{"document":{"slug":"rec-20250423-5179","title":"Comments of the Public Utilities Commission of Ohio's Office of the Federal Energy Advocate in response to FERC's 02/20/2025 Order","issued":"2025-04-23","accession":"20250423-5179","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Ohio Federal Energy Advocate","kind":"comments","file":"sources/filings/text/20250423-5179_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250423-5179","tier":"record","sha256":"ee551975d39f9bcfb0c788dbeda135b472842f84d50477c5fee9c1b66a9e59b2","pages":7,"tokens":1425,"emptyPages":[],"textThemes":["colo","adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":209,"text":"1 \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nPJM Interconnection, L.L.C. et al. \n) \nDocket No. EL25-49-000 \n \n \nLarge Loads Co-Located at Generating \n) \nDocket No. AD24-11-000 \nFacilities \n) \n \n \nConstellation Energy Generation, LLC \n) \nDocket No. EL25-20-000 \nv. \n) \nPJM Interconnection, L.L.C.  \n) \n(consolidated) \n \n \n \n \n \n \nCOMMENTS OF THE PUBLIC UTILITIES COMMISSION OF OHIO’S  \nOFFICE OF THE FEDERAL ENERGY ADVOCATE \n \nThe Office of the Federal Energy Advocate (Ohio FEA) of the Public Utilities \nCommission of Ohio, fulfilling its statutory duty to advocate on behalf of Ohio’s retail electricity \nconsumers,1 submits the following in response to the Federal Energy Regulatory Commission’s \n(FERC or Commission) February 20, 2025 Order instituting a show cause proceeding pursuant to \nsection 206 of the Federal Power Act (FPA) regarding large loads co-located at generating \nfacilities in the PJM Interconnection, LLC (PJM) region. \nI. \nBackground \nThe substantial grid challenges PJM is working to address are well known and a result of \nnumerous simultaneous issues, including a changing generation resource mix, delayed capacity \nauctions, lengthy interconnection queue reform, and unprecedented forecasted load growth \ndriven primarily by data centers. Given the current landscape of tight supply and increasing \ndemand, interest in the topic of co-locating large loads with generating facilities in PJM has \n \n1 Ohio Revised Code 4928.24."},{"page":2,"startToken":209,"endToken":437,"text":"2 \nescalated over the last two years. On November 1, 2024, the Commission convened a technical \nconference in Docket No. AD24-11-000 related to large loads co-located at generating facilities, \nfollowed by a request for post-technical conference comments.2 Separately, on November 22, \n2024, Constellation Energy Generation, LLC (Constellation) filed an FPA section 206 complaint \nagainst PJM in Docket No. EL25-20-000 arguing that PJM’s Tariff is unjust, unreasonable, and \nunduly discriminatory because it does not contain rules for interconnected generators to follow \nwhen they seek to execute certain configurations and arrangements to serve co-located load.3  \nIn the instant proceedings, the Commission consolidated the show cause proceeding with \nthe technical conference and Constellation complaint proceeding for administrative efficiency \nand directed PJM and the Transmission Owners to respond to enumerated questions and \nconcerns regarding co-location arrangements.  \nThe Ohio FEA offers the following comments for FERC’s consideration. \nII. \nComments \nA. \nMultiple Pathways Are Needed to Address Resource Adequacy Needs. \nThe PJM region faces the unprecedented challenge of simultaneously managing \nsignificant load growth, premature retirement of dispatchable thermal generation, and slow entry \nof new resource additions. Significant incremental capacity is needed, and the Ohio FEA \nappreciates PJM’s effort in working with stakeholders, state regulators, and the Commission to \neffectuate market, planning, and operations reforms to ensure that resource adequacy and grid \nreliability are maintained. \n \n2 Docket No. AD24-11-000.  \n3 Docket No. EL25-20-000."},{"page":3,"startToken":437,"endToken":719,"text":"3 \nGiven PJM’s existing market conditions and speed to market concerns, it is not surprising \nthat various permutations of co-locating load with generation resources have recently come to \nthe forefront. The Ohio FEA agrees that an “all hands on deck” approach is needed to meet \nsupply and demand challenges in the region and appreciates PJM’s commitment “to facilitating \nand supporting co-location arrangements where permitted by applicable state law.”4 However, \nPJM must develop transparent processes to assess the grid impacts of co-location arrangements \nand to ensure that individual arrangements do not threaten grid reliability or worsen the resource \nadequacy concerns that exist across the region.  \nIn its answer, PJM lays out eight potential options for large load co-location \nconfigurations, including the existing standard process for integrating large loads into the grid \n(regardless of whether co-located generation shares the same point of interconnection) and the \ntraditional behind-the-meter configuration where generation that serves a primary customer is \nnetted against that customer’s use of the electric grid. PJM goes on to describe five conceptual \noptions that are not in its current Tariff but that might be of interest to states or entities \ncontemplating alternative co-location arrangements and seeking clarity from PJM or the \nCommission.  \nThrough its discussion of the range of options, PJM reiterates its recommendation and \npreference that large loads be designated as Network Load as opposed to configurations that \npropose to install off-system load behind an existing generator.5 “Network Load status offers the \nmost robust reliability benefits and holistic planning efficiencies, minimizes the need for one-off \n \n4 PJM Answer at 32.  \n5 A configuration where both the load and the generator are isolated from the grid is not addressed in PJM’s Answer."