{"document":{"slug":"rec-20250423-5248","title":"Comments of Suzanne Glatz and Abraham Silverman in response to PJM Interconnection, L.L.C.'s et al. 03/24/2025 filings","issued":"2025-04-23","accession":"20250423-5248","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"JOHNS HOPKINS UNIVERSITY","kind":"comments","file":"sources/filings/text/20250423-5248_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250423-5248","tier":"record","sha256":"1ddc8c4dde37ee729bf335a0138c7e17bfacdedc0a4c2e9a04f224f8b2a0f202","pages":16,"tokens":5504,"emptyPages":[],"textThemes":["colo","study","flex","adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":266,"text":"1 \n \nUNITED STATES OF AMERICA \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C., et al. \n \n)  Docket Nos. EL25-49-000 \n \n \nLarge Loads Co-Located at Generating Facilities \n \n \n)  AD24-11-000 \n \nConstellation Energy Generation, LLC \nv. \nPJM Interconnection, L.L.C. \n)  EL25-20-000 \n  (Consolidated) \n \n \nReply Comments of Suzanne Glatz and Abraham Silverman \n \n \n \nPursuant to Rules 206 and 213 of the Federal Energy Regulatory Commission’s \n(“Commission”) Rules of Practice and Procedure, 18 C.F.R. § 385.206 .213, and as directed \nby the Commission in Docket No. EL25-49-000, Suzanne Glatz and Abraham Silverman, \nrespectfully submits these comments in response to the filings dated March 24, 2025 of PJM \nInterconnection, L.L.C. (“PJM”), and the Indicated PJM Transmission Owners, made in \nresponse to Commission’s February 20, 2025 Order Instituting Proceeding under Section 206 \nof the Federal Power Act and Consolidating with Other Proceedings (the “Show Cause \nOrder”).1 \nI. \nSummary  \nThe unprecedented growth in demand in the PJM region driven by large customers, \nprimarily data centers, is driving the need for significant new transmission and exasperating \nresource adequacy concerns due, in large part, to an aging generation fleet and long delays in \ninterconnecting new generation.  While co-location allows large loads to bypass the \nconventional load connection process and accelerate data center deployment, if not carefully \nmanaged, co-location also has the potential to push the PJM region into a resource adequacy \nand affordability crisis.  \n \nSince the formation of PJM, load customers seeking to connect to the grid have taken \nNetwork Integration Transmission Service (“NITS”) to connect to the grid.  While the \n \n1 PJM Interconnection, L.L.C., et al., 190 FERC ¶ 61,115 (2025)."},{"page":2,"startToken":266,"endToken":593,"text":"2 \n \nArtificial Intelligence (“AI”) revolution provides an opportunity to discuss improvements to \nPJM’s existing transmission offerings – in particular, through the creation of a curtailable \nservice option and increased contract terms for new large NITS customers to protect \ncustomers against stranded transmission investments – we see the underlying NITS structure \nas fundamentally sound.  Thus, we largely agree with the position advanced by the PJM \nTransmission Owners2 and in PJM’s Existing Option 1 that the existing PJM tariff is just and \nreasonable.34  \nDisputes over co-location should not distract from the urgency to actively manage \nload growth and bring more energy resources to the grid.  PJM’s 2025/2026 capacity auction \nprocured only 514 megawatts (“MW”) of excess above the Installed Reserve Margin.  PJM \npredicts 2,700 MW of additional load growth for the 2026/2027 delivery year – largely driven \nby data centers.  Whether load is co-located with generation in a “behind-the-generator-meter” \nconfiguration or in a conventional load connection, the issue remains that PJM must balance \nthe amount of new data center load and new generation resources for the system to remain \nreliable and affordable.   \nWe recognize the interest in co-location and the commercial value of connecting data \ncenters on an expedited basis, including allowing generation to directly serve end-use \ncustomer load.  The current tariff does not contain provisions to specifically describe how a \ngenerator and a retail load can jointly or separately request to connect to the PJM grid in a co-\nlocation configuration, and recommend that PJM develop: \n• \nA new pro forma interconnection agreement with an accompanying rate structure \nspecific to the co-location business model; \n \n• \nA safety valve to ensure that co-located data center load does not plunge PJM into a \nreliability or affordability crisis; \n \n• \nMinimum term requirements for new transmission service requests from large loads, \nbacked by financial security requirements;  \n \n2 Answer of Indicated PJM Transmission Owners to the Show Cause Order, at p. 10.   \n3 Answer of PJM Interconnection to the Show Cause Order, at p. 10."},{"page":3,"startToken":593,"endToken":869,"text":"3 \n \n \n• \nA new type of non-firm transmission service that allows for faster connections in \nexchange for operational flexibility; and  \n \n• \nClear regulatory obligations of generators serving on-site customer load.    \n \nIn these comments we will discuss more specifically why the current Tariff is inadequate to \naccommodate co-location and offer potential models for consideration and further \ndevelopment in a transparent and open stakeholder forum. \nII. \nBackground of Suzanne Glatz and Abraham Silverman \nThese comments are submitted on behalf of Suzanne Glatz and Abraham Silverman.  \nThese comments are not filed on behalf of any party and represent the personal opinions of \nthe authors.   \nSuzanne Glatz has worked in the energy industry for close to 40 years in various \ncapacities that include many facets of transmission and distribution planning.  Ms. Glatz is \ncurrently an independent consultant supporting entities navigating the complexity of regional \nplanning processes.  Prior to starting her independent consulting business, Ms. Glatz was \nemployed by PJM for the period of 2011-2023, where her last position was Director, Strategic \nInitiatives and Interregional Planning.  \nAbraham Silverman is a research scholar at Johns Hopkins University’s Ralph \nO’Connor Sustainable Energy Institute and principal of Silvergreen Energy Consulting, LLC.  \nMr. Silverman holds degrees from the University of Maryland the George Washington \nUniversity Law School.  He has worked in the energy industry in a variety of positions, \nincluding at the Commission, in private law practice, at NRG Energy, Inc., a leading \nindependent power producer.  Most recently, he served as General Counsel and Executive \nPolicy Counsel at the New Jersey Board of Public Utilities from 2019 to 2023.  Since leaving \nstate service, he has been employed as a researcher at Columbia University and Johns \nHopkins University."},{"page":4,"startToken":869,"endToken":1210,"text":"4 \n \nIII. \nComments \n \n \nA. PJM’s Existing NITS Rules are Just and Reasonable and Not Unduly \nDiscriminatory or Preferential to Co-location Customers.     \n \nThe existing PJM Tariff unambiguously affords the ability to connect new customers \nin a co-location arrangement, provided the customer load is willing to be treated as network \nload and contributes to the fixed costs of operating the transmission grid through its NITS \nallocation.  While changing needs on the grid certainly leave room for improvements to the \nPJM framework for serving new data center load, it is also important to recognize that the \nexisting system provides a stable foundation that permits new load to connect to the grid.  As \nPJM notes,5 the options available to customers today include the ability of a generator to be \nphysically co-located with generation.   \nCritical to the Commission’s approach is the fact that co-location arrangements can \noccur with a rapidity that our existing planning processes are not designed to address.  While \nexisting rules also allow utilities to ensure that new loads are connected in an orderly manner \nand that new service is only allowed to commence once transmission needs have been \naddressed, any accelerated co-location process must address what happens if a co-location \nrequest would precipitate a resource adequacy or affordability crisis.  This should include \nupfront rules about deadlines for providing advance notice, study processes, and, ideally, an \nopportunity for relevant state agencies to provide feedback.  Any rules coming out of this \nproceeding should continue to prioritize system reliability and affordability and avoid creating \na situation where data center expansion contributes to a transmission or resource adequacy \nshortfall.  While it is important that PJM and the Commission facilitate access for new users \nof the electric grid, the desire of data center customers for accelerated grid access must be \nbalanced against the threat of increased rates and diminished reliability.   \nThe lost transmission revenue can be significant.  Based on data provided by the \nIndicated Transmission Owners, the potential cost impact to customers by large loads evading \n \n5 Answer of PJM Interconnection LLC, Exhibit A, Summary of Options."},{"page":5,"startToken":1210,"endToken":1596,"text":"5 \n \ngrid charges could be on the order of millions of dollars on an annual basis, potentially \nresulting in customer bill increases between 1 to 10 percent, depending on the utility zone.6  \nThe increase in resource adequacy and energy prices has the potential to be even more \nsignificant, particularly if data center-driven load growth causes the PJM region to sink below \nits IRM requirements, which puts upward pressure on both capacity and energy costs. \nB. Any Just and Reasonable Changes to PJM’s Tariff Should Ensure that \nComparable Electrical Impacts Incur Comparable Transmission Charges.  \n \nIf the Commission elects to direct changes to PJM’s existing tariff methodology for \nassigning transmission charges to co-located load, it should ensure that use-cases with similar \nelectrical impacts pay comparable rates.  As we explained in our prior comments, PJM’s \nelectrical studies “studies do not generate different results because a load is co-located with \ngeneration on one side of the breaker versus on the other side as network load.  