{"document":{"slug":"rec-20250423-5250","title":"Comments of the Maryland Office of Joint Consumer Advocates et al","issued":"2025-04-23","accession":"20250423-5250","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Maryland Office of People's CounselNew Jersey Office of Ratepayer Advocate","kind":"comments","file":"sources/filings/text/20250423-5250_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250423-5250","tier":"record","sha256":"69c46c4ee478861943645d9685359ae9346090bac635ed7cabd329ff82046aa6","pages":11,"tokens":2302,"emptyPages":[],"textThemes":["colo","retail"]},"pages":[{"page":1,"startToken":0,"endToken":177,"text":"1 \n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C., et. al. \nLarge Loads Co-Located at Generating Facilities  \nConstellation Energy Generation, LLC \nv.  \nPJM Interconnection, L.L.C. \nDocket Nos. EL25-49-000 \n \n \nAD24-11-000 \n \n \nEL25-20-000 \n(Consolidated) \n \n \n \n \n \nCOMMENTS OF THE MARYLAND OFFICE OF JOINT CONSUMER \nADVOCATES \nPursuant to Rule 211 of the Federal Energy Regulatory Commission’s \n(“Commission’s”) Rules of Practice and Procedure, 18 C.F.R. § 385.211, the Maryland \nOffice of People’s Counsel (“MPC”) and the New Jersey Division of Rate Counsel \n(“Rate Counsel”) (together, the “Joint Consumer Advocates” or “JCA”), respectfully \nsubmit these comments in support of, in part, the March 24, 2025 filings of PJM \nInterconnection, L.L.C. (“PJM”) and the Indicated PJM Transmission Owners (“TOs”) \nanswers to the Commission’s February 20, 2025 Order Instituting Proceeding under \nSection 206 of the Federal Power Act and Consolidating with Other Proceedings (the \n“Show Cause Order”). \nMPC filed a motion for leave to intervene in this proceeding on March 21, 2025, \nwhich the Commission accepted. MPC is the statutory representative of the residential"},{"page":2,"startToken":177,"endToken":418,"text":"2 \n \nratepayers of utility services in Maryland. Pursuant to Maryland Public Utility \nCompanies Code Annotated, Section 2-205(b), the People’s Counsel “may appear before \nany federal or state entity as necessary to protect the interests of residential . . . users of \n[gas, electricity or other regulated services].” Rate Counsel intervened in this proceeding \non February 26, 2025, and is the statutory representative of ratepayers of utility services \nin New Jersey. Pursuant to N.J.S.A. 52:27EE-55, Rate Counsel may “represent the public \ninterest in any federal proceeding, including but not limited to proceedings before . . . the \nFederal Energy Regulatory Commission.” \nINTRODUCTION \nThe Commission’s existing pro forma open access transmission tariff (“OATT”), \nand PJM’s OATT-compliant tariff (“PJM Tariff”), already address co-located load in a \njust and reasonable manner. Either network integration transmission service (“network \nservice”) or point-to-point transmission service (“point-to-point service”) can apply to co-\nlocated load arrangements under the PJM Tariff and render just and reasonable results \nwhen properly applied. Network service is the preferred designation to ensure co-located \nload is addressed in a just and reasonable manner, as such designation will reduce \nimpacts on existing ratepayers and prevent negative externalities such as free-riding. \nGiven the variables involved in point-to-point service, each application of point-to-point \nservice would need to be individually evaluated to determine whether it can be applied in \na just and reasonable manner. The JCA thus support, in part, the position of the Indicated \nTransmission Owners and PJM Interconnection, LLC."},{"page":3,"startToken":418,"endToken":694,"text":"3 \n \nCOMMENTS \nI. \nPJM’s current tariff provisions on co-located load arrangements can \nproduce just and reasonable results. \n \nA. \nClassifying co-located load as front-of-the-meter network service \nminimizes risks to existing customers compared to other \nconfigurations. \nCo-located load is load from a large commercial or industrial customer such as a \ndata center that has a contractual relationship with an adjacent generating facility for its \nsupply of electricity. The PJM Tariff considers co-located load arrangements as network \nservice or point-to-point service.1 Under these classifications, co-located load is studied \nto allocate the costs of reliability services, such as ancillary services, and for the impact \nthe co-located load will have on the grid for planning purposes. Co-located load receiving \nnetwork service is responsible to PJM for the costs associated with