{"document":{"slug":"rec-20250423-5227-2","title":"Brattle Energy Park Integration Report 2025-04-23","issued":"2025-04-23","accession":"20250423-5227","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Bloom Energy Corporation","kind":"attachment","file":"sources/filings/text/20250423-5227_002.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250423-5227","tier":"record","parent":"rec-20250423-5227","sha256":"221ef96d8455745cc7cf9fd5becfd7760010d0f0b818826beb1e0ab1b68a1835","pages":35,"tokens":11588,"emptyPages":[],"textThemes":["study","colo","adequacy","flex"]},"pages":[{"page":1,"startToken":0,"endToken":30,"text":"Accelerating Integration of New Co-located Generation and Loads \nBrattle.com |  \nAccelerating Integration of New \nCo-located Generation and Loads \n \nPREPARED BY \nAndrew Levitt \nJohannes Pfeifenberger \nAniruddh Mohan \nPREPARED FOR \nBloom Energy"},{"page":2,"startToken":30,"endToken":148,"text":"Accelerating Integration of New Co-located Generation and Loads \nBrattle.com | i \nNOTICE  \n• This report was prepared for Bloom Energy Corporation, in accordance with The Brattle \nGroup’s engagement terms, and is intended to be read and used as a whole and not in \nparts.  \n• The report reflects the analyses and opinions of the authors and does not necessarily reflect \nthose of The Brattle Group’s clients or other consultants. \n• There are no third-party beneficiaries with respect to this report, and The Brattle Group \ndoes not accept any liability to any third party in respect of the contents of this report or \nany actions taken or decisions made, as a consequence of the information set forth herein. \n \n© 2025 The Brattle Group"},{"page":3,"startToken":148,"endToken":280,"text":"Accelerating Integration of New Co-located Generation and Loads \nBrattle.com | ii \nTABLE OF CONTENTS \nExecutive Summary................................................................................................. 1 \n \nIntroduction ...................................................................................................... 7 \n Energy Park Integration Is a Practical Way to Quickly Connect Large Loads \nwith Fewer Transmission Upgrades ................................................................ 11 \nA. EPI-Based Contingency Studies Reduce Transmission Impacts and Interconnection \nTime ................................................................................................................................ 12 \nB. Experience Elsewhere Highlights the Practicality of Energy Park Integration Studies .. 22 \nC. The Benefits of an EPI Approach Are Highest When Energy Parks Can Dependably \nTransact with the Grid on an As-Available, Non-Firm Basis ........................................... 23 \n Reforms are Needed to Realize the Speed and Cost-Effectiveness Benefits \nof Energy Park Integration .............................................................................. 24 \nA. The Status Quo Does not Achieve the Benefits of EPI Studies ....................................... 24 \nB. Reforms Can Achieve Energy Park Integration Benefits ................................................ 27 \n Energy Park Integration Reform Could Alleviate Resource Adequacy Strain ... 29 \n Conclusion ...................................................................................................... 31"},{"page":4,"startToken":280,"endToken":620,"text":"Accelerating Integration of New Co-located Generation and Loads \nBrattle.com | 1 \nExecutive Summary \n _________  \nFaster connection of large loads for artificial intelligence has been identified as a federal \npriority. Many new large loads such as data centers are applying to connect to the grid in PJM \nand elsewhere, creating opportunities for economic growth and higher utilization of electrical \ninfrastructure.  \nThis load growth is challenging both transmission and resource adequacy. In some cases, new \nlarge loads exceed existing transmission capacity, and new customers must wait while \n(potentially costly) transmission upgrades are made. In other cases, load growth exceeds \nprojected additions of generating capacity. In many areas, concerns have been raised regarding \nthe affordability implications for consumers of these transmission and capacity impacts from \ngrowth in large loads. The co-location of such loads with generation has emerged as one \nsolution to address these transmission and resource adequacy challenges.1 PJM \nInterconnection L.L.C. (PJM) recently validated co-location as a possible solution in its Answer \nto the Federal Energy Regulatory Commission (FERC) in Docket No. EL25-49-000.2 \nIn this report we assess the concept of connecting new generation and co-located load as a \ncomposite facility called an “Energy Park.” This approach can significantly reduce the need for \nnew transmission while accelerating integration of new loads together with new generation \nresources that can ease resource adequacy concerns, reducing costly resource and grid \ninvestments and mitigating bill impacts for consumers. We assess current processes in PJM and \nidentify possible reforms necessary to facilitate the interconnection of such Energy Parks.  \nThe key findings in our study are as follows: \n1. Integrated Energy Park interconnection is a practical way to quickly connect large \nloads with fewer transmission upgrades \n \n1  See for e.g., Large Loads Co-Located at Generating Facilities, Docket No. AD24-11-000 (technical conference \nheld on November 1, 2024); Office of Policy, Department of Energy, Request for Information on Artificial \nIntelligence on DOE Lands (issued April 3, 2025). \n2  PJM, Answer of PJM Interconnection L.L.C, FERC Docket No. EL25-49-000, March 24, 2025, hereafter “PJM \nAnswer.”"},{"page":5,"startToken":620,"endToken":1005,"text":"Accelerating Integration of New Co-located Generation and Loads \nBrattle.com | 2 \nEnergy Parks connected to the transmission system consist of three components: generation, \nco-located load, and a mechanism to control flows into or out of the Energy Park at the point of \ninterconnection (POI) with the transmission grid. Following the interconnection approach for \nPrivate Use Networks (PUNs) used in the Electric Reliability Council of Texas (ERCOT), we \ndescribe an Energy Park Integration (EPI) process that would study the Energy Park as a \ncomposite load and generation facility (at smaller scale referred to as a “micro grid”), instead of \nseparately studying the load in one process and the generator in another.3  \nWe illustrate stylized contingency cases (such as shown in Figure ES-1 below) that are used in \nreliability studies to show how an Energy Park studied as a composite facility can be connected \nto the grid more quickly and less expensively due to lower transmission upgrades relative to a \nconventional study approach. This is because, in the conventional approach, PJM and the \ntransmission owner separately evaluate generation and load components respectively without \nconsideration of the self-balancing effect of co-located generation on co-located load, and \npotentially ignore the action of a control system (and system protection mechanism) that limits \nEnergy Park power flows to and from the grid to specified levels.  \nIn all cases where the grid connection of the Energy Park itself is smaller than the Energy Park’s \nload and generation, the park’s embedded generation—such as a combination of fuel cells, \nnatural gas resources, battery storage, and variable resources—would serve as the primary \ngeneration source supplying the relevant portion of the Energy Park’s load. For the portion of \nEnergy Park load that can be served from the grid, the embedded generation would both be \ndispatchable into the regional market and serve as backup generation for the Energy Park load.4 \n \n \n3  See  ERCOT Update to Texas House of Representatives Committee on State Affairs, March 5, 2025, at p. 6 \n4  We understand from Energy Park developers that installed (backup or primary) generating capacity typically \nconsists of numerous individual generators with surplus total capacity such that the planned or forced outage \nof individual Energy Park generators would not affect the Energy Park’s ability to serve its load even if the grid \nconnection is unavailable."},{"page":6,"startToken":1005,"endToken":1322,"text":"Accelerating Integration of New Co-located Generation and Loads \nBrattle.com | 3 \nFIGURE ES-1: CONTINGENCY CASE FOR THE PROPOSED ENERGY PARK INTEGRATION APPROACH (LEFT) \nVS. CONVENTIONAL LOAD-ONLY APPROACH (RIGHT), SHOWING OVERLOADS AND UNNECESSARY \nUPGRADES IN THE LATTER  \n \nNotes: The local grid contains the Energy Park with 500 MW of co-located load and an array of co-located \ngenerators, as well as an unaffiliated generator nearby, all of which are connected to the rest of the grid by a pair \nof transmission lines that together can transfer 340 MW. While the local grid can host the 500 MW load of the \ndata center in a base case by relying on grid imports that include the unaffiliated generator, such a base case \nwould not be deemed secure to the contingency (the outage of the nearby unaffiliated generator) under \nconventional load-only study criteria as shown on the right, and would therefore require significant transmission \nupgrades. As shown on the left, these upgrades can be avoided when considering that the Energy Park’s controls \nof load and generation will be able to limit grid imports to 340 MW (by dispatching at least 160 MW of self-\ngeneration within the Energy Park). \n \n2. Accelerated interconnection of Energy Parks with co-located data center loads and \nnew generation is in the interest of many stakeholders  \nPJM in its response to FERC stated there is nearly 8.5 GW of proposed large loads waiting to be \nconnected to the transmission system and co-located with existing generation, and highlighted \na faster interconnection option for new loads that are co-located with new generation (i.e., \nEnergy Parks).5  \nMeanwhile, there are many more large new loads planned that will not be co-located with \nexisting generation, representing much of the rapid increase in PJM load forecasts—which, in \nturn, is driving costly transmission upgrades and accelerating