{"document":{"slug":"rec-20250423-5227","title":"Comments of Bloom Energy Corporation","issued":"2025-04-23","accession":"20250423-5227","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Bloom Energy Corporation","kind":"comments","file":"sources/filings/text/20250423-5227_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250423-5227","tier":"record","sha256":"f5e9134e095b0a847cad2bffc815f5f092806acf843f172fddd933f5888d2aae","pages":15,"tokens":4224,"emptyPages":[],"textThemes":["colo","study","flex","adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":271,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C., et al. \n \nLarge Loads Co-Located at Generating Facilities  \n \nConstellation Energy Generation, LLC \nv. \nPJM Interconnection, L.L.C. \n) \n \n) \n) \n \n) \n) \n) \n \nDocket Nos. EL25-49-000 \n \nAD24-11-000 \n \n \nEL25-20-000 \n(Consolidated) \n \nCOMMENTS OF BLOOM ENERGY CORPORATION \n \n \nPursuant to Rule 213 of the Federal Energy Regulatory Commission’s (“FERC” or \n“Commission”) Rules of Practice and Procedure,1 Bloom Energy Corporation (“Bloom”) \nsubmits comments in response to the Commission’s February 20, 2025 order.2  In addition to \nthese comments, attached hereto is a report by the Brattle Group (“Brattle”) entitled, \n“Accelerating Integration of New Co-located Generation and Loads” (“Brattle Report”).    \nBloom’s comments herein focus on two approaches addressed in the PJM \nInterconnection, L.L.C. (“PJM”) answer:3 (i) PJM’s existing Behind the Meter Generation rules \n(labeled Option 3), and (ii) PJM’s proposal for co-located load that brings its own generation \n(labeled New Option 6).  Bloom appreciates PJM’s desire to expand options available to \ninterconnect large load co-located with generation, but as explained below, finds that PJM has \nunnecessarily narrowed their applicability and created hurdles to their implementation.  As \nOption 3 and New Option 6 are the only options included in the PJM Answer that apply to co-\nlocation with new generation, as opposed to existing generation, they are insufficient.   \n \n1  \n18 C.F.R. § 385.213. \n2  \nPJM Interconnection, L.L.C., et al., 190 FERC ¶ 61,115 (Feb. 20, 2025) (“Order”).  Bloom submitted a \ndoc-less motion to intervene in Docket No. EL25-49-000 on March 10, 2025.   \n3  \nAnswer of PJM Interconnection, L.L.C., Docket Nos. EL25-49-000, et al. (Mar. 24, 2025) (“PJM \nAnswer”)."},{"page":2,"startToken":271,"endToken":605,"text":"2 \n \nGiven the identified national security goal to advance artificial intelligence (“AI”), there \nis a need to accelerate and coordinate the interconnection of data centers and co-located supply. \nThe options proposed by PJM do not adequately meet this challenge.  The Brattle Report \nassesses the concept of interconnecting new generation and co-located load as a composite \nfacility called an “Energy Park,” which shares some traits with the approach PJM calls New \nOption 6.  An Energy Park as analyzed by Brattle refers to: (i) load designated as Network Load, \n(ii) co-located generation that provides primary power to load,4 and (iii) controls and protection \nmechanisms used to limit physical withdrawals and injections between the Energy Park and the \ngrid to pre-specified amounts.  Brattle finds that an integrated interconnection approach in \nassessing new load and new generation can significantly reduce the need for transmission \nupgrades, potentially avoiding billions in transmission expansion costs that have in the recent \npast been allocated to other consumers,5 while also significantly accelerating the interconnection \ntimeline.  This approach would in turn creates an incentive for data centers to bring along \nprimary generation resources that supply their needs on-site, ease resource adequacy concerns \nthat have been highlighted by PJM, NERC and others.  \nBloom urges the Commission to develop and provide detailed guidance to PJM, as well \nas clear compliance deadlines for future filings to implement co-location tariff rules, including \nthe reforms proposed in the Brattle Report.    \n \n \n \n4  \nUnder this approach, there is no limitation on ownership of co-located generation.  It may be owned by an \nindependent generator, the co-located load itself, or a local utility.  Bloom concurs with PJM and others that \ngeneration ownership may in these scenarios be driven by state law.  