{"document":{"slug":"rec-20250423-5220","title":"Comments of Talen Energy Corporation on Answer of PJM Interconnection, L.L.C. to the Order Instituting Proceeding Under Section 206 of the Federal Power Act…","issued":"2025-04-23","accession":"20250423-5220","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Talen Energy Corporation","kind":"answer","file":"sources/filings/text/20250423-5220_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250423-5220","tier":"record","sha256":"97d5d317c0010832b8ee29477f7c90c1912503c81436bd949693011268431b24","pages":15,"tokens":4442,"emptyPages":[],"textThemes":["colo"]},"pages":[{"page":1,"startToken":0,"endToken":225,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C., et al. \n) \n \nDocket No. EL25-49-000 \n \n \nLarge Loads Co-Located at Generating  \n) \n \nDocket No. AD24-11-000 \nFacilities  \n) \n \nConstellation Energy Generation, LLC \n) \nDocket No. EL25-20-000 \n \n) \n(consolidated) \nv.  \n) \n \n) \nPJM Interconnection, L.L.C.  \n) \n \nCOMMENTS OF TALEN ENERGY CORPORATION \nON ANSWER OF PJM INTERCONNECTION L.L.C.  \nTO ORDER INSTITUTING PROCEEDING UNDER SECTION 206 OF THE  \nFEDERAL POWER ACT AND CONSOLIDATING WITH OTHER PROCEEDINGS \nTime is of the essence for the Commission to order PJM Interconnection, L.L.C. (“PJM”) \nto file revisions to its Open Access Transmission Tariff (“OATT” or “Tariff”) to incorporate all \neight of PJM’s proposed co-located load configurations in its Answer to the Show Cause Order \n(“Answer”).1  Talen Energy Corporation (“Talen”) largely agrees with the jurisdictional principles \nlaid out by the Commission in its Show Cause Order2 and believes that specific grounds for the \nCommission’s jurisdiction over the types of large-scale co-location arrangements detailed in  \nPJM’s Answer will depend on the specific facts and circumstances of each co-location \narrangement.   \n \n1 PJM Interconnection, et al., Docket No. EL25-49-000, Answer of PJM Interconnection, L.L.C. (filed Mar. 24, 2025). \n(“PJM Answer”) \n2 PJM Interconnection, et al., Docket No. EL25-49-000, Order Instituting Proceeding Under Section 206 of the Federal \nPower Act and Consolidating with Other Proceedings (filed Feb. 20, 2025) (“Show Cause Order”)."},{"page":2,"startToken":225,"endToken":521,"text":"2 \nTalen appreciates PJM’s endeavors to devise creative configuration options for the co-\nlocation of large load that meet the needs of its diverse stakeholders.  All eight options presented \nby PJM for the co-location of large load are just and reasonable and not unduly discriminatory, \nand all required tariff changes for the latter five options should be implemented quickly into PJM’s \nTariff.  Ordering PJM to file amended Tariff language no later than thirty (30) days after such a \nCommission order is essential.  It will provide stakeholders with the regulatory certainty they need \nto make investments that will support our national security goals and meet resource adequacy and \nreliability goals. \nI. COMMENTS \n \nA.  \nFERC Has Limited Jurisdiction Over Co-Location Arrangements and Should Not \nInterfere with Innovative, State-Led Approaches to Co-Located Load. \nIn broad strokes, Talen agrees with the general jurisdictional principles articulated in \nSection VI.A of the Commission’s Show Cause Order.3  It is well-settled that the Commission has \njurisdiction over wholesale sales and transmission of electricity in interstate commerce, the \nfacilities used for such sale and transmission, and rules or practices that “directly affect the \nwholesale rate.”4  States, by contrast, have exclusive jurisdiction over retail sales of electricity, \nand generation and distribution facilities.  Congress explicitly “entrusted the choice of electric[ \nenergy] generation to the States,” and States—through their siting, franchise, and other police \npowers—“retain authority to choose their preferred mix of energy generation resources.”5 \n \n3 Show Cause Order PP 66–73.   \n4 See FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 278 (2016) (“EPSA”) (citation omitted); Show Cause Order \nP 66 & nn.210–11. \n5 See Show Cause Order PP 67, 70; Citizens Action Coal. of Ind., Inc. v. FERC, 125 F.4th 229, 238-39 (D.C. Cir. \n2025)."