{"document":{"slug":"rec-20250423-5240","title":"Comments of EDF Renewables, Inc. in response to PJM Interconnection, L.L.C.’s Answer filed on 03/24/2025","issued":"2025-04-23","accession":"20250423-5240","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"EDF Renewables, Inc.","kind":"answer","file":"sources/filings/text/20250423-5240_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250423-5240","tier":"record","sha256":"d90a1a196799f66eb2c422c4c4ec77e32784cf1b3fdb9b60a0c92278e0b99f0f","pages":13,"tokens":3193,"emptyPages":[],"textThemes":["colo","flex"]},"pages":[{"page":1,"startToken":0,"endToken":186,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nPJM Interconnection, L.L.C.  \n \n \n \n \nDocket No. EL24-49-000 \nAllegheny Electric Cooperative, Inc.  \n \n \nAmerican Transmission Systems, Incorporated \nAtlantic City Electric Company \nBaltimore Gas and Electric Company \nDelmarva Power & Light Company \nDuke Energy Ohio, Inc. \nDuke Energy Kentucky, Inc. \nEast Kentucky Power Cooperative, Inc. \nEssential Power Rock Springs, LLC \nHudson Transmission Partners, LLC \nJersey Central Power & Light Company \nMid-Atlantic Interstate Transmission, LLC \nNeptune Regional Transmission System, LLC \nOld Dominion Electric Cooperative \nPECO Energy Company \nPPL Electric Utilities Corporation \nPotomac Electric Power Company \nPublic Service Electric and Gas Company \nRockland Electric Company \nTrans-Allegheny Interstate Line Company \nTransource West Virginia, LLC \nUGI Utilities, Inc. \nMonongahela Power Company \nThe Potomac Edison Company \nCommonwealth Edison Company \nCommonwealth Edison Company of Indiana, Inc. \nThe Dayton Power and Light Company \nAEP Appalachian Transmission Company, Inc. \nAEP Indiana Michigan Transmission Company, Inc.  \nAEP Kentucky Transmission Company, Inc. \nAEP Ohio Transmission Company, Inc. \nAEP West Virginia Transmission Company, Inc.  \nAppalachian Power Company \nIndiana Michigan Power Company \nKentucky Power Company \nKingsport Power Company \nOhio Power Company \nWheeling Power Company \nDuquesne Light Company \nVirginia Electric and Power Company"},{"page":2,"startToken":186,"endToken":380,"text":"2 \n \nLinden VFT, LLC \nCity of Cleveland, Department of Public Utilities,  \n     Division of Cleveland Public Power \nCity of Hamilton, OH \nSouthern Maryland Electric Cooperative, Inc. \nOhio Valley Electric Corporation \nAMP Transmission, LLC \nSilver Run Electric, LLC \nNextEra Energy Transmission MidAtlantic Indiana, Inc. \nWabash Valley Power Association, Inc. \nKeystone Appalachian Transmission Company \n \n \nLarge Loads Co-Located at Generating Facilities \n \n \nDocket No. AD24-11-000 \n \n \nConstellation Energy Generation, LLC \n \n \n \nDocket No. EL25-20-000 \n \n \n \n \n \n \n \n \n \n(consolidated) \nv. \n \nPJM Interconnection, L.L.C \n \n \nCOMMENTS OF EDF RENEWABLES, INC.  \n \n \nPursuant to Rules 212 and 213 of the Rules of Practice and Procedure of the Federal \nEnergy Regulatory Commission (Commission or FERC),1 EDF Renewables, Inc. (EDFR) \nrespectfully submits these comments in response to the answer filed by PJM Interconnection, \nL.L.C. (PJM) on March 24, 2025 (PJM Answer).  The PJM Answer was filed in response to the \nCommission’s Order Instituting Proceeding Under Section 206 of the Federal Power Act and \nConsolidating with Other Proceedings, issued on February 20, 20252 regarding the co-location of \nlarge loads in PJM. \n \n1 18 C.F.R. §§ 385.212, 385.213 (2024). \n2 PJM Interconnection, L.L.C., et al., 190 FERC ¶ 61,115 (2025) (February 20 Order)."},{"page":3,"startToken":380,"endToken":656,"text":"3 \n \nI. \nSUMMARY OF COMMENTS  \nThe challenges of serving new large load data centers are present across the country.  \nData centers and their co-location arrangements can take many forms, including structures with \noperational flexibility that can provide a host of benefits to the transmission system, and some \nthat have less operational flexibility and thereby place more demands on the transmission \nsystem.  Although this proceeding is directed at PJM, any decision in this proceeding may have \nimplications for other regions as well.  