{"document":{"slug":"rec-20250423-5208","title":"Answer of the Indicated PJM Transmission Owners in response to PJM Interconnection, L.L.C.'s 03/24/2025 Answer, et al","issued":"2025-04-23","accession":"20250423-5208","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Exelon CorporationAmerican Electric Power Service CorporationAMP Transmission, LLC ,City of Cleveland, Department of Public Utilities, Division ,City of Hamilton, OH ,Dominion Energy Services, Inc. ,Duke Energy Corporation ,Duquesne Light Company ,The FirstEnergy Transmission Companies ,East Kentucky Power Cooperative, Inc. ,Old Dominion Electric Cooperative ,PPL Electric Utilities Corporation ,Rockland Electric Company ,southern maryland electric cooperative ,Wabash Valley Power Association, Inc. ,UGI Utilities Inc. ,","kind":"answer","file":"sources/filings/text/20250423-5208_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250423-5208","tier":"record","sha256":"360fd8f14f52c6118edded26b8b4ba5c548afa41284964d9d3a776a9fb28e4b0","pages":20,"tokens":5655,"emptyPages":[],"textThemes":["colo"]},"pages":[{"page":1,"startToken":0,"endToken":349,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C., et al. \n \n) \nDocket No. EL25-49-000 \n \nLarge Loads Co-Located at Generating \nFacilities \n) \nDocket No. AD24-11-000 \nConstellation Energy Generation, LLC \n \nv. \n \nPJM Interconnection, L.L.C. \n) \n \n) \n \n) \nDocket No. EL25-20-000 \n(consolidated) \n \nANSWER OF THE INDICATED PJM TRANSMISSION OWNERS  \n \nPursuant to Rules 212 and 2131 of the Rules of Practice and Procedure of the Federal \nEnergy Regulatory Commission (“FERC” or “Commission”) and the Commission’s Show Cause \nOrder,2 the Indicated PJM Transmission Owners (hereinafter, “Indicated TOs”)3 submit this \n \n \n1 18 C.F.R. §§ 385.212, 385.213 (2024). \n2 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115, at Ordering Paragraph (D) (2025) (“Show Cause Order”). \n3 The Indicated PJM Transmission Owners include: American Electric Power Service Corporation, on behalf of \nAppalachian Power Company, Indiana Michigan Power Company, Kentucky Power Company, Kingsport Power \nCompany, Ohio Power Company, Wheeling Power Company, AEP Appalachian Transmission Company, Inc., AEP \nIndiana Michigan Transmission Company, Inc., AEP Kentucky Transmission Company, Inc., AEP Ohio Transmission \nCompany, Inc., and AEP West Virginia Transmission Company, Inc.; AMP Transmission, LLC; City of Cleveland, \nDepartment of Public Utilities, Division of Cleveland Public Power; City of Hamilton, OH; Dominion Energy \nServices, Inc. on behalf of Virginia Electric and Power Company d/b/a Dominion Energy Virginia; Duke Energy \nCorporation on behalf of its affiliates Duke Energy Ohio, Inc., Duke Energy Kentucky, Inc., and Duke Energy Business \nServices LLC; Duquesne Light Company; East Kentucky Power Cooperative; Exelon Corporation, on behalf of \nAtlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company, \nCommonwealth Edison Company of Indiana, Inc., Delmarva Power & Light Company, PECO Energy Company, and \nPotomac Electric Power Company; FirstEnergy Service Company, as agent for its affiliates American Transmission \nSystems, Incorporated, Jersey Central Power & Light Company, Mid-Atlantic Interstate Transmission LLC, Keystone \nAppalachian Transmission Company, The Potomac Edison Company, Monongahela Power Company and Trans-\nAllegheny Interstate Line Company (collectively, the “FirstEnergy Transmission Companies”); Old Dominion Electric \nCooperative; PPL Electric Utilities Corporation; Rockland Electric Company; Southern Maryland Electric \nCooperative, Inc.; UGI Utilities Inc; and Wabash Valley Power Association, Inc."},{"page":2,"startToken":349,"endToken":640,"text":"2 \n \nAnswer to the March 24, 2025 Answer of PJM Interconnection, L.L.C., the March 24, 2025 \nAnswer of Public Service Electric and Gas Company, and the April 4, 2025 Motion for \nClarification of Vistra Corp.  Paragraph 87 of the Show Cause Order and the Commission’s \nOrdering Paragraph (D) permit responses by “[i]nterested entities” within “30 days of PJM’s . . . \nfiling.”4 \nThe record in this proceeding demonstrates that the existing PJM Interconnection, L.L.C. \n(“PJM”) Open Access Transmission Tariff (“PJM Tariff”) remains just and reasonable and that co-\nlocated load is Network Load that uses and relies on the transmission system and should pay for \ntransmission service, and other PJM services.  While no changes to the existing PJM Tariff are \nnecessary, to the extent FERC believes it would provide helpful clarity, the Indicated TOs \nrecommend adopting a proposed definition of co-located load clarifying that it is Network Load, \nso that all parties may proceed with the timely interconnection of co-located arrangements based \non clear and common understanding of the applicable rates for service.  The definition proposed \nin the Indicated TOs’ initial response accomplishes that goal.  \nI. \nBecause the Requisite Showing Has Not Been Made Under Federal Power Act \nSection 206, the Commission Should Terminate the Show Cause Proceeding and \nReaffirm that the Existing PJM Tariff Is Just and Reasonable. \n \nThe record in this proceeding demonstrates that the existing PJM Tariff is just and \nreasonable.  Consequently, the legally proper course of action is for the Commission to terminate \nthis Federal Power Act (“FPA”) section 206 proceeding.  The Commission should act promptly to \nprovide interested stakeholders much needed and much desired certainty. \n \n \n4 Show Cause Order, 190 FERC ¶ 61,115 at P 87; see also id. at Ordering Paragraph (D)."},{"page":3,"startToken":640,"endToken":949,"text":"3 \n \na. The Existing PJM Tariff Is Just and Reasonable. \nPJM—the administrator of the PJM markets and the PJM Tariff—and virtually all of the \nPJM transmission owners, including investor-owned utilities, municipalities, and cooperatives, are \nin agreement: the “existing Tariff remains just and reasonable.”5  As PJM explains, “[t]he Tariff \ntoday permits co-located loads to interconnect through existing load interconnection processes.”6  \nThose end-use load connection processes, governed by the states and fully consistent with the PJM \nTariff, are available to all, and those processes work.  Moreover, the transmission service provided \nto co-located load under the PJM Tariff is available to all on a non-discriminatory basis.  Nowhere \nin the record is there an allegation—let alone evidence—that the current PJM Tariff impedes the \ndevelopment of or service to any load, co-located or otherwise.  Therefore, there is no basis to alter \nthe existing PJM Tariff under section 206 of the FPA.  \nIn a proceeding under section 206 of the FPA, the Commission can only remedy a “rate \n[or] charge” or “any rule, regulation, practice, or contract affecting such rate [or] charge” after it \nis found to be “unjust [or] unreasonable.”7  “The burden of proving an unjust or unreasonable rate \nrests with the party that initiated the proceeding—the Commission [(as in this case)] or the third-\nparty complainant.”8  Only after a successful showing that the prevailing rate is unjust and \nunreasonable may the Commission order a replacement rate.9  No such showing has been made \nhere. \n \n \n5 Answer of PJM Interconnection, L.L.C. at 4 (Mar. 24, 2025) (“PJM Answer”); see also id. at 32 (“PJM’s Tariff \nremains just and reasonable.”). \n6 Id. at 32. \n7 16 U.S.C. § 824e(a). \n8 Pub. Citizen, Inc. v. FERC, 7 F.4th 1177, 1183 (D.C. Cir. 2021). \n9 16 U.S.C. § 824e(a)."},{"page":4,"startToken":949,"endToken":1294,"text":"4 \n \nAlthough some entities “may prefer, for their own business reasons, alternative pathways \nto co-location,” business preferences “do not render the [PJM] Tariff unjust and unreasonable.”10  \nNor should PJM develop its rules addressing co-located load specifically to appease or conform to \na particular entity’s business model.  As the Indicated TOs explained in their Answer, the PJM \nTariff already has mechanisms to allow co-located load to connect to the grid and ensure that, as \nNetwork Load, these co-located loads pay for their share of grid services.11  Indeed, PJM’s Answer \nemphasizes the numerous ways in which the existing PJM Tariff ensures just and reasonable rates \nfor co-located loads.  As the Indicated TOs explained, and PJM further validated in its answer, \nPJM’s Tariff remains just and reasonable because “co-located load is interconnected with the grid \nand relies on the grid.”12  Just like every other load, those loads connect to and receive service \nfrom PJM’s transmission system and there is no indication that the PJM Tariff’s construct does not \nwork.  Significantly, PJM agrees.13  \nWhile one transmission owner suggests otherwise, citing what it characterizes as \nCommission “skepticism” that existing provisions of the PJM Tariff are appropriate for all types \n \n \n10 PJM Answer at 32. \n11 See Indicated TOs Answer at 14–17 (Mar. 24, 2025).  In appropriate circumstances, the PJM Tariff may alternatively \npermit Point-to-Point Service as an option. \n12 Id. at 13. \n13 See PJM Answer at 4, 32 (stating that the PJM Tariff “remains just and reasonable”); see also id. at 38 (“PJM \ncontinues to prefer that co-location arrangements be designated ‘Network Load’ in front of the meter.”); id. at 44 \n(“Absent an arrangement where both the load and the generator are completely isolated and physically disconnected \nfrom the grid, (a situation which is very different from the claimed ‘totally isolated’ configuration offered by some in \nthese proceedings), PJM is not aware of a configuration that would ‘ensure the co-located load never takes any form \nof transmission service.’  As noted above, grid-connected facilities benefit from their connection and should pay for \ngrid services consumed.”)."},{"page":5,"startToken":1294,"endToken":1662,"text":"5 \n \nof co-located load configurations,14 “skepticism” is not the standard of proof under section 206 of \nthe FPA.  