},{"page":3,"startToken":521,"endToken":881,"text":"3 \nAs the Commission’s November 2024 technical conference made clear, market \nparticipants urgently require clarification about how the general jurisdictional principles described \nabove apply to the specific issue of co-located load.6  Talen respectfully requests that the \nCommission use this proceeding to clarify that (1) FERC generally does have jurisdiction over the \ntypes of large-scale co-location arrangements discussed in PJM’s Answer to the Show Cause \nOrder, and that (2) the particular basis (or bases) of the Commission’s jurisdiction will vary based \non the specifics of the co-location arrangement. \n1.  \nThe Basis for the Commission’s Jurisdiction Is Fact Specific and Will Vary for \nEach Co-Located Load Arrangement.  \n \nTalen agrees with PJM that “the Commission’s jurisdiction over transmission service in \ninterstate commerce” is “necessarily implicated in matters relating to co-located load arrangements \nwhere generator interconnections are being modified” or where a generator’s interconnection \nservice agreement (“ISA”) contemplates a co-located load arrangement.7  Phrased differently, the \ntransmission interconnection service received by generators is itself a form of FERC-jurisdictional \ntransmission service.  FERC’s jurisdiction to evaluate whether such a generator’s ISA is just and \nreasonable will also extend to the co-located load arrangement, given that (1) the co-located load \nwill be enabled and facilitated by equipment and facilities described in the FERC-jurisdictional \nISA and (2) FERC’s evaluation of the ISA may consider specific reliability concerns, which in \nturn may require consideration of the co-located load arrangement and the extent to which the \nspecific behind-the-meter configuration affects system reliability.8  In this regard, FERC would \n \n6 Constellation Energy Generation, LLC, Docket No. EL25-20-000, Motion to Intervene and Comments of Talen \nEnergy Corporation at 3 & nn.6–9 (filed Dec. 4, 2024); Constellation Energy Generation, LLC, Docket No. EL25-20-\n000, Motion for Leave to Answer and Answer of Talen Energy Corporation at 7 & nn. 24–26 (filed Dec. 23, 2024). \n7 PJM Answer at 31.  \n8 Under the FPA, FERC’s jurisdiction extends to any “classifications, practices, and regulations affecting  \n. . . rates and charges, together with all contracts which in any manner affect or relate to such rates, charges, \nclassifications, and services.”  16 U.S.C. § 824d(c).  FERC explained in Order No. 1920 that its jurisdiction over the"},{"page":4,"startToken":881,"endToken":1265,"text":"4 \nhave limited jurisdiction over the co-located load arrangements set out in and contemplated by \nOptions 4 and 5 in PJM’s Answer.  \nTalen appreciates that, with respect to other co-located load arrangements, there may be \ndifferent (or supplementary) bases for FERC jurisdiction.  For example, there may be situations in \nwhich sales from generators to co-located load are interstate sales, or when such sales constitute \n(or are indirectly enabled by) sales for resale; in either case, the co-location arrangement would be \nFERC-jurisdictional under Section 205 of the FPA.  Moreover, there may be situations in which \nco-located load takes FERC-jurisdictional transmission service—e.g., when the co-located load is \nnetwork load that has its own point of interconnection (PJM Option 1), when co-located load shares \na point of interconnection with the generator but is separately metered as network load (PJM \nOption 2), or when co-located load is network load that either takes interruptible service (PJM \nOption 7) or participates in demand response (PJM Option 8).   \nThe key point is this:  Talen of course agrees that co-located load that actually uses \ntransmission network or grid services—i.e., load that is directly connected to a generator with \nno grid power flow—should pay for those services to the extent they are used, and that the \nCommission has jurisdiction over the rates and terms of such transmission service, if it is in \ninterstate commerce.9  The basis of FERC jurisdiction over each of the co-location \n \ninterstate transmission system includes a power to “respond[] to evolving reliability concerns.”  187 FERC ¶ 61,068, \nP 261 (2024).  Thus, as Talen has previously explained, FERC “can take the reliability of the FERC-jurisdictional \ntransmission grid into account” when evaluating ISAs or tariffs that implicate issues related to co-located load, “but \nthat authority does not extend to changes in electricity demand and load growth presented by co-located load \narrangements.”  