EDFR urges the Commission in this proceeding to adopt \na flexible, performance-based framework that recognizes large load diversity within the data \ncenter industry and other industries (hydrogen, e-fuels, and Carbon Capture, Utilization and \nStorage (CCUS)), encourages “grid-light” development structures, and avoids inadvertently \npenalizing innovative co-located load configuration models.  Such a flexible framework can be \nreplicated in other regions.  \nCo-location can streamline the interconnection process, reduce the need for expensive \ngrid upgrades, and minimize delays in bringing new generation and load online.  Not all large \nelectricity-consuming facilities that co-locate with existing or new power generators need to \nundergo the same interconnection and reliability planning processes.  Some large loads can \nlocate in areas with surplus energy – generation pockets where frequently-curtailed energy is \n“trapped” behind constrained transmission.  Locating large loads in these generation pockets will \nprevent curtailed energy from being wasted, reduce the frequency of the transmission constraints, \nand may allow the load to be integrated faster with less impact on the bulk electric system.  In \neffect, this load could delay the need for flowrate capacity expansion and reduce congestion cost \nin the case of an RTO LMP market structure.  Due to their flexibility, large curtailable loads can"},{"page":4,"startToken":656,"endToken":926,"text":"4 \n \nprovide net benefits to the grid by reducing congestion, delaying need for transmission, and \nproviding demand response services when needed.  \nIn contrast, some co-locating loads are highly dependent on uninterruptible service and \nthus place significantly more demand on the grid.  Loads that lack operational flexibility can lead \nto grid instability, unexpected power shortages and higher costs for other consumers.  Large \ninflexible loads should not dictate a set of rules that apply to more operationally flexible, \npotentially beneficial, co-location arrangements.  Rather, the rules governing large co-located \nloads should be balanced with the ability for grid operators to use the flexibility of that load to \noperate the system more reliably.  Further, the more flexible the load, the simpler it should be to \ninterconnect behind a generator’s meter, thus warranting different rules for interconnecting. \nLarge loads are not one-size-fits-all and the processes for interconnecting, serving, and \nallocating costs to large loads should accommodate this diversity.  This proceeding presents an \nopportunity for the Commission to establish rules that (1) encourage co-location development in \na way that allows large flexible co-located loads to interconnect expeditiously and efficiently and \n(2) can be applied to various reliable and commercially beneficial structures across the country.  \nII. \nBACKGROUND \nEDFR, develops, builds, operates, and manages renewable energy projects throughout \nNorth America, including in PJM, MISO, SPP and ERCOT.  As a market-leading independent \npower producer and service provider for over 35 years, EDFR delivers grid-scale power, \nincluding wind (onshore and offshore), solar photovoltaic, and storage projects; distribution-\nscale power, including solar and storage, and asset optimization.  The company also provides \ntechnical, operational, and commercial expertise to maximize performance of generating"},{"page":5,"startToken":926,"endToken":1207,"text":"5 \n \nprojects.  EDFR is an active participant in interconnection-related policy discussions and \nrulemaking proceedings, including interconnection reform efforts.   \nEDFR has also been exploring data center co-location in other parts of the country and \nhas announced plans for a 166 MW data center to co-locate with EDFR’s 273 MW Las Majadas \nWind Project in ERCOT.  The data center will connect to EDFR’s private substation and the data \ncenter and Las Majadas will co-own as tenants-in-common the private electric delivery facilities \ninterconnected to the grid pursuant to a Shared Facilities Agreement.  \nThe data center will utilize behind-the-meter (BTM) power generated by the wind \nproject, while also curtailing their operations under certain market conditions when energy is \nmost needed by the grid.  