Where, for example, state law grants a \nfranchised utility the exclusive right to make power sales to retail customers, the direct sale by an independent \ngenerator to load may be prohibited.  \n5  \nSee, e.g., Protest and Comments of Maryland Office of People’s Counsel, Docket No. ER24-843-000 (Feb. \n9, 2024)."},{"page":3,"startToken":605,"endToken":938,"text":"3 \n \nI. \nINTRODUCTION \nThe Commission has increasingly recognized the national security implications of AI \ndata centers, particularly regarding their large energy demands and their role in supporting \ntechnologies.  Likewise, both the current and prior administration have explicitly linked the \nadvancement of AI infrastructure (including data centers) to national security.  For example, on \nJanuary 23, 2025, President Trump signed an executive order entitled “Removing Barriers to \nAmerican Leadership in Artificial Intelligence,” requiring within 180 days of the order an action \nplan to enhance AI in order to promote economic competitiveness and national security.6  \nAccelerating the interconnection of data centers co-located with generation is an action that the \nCommission can take in support of this national security goal. \nBloom is a manufacturer of solid oxide fuel cell technology that utilizes an \nelectrochemical process to power non-combustion distributed energy resources that can be \nlocated either behind the meter or in front of the meter.  Bloom’s solid oxide fuel cell systems are \ndesigned in a modular fault-tolerant format that provides critical reliability, and can be designed \nto provide three nines (99.9%) and five nines (99.999%) availability.  Bloom has installed over \n1.4 GW of its systems, of which over 300 MW power data centers.  The fuel cell systems are \nbaseload, with the ability to quickly ramp up and down to follow load fluctuations, and have \nbeen recognized as an excellent option for data centers in PJM and elsewhere.7  While Bloom \ncan install hundreds of megawatts at a site in as little as 6 to 9 months, where grid \ninterconnections are needed and interconnection queues are long, meeting a data center’s request \n \n6  \nSee https://www.whitehouse.gov/presidential-actions/2025/01/removing-barriers-to-american-leadership-\nin-artificial-intelligence/.  \n7  \nIn 2024, AEP entered into an agreement with Bloom to purchase and co-locate up to 1,000 MW of Bloom’s \nsystems at data centers.  See https://www.utilitydive.com/news/aep-bloom-energy-fuel-cell-data-center/733150/ \n(“AEP, Bloom Energy 1-GW fuel cell deal to power data centers would set new record”) (Nov. 18, 2024)."},{"page":4,"startToken":938,"endToken":1298,"text":"4 \n \nfor timely power is not possible.  We urge the Commission to provide guidance to PJM in the \ndevelopment of new options to co-locate large loads and generation.  \nAs highlighted in the eight options presented in the PJM Answer, co-located \nconfigurations generally fall into one of two general buckets:  \n• Network Load, Served by a Co-located Generator.  Here, co-located load and generation \nare configured such that (1) load is designated as Network Load and may take power \nfrom the transmission grid to meet a portion of its demand, and (2) the generator makes \nphysical sales directly to the co-located load and also may make PJM market sales \n(though the generator could also be dedicated solely to serve the co-located load).  \nCurrent tariff rules require the co-located generator to enter the interconnection queue \nand be studied for “deliverability” to all PJM load either if the generator intends to \nengage in wholesale sales or will utilize the transmission grid to deliver energy to load.   \n \n• Behind-the-Meter, Isolated Load Served Co-located with an Existing Generator.  This is \nthe configuration being pursued by a number of nuclear plant owners located in the PJM \nregion and elsewhere, as well as the owner of a natural gas facility located in Virginia.  In \nthis configuration, an existing interconnected generator co-locates new load and seeks to \n“isolate” the new load behind the co-located generator’s point of interconnection (“POI”).  \nWhether the load must be designated as Network Load is a matter being litigated in this \nproceeding, but which Bloom does not address. \n \nBoth Bloom’s comments and the Brattle Report’s analysis focus on improvements to the \ninterconnection rules associated with the first configuration.  