{"document":{"slug":"rec-20250423-5213","title":"Response of Enchanted Rock, LLC on the Order Instituting Proceeding Under Section 206 of the Federal Power Act and Consolidating with Other Proceedings","issued":"2025-04-23","accession":"20250423-5213","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Enchanted Rock, LLC","kind":"filing","file":"sources/filings/text/20250423-5213_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250423-5213","tier":"record","sha256":"29307f3748a7ec63a2b55bff4dbdd622fa2ead89a72a3839b40e415f8373a9aa","pages":41,"tokens":9783,"emptyPages":[],"textThemes":["colo","flex","study","cost"]},"pages":[{"page":1,"startToken":0,"endToken":268,"text":"UNITED STATES OF AMERICA  \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C., et al.\n)\nDocket No. EL25-49-000\nLarge Loads Co-located at Generating \nFacilities\n) \n) \n)\nDocket No. AD24-11-000\nConstellation Energy Generation, LLC \n     v.  \nPJM Interconnection, L.L.C.\n) \n) \n) \n)\nDocket No. EL25-20-000\n(consolidated)\nRESPONSE OF ENCHANTED ROCK, LLC \nEnchanted Rock, LLC (“Enchanted Rock”) submits this response (“Response”) in \nconnection with the Federal Energy Regulatory Commission (“Commission”)’s February 20, \n2025 “Order Instituting Proceeding under Section 206 of the Federal Power Act and \nConsolidating with Other Proceedings.”1  In the Show Cause Order, the Commission directed \nPJM Interconnection, L.L.C. (“PJM”) and the PJM transmission owners to show cause as to why \nthe PJM Open Access Transmission Tariff, the Amended and Restated Operating Agreement of \nPJM, and Reliability Assurance Agreement Among Load Serving Entities in the PJM Region \n(together, the “Tariff”)2 remains just and reasonable and not unduly discriminatory or \npreferential, or explain what changes to the Tariff would remedy the identified concerns if the \nCommission were to determine that the Tariff has become unjust and unreasonable or unduly \ndiscriminatory or preferential and establish a replacement Tariff.3\nEnchanted Rock submits this response in accordance with the Commission’s directive in \nthe Show Cause Order providing that interested entities may respond within 30 days of the show \ncause filings to address whether the Tariff remains just and reasonable and not unduly \n1 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115 (2025) (“Show Cause Order”). \n2 Capitalized terms not otherwise defined herein have the same meaning as in the Tariff. \n3 See Show Cause Order at P 2."},{"page":2,"startToken":268,"endToken":604,"text":"2 \ndiscriminatory or preferential, and if not, what changes to the Tariff should be implemented as a \nreplacement rate.4\nEnchanted Rock’s microgrids and state-of-the-art gas generators provide continuous, \ndependable power supply to customers including manufacturing facilities, data centers, hospitals, \nwater utilities, and other critical infrastructure.  Enchanted Rock submitted post-technical \nconference comments in AD24-11-0005 and appreciates the opportunity to further comment on \nco-location solutions to grid and resource adequacy challenges in PJM.   \nAs further described below, Enchanted Rock offers an additional option6 to facilitate co-\nlocation arrangements, which Enchanted Rock refers to herein as the Load Co-located with \nDispatchable Generation (“LCDG”) option.  Although the LCDG option is different than the \nNew Options proposed by PJM, the LCDG option shares characteristics similar to New Options \n6 and 7.  Changes to the Tariff are necessary to effectuate the LCDG option and, therefore, \nEnchanted Rock respectfully submits that PJM’s existing Tariff is not just and reasonable.7\nEnchanted Rock requests that the Commission issue an order directing replacement tariff \nprovisions that allow customers in PJM to realize the benefits of LCDG as a co-location option.  \nTo the extent the Commission determines that further proceedings—either before the \nCommission, or as part of PJM’s stakeholder process—are needed before directing any changes \nto PJM’s Tariff, Enchanted Rock is committed to working collaboratively with PJM and \nstakeholders to develop such necessary changes to the Tariff.8\n4 See Show Cause Order at Ordering Para (D).  \n5 Post-Technical Conference Comments of Enchanted Rock, LLC, Docket No. AD24-11-000 (Dec. 9, 2024) (“Post-\nTech. Comments”). \n6 PJM presented eight existing or new co-location options (“New Options”).  See Answer of PJM Interconnection, \nL.L.C., Docket Nos. EL25-49-000, et al. (Mar. 24, 2025) (“PJM Answer”).  \n7 In support of the LCDG option, Enchanted Rock presents the Affidavit of Dr. Albert W. Bremser, included \nherewith as Attachment A (“Bremser Affidavit”).  See Bremser Affidavit ¶¶ 9-20.  \n8 Enchanted Rock, through its subsidiary Electranet REP I, LLC, is a member of PJM and participates through the \nOther Supplier sector."},{"page":3,"startToken":604,"endToken":970,"text":"3 \nI.\nINTRODUCTION AND NEED FOR REFORM \nThe United States stands at the precipice of an unprecedented surge in electricity demand \nfrom large loads including data centers and large industrial and manufacturing facilities.9\nExtraordinary load growth is fueled mostly by the proliferation of data centers that support \nartificial intelligence, cloud computing, and other services.  Over the next 15 years, PJM \nanticipates significant peak demand growth, with the summer peak rising by roughly 70 \ngigawatts (“GW”), and the winter peak rising by roughly 65 GW.10  Enchanted Rock understands \nthat securing a global competitive advantage in artificial intelligence is a U.S. priority and that \nmaintaining data centers within U.S. borders is a critical national security interest.11  These \nextraordinary changes in demand require federal and state regulators, grid operators, market \nparticipants, and customers to pivot and look to innovations that optimize infrastructure without \ncreating new reliability risks—particularly during periods when new generation capacity and \ntransmission infrastructure is planned, permitted, and constructed.  The accelerating demand for \nelectricity coupled with supply delays caused by lengthy permitting processes for generation and \ntransmission infrastructure, as well as persistent supply chain delays for equipment, means the \nindustry must devise immediately implementable solutions that optimize existing infrastructure \nand ensure that transmission expansion occurs in the most cost-effective way possible. \n9 See Large Loads Co-Located at General Facilities Technical Conference Transcript, Docket No. AD24-11-000, \n10:25 – 11:6 (Nov. 1, 2024) (“Technical Conf. Tr”) (Commissioner Christie stating “we’re seeing load forecasts \nshooting up . . . driven by data centers”). \n10 See Asim Z. Haque, Sr. Vice President – Governmental and Member Services, PJM Interconnection, L.L.C., \nTestimony before the U.S. House of Representatives, Committee on Energy & Commerce, Subcommittee on Energy \n(Mar. 5, 2025), available at: https://www.pjm.com/-/media/DotCom/library/reports-\nnotices/testimony/2025/20250305-haque-testimony-us-house-committee-on-energy-commerce.pdf. \n11 See Energy Subcommittee: “Scaling for Growth: Meeting the Demand for Reliable, Affordable Electricity” \nhttps://energycommerce.house.gov/events/energy-subcommittee-scaling-for-growth-meeting-the-demand-for-\nreliable-affordable-electricity (Rep. Gary Palmer (R-AL) stating “My concern today is we’re in an arms race for \nartificial intelligence,” “And it’s clear we don’t have the capacity to build the data systems that we need in order to \nwin that arms race with China.”)."},{"page":4,"startToken":970,"endToken":1341,"text":"4 \nThe Commission has already started work—issuing landmark rulemakings to improve the \nnation’s generator interconnection processes (via Order No. 202312), regional transmission \nplanning and cost allocation processes (via Order No. 192013), siting interstate electric \ntransmission facilities (via Order No. 197714), and increasing transmission capacity through \nambient-adjusted transmission facility ratings (via Order No. 88115).  However, the full benefits \nof these rules have not yet been realized and will not be enough in the time horizon needed to \nsupport interconnection of, and service to, large loads.  Even with new procedures to secure \nneeded generation capacity through surplus interconnection and expedited interconnection \nprocesses,16 PJM will still be challenged to meet the needs of rapidly growing demand, \nparticularly for the artificial intelligence race. \nThese challenges underscore the urgent need for innovative solutions.  A recent white \npaper from Duke University, entitled “Rethinking Load Growth,” published by the Nicholas \nInstitute for Energy, Environment & Sustainability highlights that the U.S. power system has \nsubstantial headroom due to planning decisions to maintain reserves for infrequent peak demand \nevents.17  By strategically curtailing their load during peak periods, flexible loads can tap into \nthis existing headroom,18 allowing the grid to reliably and safely accommodate more load \nwithout requiring significant infrastructure upgrades.  