Electrically, \nthe flows are the same.”7 \nThe corollary to this principle is that what “type” of meter is used to connect a new \nload can have significant implications for cost allocation.  Load located behind a “generator \nmeter” pays one rate; load located behind a “load meter” pays a different rate – even though   \nthe electrical impacts are identical.  Customers located behind a load meter are subject to a \nhost of charges that simply do not apply to customers locating behind a generator meter.8  For \nexample, generators only pay for “but-for the generator” system upgrades when they go \nthrough the initial interconnection cost allocation process and are categorically exempt from \ntransmission service, ancillary service, and Schedule 12 Regional Transmission Expansion \nPlanning (“RTEP”) baseline upgrade costs.  If any new (i.e., post-interconnection) upgrades \nare required to maintain a reliable grid and comply with mandatory NERC standards, \ngenerators will not be assigned cost responsibility.  This is true even if the generator retires, in \n \n6 Answer of the PJM Indicated Transmission Owners, at p. 19. \n7 Post-Technical Conference Comments of Suzanne Glatz and Abraham Silverman, at p. 5. \n8 The differing rate treatment between “generator meters” and “load meters” also helps explain why \ntraditional combined heat and power facilities have not triggered the same concern.  There, the co-\ngeneration facility is typically located behind a load meter."},{"page":6,"startToken":1596,"endToken":1987,"text":"6 \n \npart or in entirety.  RTEP upgrade costs are likewise paid for solely by network load \ncustomers.   \nAssigning all transmission costs to network load is a reasonable method of assigning \ncosts when all generation serves load connected to the grid and is subject to the same rates.  \nOtherwise, connected load under a rate that is applicable to a generator will result in the load \nnot paying its fair share of the cost of operating the transmission grid and leading to \npreferential treatment to co-located load and potentially free ridership on the grid.  \nC. Principles for a New Interconnection Service if FERC Determines that \nAlternative Tariff Rules are Required. \n \nOne of the key questions facing the Commission in this docket (assuming it elects to \ntake action) is whether generators that have gone through the existing PJM interconnection \nprocess need to be re-analyzed when adding co-located load, and if so, what that study should \nlook like.  As a guiding principle, we recommend that the Commission adopt a principle of \n“comparability” designed to ensure that new co-location arrangements go through a study \nprocess that is comparable in terms of timing and cost responsibility to a new load locating in-\nfront-of-the-meter.  Such an approach would help the “regulatory gap”9 between the generator \ninterconnection process and the Commission’s prior holding in Order No. 2003-A that \n“Interconnection Service is separate from the delivery component of Transmission Service.”10      \nIn its answer, PJM identified five options as new options that are not currently available to \ncustomers without revisions to the tariff.  These options all fall short of achieving the type of \ncomparability between co-located and front-of-the-meter customers that we advocate.  We are \nconcerned that an appropriate set of studies should recognize all potential modes of operation \n– both generation and load – and be studied appropriately, including addressing what happens \n \n9 See Post-Technical Conference Comments of Suzanne Glatz and Abraham Silverman in Docket No. \nAD24-11-000, Page 6 (“It is difficult (if not impossible) to harmonize the concept of connecting new \nnetwork load behind the meter of an existing generation facilities with the Commission’s directive that \ngenerator interconnection service is “not the same as, or a substitute for” NITS.  The end result is a gap \nin how transmission providers are studying and assigning cost responsibility for load collocated with \ngeneration.”) \n10 Order No. 2003-A at P 113 (capitalization in original)."},{"page":7,"startToken":1987,"endToken":2375,"text":"7 \n \nif a generator elects to effectively remove itself from the grid as part of a co-location \narrangement.   \nFor example, PJM Options 4, 5, 7 and 8 all raise significant transparency issues \naround whether the studies PJM would carry out are comparable to the studies normally \ncarried out both as part of a large load interconnection process and the generator \ninterconnection process.  PJM states “that any configuration where the co-located load is \nNetwork Load (Options 2, 3, 7, and 8, and in some circumstances Options 4 and 5) is limited \nin scope to generator interconnection modifications [and] Transmission Owner retail load \nintegration studies would be performed in addition to necessary studies.”11  However, we \nhave significant concerns that the PJM Necessary Study Process would not be suitable for the \naddition of retail/end-use load, only for “...modifications to its facilities.”12  To accommodate \nthis new business model, it may be determined that with suitable revisions to the Tariff, the \nNecessary Study may be applicable under certain conditions, but should not be used as a \nmatter of course due to, among other things, its lack of transparency.   \nOur concerns with the lack of transparency associated with the Necessary Study \nprocess is underscored by the response from the PJM Indicated Transmission Owners which \nidentifies the need for “the necessary study process, together with other studies and analysis, \nwhich include the individual TO’s feasibility/engineering studies[.]”13  However, these \nadditional studies and analyses are not clearly spelled out, nor is there any transparency for \nconsumers.  Further, we continue to question whether the necessary study process is \n \n11 Answer of PJM to the Show Cause Order, at p. 8. \n12 See PJM Tariff, Section Appendix 2, Standard Terms and Conditions, para 3.1 specifies that the \nNecessary Study is intended to address modifications to its facilities, “[i]ncluding any modification to \nits project that causes the project’s capacity, location, configuration or technology to differ from any \ncorresponding information provided in the Interconnection Request.”  The Necessary Study provisions \ndo not specify changes to or modifications to customer load and Tariff changes should implemented to \nspecify the conditions when such a study might be suitable and when it is not, comparable to the \nprovisions that detail changes to the generator facilities. \n13 Answer of the PJM Indicated Transmission Owners, at Attachment A, p. 12."},{"page":8,"startToken":2375,"endToken":2783,"text":"8 \n \nappropriate for understanding the impacts of a generator that is, effectively, electing to \nremove a portion, or all, of its generating capacity from the PJM markets.14   \nA reduction in Capacity Injection Rights (“CIRs”) is effectively a partial deactivation.  \nTo suggest a reduction of 300 MW of capacity does not warrant a deactivation study when a \nfull deactivation of a 20 MW generator does, appears illogical on its face.  The generator will \nnot have the obligation to offer in those CIRs, whether due to a reduction or a full retirement.  \nAny change in available capacity will impact markets and transmission flows.  The system \ncapacity that is made available by a reduction in CIRs could potentially benefit all system \nusers but is not made available if it is studied in concert with a behind-the-meter discrete load \naddition.  When CIRs are removed from the system, the existing load must still be served and \nthe generation to serve that load may require new network upgrades.  Further, without a \ndeactivation study, it is unclear how the market monitor can be effective in providing \nindependent oversight of PJM markets and operations when such CIR reductions can be \naffecting market outcomes. Evaluating such changes in CIRs without a deactivation study \nthrough an opaque necessary study process appears to be a means to avoiding review by the \nMarket Monitor.   \nAdditionally, the majority of PJM’s proposed options aim at facilitating co-location \nof load at existing generators that already have an interconnection agreement, rather than \nfocusing on the development of sorely needed new generation to serve the new loads.  Option \n6 includes new generation with the load and suggests “faster interconnection when load is \nnetwork load,” but it is unclear how this would be accomplished any faster than the current \ninterconnection queue.  Nor is it clear why Option 6 should provide large load customers a \n \n14 The Indicated Transmission Owner’s Answer suggests that PJM is effectively powerless to \naddress any loss of generator capacity associated with co-location, suggesting that “PJM’s \nrole should be limited to the standard transmission planning process for all new load additions” \nand that “the loss of capacity from an existing generator seeking to enter into a co-location \narrangement should be studied by PJM.  Because the federal role in end-use load additions is \nlimited, PJM and the Commission should not create processes in the PJM Tariff that would \ninterfere with state jurisdiction.”  Answer of PJM Indicated Transmission Owners, at \nAppendix A, p. 12."},{"page":9,"startToken":2783,"endToken":3133,"text":"9 \n \npreference in interconnection over customers who are looking to meet other energy objectives, \nincluding clean energy commitments.   \nOne option would be a four-party agreement among the co-located generator, co-\nlocated load, interconnecting transmission owner, and PJM.  A new pro forma process would \nentail the following steps: \n1. \nEstablish new customer categories: Co-located Generator and Co-located Load, \nwhere the generator and the load parties would be eligible to interconnect to a single \nPOI under a single interconnection agreement and both the generator and load \nwould be parties to the agreement. \n2. \nDevelop new transparent procedures for co-location customers (load and generators) \nto request to interconnect via the PJM Interconnection Queue Study Process, \nincluding for existing generators that wish to interconnect new end-use load \ncustomers.  