In particular, how to expeditiously \ninterconnect generation and co-located load (both new) as a composite facility.  The Brattle \nReport employs the term “Energy Park” to describe this configuration.  While the term Energy \nPark has previously referred to a collection of different supply technologies, focusing on variable \nenergy resources,8 as used in the Brattle Report an Energy Park consists of three functional \ncomponents: (i) generation that serves as primary power for on-site supply and is subject to PJM \n \n8  \nSee, e.g., https://energyinnovation.org/wp-content/uploads/Energy-Parks-Report.pdf."},{"page":5,"startToken":1298,"endToken":1647,"text":"5 \n \ninterconnection,9 (ii) co-located load, and (iii) a physical control or protection mechanism to \npotentially limit maximum flows in and out of the Energy Park at the POI.   \nBy planning to co-locate new primary generation that can run at any time, the co-located \nload can supply all or part of its energy and resource adequacy on-site, thereby minimizing the \nimpact on markets and transmission and supporting the interconnected grid.  And by reflecting \nthe controllable nature of Energy Park withdrawals and injections to the grid through one or \nmore control and protection mechanism, properly structured studies that reflect the integrated \nnature of these resources when performed by PJM and transmission owners are less likely to \nidentify expensive and time-consuming transmission upgrades, thus facilitating the \ninterconnection of new loads and much needed new supply.  Any net injections by generation or \nnet withdrawals by load at an Energy Park would depend on what the grid is able to \naccommodate in real-time operations.  Thus, withdrawals by load would be based on available \ngrid capacity, and injections (market sales) by the co-located generator would be on a non-firm \nbasis.  Brattle demonstrates that all of this can be accomplished while meeting PJM- and NERC-\nmandated N-1 and N-1-1 requirements.   \nAdoption of Brattle’s proposed integrated interconnection process for Energy Parks will \nrequire a number of reforms in the studies, protocols and procedures of PJM and transmission \nowners, which are necessary to achieve the speed and cost benefits of the proposal, including: \n• PJM and transmission owners: develop and document protocols for integrated Energy \nParks interconnection studies, as an alternative to the currently applicable separate study \nprocesses, including the PJM generator interconnection study process, the PJM ‘Do No \nHarm’ study, transmission owner load integration study, and in limited cases the PJM \nregional transmission expansion process (RTEP).  Protocols would need to include \nprovisions for coordination between separate study processes. \n \n \n9  \nNote that PJM interconnection studies are not required for all behind-the-meter generator interconnections.  \nSee infra at note 11.  Bloom’s comments herein do not seek to expand the scope of PJM’s jurisdiction to study the \ninterconnection of new generation."},{"page":6,"startToken":1647,"endToken":1983,"text":"6 \n \n• PJM and/or transmission owners: Document technical standards for the Energy Park \ncontrols and protection mechanisms used to limit physical withdrawals and injections \nbetween the Energy Park and the grid to the pre-specified amounts.  Develop provisions \nto ensure that PJM and transmission operators can rely on the Energy Park to control net \ninjections or withdrawals when grid capacity is limited (during contingencies) in real \ntime operations. \n \n• PJM: allow for and study non-firm grid injection requests based on “as available” grid \ncapacity (i.e., less firm than current Energy-only interconnections.  Study these non-firm \nEnergy Park injections through an expedited screening process similar to that of PJM’s \nnew Surplus Interconnection Service (SIS) or Capacity Interconnection Rights (CIR) \nreplacement processes, given that non-firm net injections by the Energy Park can be \ncontrolled automatically so they will not cause transmission impacts beyond the \ndesignated levels. \n \nCollectively, the reforms will lead to an accelerated interconnection process and will \nincentivize new data centers and other large load customers to bring their own generation, thus \nhelping to meet the resource adequacy needs of the region, while also reducing consumer billing \nimpacts from large load growth. \nII. \nComments \nBloom’s comments in response to the PJM Answer focus on PJM’s Option 3 (existing \nBehind the Meter Generation rules) and New Option 6 (Co-located load that elects to be \nNetwork Load and bring own generation BYOG).  