See PJM Interconnection, L.L.C, Docket No. ER24-2172-001, Comments of Susquehanna Nuclear, \nLLC in Support of the Deficiency Letter Response Filed by PJM Interconnection, L.L.C. at 8 (filed Sept. 24, 2024) \n(“Susquehanna September 2024 ER24-2172 Comments”). \n9 See Large Loads Co-Located at Generating Facilities, Docket No. AD24-11-000, Comments of Talen Energy \nCorporation on Issues Related to Co-Location of Large Loads at Generating Facilities at 2 (filed Dec. 9, 2024) (“Talen \nPost-Conference Comments”)."},{"page":5,"startToken":1265,"endToken":1565,"text":"5 \narrangements contemplated by PJM’s Answer is that each co-location arrangement takes a type \nof jurisdictional service.   \nHowever, if the load is not using any transmission network, point-to-point, or ancillary \nservices, then the basis of FERC jurisdiction is not that the co-located load itself takes a FERC-\njurisdictional form of transmission service.  Instead, in such co-location arrangements, the ISA \ngoverning the co-location arrangement is the only part of the arrangement that is FERC-\njurisdictional.  The sole basis for the Commission’s jurisdiction will be that the co-location \narrangement requires an amendment to the generators’ FERC-jurisdictional ISA (or alteration \nof an RTO/ISO pro forma document).  This would occur, for example, when a generator decides \nto disconnect entirely from the grid to serve a behind-the-meter load.  When the load has no \ngrid connection, there can be no jurisdictional service. \n2.  \nThe Utilities’ Jurisdictional Arguments Are Incorrect. \nExelon Corporation and aligned parties (together, the “Utilities”) have a different view of \nthe Commission’s jurisdiction.  In a series of related dockets, the Utilities have sought to extract \ntwo holdings from the Commission: (1) that co-located load always takes a form of FERC- \njurisdictional transmission service and (2) that the interconnection of co-located load is not FERC \njurisdictional.  In addition to being internally inconsistent, those two arguments are both wrong. \na.  \nFERC Jurisdiction Over Transmission Service Provided to Co-Located \nLoad.  \n \nIn the Susquehanna ISA proceeding (Docket No. ER24-2172), the Utilities have insisted \nthat “[a]ll co-located load is grid connected” and that the Commission has jurisdiction due to the \ntransmission service that the co-located load receives.10  These Utilities’ view is essentially that \n \n10 Cf. PJM Interconnection, L.L.C., Docket No. ER24-2172-001,  Exelon and AEP Request for Leave to Answer and \nAnswer to Susquehanna, Constellation, and PPL Comments at 15–16 (filed Oct. 16, 2024)."},{"page":6,"startToken":1565,"endToken":1895,"text":"6 \nFERC cannot require transmission owners to accommodate interconnection of generators if the \nconfiguration involves co-located load.  If credited, that view would create a situation even worse \nthan the Attleboro gap, because (in this iteration of the vacuum) the transmission owners would \nhappily occupy the vacant regulatory space, and exercise unilateral power to stop generators from \nserving co-located load merely by withholding their supposedly “required” consent to an amended \nISA, and thus profit in all instances (by, e.g., functionally forcing data centers in front of the meter \nso as to achieve their long-term financial goals).  That arrangement benefits no one except these \nUtilities. Of course, not all utilities share these views. \nThe Utilities’ suggestion that co-located load always takes a form of FERC-jurisdictional \ntransmission service is driven not by any coherent description of the facilities in question, but \nrather by these Utilities’ desire to remain profitable within a market in which certain of their legacy \nservices are increasingly less in demand.  Their goal is to either (1) force large loads to interconnect \nwith their systems in front of the meter, which in turn will enable them to build system upgrades, \nsocialize the costs to their ratepayers, and collect a return on their investment; or (2) convince the \nCommission to adopt a blunt rule under which all behind-the-meter loads would be treated as \nnetwork customers, which would enable the Utilities to charge rents to co-located load for services \nthat it does not need or use.  In short, these Utilities are determined to position themselves as \nintermediaries with veto power over privately-negotiated economic arrangements that do not \ninvolve them, but do limit their ability to collect rent when not actually providing service. \nIt is of course true that co-located load is electrically connected to generation that in turn \nis often connected to the grid.  