The procedures and interconnection reliability studies would cover all \npotential modes of operation. \n3. \nClearly define the terms and conditions of the Co-location Arrangement, including \nthe right to make retail sales and cost responsibilities associated with serving the \nend-use load that is on par with serving network load that is front-of-the-meter. \nAn alternative option would be a three-party agreement between the co-located \ngenerator, Interconnecting transmission owner and PJM, where the co-location generator will \nserve end-use load.   \nUnder either a three- or four-party agreement, the co-located generator would be able \nto connect to the grid, make wholesale sales to network load or point-to-point load customers, \nand make retail sales to its directly connected customers, subject to any applicable state tariff \ngoverning such retail sales.  The generator would be responsible for paying for transmission \nservice commensurate with the maximum amount of load that it seeks to supply.  If the new \nco-located load and generation are appropriately sized to minimize new power flows on the \ngrid, such a configuration would provide the least impact to the grid and therefore likely a \ncandidate for an expedited study process.    \nD. The Need for a Co-Location “Safety Valve” to Ensure System Reliability and \nCustomer Affordability. \n \nThe Show Cause Order asked the parties to “explain whether the existing Tariff rules \nare sufficient to ensure resource adequacy if increasing numbers of large existing generators"},{"page":10,"startToken":3133,"endToken":3505,"text":"10 \n \nchoose to co-locate with load.”15  In our view, the mass migration of existing generators to a \nco-location configuration could absolutely threaten the reliability of the PJM grid and worsen \nthe already dire affordability crisis faced by many PJM consumers.  To the best of our \nknowledge, none of the studies proposed by PJM or the Indicated Transmission Owners \nwould evaluate resource adequacy considerations.   \nThe Commission should strongly consider a co-location “safety valve” that ensures \nthat co-location does not drive PJM into shortage conditions.  As noted in NERC in 2023, \n“[d]riven by electrification, hydrogen production, data centers, crypto mining, and other \ncomputational and energy-intensive methods such as artificial intelligence (AI), new loads \ncan emerge and grow faster than generation and transmission can be built.”16  And the \nsituation has only grown more challenging since then.17  Requiring completion of the study \nprocess that addresses both transmission reliability and resource adequacy prior to energizing \nany new co-located load additions would help ensure system reliability and provide adequate \ntime for markets to adjust to the changing supply-demand balance.   \nAs noted above, PJM had only 514 MW of excess capacity in the 2025/2026 delivery \nyear.  Load is projected to grow substantially in 2026, with over 2,700 MW of new load \ngrowth now expected above levels projected in 2024.  There is no need to recount the litany \nof challenges that PJM has faced interconnecting new generators or the fact that its three-year \nforward auction is now effectively a prompt auction.  Nuclear generating units, for example, \nhave been particularly attractive candidates for co-location.  Removing even a single nuclear \ngenerator from the capacity supply stack would, assuming current market trends hold, drive \nPJM into a resource adequacy shortfall.  PJM’s existing rules appear to have no effective \n \n15 Show Cause Order at p. 53.   \n16 ERO Reliability Risk Priorities Report North American Electric Reliability Corporation, August \n2023 at p. 27 (emphasis added). \n17 See Statement PJM CEO to OPSI, “I feel more concerned today than I did two years ago about \nresource adequacy.  Load is growing much faster than we had projected then, which even back then \nwas an eye-popping set of numbers.”  Available at:  \nhttp://www.paenvironmentdigest.com/newsletter/default.asp?NewsletterArticleID=61689&SubjectID=\n217."},{"page":11,"startToken":3505,"endToken":3861,"text":"11 \n \nmeans of limiting these departures or staggering the departures until new replacement \nresources are identified and built.  The clogged interconnection queue and short capacity \nauction time horizon makes bringing replacement resources to market quickly would be near \nimpossible under the current circumstances.   \nThe reality is that the existing rules, which treat new load as network load, create a \nsignificant lag between the time new service is requested and the time it is provided by the \nutility.  While this is obviously commercially challenging for data center customers, it does \nact as something of a “governor” on the rate at which load can grow.  If the Commission \nelects to significantly accelerate co-location opportunities, the speed at which the new load \ncomes online may accelerate significantly.  