As to Option 3, PJM makes clear its lack of \nsupport for large loads to use of the Behind the Meter Generation tariff rules and omits that this \noption has been employed by both large and small loads over the past two decades.  Regarding \nNew Option 6, the PJM matrix provides that all generation associated with New Option 6 must \nbe a capacity resource, which as a result calls into question PJM’s statement that the option is \navailable both to physical and financial arrangements by co-located load that brings its own \ngeneration.  Finally, we briefly describe the attached Brattle Report on “Accelerating Integration \nof New Co-located Generation and Loads.”"},{"page":7,"startToken":1983,"endToken":2450,"text":"7 \n \nA. \nOption 3: PJM Should Clarify its Statements that Existing Behind the Meter \nGeneration Rules were Not Intended for Use by Large Load (Question a.iv) \n \nIn describing the existing Behind the Meter Generation rules,10 PJM repeatedly states that \nits use was never intended for large loads: “While this option is already available under the \nTariff, it was conceived for, and has been implemented for, substantially smaller loads (like large \nwarehouse with solar panels) and not on the scale of large data centers.”11  Data centers can have \na range of customer loads—from just a few megawatts, to tens of megawatts, to hundreds of \nmegawatts.  PJM, however, neither defines what it deems to be a “large load” nor provides the \nCommission with any sense of the customers being served by Behind the Meter Generation \ntoday, beyond large warehouses and solar panels.   \nFor years, cogeneration facilities have served behind the meter customers.  For example, \nthe Linden Cogeneration Plant (Linden 6) sells to a behind the meter customer, the Tosco \nrefinery, up to 160 MW.12  Likewise, Delaware City Refining Company owns a 324 MW \ncombined cycle cogeneration facility, which has been described as “an integral part of the \nDelaware City refinery and refining operations.”13  Although the exact amount of customer load \nserved from the co-located generation facility is unknown, it can readily be distinguished from \n \n10  \nPursuant to the tariff’s definition of Behind the Meter Generation, there are three criteria that a generator \nmust meet: 1) it delivers generation to load without using the transmission or distribution grids; 2) it is not a capacity \nresource; and 3) it does not engage in wholesale energy sales.  Per PJM Manual 14G, Generation Interconnection \nRequests Sec. 1.6 Behind the Meter Generation, “generating resources operating “behind the meter,” in isolation \nfrom the PJM bulk power transmission system and which do not intend to participate in the PJM wholesale energy \nmarket, need only coordinate planning, construction and/or operation with the host Transmission Owner.” Such \nfacilities do not need to complete the interconnection process if the facility does not intend to engage in wholesale \nsales or utilize the transmission grid to deliver energy to load. \n11  \nPJM Answer at 13; see also id. at 11 (Description: “Large load behind generation was not intended”); id. at \n12 (PJM Preference: “Not for Large Loads”); id. at 34 (Behind the Meter Generation “paradigm does not fit co-\nlocation arrangements particularly well because it was not designed with large load co-location in mind”). \n12  \nSee https://www.pjm.com/pjmfiles/pub/planning/project-queues/isa/y1_026_isa.pdf.   \n13  \nSee Delaware City Refining Company LLC, Amended Application for Market-Based Rate Authorization, \nDocket No. ER10-1093, at p. 3 (May 25, 2010).  The refinery is owned by an affiliate of Delaware City Refining \nCompany."},{"page":8,"startToken":2450,"endToken":2808,"text":"8 \n \nsmaller loads like a large warehouse and solar panels.  