more attractive. Again, PPL Electric reserves comment as there are \nnot sufficient details to understand the proposed changes from the existing rules under the PJM \nTariff or their potential impacts on the transmission system and energy markets.  \nB. \nResponses to PSEG  \n \nPSE&G argues that the Commission should apply cost allocation rules developed in dis-\nputes between different transmission zones to the newly presented question of how transmission \ncosts should be allocated among retail customers in a single transmission zone.43 It argues such a \nrule would require transmission charges “be assessed based on a party’s ‘actual use’ of the trans-\nmission system.44 This would trample on state jurisdiction over retail rates, which governs allo-\ncation of transmission costs to retail customers. It would require FERC to recognize a new class \nof retail customer and then direct the states how to assign transmission costs (assessed to the \ntransmission zone via Schedule 12 of the PJM Tariff) among these retail rate classes. PSE&G’s \nproposal would also violate a longstanding tenet of FERC law, which “consistently reject[s] cost \ncausation arguments made by network customers that [seek] to lower their load ratio share based \non actual use of the transmission system.”45 The Commission should reject this argument.  \nC. \nResponse to AES Ohio \nPPL Electric agrees with AES Ohio that, while the PJM Tariff “remains just and reasona-\nble as to service … co-located load take[s],” there are potentially other solutions, especially in \nstates willing to accommodate behind-the-meter load.46 As explained above, state law \n \n43 PSE&G Answer at 11 and Note 24.  \n44 Id. at 11.  \n45 National Railroad Passenger Corporation v. PPL Electric Utilities Corporation and PJM Interconnec-\ntion, L.L.C., Order Denying Complaint, 171 FERC ¶ 61,237, Docket No. EL19-78 (Jun. 18, 2020) at ¶ 41.  \n46 AES Ohio Answer at 1–2."},{"page":16,"startToken":4871,"endToken":5008,"text":"15 \n \ndetermines whether or not to allow behind-the-meter retail load. The PJM Tariff must accommo-\ndate whatever choice the states make, but in doing so it must ensure (a) the safety and reliability \nof the transmission system is protected, and (b) that costs are not transferred from the behind the \nmeter load to the network load.  \nIV. \nCONCLUSION \n \nFor the reasons stated above and in the Comments of the Indicated PJM Transmission \nOwners, PPL Electric respectfully requests the Commission accept this Answer, find the existing \nPJM Tariff just and reasonable, and provide additional clarification regarding the treatment of \nbehind-the-meter co-located load as it determines necessary.  \n \n \nSteven M. Nadel \nSenior Counsel \nPPL Services Corp.  \n645 Hamilton Street, Suite 601 \nAllentown, PA 18101 \nTel. 610.774.4775   \nSMNadel@pplweb.com \n \nCounsel for PPL Electric Utilities Corp. \nApril 23, 2025"},{"page":17,"startToken":5008,"endToken":5055,"text":"16 \n \nCERTIFICATE OF SERVICE \nI hereby certify that I have this day served the foregoing document upon each person des-\nignated on the official service list compiled by the Secretary in this proceeding. \nDated at Allentown, PA this 23rd day of April, 2025. \n \n \nJohn Feller \n \nJohn Feller"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":5,"startToken":0,"endToken":245},{"p":2,"at":5,"title":"I. INTRODUCTION","method":"printed heading","endPage":3,"endAt":1388,"startToken":245,"endToken":778},{"p":3,"at":1388,"title":"II. BACKGROUND","method":"printed heading","endPage":7,"endAt":921,"startToken":778,"endToken":1923},{"p":7,"at":921,"title":"III. ANSWER","method":"printed heading","endPage":7,"endAt":935,"startToken":1923,"endToken":1925},{"p":7,"at":935,"title":"A. Responses to PJM","method":"printed heading","endPage":15,"endAt":285,"startToken":1925,"endToken":4601},{"p":15,"at":285,"title":"B. Responses to PSEG","method":"printed heading","endPage":15,"endAt":1366,"startToken":4601,"endToken":4772},{"p":15,"at":1366,"title":"C. Response to AES Ohio","method":"printed heading","endPage":16,"endAt":336,"startToken":4772,"endToken":4927},{"p":16,"at":336,"title":"IV. CONCLUSION","method":"printed heading","endPage":17,"endAt":6,"startToken":4927,"endToken":5009},{"p":17,"at":6,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":17,"endAt":288,"startToken":5009,"endToken":5055}]}