According to the report, 98 GW of new \n12 See Improvements to Generator Interconnection Procedures and Agreements, Order No. 2023, 184 FERC ¶ \n61,054 (2023). \n13 See Building for the Future Through Electric Regional Transmission Planning and Cost Allocation, Order \nNo.1920, 187 FERC ¶ 61,068, order on rehearing and clarification, Order No. 1920-A, 189 FERC ¶ 61,126 (2024). \n14 See Applications for Permits to Site Interstate Electric Transmission Facilities, Order No. 1977, 187 FERC ¶ \n61,069 (2024). \n15 See Managing Transmission Line Ratings, Order No. 881, 177 FERC ¶ 61,179 (2021). \n16 See PJM Interconnection, L.L.C., 190 FERC ¶ 61,083 (2025); PJM Interconnection, L.L.C., 190 FERC ¶ 61,084 \n(2025). \n17 See Tyler H. Norris, Tim Profeta, Dalia Patino-Echeverri, and Adam Cowie-Haskell, Rethinking Load Growth: \nAssessing the Potential for Integration of Large Flexible Loads in US Power Systems, Nicholas Institute for Energy, \nEnvironment & Sustainability (2025), available at: \nhttps://nicholasinstitute.duke.edu/sites/default/files/publications/rethinking-load-growth.pdf.  \n18 See Bremser Affidavit ¶¶ 13-17."},{"page":5,"startToken":1341,"endToken":1747,"text":"5 \nload—equivalent to more than 10% of the nation’s current aggregate peak demand—could be \nintegrated at an average annual load curtailment rate of 0.5%, and 126 GW at a rate of 1.0%.19\nIn other words, the grid can accommodate a significant increase in demand if users are flexible \nand reduce their usage during system stress, which can occur during any time of the year, such as \nduring the summer and winter peaks and during unplanned and planned transmission and \ngenerator outages in shoulder months. \nA risk exists that investments in new infrastructure responsive to the demand boom may, \nultimately, be underutilized.20  Flexibility can hedge against this uncertainty by enabling a more \ngradual and adaptive approach to infrastructure development as a temporary measure until such \ntime that new infrastructure can be built.  To bridge the timeline for construction of large-scale \ncapacity expansion, flexible arrangements like the LCDG option can reduce demand during \nperiods of system stress, whenever they may occur, in the interim.21  Enabling a temporary \nflexibility option that large loads can opt into would therefore mitigate some of these risks and \nallow for faster load interconnection.  Further, recognizing that load forecasting discussions \naround the country have coalesced around the need for greater transparency, Enchanted Rock \nbelieves that an opportunity exists for load forecasting practices to allow for greater granularity \nand to take into account more sophisticated concepts of flexibility, as the LCDG option would \nprovide. \n19 See Tyler H. Norris, Tim Profeta, Dalia Patino-Echeverri, and Adam Cowie-Haskell, Rethinking Load Growth: \nAssessing the Potential for Integration of Large Flexible Loads in US Power Systems, Figure 1, Nicholas Institute \nfor Energy, Environment & Sustainability (2025), available at: \nhttps://nicholasinstitute.duke.edu/sites/default/files/publications/rethinking-load-growth.pdf\n20 See, e.g., PJM Answer at 66 (“With any forecast of future load growth, additional transmission and generation \ncapacity may be required, and there is the risk of overbuilding due to a forecast that is too high, or underbuilding due \nto a forecast that is too low. The same is true with respect to large load additions, regardless of whether the load is \nco-located with generation. Given the potential size of these individual, large load additions that are in the forecast, \nuncertainty with respect to whether the large loads are actually added to the system could cause either overbuild or \nunderbuild to occur based on a single customer addition.”). \n21 See Bremser Affidavit ¶¶ 18-19."},{"page":6,"startToken":1747,"endToken":1945,"text":"6 \nAs Commissioner Rosner recently recognized, flexibility is critical for addressing the \nrapid increase in the country’s electricity demand.22  As such, Enchanted Rock respectfully urges \nthe Commission to direct changes to PJM’s Tariff to effectuate the LCDG option in order to \nfacilitate large load flexibility in PJM.\nII.\nLCDG OPTION: LOAD CO-LOCATED WITH DISPATCHABLE GENERATION  \nAs PJM demonstrates in its answer, co-location may exist through a spectrum of different \nconfigurations.23  Enchanted Rock agrees.  At one end of the spectrum is what Enchanted Rock \nwould describe as “Complete Electrical Isolation,” where the load and generation are entirely \nself-sufficient and islanded; at the other end is “Full Grid Integration,” with unrestricted power \nexchange with the grid, operating as a fully integrated load, using exclusively grid-sourced \nenergy and capacity.  As shown below in Figure 1, between these two extremes (but closer to \nFull Grid Integration, as shown below) lies “Flexible Grid Integration,” which the LCDG option \nwould facilitate.   \nFigure 1 \n22 See Technical Conf. Tr at 96:1-7 (Commissioner Rosner acknowledging the value of “flexibility of large load” \ngiven the “really rapid increase in demand”). \n23 See, e.g., PJM Answer, Exhibit A (Options for Service to Large Loads)."},{"page":7,"startToken":1945,"endToken":2138,"text":"7 \nUnder Enchanted Rock’s view, Flexible Grid Integration is a co-location arrangement \nthat relies on the PJM-operated transmission network for grid-sourced energy but provides \nflexibility commitments through dispatch of the customer’s co-located dispatchable generation \nduring periods of system stress.  Flexible Grid Integration facilitates a system committed to grid-\nsourced energy and regulated markets, integrates large loads into system planning, provides \noperational transparency into large loads, and enhances grid operator capabilities by giving large \nloads the opportunity to provide flexibility when grid operators need it. \nEnchanted Rock’s LCDG option, a type of Flexible Grid Integration, shares \ncharacteristics with PJM New Options 6 and 7, while also offering additional functionality.  The \npremise of the LCDG option is that load flexibility provides substantial benefits to a constrained \nsystem.  Load flexibility is key to accelerating large load interconnections and optimizing the \nefficient and cost-effective utilization of grid infrastructure.  Under the LCDG option, load and \ngeneration may be separately metered but are studied together for purposes of retail load \ninterconnection and integration, transmission and resource adequacy planning, and operations.   \nTable 1 below summarizes the key components of Enchanted Rock’s LCDG option, \nwhich is discussed in further detail herein."},{"page":8,"startToken":2138,"endToken":2651,"text":"8 \nTable 1\nEnchanted Rock’s LCDG Option24\nDescription \nThe LCDG option applies to co-located load that takes Interruptible Service and Available \nTransmission Capacity Service (which, as defined and discussed below, is load willing to \n“curtail” in advance of Emergency Procedures), and self-supplies generation. \nThe LCDG option includes two-phases, providing an opportunity for load to bring-its-own \ngeneration when transmission or generation capacity on the system is not sufficient for full \nintegration, thereby expediting interconnection and dispatch. \nDuring the waiting period for new transmission, or “Phase 1,” large load is treated as a non-\ncapacity backed load and avoids generation capacity costs in exchange for making firm \ncommitments to support reliability in advance of emergency conditions via the dispatch of co-\nlocated generation.  Large load also avoids paying full Network Integration Transmission \nService (“NITS”) costs as non-Network Load, and instead will pay for Available Transmission \nCapacity Service (defined below), which would allow load to access generation on the network \nduring time periods when there is available transmission capacity. \nDuring “Phase 2,” the load transitions to full Network status through existing PJM Tariff \nprocesses, once system upgrades are in place, or broader resource adequacy concerns are \nresolved. \nThe LCDG generator would act to curtail load, if necessary, during Phase 1.  In Phase 2, to the \nextent the Commission orders fast-track interconnection processes consistent with PJM Option \n6, the LCDG generation would also be eligible to be accelerated through the interconnection \nprocess.\nPJM Preference \nN/A \nLoad Status \nDuring Phase 1, LCDG load would have non-Network status, subject to advance curtailment \nby PJM.  LCDG generation could be committed to be dispatched to co-located load during \nPJM curtailment events (consistent with applicable provisions of the PJM Tariff). \nDuring Phase 2, the co-located load would be classified as full Network Load.