In addition, the Commission’s recent \nconsent agreement with Stronghold Digital Mining implies its 85 MW generator serves its \nvertically integrated Bitcoin mining operation behind the meter, given the significant percentage \nof hours Stronghold failed to offer in the market.14  And, there are numerous other examples of \ncogeneration that is co-located and serving load behind a single meter.  PJM ought not write off \nthis import existing means to interconnect both large and small load. \nPerhaps underlying the assertion that Behind the Meter Generation rules were never \nintended for larger loads is PJM’s conclusion that it is not clear that the netting of loads served \nby Behind the Meter Generation should apply to co-located data center load.15  PJM proffers that \n“very large loads like data centers” (another undefined term) perhaps should be treated \ndifferently based on cost causation principles,16 yet provides nothing more.  Bloom urges the \nCommission to take no action that would undermine or call into question the existing Behind the \nMeter Generation rules based on the limited facts set forth in the PJM Answer. \nB. \nOption 6: PJM’s bring your own generation with incentive for faster \ninterconnection when the load is Network Load is too narrow (Question d.vii) \n \nBloom appreciates PJM expanding its ideas on co-located resources by recognizing that \nfaster interconnections ought to be both possible and practical.17  With regard to New Option 6, \nwhich PJM describes as a “Bring Your Own Generation” approach for interconnecting new co-\nlocated generation and load more quickly, PJM notes that: “[i]ncentives would be explored to \noffer faster processing of generation that enters the queue through this option [6]” including \n \n14  \nStronghold Digital Mining Inc., et al., 190 FERC ¶ 61,059 (2025) (see id. at 8 (failing to offer in the hour-\nahead market 67% of the time and the real-time market 69% of the real-time hours, implying that over half of the \nplant’s available energy during the relevant period was used for mining rather than being sold to the grid)). \n15  \nPJM Answer at 35. \n16  \nId. at 36-37. \n17  \nSee id. at 17."},{"page":9,"startToken":2808,"endToken":3110,"text":"9 \n \n“providing options for accelerating interconnection studies of new generation proposed as part of \nthis option.”18  Nevertheless, PJM offers no specifics.   \nPJM’s desire to accelerate interconnection studies for new generation brought on by new \nlarge load is in conflict with a requirement in New Option 6 that the co-located generator be a \ncapacity resource.19  As a capacity resource, a generator must have firm Capacity Interconnection \nRights.  But acquiring Capacity Interconnection Rights should be an option and not a mandate.  \nAs discussed further below and in the Brattle Report, where generation is contractually meeting \nthe load requirements of co-located load and only seeking to inject energy—that is, make market \nsales—on an as-available, non-firm basis, PJM ought not require a generator to be a capacity \nresource.  If co-located generation must have Capacity Interconnection Rights, PJM’s \n“deliverability” interconnection study process tests the network’s ability to deliver the full output \nof the new generation to all PJM load, thus ignoring the intent of the generation to supply the co-\nlocated load resource on-site at the same grid connection point.  Such overbroad studies, in turn, \nlikely will lead to overstated transmission upgrade requirements and long interconnection queue \nprocesses.20   \nAdditionally, the requirement to have Capacity Interconnection Rights seems to \nundermine PJM’s conclusion under New Option 6 that a physical co-location or financial \narrangement can be utilized.21  A financial arrangement is in essence a contract for differences \nassociated with the co-located generator’s market sales of energy and capacity.  PJM’s capacity \nresource mandate appears to undermine the physical co-location option.  Under the PJM tariff \n \n18  \nId. \n19  \nSee Id., Appendix A, New Option 6 (identifying the generator as a capacity resource and a source of \nrevenues being capacity “based on full CIRs”). \n20  \nSee Brattle Report at pp. 10-11. \n21  \nPJM Answer at 17."},{"page":10,"startToken":3110,"endToken":3495,"text":"10 \n \nrules, a capacity resource must submit offers into the day-ahead and real-time energy markets.22  \nAs a result, a requirement that a co-located generator be a capacity resource appears to mandate \nthat the generator enter into a financial contract with co-located load, as contractual terms and \nmarket clearing prices will differ.  