This BTM offtake arrangement presents a unique advantage for \nmarket-exposed renewable projects by physically delivering a portion of a plant’s power directly \nto the co-located buyer’s facility.  This innovative power purchase agreement (PPA) structure \nprovides a flexible solution to the challenges of transmission constraints and curtailment, \nessentially allowing an alternate route to capture under-utilized electricity. Concurrently, it \nprovides an opportunity for an energy-intensive load that is seeking clean power solutions to \nfulfill that need while advancing computing applications, including artificial intelligence (AI). \nIII. \nCOMMENTS \n \nAs the Commission noted in the February 20 Order, co-located load arrangements are \nbecoming increasingly common, in large part driven by the development of new data centers \n(e.g., facilities used for AI, cloud data storage, and cryptocurrency mining, etc.).3  Many of these \nnew large load facilities are already operating, and forecasts suggest that many more are in \ndevelopment.  Traditional utility structures and current RTO interconnection rules are often \n \n3 February 20 Order at PP 3, 15"},{"page":6,"startToken":1207,"endToken":1511,"text":"6 \n \nunworkable to meet this new demand, in large part due to the facilities’ near-term need for \npower.  Given the speed with which the new large load facilities can be built, the existing load \ninterconnection process and the congested generator interconnection processes currently in place \nare often insufficient to meet the timing of power needs.  Co-location structures have emerged as \na solution to meet this need.  The question is how these large load facilities can co-locate with \nexisting power generators in a manner that is just and reasonable and not unduly discriminatory \nfor cost allocation purposes and that is reliable from a grid operation perspective.   \nA. \nThe Commission Should Act Expeditiously to Encourage Flexible Co-\nLocation Structures that Will Enable Speedy and Reliable Interconnection \nfor Large Loads.  \n \nThis proceeding is an opportunity for the Commission to provide guidance to PJM and \nother RTO/ISO and non-RTO/ISO regions for developing a standardized and transparent load \ninterconnection process at the federal level.  A generic rulemaking proceeding would take too \nlong.  It is possible that a case-by-case approach can be workable if it is fair and non-\ndiscriminatory, such as the Expedited Project Review Request in MISO.  In some instances, \nexisting rules prohibit certain co-location arrangements that should otherwise be allowed.  For \nexample, EDFR has found that SPP does not provide a co-location option for optimal \ncommercial operation in that region.4  \nHere, the Commission has an opportunity to determine what structures work and how \ncosts should be allocated, and to identify the barriers to the efficient and reliable co-location of \nlarge loads.  Lessons learned and best practices identified here should be applicable across other \n \n4 For example, SPP does not allow netting for grid-connected behind-the-meter generation and most \nexemptions from network load status are for non-grid connected and non-market participation generation.  \nSPP Tariff, Att. AE."},{"page":7,"startToken":1511,"endToken":1822,"text":"7 \n \nregions on an expedited basis to ensure that new large loads can be served while maintaining \nreliability and ensuring that existing customers are not bearing unnecessary costs.  \nThe Commission can encourage PJM and other RTOs, as well as transmission providers \nin non-RTO regions to develop standardized yet flexible rules to accommodate different co-\nlocation structures with varying operational capabilities.  Specifically, the Commission should:  \n1. \nClarify that co-located loads using non-firm grid power and backed by onsite \ngeneration may qualify for modified transmission cost allocation (e.g., based on \nusage, not full network load charges). \n2. \nDirect each RTO and ISO to develop and file tariff provisions for co-located load \nand generation under a shared interconnection with clear netting, metering, and \nsettlement rules. \n3. \nConsider standardized registration and modeling of flexible co-located load \nbehind interconnections. \n4. \nEncourage RTOs/non-RTOs, if not already the case, to simultaneously evaluate \nflexible load and generation with expedited timelines.  \n5. \nEnsure that any capacity market participation requirements for co-located \ngeneration should depend on the type of co-location arrangement. \n6.  \nGuarantee that states and local communities can make their own policies \nregarding distribution system interconnection processes and retail rates when co-\nlocated generation is not available to supplying load. \nWhile Federal rules should be consistent across all regions, they should also be flexible \nenough to allow developers to work within different state rules/policies.  Any Commission action \nin response to PJM’s proposal should enable flexibility in other regions.   \nB. \nCo-Locating Large Loads at Existing Generation Sites Can Provide \nSignificant Benefits to Existing Generation and the Transmission System. \nCo-location arrangements can benefit the transmission system in many ways.  Large \nflexible co-located load arrangements can help streamline the generator interconnection process \nby reducing the need for expensive grid upgrades and avoiding queue delays in bringing new \ngeneration online.  Even where new transmission needs to be built, co-location can minimize"},{"page":8,"startToken":1822,"endToken":2082,"text":"8 \n \nrequired new upgrades.  Co-locating large loads can also reduce congestion costs and provide \ndemand response services if the power demands are flexible.  When near-term load growth \nforecasts are high, co-location can help with transmission planning as well.   \nCo-location arrangements can provide significant benefits to existing generators.  For \ninstance, by locating in areas with surplus energy, large loads can help prevent wasteful \ncurtailments.  By using energy that would otherwise be curtailed, large flexible loads like crypto \nmining or batch AI data centers can significantly improve generator economics without stressing \nthe grid.  As a result, large interruptible co-located load pairs well with resources like wind and \nsolar by using underutilized resources and not requiring new transmission build. \nCo-location arrangements also provide benefits to American industries looking for \naffordable, carbon-free energy. Industrial consumers can access areas of surplus energy to foster \nthe growth of globally competitive industries otherwise subject to expensive utility pricing and \npotentially lacking alternative energy options. \nFinally, co-location arrangements will provide benefits to states and communities. Large \nload facilities can provide a host of benefits to local communities in the form of tax revenues, \nconstruction jobs, and employment.  In this regard, it is important that any rule coming out of \nthis proceeding allows states and local communities the freedom to make their own policies \nregarding retail rates and distribution system interconnection processes.   \nC. \nCo-Location Arrangements are Not One-Size-Fits-All; Any New Rules \nShould Be Flexible.  \n \nAs demonstrated by PJM’s eight options to facilitate co-location arrangements, there are \nmany potential co-location structures that vary depending on the size and operational flexibility"},{"page":9,"startToken":2082,"endToken":2412,"text":"9 \n \nof the load.  AI data centers that need “five-nines”5 power reliability should not be treated the \nsame as crypto mining load that has considerable operating flexibility. For example, EDFR’s Las \nMajadas project is a flexible BTM structure where the data center can curtail when Las Majadas \ngeneration capacity is needed in the ERCOT market. In contrast, AI data centers typically require \n24/7 firm service and do not provide the same flexibility for the co-located generation resource \nto inject into the grid. Some industries able to co-locate load behind the generator’s meter do not \nrequire grid firming beyond their auxiliary power needs at all. \nThe Commission should ensure that any new rules and processes that are developed have \nflexibility for different co-location arrangements.  Rules should accommodate diverse structures \nwhile ensuring that those structures pay their fair share of grid costs.  