serving its load and \nwould be included in PJM’s planning process.2  \nClassifying co-located load as front-of-the meter network service is thus \npreferrable from a reliability and cost causation standpoint. When such a large amount of \nload is “off-network” but still benefitting from the transmission system, a basic principle \nof cost allocation is frustrated—the principle that those who cause the costs and reap the \nbenefits, bear responsibility for the costs.3 The appearance of co-located load on the grid \ncould have the same effect as generation retirement, triggering transmission upgrades \n \n1  PJM, Intra-PJM Tariffs, OATT, § 1 Definition of Network Load (providing that load shall be designated \nas Network Load or served by Point-to-Point service) (“PJM Tariff”). \n2 Id. \n3 BNP Paribas Energy Trading GP v. FERC, 743 F.3d 264, 268 (D.C. Cir. 2014) (Cost causation is a \n“matter of making sure that burden is matched with benefit.”)."},{"page":4,"startToken":694,"endToken":974,"text":"4 \n \neither directly to accommodate the co-located load or indirectly to accommodate future \nload that would otherwise have headroom on the existing transmission system but for the \nco-located load. Even though the costs of such upgrades would be allocated to all \nnetwork service customers, if co-located load is located behind the meter, the entity co-\nlocating its load would evade transmission rates. These transmission rates would pay for \ninitial upgrades needed because of the co-location arrangement or future upgrades needed \nto serve all customers in the service territory. Other ratepayers, not the cost causers, \nwould instead bear these costs, as described in the TO’s Answer.  \nThe impact on customers from treating services for co-located load as non-\nnetwork service could be substantial. As Exelon warned in its comments in Docket No. \nEL25-20 and as the TO’s highlight in their answer, even a relatively small co-located load \ncarveout of 480 megawatt (“MW”) from network service in the Southern Maryland \nElectric Cooperative (“SMECO”) territory—where the Calvert Cliffs nuclear facility is \nlocated—would result in the avoidance of over $53 million in charges per year.4 The \nfinancial impacts more than double if one gigawatt (“GW”) of load is not considered \nnetwork service, allowing the co-located load customer to shift $112 million of annual \navoided transmission charges onto other ratepayers. Even if some benefits were to accrue \nto non-cost causers, the ratepayer impact that such an arrangement would cause is too \nlarge to ignore. The PJM Tariff covering network service prevents this illegal cost \nshifting and should thus apply to co-located load. \n \n4 See Answer of the Indicated PJM Transmission Owners to Order to Show Cause at 18–19 (hereinafter \n“TO Answer”)."},{"page":5,"startToken":974,"endToken":1216,"text":"5 \n \nAlthough co-located load is located behind the point of interconnection, it is \nalways electrically connected and synchronized to the transmission system; the generator \ncannot operate or supply the co-located load without that connection to the transmission \nsystem. As the TOs and the Union of Concerned Scientists (“UCS”) emphasize, it is \neconomically and technically impossible to “fully isolate” co-located load from the \ntransmission grid.5 Indeed, co-location with nuclear generation is being widely discussed, \nand nuclear industry standards require synchronization with the grid for stability, off-site \npower, and restoration. Co-location with baseload generation also poses reliability \nconcerns, which are exacerbated if the co-located load is considered non-network load. \nAs the Maryland Public Service Commission opined in its recent report on co-located \nload:  \nIf [non]-network load co-locates with baseload generation, such as the \nCalvert Cliffs nuclear plant, significant quantities of existing capacity will \nbe effectively removed from the grid and resource adequacy may be \ndegraded at an accelerated pace relative to connecting such load in \ntraditional ways. Baseload capacity of the type Calvert Cliffs provides \ncould take years to plan, certificate, and build.6 \nTherefore, the Commission should clarify that co-located load is always network \nload, with a preference for network service, to prevent evasion of grid service charges \nand transmission grid upgrade charges to the detriment of other customers.  \n \n5 See TO Answer at 7–9; UCS Comments at 8. \n6 Maryland Public Service Commission, Report on Co-Location, at 1 (2024)."