The standard is whether the existing PJM Tariff is unjust and unreasonable—a showing \nthat has not been satisfied. \nb. Behind the Meter Generation Is Not Similarly Situated to Co-Located Load. \n \nAlthough the vast majority of PJM transmission owners, including traditional transmission \nowners, municipalities and cooperatives are aligned, a single transmission owner also claims that \n“[a]n approach that aligns with cost causation principles is one that treats all co-located customers \nas [Network Integration Transmission Service] customers with netting rules applied” and that “this \nis the current construct for [Behind the Meter Generation (“BTMG”)] customers under the PJM \nTariff.”15  Notwithstanding this allegation, the two configurations—BTMG and co-located load—\nremain distinct.  Accordingly, reference to behind the meter generation is wholly inapposite to the \nco-located load inquiry here.    \nNetting is permitted under the PJM Tariff for BTMG when load takes Network Integration \nTransmission Service (“Network Service”) from a network service customer and the load has its \nown generator.16  Netting occurs when a generator provides power directly to a load and the billing \ndeterminant used to compute the Network Service costs for that network load is reduced by the \nquantity of power consumption offset by its BTMG.  By way of example, electric cooperatives in \n \n \n14  Response of Public Service Electric and Gas Company to the Order to Show Cause at 10 (Mar. 24, 2025) (“PSEG \nAnswer”) (alleging that “[i]t is telling that the Commission acknowledged that while PJM’s preference is that ‘large \nloads be in front of the meter and designated as PJM Network Load,’ the Commission stated that the PJM Tariff does \nnot appear to require this service” and that the “Commission expressed skepticism that this is the appropriate type of \ntransmission service that should be required of all co-located configurations”). \n15 Id. at 13. \n16 PJM OATT, Section 34.2, Netting of Behind the Meter Generation (“The daily load of a Network Customer does \nnot include load served by operating Behind The Meter Generation.  The daily load of a Network Customer shall not \nbe reduced by energy injections into the transmission system by the Network Customer.”)."},{"page":6,"startToken":1662,"endToken":2077,"text":"6 \n \nparticular use BTMG including certain diesel generating facilities to serve load and rely on the \nPJM Tariff provisions that provide for netting of this BTMG for purposes of charges for Network \nService and other services used to facilitate the public utility service they provide.   \nCo-located load is distinct from BTMG.  Were co-located load netted against generation it \nwould not be measured as load even though it uses the transmission system.  The PJM Tariff \nprovisions on BTMG define it as follows: \n“Behind The Meter Generation” shall refer to a generation unit that \ndelivers energy to load without using the Transmission System or \nany distribution facilities (unless the entity that owns or leases the \ndistribution facilities has consented to such use of the distribution \nfacilities and such consent has been demonstrated to the satisfaction \nof the Office of the Interconnection); provided, however, that \nBehind The Meter Generation does not include (i) at any time, any \nportion of such generating unit’s capacity that is designated as a \nGeneration Capacity Resource; or (ii) in an hour, any portion of the \noutput of such generating unit that is sold to another entity for \nconsumption at another electrical location or into the PJM \nInterchange Energy Market.17 \nBecause the record in this proceeding is clear that co-located load arrangements do use the \ntransmission system, they cannot qualify as BTMG.  Service to co-located load using generators \nconnected to the transmission system inherently both use and rely on the transmission system.18   \nTreating co-located load similarly to BTMG would result in “the costs assessed” not \n“bear[ing] some resemblance ‘to the burdens imposed or benefits drawn by that party.’”19  To \n \n \n17 PJM OATT, Section 1 (Definitions). \n18 See, e.g., Declaration of David Weaver, PE at PP 10–24, Attach. 1 to Exelon Comments, Docket No. EL25-20 (Dec. \n12, 2024) (“Weaver Decl.”); see also, e.g., id. P 17 (explaining that because nuclear units are unable to provide black \nstart services, co-located load must rely on those services from other resources in PJM that are connected to the grid \nin order to come back online); id. P 19 (explaining that the co-located load will take service that is dependent “on a \nstrong interconnection with the grid that is supported by reactive power, operating reserves, and black start”). \n19 Pub. Serv. Elec. & Gas Co. v. FERC, 989 F.3d 10, 13 (D.C. Cir. 2021) (quoting Midwest ISO Transmission Owners \nv. FERC, 373 F.3d 1361, 1368–69 (D.C. Cir. 2004))."},{"page":7,"startToken":2077,"endToken":2403,"text":"7 \n \nafford similar treatment would be to grant an undue preference to such configurations over others \nthat also rely upon Network Service.20  Just like all other loads, Network Service should be paid \nwhen there is co-located load.  