{"document":{"slug":"rec-20250423-5214","title":"Comments of Consumers' Research re the large loads co-located at generation facilities","issued":"2025-04-23","accession":"20250423-5214","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Consumers' Research","kind":"comments","file":"sources/filings/text/20250423-5214_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250423-5214","tier":"record","sha256":"af0f088111c4843eff7edff0c80fa57218660cb16bdefca7d3e8938db9fcc433","pages":5,"tokens":1330,"emptyPages":[],"textThemes":["colo","study"]},"pages":[{"page":1,"startToken":0,"endToken":218,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nPJM Interconnection, L.L.C., et al.    \n \n) \n \nDocket Nos. EL25-49-000 \n \n \n \n \n \n \n \n) \nLarge Loads Co-Located at Generating  Facilities \n) \n \n \n \nAD24-11-000 \n \n \n \n \n \n \n \n) \nConstellation Energy Generation, LLC   \n \n) \n \n \n \nEL25-20-000 \n \n \n \n \n \n \n \n) \n \n \n \n(Consolidated) \nv.         \n \n \n \n \n \n) \n \n \n \n \n \n \n \n) \nPJM Interconnection, L.L.C.  \n \n \n) \n \n \nCOMMENT OF CONSUMERS’ RESEARCH \nPursuant to the Commission’s Order entered on February 20, 2025, at Docket Nos. EL25-\n49-000 et al., Intervenor Consumers’ Research submits the following comment responding to the \nfilings in this docket and addressing four key principles that should guide the Commission’s \ndecision making when considering how to protect consumers and ensure reliable and affordable \nelectricity in the context of large loads co-located at generating facilities. \nConsumers’ Research is an independent educational 501(c)(3) nonprofit organization \nwhose mission is to increase the knowledge and understanding of issues, policies, products, and \nservices of concern to consumers and to promote the freedom to act on that knowledge and \nunderstanding.1  The cost and reliability of energy is a critical issue for the organization because \nit affects not only household utility bills but also the cost of energy that is factored into every good \nand service that consumers purchase.  \nFirst, retail customers should not subsidize the costs of co-location of large loads. \nConsumers’ Research agrees with PJM that “participants involved in co-location arrangements \n \n1 See https://consumersresearch.org/"},{"page":2,"startToken":218,"endToken":539,"text":"2 \nshould pay the costs of any grid services they consume and the arrangements must be reliable and \noperationally manageable.” See PJM Answer at 4. And it is undisputed that “many co-located load \nconfigurations utilize grid support and consume ancillary services (including, for example, \nfrequency regulation, black start service, and reactive service).” Id. \nTo avoid improper subsidization, the Commission and regional transmission organizations \nshould consider both direct and indirect costs, including the following: infrastructure that is built \nto power the co-located load itself; existing and new or upgraded infrastructure, including \ngenerators and transmission, that is ostensibly for the benefit of regular consumers but that is made \nnecessary by the allocation of existing base-load power to the co-located load; developments to \nensure reliability and resource adequacy, including ancillary developments like backups and black \nstart, that are necessary because of the co-located load’s impact on reliability; grid support that \nenables the co-located load to receive reliable power in case of the connected generator’s failure \nor shortfall; and potential rate increases resulting from decreased supply caused by co-location. In \nconsideration of this, a co-located load’s access to, dependence on, and use of grid-supplied energy \nmust be thoroughly accounted for when forming the co-located load’s rate structure.  \nSecond, retail customers should not bear the risks of co-location. The risks of co-location \nshould not be distributed to or socialized among regular consumers. Co-location may require large \nupfront costs for infrastructure, and there is a risk that those costs will not be recovered (e.g., if the \ncompany that obtained the co-location fails). Another risk of co-location is that the co-located load \ncould obtain the first right of access to reliable, dispatchable power, while regular consumers are \nleft with less reliable resources like wind and solar. \nTo protect regular consumers from the risks of co-location, including the risk of stranded \nassets, co-located loads could be required to do the following as a precondition to the risks: make"},{"page":3,"startToken":539,"endToken":861,"text":"3 \nlong-term financial commitments that will insure against risks; agree to a take-or-pay clause that \napplies over a defined period of time; and paying for the development of additional reliable power \ngeneration to ensure that regular consumers maintain the same level of generation from reliable \nsources as they did before the co-location. \nThird, co-location should not be allowed to undermine dispatchable power—including by \nserving as an alternative to using existing dispatchable, generating sources that will otherwise \nretire. According to the North American Electric Reliability Corporation (“NERC”), many states \nare now at risk