},{"page":6,"startToken":1216,"endToken":1514,"text":"6 \n \nB. \nPJMs’ proposed new options four and five, with special protection \nschemes, are misplaced and unnecessary.  \nThe Commission should reject PJM’s suggested configurations that offer \nprotective schemes to co-located load that is non-network load—specifically new options \nfour and five as detailed in Exhibit A to the PJM Answer. As the TOs underscore in their \nanswer, inadvertently or directly creating a new class of service, especially non-network \nload, for co-located load is unnecessary and unduly preferential.7 PJM itself cautions \nagainst these options that involve complex special protection schemes to “prevent” \nwithdrawal from the grid, conceding in its answer that such schemes in place at the \nSusquehanna Steam Electric Nuclear Power Facility — which has an interconnection \nagreement with a co-located data center —failed, causing the data center to instead rely \non the PJM grid for its supply during an unplanned outage.8 Monitoring Analytics, the \nindependent market monitor for PJM, also expressed concern over the issues of backup \npower for co-located load arrangements and emphasized it is “not possible for co-located \nload to be off the grid.”9 Moreover, as UCS notes, the variability of power demand from \ndata centers creates “imbalances more quickly than generators can correct, resulting in [] \nvoltage disturbances, thermal overloads and stability issues.”10 The risk that the \nprotective measures in these complex options will fail is extremely high given that such \nvariability affects multiple aspects of PJM service, such as ancillary services, \n \n7 See TO Answer at 18–19. \n8 See PJM Answer to Order to Show Cause at 39, FN 60. \n9 Monitoring Analytics, Comments to the Maryland PSC Senate Bill 1 Co-location Study Administrative \nDocket PC 61, Sept. 24, 2024 at 2. \n10 Comments of the Union of Concerned Scientists to Order to Show Cause at 14 (hereinafter “UCS \nComments”)."},{"page":7,"startToken":1514,"endToken":1794,"text":"7 \n \ntransmission capacity, and generation margin reserves. Allowing for an option that \nheightens the risk of these imbalances and miscalculations of reserves goes against PJM’s \nmission “to ensure the safety, reliability and security of the bulk electric system.”11  \nFinally, the TOs aptly point out that consistency is key to advance the goals of all \nrelevant stakeholders, including co-located load customers. Forms of service tailored to \nspecific co-located load will all but guarantee protracted litigation over intricate \nprotective schemes that further muddy the regulatory waters, to the detriment of both \nratepayers and co-located load customers. Therefore, the Commission should dismiss \nproposals for options four and five in Exhibit A to the PJM Answer and clarify that co-\nlocated load should be classified as network service under the PJM Tariff. \nII. \nThe Commission should defer to state law control over how the costs of \nthe wholesale sale and transmission of electricity are allocated among \nretail customers.  \nMaryland recently passed legislation revising the definition of “retail electric \ncustomer” to include co-located load customers and specifying that a generating facility \nwith co-located load can supply retail electricity in these instances.12 Once signed into \nlaw, this definitional revision will enhance jurisdictional clarity for co-located load within \nMaryland. As the Commission notes, “states retain exclusive jurisdiction over the terms \nof retail sales, generally including the rate designs that determine how the costs of the \nwholesale sale and transmission of electricity assigned to a wholesale customer are \n \n11 PJM, “Problem/Opportunity Statement”, July 26, 2023, accessible at, chrome-\nextension://efaidnbmnnnibpcajpcglclefindmkaj/https://www.pjm.com/-/media/DotCom/committees-\ngroups/task-forces/rcstf/postings/problem-statement.pdf. \n12 HB 1035 (the “Next Generation Energy Act”) is awaiting gubernatorial signature."