resource adequacy concerns. \n \n5  PJM Answer, Exhibit B, and New Option 6, at page 16"},{"page":7,"startToken":1322,"endToken":1783,"text":"Accelerating Integration of New Co-located Generation and Loads \nBrattle.com | 4 \nMost of these large consumers, while apparently standalone load, are in fact planning to install \nco-located backup generation. Because this backup generation typically consists of diesel \ngenerators that are only permitted to run for a limited number of hours per year, and are \nconfigured to run only while disconnected from the grid, most large load customers have not \ndesigned their backup generation to support system-wide transmission and resource adequacy \nneeds (not even as self-supply capacity that seldom runs). However, by planning to co-locate \nnew primary generation that can run at any time (as well as potentially providing backup power \nif needed), the new customer can supply all or part of its energy and resource adequacy on-site, \nminimizing the impact on markets and transmission and supporting the interconnected grid.6  \nBecause an integrated EPI process as described in this report offers substantial benefits for \ndevelopers to more quickly connect new loads in an Energy Park configuration, nearly all new \nlarge load customers would be incentivized to design their on-site generation plans such that, in \naddition to meeting backup power needs, it can also serve as primary generation to self-supply \nenergy and resource adequacy and provide valuable grid support (as necessary). By \nincentivizing new large load customers to bring their own new generation, the proposed \nintegrated Energy Park interconnection process offers a solution that can more quickly \nintegrate large new loads (consistent with federal priorities) while addressing the resource \nadequacy and transmission challenges and lowering cost impacts on consumers. \n3. The benefits of an EPI approach are highest when Energy Parks are dispatchable by \nthe transmission operator or regional market to dependably transact with the grid on \nan “as-needed” basis \nWith dispatchable onsite generation such as fuel cells, gas turbines, or battery storage, an \nEnergy Park can self-supply in full or in part (depending on configuration) its own load when \n(i) the grid is not available, (ii) purchases from the grid are not advantageous, or (iii) based on \nbilateral contractual terms (i.e., if during off-peak hours that the co-located generation is more \nthan sufficient to meet the lower power needed by load).  \nAt times, an Energy Park would not only be able to self provide the resource adequacy needs of \nits load, it would also be able to export power to the grid when grid capacity is available and \nsurplus generation exists and is cost effective. This capability of the Energy Park can provide a \n \n6  The on-site provision of energy and resource adequacy to the load could be through self-supply, through an \narrangement with an independent generation owner, or with the local utility, depending on state law. \nGeneration ownership is not determinative in applying the integrated EPI arrangement proposed here."},{"page":8,"startToken":1783,"endToken":2184,"text":"Accelerating Integration of New Co-located Generation and Loads \nBrattle.com | 5 \nvaluable reliability contribution to the grid to the extent such net injections are possible during \ntimes of scarcity or local emergencies. \nBy reflecting the controllable nature of Energy Park withdrawals and injections to the grid, EPI \nstudies are less likely to conclude that expensive and time-consuming transmission upgrades \nare necessary, and therefore can facilitate the more timely interconnection of new loads. This \noutcome is premised on the grid operator’s ability to rely on the Energy Park to control net \ninjections or withdrawals depending on what the grid is able to accommodate in real-time \noperations. The energy market offer, clearing, and dispatch systems already used for other grid-\nconnected generators, storage, and demand-response resources can be utilized for Energy \nParks, provided that Energy Park operators follow the grid operators dispatch instructions for \ncontingency response and market interactions.7 Transmission planning benefits are maximized \nwhen an Energy Park is able to respond automatically to grid contingencies (transmission \noutages and generator outages) in coordination with PJM and transmission owner operations. \n* \n* \n* \nIn summary, EPI is practical, addresses resource adequacy and grid challenges, and offers \nsignificant benefits if the Energy Park resources are dispatchable on as-needed basis. The \nadoption of an EPI process would greatly accelerate the interconnection of large new loads by \nreplacing or supplementing backup-only generation with primary generation resources that can \nself-supply all or a portion of Energy Park loads, thereby mitigating the resource adequacy and \ntransmission challenges and consumer cost impacts of rapid load growth. \nAs detailed in Section III below, we find that current practice in PJM would need to be \nenhanced via the following enabling reforms in order to obtain the benefits of the EPI study \nprocess: \n• PJM and transmission owner: develop and document EPI protocols, applicable for Energy \nParks, as an alternative to the currently applicable separate study processes, including the \nPJM generator interconnection study process, the PJM ‘Do No Harm’ study, transmission \nowner load integration study, and (in limited cases) the PJM regional transmission \nexpansion process (RTEP).  The EPI protocols would need to include provisions for \n \n7  While the main focus of this report is on Energy Parks with the ability to export to the grid, non-exporting \nEnergy Parks could be similarly dispatched by PJM and transmission owners in real time operations (e.g., \nthrough modified demand response frameworks that are incorporated into security constrained economic \ndispatch)."},{"page":9,"startToken":2184,"endToken":2455,"text":"Accelerating Integration of New Co-located Generation and Loads \nBrattle.com | 6 \ncoordination between separate study processes (unless the relevant parties integrate them \ninto a single process). \n• PJM and/or transmission owner: Document technical standards for the Energy Park \ncontrols and protection mechanisms used to limit physical withdrawals and injections \nbetween the Energy Park and the grid to the pre-specified amounts. Develop provisions to \nensure that PJM and transmission operators can rely on the Energy Park to control net \ninjections or withdrawals when grid capacity is limited (during contingencies) in real time \noperations. \n• PJM: allow for and study non-firm grid injection requests based on “as available” grid \ncapacity (i.e., less firm than current Energy-only interconnections). Study these non-firm \nEnergy Park injections through an expedited screening process similar to that of PJM’s new \nSurplus Interconnection Service (SIS) or Capacity Interconnection Rights (CIR) replacement \nprocesses, given that non-firm net injections by the Energy Park can be controlled \nautomatically so they will not cause transmission impacts beyond the designated levels.8  \n \n \n \n8  The SIS process is an accelerated path through the generation interconnection queue process that assesses the \naddition of new supply technologies to existing generators (e.g., adding solar to an existing combustion turbine \ninterconnection point) as long as total injections can be controlled to stay within the limits of the existing \ninterconnection service agreement. This allows for an expedited study process to confirm that the new \nconfiguration does not materially impact grid reliability. CIR replacement takes a similar approach to confirm \nabsence of impact when a retiring generator is replaced with a different generation technology type at \nsubstantially the same interconnection point."},{"page":10,"startToken":2455,"endToken":2916,"text":"Accelerating Integration of New Co-located Generation and Loads \nBrattle.com | 7 \n Introduction \n _________  \nPJM, the Regional Transmission Organization (RTO) serving 13 states and the District of \nColumbia, forecasts rapid growth in electricity demand, driven in large part by expansion of \nplanned data centers and other large loads.9 Transmission infrastructure and resource \nadequacy are being strained to integrate the new loads. In some cases, new large loads must \nwait years while time-consuming and costly transmission upgrades are made.10 Importantly, \nPJM has expressed significant concerns over resource adequacy challenges.11 \nSpeed to market is a critical motivation for many new large data center customers, as the ability \nto launch new services and scale operations is critical to competitiveness. There has therefore \nbeen interest in co-locating loads with existing generation instead of going through a lengthy \nload integration process.12 PJM has cited nearly 8.5 GW of large loads (including data centers) \nthat have requested to interconnect in co-location arrangements with existing generators.13 \nCo-locating load with existing generation could avoid the need for time-consuming network \nupgrades prior to connection, but raises a variety of questions (such as cost allocation) that are \nbeyond the scope of this report. Co-location of new loads with existing generation also \nexacerbates PJM’s resource adequacy concerns and can cause transmission reliability issues by \neffectively adding new large load without a corresponding increase in local supply or \ntransmission capability.  \n \n9  PJM’s 2025 load forecast report estimates winter peak load to grow at an average of 3.8% annually over the \nnext 10 years. PJM, Long-Term Load Forecast Report, January 24, 2025 \n10  Josh Saul, Data Centers Face Seven-Year Wait for Dominion Power Hookups, Bloomberg News, August 29, 2024 \n11  PJM, 2024 in Review: Maintaining an Adequate Generation Supply, January 9, 2025 \n12  In November 2024, FERC rejected a proposed amendment to an interconnection service agreement for Talen’s \nSusquehanna power plant in PJM, which sought to increase the transfer capacity to a co-located data center, \nand to recognize the co-located load as fully behind the meter and not ”network load”. PJM Interconnection, \nL.L.C., 189 FERC ¶ 61,078 (2024), reh’g denied, 191 FERC ¶ 61,025 (2025). FERC also held a technical conference \non co-location on November 1, 2024. See note 1 above; see also e.g., Google, Post-Technical Conference \nComments, Large Loads Co-Located at Generating Facilities, FERC Docket No. AD24-11-000, December 10, \n2024, p2-3. In February 2025, FERC issued a show cause order directing PJM and its transmission owners to \ndemonstrate why the existing tariff provisions are adequate for managing co-location scenarios. PJM \nInterconnection, L.L.C., et al., 190 FERC ¶ 61,115 (2025). \n13  Frederick S. Bresler, Statement on Behalf of PJM Interconnection L.L.C, Co-Located Load Technical Conference, \nFERC Docket No. AD24-11-000, November 1, 2024."},{"page":11,"startToken":2916,"endToken":3445,"text":"Accelerating Integration of New Co-located Generation and Loads \nBrattle.com | 8 \nWe focus on a different co-location use case: new large loads that are co-located with new \ngeneration.14 By balancing new load with co-located new supply, integration of the large load is \nfacilitated both in terms of the transmission network (for quicker interconnection) and the \nresource adequacy impact.  \nThe idea of new large loads co-locating with new generation is gaining interest, as highlighted \nby President Trump at the World Economic Forum in Davos, Switzerland in January 2025.15 PJM \nlikewise outlined potential co-location arrangements for this use case that could lead to more \ntimely interconnection while bringing to PJM additional capacity to address resource adequacy \nchallenges.16 In venues across the country, the pros and cons of “bring your own capacity” \nrequirements and incentives have been circulating.17  \nIn this report, we describe a cohesive process to study the integration onto the grid of new \nco-located generation and load at a single facility (including a control mechanism that limits net \nbi-directional grid flows), and we assess whether the approach can accelerate the connection \nprocess. We refer to the composite facility as an “Energy Park,” and propose that PJM \nimplement an Energy Park Integration (EPI) study process to make possible the timely \n \n14  We focus on Energy Parks connected to the transmission system, which have different interconnection \nconsiderations relative to systems connected to lower-voltage distribution facilities. Transmission facilities tend \nto have higher voltages (e.g., above 100 kV) and operate in a networked rather than radial topology, among \nother differences.  \n15  Argus Media, Trump touts off-grid gas, coal for AI data centers, January 24, 2025; Both the current and former \npresidential administrations have encouraged co-location of planned data centers with new energy \ninfrastructure in order to rapidly build out AI infrastructure. See e.g., Department of Energy, Request for \nInformation on co-locating data centers on federal sites for rapid construction with in-place energy \ninfrastructure, April 3, 2025; White House Archives, Executive Order on Advancing United States Leadership in \nArtificial Intelligence Infrastructure, January 14, 2025. \n16  PJM Answer, “New Option 6” on p 17-18 and in Exhibit B. PJM has said it can explore incentives to offer “faster \nprocessing of generation that enters the queue through this option” including through “accelerating \ninterconnection studies of new generation” proposed under this option.  \n17  For example, New Jersey Assembly Bill 5564, introduced on April 10 2025, which requires that new AI data \ncenters arrange for new energy supply; “The addition of large data centers would be easier if the data centers \nbrought new generation to the market in addition to new load.”; Utah Senate Bill 132 allows large loads such as \ndata centers to directly procure power from a co-located generation provider if the local utility and load \ncustomer cannot agree a contract within 90 days; Post-Technical Conference Comments of PJM IMM, Co-\nLocation Technical Conference, at 3; “Pennsylvania could encourage—or require, if necessary, through carefully \ndrafted and structured legislation—new large loads such as data centers to BYOG rather than draw from \nexisting generation supply,” Exelon, Comments in Technical Conference on Resource Adequacy in Pennsylvania \nDocket No. M-2024-3051988, January 9, 2025."},{"page":12,"startToken":3445,"endToken":3750,"text":"Accelerating Integration of New Co-located Generation and Loads \nBrattle.com | 9 \ninterconnection of the co-located new loads and new generation within such Energy Parks and \nderive benefits for reliability and other consumers. 18 \nAs illustrated in Figure 1 below, we define the Energy Park as new generation and load that is \nco-located behind the same grid connection, together with controls and protection mechanisms \nthat can limit maximum flows into and out of the Energy Park. 19  \nFIGURE 1: ENERGY PARK CONCEPT \n \n \nThe EPI study approach shares some traits with the approach PJM labeled “New Option 6” in an \nAnswer to FERC’s recent show cause order regarding load co-location. Of the new potential \noptions described in the PJM Answer, New Option 6 is the only one that applies to co-location \nwith new generation, as opposed to existing generation.20 PJM describes New Option 6 as a \n“Bring Your Own Generation (BYOG)” approach for interconnecting new co-located generation \nand load more quickly. However, New Option 6 envisages firm Capacity Interconnection Rights \n(CIRs) for the full output of Energy Park generation, and Network Load status for all of the load, \nand utilizes separate processes for load integration vs. generator interconnection. Because \n \n18  The concept of ‘Energy Parks’ has been described in the literature referring to co-located load and generation \nbehind a single Point of Interconnection (POI). Energy Innovation Policy and Technology LLC, Energy Parks: A \nNew Strategy to Meet Rising Electricity Demand, December 2024. \n19  For example, the physical principles supporting such protection mechanisms have been described in Schedule \nF, Part E of the amended Interconnection Service Agreement (ISA) between Talen and PJM submitted to FERC \nin June 2024 [FERC Docket No. ER24-2172-000] and cited by Commissioner Phillips in his dissent on the Talen \nISA decision in FERC on November 1, 2024. \n20  See Exhibit A, PJM Answer."},{"page":13,"startToken":3750,"endToken":4110,"text":"Accelerating Integration of New Co-located Generation and Loads \nBrattle.com | 10 \nPJM’s proposed New Option 6 involves an interconnection queue request for CIRs for the \nentirety of the energy park generation, the study process will test the network’s ability to \ndeliver the full output of the generation to all PJM load (ignoring the energy park load unless \nconducting an EPI-style approach), despite the intent of the generation to inject only a non-firm \nbasis, and to self-supply resource adequacy only at the same grid connection point as the load. \nIn the example shown above, the 550 MW fleet of many small energy park generators meets all \nof the firm resource adequacy needs of the 500 MW energy park load without any PJM \ntransmission; however, as shown below, the generation may not be able to deliver any capacity \nto the rest of PJM, for example in the case that the transmission network is fully committed to \ndeliverability associated with CIRs of other, unaffiliated generators. In contrast, the proposed \nEPI process allows for non-firm net injections and non-firm net withdrawals, recognizes the \nability of the energy park to self-supply energy and capacity, and studies the energy park in light \nof the self-balancing effect of co-located generation and load, reducing the estimated network \nupgrades and time required to connect the Energy Park.  \nPrecedent for the practicality of the proposed EPI approach exists in the interconnection \nprocess for Private Use Networks (PUNs) in the Electric Reliability Council of Texas (ERCOT), \nwhich models the PUN as a composite of both load and generation. It is also reflected in a \npending proposal in ERCOT regarding interconnection of other non-PUN co-located large load \narrangements.21  \nIn the following sections, we describe the EPI studies, show how they accelerate energy park \nconnection time and cost by reducing upgrades, and identify the reforms needed to achieve the \nbenefits of EPI studies. We also highlight how EPI study reform can contribute to addressing the \nresource adequacy strain faced by PJM and reduce bill impacts for all consumers from growth \nin large loads.  \n \n \n \n21  ERCOT, NPRR1234 and PGRR115: Overview, Key Concepts, and Impact to the Generation Interconnection \nProcess, June 12, 2024, p10"},{"page":14,"startToken":4110,"endToken":4518,"text":"Accelerating Integration of New Co-located Generation and Loads \nBrattle.com | 11 \n Energy Park Integration Is a Practical Way to \nQuickly Connect Large Loads with Fewer \nTransmission Upgrades \n _________  \nAs shown below, because an Energy Park locally supplies all or part of its load, it can be \nconnected to the grid with fewer transmission upgrades (and thus more quickly) when it is \nstudied as an integrated unit. By contrast, using the existing separated processes to study the \nnew load component of an Energy Park (without recognizing the co-located generation) while \nstudying the new generation (without recognizing the co-located load) will ignore these self-\nsupply benefits and overstate the necessary transmission upgrades, slowing down \ninterconnection and unnecessarily increasing costs.  \nThe proposed EPI approach models the composite behavior of load and generation in an Energy \nPark by accounting for its three essential components: generators, load, and a control \nmechanism that limits net exchanges with the grid. \nFor example, as shown in Figure 1 above, consider an Energy Park with 500 MW of load; on-site \nprimary generation totaling 550 MW of installed capacity (e.g., composed of approximately \n1,700 individual generation units of 325 kW each to ensure high availability for on-site supply in \ncase of maintenance or other unit outages, such as Bloom Energy’s 325 kW individual Energy \nServer systems); and a control mechanism that limits net grid withdrawals to less than 340 MW \nand (non-firm) net grid injections to less than 50 MW. The EPI study approach would model \nboth the Energy Park generation and load online in the base load study case. Studied net load \nimpacts would be limited to just the maximum net grid withdrawal at the Energy Park (340 MW \nnet withdrawal in the example), while assessed net injection impacts from the generation \nwould be limited to the maximum possible injection level (50 MW). \nBy contrast, if today’s studies are performed separately on the generation or load component \nin isolation, they will analyze reliability needs to accommodate up to 500 MW of withdrawals \nfrom the grid and 550 MW of injections into the grid, as highlighted in the New Option 6 \nrequirement that a co-located generator have firm CIRs. In other words, the integration study \nof the Energy Park load would have no mechanism to simultaneously consider the co-located \nEnergy Park generation (which would be represented in a separate process, the PJM generation \ninterconnection queue), leading PJM to model a 550 MW base case injection and the"},{"page":15,"startToken":4518,"endToken":4985,"text":"Accelerating Integration of New Co-located Generation and Loads \nBrattle.com | 12 \ntransmission owner to model a 500 MW base case withdrawal. The current co-location studies \ndescribed by PJM (load integration, do no harm, generator interconnection, etc.) are not set up \nto coordinate outcomes for the separate components they study, this obstructing the ability of \nany process to study the injections and withdrawals levels on the lower net basis (which relies \non successful integration outcomes for all processes), rather than on the gross. \nThe above aptly captures the intuition behind PJM reliability study cases. One needs to \nrecognize, however, that transmission reliability needs are often driven by “contingency” \nstudies, which are less intuitive. In the next section, we therefore step through the standard \ncontingency studies used for load reliability planning to show that the proposed EPI study \napproach yields lower transmission impacts even considering the contingency cases used in \ntransmission planning. These also show the role of the control mechanism in reducing such \ntransmission impacts. \nA. EPI-Based Contingency Studies Reduce \nTransmission Impacts and Interconnection Time \nTo assess the effect of the EPI approach on transmission upgrades, we evaluate several \ncontingency study cases using an expanded example of the Energy Park shown in Figure 1 \nabove. The EPI approach is an integrated connection process relying on specified maximum net \nwithdrawals (and, if applicable, net injections). Relying on a set configuration that has been \nsubmitted by the EPI customer, and which can only be changed under prescribed protocols, the \nEPI study process assesses different cases for net withdrawals (as load) and the net injections \n(as generation). For the net load/withdrawal cases, the EPI process conducts general reliability \nstudies (like those used in the transmission owner load integration studies).22 For the net \ninjection/generation cases, the EPI process assesses non-firm net injections using a process \nsimilar to that used to study Surplus Interconnection Service (SIS) or CIR replacement. This non-\nfirm injection assessment recognizes the secondary purpose of energy park net injections, \n \n22  PJM planners conduct different categories of studies: general reliability is ensured through test cases including \nthe P0 through P7 events described in the North American Electric Reliability Corporation (NERC) standard \nTPL-001; congestion is limited through a suite of generator deliverability cases; and zonal adequacy is ensured \nthrough load deliverability studies. We use general reliability study cases from TPL-001 to illustrate the effect \nof the EPI approach on the potential for thermal overloads in contingency cases, including those in the \ngenerator and load deliverability studies. In addition to thermal studies, planners study voltage, stability, and \nshort circuit effects of interconnection. Our findings apply to some extent to voltage results, but do not apply \nto the short circuit or stability studies for Energy Parks, which are not frequent causes of the major \ntransmission upgrades that delay load interconnections."},{"page":16,"startToken":4985,"endToken":5508,"text":"Accelerating Integration of New Co-located Generation and Loads \nBrattle.com | 13 \nwhich do not need to be deliverable and can be limited operationally to only those intervals in \nwhich the grid is available to accommodate them.23 Energy Park customers that wish to request \nmore firm generation interconnection service can make requests for CIRs.  \nThe EPI grid injection assessment captures the intent of the Energy Park in this example to \ninject onto the grid and make wholesale sales of energy on a non-firm, as-feasible basis (i.e., \nsimilar to today’s Energy-only interconnections, but even less firm). In our Energy Park example, \nthese injections are illustrated up to 50 MW, as reflected in the EPI injections base case shown \nin Figure 2 below. 24 By allowing non-firm injections only when the grid is available, the system \noperator can take advantage of the reliability benefit of the Energy Park’s injection capability to \nthe extent the system needs it and can reliably accommodate it, without needing to undertake \ncostly transmission upgrades. \nTo illustrate the interaction of the Energy Park with the broader grid, the example assumes that \nthe Energy Park and a nearby 170 MW unaffiliated generator form the local grid area, which is \nconnected to the broader PJM grid by two 170 MW transmission lines. The two transmission \nlines and the nearby unaffiliated generator play an important role in contingency analysis. The \ntransmission lines equally split the net flows between the rest of PJM and the local grid. For \nexample, in the net injection base case shown in Figure 2, the local grid area shows a 50 MW \nnet injection from the Energy Park with the nearby unaffiliated generator offline, together \ncausing a 50 MW total outflow on the interface to the rest of the grid (25 MW over each of the \ntwo transmission lines).  \n \n23  PJM and the other U.S. RTOs lead the world in the use of the Security Constrained Economic Dispatch (SCED) \nmechanism to manage congestion in real time, ensuring all generator dispatches are consistent with reliability \nvia N-1 security given the actual operational configuration of the grid, so that dispatched injections cannot be \ninconsistent with thermal and voltage security on the grid. Therefore, PJM can limit the assessment of the \nuniquely non-firm net injections of energy parks to studies that do not have any associated deliverability, \nwithout introducing concerns about unreliable injections in operations. Such studies would be set to zero MW \nin the summer peak case (like today’s Energy-only interconnection requests), but also set at zero MW in the \nwinter peak case and the light load case (unlike Energy-only requests). In order to cover reliability needs not \nsecured by SCED, the Energy Park injection assessment should include a short circuit study, a stability study \nwhere necessary, and a local connection study for the physical interconnection point and the immediate \nelectrical vicinity. \n24  Today this would be effectuated with an Energy-only interconnection request to the interconnection queue for \n50 MW, with zero MW of requested CIRs. The control mechanism described below can be used to prevent any \ninjections above 50 MW if necessary for the purposes of generation injection studies."},{"page":17,"startToken":5508,"endToken":5786,"text":"Accelerating Integration of New Co-located Generation and Loads \nBrattle.com | 14 \nFIGURE 2: EPI INJECTION BASE CASE STUDYING NET GENERATION WITHOUT CONTINGENCIES \n \nNote: To study a net injection, the Energy Park generation is assumed to operate at maximum output. The Energy \nPark’s generation is competing with the unaffiliated generator for 170 MW of export capability from the local grid; \nbecause the RTO is assumed to operate with N-1 security, the local grid can only flow 170 MW to the rest of grid \n(not the full 340 MW rating of the two transmission lines); the Energy Park therefore cannot inject when the entire \n170 MW unaffiliated local generator clears and is dispatched in the energy market. This is consistent with the \nEnergy Park’s assumed non-firm injection service. \nFor simplicity, the illustrated Energy Park does not apply for firm CIRs, which would require the \nfull generation deliverability studies PJM undertakes for resources in its interconnection \nqueue.25 Rather, the 50 MW injections are non-firm as illustrated in the case above.  \nFor EPI reliability studies of Energy Park withdrawals, the base case example is shown in Figure \n3, showing a net withdrawal from the grid of 340 MW (despite the Energy Park’s capability to \nwithdraw zero or even net inject 50 MW with its large array of on-site generation).  \n \n25  PJM applies a suite of generation deliverability tests even to Energy-only requests, sometimes referred to as \n“Energy Resources.” E.g., “Deliverability requirements for Capacity and Energy Resources are identical except \nfor summer, single contingency conditions where the deliverability requirement is limited to the CIR MW,” in \nPJM, Generator Deliverability Test Modifications: Light Load, Summer & Winter, July 12, 2022 at p. 3."