{"document":{"slug":"rec-20250423-5175","title":"Comments of Edison Electric Institute in response to FERC’s Order issued on 02/20/2025","issued":"2025-04-23","accession":"20250423-5175","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Edison Electric Institute","kind":"comments","file":"sources/filings/text/20250423-5175_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250423-5175","tier":"record","sha256":"03451d8a3c98b2af6253f7876b937a0faf81539abf3da69ed7360c547c3d6956","pages":9,"tokens":2147,"emptyPages":[],"textThemes":["colo"]},"pages":[{"page":1,"startToken":0,"endToken":243,"text":"1 \n \n UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \nPJM Interconnection, L.L.C., \net al.  \n) \nDocket No. EL25-49-000  \nLarge Loads Co-Located at \nGenerating Facilities  \n \n) \n \nDocket No. AD24-11-000  \nConstellation Energy \nGeneration, LLC  \nv.  \nPJM Interconnection, L.L.C.  \n \n) \n \nDocket No. EL25-20-000  \n(consolidated)  \n \n \nCOMMENTS OF THE EDISON ELECTRIC INSTITUTE  \n \n \n \nPursuant to Rules 206 and 213 of the Rules of Practice and Procedure of the Federal \nEnergy Regulatory Commission (“FERC” or “Commission”),1 the Edison Electric Institute \n(“EEI”) respectfully submits the following comments in response to FERC’s order issued on \nFebruary 20, 2025 (“Show Cause Order”) instituting this proceeding under section 206 of the \nFederal Power Act (“FPA”)2 and consolidating it with other proceedings.3  In the Show Cause \nOrder, the Commission found that PJM Interconnection, L.L.C.’s (“PJM”) Tariff appears to be \nunjust, unreasonable, unduly discriminatory or preferential with respect to its treatment of issues \nrelated to large loads co-located at generating facilities.  FERC directed PJM and the \ntransmission owners of PJM (“PJM TOs”) to either: (1) show cause as to why the PJM Tariff \nremains just and reasonable and not unduly discriminatory or preferential without provisions \naddressing with sufficient clarity or consistency the rates, terms, and conditions of service that \n \n1 18 C.F.R. § 385.206 (2012); see also 18 C.F.R. § 385.213 (2012). \n2 16 U.S.C. § 824e (2006). \n3 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115 (2025) (“Show Cause Order”)."},{"page":2,"startToken":243,"endToken":529,"text":"2 \n \napply to co-location arrangements; or (2) explain what changes to the PJM Tariff would remedy \nthe identified concerns if the Commission were to determine that the PJM Tariff has in fact \nbecome unjust and unreasonable or unduly discriminatory or preferential and, therefore, \nproceeds to establish a replacement PJM Tariff.  PJM, a group of indicated PJM TOs, and Public \nService Electric and Gas Company (PSE&G) filed responses to the Show Cause Order on March \n24, 2025. \n \nEEI is the association that represents all investor-owned electric companies in the United \nStates.  EEI members provide electricity for nearly 250 million Americans and operate in all 50 \nstates and the District of Columbia.  The electric power industry supports more than seven \nmillion jobs in communities across the United States.  EEI’s member companies own and \noperate generation, transmission, and distribution facilities in regions all throughout the country.  \nEEI members are focused on keeping customer bills as low as possible, and these generation, \ntransmission, and distribution facilities are helping to meet rising demand while creating good-\npaying jobs and a cleaner, resilient, and affordable energy future for the customers and \ncommunities they serve.  Accordingly, EEI can provide a broad-based perspective on the issues \nraised in the Show Cause Order. \nI. \nBACKGROUND \nThe electric grid has long provided an extraordinary platform to reliably and affordably \nserve the nation’s electric customers.  Among other things, the electric grid supports and \nfacilitates the deployment of resilient, reliable sources of power, at scale, to address customers’ \nneeds.  After an extended period of relatively low demand growth rates, the country’s electric \nsector has entered an era of rapid transformation and unprecedented and sustained load growth.  \nThe North American Electric Reliability Corporation (“NERC”), among others, has observed"},{"page":3,"startToken":529,"endToken":915,"text":"3 \n \nthat load and demand on the nation’s electric system will continue to increase as a result of many \nfactors, including growing digitization and electrification, as well as the “changing resource mix \nand increased reliance on variable resources and natural gas.”4  The Commission, in its most \nrecent State of the Markets Report, stated that “[r]egions continue to confront challenges in \nassuring resource adequacy – challenges caused by extreme weather events, a changing resource \nmix, and shifts in load profiles.”5  The report also noted that most RTO/ISO peak demand \nforecasts have shown a trend towards faster load growth in recent years, shifting from prior \nprojections of flattening or declining growth to projections of increasing growth.  A key facet of \nthis growth in many regions is the emergence of new large load additions (e.g., from data \ncenters).  Growth from this segment of the power sector is forecast to persist well into the future, \nand many regions are likely to see increases in large new loads seeking to connect to the electric \nsystem over the next several years.  