\nGeneration Capacity Status \nNo, while in Phase 1. \nCapacity eligible during Phase 2. \nPJM obligation to serve load \nYes, but lower priority (interruptible) during Phase 1 \nYes, with standard priority during Phase 2\nLoad System Used and Charged \nAvailable Transmission Capacity Service, during Phase 1. \nNITS (full load during coincident peak), Energy, Capacity (Full load during coincident peak) \nduring Phase 2. \nAncillary Services Used \nReactive, Black Start, Regulation, Sync, Non Sync, Day-ahead Scheduling Reserves\nAncillary Services Charged \nReactive, Black Start, Regulation, Sync, during Phase 1. \nReactive, Black Start, Regulation, Sync, Non Sync, Day-ahead Scheduling Reserves, during \nPhase 2.\nGeneration Revenue \nCapacity (based on full CIRs), during Phase 2 \nEnergy and Ancillary Services (based on entire generation output to grid), during Phase 2 \nCapacity-Related Studies \n•TO Load Integration study (Phase 2) \n•PJM Do No Harm study (Phase 2) \n•RTEP process inclusive of Load Forecast (Phase 2) \n•Necessary Study (Phase 2)  \n•Generator Interconnection Study (Phase 2) \nIncluded in Load Forecast (RTEP) \nYes  \nIncluded in RPM Reliability \nRequirement \nNo, for non-capacity backed load, during Phase 1 \nYes for load; CIRs included in RPM, during Phase 2. \n24 Enchanted Rock recognizes that the LCDG option may be subject to state laws that affect when and how load in a \njurisdiction can be served by a supplier other than a franchised public utility."},{"page":9,"startToken":2651,"endToken":2957,"text":"9 \nCost Allocation for Interconnection \nUpgrades \n• Supplemental projects pursuant to local TO methodology (Phase 2) \n• RTEP upgrades pursuant to RTEP cost allocation (Phase 2) \n• Generator for the changes to its facility to accommodate the load (Phase 2) \nSystem Protection Requirements \nN/A \nDemand Response Eligibility \nNo \nTariff Modifications \nYes \nThe LCDG option provides more than a traditional demand response or peak shaving \nprogram during the operating period.  The flexibility provided by the LCDG option would be \nconsidered in the planning and study process for large load interconnection, local and regional \nplanning, and resource adequacy.  The LCDG option therefore permits large loads to utilize \nflexibility to achieve faster interconnection through the deployment of dispatchable, co-located \ngeneration.  Under the LCDG option, the firm commitment to dispatch co-located generation \nwould serve as a bridge to permanent grid upgrades for projects that would otherwise be delayed \nwhile new infrastructure is planned, permitted, and constructed.  \nSpecifically, under Phase 1 of Enchanted Rock’s proposal, LCDG load would be treated \nas curtailable non-Network Load, subscribing to Interruptible Service (as contemplated in PJM’s \nNew Option 7) for generation service, and subscribing to Enchanted Rock’s proposed Available \nTransmission Capacity Service for transmission service.  Under Phase 1, LCDG generators \nwould be classified as non-Network Resources (i.e., interconnected on a non-network basis), and \nwould be limited to serving the co-located load’s main function of reducing or zeroing demand.25\nUnder Phase 2, LCDG load would be eligible to go through the normal PJM Tariff \nprocess as Network Load, when PJM deems that the supply/demand conditions are no longer \nconstrained, and necessary transmission infrastructure (e.g., Network Upgrades) have been \n25 Additionally, during Phase 1, the Commission and PJM should allow the LCDG generators to participate in PJM’s \nwholesale markets and earn revenue for the services they are capable of providing consistent with the PJM Tariff."},{"page":10,"startToken":2957,"endToken":3226,"text":"10 \nconstructed and placed into service.  Unlike PJM’s New Option 6, LCDG load would not be \nNetwork Load, but would utilize Interruptible Service as a non-Network Load (i.e., for \ngeneration service) as contemplated in PJM’s New Option 7. \nMoreover, during Phase 1, the LCDG generator would act to curtail load (to the extent \nnecessary).  Under Phase 2, LCDG generators would be eligible to go through the normal PJM \nTariff process as a Network Resource and fast tracked through the generator interconnection \nprocess to the extent allowed by the Commission (e.g., consistent with PJM New Option 6).  \nNotably, new load may be incentivized to self-supply generation if that generation were eligible \nto be fast-tracked in the generator interconnection process.   \nAdditionally, under Phase 1, Enchanted Rock proposes that projects choosing the LCDG \noption take a variation of non-firm transmission service to be called Available Transmission \nCapacity Service (“ATCS”),26 with commitments to dispatch co-located generation during PJM \ncurtailments.  ATCS would be a transitional option available only until the transmission \ninfrastructure is constructed and the utility is able to serve the load taking full network \ntransmission service.  The proposed ATCS would allow load to access generation on the network \nduring time periods when there is available transmission capacity.  Given the firm service nature \nof NITS, it would be appropriate to provide a new solution to unlock the unused capacity as \ninterim transmission service for co-located arrangements.27\nSimilar to ERCOT’s “Connect and Manage” process for generation resources which \nexpedites the interconnection of new generation resources by prioritizing local grid connections \n26 See Bremser Affidavit ¶¶ 6, 12-19\n27 See id. ¶¶ 12-19."},{"page":11,"startToken":3226,"endToken":3507,"text":"11 \nand managing broader system impacts in real-time operations,28 LCDG projects create a \n“Connect and Manage” option for large loads that make firm commitments to dispatch their co-\nlocated generation.  During periods of grid stress in the waiting period, PJM operators would \ndirect the dispatch available megawatts (“MWs”) of LCDG generation so that the LCDG load \nreduces electricity consumption from the grid.  In the event LCDG generation fails to respond to \ndispatch instructions, the LCDG load would need to be curtailed to provide the requested \nresponse.   \nEnchanted Rock expects that LCDG generation would be dispatched only for a small \nnumber of hours per year.  As shown below in Figure 2, a typical load duration curve (the blue \nline) reflects the entire annual hourly load for 8760 hours.  The orange line represents a \nhypothetical addition of X MWs from data centers.  Data centers typically have baseload \ncomputing needs and exceptionally high load factors29 due to their high uptime requirements \nnecessary to align with customer needs,30 meaning that the applicable curve will just shift \nupwards by that amount. \n28 See ERCOT Interconnection Process: Generation Entity Winter Weather Preparedness Workship, 2 (Oct. 28, \n2024), available at: https://www.ercot.com/files/docs/2024/10/30/0940-AM-ERCOT-Interconnection-Process-\nGeneration-Entity-Winter-Weather-Preparedness-Fernandes.pdf. \n29 See I. Riu, D. Smiley, S. Bessasparis, K. Patel, Load Growth Is Here to Stay, but Are Data Centers?: Strategically \nManaging the Challenges and Opportunities of Load Growth, Energy and Environmental Economics, Inc. (Jul. \n2024), available at: https://www.ethree.com/wp-content/uploads/2024/07/E3-White-Paper-2024-Load-Growth-Is-\nHere-to-Stay-but-Are-Data-Centers-2.pdf. \n30 See The Data Center, The Importance of Uptime in the Data Center (Sept. 11, 2019), available at: \nhttps://datacenter.com/news_and_insight/the-importance-of-uptime-in-the-data-center/."},{"page":12,"startToken":3507,"endToken":3586,"text":"12\nFigure 2 \nFigure 2. Load (blue), plus hypothetical X MWs of data centers (orange), all X MWs of data centers utilize co-\nlocated dispatchable generation during the highest load hours of the year (green)\nIn this way, LCDG projects would support efficient utilization of existing generation and \ntransmission capacity, lowering costs for customers of the existing transmission system, and \nbuying time for new infrastructure necessary to serve the load on a firm basis to be placed in \nservice."},{"page":13,"startToken":3586,"endToken":3869,"text":"13 \nIII.\nENCHANTED ROCK’S RESPONSE TO SELECTED COMMISSION \nQUESTIONS \na. General \niv. Parties may also address how co-located loads are similar to or disparate \nfrom other types of arrangements where load and generation share the same \npoint of interconnection (such as Behind the Meter Generation as defined in \nPJM’s Tariff or non-retail behind the meter generation). \nEnchanted Rock’s Response: \nUnlike LCDG, the Behind the Meter Generation (“BTMG”) construct assumes \ncontinuous supply if the load cannot draw from the transmission network, whereas a more \nflexible solution would allow for periodic supply to load but continued access to the transmission \nnetwork during normal operating conditions.  BTMG assets can reduce customers’ capacity and \ntransmission demand payments via full netting of the load, whereas LCDG projects temporarily \nrelieve constraints on existing infrastructure allowing for immediate utilization of idle or \nunderutilized transmission capacity for faster load interconnections. \nd. Interconnection Procedures and Cost Allocation \nii. Please explain whether PJM’s necessary study process allows a colocation \narrangement to demonstrate its capability to flexibly adjust its withdrawals \nfrom or injections to the transmission system (e.g., by using secondary \nbackup generation or by curtailing on-site load), and reflect this capability in \nthe operating assumptions PJM considers when estimating the co-location \narrangement’s impacts on the transmission system?  