But the fact that co-located load is indirectly connected to the grid, \nwithout more, does not mean that co-located load is taking FERC jurisdictional service from the"},{"page":7,"startToken":1895,"endToken":2240,"text":"7 \ngrid.11  Indeed, the specifics of Susquehanna’s co-location arrangement make clear why it would \nbe a mistake for the Commission to assert blanket jurisdiction over co-location arrangements based \non that load’s supposed receipt of jurisdictional transmission service of ancillary services.  As \nTalen has elsewhere explained at length, the data center co-located with Susquehanna is not a \nnetwork customer and has no right to take transmission service or backup power from the grid.12  \nSusquehanna installed a protection scheme under which the co-located load will separate in the \nevent of a loss of output from the generation facilities; in such a case, “redundant signals will be \nsent to an isolation breaker which will then open and prevent the co-located load from receiving \nany power or services from the grid,” meaning that it is physically impossible for power to be \nwheeled from the network to the generator and then to the co-located load.13  It therefore makes \nno sense to suggest that FERC’s jurisdiction over this type of co-location arrangement stems from \nany draw that the data center makes on the network, since such a draw would be impossible.   \nAny assertion of FERC jurisdiction premised on the idea that “islanded” co-located load \nalways takes jurisdictional transmission service would be overbroad and arbitrary.  The practical \neffect of such an assertion would be to improperly federalize the entire electric system, in \ncontravention of the careful jurisdictional lines Congress has drawn.  Importantly, the Commission \ncan order PJM to implement all five options not currently in its Tariff that it presented for the co-\nlocation of large loads while respecting the jurisdictional lines Congress has established. \n \n11 PJM Interconnection, L.L.C., Docket No. ER24-2172-001, Motion for Leave to Answer and Answer of \nSusquehanna Nuclear, LLC at 2 (filed Oct. 22, 2024) (“Susquehanna October 2024 ER24-2172 Answer”); see id. at \n4–6. \n12 See PJM Interconnection, L.L.C., Docket No. ER24-2172-000, Motion for Leave and Answer of Susquehanna \nNuclear, LLC at 9 (filed July 5, 2024). \n13 Susquehanna October 2024 ER24-2172 Answer at 3; see id. at 4–6."},{"page":8,"startToken":2240,"endToken":2542,"text":"8 \nFurther, it is important to consider the fact that large load customers are not opting to co-\nlocate with a generator in an effort to avoid FERC (or state) jurisdiction.  Instead, co-location often \noffers a faster path to energization that traditional utility connections (at least in the short-term).  \nTransmission utility companies should not be permitted to slow down economic development \nsimply to insert themselves and collect rent (at the expense of their ratepayers). \nb.  \nFERC Jurisdiction Over Interconnection.    \nIn Exelon’s pending PDO Proceeding (EL24-149), the Utilities have argued that the \ninterconnection of end-use load is not FERC jurisdictional, supposedly because the \ninterconnection procedures implemented by Order No. 2003 apply only to generation and not to \nload.14  At bottom, the Utilities’ position reduces to the notion that, if a State has jurisdiction over \none stream of a wholesale generator’s output (e.g., a retail sale to co-located load), then the \nCommission somehow loses jurisdiction over that generator’s interconnection to the interstate \ngrid.   \nThat makes no sense.  These Utilities cannot be right that the presence of non-jurisdictional \nfacilities behind the meter divests FERC of all jurisdiction over the generator’s interconnection, \nbecause non-jurisdictional facilities (including the generator itself) always exist behind the meter.  \nInterconnection service is a form of FERC-jurisdictional service, and a generator’s interconnection \nto the interstate transmission system does not stop being FERC-jurisdictional merely because there \nis co-located load behind the point of interconnection.  For that reason, FERC has for decades \napproved amendments to ISAs designed to accommodate co-located load.  Were that precedent \nnot enough to resolve the question, Order No. 2003 itself expressly rejected the idea that FERC \n \n14 See, e.g., Baltimore Gas & Elec. Co., Docket No. EL24-149-000 Baltimore Gas & Electric Company and PECO \nEnergy Company Petition for a Declaratory Order at 1, 8–12 (filed Sept. 30, 2024)."