Where co-located load is seeking only a physical arrangement, \nrequiring the co-located generator to be a capacity resource could interfere with contracting and, \nthrough such a disincentive, undermine the resource adequacy sought by New Option 6.  \nC. \nBrattle Report: Integrated Energy Park Interconnection is a Practical \nSolution (Questions d.vii, e.v, f.i, f.iii, and f.iv) \n \nThe attached Brattle Report assesses the concept of interconnecting new generation and \nco-located load as a composite facility called an Energy Park.  This is not a unique concept.  The \nElectric Reliability Council of Texas (“ERCOT”) has been doing so for years through its \napproach to interconnecting Private Use Networks.  Brattle describes the process it proposes as \n“Energy Park Integration” (“EPI”) interconnection, where the Energy Park is studied as a \ncomposite load and generation facility, instead of studying the load in one process and the \ngeneration in another.23 \nBecause an Energy Park supplies all or part of its load on-site, when studied as an \nintegrated unit, it can be connected to the grid with fewer transmission upgrades (thus \naccelerating the interconnection).  That is not the case today, as there are no existing protocols \nfor doing so.  Transmission owners may study the new load component of an Energy Park \n \n22  \nUnder the Appendix to Attachment K of PJM’s Tariff, Section 1.10.1A(d), a capacity resource is required \nto: (1) offer its Installed Capacity (ICAP) equivalent of the resource’s cleared Unforced Capacity (UCAP) into the \nPJM energy markets every day if not on outage or derated; and (2) be available for scheduling and dispatch unless \nthe unit designates its offers as a “Maximum Emergency” offer (requiring it to fall under at least one of four tariff-\ndefined categories). \n23  \nWhile each of PJM and the transmission owner may have different roles in the study, both would take the \nEnergy Park as a whole into account for purposes of their studies, similar to the coordinated roles currently in place \nin the interconnection queue for generators."},{"page":11,"startToken":3495,"endToken":3747,"text":"11 \n \n(without recognizing the co-located generation), while PJM may study interconnection of the \nnew generation (without recognizing the co-located load).  These bifurcated, non-integrated \nprocesses ignore the on-site supply benefits and overstate the necessary transmission upgrades, \nwhich result in slowing down interconnection and unnecessarily increasing costs.24  \nThe proposed EPI approach by Brattle models the composite behavior of load and \ngeneration in an Energy Park by accounting for three essential components: the generator, load, \nand a control mechanism that limits net exchanges with the grid.  Net load impacts would be \nlimited to just the nominated net grid withdrawal by load, while net injection impacts from the \ngeneration would be limited to the nominated injection level. \nThe Brattle Report demonstrates that the EPI approach can lower transmission impacts \nand interconnection time without sacrificing reliability (and indeed, improving it through \naccelerated integration of new supply).  The report steps through the standard contingency \nstudies used for load reliability planning to show that the proposed EPI study approach yields \nlower transmission impacts even considering the contingency cases used in transmission \nplanning.  These analyses also show the role of the control mechanism in reducing such \ntransmission impacts.25 \nThe Brattle Report further explains how the EPI study is practical.  ERCOT for one has \nadopted an integrated approach to studying Private Use Networks, representing over 16,000 \nMW, a quarter of which was added in the last decade.26  Other regions have considered similar \n \n24  \nBrattle Report, p. 12-13. \n25  \nId. at pp. 13-22. \n26  \nId. at p. 22."},{"page":12,"startToken":3747,"endToken":4038,"text":"12 \n \napproaches, and Google recommended fast-track connection of co-located load and generation in \nDocket No. AD24-11-000.27 \nThe PJM “deliverability” studies currently used to study both network and energy-only \ngeneration resources will require reform to implement an EPI approach for Energy Parks that \nseek to net inject to the grid on a non-firm basis.  