To restate: the PJM Tariff and Order No. 888’s pro forma open \naccess transmission service tariff contemplate two types—and only two types—of service: (1) \nNetwork Service for general network service; and (2) Point-to-Point Transmission Service (“Point-\nto-Point Service”) for wheeling.  As PJM itself has stated, if you are looking to serve co-located \nload, Network Service is the correct service to take under the Tariff.21 \nBTMG and co-located load are not similarly situated.  As PJM explains, BTMG was \nconceived for, and has been implemented for, substantially smaller loads.22  Under the PJM Tariff, \nco-located load is Network Load and should be in front of the meter.  The majority of the \ntransmission owners in PJM, inclusive of investor-owned utilities, municipalities, and \ncooperatives, remain aligned that treating co-located load as Network Load is essential for \nreliability, transmission planning, PJM’s procurement of adequate capacity, and appropriate cost-\nallocation.23 \nThe notion that “the data center load could be structured on a front of the meter basis with \nthe co-located generator providing primary power and with back-up power coming from the grid; \nor the data center load could be fully isolated behind the meter with system protection facilities in \n \n \n20 See 16 U.S.C. § 824d(b) (“No public utility shall, with respect to any transmission or sale subject to the jurisdiction \nof the Commission, (1) make or grant any undue preference or advantage to any person or subject any person to any \nundue prejudice or disadvantage, or (2) maintain any unreasonable difference in rates, charges, service, facilities, or \nin any other respect, either as between localities or as between classes of service.”). \n21 See PJM Answer at 38. \n22 Id. at 13. \n23 Cf. id. at 39 n.64."},{"page":8,"startToken":2403,"endToken":2740,"text":"8 \n \nplace to ensure that there is no flow of power from the grid to the load”24 is, at best, inaccurate.  \nAs explained by the Indicated TOs, there is no such thing as data center load configured to be \n“fully isolated” behind the meter through “system protection facilities,” because co-located load \nthat is connected to the electric grid (a) necessarily relies on reliability services, such as ancillary \nservices, including black start; (b) retains the potential to draw real or reactive power from the grid \nat any time; and (c) relies on and benefits from its connection to the transmission system at all \ntimes.25  In other words, there is no such thing as a co-located configuration, connected to and \nsynchronized with the electric grid, that is “fully isolated.”  While protection systems may serve \nimportant roles, they do not isolate the load from the grid, and the grid must be maintained—with \nthe attendant costs—to accommodate this reality. \nIndeed, PJM has recognized this, stating that it \nobjects to the [Commission’s] use of the phrase “wholly isolated \nfrom the grid” [in a question] as it is contrary to engineering and \neconomic principles.  The notion that any of the proposed co-\nlocation arrangements can be “wholly isolated” is misleading.  The \nload and generator are connected to and synchronized with the \nmulti-state bulk power system.  It is not operating as a micro grid \n(nor can it if the generating facility is a nuclear unit).  Nor is the \ngenerator delivering power through an intermediary to a load with a \nbreaker open.  Further, by way of example, there are obligations to \nensure power to nuclear plants to ensure safe shutdown (among \nother things).  The load and generator are benefiting from ancillary \nservices (including but not limited to black start).  Any system \nprotection facilities are designed to only handle less complex N-1 \nconditions, and can misoperate (and indeed have misoperated).26 \n \n \n24 PSEG Answer at 11. \n25 See Indicated TOs Answer, Attach. (A) at 4–5. \n26 PJM Answer at 42–43."},{"page":9,"startToken":2740,"endToken":3003,"text":"9 \n \n \nPJM also explained that, \n \n[a]bsent an arrangement where both the load and the generator are \ncompletely isolated and physically disconnected from the grid, (a \nsituation which is very different from the claimed “totally isolated” \nconfiguration offered by some in these proceedings), PJM is not \naware of a configuration that would “ensure the co-located load \nnever takes any form of transmission service.”  As noted above, \ngrid-connected facilities benefit from their connection and should \npay for grid services consumed.27  \n \nIn other words, transmission services are being provided to and relied upon by the co-located load \nwhether or not it is behind the meter.  The PJM Tariff allows for service to co-located load as \nNetwork Service.  