AI data centers with five-\nnines reliability needs should not dictate rules for large loads that have significant flexibility.  \nThe recent PJM example involving Talen Energy’s AI data center paired with the Susquehanna \nnuclear facility presents a much different set of needs and risks than a flexible crypto-mining \nfacility paired with an intermittent wind resource.  The latter has significant operational \nflexibility and can even offer services back to the grid that can help with grid operations.  \n \nAs was developed in ERCOT, the Commission should encourage PJM and other ISOs to \ndevelop an expedited process for controllable load to interconnect and economically dispatch in \nthe wholesale market, or to participate as voluntary load shed resources.  These flexible \nresources present a minimal impact on the transmission system and can even offer system-wide \nreliability benefits while maximizing the efficient use of otherwise underutilized energy \nresources.  In this proceeding, the Commission should encourage: \n \n5 This is a reference to high availability of services, such as when a service is available for 99.999% of the \ntime, or around 5 minutes of downtime per year.  See https://en.wikipedia.org/wiki/Five_nines."},{"page":10,"startToken":2412,"endToken":2738,"text":"10 \n \n Implementation of an expedited interconnection process for controllable co-located \nload resources or voluntary load-shed resources to come online and provide benefits \nto the grid.  \n Establishment of a requirement that the size of the co-located load must be a certain \npercentage less than the generation at an interconnection point.  (E.g., Load can be up \nto 70% of the Main Power Transformer).  \n Implementation of an ERCOT-type settlement rules during production period so that \nlarge loads and generation resources that are co-located behind a shared Point of \nInterconnection (POI) are netted together.  \nIn addition, the Commission should recognize the importance of allowing co-location to \nevolve with RTO design.  The Commission should ensure that flexibility is maintained as market \ndesigns evolve, including recognition of load response, load netting, and demand-side dispatch. \nD. \nTransmission Costs Should be Assigned Based on the Specific Grid Services \nUsed in a Particular Co-Location Structure Consistent with the \nCommission’s Beneficiary Pays Principle. \n \n \nConsistent with the Commission’s beneficiary pays principle,6 transmission charges \nshould be assigned to large load facilities based on the specific grid services that the load uses \nand the configuration of the co-location structure.  Therefore, a range of transmission system \ncharges should be available that match the load’s reliance on the grid.  Co-location structures that \nplace minimum demands on the transmission system (i.e., “grid-light”) or that allow load to be \n \n6 Under the “beneficiary pays” cost causation principle, rates must “reflect to some degree the costs \nactually caused by the customer who must pay for them.” Midwest ISO Transmission Owners v. FERC, \n373 F.3d 1361, 1368 (D.C. Cir. 2004).  Costs must be allocated in a manner that is at least roughly \ncommensurate with the benefits an entity receives.  Ill. Com. Comm’n v. FERC, 576 F.3d 470, 474-78  \n(7th Cir. 2009) (remanding Commission order for further proceedings in light of Commission’s failure to \nprovide substantial evidence supporting Commission’s approval of cost allocation method as complying \nwith “beneficiary pays” principle)."},{"page":11,"startToken":2738,"endToken":3006,"text":"11 \n \navailable for demand response or periodic outages to respond to grid congestion should pay less \nin grid costs than co-location structures where the load requires five-nines reliability.  Full \nnetwork load charges should not be the default rate charged to all co-location structures. \nFlexible co-located load that does not rely on the transmission system the same way as \nnetwork connected load should only be assigned charges for grid services when they are taking \npower from the grid.  