},{"page":9,"startToken":2542,"endToken":2899,"text":"9 \nloses jurisdiction over interconnections if the generator makes behind-the-meter sales.15  The \nUtilities’ premise is also flatly undermined by the Supreme Court’s decision in EPSA, which \nconfirmed that FERC can exercise jurisdiction over matters the FPA charges it with administering, \neven if the exercise of jurisdiction indirectly affects the States’ regulatory powers, so long as \nFERC’s action does not “target” the States’ domain.16 \nAs a final matter, it bears mention that these Utilities’ jurisdictional theories cannot be \nsquared with one another.  Indeed, multiple commenters have already flagged how “odd[]” it is \nfor the Utilities to argue in one proceeding that FERC lacks jurisdiction over co-located load, only \nto turn on a dime and argue in numerous other proceedings that FERC does have jurisdiction over \nco-located load and should leverage that jurisdiction to approve tariff proposals that would treat \nco-located load as always taking FERC-jurisdictional transmission service.17  The Commission \nshould reject these Utilities’ outcome-driven jurisdictional theories. \n3.  \nThe Commission’s Jurisdiction Is Limited to Establishing Operating \nParameters for Co-Located Load Arrangements.  \nOnce the Commission confirms that it does have jurisdiction over the co-location \narrangements contemplated by PJM’s Answer to the Show Cause Order, its next task will be to \ndefine the scope of that jurisdiction and explain how it will be exercised. \nAs the Supreme Court has explained, the Federal Power Act contemplates a system of \ncooperative federalism under which both FERC and the States have important roles to play.18  With \n \n15 Order No. 2003, 104 FERC ¶ 61,103, PP 813–14 (2003). \n16 See EPSA, 577 U.S. at 264–65; see also Baltimore Gas & Elec. Co., Docket No. EL24-149-000, Protest of \nConstellation Energy Generation, LLC at 16 (filed Oct. 30, 2024) (“Constellation EL24-149 Protest”); Baltimore Gas \n& Elec. Co., Docket No. EL24-149-000, Protest of the PSEG Companies at 6–9 (filed Oct. 30, 2024) (“PSEG EL24-\n149 Protest”). \n17 PSEG EL24-149 Protest at 5 n.16; see Baltimore Gas & Elec. Co., Docket No. EL24-149-000, Protest of Calpine \nCorporation at 4 (filed Oct. 30, 2024); Constellation EL24-149 Protest at 8 & n.25. \n18 See New York v. FERC, 535 U.S. 1, 20–24 (2002)."},{"page":10,"startToken":2899,"endToken":3247,"text":"10 \nrespect to co-location, FERC’s limited role is merely to ensure that the rates and practices within \nits limited jurisdiction are “just and reasonable”19—e.g., that the co-location arrangement does not \nimpair overall system reliability; that interconnections between generators and the grid are safe \nand reliable; and, when co-located load takes jurisdictional transmission service, that the rate for \nthat service is reasonable.  But because States have “regulatory authority over retail sales (as well \nas intrastate wholesale sales),”20 FERC cannot act to superintend the more granular details of co-\nlocated load arrangements.21  Likewise, FERC cannot prohibit or discourage co-location \narrangements because of supposed retail rate impacts,22 and cannot force entities to participate in \nfederally regulated energy or capacity markets.23  Nor can FERC put a thumb on the scale and \nfavor one type of co-location arrangement or configuration over another; it is the role of the \nmarket—not the Commission—to pick winners and losers.24  In short, FERC’s role is simply to \nset basic guardrails within which co-location arrangements must operate.   \nStates, by contrast, have the power to fill in the details.  States control facility siting and \nthe resource generation mix, as explained above.  States decide which entities (if any) can make \nretail sales in co-location arrangements, and how costs will be recovered with respect to those \nsales.  States should therefore be in the drivers’ seat with respect to crafting the bulk of the on-the-\nground regulatory framework governing co-location.  Indeed, a central feature of “Our \n \n19 16 U.S.C. § 824d. \n20 EPSA, 577 U.S. at 279. \n21 The FPA makes clear that, while FERC does have jurisdiction over the “transmission of electric energy in interstate \ncommerce and to the sale of electric energy at wholesale in interstate commerce,” it does not have jurisdiction over \n“any other sale of electric energy” nor over “facilities used for the generation of electric energy.” 