},{"page":18,"startToken":5786,"endToken":5996,"text":"Accelerating Integration of New Co-located Generation and Loads \nBrattle.com | 15 \nFIGURE 3: EPI WITHDRAWAL BASE CASE STUDYING NET LOAD WITHOUT CONTINGENCIES \n \nNote: The Energy Park generation in this case is backed down to just 160 MW in order to study a net withdrawal to \nthe Energy Park of 340 MW, reflecting the maximum possible withdrawal. For cases in which RTO operators can \ndepend on the control mechanism to reduce net flows immediately following contingencies, for instance as a \nRemedial Action Scheme (RAS), the Energy Park could withdraw up to 500 MW, with the control mechanism \nlimiting withdrawals to 170 MW within seconds (or less) of a contingency. \n \nIn this case, the Energy Park’s generation supplies the remaining 160 MW to meet the total \n500 MW of co-located load. This 340 MW modeled withdrawal from the grid could represent a \nrequest by the Energy Park customer for a requested level of grid withdrawal capability to serve \nload (e.g., occasionally, for economic reasons, despite having the ability to fully self-supply). \nThe 340 MW withdrawal limit imposed by the control mechanism effectively represents an “as \navailable” maximum non-firm withdrawal level that, for reliability reasons, cannot be exceeded \nat any time. \nTable 1 lists the assumptions underlying the stylized Energy Park interconnection."},{"page":19,"startToken":5996,"endToken":6296,"text":"Accelerating Integration of New Co-located Generation and Loads \nBrattle.com | 16 \nTABLE 1: UNDERLYING ASSUMPTIONS FOR STYLIZED INTERCONNECTION EXAMPLE \nItem \nRated Capacity \nBase Injection \nScenario \n[Figure 2] \nBase Withdrawal \nScenario \n[Figure 3] \nLocal Grid Area Transmission \nInterface to Rest of Grid \n+/- 170 for each \nline \n+50 \n(to rest of grid) \n-170 (from rest of \ngrid) \nUnaffiliated Nearby Generator \n170 \n0 \n170 \nEnergy Park Generation \n550  \n[composed of \nmany individual \nunits] \n550 \n160 \nEnergy Park Load \n-500 \n-500 \n-500 \nEnergy Park Net Power to Grid \n- \n+50 \n-340 \nControl Mechanism \n-340 to +50 \nInactive \nInactive \nCapacity Interconnection Rights \n0 \n- \n- \nFirm Withdrawal Request \n170 \n- \n- \nMax Non-firm Withdrawals \n340  \n- \n- \nMax Non-firm Injections  \n50 \n- \n- \n \nFigure 4 below shows the N-1 “contingency case” for the EPI withdrawal study, reflecting \nconditions immediately following the loss of the unaffiliated generator.26 This EPI withdrawal \nstudy case for N-1 shows no contingency overloads for this case in which the local grid area has \nlost 170 MW of supply. As shown, the joint loading over the two transmission lines interfacing \nwith the rest of the grid immediately changes from an inflow of 170 MW to an inflow of 340 \nMW. All facilities remain within limits while continuing to serve the Energy Park load, so this \ncase would not indicate the need for transmission upgrades. \n \n26  In order to avoid system-wide cascading blackouts, transmission networks are operated and planned to ensure \nthey are reliable even after one contingency (i.e., after any one transmission line or generator suddenly fails \nand trips offline, referred to as an N-1 condition) or after two sequential contingencies (referred to as N-1-1). \nThe N-1 contingency case is comparable to P1 (single contingency) in TPL-001, as well as the N-1 security that is \nmodeled in the generator deliverability tests and that is ensured in operations via SCED."},{"page":20,"startToken":6296,"endToken":6571,"text":"Accelerating Integration of New Co-located Generation and Loads \nBrattle.com | 17 \nFIGURE 4: EPI WITHDRAWAL CASE WITH N-1 CONTINGENCY AND NO UPGRADES NEEDED \n \n \nHowever, the EPI withdrawal reliability assessment is not yet complete, as PJM would also \nstudy grid conditions under second contingency, or so-called N-1-1, conditions. The N-1-1 EPI \nreliability study example is shown in Figure 5 below. \nAs the example shows, the EPI withdrawal study’s N-1-1 (second contingency) case does not \nshow any overloads either due to the “redispatch” action of the Energy Park’s control \nmechanism, which limits Energy Park withdrawals when necessary, such as following a \ncontingency. This unlikely case represents failure of one element of the system (the N-1 case) \nfollowed by redispatch, followed later by failure of a second element (creating the N-1-1 \ncase).27 As before, Figure 5 shows the unaffiliated generator has tripped offline (1st event), but \nis followed shortly by operator redispatch of the Energy Park to limit grid withdrawals to 170 \nMW (by rapidly ramping up internal generation to 330 MW), while the unaffiliated generator \nremains offline. This result depends on a rapid ramp rate from the energy park generation \n(typical of such resources, especially when configured in an array of small units) and a \nsophisticated control interaction with PJM, such as provided via its Security Constrained \nEconomic Dispatch (SCED) via the real-time energy market. As shown in Figure 5, this result \n \n27  The N-1-1 contingency case shown is comparable to P3 (multiple contingency); a similar scenario in which the \nfirst contingency is a trip of one of the local grid interface transmission lines is comparable to P6 (multiple \ncontingencies, two overlapping singles) in NERC’s TPL-001."},{"page":21,"startToken":6571,"endToken":6823,"text":"Accelerating Integration of New Co-located Generation and Loads \nBrattle.com | 18 \nshows that, when one of the two external transmission lines that connect to the local grid trip \noffline after the unaffiliated generator also trips offline, operations are still reliable, because \nonly 170 MW flows across the remaining transmission line, consistent with its rated in-service \ncapacity.  \nFIGURE 5: EPI GENERAL RELIABILITY CASE WITH N-1-1 CONTINGENCY AND NO UPGRADES NEEDED \n \n \nNote that loss of all Energy Park generator units is not shown as a contingency. This is because \nthe Energy Park has configured its on-site generation to use hundreds of individual units, such \nthat there is no single point of failure. In our experience, such a configuration is typical of \nprimary power at data center sites, which use fuel cells (such as Bloom Energy’s 325 kW \nindividual Energy Server systems) or small gas generators.  \nWe now contrast the EPI approach illustrated in the previous figures to PJM’s existing process, \nwhereby the Energy Park load is studied separately from the Energy Park generation.28 As \nexplained further in Section III.A below, PJM states that it is responsible for conducting the \ngenerator deliverability studies for the Energy Park, while the transmission owner is responsible \n \n28  This appears to be the case in PJM today for new Energy Parks; for example, Option 6 in PJM’s Answer \ndescribes new Energy Park generation as being studied in the Queue process while the same Energy Park’s new \nload would be studied in the transmission owner’s Load Integration study."},{"page":22,"startToken":6823,"endToken":7088,"text":"Accelerating Integration of New Co-located Generation and Loads \nBrattle.com | 19 \nfor studying the reliability implications of the load integration. Because of this split in \nresponsibility, and because we are not aware of documented planning case definitions for \nEnergy Parks to the contrary in either of the two processes, we assume the transmission owner \nload integration studies ignore the Energy Park generation (since the transmission owner could \nnot dependably assume that the on-site generation will be developed and be able to offset grid \nwithdrawals), while the PJM generator interconnection studies ignore the Energy Park Network \nLoad (which would not yet be in the base case). Therefore, the assumed inflows to the local grid \narea are much higher in the load integration study cases, which use the same type of base case \nand contingency case definitions as shown above (albeit without the Energy Park generation).  \nFor example, while the base load-only case can serve 500 MW of load, the N-1 load-only \ncontingency case already exceeds the transmission limits and would require network upgrades, \nas illustrated in Figure 6. This is because 500 MW would be assumed to flow into the local zone \nto serve the load after the unaffiliated generator trips offline (assuming there is no Energy Park \ngeneration nor control mechanism that could limit Energy Park withdrawals), exceeding the \n340 MW joint capacity of the two transmission lines. In contrast to the EPI approach, this study \nresult would trigger at least 170 MW of transmission upgrades, delaying interconnection of the \nEnergy Park and potentially adding significant costs that the Energy Park is designed to avoid."},{"page":23,"startToken":7088,"endToken":7327,"text":"Accelerating Integration of New Co-located Generation and Loads \nBrattle.com | 20 \nFIGURE 6: CASE SHOWING N-1 CONTINGENCY FOR THE LOAD-ONLY INERCONNECTION STUDY; \n500 MW FLOWS OVER EXTERNAL TRANSMISSION LINES, WHICH IS ABOVE THEIR RATED CAPACITY  \n \nNote: If a RAS-type control mechanism limiting post-contingency Energy Park withdrawals to 340 MW were \nconsidered in the load-only study, this load-only interconnection process would be secure at 500 MW of Energy \nPark load, as load could be curtailed automatically and immediately (from 500 MW to 340 MW). However, the \nsystem would still show reliability violations at the N-1-1 case (after one of the two transmission line trips) unless \nthe load-only study could assume that the Energy Park controller could further rapidly curtail load to only 170 MW \nduring N-1-1 conditions. \n \nThese load-only cases illustrate how the presence of the Energy Park generation in the EPI cases \nhelps avoid transmission upgrades, even when severe contingency cases are considered. In a \nsense, the load-only N-1-1 study is an unrealistic N-1-1-1 study by implicitly taking three \nelements out of service—the two grid contingencies (already very unlikely) plus all of the \nhundreds of Energy Park generator units, thus resulting in an excessively conservative planning \ncase. The proposed EPI approach is instead to follow NERC standards and take only two \nfacilities out of service in the N-1-1 planning cases. \nA summary table showing the power flows across the different assets and scenarios is provided \nin Table 2."