In such circumstances, the Commission should \nconsider whether it is necessary for PJM to strategically manage the rate at which co-location \nis allowed if necessary to ensure continued system reliability.   \nA safety valve could also help ensure customer affordability, which has been \nextremely challenged in light of the significant increases in capacity market prices for the \n2025/2026 delivery year.  It is important to recognize that co-location has the potential to \nsignificantly increase both capacity and energy prices, as energy prices tend to increase when \nthe amount of excess generation shrinks.  As noted above, nuclear units are particularly \nattractive co-location candidates, and the sudden removal of significant quantities of $0 \nmarginal cost generation could put significant upward pressure on Locational Marginal Prices.    \nE. The Commission Should Address the Risk of Stranded Transmission \nInvestment Associated with Co-Location. \n \nOne significant consumer protection concern is how to manage the risk associated \nwith transmission facilities to support new co-located or network load if that load does not \nmaterialize.  The transmission investment necessary to serve these new mega-loads is large \nand the payback period is long, and their electricity usage is highly uncertain.  Data center \nenergy efficiency breakthroughs, better algorithm optimization, quantum computing, and the \nnormal ups and downs of a new industry could all result in data centers using less – or more – \nenergy than anticipated.  The stranded cost risk to consumers is real, particularly as virtually"},{"page":12,"startToken":3861,"endToken":4168,"text":"12 \n \nall of PJM’s proposed solutions continue to have data center-driven transmission investments \ncollected through socialized cost allocation methodologies that are often spread costs over \nmultiple jurisdictions.   \nIndeed, individual states and utilities have begun implementing minimum contract \nterms, minimum service level requirements, and “take or pay” structures backed by financial \nsecurity requirements, these measures only protect customers in the specific utility zone that \nis implementing those protections.  While long-term contracts, backed by postings of \nfinancial security may protect the customers of a single utility, such payments do little to \nprotect customers in the rest of PJM.   \nWhile the Commission is certainly not in the business of managing the economic \ndevelopment decisions of individual states, it should ensure that any PJM tariff changes \naccount for the potential that data center load may not materialize and collaborate with its \nstate partners to manage this risk.  The need for federal-state coordination is perfectly \nillustrated in an ongoing proceeding before the Ohio Public Utilities Commission.18  There, \nOhio utilities are battling over whether data center customers should be required to enter \nlong-term contracts before being allowed to connect to the grid.  Thus, the Commission \nshould consider imposing comparable “take or pay” structures for new large loads triggering \ntransmission upgrades and backed by financial security postings.   \nF. The Commission Should Take PJM Up on its Offer to Develop a Non-Firm \nor Interruptible Tariff for Co-Located Resources.    \n \nWe recommend that the Commission explore the potential to develop a new level of \ntransmission service that prioritizes connection of new flexible loads – both co-located and \nnon-co-located.  Research has demonstrated that greater flexibility in operations could \n \n18 For a summary of the Ohio proceeding, see Yoon Kim, Connecting Data Centers to the Grid: An \nInnovative and Controversial Proposal from AEP Ohio, Sept. 2024, available at: \n https://blogs.law.columbia.edu/climatechange/2024/09/12/guest-blog-connecting-data-centers-to-the-\ngrid-an-innovative-and-controversial-proposal-from-aep-ohio."},{"page":13,"startToken":4168,"endToken":4525,"text":"13 \n \nalleviate the need for upgrades needed to enable connection of the new loads.19  As PJM notes \nin its description of Options 7, allowing flexible load to be dispatched in the real-time horizon \n“provides an opportunity for large load to integrate as a non-capacity backed load where it \navoids capacity costs if willing to curtail to support reliability in advance of emergency \nconditions.”20  A new level of service might be beneficial to both conventionally connected \nlarge loads and co-located arrangements (and potentially benefit other customer types \ninterested in activating demand-side flexibility).   \nTo implement a new non-firm or interruptible type of service, consideration would \nhave to address the nature of the service, how such service would be compliant with NERC \nmandatory reliability standards, address operational control mechanisms and establish an \nappropriate rate for the service.  