For example, a recent Lawrence Berkeley National \nLaboratory report estimated that data center load growth tripled over the past decade and is \nprojected to double or triple by 2028.6  A 2024 report by the Electric Power Research Institute \n(EPRI) projected that data centers will grow to consume up to 9.1 percent of U.S. electricity \ngeneration annually by 2030, compared to an estimated 4 percent today.7  At the same time, the \nelectric industry is in the midst of a transformation, both in terms of the generation mix serving \ncustomers and customer makeup.  The electric system resource mix is evolving rapidly.   \n \n4 See Statement of North American Electric Reliability Corporation, Technical Conference on Large Loads Co-\nlocated at Generating Facilities, Docket No. AD24-11-000 (Nov. 1, 2024), at 2-3. \n5 See Fed. Energy Reg. Comm’n, 2024 State of the Markets Staff Report (March 20, 2025) at 8, \nhttps://www.ferc.gov/news-events/news/SMR-2024.  \n \n6 Dep’t of Energy, DOE Releases New Report Evaluating Increase in Electricity Demand from Data Centers (Dec. \n20, 2024), https://www.energy.gov/articles/doe-releases-new-report-evaluating-increase-electricity-demand-data-\ncenters.  \n7 Elec. Power Research Inst., Powering Intelligence: Analyzing Artificial Intelligence and Data Center Energy \nConsumption(May 2024) at 2, https://www.epri.com/research/products/3002028905."},{"page":4,"startToken":915,"endToken":1192,"text":"4 \n \nEnsuring that the nation’s electric companies can accommodate these generational \nchanges and continue to serve customers in a reliable and affordable manner will require new \nand upgraded energy infrastructure at all points on the electric value chain: generation, \ntransmission, and distribution.  Electric companies stand ready to lead the expansion of energy \ninfrastructure needed to accommodate these changes.  The regulatory model that underlies the \nelectric sector is, and will be, critical to meet this extraordinary period of new growth.  It ensures \ncollaboration and partnerships between electric companies, stakeholders, and customers.  \nMoreover, it serves as the foundation that supports the financing and construction of long-lived \ninfrastructure.   \nAgainst this backdrop, EEI submits the following general comments for the \nCommission’s consideration.  In doing so, EEI asks that the Commission ensure any action or \ndecision in this proceeding does not adversely affect other regions and/or impede the ability of \nthose regions to address any similar challenges in ways they believe to be just and reasonable. \nII. \nCOMMENTS \na. Electric companies stand ready to lead energy infrastructure \nexpansion. \nElectric companies are best positioned to lead the expansion of energy infrastructure \ndriven by the dynamics previously described.  This year, EEI members will invest $200 billion to \nmake the energy grid smarter, more dynamic, more flexible, and more secure; to diversify the \nnation’s energy mix; and to integrate new technologies that benefit customers.  Electric \ncompanies have extensive knowledge of the electric system, deep, collaborative relationships \nwith states and stakeholders, and, for decades, managed the development of infrastructure \nprojects that take years to design, finance, and build.  Each of these capabilities is essential in \nassuring efficient, cost-effective, and timely infrastructure additions.  Moreover, experience in"},{"page":5,"startToken":1192,"endToken":1479,"text":"5 \n \nthe recent past demonstrates that electric companies are capable of meeting new demand from \nlarge loads, including data center-based demand.  There is a data center located in every state in \nthe country, and each project required careful planning before going into service.   \nElectric companies have direct experience with the effects of rapid growth of large loads \nin their service territories.  Working in partnership with their states, these companies successfully \naccommodated that growth over time.  Electric companies have also announced numerous \nagreements and partnerships to facilitate data center development.  For example, northern \nVirginia, Dominion’s service territory, boasts the largest data center market in the world, and \nDominion serves more data centers today than the next five largest national data center markets \ncombined.8  In addition, AEP anticipates 20 gigawatts in new load by the end of the decade.9  \nExelon serves 200 online data centers in its service territories and projects significant continued \nload growth from data centers.10  States have also actively worked to prepare for load growth \nfrom large customers.  In January, the Georgia Public Service Commission voted unanimously to \napprove new rules that allows for longer contract lengths between and minimum billing \nrequirements for high-load customers.11   \n       \n \n \n \n8 Comments of Dominion Energy Services, Docket No. AD24-11-000 (Dec. 9, 2024), at 2. \n9 Am. Elec. Power, AEP Reports 2024 Earnings Results (Feb. 13, 2025), \nhttps://www.aep.com/news/stories/view/10018/.  \n \n10 Exelon, 2024 Earnings Call Presentation Slides (Feb. 12, 2025), https://investors.exeloncorp.com/events/event-\ndetails/q4-2024-exelon-corporation-earnings-conference-call.  \n \n11 GA Pub. Serv. Comm’n, PSC Approves Rule to Allow New Power Usage Terms for Data Centers (Jan. 23, 2025), \nhttps://psc.ga.gov/site/assets/files/8617/media_advisory_data_centers_rule_1-23-2025.pdf."