},{"page":24,"startToken":7327,"endToken":7595,"text":"Accelerating Integration of New Co-located Generation and Loads \nBrattle.com | 21 \nTABLE 2: POWER FLOWS ACROSS THE DESCRIBED SCENARIOS \nAsset \nRated \nCapacity \n(MW) \nEPI Process \n(Net-Load) \nLoad-only \nProcess (w/o Control \nMechanism) \n Base \nCase \n(MW) \nN-1 \n(MW) \nN-1-1 \n(MW) \nBase Case \n(MW) \nN-1 \n(MW) \nHigh Voltage \nTransmission Lines \n+/- 170 MW \nfor each line \n-170 \n-340 \n-170 \n-330 \n-500 \nUnrelated Nearby \nGenerator \n170 \n170 \n0 \n0 \n170 \n0 \nOn-site Primary \nGeneration \n550  \n[composed \nof many \nindividual \nunits] \n160 \n160 \n330 \nNot \nConsidered \nNot \nConsidered \nOn-site Load \n-500 \n-500 \n-500 \n-500 \n-500 \n-500 \nEnergy Park Net \nPower to Grid \n- \n-340 \n-340 \n-170 \n-500 \n-500 \nControl mechanism \n-340 to +50 \nInactive \nInactive \n-170 \n(Active) \nNot \nConsidered \nNot \nConsidered \n \nThe stylized scenarios presented show how the proposed EPI process can unlock accelerated \ninterconnection of Energy Parks with co-located load and generation by avoiding unnecessary \nnetwork upgrades that would be the result of a load-only interconnection process. While we \nonly consider in detail the study process here for contingencies under general reliability studies, \nthe injection study assessment for the Energy Park modeled with the same EPI approach would \nsimilarly yield accelerated interconnection compared to PJM’s generator-only interconnection \nprocess. \nAvoiding unnecessary transmission upgrades provides three important benefits: new large load \ncustomers can be connected more quickly; such customers can save on the costs of connection; \nand transmission upgrade costs that would otherwise be socialized to other customers (which \nalready totals billions of dollars in PJM according to some analysis) would be avoided.29  \n \n29  David Lapp, Protest and Comments of Maryland Office of People’s Counsel, filed in FERC Docket No. ER24-843, \nFebruary 9, 2024"},{"page":25,"startToken":7595,"endToken":8029,"text":"Accelerating Integration of New Co-located Generation and Loads \nBrattle.com | 22 \nB. Experience Elsewhere Highlights the Practicality of \nEnergy Park Integration Studies \nOther Independent System Operators (ISOs)/RTOs take an integrated approach to studying \nEnergy Parks, showing that it is a practical option for consideration by PJM and other ISO/RTOs.  \nFor example, ERCOT has an integrated process for connecting co-located load and generation \nbehind a single POI, called Private Use Networks or PUNs. Historically associated with large \nindustrial facilities, ERCOT defines a PUN as “an electric network connected to the ERCOT \nTransmission Grid that contains Load that is not directly metered by ERCOT (i.e., Load that is \ntypically netted with internal generation).”30 PUNs can act as both net load and net generation. \nRecently, there has been interest in establishing PUNs from new large loads such as data \ncenters. Generators have also begun pursuing the addition of new behind-the-meter loads in \ntransmission constrained areas such as South Texas. For interconnecting PUNs to the ERCOT \ngrid, ERCOT and the interconnecting transmission owner study the PUN in an integrated \nprocess as independent load, independent generation, and a composite of both load and \ngeneration.31 With over 16,000 MW of PUN capacity in ERCOT, a quarter of which has been \nadded in the last decade, the PUN (i.e., Energy Park) interconnection process has proven to be a \npractical approach for bringing online co-located load and generation.32  \nIn addition, in the most recent planning guide revisions awaiting approval in ERCOT for large \nload interconnection, ERCOT’s Large Flexible Load Task Force proposes that new large loads \nco-located with new generation (that are not registered as PUNs) undertake a single process in \nwhich load may be studied as part of the generator interconnection study, instead of separate \nload and generator interconnection processes.33 \nIn response to ongoing interest in co-location, stakeholders in the Midcontinent Independent \nSystem Operator (MISO) and PJM have expressed support for an EPI approach that studies both \nload and generation together in order to fast-track connection of new Energy Parks.34  \n \n30  ERCOT, Nodal Protocols Section 2: Definitions and Acronyms, April 1, 2025  \n31  ERCOT, ERCOT Update to Texas House of Representatives Committee on State Affairs, March 5, 2025, p6 \n32  ERCOT, PUN Capacity Report, April 14, 2025 \n33  ERCOT, NPRR1234 and PGRR115: Overview, Key Concepts, and Impact to the Generation Interconnection \nProcess, June 12, 2024, p10 \n34  For example, in MISO, NextEra Energy Resources submitted a proposal to study co-located load and generation \ntogether to accurately identify the system upgrades required for interconnection. NextEra has proposed that \nContinued on next page"},{"page":26,"startToken":8029,"endToken":8463,"text":"Accelerating Integration of New Co-located Generation and Loads \nBrattle.com | 23 \nC. The Benefits of an EPI Approach Are Highest When \nEnergy Parks Can Dependably Transact with the \nGrid on an As-Available, Non-Firm Basis \nThe EPI approach avoids transmission upgrades by incorporating the Energy Park’s primary \ngeneration and control mechanism to meet on-site load and limit withdrawal and injection \nexchanges with the grid based on available grid capacity, including during contingencies. \nOperators can therefore take advantage of dispatchable injection capability during times that \nthe system needs the Energy Park’s surplus power and can accommodate it, and can serve \nEnergy Park load to the extent it is economically advantageous and reliable. To ensure a reliable \nsystem, planners must know that operators can depend on the Energy Park controller to \nrestrict “non-firm” purchases when the grid is not available to facilitate them. For example, \nduring times that the Energy Park described above wishes to withdraw 340 MW from the grid, \nbut grid conditions limit reliable withdrawals to only 170 MW, the Energy Park must \ndependably self-supply any load in excess of 170 MW (or else curtail the load).35 By the same \ntoken, energy injections from the Energy Park can only be effectuated when grid conditions \nallow it.   \nOperational processes and controls are necessary to ensure the ongoing ability of the Energy \nPark to reduce withdrawals (and injections) when grid capacity is not available. We do not \nexplore these in detail, but they could be achieved through the PJM energy market and SCED \ndispatch, or through a locally automated response to grid conditions. \nThe controls for PJM-dispatchable energy transactions and contingency responses would be in \nplace without necessarily making the Energy Park generation a PJM “Generation Capacity \nResource.” Rather, Energy Park generation would locally supply the load’s resource adequacy \nneed, and its control requirements would support the transmission system interactions of the \nEnergy Park (to avoid unnecessary transmission upgrades). Because the load has its resource \nadequacy needs met locally, it does not add to PJM’s resource adequacy requirement, and its \n \nMISO should factor in proposed co-located loads in the generator interconnection queue, by assigning new \nloads to specific generators, with a generator interconnection agreement conditional on the load showing up. \nOn the load side, Google, in its response to the co-location FERC Docket No. AD24-11-49000, expressed support \nfor a fast-tracked study process for co-located loads in PJM by “studying new co-located load and generation \ntogether in an effort to consolidate upgrades and reduce timelines.”, p5 \n35  The PJM Answer acknowledges the role of as-available withdrawals. See New Options 7 and 8 in Exhibit A, PJM \nAnswer."},{"page":27,"startToken":8463,"endToken":8812,"text":"Accelerating Integration of New Co-located Generation and Loads \nBrattle.com | 24 \ngeneration is not necessary to support PJM-wide resource adequacy needs nor does it need to \nparticipate in PJM’s capacity market. \n Reforms are Needed to Realize the Speed \nand Cost-Effectiveness Benefits of Energy \nPark Integration  \n _________  \nA. The Status Quo Does not Achieve the Benefits of \nEPI Studies \nUnder current PJM rules, a new generator seeking to connect to the transmission system is \nstudied in the PJM queue. These studies are coordinated with the local transmission owner. At \nthe same time, new load requesting to be integrated in PJM must be studied through a two-\nstep process that involves: (1) a transmission owner retail load integration study that identifies \nlocal upgrades required to meet load based on the transmission owner’s criteria;36 and (2) a \nPJM ‘Do No Harm’ study in which PJM evaluates if the new load and any transmission owner-\nidentified upgrades will adversely impact the reliability of the transmission system. In some \ncases, large load additions can also trigger the need for regional transmission expansions, which \nare handled through PJM’s regional transmission expansion planning (RTEP) process. \nFor co-located generation and load, PJM prescribes separate processes for load and generator \ninterconnection. For example, in PJM’s new Option 6 (offering faster interconnection for \nNetwork Load that brings its own generation), PJM describes all 4 steps (transmission owner \nload integration study, PJM ‘Do No Harm’ study, RTEP, and Generator Interconnection Study) as \nrequired for interconnection of the co-located set of facilities (i.e., the Energy Park).37 PJM does \nnote that “incentives would be explored to offer faster processing of generation that enters the \nqueue through this option [6]” including “providing options for accelerating interconnection \nstudies of new generation proposed as part of this option” and allowing that “states could \nremove a barrier to entry for investment in large load infrastructure by assuming cost \nresponsibility for transmission upgrades in the Regional Transmission Expansion Plan (“RTEP”) \n \n36  These local system needs are typically in the form of Supplemental Projects; PJM Answer \n37  See New Option 6 in Exhibit A, PJM Answer"},{"page":28,"startToken":8812,"endToken":9261,"text":"Accelerating Integration of New Co-located Generation and Loads \nBrattle.com | 25 \npursuant to the State Agreement Approach.”38 While PJM offers no specifics, the EPI approach \nwe propose achieves the goal of faster and lower-cost Energy Park integration by recognizing \nthe benefits of co-located Energy Park loads and generation that avoids the more expansive \nnetwork upgrades triggered by studies that independently consider the associated loads and \ngeneration, without