},{"page":4,"startToken":719,"endToken":1019,"text":"4 \noperational procedures (both interim and longer term), and offers a cost allocation framework \nthat assesses charges for use of and reliance on the transmission system.”6  \nThe Ohio FEA shares concern that installing large off-system loads behind existing \ngenerators adds complexity, including that the load would not be captured in the annual load \nforecasting and planning processes conducted by Load Serving Entities and PJM. Additionally, \nthe Ohio FEA notes an important difference between new loads that are paired with new \ngeneration and co-location arrangements that propose to take existing generation off the system. \nThe latter has broader implications because it would change the power flow across the \ntransmission system and affect the mix of resources available to participate in PJM’s energy and \ncapacity markets. Because of the wider range of impact, co-location arrangements that take \nexisting generation off the system should be subject to robust analysis before they are allowed to \nproceed, including studying the impacts on the markets, grid reliability, and resource adequacy. \nB. \nBring Your Own Generation (BYOG) Should Be Encouraged.  \nIn encouraging load additions to be Network Load, PJM acknowledges that any \nadditional load on the system requires either the addition of supply resources to serve that load or \nflexibility on the part of the load to curtail its consumption from the transmission system when \nnecessary to maintain reliability.7 Three of the five conceptual options PJM outlines in its \nAnswer could serve to bring new Network Load on faster without exacerbating resource \nadequacy concerns. The Ohio FEA supports further consideration of these options.  \nIn particular, co-located load that elects to be Network Load and brings its own \ngeneration, or BYOG, could augment the steps PJM is already taking, such as through the \n \n6 PJM Answer at Exhibit B at 2. \n7 PJM Answer at 62."},{"page":5,"startToken":1019,"endToken":1267,"text":"5 \nReliability Resource Initiative, to ensure that needed generation resources can be timely \nintegrated onto the transmission system to serve significant future load growth. BYOG may \nprovide a pathway in some states for new generation resources to support co-located load and \nalso serve as PJM Capacity Resources. Under this option, various incentives could be explored, \nincluding faster processing of generation that enters the PJM interconnection queue to \naccommodate the co-located load. Importantly, under BYOG, the new Network Load would \nbring generation resources that could also serve as Capacity Resources, mitigating both local grid \nimpacts at the point of interconnection and regional resource adequacy concerns.  \nC. \nCo-Located Load Must Pay for Grid Services Used. \nThe Ohio FEA agrees with PJM that “participants involved in co-location arrangements \nshould pay the costs of any grid services they consume and the arrangements must be reliable \nand operationally manageable.”8 Regardless of the co-located load configurations that may be \napprovable by the Commission and under state laws, PJM must establish transparent processes to \ndetermine the extent to which individual co-located load relies on the bulk power system (for \nAncillary Services or otherwise) and a means by which to allocate those transmission costs \naccordingly so that co-located load arrangements do not shift costs to other customers.  \nIII. \nConclusion \nThe Ohio FEA appreciates the Commission’s thorough investigation into issues \nsurrounding co-located loads to assist PJM and state regulators in meeting the resource adequacy \nneeds of the region without compromising reliability.  \n \n \n \n8 PJM Answer at 4."},{"page":6,"startToken":1267,"endToken":1332,"text":"6 \nRespectfully submitted,  \nDave Yost  \nOhio Attorney General  \n \nJohn H. Jones  \nSection Chief \n \n \n \n \n \n \n \n/s/ Thomas G. Lindgren \n \n \n \nThomas G. Lindgren  \nAssistant Attorney General  \nPublic Utilities Section  \n30 East Broad Street, 16th Floor  \nColumbus, Ohio 43215-3414  \n614.644.8768 (telephone)  \n866.818.6152 (facsimile)  \nThomas.Lindgren@OhioAGO.gov  \n \nOn Behalf of the Public Utilities  \nCommission of Ohio’s Office of the  \nFederal Energy Advocate  \n \n \n \nApril 23, 2025"},{"page":7,"startToken":1332,"endToken":1425,"text":"7 \nCERTIFICATE OF SERVICE \nI hereby certify that I have on this date caused a copy of the foregoing document to be \nserved on each person included on the official service list maintained for this proceeding by the \nCommission’s Secretary, by electronic mail or such other means as a party may have requested, \nin accordance with Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § \n385.2010. Dated this the 23rd day of April 2025, at Columbus, Ohio. \n \n/s/ Thomas G. Lindgren \n \nThomas G. Lindgren \nAssistant Attorney General"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":980,"startToken":0,"endToken":135},{"p":1,"at":980,"title":"I. Background","method":"printed heading","endPage":2,"endAt":1052,"startToken":135,"endToken":353},{"p":2,"at":1052,"title":"II. Comments","method":"printed heading","endPage":2,"endAt":1067,"startToken":353,"endToken":355},{"p":2,"at":1067,"title":"A. Multiple Pathways Are Needed to Address Resource Adequacy Needs.","method":"printed heading","endPage":4,"endAt":1108,"startToken":355,"endToken":884},{"p":4,"at":1108,"title":"B. Bring Your Own Generation (BYOG) Should Be Encouraged.","method":"printed heading","endPage":5,"endAt":732,"startToken":884,"endToken":1123},{"p":5,"at":732,"title":"C. Co-Located Load Must Pay for Grid Services Used.","method":"printed heading","endPage":5,"endAt":1433,"startToken":1123,"endToken":1229},{"p":5,"at":1433,"title":"III. Conclusion","method":"printed heading","endPage":7,"endAt":3,"startToken":1229,"endToken":1333},{"p":7,"at":3,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":7,"endAt":548,"startToken":1333,"endToken":1425}]}