If not, would it be \nappropriate to establish a new or revised study process that allows for such a \ndemonstration? \nEnchanted Rock’s Response: \nCurrently, load and generation interconnection requests are studied separately.  This \ndisjointed approach creates several issues, particularly for co-located arrangements where the \nload and generation components are intended to function as an integrated system.  First, it can \nlead to a mismatch in timing.  The generation and load portions of a co-located arrangement may"},{"page":14,"startToken":3869,"endToken":4130,"text":"14 \nface different timelines for interconnection, making it challenging to bring the entire facility \nonline in a coordinated manner.  This mismatch in study timelines can delay project completion \nand create bottlenecks, as project timelines become constrained by the interconnection study \nprocess with the longest duration.  \nSecond, separate studies fail to account for the interdependencies between the load and \ngeneration components of a co-located arrangement.  When studies are conducted independently, \nthe load interconnection study may not consider the impact of the co-located generation, and vice \nversa.  This can result in inaccurate assessments of the necessary transmission upgrades and can \nlead to inefficient interconnection solutions.  \nRecognizing and respecting jurisdictional boundaries between load and generator \ninterconnections, Enchanted Rock recommends improving coordination so that grid planners in \nmultiple jurisdictions can gain a more accurate understanding of the co-located arrangement’s \noverall impact on the grid.  For example, by enabling the generation component to offset some of \nthe load’s impact on the grid, it may defer the need for certain upgrades for reliable \ninterconnection until such time that infrastructure expansion can occur.  Consideration for co-\nlocated arrangements in the retail load integration process would also allow for faster load \ninterconnections and mitigates commercial risks for both load and generation developers.  \nFacilitating improved coordination aligns with the response to the Show Cause Order of certain \nindicated transmission owners in PJM, which transmission owners also emphasized the need to \nvalue load flexibility in the overall planning process.31\n31 See Answer of the Indicated PJM Transmission Owners, Docket Nos. EL25-49-000, et al., Attachment A at 13 \n(Mar. 24, 2025)."},{"page":15,"startToken":4130,"endToken":4391,"text":"15 \nvii. Please explain whether changes to interconnection procedures and \nagreements are necessary to accommodate new generation interconnecting \nwith co-located load, including whether the existing queue process is \nsufficient for such arrangements. \nEnchanted Rock’s Response: \nPJM’s interconnection procedures were developed for generation-only projects, not co-\nlocated arrangements, which by their nature, integrate generation and load to function as a \nunified resource, yet the separate processes fail to recognize this fundamental characteristic.  \nThis separation manifests in several critical ways within the interconnection process: \n·\nUncoordinated Studies: the generation interconnection study (mainly FERC-\njurisdictional) and the load interconnection study (mainly state-jurisdictional) are \nfrequently conducted independently, without proper consideration of co-located \narrangements’ combined impact. \n·\nTiming Mismatches: the separate processes can result in different timelines for \ninterconnecting generation and load at co-located arrangements. This can create \nsignificant delays and logistical hurdles for co-located projects.  \n·\nInadequate Agreements: existing interconnection agreements are generally designed for \neither standalone generation facilities or standalone loads and may not contain the \nnecessary provisions to address the unique operational arrangements of co-located \nfacilities. \n·\nQueue Management: generator interconnection study processes and queues may not \nadequately recognize the benefits that co-located arrangements can provide and may \nrequire reforms to prioritize the grid flexibility benefits offered by co-located \narrangements, like LCDG projects. \nMoreover, to the extent that the Commission orders an accelerated interconnection \nprocess consistent with PJM’s proposed Option 6, LCDG projects should also be permitted to \nparticipate in any accelerated interconnection process for any generation co-located with load.  \nFacilitating the integration of LCDG projects will incentivize the development of resources that \nalign with grid needs."},{"page":16,"startToken":4391,"endToken":4672,"text":"16 \nf.  Other \nii. Please discuss whether back-up service can provide benefits to customers \nor otherwise help minimize system costs, including with specific examples or \nbest practices, if possible. \nEnchanted Rock’s Response: \nBackup generators can indeed provide benefits to customers and help minimize system \ncosts.  Large loads, like data centers, may already have capital and ongoing expenses earmarked \nfor backup generation to maintain operational continuity during disruptions of their primary \npower source as a matter of normal planning.  In PJM’s Option 8, PJM appears to suggest that \nthe easing of existing restrictions, such as EPA’s National Emission Standards for Hazardous Air \nPollutants (NESHAP), particularly for Tier 2 diesel generators, could be low hanging fruit to add \nto the supply stack as grid servicing assets via demand response. \nHowever, the proposition to relax environmental constraints on Tier 2 diesel generators \nwarrants careful scrutiny.  While such a measure may appear to offer increased flexibility in grid \nmanagement and demand response, it is ultimately unnecessary and potentially \ncounterproductive, given the readily available and cost-competitive cleaner alternatives.  Natural \ngas generators, for example, present a superior emissions profile,32 yielding lower levels of \nparticulate matter (PM), sulfur oxides (SOX), and nitrogen oxides (NOX).  Additionally, diesel \ngenerators carry risks related to fuel availability and delivery, especially after widespread \noutages when a surge in demand from numerous diesel users simultaneously attempting to refuel \nGWs of backup generation capacity can quickly overwhelm supply chains. \nWhile the relaxation of environmental limits on Tier 2 diesel generators may offer a \nseemingly expedient solution for valuing backup power in the supply stack, the adoption of \n32 Enchanted Rock Fact Sheet (last visited April 23, 2025), available at: https://enchantedrock.com/enchanted-rock-\nfact-sheet/."},{"page":17,"startToken":4672,"endToken":4940,"text":"17 \nEnchanted Rock’s proposed LCDG option would encourage large loads to adopt commercially \navailable generation technologies that can improve flexibility on the grid and ultimately provide \nresource adequacy value to the grid without special environmental waivers. \niii. Parties may also choose to address how co-location arrangements may \nprovide benefits, including potentially reducing required transmission \nupgrades to interconnect large loads, reducing congestion, or providing   \noperational flexibility during system peaks or emergencies. \nEnchanted Rock’s Response: \nCo-location arrangements, particularly those involving LCDG, can provide several \nbenefits to the grid and its operation.  By deploying dispatchable co-located generation, a large \nload can effectively become an interruptible load.  If this capability is valued in the transmission \nplanning process before load interconnection, it may allow grid planners to defer the need for \ncertain transmission upgrades that would otherwise be required to serve the new load.  The co-\nlocated generation can be used to offset the load’s impact on the grid during peak demand and \nstress periods.  \nIn PJM utility territories that rely heavily on centralized transmission and lack sufficient \nlocal generation, co-location arrangements can help reduce congestion and backfill any required \ntransmission contingencies in the interim as new transmission is built to solve the violations.  In \nmost cases, these co-located arrangements can even be configured to export excess generation to \nthe grid because normal industry practice is to oversize backup generation for redundancy \npurposes. This capability helps to stabilize the grid, avert blackouts, and optimize the utilization \nof existing grid infrastructure. \nCo-location also contributes to improve overall system efficiency by reducing \ntransmission line losses, which represent a not insignificant portion of the total electricity"},{"page":18,"startToken":4940,"endToken":5236,"text":"18 \ngenerated, with some amount lost between the generation source and the end-use customer.33\nThe amount of energy lost is dependent on factors such as the distance the electricity travels, the \ncharacteristics of the transmission lines, and the level of current flowing through the lines.  