the need to spur incentives by transferring costs to other customers. \nAn integrated EPI process is also currently not available through the studies a transmission \nowner must undertake to integrate new loads. As PJM assigns primary responsibility for new \nload integration to the transmission owners while it is responsible for studying new generators, \nit is not clear that a transmission owner could use an EPI approach that involves studying the \nco-located generation, given the risk that the latter might fail to complete the interconnection \nqueue process. If a transmission owner were to undertake an EPI study, it would lack a defined \nor documented framework given the current division of responsibilities across interconnecting \nload and generation. \nThe generator studies used in the PJM queue (referred to as “deliverability” studies, even for \nEnergy-only interconnection requests, also referred to as Energy Resources) do not recognize \nthe controllable, non-firm nature of potential injections from Energy Park generation designed \nto self-supply of the Energy Park’s load. Even Energy-only generator interconnection requests \nare studied by PJM with stringent reliability criteria, including for light load and winter cases. \nThis may make sense for the injections of today’s Energy-only interconnections (for example \nwind farms), which are primarily designed to inject energy to the grid, and are offered less-firm \nEnergy-only service in recognition of their lower resource adequacy value, rather than the \nlower business priority associated with their injections. In contrast, in the case of an Energy \nPark, co-located generation is designed primarily for on-site supply, and would inject energy to \nthe grid only to the extent grid capacity is available or doing so is beneficial to the system. \nTherefore, Energy Park net injection assessments should reflect the controllable, as-available, \nnon-firm nature of injections from Energy Parks.  \nFor that reason, and because injections would likely be limited (and perhaps infrequent), PJM \ncan limit the assessment injections to those studies that do not have any associated \ndeliverability. Because the Energy Park controller only exchanges power with the grid when it is \nreliable to do so (for example, by following SCED dispatch), Energy Park injections will not \nintroduce concerns about unreliable operations. Therefore, the EPI injection studies would be \nset to zero MW in the summer peak case (in the same way as Energy-only MW today) but \n \n38  PJM Answer, p. 17"},{"page":29,"startToken":9261,"endToken":9733,"text":"Accelerating Integration of New Co-located Generation and Loads \nBrattle.com | 26 \nwould also set output in the winter peak case and the light load case to 0 MW. It follows that, in \norder to cover reliability needs not secured by the Energy Park controller, the Energy Park \ninjection assessment would include a short circuit study, a stability study where necessary, and \na local connection study for the physical interconnection point and the immediate electrical \nvicinity.39  \nAn Energy Park that is controlled only to inject into and withdraw from the grid based on \navailable real-time grid capacity (i.e., with zero firm injection and withdrawal MW) should be \npresumed in the first instance to have de minimis impact on the grid in most cases. Even with \nsome firm withdrawal MW (as in the case of the above example), an assessment of the impact \nof zero firm injection MWs would be expected to have no impact. In that respect, the \nassessment process is analogous to PJM’s recently-revised CIR Replacement process or the SIS \nprocess, both of which offer expedited interconnection processing for new resources as long as \nscreening studies confirm that there are no material impacts on the grid.40 The analogy holds \nbecause both the CIR replacement process and the SIS process contemplate a zero MW net \nincrease in firm injections. SIS allows generators to quickly add new capacity behind existing \ninterconnection points, and CIR Replacement to change the fuel type at or near existing \ninterconnection points, provided total injections remain limited to the level specified in the \nexisting interconnection agreement. This new capacity is fast-tracked through the \ninterconnection queue, using a screening assessment to ensure that accommodating the \nprojects does not require network upgrades. Such an expedited approach could be reasonably \nadapted to Energy Parks that only seek to transact with the grid on a non-firm basis based on \navailable grid capacity. \nThe Energy Park control mechanism, which may include physical protection mechanisms to \nlimit maximum flows into or out of the Energy Park, plays an important role in limiting \nunnecessary transmission upgrades to accelerate interconnection. To achieve these benefits, \ndocumentation of technical standards for the control mechanism and physical protection \nsystems is needed so that developers can reasonably anticipate and plan for necessary \nhardware, and transmission owners can process new connection requests without having to \nreinvent potentially detailed technical requirements to ensure net withdrawals or injections \nfrom the Energy Park remain within the specified range. For example, PJM has acknowledged \nand allowed the use of such physical protection mechanisms in approving Talen’s amended \n \n39  We note that a co-located generator would have the option to seek a higher level of injection “firmness” by \nrequesting Energy-only or CIR status, leading to more robust interconnection studies \n40  PJM Inside Lines, FERC Accepts Two PJM Proposals To Expedite Supply Additions, February 12, 2025"},{"page":30,"startToken":9733,"endToken":10174,"text":"Accelerating Integration of New Co-located Generation and Loads \nBrattle.com | 27 \nInterconnection Service Agreement for Susquehanna power plant, but has not established \nspecific requirements.  \nAs discussed above, operational processes and controls are necessary to ensure the ongoing \nability of the Energy Park to reduce withdrawals (and injections) when grid capacity is not \navailable. Such tariff and protocol requirements do not exist today, and would need to be \nadded in order to minimize unnecessary transmission upgrades. With dispatchable onsite self-\nsupply resources—such as fuel cells, gas turbines, or battery storage—it is possible to make the \nEnergy Park’s net transactions with the grid dispatchable (up or down) by PJM using the same \nenergy market offer, clearing, and dispatch system already used for other generators. This can \nbe accomplished by allowing Energy Park operators to bid their as-available injections and \nwithdrawals into the PJM market with the requirement to follow PJM resulting dispatches. \nTransmission planning benefits (i.e., avoiding otherwise necessary transmission upgrades) are \nmaximized through such dispatch because the system operator can rely on the Energy Park to \nlimit injections or withdrawals to the available grid capacity.41  \nFinally, while the focus of this report is on Energy Parks that are able to both withdraw from \nand inject into the grid, non-injecting Energy Parks that are able to control their net \nwithdrawals offer similar benefits to the grid. We thus propose that load integration studies of \nsuch non-injecting Energy Parks should be conducted based on the same EPI framework \n(without any screening or studies for net injections).42 \nB. Reforms Can Achieve Energy Park Integration \nBenefits  \nGiven the gaps identified in Section III.A above, the following reforms to the PJM and \ntransmission owner interconnection processes would be necessary to achieve the speed and \ncost benefits of the proposed EPI process: \n \n41  Transmission benefits could be enhanced further if the outage of large individual Energy Park generators (if \nany) is coordinated with PJM and transmission owner operations. While generators who qualify as Capacity \nResources must coordinate their outages with PJM, there are no such provisions for energy-only resources or \nEnergy Parks. \n42  Energy Parks with zero net injections can be incorporated into real time operations (SCED) in the same way as \ninjecting Energy Parks. Load is considered in demand response and that may be the default for Energy Parks \nthat lacks net injection capability, but demand response is not currently integrated into SCED. Incorporating the \ndispatchability of Energy Parks even if they do not provide net injections can maximize transmission benefits. \nERCOT’s Controllable Load Resources (CLR) framework provides a precedent for how load resources can be \ndispatched on a 5-minute basis."},{"page":31,"startToken":10174,"endToken":10399,"text":"Accelerating Integration of New Co-located Generation and Loads \nBrattle.com | 28 \n• PJM and transmission owners: develop and document EPI protocols for Energy Parks, as an \nalternative to the currently applicable separate study processes, including the PJM \ngenerator interconnection study process, the PJM ‘Do No Harm’ study, transmission owner \nload integration study, and (in limited cases) the PJM regional transmission expansion \nprocess (RTEP). The EPI protocols would need to include provisions for coordination \nbetween separate study processes (unless the relevant parties integrate them into a single \nprocess). \n• PJM: allow for non-firm grid injection requests based on “as available” grid capacity (i.e., \nless firm than current Energy-only interconnections). Study these non-firm Energy Park \ninjections through an expedited screening process similar to that of PJM’s new Surplus \nInterconnection Service (SIS) or Capacity Interconnection Rights (CIR) replacement \nprocesses, given that non-firm net injections by the Energy Park can be controlled \nautomatically so they will not cause transmission impacts beyond the designated levels. \n• PJM and/or transmission owners: Document technical standards for the Energy Park \ncontrols and protection mechanisms used to limit physical withdrawals and injections \nbetween the Energy Park and the grid to the pre-specified amounts. Develop provisions to \nensure that PJM and transmission operators can rely on the Energy Park to control net \ninjections or withdrawals when grid capacity is limited (during contingencies) in real time \noperations."