Non-firm or interruptible service may not be desirable for all \nnew large load customers, but its availability to those willing to operate more flexibly can \nyield benefits to all users connected to the grid and should be prioritized.21 \nG. The Commission Should Clarify the Regulatory Obligations of Generators \nServing On-Site Load.  \n \nAs stated by PJM, its preference for designating load as network load in-front-of-the-\nmeter is for multiple reasons, including reduced operating complexity, reduced dependence \non protective schemes that can mis-operate, more reliable service, enhanced ability to manage \nload curtailment, greater access to demand response and more comprehensive holistic \nplanning.22  This preference is an acknowledgement of the importance of having adequate \nvisibility of the system conditions such that PJM can direct the reliable operation of the grid. \nThis can be assured when all load connections are subject to the same reliability standards. \nFor load that is served by a utility that is subject to the Consolidate Transmission Owner’s \n \n19 Norris, T. H., T. Profeta, D. Patino-Echeverri, and A. Cowie-Haskell. 2025. Rethinking Load Growth: \nAssessing the Potential for Integration of Large Flexible Loads in US Power Systems. NI R 25-01. \nDurham, NC: Nicholas Institute for Energy, Environment & Sustainability, Duke University. \n20 Answer of PJM Interconnection to Show Cause Order, at Appendix A.   \n \n22 PJM Interconnection LLC Answer at Page 38."},{"page":14,"startToken":4525,"endToken":4925,"text":"14 \n \nAgreement (“CTOA”), each connection to a non-party is governed by Article 4.10 which \nrequires that the utility enter into an agreement that ensures compliance with applicable \nstandards and Good Utility Practice.23  This provision ensures that not only does each PJM \nTransmission Owner maintain its systems reliably, but also any connections to other systems, \nincluding load customers and other transmission systems as well.  When a load is directly \nconnected to another customer’s facilities without being subject to the same standards, the \nconnection potentially exposes the grid to additional risks.  For this reason, it is recommended \nthat at a minimum, any connection to a system not subject to the CTOA, be subject to \ncomparable provisions be incorporated into any co-location agreement.  \nThe importance of this requirement cannot be overstated.  The growth in hyperscale \nsized loads that may have a demand that is on par with a typical nuclear plant presents new \nchallenges for operations that as an industry we are only beginning to fully grasp.  Two \nsystem events highlight the risks that these large loads introduce to the power grid.  One \nexample was an event cited by NERC in its comments at the FERC Technical Conference on \nco-located large loads.  NERC explained how a single line to ground fault on a 138 kV line \nresulted in a momentary voltage drop that triggered the automatic separation of approximately \n1500 MW of data center load.24  ERCOT has experienced similar events where data center \nload exhibits voltage-sensitive behavior that is resulting in unexpected reduction in \nconsumption.    \nWe are years from fully assessing the risks posed by these large data center loads and \nestablishing reliability requirements and industry best practices to mitigate these risks. While \n \n23 See PJM Consolidated Transmission Owners Agreement, Article 4.10 Connections with Non-Parties.  \n“No Party shall permit its Transmission Facilities or distribution facilities to be connected with the \nfacilities of any entity which is not a Party without an interconnection agreement that contains \nprovisions for the safe and reliable operation of each interconnection in accordance with Good Utility \nPractice, and principles, guidelines and standards of the Applicable Regional Reliability Council and \nNERC or comparable requirements of an applicable retail tariff or agreement approved by appropriate \nregulatory authority.” \n24  Howard Gugel. Statement of the North American Electric Reliability Corporation. \nTechnical Conference on Large Loads Co-Located at Generating Facilities Docket No. AD24-11- \n000 November 1, 2024 at Page 2."},{"page":15,"startToken":4925,"endToken":5355,"text":"15 \n \nwe are years away, it is imperative that RTOs have the authority to require any necessary \nupdates to the interconnections that may be required to maintain safe and reliable operation of \nthe grid.  This requires that any connection is subject to an agreement with the appropriate \nterms and authority of the RTO to enforce it.  The current pro forma interconnection \nagreements do not contain sufficient protections and should, at a minimum, be updated \naccordingly if it is to be used for connecting co-located large loads. \nH.  The Commission Should Ensure that any Proposed Changes go Through a \nThorough Stakeholder Vetting.   \n \nThe Commission should ensure that any new tariff process arising out of this Show \nCause Order be subject to further development in an open stakeholder forum.  There is ample \nevidence of prior attempts by customers to effectuate rules outside the stakeholder process \nand attempt to implement new business models not defined in the PJM rules.  