16 U.S.C. \n§ 824(b)(1).   \n22 See Susquehanna September 2024 ER24-2172 Comments at 4–5. \n23 See id. at 4–5, 9. \n24 Talen Post-Conference Comments at 2."},{"page":11,"startToken":3247,"endToken":3541,"text":"11 \nFederalism”25 is that the role of the federal government and its agencies is sometimes to get out of \nthe States’ way.  This is exactly such a case. \nStates are already rising to the moment.  Indeed, many States are well along in developing \nframeworks to deal with the issue of co-location—frameworks that operate within the scaffolding \nerected by FERC, but that implement solutions tailored to local problems and reflect collaborative \nbuy-in from a variety of stakeholders. \nFor example, Talen strongly supports ongoing efforts by regulators and policy leaders in \nPennsylvania to develop a workable approach to co-location.  On April 24, 2025, the Pennsylvania \nPublic Utility Commission will hold a hearing to discuss large loads.26  At that hearing, numerous \nstakeholders—including transmission and distribution owners, large load customers, and \nconsumer advocates—will present their views on how best to ensure a fair, transparent, and \nforward-looking approach to connecting high-energy users to the grid while protecting existing \nutility customers.  The hearing will lay the groundwork for a forthcoming tariff for large loads in \nPennsylvania. \nThese are exactly the kinds of collaborative efforts that FERC should encourage.  Congress \nhas elected to place States—the laboratories of democracy27—in a leadership role with respect to \nretail sales of electricity and behind-the-meter configurations.  FERC should allow the States to \ndischarge that duty, and should not use this proceeding to block (or interfere with) States’ efforts \nto develop solutions that work for them. \n \n25 Younger v. Harris, 401 U.S. 37, 44 (1971). \n26 See Peter Hall, Pa. Public Utility Commission Sets Hearing on AI Data Centers’ Impacts on Electricity, \nPennsylvania Capital Star (Mar. 28, 2025), https://tinyurl.com/msysv8cs. \n27 See New State Ice Co. v. Liebmann, 285 U.S. 262, 311 (1932) (Brandeis, J., dissenting)."},{"page":12,"startToken":3541,"endToken":3906,"text":"12 \nB.  \nThe Eight Options Presented by PJM are Just and Reasonable, and FERC Should \nOrder PJM to Make Necessary Modifications to its Tariff to Effectuate the Five \nOptions Not Already in the PJM Tariff Within 30 Days of FERC’s Order.  \nIt is important for the Commission to provide clarity and certainty to PJM, its stakeholders, \nand market participants.  As such, Talen respectfully requests that the Commission direct PJM to \nsubmit Tariff modifications to address the five co-location configuration options proposed by PJM \nand not already addressed in its Tariff.  Talen urges the Commission to order PJM to make all \nnecessary Tariff modifications to effectuate the selection of Options 4 through 8 as a co-located \nload configuration within 30 days of FERC’s order in this proceeding.  \nAs PJM explained in its Answer, its Tariff already contains language to configure co-\nlocated load as: network load with its own point of interconnection (“POI”) to the grid (Option 1); \nnetwork load that shares the same POI with the generator but is separately metered (Option 2); or \nnetwork load that has a behind-the-meter generation agreement with a co-located generator \n(Option 3).28  Conversely, PJM believes it will need to modify its Tariff language to allow co-\nlocation configuration arrangements where: co-located load is non-network load connected \ndirectly to a generator connected to the PJM transmission system with various protections in place \nto avoid the potential of delivery of system energy to serve the load (Option 4); co-located load is \nconfigured the same as Option 4 and also has conditional approval from PJM to take back-up \npower from the grid if necessary (Option 5); co-located load is network load and it brings \nadditional generation to the PJM transmission system that could serve as a capacity resource for \nPJM (Option 6)29; co-located load is network load but it uses a new transitional non-capacity \n \n28 PJM Answer at 9-13; see PJM Answer Ex. A.  \n29 Talen believes Option 6 is not actually a separate option for configuration.  Instead, Talen believes Option 6 is a \nresource adequacy proposal.  However, Talen does oppose PJM referring to and including Option 6 as a co-located \nload configuration option for the purposes of its Answer."