For example, under ERCOT’s generation netting rules, generation \nresources that are co-located behind a shared POI are netted together such that in each market \nsettlement interval if more power is flowing out (net generation) then it is settled as generation \nand no grid charges apply.  If more power is flowing in during the interval (net load), then it is \nsettled as load with applicable grid charges.  \nEDFR appreciates PJM’s efforts to develop Options 1 through 8 outlining potential co-\nlocation structures.7  These options, some already existing and some that need further \ndevelopment, show that there is considerable variation in potential co-location configurations \nwith differing reliance on grid services.  Grid charges should be assessed according to the co-\nlocation arrangement, the flexibility of that load, and its reliance on the grid.  Thus, the \nCommission should affirm that discrete delivery points with flexible arrangements, mostly \nbehind-the-meter use, and minimal reliance on the grid should not be swept into a network load \nclassification.  Only co-location structures with load that regularly and materially use the grid \nshould pay network load transmission charges, consistent with the Commission’s beneficiary \npays principle.   \n \n7 PJM Answer, Ex. A."},{"page":12,"startToken":3006,"endToken":3107,"text":"12 \n \nIV. \nCONCLUSION \nFor the foregoing reasons, EDFR requests that the Commission adopt a flexible, \nperformance-based framework that recognizes load diversity, encourages “grid-light” \ndevelopment, and avoids inadvertently penalizing innovative renewable-first load models. \nRespectfully submitted, \n \n \n \n \n \n \n \n \n/s/ Linda Walsh_____ \nTemujin Roach \n \n \n \nLinda Walsh \nEmma Nix Simon \n \n \n \nCarrie Collier-Brown \nEDF Renewables, Inc. \n \n \nMichael Blackwell \n15445 Innovation Dr.  \n \n \nHusch Blackwell LLP \nSuite 1000 \n \n \n \n \n1801 Pennsylvania Ave., NW \nSan Diego, CA 92128  \n \n \nWashington, DC  20006 \nTel: (612) 486-4498  \n \n \nTel: (202) 378-2308 \nTemujin.Roach@edf-re.com  \n \nlinda.walsh@huschblackwell.com  \nEmmaNix.Simon@edf-re.com \n \nmichael.blackwell@huschblackwell.com \n \n \n \n \n \n \n \n \n \nCounsel to EDF Renewables, Inc. \nDated: April 23, 2025"},{"page":13,"startToken":3107,"endToken":3193,"text":"CERTIFICATE OF SERVICE \n \n \nPursuant to Rule 2010 of the Federal Energy Regulatory Commission’s Rules of Practice \nand Procedure, 18 C.F.R. § 385.2010, I certify that I served the foregoing document upon each \nperson designated on the official service list compiled by the Secretary in this proceeding. \n \n \nDated at Washington, D.C. this 23rd day of April 2025. \n \n \n/s/ Corban A. Coffman \n \nCorban A. Coffman   \nHusch Blackwell LLP  \n1801 Pennsylvania Ave. NW, Suite 1000  \nWashington, D.C. 20006 \nTel: (202) 378-5856  \nCorban.Coffman@huschblackwell.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":5,"startToken":0,"endToken":381},{"p":3,"at":5,"title":"I. SUMMARY OF COMMENTS","method":"printed heading","endPage":4,"endAt":1408,"startToken":381,"endToken":854},{"p":4,"at":1408,"title":"II. BACKGROUND","method":"printed heading","endPage":5,"endAt":1452,"startToken":854,"endToken":1127},{"p":5,"at":1452,"title":"III. COMMENTS","method":"printed heading","endPage":6,"endAt":677,"startToken":1127,"endToken":1312},{"p":6,"at":677,"title":"A. The Commission Should Act Expeditiously to Encourage Flexible Co-","method":"printed heading","endPage":7,"endAt":1723,"startToken":1312,"endToken":1753},{"p":7,"at":1723,"title":"B. Co-Locating Large Loads at Existing Generation Sites Can Provide","method":"printed heading","endPage":8,"endAt":1610,"startToken":1753,"endToken":2045},{"p":8,"at":1610,"title":"C. Co-Location Arrangements are Not One-Size-Fits-All; Any New Rules","method":"printed heading","endPage":10,"endAt":905,"startToken":2045,"endToken":2541},{"p":10,"at":905,"title":"D. Transmission Costs Should be Assigned Based on the Specific Grid Services","method":"printed heading","endPage":12,"endAt":6,"startToken":2541,"endToken":3007},{"p":12,"at":6,"title":"IV. CONCLUSION","method":"printed heading","endPage":13,"endAt":0,"startToken":3007,"endToken":3107},{"p":13,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":13,"endAt":555,"startToken":3107,"endToken":3193}]}