By \nlocating generation sources closer to load, co-location arrangements minimize the distance that \nelectricity needs to travel across the transmission network.  Lower transmission losses mean that \nless electricity needs to be generated to serve the same amount of load, freeing up capacity on \nexisting transmission infrastructure for use by other customers. \niv. Parties may also address whether, and if so, how, the Tariff should be \nmodified to best accommodate or encourage co-location arrangements to be \nconstructed in such a way as to minimize total system costs or otherwise \nprovide certain benefits, including protections for existing customers and    \nallocation of costs consistent with the cost-causation principle. \nEnchanted Rock’s Response: \nFor the reasons described herein, Enchanted Rock respectfully submits that the PJM \nTariff should be modified to adopt Enchanted Rock’s LCDG option as outlined above, including \nthe proposed Available Transmission Capacity Service.34  Enchanted Rock’s proposed LCDG \noption would encourage co-location of dispatchable generation with new loads at a time when \nresource adequacy is being challenged and markets are expecting to continue to deal with thin \nreserve margins going forward.  In essence, a combination of PJM’s New Option 6 and New \nOption 7, with additional transmission-related considerations, would enable LCDG projects to \nprovide their full value to the grid.   \n33 See EIA, Frequently Asked Questions: How much Electricity is Lost in Electricity Transmission and Distribution \nin the United States (Nov. 7, 2023), available at: https://www.eia.gov/tools/faqs/faq.php?id=105&t=3. \n34 See Bremser Affidavit ¶¶ 6, 12-19."},{"page":19,"startToken":5236,"endToken":5350,"text":"19 \nIV.\nCONCLUSION \nWherefore, for the foregoing reasons, Enchanted Rock respectfully requests that the \nCommission consider the Response, and the recommendations of Enchanted Rock. \nJoel Yu \nSenior Vice President, Policy & External \nAffairs \nEnchanted Rock, LLC \n1113 Vine Street, Suite 101\nHouston, TX 77002  \nJyu@enchantedrock.com\nJames Huang  \nDirector, Wholesale Markets Policy \nEnchanted Rock, LLC \n1113 Vine Street, Suite 101 \nHouston, TX 77002 \nJhuang@enchantedrock.com \nRespectfully submitted, \n/s/ Steven Shparber \nSteven Shparber \nOmar Bustami \nMintz, Levin, Cohn, Ferris, Glovsky and \nPopeo, P.C. \n555 12th Street NW, Suite 1100 \nWashington, D.C. 20004 \n(202) 434-7417 \nSShparber@mintz.com \nOBustami@mintz.com \nCounsel to Enchanted Rock, LLC\nEnclosed: Attachment A \nDated: April 23, 2025"},{"page":20,"startToken":5350,"endToken":5401,"text":"CERTIFICATE OF SERVICE\nI hereby certify that I have this day caused the foregoing and its attachment to be served \nupon each person designated on the official service list compiled by the Secretary in the captioned \nproceedings. \nDated at Washington, D.C., this 23rd day of April, 2025. \n/s/ Steven Shparber"},{"page":21,"startToken":5401,"endToken":5409,"text":"Attachment A \nAffidavit of Dr. Albert W. Bremser"},{"page":22,"startToken":5409,"endToken":5465,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C. \n) \n                      Docket No. EL25-49-000 \nLarge Loads Co-Located at Generating \n)  \nDocket No. AD24-11-000 \nFacilities \n) \nConstellation Energy Generation, LLC \n) \nDocket No. EL25-20-000 \n) \n(consolidated) \nv. \n) \n) \nPJM Interconnection, L.L.C. \n) \nAffidavit of Dr. Albert W. Bremser \non behalf of Enchanted Rock, LLC \nApril 23, 2025"},{"page":23,"startToken":5465,"endToken":5528,"text":"PJM Interconnection, L.L.C. \nDocket No. EL25-49-000 \nDr. Bremser Affidavit \nPage ii of ii\nTABLE OF CONTENTS\nHEADING\nPAGE\nI.\nINTRODUCTION ............................................................................................................... 1\nII.\nAFFIDAVIT PURPOSE AND SUMMARY CONCLUSIONS ....................................... 2\nIII.\nREASONS TO UPDATE THE PJM TARIFF (POTENTIAL ISSUES WITH THE \nCURRENT PJM TARIFF) ................................................................................................. 3\nIV.\nAVAILABLE TRANSMISSION CAPACITY SERVICE .............................................. 3\nLIST OF ATTACHMENTS \nATTACHMENT NO. 1 \nCURRICULUM VITAE OF ALBERT W. BREMSER"},{"page":24,"startToken":5528,"endToken":5780,"text":"PJM Interconnection, L.L.C. \nDocket No. EL25-49-000 \nDr. Bremser Affidavit \nPage 1 of 8 \nAFFIDAVIT \nOF DR. ALBERT W. BREMSER \nI.\nINTRODUCTION \n1. My name is Albert W. Bremser.  My business address is 11401 Lamar Ave., Overland \nPark, Kansas 66221.  Black and Veatch Corporation employs me as a Principal \nConsultant.  My responsibilities include providing advisory services that address the \nstrategic, financial, and regulatory advisory needs of energy and utility clients.  \n2. I am a financial economist with over twenty years of experience involving energy and \nnon-energy projects including rate-making and regulatory issues subject to state and \nfederal energy regulatory authorities such as the Federal Energy Regulatory \nCommission (“FERC”).  My business background includes four years at FERC as an \nEnergy Industry Analyst (Litigation) in the Office of Administrative Litigation as part \nof FERC Trial Staff where I was an expert witness.  I hold a Bachelor of Science in \nCommerce from the University of Virginia, a Master of Business Administration from \nthe University of Pittsburgh, and a Ph.D. in Finance from Virginia Tech.  I have the \nprofessional designation as a Chartered Financial Analyst (CFA).  \n3. For over 20 years, I have been working on matters involving the energy industry in the \nareas of electricity and pipelines subject to FERC and state jurisdiction.  I use finance, \neconomic and accounting principles in this work, as well as regulatory principles and \npractices of regulators.  I have worked on non-energy matters subject to regulation, \nwhich includes testimony on public interest considerations in a railroad merger before"},{"page":25,"startToken":5780,"endToken":5991,"text":"PJM Interconnection, L.L.C. \nDocket No. EL25-49-000 \nDr. Bremser Affidavit \nPage 2 of 8 \nthe US Surface Transportation Board.  In 2024, the Commission cited, in Order No. \n904 (Final Rule, Compensation for Reactive Power Within the Standard Power Factor \nRange), affidavits I authored in support of determinations made by the Commission \nregarding compensation under Schedule 2, under the pro forma open-access \ntransmission tariff (“OATT”).1\n4. I have experience with PJM, MISO, the Electric Reliability Council of Texas \n(“ERCOT”), and the North American Electric Reliability Corporation (“NERC”). \n5. My curriculum vitae is Attachment No. 1 hereto. \nII. AFFIDAVIT PURPOSE AND SUMMARY CONCLUSIONS \n6. The purpose of my affidavit is to provide additional support and analysis supporting \nthe recommendation for PJM to adopt a new class of transmission service, which I refer \nto as “Available Transmission Capacity Service” or “ATCS.” \n7. I am providing this affidavit on behalf of Enchanted Rock, LLC (“Enchanted Rock”). \n8. This affidavit is not intended to provide any legal opinions.  I provide citations in this \naffidavit to provide references for the statements made in the affidavit. \n1 Compensation for Reactive Power Within the Standard Power Factor Range, Final Rule, \nOrder No. 904, 189 FERC ¶ 61,034, at PP 89, 118 & n.343, 186 & n.547 (2024)."},{"page":26,"startToken":5991,"endToken":6227,"text":"PJM Interconnection, L.L.C. \nDocket No. EL25-49-000 \nDr. Bremser Affidavit \nPage 3 of 8 \nIII.REASONS TO UPDATE THE PJM TARIFF (POTENTIAL ISSUES WITH THE \nCURRENT PJM TARIFF) \n9. Co-located arrangements with new generation and new large loads are differently \nsituated than a point of interconnection involving only generation or only load.  Further, \nco-located arrangements with new generation and new large loads are distinguishable \nfrom proposed co-location arrangements where there is a pre-existing relationship with \nPJM involving assets with current and continuing operations.  For example, with \nexisting generation, the PJM transmission system was likely modified to accommodate \nthat generation.  \n10. Updating the PJM Tariff to accommodate co-located arrangements with new \ngeneration and new large loads would align with removing impediments to competition \nin the PJM wholesale power markets to serve large loads.  This would align with a \nfundamental principle of Order No. 888 in promoting competition and efficiency.2\n11. Updating the PJM Tariff will help avoid undue discrimination and will help allow open \naccess to the PJM transmission system to co-located arrangements with new generation \nand new large loads. \nIV.AVAILABLE TRANSMISSION CAPACITY SERVICE \n12. The Commission should consider creating a new transmission service to unlock the \nunused capacity of the transmission system, which can be utilized by co-located \narrangements. \n2 Promoting Wholesale Competition Through Open Access Non-discriminatory Transmission \nService by Public Utilities, Order No. 888, 61 Fed. Reg. 21,540 (May 10, 1996)."