},{"page":13,"startToken":3906,"endToken":4209,"text":"13 \nbacked service offering until any resource adequacy issues associated with its load addition are \naddressed (Option 7); or co-located load is network load and participates in PJM’s demand \nresponse programs (Option 8).30  \nThe Commission has stated that it takes the reliability concerns raised by PJM with respect \nto issues of co-location of large load “extremely seriously.”31  The Commission should act \ndecisively and quickly to support PJM, so that it can meet the needs of its stakeholders and ensure \nthe ongoing reliability and stability of the PJM transmission system.   \nTalen agrees that co-located load directly connected to a generator connected to the PJM \ntransmission system should pay for jurisdictional services, to the extent they are used.  Talen has \npreviously argued that the indirect connection of load to the transmission grid does not alone \nsignify that such load is utilizing any jurisdictional services.  If co-located load is not using any \nFERC jurisdictional services at all, the load should have no financial responsibility to pay for those \nservices, including ancillary services.  While Talen continues to believe this position to be correct, \nin the interest of compromise, Talen supports the current Option 4 that includes the load paying \nfor certain ancillary services.   \nBy offering multiple types of co-located load configurations in its Tariff—including ones \nthat allow co-located load arrangements to not be network load and/or not take any jurisdictional \nservices—PJM will be adopting the straightforward and easily applied principle that co-located \nload will pay for network or grid services to the extent the load uses those services.32  Ordering \nPJM to modify its Tariff so that it may implement as soon as possible all five options not currently \n \n30 PJM Answer at 13-20; see PJM Answer Ex. A.  \n31 Show Cause Order P 83.  \n32 See Talen Post-Conference Comments at 2."},{"page":14,"startToken":4209,"endToken":4390,"text":"14 \nin its Tariff will provide the regulatory certainty needed to encourage the growth of large load co-\nlocation while at the same time ensuring steady, reliable power for all ratepayers.  \nII. CONCLUSION \nThe framework presented by PJM is just and reasonable and not unduly discriminatory.  \nPJM stakeholders rely on the Commission to make it possible for PJM to administer its \ntransmission system in a way that meets the needs of its diverse stakeholders.  The Commission \nhas limited jurisdiction to order PJM to enact the framework it introduced.  It is urgent that the \nCommission act in accordance with its jurisdiction as soon as possible to promote economic \ngrowth and support PJM in maintaining reliability on its transmission system. \n  \n                                                                      Respectfully submitted, \n \n \n/s/ William S. Scherman \nWilliam S. Scherman \nJeffrey M. Jakubiak \nJames T. Dawson   \nMelinda J. Warner \nVinson & Elkins LLP \n2200 Pennsylvania Avenue, NW \nSuite 500 West \nWashington, DC 20037 \n \nJennifer Mansh \nTalen Energy Corporation \nSenior Vice President, Regulatory and \nExternal Affairs \n600 Hamilton St., Suite 600 \nAllentown, PA  18101 \nJennifer.Mansh@TalenEnergy.com\n                                                                      Counsel for Talen Energy Corporation  \nApril 23, 2025"},{"page":15,"startToken":4390,"endToken":4442,"text":"15 \n \nCERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service lists compiled by the Secretary in these proceedings. \nDated at Washington, DC, this 23rd day of April 2025. \n \n/s/ Melinda J. Warner  \n \nMelinda J. Warner \nVinson & Elkins LLP"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":710,"startToken":0,"endToken":334},{"p":2,"at":710,"title":"I. COMMENTS","method":"printed heading","endPage":2,"endAt":725,"startToken":334,"endToken":336},{"p":2,"at":725,"title":"A. FERC Has Limited Jurisdiction Over Co-Location Arrangements and Should Not","method":"printed heading","endPage":12,"endAt":4,"startToken":336,"endToken":3542},{"p":12,"at":4,"title":"B. The Eight Options Presented by PJM are Just and Reasonable, and FERC Should","method":"printed heading","endPage":14,"endAt":191,"startToken":3542,"endToken":4240},{"p":14,"at":191,"title":"II. CONCLUSION","method":"printed heading","endPage":15,"endAt":6,"startToken":4240,"endToken":4391},{"p":15,"at":6,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":15,"endAt":329,"startToken":4391,"endToken":4442}]}