Such treatment is needed in order to ensure reliability, effective transmission \nplanning, procurement of adequate capacity, and proper cost allocation. \nII. \nNo Replacement Rate Is Necessary or Appropriate Under FPA Section 206. \na. PJM’s Potential Options Are Unnecessary to Resolve the Show Cause \nProceeding. \n \nThe Indicated TOs appreciate PJM laying out several “potential options for additional large \nload co-location.”28  However, it is important to emphasize that the mere presentation of potential \noptions does not establish that the existing PJM Tariff is unjust and unreasonable and therefore \ncannot be the basis upon which to impose a replacement rate.  In this case, moreover, the options \nare not of all one kind—some are fully available options now; others are not practical.  In fact, \nfour of the eight—options 1, 2, 3, and 8 (described below)—are currently available without any \n \n \n27 Id. at 44. \n28 Id. at 5."},{"page":10,"startToken":3003,"endToken":3320,"text":"10 \n \nchanges to the existing PJM Tariff.29  In contrast, the record in this proceeding demonstrates that \nthe potential options that would require changes to the PJM Tariff are unnecessary and have not \nbeen shown to be just and reasonable.  Therefore, no changes to the PJM Tariff may be directed \nunder FPA section 206 in this docket.  Indeed, PJM itself asserts that its tariff “remains just and \nreasonable.”30 \nThe potential options PJM presents are as follows: \n1. Load with a separate Point of Interconnection that is Network Load and the load uses \nand pays for Network Service, Energy, Ancillary Services, and Capacity.  \n2. Co-located load that is at the same Point of Interconnection but separately metered that \nis Network Load and the load uses and pays for Network Service, Energy, Ancillary \nServices, and Capacity.  Additionally, the large load is studied and could be connected \nto the grid pursuant to the existing Transmission Owner/electric distribution company \n(“EDC”) load interconnection process. \n3. Existing BTMG where the load is the customer, the BTMG rules apply, and the load \nuses and pays for Network Service, Energy, Ancillary Services, and Capacity based on \nthe net withdrawal quantity and dependent on if that withdrawal is during the Peak. \n4. Co-located load with connection to the grid with protections to avoid delivery of system \nenergy to serve the load, but relies on and takes grid services such as ancillary services \nand should pay its fair share of those charges, and carries a risk that should system \nprotections fail, significant energy would be drawn from the system.  \n \n \n29 PJM asserts that three of the options “already exist under PJM’s Tariff.”  Id.  Of course, only those that meet the \ntariff criteria would be eligible for the options.  For example, to participate in a demand response program, the load \nwould need to satisfy the various tariff criteria for demand response. \n30 Id. at 4, 32."},{"page":11,"startToken":3320,"endToken":3620,"text":"11 \n \n5. Co-located load with connection to the grid with protections to avoid delivery of system \nenergy to load (same as option 4) but allowed to use back-up service from PJM with \npermission.  Like option 4, it relies on and takes grid services such as ancillary services \nand should pay its fair share of those charges, and carries a risk that should system \nprotections fail, significant energy would be drawn from the system. \n6. Co-located load that elects to be Network Load and bring its own generation where \nlarge load additions interconnecting as Network Load could also bring to PJM \nadditional generation that could serve as Capacity Resources. \n7. Potential new non-capacity backed service as a Transitional Service, with a co-location \nconfiguration where load is curtailable. \n8. Co-located load participating in Demand Response, where load is Network Load and \nparticipates as a Demand Response resource. \nPJM’s options reinforce the straightforward conclusion that the existing PJM Tariff is just \nand reasonable.  Options 1, 2, 3, and 8 all lay out fact patterns for load that meets the needs \nidentified in this docket for co-located load.  Options 1 and 2 make clear that the addition of load \nat or near generation, whether or not it shares the same points of interconnection as a generator, \ncan be accomplished quickly and easily.  The load simply needs to agree to pay for the services \nthat all load receives and take service as Network Load.  No tariff amendments are needed to add \nload to the system.  Some commenters have claimed that netting load and generation that share an \ninterconnection is an important option for co-located load.31  Indeed, Option 3 demonstrates that a \npath to netting exists under the PJM Tariff, if in fact the particular arrangement has been configured \n \n \n31 See PSEG Answer at 13."},{"page":12,"startToken":3620,"endToken":3927,"text":"12 \n \nso that it does qualify as BTMG, as defined under the PJM Tariff.  Other entities have argued that \nco-located load can provide benefits to the system by relying on back-up generation or otherwise \nleaving the system under certain circumstances.  