Because an Energy Park is designed primarily \nto supply on-site co-located load and would inject energy to the grid only to the extent grid \ncapacity is available or when doing so is beneficial to system reliability, interconnection studies \nought to reflect the controllable, as-available, non-firm nature of injections from Energy Parks.  \nTransmission owners studying load likewise would need to adopt processes to incorporate \nassumptions related to the co-located generator in their load studies.  This is possible so long as \nPJM and transmission owners know that Energy Parks have control and protection mechanisms \nin place to limit grid injections and withdrawals.28  Interconnection studies of the co-located \ngeneration can be performed on an expedited basis using protocols similar to PJM’s recently-\nrevised CIR Replacement process or Surplus Interconnection Service, as controllable net \ninjections will not cause transmission impacts beyond the designated levels.  In exchange, PJM \ncould provide for non-firm grid injection requests based on “as available” grid capacity (i.e., less \nfirm than current energy-only interconnections).29 \n \nAs the Brattle Report concludes: “By avoiding unnecessary transmission upgrades to \naccommodate new large loads, the EPI process avoids any costs that would otherwise be \nallocated broadly to all customers.  By facilitating and accelerating a ‘bring-your-own capacity’ \n \n27  \nId. at p. 23 and note 34 (citing Post-Technical Conference Comments of Google LLC, Docket No. AD24-\n11-000, at p. 5 (filed Dec. 10, 2024)). \n28  \nBrattle Report at pp. 24-28. \n29  \nId."},{"page":13,"startToken":4038,"endToken":4160,"text":"13 \n \napproach, the proposal mitigates the resource adequacy impact of load growth, easing price \nincreases in the capacity market ad the commensurate bill impacts for all consumers.”30  The \nCommission should direct PJM to expeditiously implement the EPI approach for Energy Parks. \nIII. \nCONCLUSION \nFor the foregoing reasons, Bloom urges the Commission to provide detailed guidance to \nPJM, and set forth compliance deadlines for future filings to implement co-location tariff rules \nincluding the EPI approach developed in the Brattle Report for studying Energy Parks. \n \n \n \n \n \nRespectfully submitted, \n \n \n \n \n \n \n/s/ Joel D. Newton \n \n \n \n \n \n \nJoel D. Newton \n \n \n \n \n \n \nVice President, Regulatory Law \n \n \n \n \n \n \nBloom Energy Corporation \n4353 North First Street  \nSan Jose, CA 95134  \n(202) 329-1119 \njoel.newton@bloomenergy.com \n \nApril 23, 2025 \n \n \n30  \nId. at p. 31."},{"page":14,"startToken":4160,"endToken":4222,"text":"14 \n \nCERTIFICATE OF SERVICE \n \n \nI hereby certify that I have on this 23rd day of April, 2025, caused to be served a copy of \nthe foregoing upon all parties on the service lists in these proceedings in accordance with the \nrequirements of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § \n385.2010. \n \n \n \n \n \n \n \n   /s/ Joel D. Newton"},{"page":15,"startToken":4222,"endToken":4224,"text":"15 \n \n \n \n \nATTACHMENT"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":5,"startToken":0,"endToken":606},{"p":3,"at":5,"title":"I. INTRODUCTION","method":"printed heading","endPage":6,"endAt":1318,"startToken":606,"endToken":1836},{"p":6,"at":1318,"title":"II. Comments","method":"printed heading","endPage":7,"endAt":5,"startToken":1836,"endToken":1984},{"p":7,"at":5,"title":"A. Option 3: PJM Should Clarify its Statements that Existing Behind the Meter","method":"printed heading","endPage":8,"endAt":1197,"startToken":1984,"endToken":2637},{"p":8,"at":1197,"title":"B. Option 6: PJM’s bring your own generation with incentive for faster","method":"printed heading","endPage":10,"endAt":589,"startToken":2637,"endToken":3198},{"p":10,"at":589,"title":"C. Brattle Report: Integrated Energy Park Interconnection is a Practical","method":"printed heading","endPage":13,"endAt":284,"startToken":3198,"endToken":4080},{"p":13,"at":284,"title":"III. CONCLUSION","method":"printed heading","endPage":14,"endAt":6,"startToken":4080,"endToken":4161},{"p":14,"at":6,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":15,"endAt":22,"startToken":4161,"endToken":4224}]}