of suffering critical shortfalls in electric power. The amount of money at issue to \naddress this shortfall is enormous: construction costs alone are estimated to be in the trillions,2 and \nthat does not even account for the indirect costs to consumers and the economy from bad policy \nchoices. Early retirement and non-repair of dispatchable generating assets is shortening their useful \nlifespans, and there is a general failure to build new dispatchable generating assets. As Chair \nChristie stated, “I have repeatedly warned that America is facing a reliability crisis driven by the \ndangerous pace of retirements of dispatchable generation units and failure to build sufficient new \ngeneration.”3 It is important that co-location of certain resources not occur in a way that \nexacerbates (or fails to ameliorate) the reliability crisis facing many states. \nFERC should therefore consider several possible policies. For example, parties engaged in \nco-location arrangements could be required to maintain a specified reserve capacity of \ndispatchable power for use by ratepayers that are not part of the co-location. This could help to \n \n2 BloombergNEF estimated that the cost of the grid overhaul globally could be $21 trillion \nbetween 2020-2035. https://www.ft.com/content/bf1b788a-f366-4637-9ae4-08dbc0bd90fa. The \nU.S. portion of that may be $2.5 trillion according to an IEA report. \nhttps://markets.businessinsider.com/news/stocks/grid-upgrades-estimated-to-cost-over-25-\ntrillion-by-2035-1032726083 \n3 https://www.ferc.gov/news-events/news/president-trump-names-mark-christie-chairman-ferc"},{"page":4,"startToken":861,"endToken":1146,"text":"4 \nensure that generators and utilities, in addition to companies seeking to co-locate, are properly \nincentivized to promote dispatchable power.  \nIt is also critical that co-location not be allowed unless the parties involved, including the \ngenerator and the company seeking the co-location, have no targets or commitments for net zero \nor any related low-carbon goals. Co-located loads often demand 24/7 dispatchable power, so they \nshould not be allowed to misleadingly claim that they are lowering their emissions by co-locating \nto a “clean” facility while simultaneously creating risks to existing dispatchable generation that is \nsupplied to the grid. Net-zero commitments and related targets harm consumers by artificially \nweakening the market for dispatchable power.  \nIn contrast, if a co-located load plans to connect a new generator that provides dispatchable \npower (e.g., a new fossil-fuel-powered generator) and will also increase grid reliability overall \n(rather than decrease it), then FERC should consider policies that allow that new generation to \nmove ahead in the interconnection queue, in front of projects for non-dispatchable resources. \nTime-savings incentives may be important in this context, as one of the reasons that companies \nseek co-location is to avoid delays and start operating profitably as quickly as possible. Allowing \ndispatchable generation (that benefits consumers generally) to move forward in the queue is \nconsistent with solving a problem identified by Interior Secretary Burgum, who identified the \nproblem of the 2,600 GW of wind, solar and storage sitting in the interconnection queues as a \nmajor energy imbalance that could lead to brownouts or blackouts.4  And the Commission has \nadopted a rule allowing dispatchable generation to get priority in the queue.5  \n \n4 https://www.rtoinsider.com/95864-burgum-criticizes-ferc-queues-renewables/  \n5 https://medium.com/@kennedymaize/ferc-approves-line-jumping-pjm-connections-\n32561997e8bd"},{"page":5,"startToken":1146,"endToken":1330,"text":"5 \nFourth, co-location arrangements should be transparent to the public. Companies seeking \nco-location may try to benefit from special contracts that are not open to the public. Transparency \nwill also help protect consumers from the risk that their power infrastructure will be built up, at \nthe consumers’ long-term expense, for a co-location that eventually falls through when a company \ndecides to withdraw its interconnection request and instead follow through on a duplicative request \nthat it made somewhere else. Companies seeking co-location should also be required to disclose \ninformation about the extent and nature of any on-site backup generating facilities. \nThank you for considering the comments of Consumers’ Research on this important issue. \nUltimately, the key consideration must be promoting affordable and reliable electricity to \nconsumers. The foregoing principles will help achieve that goal. \nDated: April 23, 2025  \n \n \n \nRespectfully submitted,  \n \n \n \n \n \n \n \nWill Hild \n \n \nCERTIFICATE OF SERVICE \nI hereby certify that I have this day served the foregoing document on each person \ndesignated on the official service list compiled by the Secretary of the Federal Energy Regulatory \nCommission in this proceeding.  \nDated: April 23, 2025.  \nWill Hild"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":5,"endAt":1006,"startToken":0,"endToken":1287},{"p":5,"at":1006,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":5,"endAt":1281,"startToken":1287,"endToken":1330}]}