As Option 8 shows, demand response is a well-\nestablished regime for compensating load that agrees not to call on the system when required.  No \nnew tariff provisions are needed to accomplish that goal. \nPJM’s options make clear the high burden presented by FPA section 206 is not met here.  \nFor example, if co-located load wishes to be compensated for being interruptible, at the \ntransmission level,32 advocates of that position need to show why that outcome is the correct rate \ndesign and why the current demand response rules fail to adequately compensate load \nappropriately.  Such a showing has not been made for any of the currently available Tariff options.  \nAccordingly, PJM’s potential options that would require changes to the PJM Tariff do not present \na viable replacement rate, and PJM has not argued otherwise.  Indeed, PJM notes that it “does not \nmean to suggest that all identified ‘options’ . . . are equivalent, desirable, or even necessarily \nworkable.”33    \nb. Changes to the PJM Tariff May Undercut Reliability. \n \nThe North American Electric Reliability Corporation (“NERC”) has warned of impending \nreliability challenges that will attend the increased demand growth in PJM.34  This is important \nbecause the reasonableness of a rate, including any replacement rate set under FPA section 206, \n“is assessed in light of the FPA’s goals of promoting reliable service at reasonable rates and \n \n \n32 States, which regulate the general terms and conditions governing service to co-located end-use load, can and do \noffer optional or mandatory interruptible service rates. \n33 PJM Answer at 5. \n34 See Indicated TOs Answer at 3–4 (discussing NERC’s 2024 Long-Term Reliability Assessment)."},{"page":13,"startToken":3927,"endToken":4216,"text":"13 \n \ndeveloping plentiful energy supplies.”35  To treat co-located load as anything other than Network \nLoad would increase the risk of reliability failures and resource inadequacy in PJM.  As PJM \nexplained in its filing, “[i]f the co-located load is PJM Network Load, PJM and the Transmission \nOwners have means through existing Tariff provisions and agreements to obtain the information \nto have both sufficient visibility and sufficient control of this load and ensure the load could be \nserved reliably without compromising overall system reliability.”36  When co-located load is \nhidden and not appropriately accounted for, however, there is not only a cost-allocation problem, \nbut the study process is undermined and, consequently, PJM may be unable to adequately procure \nenough capacity to serve the load because the full load will not be accounted for in the Reliability \nPricing Model.  Nor would the full load be reliably and safely factored into both PJM’s \ntransmission planning and operations processes and protocols. \nThe Commission must prioritize the safety and reliability of the electric grid.   \nc. The Potential Options that Require Changes to the PJM Tariff Would Slow \nData Center Development, the Opposite of What the Commission Should \nEncourage. \n \nAs PJM and the Indicated TOs have asserted, the PJM Tariff remains just and reasonable, \nand no party has shown that the existing PJM Tariff is unjust and unreasonable.  As such, the \nCommission has no basis under FPA section 206 to implement any proposed changes to the PJM \nTariff.  Moreover, recognizing that several of PJM’s proposed options are wholly consistent with \nthe existing PJM Tariff further supports the Commission in providing additional guidance and \n \n \n35 Constellation Mystic Power, LLC v. FERC, 45 F.4th 1028, 1035 (D.C. Cir. 2022).   \n36 PJM Answer at 61."},{"page":14,"startToken":4216,"endToken":4520,"text":"14 \n \ncertainty through an order either stating affirmatively that is the case or simply terminating this \nproceeding.37     \nThe need to provide power to large load customers is clear and the best way to promote co-\nlocated large load customers is to provide all stakeholders—inclusive of customers, EDCs/load \nserving entities, transmission owners, and investors—with certainty, which the Commission can \nquickly accomplish by clarifying that co-located loads should seek service under the well-\nestablished, just and reasonable terms of the existing PJM Tariff.  It is also worth noting that any \nattempt to change the PJM Tariff would likely stymie data-center development, as such \nhypothetical new terms would require development through the PJM stakeholder process followed \nby Commission consideration and acceptance.  But no new terms are required.  The PJM Tariff \nalready allows co-located load to interconnect to the grid and rely on the grid as Network Load.  \nState-jurisdictional special contracts or rates can continue to provide other financial benefits to the \nco-located load.  But pursuing drastic changes to the PJM Tariff will only increase uncertainty—\nnot just about the development of infrastructure for large load customers but about the future of \nthe very grid that desperately needs development, a task that is only made more difficult when \ncertainty and regulatory clarity are undermined.  