},{"page":32,"startToken":10399,"endToken":10798,"text":"Accelerating Integration of New Co-located Generation and Loads \nBrattle.com | 29 \n Energy Park Integration Reform Could \nAlleviate Resource Adequacy Strain  \n _________  \nPJM is experiencing unprecedented resource adequacy challenges in large part due to rapid \nload growth, largely from new data centers and other large loads requesting to be integrated to \nthe grid.43 PJM’s 2025 load forecast report estimates winter peak load to grow at an average of \n3.8% per year over the next 10-year period.44 The consumer impact of high capacity prices \ndriven in part by load growth has been a subject of particular concern.45  \nLarge load customers are motivated to accelerate the timelines to integrate their new facilities, \ngenerally prioritizing speed over reducing the cost of their power supply, given the high \nprofitability and robust demand for these services.46 \nThe EPI process proposed in this report is not meant to apply to Energy Parks that are planned \nto include only backup generation (such as diesel generators) that would operate only in cases \nwhere the grid connection is lost. Diesel backup generation, as discussed above, is limited by \nthe number of hours they can operate due to air pollution permitting requirements.47 Instead, \nthe proposed EPI reforms are meant for Energy Parks in which the embedded new generation is \ndesigned to be able to serve the embedded new load during normal operations.  \nAn accelerated EPI process would provide an appealing mechanism to incentivize developers of \nnew large loads (such as data centers) to serve their loads with new co-located primary \ngeneration resources in return for faster online times and reduced grid interconnection costs. \nTo achieve this, these customers could enhance their on-site generation plans from back-up \nonly (typical today) to inclusion of primary generation technologies capable of self-supplying \n \n43  PJM Inside Lines, 2024 in Review: Maintaining an Adequate Generation Supply, January 9, 2025; NERC, 2024 \nLong-Term Reliability Assessment, December 2024; American Public Power Association, PJM CEO Voices \nConcerns About Resource Adequacy, October 23, 2024. \n44  PJM, Long Term Load Forecast Report, January 24, 2025. \n45  Governors of Illinois, Maryland, Delaware, New Jersey, and Pennsylvania, Letter to the PJM Board, dated \nOctober 25, 2024 \n46  Center for Strategic & International Studies, The Electricity Supply Bottleneck on U.S. AI Dominance, March \n2025. \n47  See for e.g. Northeast States for Coordinated Air Use Management, Air Quality, Electricity, and Back-up \nStationary Diesel Engines in the Northeast, January 2014."},{"page":33,"startToken":10798,"endToken":10998,"text":"Accelerating Integration of New Co-located Generation and Loads \nBrattle.com | 30 \ntheir load on an ongoing basis in normal operations (e.g., through a combination of gas \nturbines, fuel cells, batteries, and/or renewable resources).  \nNew off-site capacity therefore does not have to be planned to meet load at an Energy Park to \nthe extent that co-located generation offsets capacity for co-located load. Given the \npredominance of large load customers in the load forecast, and the breadth of those customers \nthat could benefit from the EPI study approach, this could have an outsized effect on mitigating \nPJM’s current resource adequacy challenge. \nThis EPI process would also allow new loads to be added at sites where new generation could \nbe developed from a permitting perspective, but is not possible in a timely or cost-effective \nfashion due to grid constraints.  \nBy incentivizing new customers to largely or fully self-supply their own load, grid expansion and \nresource adequacy challenges are reduced. The consumer bill impacts of large load growth \nwould likewise be mitigated. New generation resources that are brought online through an EPI \nprocess could then also have the option to sell surplus generation to PJM, which would further \nreduce PJM’s supply challenges."},{"page":34,"startToken":10998,"endToken":11347,"text":"Accelerating Integration of New Co-located Generation and Loads \nBrattle.com | 31 \n Conclusion \n _________  \nWe have described an EPI process that can accelerate the integration of Energy Parks consisting \nof co-located load, primary generation, and a control mechanism that regulates grid \nwithdrawals and injections. We illustrate with stylized N-1 and N-1-1 contingency scenarios \nhow EPI studies allow grid planners to leverage an Energy Park’s generation and control \nmechanism that limit net withdrawals to those serviceable by the grid with minimal upgrades. \nWe identify the reforms necessary to enable new large loads and co-located generation to \ninterconnect quickly under the EPI framework. Namely: establishing EPI protocols; clarifying the \nrole of the grid operator and transmission owners; allowing for an expedited study process and \nassessment protocol that reflects the lower expected grid impact of Energy Parks; and \nintegrating the dispatchability of the Energy Park’s assets in real-time operational frameworks \n(SCED or otherwise) to maximize their benefits for grid reliability and economic dispatch of \navailable resources. An accelerated interconnection process under the EPI framework offers the \nopportunity to support federal and state priorities on data centers, manufacturing, and artificial \nintelligence infrastructure and addresses critical challenges with resource adequacy and grid \nupgrades. In particular, the benefits of the proposed EPI framework are as follows: \nACCELERATES INTERCONNECTION OF NEW LOAD AND NEW GENERATION  \nEliminating network upgrades through controllable Energy Parks can immediately reduce large \nload interconnection lead times by eliminating the need to pursue lengthy new transmission \nbuilds that need to be brought online prior to energizing the new load. Under the currently \navailable processes, a large new load might wait for years until transmission expansion \n(planning through a local or regional transmission planning process) is online. Similarly, a new \ngenerator meant to serve the new load would be delayed through the existing multi-year \ngeneration interconnection queue process. By co-locating new load with new generation and \nacknowledging their controllable grid interaction (self-balancing with maximum withdrawal or \ninjections) in the study process, time consuming and expensive network upgrades are avoided, \nexpediting the process for bringing these resources online and supporting federal and state \npriorities at lower cost."},{"page":35,"startToken":11347,"endToken":11588,"text":"Accelerating Integration of New Co-located Generation and Loads \nBrattle.com | 32 \nSUPPORTS RESOURCE ADEQUACY AND ENSURES MORE EFFICIENT USE OF THE \nEXISTING NETWORK \nBy offering expedited integration of co-located new loads and new generation through the EPI \nframework, grid planners incentivize new loads to bring their own generation. This has multiple \nbenefits. First, the dispatchable new Energy Park generation serves the resource adequacy \nneeds of the Energy Park load, mitigating PJM’s resource adequacy challenges. This can be \nenhanced further for Energy Parks with excess supply that can inject onto the grid during \nsystem peaks or emergencies in coordination with the grid operator, potentially serving system \nload during scarcity events. Second, the EPI framework utilizes existing grid capacity more \nefficiently because the Energy Park’s generation can be controlled to supply the co-located load \nwhenever doing so is necessary to limit the Energy Park’s withdrawals or injections to the \navailable grid capacity. Thus, the need for network transmission upgrades to serve grid \nwithdrawals by new load or non-firm injections by new generation is greatly reduced or \neliminated.  \nREDUCES CONSUMER BILL IMPACTS FROM LARGE LOAD GROWTH \nBy avoiding unnecessary transmission upgrades to accommodate new large loads, the EPI \nprocess avoids any costs that would otherwise be allocated broadly to all customers. By \nfacilitating and accelerating a “bring-your-own capacity” approach, the proposal mitigates the \nresource adequacy impact of load growth, easing price increases in the capacity market and the \ncommensurate bill impacts for all consumers."}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":83,"startToken":0,"endToken":159},{"p":3,"at":83,"title":"TABLE OF CONTENTS","method":"printed heading","endPage":3,"endAt":519,"startToken":159,"endToken":184},{"p":3,"at":519,"title":"A. EPI-Based Contingency Studies Reduce Transmission Impacts and Interconnection","method":"printed heading","endPage":3,"endAt":833,"startToken":184,"endToken":207},{"p":3,"at":833,"title":"C. The Benefits of an EPI Approach Are Highest When Energy Parks Can Dependably","method":"printed heading","endPage":4,"endAt":82,"startToken":207,"endToken":291},{"p":4,"at":82,"title":"Executive Summary","method":"printed heading","endPage":10,"endAt":82,"startToken":291,"endToken":2466},{"p":10,"at":82,"title":"Introduction","method":"printed heading","endPage":15,"endAt":1120,"startToken":2466,"endToken":4682},{"p":15,"at":1120,"title":"A. EPI-Based Contingency Studies Reduce","method":"printed heading","endPage":25,"endAt":83,"startToken":4682,"endToken":7606},{"p":25,"at":83,"title":"B. Experience Elsewhere Highlights the Practicality of","method":"printed heading","endPage":26,"endAt":83,"startToken":7606,"endToken":8040},{"p":26,"at":83,"title":"C. The Benefits of an EPI Approach Are Highest When","method":"printed heading","endPage":27,"endAt":332,"startToken":8040,"endToken":8508},{"p":27,"at":332,"title":"A. The Status Quo Does not Achieve the Benefits of","method":"printed heading","endPage":30,"endAt":1716,"startToken":8508,"endToken":9991},{"p":30,"at":1716,"title":"B. Reforms Can Achieve Energy Park Integration","method":"printed heading","endPage":34,"endAt":83,"startToken":9991,"endToken":11009},{"p":34,"at":83,"title":"Conclusion","method":"printed heading","endPage":35,"endAt":1667,"startToken":11009,"endToken":11588}]}