Invariably, PJM \nrejected such attempts and worked with members to convene a stakeholder process to \ndetermine if tariff changes were warranted, and if so, what those tariff changes and \naccompanying manuals should be.25  PJM and FERC should again reject implementing new \nrules for customers without allowing for an open stakeholder process to vet such efforts. \nIV. \nConclusion \nThe current PJM Tariff process for connecting network load or point-to-point load is \njust and reasonable as it currently exists.  The well-published concerns about inadequate \nresource additions to meet the projected load, however, warrant active FERC and PJM efforts \nto actively manage the amount of co-location load coming onto the system, the rate of such \nadditions, and the protection of consumers from the risks that the load does not materialize as \nexpected.  Data centers are being built within 2-3 years, but the lead time for new natural gas \n \n25 In April 20219 PJM initiated a stakeholder process to “[e]xplore alternatives, if any, in two phases to \naddress the challenges with interconnecting merchant transmission such that the project may be eligible \nfor rights that can be used for interconnection of future offshore generation” in response to a customer \nseeking to implement a new business model.  Another example is the High Voltage Direct Current \nSenior Task Force to “...to explore the possibility of participation of HVDC converters in PJM’s \ncapacity market, including their technical capabilities, existing tariff and manual provisions and hurdles \nto participation, as well as potential tariff changes needed to enable such participation.”  PJM has a \nwell-established protocol where members can identify a problem and request endorsement of an issue \ncharge to address a need."},{"page":16,"startToken":5355,"endToken":5504,"text":"16 \n \ngenerators is on the order of 5 years or more.  While co-location may offer advantages that \ncan ultimately be beneficial to all users, it should not distract from PJM’s active management \nof co-location arrangements.    \nShould FERC make that determination that co-location should be permitted in the \nPJM footprint, it should direct PJM to convene an open stakeholder process to develop the \nrules to do so.  FERC should provide clear principles for PJM and others in developing tariff \nrevisions.  FERC should establish a timeframe that would allow for robust stakeholder \nengagement to develop tariff revisions that can fairly balance the interests of all grid \ncustomers and consumers who rely on cost-effective and efficient system planning and \noperations.   \nRespectfully submitted, \n \n/s/  \n \n \n \n \n/s/ \nSuzanne Glatz  \n \n \nAbraham Silverman \nGlatz Energy Consulting  \nResearch Scholar, Ralph O’Connor \nPrincipal Consultant \nSustainable Energy Institute, Johns Hopkins  \nSue@glatzconsulting.com \n \nabe@silvergreen.energy  \n \n \nOn behalf of themselves"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":997,"startToken":0,"endToken":141},{"p":1,"at":997,"title":"I. Summary","method":"printed heading","endPage":3,"endAt":455,"startToken":141,"endToken":654},{"p":3,"at":455,"title":"II. Background of Suzanne Glatz and Abraham Silverman","method":"printed heading","endPage":4,"endAt":5,"startToken":654,"endToken":870},{"p":4,"at":5,"title":"III. Comments","method":"printed heading","endPage":4,"endAt":25,"startToken":870,"endToken":872},{"p":4,"at":25,"title":"A. PJM’s Existing NITS Rules are Just and Reasonable and Not Unduly","method":"printed heading","endPage":5,"endAt":461,"startToken":872,"endToken":1285},{"p":5,"at":461,"title":"B. Any Just and Reasonable Changes to PJM’s Tariff Should Ensure that","method":"printed heading","endPage":6,"endAt":563,"startToken":1285,"endToken":1688},{"p":6,"at":563,"title":"C. Principles for a New Interconnection Service if FERC Determines that","method":"printed heading","endPage":9,"endAt":2129,"startToken":1688,"endToken":3091},{"p":9,"at":2129,"title":"D. The Need for a Co-Location “Safety Valve” to Ensure System Reliability and","method":"printed heading","endPage":11,"endAt":1677,"startToken":3091,"endToken":3751},{"p":11,"at":1677,"title":"E. The Commission Should Address the Risk of Stranded Transmission","method":"printed heading","endPage":12,"endAt":1501,"startToken":3751,"endToken":4072},{"p":12,"at":1501,"title":"F. The Commission Should Take PJM Up on its Offer to Develop a Non-Firm","method":"printed heading","endPage":13,"endAt":1155,"startToken":4072,"endToken":4343},{"p":13,"at":1155,"title":"G. The Commission Should Clarify the Regulatory Obligations of Generators","method":"printed heading","endPage":15,"endAt":533,"startToken":4343,"endToken":5011},{"p":15,"at":533,"title":"H. The Commission Should Ensure that any Proposed Changes go Through a","method":"printed heading","endPage":15,"endAt":1350,"startToken":5011,"endToken":5137},{"p":15,"at":1350,"title":"IV. Conclusion","method":"printed heading","endPage":16,"endAt":1065,"startToken":5137,"endToken":5504}]}