Not even PJM knows how its options would be \naffected by other provisions of the PJM Tariff.  As noted above, by its own admission, PJM’s \nproposed new options have not been vetted to determine if they are “desirable, or even necessarily \nworkable.”38   \n \n \n37 As explained above, to the extent to which the Commission thinks it would be helpful to have further clarity in the \nPJM Tariff, the Indicated TOs suggest considering whether the addition of their proposed co-located load definition \nwould improve the PJM Tariff.  \n38 Id. at 5."},{"page":15,"startToken":4520,"endToken":4777,"text":"15 \n \nIII. \nVistra’s Motion for Clarification Should Be Denied. \nOn April 4, 2025, Vistra filed a Motion for Clarification and Request for Expedited \nTreatment.  Vistra seeks the Commission’s interpretation of its order issued in November 2024 in \nDocket No. ER24-2172 (“Susquehanna ISA Proceeding”).39  According to Vistra, there is \nconfusion on the scope and holding of the Susquehanna ISA Order.  The Commission should reject \nVistra’s motion.  \nIn the Susquehanna ISA Proceeding, the Commission rejected the amended \ninterconnection agreement between Susquehanna Nuclear LLC, PJM, and PPL Electric Utilities \nCorporation because the Commission found that “PJM has not demonstrated that the proposed   \nnon-conforming provisions in the Amended ISA are necessary deviations from the pro forma ISA \ndue to specific reliability concerns, novel legal issues, or other unique factors.”40 \nOn April 10, 2025, the Commission issued in Docket No. ER24-2172, an Order Addressing \nArguments on Rehearing and Granting Clarification, In Part.41  Therein, the Commission \naddressed Vistra’s request for clarification in the Susquehanna ISA Proceeding.  In Susquehanna \nISA Rehearing Order, the Commission clarified that it “uses the necessary standard . . . to \ndetermine whether the filing of a non-conforming agreement is justified” and that the Susquehanna \nISA Order “does not prevent entities from filing non-conforming interconnection agreements to \naddress matters related to a generator serving co-located load, or prejudge any such future filing.”42  \n \n \n39 PJM Interconnection, L.L.C., 189 FERC ¶ 61,078 (2024) (“Susquehanna ISA Order”). \n40 Id. P 85. \n41 PJM Interconnection, L.L.C., 191 FERC ¶ 61,025 (2025) (“Susquehanna ISA Rehearing Order”). \n42 Id. P 30."},{"page":16,"startToken":4777,"endToken":4976,"text":"16 \n \nTherefore, Vistra’s request for clarification has been addressed and the April 4th motion submitted \nin this proceeding is moot. \nNo further clarification is needed in this proceeding.  Any attempt by Vistra to seek further \nclarification in this proceeding would amount to Vistra asking the Commission to tell PJM to alter \nits view on what is permissible under the PJM Tariff.  That is not an appropriate basis for the \nCommission to grant its motion for clarification in the instant proceeding. \nIV. \nConclusion \nFor the reasons stated above, the Indicated TOs respectfully request that the Commission \nfind that the existing PJM Tariff is just and reasonable, that co-located load can be served with the \nexisting forms of transmission service in the PJM Tariff, and that the Commission accordingly \nterminate this FPA section 206 proceeding and the above-captioned dockets. \n \nRespectfully submitted, \n \n \n \n \n/s/ William Sauer \nWilliam Sauer \nVice President, Federal Regulatory Affairs  \nExelon Corporation  \n701 Ninth St. N.W.  \nWashington, DC 20001  \nTelephone: 202-868-7499  \nEmail: william.sauer@exeloncorp.com   \n/s/ Max Minzner \n \nMax Minzner \nVice President and Deputy General Counsel \nExelon Corporation \n701 Ninth St. N.W.  \nWashington, DC 20001  \nTelephone: 202-934-4740 \nEmail: max.minzner@exeloncorp.com \n \n \nOn behalf of Exelon Corporation"},{"page":17,"startToken":4976,"endToken":5194,"text":"17 \n \n/s/ Jessica Cano \nJessica Cano \nAssistant General Counsel - FERC \nAmerican Electric Power Service Corporation \n1 Riverside Plaza  \nColumbus, OH 43215 \nTelephone: 614-716-2921  \nEmail: jacano@aep.com \n \n/s/ Lisa G. McAlister \nLisa G. McAlister \nAMP Transmission, LLC \n1111 Schrock Road, Suite 100 \nColumbus, Ohio 43229 \nTelephone: 614-540-6400 \nEmail: lmcalister@amppartners.org \n \nOn behalf of American Electric Power \nService Corporation \n \nOn behalf of AMP Transmission, LLC \n \n/s/ Martin J. Keane \nMartin J. Keane \nDirector of Public Utilities \nCleveland Public Power \n1300 Lakeside Ave. \nCleveland, OH 44114 \nTelephone: 216-664-2444 ext. 75604 \nEmail: martin_keane@clevelandwater.com \n \n/s/Debra D. Roby \nDebra D. Roby \nWashington Energy Law LLP \n900 17th Street N.W., Suite 500-A \nWashington, D.C. 20006 \nTelephone: 703-785-9270 \nEmail: droby@washingtonenergylaw.com \n \nOn behalf of City of Cleveland, Department of \nPublic Utilities, Division of Cleveland Public \nPower \n \nOn behalf of the City of