},{"page":27,"startToken":6227,"endToken":6514,"text":"PJM Interconnection, L.L.C. \nDocket No. EL25-49-000 \nDr. Bremser Affidavit \nPage 4 of 8 \n13. In Table 1 below, the PJM peak loads for 2023 and 2024 without exports and with \nexports are shown as provided in the 2024 State of the Market Report for PJM.  The \npeak loads for the period of 2009 to 2024, which occurred in 2011, is also shown in \nTable 2.   \nTable 1 \nActual PJM Peak Load Without Exports and With Exports for 2023 and 2024, \nand Highest Peak for 2009 to 20243\nYear\nDate\nHour Ending \n(EPT)\nPJM Load \n(MWh)\nPeak Load Without Exports\n2011 (Peak \nLoad 2009 \nto 2024)\nJuly 21 (Thu) \n17 \n154,095 \n2023\nJuly 27 (Thu)\n18\n144,215\n2024\nJuly 16 (Tue)\n18\n144,890\nPeak Load With Exports\n2011 (Peak \nLoad 2009 \nto 2024)\nJuly 21 (Thu) \n17 \n169,290 \n2023\nJuly 27 (Thu)\n18\n152,797\n2024\nJuly 15 (Mon)\n17\n154,045\n14.  The 2024 State of the Market Report for PJM provides a graph, which is shown in \nFigure 1 below, that shows the real-time monthly average hourly load plus exports for \n2023 and 2024.  As shown above in Table 1, the peak load with exports was about \n153,000 MWh in 2023 and 154,000 MWh in 2024, which is much higher than the \n3 Monitoring Analytics, LLC (Independent Market Monitor for PJM), State of the Market \nReport for PJM, Volume 2: Detailed Analysis, 2024, Section 3 (Energy Market), page 146 at \nTable 3-6 (Actual PJM peak load without: 2009 through 2024) and Table 3-7 (Actual PJM peak \nload plus export: 2009 through 2024), available at: \nhttps://www.monitoringanalytics.com/reports/PJM_State_of_the_Market/2024/2024-som-pjm-\nvol2.pdf."},{"page":28,"startToken":6514,"endToken":6678,"text":"PJM Interconnection, L.L.C. \nDocket No. EL25-49-000 \nDr. Bremser Affidavit \nPage 5 of 8 \nmonthly average.  Since the load is below peak load, this suggests that the transmission \nsystem likely has available capacity, because the transmission system is designed to \nhandle peak load conditions.  \nFigure 1 \nCopy of Figure 3-11 Showing Hourly Load With Exports \non the Peak Load Day for 2023 and 2024 4\n15. The 2024 State of the Market Report for PJM provides a graph, which is shown in \nFigure 2 below.  Figure 2 shows that even during peak load days there are hours where \nthere is likely available transmission capacity given the load is below the peak load. \n4 Monitoring Analytics, LLC (Independent Market Monitor for PJM), State of the Market \nReport for PJM, Volume 2: Detailed Analysis, 2024, Section 3 (Energy Market), page 148 at \nFigure 3-11 (Real-time monthly average hourly load plus exports: 2023 through 2024), available \n2023 Peak: 152,797; 2024 Peak:154,045 \n154 045"},{"page":29,"startToken":6678,"endToken":6838,"text":"PJM Interconnection, L.L.C. \nDocket No. EL25-49-000 \nDr. Bremser Affidavit \nPage 6 of 8 \nFigure 2 \nCopy of Figure 3-9 Showing Hourly Load With Exports  \non the Peak Load Day for 2023 and 20245\n16. PJM also provides a “Data Miner” on its website, which includes access to metered \nhourly load data.  Figure 3 below shows a plot of the metered hourly load data, which \nshows that the highest load levels occur during a small number of hours during a year.  \nThis implies that the transmission system overall has unused transmission capacity \nat https://www.monitoringanalytics.com/reports/PJM_State_of_the_Market/2024/2024-som-\npjm-vol2.pdf\n5 Monitoring Analytics, LLC (Independent Market Monitor for PJM), State of the Market \nReport for PJM, Volume 2: Detailed Analysis, 2024, Section 3 (Energy Market), page 147 at \nFigure 3-9 (Peak load and export day comparison), available at \nhttps://www.monitoringanalytics.com/reports/PJM_State_of_the_Market/2024/2024-som-pjm-\nvol2.pdf"},{"page":30,"startToken":6838,"endToken":7027,"text":"PJM Interconnection, L.L.C. \nDocket No. EL25-49-000 \nDr. Bremser Affidavit \nPage 7 of 8 \nmost of the time since the transmission system is designed to handle peak load \nconditions. \nFigure 3 \nHourly Metered Load for PJM for 20246\n17. I recognize that the PJM system has transmission constraints, but in general, there is \nunused transmission capacity during many hours of the year. \n18. Due to the firm service nature of Network Integration Transmission Service (“NITS”), \nit would be reasonable to provide a new solution to unlock the unused transmission \n6 PJM, Data Miner 2, Load, Hourly Load: Metered, available at: \nhttps://dataminer2.pjm.com/feed/hrl_load_metered/definition and \nhttps://dataminer2.pjm.com/feed/hrl_load_metered. \n 60,000\n 70,000\n 80,000\n 90,000\n 100,000\n 110,000\n 120,000\n 130,000\n 140,000\n 150,000\n 160,000\n1/1/2024\n2/1/2024 3/1/2024\n4/1/2024 5/1/2024\n6/1/2024 7/1/2024\n8/1/2024\n9/1/2024 10/1/2024 11/1/2024 12/1/2024\nMWh (Megawatt Hours)\nHours in 2024\nHIGHEST VALUE IN 2024 DATA SET"},{"page":31,"startToken":7027,"endToken":7244,"text":"PJM Interconnection, L.L.C. \nDocket No. EL25-49-000 \nDr. Bremser Affidavit \nPage 8 of 8 \ncapacity.  Depending on what the Commission believes is appropriate, it could be an \ninterim-type transmission service or a permanent transmission service for a co-located \narrangement.  I have named this concept “Available Transmission Capacity Service.”  \nThe service would allow load to access generation on the network during time periods \nwhen there is available transmission capacity.  This means that the Available \nTransmission Capacity Service would be a non-firm transmission service. \n19. The Commission might not agree with the general framework I have presented for the \nAvailability Transmission Capacity Service.  If that is the case, I believe the \nCommission should consider designing a transmission service to unlock the unused \ntransmission capacity for the purpose of facilitating new generation and new large load \nto join the PJM system without waiting on transmission upgrades and new generation \ncapacity to be built, which will take many, many years.  In a sense, this is analogous to \nthe “connect and manage” approach that ERCOT is using for new generation.7\n20. This concludes my affidavit.\n7 ERCOT, ERCOT Interconnection Process: Generation Entity Winter Weather Preparedness \nWorkshop, October 28, 2024 (Jenifer Fernandes, Manager, Resource Integration), Slide 2, \navailable at: https://www.ercot.com/files/docs/2024/10/30/0940-AM-ERCOT-Interconnection-\nProcess-Generation-Entity-Winter-Weather-Preparedness-Fernandes.pdf."},{"page":32,"startToken":7244,"endToken":7349,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \n \n \n \n \n \nPJM Interconnection, L.L.C. \n \n) \n                      Docket No. EL25-49-000 \n \nLarge Loads Co-Located at Generating \n)  \n \n \nDocket No. AD24-11-000 \nFacilities \n \n \n \n \n) \n \nConstellation Energy Generation, LLC \n) \n \n \nDocket No. EL25-20-000 \n \n \n \n \n \n \n) \n \n \n(consolidated) \nv. \n \n \n \n \n \n) \n \n \n \n \n \n \n) \nPJM Interconnection, L.L.C. \n \n) \n \n \nAFFIDAVIT OF ALBERT W. BREMSER \n \n \nI, Albert W. Bremser, certify under penalty of perjury that the attached affidavit in this proceeding \nwas prepared by me or under my direct supervision. The statements contained in my affidavit and \nthe supporting attachment are true and correct to the best of my knowledge, information, and belief. \n \nExecuted on the 23th day of April 2025. \n \n__________________________________ \nAlbert W. Bremser"},{"page":33,"startToken":7349,"endToken":7359,"text":"Attachment No. 1 \n \nCurriculum Vitae of Dr. Albert W. Bremser"},{"page":34,"startToken":7359,"endToken":7802,"text":"PJM Interconnection, L.L.C. \nDocket No. EL25-49-000 \nDr. Bremser Affidavit, Attachment No. 1 \nPage 1 of 8 \n \nAlbert (Al) Bremser, Ph.D. \nDr. Bremser advises on energy infrastructure issues involving \nelectricity and pipeline transportation. This advisory work includes \ntestifying as an expert witness. He focuses on rates (i.e., prices), \npolicy, and markets for rate-regulated and market-rate participants in \nthe electric and pipeline sectors. His work involves issues overseen \nby energy regulators. This includes the Federal Energy Regulatory \nCommission (FERC) and state public utility commissions. Dr. \nBremser uses finance, economics, and accounting principles in his \nwork. This includes understanding the regulatory principles and \npractices of regulators. \nDr. Bremser is a financial economist. He has a Ph.D. in Finance and \nholds the Chartered Financial Analyst® (CFA®) designation. Dr. \nBremser was an expert witness at FERC in the Office of \nAdministrative Litigation as a member of FERC Trial Staff from 2015 \nto 2019. He has more than 20 years of experience with energy \ninfrastructure issues. \nFor regulated rates, he has experience determining a regulated \nentity's annual revenue requirement from either a cost-of-service \nanalysis or a formula rate analysis. He works with companies making \na filing for an initial tariff rate or tariff rate changes, or intervening and \nprotesting a tariff rate filing. He has expertise in cost-of-service and \nformula rate analysis. This includes return on equity (ROE), cost of \ndebt, capital structure, rate design, and cost allocation. He has \nworked on cases with regulated rates set by settlement or \nnegotiation.    \nFor non-regulated rates, he has worked on projects involving \napplications for market-based rate authority to be granted by FERC, \ncomplaint cases challenging FERC granted market-based rate \nauthority, or review of current FERC market-based rate authority. \nDr. Bremser has served as an expert witness in several cases. He has \ntestified at FERC, the US Surface Transportation Board, and state \nutility regulatory bodies (Wisconsin, New Hampshire, and Ohio). His \nwork includes written testimony, cross-examination during hearings, \nand deposition testimony. \nAs a FERC Trial Staff member, Dr. Bremser was involved in many settlement proceedings before \nFERC Administrative Law Judges for electric and pipeline cases. Dr. Bremser has participated in \nsettlement proceedings at FERC before and after being a member of FERC Trial Staff. Dr. \nEducation\nPh.D., Finance, Virginia Tech, \n1997 \nM.B.A, University of \nPittsburgh, 1992 \nB.S., Commerce, University of \nVirginia, 1989 \nAdditional Credentials \nChartered Financial Analyst \n(CFA) \nYears of Experience \n25 \nSpecializations and Skills \nReturn on Equity (ROE); Cost \nof Capital; Cost of Service; \nElectric Utilities; Pipelines \n(Crude Oil, Refined Products \nand Natural Gas \nLiquids/NGLs); Federal Energy \nRegulatory Commission \n(FERC) Energy Regulation; \nExpert Witness; Dispute \nResolution; Litigation; \nEconomic Damages. \nPRINCIPAL \nCONSULTANT"},{"page":35,"startToken":7802,"endToken":8173,"text":"PJM Interconnection, L.L.C. \nDocket No. EL25-49-000 \nDr. Bremser Affidavit, Attachment No. 1 \nPage 2 of 8 \n \nBremser completed formal negotiation training in a 5-day executive education program from the \nProgram on Negotiation at Harvard Law School. \nDr. Bremser has experience in proceedings on a hearing track as an expert witness, supporting an \nexpert witness, and being a non-testifying member of FERC Trial Staff case teams. \nFor commercial litigation disputes, Dr. Bremser has experience with determining the dollar \namount of economic damages due to alleged defendant conduct. In energy matters, he has \nanalyzed merchant electricity generation, natural gas storage, spent nuclear fuel, and crude oil \ncontracts for proceedings involving breach of contract allegations and the determination of \neconomic damages. He has experience with MTBE gasoline and underground gasoline storage \ntanks, and solar panels for proceedings to determine economic damages that were not related to \nbreach of contract allegations. \nDr. Bremser holds a B.S. in Commerce from the University of Virginia, an M.B.A. from the \nUniversity of Pittsburgh, and a Ph.D. in Finance from Virginia Tech. Dr. Bremser has taught \nfinance courses at Virginia Tech, and has published articles in the Journal of Legal Economics.   \nHe has completed 28 college credit hours of statistics and econometrics. He also completed an \nAccounting Career Studies Certificate at Northern Virginia Community College in 2017, which \nrequires completion of 24 credit hours of accounting course that also meets the accounting \ncourse requirements of the Virginia Board for Accountancy to take the Certified Public \nAccountancy (C.P.A.) examination. \nPROFESSIONAL EXPERIENCE  \n Black & Veatch, Global Advisory, Principal Consultant, Arlington, VA, 2022 – Present  \n NERA Economic Consulting, Associate Director, Washington, DC, 2019 – 2022 \n Federal Energy Regulatory Commission, Energy Industry Analyst, Office of Administrative \nLitigation, Washington, D.C., 2015 – 2019 \n Bremser Finance and Economics, Principal, Vienna, VA, 2013 – 2015 \n Exponent, Manager, Alexandria, VA, 2011 – 2013 \n Bremser Finance and Economics, Principal, Vienna, VA, 2009 – 2011 \n LECG, Senior Managing Consultant, Washington, DC, 1999 – 2009 \n KPMG, Economic Consulting Services, Senior Consultant, Washington, DC, 1997 – 1999 \n Virginia Tech, College of Business, Finance Instructor, Blacksburg, VA, Summer 1995, 1996 – \n1997 \n MCI Telecommunications, Financial Systems Analyst, Arlington, VA, 1990 – 1991 \n Freddie Mac (Federal Home Loan Mortgage Corp.), Accountant, Vienna, VA, 1989 – 1990"},{"page":36,"startToken":8173,"endToken":8398,"text":"PJM Interconnection, L.L.C. \nDocket No. EL25-49-000 \nDr. Bremser Affidavit, Attachment No. 1 \nPage 3 of 8 \n \nPROJECT EXPERIENCE \nPRIMARY AREAS OF GOVERNMENT AND PRIVATE SECTOR EXPERIENCE \nEnergy – Regulated and Unregulated (Federal Energy Regulatory Commission (FERC) \nTrial Staff and private sector) \n Return on equity determination \n Discount cash flow model (DCF) \n Capital asset pricing model (CAPM) \n Risk premium model \n Expected earnings model \n Proxy group selection \n Wholesale electric transmission formula rates and stated rates (annual transmission revenue \nrequirement) \n Revenue requirement/Cost of service elements (electric transmission, reactive power, liquid \nenergy pipelines) \n Return on equity (ROE), cost of debt and capital structure (return on rate base; cost of \ncapital) \n Rate base (original cost rate base, depreciation, net rate base, accumulated deferred \nincome taxes (ADIT), deferred earnings, allowance for funds used during construction \n(AFUDC)) \n Alternative rate base treatments: depreciated original cost (DOC), trended original cost \n(TOC), levelized original cost \n Income tax allowance (ITA) \n Operating expenses (operations and maintenance (O&M), and general and administrative \n(G&A)) \n Cost allocation of rate base and operating expenses \n Application of cost causation principles to determine cost allocation \n Corporate overhead \n Jurisdictional versus non-jurisdictional services \n Separate and joint jurisdictional systems \n Affiliate transactions \n Market-based rate authority \n Federal Energy Regulatory Commission rate making and non-rate making practices \n Economic damages in dispute resolution (breach of contract, etc.) \nFERC Settlement and Litigation Experience \n FERC settlement negotiations and hearings"},{"page":37,"startToken":8398,"endToken":8678,"text":"PJM Interconnection, L.L.C. \nDocket No. EL25-49-000 \nDr. Bremser Affidavit, Attachment No. 1 \nPage 4 of 8 \n \n 30+ dockets (not counting related dockets) in settlement proceedings \n 11 hearing proceedings while in the private sector and as a member of FERC Trial Staff \nEXPERIENCE BY INDUSTRY SECTOR \nIndustry: Electric (FERC; wholesale) \n Return on equity (ROE) determination \n DATC Path 15 (ER17-998-001 and EL17-61-001) (and other elements of regulatory cost of \ncapital – cost of debt and capital structure) – electric transmission \n System Energy Resources, Inc. (SERI) (EL17-41-001 and EL18-142-000) (two separate \ncompliant cases for different time periods) – electric generation, nuclear power plant \n Panda Stonewall (ER17-1821-002), generator based reactive power compensation under \nSchedule 2 of PJM OATT \n Consolidated Water Power Company (Wisconsin Public Service Commission, 1330-ER-\n104) (comparative authorized return on rate base analysis, dividend policy) – electric \nutility rates to customers \n FERC cost of service and cost of service elements such as income tax allowance, \naccumulated deferred income taxes (ADIT), and cost of capital (including return on equity \n(ROE)) for cost of service \n Electric transmission rates \n Formula rates \n Stated rates \n Reactive power capability compensation (generation-based; Schedule 2 of OATT) \n Panda Stonewall (ER17-1821-002; Op. No. 574); testimony on fixed charge rate \nframework, cost allocation, return on equity, cost of debt, capital structure, plant \nconstruction costs for a new natural gas fueled power plant, categorization of plant \nconstruction cost, appropriateness of recovering plant construction costs and other topic \nareas; on behalf of FERC Trial Staff \n Affidavits for Initial Comments and Reply Comments in the Notice of Proposed \nRulemaking on Compensation Within the Standard Power Range (RM22-2-000) \n Generation types \n \nWind \n \nSolar \n \nNatural gas fueled (combined cycle, combustion turbine) \n \nCoal fueled \n \nNuclear fueled \n \nCo-generation \n \nHydro \n \nOther fuel sources"},{"page":38,"startToken":8678,"endToken":8914,"text":"PJM Interconnection, L.L.C. \nDocket No. EL25-49-000 \nDr. Bremser Affidavit, Attachment No. 1 \nPage 5 of 8 \n \n \nFixed charge rate framework \n Non-fuel fixed operations and maintenance (O&M) expenses \n Fixed general and administrative (A&G) expenses \n Depreciation (sinking-fund deprecation) \n Income tax allowance \n Return on rate base (return on equity (ROE), cost of debt and capital structure) \n Accumulated deferred income taxes (ADIT) \n Knowledge of certain aspects of PJM, MISO, ERCOT and other RTOs/ISOs \n Energy related breach of contract cases involving electricity tolling agreements and spent \nnuclear fuel \n Valuation of electric power plants \nIndustry: Natural Gas Pipelines (FERC) \n Knowledge of natural gas pipelines and natural gas storage involving acquisition of assets \nand investment interests. \n FERC shipper creditworthiness standards and associated tariff language of pipelines.  \n Return on equity determination. \nIndustry: Electric Local Distribution Companies (State; Non-FERC) \n Cost of service elements \n Return on equity \n Multi-year investment plan \n Advisory on testimony for filing and stakeholder engagement \nIndustry: Natural Gas Local Distribution Companies (State; Non-FERC) \n Cost of service elements \n Lead-lag studies to determine cash working capital \n Multi-year investment plan \nAdvisory on testimony for filing and stakeholder engagement \nIndustry: Crude Oil, Refined Product, and Natural Gas Liquid (NGL) Pipelines (FERC) \n Cost of service elements \n Return on equity (ROE), cost of debt and capital structure (return on rate base) \n Rate base (net rate base, accumulate deferred income taxes (ADIT), deferred earnings, \nallowance for funds used during construction (AFUDC)) \n Income tax allowance (ITA)"},{"page":39,"startToken":8914,"endToken":9174,"text":"PJM Interconnection, L.L.C. \nDocket No. EL25-49-000 \nDr. Bremser Affidavit, Attachment No. 1 \nPage 6 of 8 \n \n Operating expenses (operations and maintenance (O&M), and general and administrative \n(G&A)) \n Application of cost causation principles to determine cost allocations \n Cost of service \n Tariff rate filing advisory and preparation of cost of service statements \n Cost of service advisory \n Page 700 advisory \n Rate design \n Market-based rate authority \n Seaway Crude Pipeline’s application (OR15-6-000 and -002); testimony on behalf of FERC \nTrial Staff \n Mobil Pipe Line application (Pegasus system; OR07-21-000); support of Mobil’s expert and \nsupport in hearing proceeding. First crude oil pipeline application for market-based rate \nauthority \n Guttman Energy, et al v. Buckeye Pipe Line (OR14-4-000); member of FERC Trial Staff \ncase team for the hearing proceeding. First compliant case challenging market-base rate \nauthority for a refined products pipeline \n Epsilon Trading, et al v Colonial Pipeline (OR18-7-002, et al); support of Colonial’s expert \nfor the market-based rate phase of the hearing proceeding \n Unnamed pipeline; support for an expert for an application that was not filed. \n Cost of service rates, settlement rates, index ceiling rates/levels, uncommitted and \ncommitted rates \n Non-rate issues – pro-rationing policies and allegations of discriminatory conduct \n BP v Sunoco (OR15-25-000 and -001); member of FERC Trial Staff case team \n Equinor v Mustang (OR21-5-001); support of Mustang’s expert \n Valuation of refined product pipelines \nOTHER EXPERIENCE \nOther Energy Experience: \n Energy related breach of contract cases involving natural gas storage and crude oil purchase \ncontacts \n Energy related business tort involving MTBE gasoline and underground gasoline storage \ntanks \n Energy related dispute involving solar panels"},{"page":40,"startToken":9174,"endToken":9549,"text":"PJM Interconnection, L.L.C. \nDocket No. EL25-49-000 \nDr. Bremser Affidavit, Attachment No. 1 \nPage 7 of 8 \n \nOther Economic, Financial, and Accounting Analysis \n Economic analysis to determine economic damages in case involving breach of contract or \nfiduciary duty (non-investment and investment related), business torts, and intellectual \nproperty (patent, trademark, copyright, trade secrets) \n Analysis of financial documents, financial statements, and accounting records \n Option pricing techniques (derivative securities) \n Railroad transportation rates \n Public interest issues in a railroad merger \n Regulatory proceedings such as those before the Federal Energy Regulatory Commission, the \nUS Surface Transportation Board, the Public Service Commission of Wisconsin, Public Utilities \nCommission of Ohio, and the New Hampshire Public Utilities Commission. \nTESTIMONY/AFFIDAVITS/VERIFIED STATEMENTS \n Seaway Crude Pipeline Company LLC, FERC Docket No. OR15-6-000 \n Panda Stonewall, LLC, FERC Docket No. ER17-1821-002 \n DATC Path 15, LLC, Docket No. ER17-998-001 and EL17-61-001 \n System Energy Resources, Inc., Docket No. EL17-41-001 and EL18-142-000 \n Consolidated Water Power Company, Public Service Commission of Wisconsin Docket No. \n1330-ER-104 \n American Electric Power Service Corporation (Appalachian Power Company, et al), FERC \nDocket No. ER11-46-016, ER11-47-013, et al. Joint affidavit with Julie M. Carey \n American Electric Power Service Corporation (Appalachian Power Company, et al), FERC \nDocket No. ER11-47-014, et al. Joint affidavit with Julie M. Carey \n Railroad Control Application, Canadian Pacific Railway Limited; Canadian Pacific Railway \nCompany; Soo Line Railroad Company; Central Maine & Quebec Railway US Inc; Dakota, \nMinnesota & Eastern Railroad Corporation; and Delaware & Hudson Railway Company, Inc. – \nControl – Kansas City Southern; The Kansas City Southern Railway Company; Gateway \nEastern Railway Company; and The Texas Mexican Railway Company, U.S. Surface \nTransportation Board Docket No. FD 36500. Joint Verified Statement with Julie M. Carey \n Liberty Utilities (EnergyNorth Natural Gas) Corp. d/b/a Liberty, request for change in distribution \nrates, New Hampshire Public Utility Commission Docket No. DG23-067 \n Unnamed Entity, Utah Tax Commission, Utah Appeal Nos. 18-1322, 19-1325, 20-1512, 21-1212, \n22-1345, and 23-957 \n Old Dominion Electric Cooperative, Northern Virginia Electric Cooperative, Inc., and Dominion \nEnergy Services, Inc. on behalf of Virginia Electric and Power Company d/b/a Dominion \nEnergy Virginia, FERC Docket No. RM22-2-000 (2 filings) \n Ohio Power Company Application for New Tariffs Related to Data Centers and Mobile Data \nCenters, Public Utilities Commission of Ohio, Case No. 24-508-EL-ATA, on behalf of Enchanted \nRock"},{"page":41,"startToken":9549,"endToken":9783,"text":"PJM Interconnection, L.L.C. \nDocket No. EL25-49-000 \nDr. Bremser Affidavit, Attachment No. 1 \nPage 8 of 8 \n \nREPRESENTATIVE PUBLICATIONS AND PRESENTATIONS \nPUBLICATIONS \n“Two Essays on Convertible Debt”, Ph.D. dissertation, March 1997.  \n“Calculating a Taxable Damages Award: A Comparison of Two Calculation Methods”, Journal of \nLegal Economics, April 2010. \n“Valuation of a Trade Subsidy Using Option Pricing Theory”, Journal of Legal Economics, April \n2011. \nCantor, R and A. Bremser. “Market Share Liability from an Economics Perspective”, BRG Review, \nWinter 2014. \nPRESENTATIONS \nPresentation on issues in discounting cash flows, presentation to the Western States Petroleum \nAssociation (WSPA), South Lake Tahoe, CA, August 2007. \n“Lost Profits: Principles, Methods and Strategies to Prove and Defend Damages”, presentation for \nThe Knowledge Group, with Richard Eichmann of NERA, October 7, 2019. \n“Energy Disputes and Litigation: Effective Strategies and Best Practices for the Year Ahead”, \npresentation for The Knowledge Group, with Julie Carey of NERA, December 5, 2019.  \n“The Future of the U.S. Renewable Energy Disputes: Decoding Recent Trends and Updates”, \npresentation for The Knowledge Group, with Julie Carey of NERA, March 24, 2020. \n“Cost-of-Service and Rate Design for Oil Pipelines”, presentation to Bracewell LLP (law firm), with \nJulia Williams of NERA, August 31, 2021. \n“Federal Energy Regulatory Commission (FERC) 101”, presentation to the Unitary Appraisal \nSchool, Western States Association of Tax Administrators Committee on Centrally Assessed \nProperties (WSATA-CCAP), Utah State University, January 28, 2025. \nApril 23, 2025"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":3,"startToken":0,"endToken":605},{"p":3,"at":3,"title":"I. INTRODUCTION AND NEED FOR REFORM","method":"printed heading","endPage":6,"endAt":324,"startToken":605,"endToken":1795},{"p":6,"at":324,"title":"II. LCDG OPTION: LOAD CO-LOCATED WITH DISPATCHABLE GENERATION","method":"printed heading","endPage":13,"endAt":4,"startToken":1795,"endToken":3587},{"p":13,"at":4,"title":"III. ENCHANTED ROCK’S RESPONSE TO SELECTED COMMISSION","method":"printed heading","endPage":19,"endAt":4,"startToken":3587,"endToken":5237},{"p":19,"at":4,"title":"IV. CONCLUSION","method":"printed heading","endPage":20,"endAt":0,"startToken":5237,"endToken":5350},{"p":20,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":21,"endAt":0,"startToken":5350,"endToken":5401},{"p":21,"at":0,"title":"Attachment A","method":"printed heading","endPage":23,"endAt":90,"startToken":5401,"endToken":5480},{"p":23,"at":90,"title":"TABLE OF CONTENTS","method":"printed heading","endPage":23,"endAt":339,"startToken":5480,"endToken":5495},{"p":23,"at":339,"title":"III. REASONS TO UPDATE THE PJM TARIFF (POTENTIAL ISSUES WITH THE","method":"printed heading","endPage":24,"endAt":126,"startToken":5495,"endToken":5549},{"p":24,"at":126,"title":"I. INTRODUCTION","method":"printed heading","endPage":25,"endAt":653,"startToken":5549,"endToken":5877},{"p":25,"at":653,"title":"II. AFFIDAVIT PURPOSE AND SUMMARY CONCLUSIONS","method":"printed heading","endPage":41,"endAt":1659,"startToken":5877,"endToken":9783}]}