},{"page":6,"startToken":1479,"endToken":1755,"text":"6 \n \nb. The existing regulatory model can accommodate significant demand \ngrowth. \nThe regulatory model that governs the electric sector is long-standing, well-understood \nand provides transparent processes that ensure prudent investment to serve customers.  This \nmodel successfully accommodated significant demand growth at different periods in the nation’s \nhistory and can continue to do so in the current environment.  In addition, this model provides \nstability and facilitates valuable partnerships between electric companies, regulators, \nstakeholders, and customers.  It will be a critical supporting element in meeting this \nextraordinary period of new demand growth.  Further, this regulatory model has been carefully \ndeveloped over more than one hundred years and, as a result, electric companies, customers, and \nregulators have long-established approaches for working collaboratively to plan the supply \nadditions and system expansions required to serve customers.  When they function properly, \nthese approaches foster collaboration that ensures the necessary investments are made, \ninfrastructure is developed, and critical public services are provided. \nThis regulatory model has, among other things, helped to build an electric system that \nevolves and modernizes as it integrates new supply resources and demand (e.g., data centers).  \nThis networked system captures economies of scale and allows electric companies to meet new \ndemand efficiently and cost-effectively, as demonstrated by the reliable addition of thousands of \ndata centers across the nation.  Indeed, as noted above, America’s electric companies have been \nat the forefront in partnering with new large loads, such as data centers, to enable timely \ninterconnections to the grid.  These instances demonstrate electric companies’ ability to \nproactively plan and invest in transmission and generation infrastructure that can facilitate large \nload development while achieving broader benefits for existing customers and communities."},{"page":7,"startToken":1755,"endToken":2036,"text":"7 \n \nAs the Commission recognized in its February 20th order in this proceeding, there are \nmany different co-location configurations. Co-location, depending on configuration, provides \noptionality to serve data centers and may support data center development necessary for \neconomic development and national security.  This could include: \n• Access to an integrated network of supply resources that permit cost-efficient operations \n• Holistic and comprehensive system planning that identifies new grid infrastructure to \nensure reliable delivery of power \n• Provision of black start and ancillary services \n• Cybersecurity and physical security measures and protections will all contribute benefits \nto co-located load that is connected to the electric system.  \n \nc. Principles for the Commission to bear in mind as it evaluates next \nsteps. \nAs the Commission evaluates the comments it receives in response to the Show Cause \nOrder and contemplates its next steps, EEI asks that it keep several key principles in mind.  First \nand foremost, the Commission should strive to ensure that reliable system operations and \nresource adequacy are maintained and enhanced over the long term.  At the same time, co-\nlocation policies should be grounded in cost-causation principles, ensuring that data center \ncustomers pay just and reasonable rates for service they use and protecting existing customers \nfrom any potential undue and unfair shifts in costs.  The Commission should also respect the \njurisdiction of state regulatory authorities and consider how collaboration with state \ncommissions, and RTOs/ISOs where applicable, may be valuable in addressing specific co-\nlocation arrangements.  Adherence to these principles will ensure that rules and regulations will \nenable electric companies to continue their long history of delivering reliable and affordable \nservice to customers and meeting the new system demands in a cost-effective, efficient, and \ntimely way."},{"page":8,"startToken":2036,"endToken":2092,"text":"8 \n \nIII. \nCONCLUSION \nEEI appreciates the opportunity to submit comments in this proceeding and urges the \nCommission to act in a manner consistent with the principles discussed herein. \n \n \n \n \n \n \nRespectfully submitted, \n \n      /s/             _ \nKevin Huyler \nManaging Director, Federal Regulatory Affairs \nkhuyler@eei.org \nEdison Electric Institute \n701 Pennsylvania Ave., N.W. \nWashington, D.C. 20004 \n \n \n \nApril 23, 2025"},{"page":9,"startToken":2092,"endToken":2147,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list compiled by the Secretary in this proceeding.  Dated at \nWashington, D.C. this 23rd day of April 2025.  \n      /s/            _ \n \nSandra Safro \n \nDeputy General Counsel \n \nEdison Electric Institute \n \nSSafro@eei.org   \n \n202-508-5129"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":1361,"startToken":0,"endToken":448},{"p":2,"at":1361,"title":"I. BACKGROUND","method":"printed heading","endPage":4,"endAt":1137,"startToken":448,"endToken":1077},{"p":4,"at":1137,"title":"II. COMMENTS","method":"printed heading","endPage":8,"endAt":5,"startToken":1077,"endToken":2037},{"p":8,"at":5,"title":"III. CONCLUSION","method":"printed heading","endPage":9,"endAt":0,"startToken":2037,"endToken":2092},{"p":9,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":9,"endAt":384,"startToken":2092,"endToken":2147}]}