Hamilton, OH \n \n/s/ Wesley Walker \nWesley Walker \nSenior Assistant General Counsel \nDominion Energy Services, Inc. \n120 Tredegar Street \nRichmond, VA 23219 \nTelephone: 804-819-2345 \nEmail: wesley.walker@dominionenergy.com \n \n/s/ Molly Suda  \nMolly Suda \nAssociate General Counsel \nAnnelise Rickert  \nFederal Government Affairs Director \nDuke Energy Corporation \n1301 Pennsylvania Ave NW, Suite 200 \nWashington, DC 20004 \nTelephone: 202-824-8011 \nEmail:  molly.suda@duke-energy.com  \nAnnelise.rickert@duke-energy.com         \n   \nOn behalf of Dominion Energy \nOn behalf of Duke Energy"},{"page":18,"startToken":5194,"endToken":5400,"text":"18 \n \n/s/ Michael Brechlin \nMichael Brechlin \nPA Bar # 335424 \nDuquesne Light Company \n411 7th Ave \nPittsburgh, PA 15219 \nTelephone: 412-393-6431 \nEmail: mbrechlin@duqlight.com \n/s/   Amanda P. Parker \nAmanda P. Parker \nAttorney \nFirstEnergy Service Company \n76 South Main Street \nAkron, OH 44308 \nTelephone: (330) 384-4592 \nEmail: aparker@firstenergycorp.com  \n \nOn behalf of Duquesne Light Company \nOn behalf of The FirstEnergy Transmission \nCompanies \n \n/s/ Denise R. Foster Cronin \nDenise R. Foster Cronin \nVice President, Federal and RTO Regulatory \nAffairs \nEast Kentucky Power Cooperative, Inc. \n4775 Lexington Road, P.O. Box 707 \nWinchester, KY 40392-0707 \nTelephone: 859-745-9615 \nEmail: denise.cronin@ekpc.coop \n \n/s/ Daniel E. Frank                  \nDaniel E. Frank \nKelly Cuthbertson \nEversheds Sutherland (US) LLP \n700 Sixth St., N.W., Suite 700 \nWashington, DC 20001-3980 \nTelephone: 202-383-0100 \nEmail:  \ndanielfrank@eversheds-sutherland.com \nkellycuthbertson@eversheds-sutherland.com \n \n \n \nOn Behalf of East Kentucky Power \nCooperative, Inc. \n \n/s/ Adrienne E. Clair \nAdrienne E. Clair \nThompson Coburn LLP \n1909 K Street, N.W., Suite 600 \nWashington, D.C.  20006-1167 \nTelephone: 202-585-6900 \nEmail: aclair@thompsoncoburn.com \n \n/s/ Steve Nadel \nSteven M. Nadel \nSenior Counsel \nPPL Services Corp.  \n645 Hamilton Street, Suite 601 \nAllentown, PA 18101 \nTelephone: 610-774-4775   \nEmail: SMNadel@pplweb.com \n \nOn behalf of Old Dominion Electric \nCooperative \n \nOn behalf of PPL Electric Utilities Corp."},{"page":19,"startToken":5400,"endToken":5609,"text":"19 \n \n/s/David Burns  \nDavid Burns  \nSenior Manager,  \nFERC Policy & Regulatory Affairs  \nConsolidated Edison Company of New York, \nInc.   \n4 Irving Place \nNew York, NY 10003   \nTelephone: 571-678-9152  \nEmail: burnsd@coned.com \n/s/Joshua Kirstein \nJoshua A. Kirstein  \nSenior Attorney  \nLaw Department \nConsolidated Edison Company of New York, \nInc.  \n4 Irving Place, 18th Floor  \nNew York, NY 10003  \nTelephone: 929-656-5971 \nEmail: kirsteinj@coned.com \n \n \nOn behalf of Rockland Electric Company \n \n/s/ Damon L. Krieger \nDamon L. Krieger \nGroup Vice President, Legal, Strategy, and \nSustainability, and Deputy General Counsel \nSouthern Maryland Electric Cooperative, Inc. \n15035 Burnt Store Road \nP.O. Box 1937 \nHughesville, Maryland 20637-1937 \nTelephone: 301-274-4323 \nEmail: Damon.Krieger@SMECO.coop \n \n/s/ Jeremy L. Fetty \n \nJeremy L. Fetty \nParr Richey \n251 N. Illinois, Suite 1800 \nIndianapolis, Indiana 46204  \nTelephone: 317-269-2500 \nEmail: j_fetty@wvpa.com \n \n \nOn behalf of Southern Maryland Electric \nCooperative \n \nOn behalf of Wabash Valley Power \nAssociation, Inc. \n \n/s/ Lindsay Berkstresser \nLindsay Berkstresser \nCounsel – Energy & Regulatory \nUGI Corporation \n500 North Gulph Road \nKing of Prussia, PA 19406 \nTelephone: 717-504-9925 \nEmail: berkstresserl@ugicorp.com \n \n/s/ Richard P. Bonnifield \nRichard P. Bonnifield \nHusch Blackwell \n1801 Pennsylvania Avenue, NW, \nSuite 1000 \nWashington, DC 20006-3606 \nTelephone: 202-243-8844 \nEmail: \nrichard.bonnifield@huschblackwell.com \n \n \n \nOn behalf of UGI Utilities Inc. \n \nApril 23, 2025"},{"page":20,"startToken":5609,"endToken":5655,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list in the above captioned dockets. \nDated at Chicago, IL this 23rd day of April, 2025. \n \n/s/ Geneva Kennedy  \nGeneva Kennedy  \nExelon Corporation"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":1206,"startToken":0,"endToken":537},{"p":2,"at":1206,"title":"I. Because the Requisite Showing Has Not Been Made Under Federal Power Act","method":"printed heading","endPage":9,"endAt":910,"startToken":537,"endToken":2876},{"p":9,"at":910,"title":"II. No Replacement Rate Is Necessary or Appropriate Under FPA Section 206.","method":"printed heading","endPage":15,"endAt":6,"startToken":2876,"endToken":4521},{"p":15,"at":6,"title":"III. Vistra’s Motion for Clarification Should Be Denied.","method":"printed heading","endPage":16,"endAt":505,"startToken":4521,"endToken":4857},{"p":16,"at":505,"title":"IV. Conclusion","method":"printed heading","endPage":20,"endAt":0,"startToken":4857,"endToken":5609},{"p":20,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":20,"endAt":295,"startToken":5609,"endToken":5655}]}