},{"page":8,"startToken":1794,"endToken":2082,"text":"8 \nallocated among that wholesale customer’s retail customers.”13 Further, the Commission \nexplained that “the states also get to determine how the wholesale costs of providing \nelectricity to those retail customers are recovered through retail rates. . . . irrespective of \nwhere the load interconnects (i.e., to the distribution system, the transmission system, or \nthe generator itself).”14  \nIn New Jersey, it is well-established precedent that the New Jersey Board of Public \nUtilities has the authority to regulate activities that are “clothed in the public interest,” \nand this includes the sale of “public-utility-type services to a limited market . . . .”15   \nThe Commission should make clear in this proceeding that states have the \nauthority to allocate costs for “the wholesale sale and transmission of electricity assigned \nto a wholesale customer” and take no action that interferes with that authority. As the TOs \nnote, the PJM Tariff ensures “all customers pay their fair share of the transmission \nnetwork from which they benefit.” Maryland’s new legislation clarifies how state law \nadvances the important goal of ensuring all customers pay their fair share of transmission \nsystem costs, including co-located load customers.  \nCONCLUSION \nCo-located load affects and benefits from the PJM grid. Consequent policy \ndecisions about co-located load in PJM will thus have significant implications for all PJM \ncustomers, in Maryland, New Jersey, and in the PJM region at large. A straightforward \n13 Order to Show Cause, EL25-49-000, et al., Feb. 20, 2025, P68. \n14 Order to Show Cause, P69. \n15 See In re in re S. Jersey Gas Co., 116 N.J. 251, 258 (1989) (affirming a final agency decision that a \nchemical company selling gas to a select group of large industrial users, is a “public utility” subject to the \njurisdiction of the Board)."},{"page":9,"startToken":2082,"endToken":2234,"text":"9 \n \napproach that clarifies co-located load is network load that takes network service is the \nmost cost-effective and equitable decision. Although point-to-point service may also be \njust and reasonable, implementation is more challenging and riskier for customers, \nrequiring consideration on an individual basis. At minimum, the Commission should \ndisallow non-network load configurations, while leaving undisturbed the states’ authority \nto allocate costs for wholesale sales and transmission, in determining the just and \nreasonable approach to co-located load.  \nRespectfully submitted,  \n \n \n \n \n \n \nDAVID S. LAPP \n \n \n \n \n \n \nPeople’s Counsel  \n \n \n \n \n \n \n \n \n \n \n \n \n \n/electronic signature/ \nWilliam F. Fields \n \n \n \n \n \n \nDeputy People’s Counsel  \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \nAlexis H. Lewis \n \n \n \n \n \n \nAssistant People’s Counsel \n    \n \n \n \n \n \n \n \n \n \n \n \nOffice of People's Counsel     \n \n \n \n \n \n \n6 St. Paul Street, Suite 2102     \n \n \n \n \n \n \nBaltimore, Maryland 21202  \n \n \n \n \n \n \n(410) 767-8171  \n \n \n/s/ Emily Lam \nEmily Lam, Esq. \nT. David Wand, Esq. \nBrian O. Lipman, Esq. \n \nNew Jersey Division of Rate Counsel \n140 East Front Street, 4th Floor \nP.O. Box 003 \nTrenton, NJ 08625 \nT (609) 984-1460 \nelam@rpa.nj.gov"},{"page":10,"startToken":2234,"endToken":2247,"text":"10 \n \ndwand@rpa.nj.gov \nblipman@rpa.nj.gov \n \n      \n \nDated:  April 23, 2025"},{"page":11,"startToken":2247,"endToken":2302,"text":"11 \n \nCERTIFICATE OF SERVICE \n \nI HEREBY CERTIFY that, on this 23rd day of April 2025, the foregoing \n“Comments of the Maryland Office of People’s Counsel” was either hand‐delivered, e‐\nmailed or mailed first‐class, postage prepaid to all parties of record to this proceeding.  \nRespectfully submitted, \n \n/electronic signature/ \nAlexis H. Lewis \n \n \n \n \nAssistant People’s Counsel"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":677,"startToken":0,"endToken":276},{"p":2,"at":677,"title":"INTRODUCTION","method":"printed heading","endPage":3,"endAt":15,"startToken":276,"endToken":420},{"p":3,"at":15,"title":"I. PJM’s current tariff provisions on co-located load arrangements can","method":"printed heading","endPage":3,"endAt":128,"startToken":420,"endToken":435},{"p":3,"at":128,"title":"A. Classifying co-located load as front-of-the-meter network service","method":"printed heading","endPage":6,"endAt":5,"startToken":435,"endToken":1217},{"p":6,"at":5,"title":"B. PJMs’ proposed new options four and five, with special protection","method":"printed heading","endPage":7,"endAt":867,"startToken":1217,"endToken":1643},{"p":7,"at":867,"title":"II. The Commission should defer to state law control over how the costs of","method":"printed heading","endPage":8,"endAt":1248,"startToken":1643,"endToken":1978},{"p":8,"at":1248,"title":"CONCLUSION","method":"printed heading","endPage":11,"endAt":6,"startToken":1978,"endToken":2248},{"p":11,"at":6,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":11,"endAt":381,"startToken":2248,"endToken":2302}]}